cost estimates 2s bldg
DESCRIPTION
Building EstimateTRANSCRIPT
Project : PROPOSED TWO (2) STOREY BUILDING (DUPLEX TYPE)
Location : Lapasan, Cagayan de Oro City
Owner : Mr. Rolando G. Gironella, III
Item no. Description % Wt.
I GENERAL REQUIREMENTS1 Mobilization2 Temporary Facilities
item I sub-total 0.59
II EARTHWORKS1 Site Clearing and Grubbing2 Structural Excavation3 Structural Backfill and Compaction4 Earthfill and Compaction5 Gravel Bedding
item II sub-total 2.23
III CONCRETE WORKS1 Footings2 Wall Footings3 Columns4 Beams5 Stairs 6 Interior Slab
item III sub-total 7.71
IV REINFORCING STEEL BARS1 16mmØ Deformed Bars Gr.402 10mmØ Deformed Bars Gr.33 3 20mmØ Deformed Bars Gr.404 12mmØ Deformed Bars Gr.335 Tie Wires
item IV sub-total 12.31
V MASONRY WORKS1 6" Machine Made CHB with Reinforcements2 4" Machine Made CHB with Reinforcements3 Plastering4 Plain Cement Finish
item V sub-total 16.26
VI FORMWORKS and SCAFFOLDINGS1 Ordinary Plywood and Coco Lumber
item VI sub-total 5.70
VII STRUCTURAL STEEL WORKS1 1.5mm THK x 2" x 6" C-Purlins2 1.5mm THK x 2" x 3" C-Purlins
item VII sub-total 2.49
VIII THERMAL and MOISTURE PROTECTION1 Roofing and Accessories
( Ordinary Corr. Ga.22 Long Span Pre-painted )2 Insulation
( 10mm Thk. Double Foil Foam )3 Interior Slab Vapor Barrier
item VIII sub-total 4.31
IX DOORS and WINDOWS1 Doors and Windows
item IX sub-total 4.43
X CEILING WORKS1 4.5mm Thk. Hardiflex Board on Lite Metal Frames ( Two Sides )
item X sub-total 7.39
XI TILE WORKS1 300mm x 300mm Ceramic Floor Tiles2 200mm x 200mm Ceramic Floor Tiles3 200mm x 200mm Ceramic Wall Tiles ( 1.55m Ht. )
item XI sub-total 5.74
XII METAL WORKS1 Railings and Balustrades
item XV sub-total 2.25
XIII PAINTING WORKS1 Masonry Walls2 Ceiling
item XII sub-total 8.62
XIV ELECTRICAL WORKS1 Rough-in2 Fixtures
item XIII sub-total 9.48
XV PLUMBING WORKS1 Potable Water2 Waste Water Line & Storm Drainage3 Fixtures4 Septic Tank5 Catch Basin6 Grease Trap
item XIV sub-total 10.50
TOTAL AMOUNT 100.00
Unit Quantity Unit Price Amout ( P ) ( P )
lot 1.00 21,269.04 21,269.04 lot 1.00 21,560.76 21,560.76
42,829.80
sq.m. 294.00 14.12 4,150.38 cu.m. 77.90 1,277.74 99,529.56 cu.m. 8.03 1,325.01 10,634.52 cu.m. 44.10 665.10 29,331.12 cu.m. 15.00 1,150.08 17,251.26
160,896.84
cu.m. 9.94 4,947.14 49,154.82 cu.m. 8.56 4,947.14 42,352.50 cu.m. 16.50 4,947.14 81,627.87 cu.m. 12.76 4,947.14 63,113.19 cu.m. 0.96 4,947.14 4,749.26 cu.m. 63.60 4,947.14 314,638.34
555,635.97
lgth. 377.00 604.72 227,979.18 lgth. 1,716.00 183.81 315,426.23 lgth. 532.00 604.72 321,710.67 lgth. 156.00 60.18 9,388.08 kgs. 216.00 60.18 12,998.88
887,503.04
sq.m. 73.38 1,273.81 93,472.39 sq.m. 1,459.35 471.43 687,984.49 sq.m. 2,918.71 98.42 287,264.64 sq.m. 2,860.12 36.24 103,640.16
1,172,361.68
sq.m. 355.90 1,154.94 411,040.11 411,040.11
lgths. 23.00 2,631.76 60,530.57 lgths. 48.00 2,482.00 119,135.80
179,666.37
sq.m. 266.96 952.89 254,379.84
sq.m. 266.96 127.56 34,051.68
sq.m. 294.00 75.73 22,263.54 310,695.06
lot 1.00 319,300.80 319,300.80 319,300.80
sq.m. 533.91 997.94 532,813.32 532,813.32
sq.m. 375.80 775.91 291,587.40 sq.m. 25.20 1,046.17 26,363.48 sq.m. 117.18 818.46 95,906.93
413,857.81
li.m. 87.93 1,844.56 162,196.32 162,196.32
sq.m. 2,136.54 229.60 490,540.44 sq.m. 533.91 245.18 130,902.72
621,443.16
lot 1.00 431,817.20 431,817.20 lot 1.00 252,046.08 252,046.08
683,863.28
lot 1.00 112,935.42 112,935.42 lot 1.00 158,350.92 158,350.92 lot 1.00 321,687.60 321,687.60
units 2.00 45,605.00 91,210.00 units 8.00 6,087.25 48,698.00 units 4.00 6,062.00 24,248.00
757,129.94
7,211,233.51
Poject : PROPOSED TWO (2) STOREY BUILDING (DUPLEX TYPE)Locatio : Lapasan, Cagayan de Oro CityOwner : Mr. Rolando G. Gironella, III
I. GENERAL REQUIREME1) Mobilization and Demobilization
Quantity : 1.00 lotUnit Cost : P 21,269.04 '/lot
Equipment :1 '- Service Vehicle '- 4.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 8 '- Laborer '- 4.00 days @ P 220.00 '/day =
P
DIRECT COST :Equipment : P 4,000.00 Manpower : P 12,040.00
P 16,040.00
INDIRECT COST :15% OCM ': P 2,406.00 15% CP ': P 2,406.00 2% Tax ': P 417.04
P 5,229.04
TOTAL COST ': P 21,269.04 Unit Cost ': P 21,269.04 '/lot
2) Temporary FacilitiesQuantity : 1.00 lotUnit Cost : P 21,560.76 '/lot
Materials : 1.00 lot Miscellaenous Materials '@ P ### '/lot = P
P
Equipment :1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 4 '- Laborer '- 2.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 10,000.00 Equipment : P 2,000.00 Manpower : P 4,260.00
P 16,260.00
INDIRECT COST :15% OCM ': P 2,439.00 15% CP ': P 2,439.00 2% Tax ': P 422.76
P 5,300.76
TOTAL COST ': P 21,560.76 Unit Cost ': P 21,560.76 '/lot
II. EARTHWORKS1) Site Clearing and Grubbing
Quantity : 294.00 sq.m.Unit Cost : P 14.12 '/sq.m.
Equipment :1 '- Service Vehicle '- 1.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 1.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 1.00 days @ P 400.00 '/day = 1 '- Service Driver '- 1.00 days @ P 250.00 '/day = 4 '- Laborer '- 1.00 days @ P 220.00 '/day =
P
DIRECT COST :Equipment : P 1,000.00 Manpower : P 2,130.00
P 3,130.00
INDIRECT COST :15% OCM ': P 469.50 15% CP ': P 469.50 2% Tax ': P 81.38
P 1,020.38
TOTAL COST ': P 4,150.38 Unit Cost ': P 14.12 '/sq.
2) Structural ExcavationQuantity : 77.90 cu.m.Unit Cost : P 1,277.74 '/cu.m.
Equipment :1 '- Backho '- 6.00 days @ P 8,500.00 '/day = 1 '- Service Vehicle '- 6.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 1 '- Service Driver '- 6.00 days @ P 250.00 '/day = 8 '- Laborer '- 6.00 days @ P 220.00 '/day =
P
DIRECT COST :
Equipment : P 57,000.00 Manpower : P 18,060.00
P 75,060.00
INDIRECT COST :15% OCM ': P 11,259.00 15% CP ': P 11,259.00 2% Tax ': P 1,951.56
P 24,469.56
TOTAL COST ': P 99,529.56 Unit Cost ': P 1,277.74 '/cu.
3) Structural Backfill and CompactionQuantity : 8.03 cu.m.Unit Cost : P 1,325.01 '/cu.m.
Equipment :1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 8 '- Laborer '- 2.00 days @ P 220.00 '/day =
P
DIRECT COST :Equipment : P 2,000.00 Manpower : P 6,020.00
P 8,020.00
INDIRECT COST :15% OCM ': P 1,203.00 15% CP ': P 1,203.00 2% Tax ': P 208.52
P 2,614.52
TOTAL COST ': P 10,634.52 Unit Cost ': P 1,325.01 '/cu.
4) Earthfill and CompactionQuantity : 44.10 cu.m.Unit Cost : P 665.10 '/cu.m.
Equipment :1 '- Compactor '- 4.00 day @ P 2,400.00 '/day = 1 '- Service Vehicle '- 4.00 day @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 4.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 day @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 4 '- Laborer '- 4.00 day @ P 220.00 '/day =
P
DIRECT COST :
Equipment : P 13,600.00 Manpower : P 8,520.00
P 22,120.00
INDIRECT COST :15% OCM ': P 3,318.00 15% CP ': P 3,318.00 2% Tax ': P 575.12
P 7,211.12
TOTAL COST ': P 29,331.12 Unit Cost ': P 665.10 '/cu.
5) Gravel BeddingQuantity : 15.00 cu.m.Unit Cost : P 1,150.08 '/cu.m.
Materials : 15.00 cu.m. Gravel '@ P 450.00 '/cu.m.=
PEquipment :
1 '- Service Vehicle '- 2.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 2.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 day @ P 400.00 '/day = 1 '- Service Driver '- 2.00 day @ P 250.00 '/day = 4 '- Laborer '- 2.00 day @ P 220.00 '/day =
P
DIRECT COST :Materials : P 6,750.00 Equipment : P 2,000.00 Manpower : P 4,260.00
P 13,010.00
INDIRECT COST :15% OCM ': P 1,951.50 15% CP ': P 1,951.50 2% Tax ': P 338.26
P 4,241.26
TOTAL COST ': P 17,251.26 Unit Cost ': P 1,150.08 '/cu.
III. CONCRETE WORK1) Footings
Quantity : 9.94 cu.m.Unit Cost : P 4,947.14 '/cu.m.Materials : 10.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 5.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 90.00 bags Portland Cement '@ P 220.00 '/bag =
PEquipment :
1 '- Bagger Mixer '- 2.00 days @ P 750.00 '/day =
1 '- Concrete Vibrator '- 2.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 8 '- Laborer '- 2.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 26,550.00 Equipment : P 4,500.00 Manpower : P 6,020.00
P 37,070.00
INDIRECT COST :15% OCM ': P 5,560.50 15% CP ': P 5,560.50 2% Tax ': P 963.82
P 12,084.82
TOTAL COST ': P 49,154.82 Unit Cost ': P 4,947.14 '/cu.
2) Wall FootingsQuantity : 8.56 cu.m.Unit Cost : P 4,947.14 '/cu.m.
3) ColumnsQuantity : 16.50 cu.m.Unit Cost : P 4,947.14 '/cu.m.
4) BeamsQuantity : 12.76 cu.m.Unit Cost : P 4,947.14 '/cu.m.
5) StairsQuantity : 0.96 cu.m.Unit Cost : P 4,947.14 '/cu.m.
6) Interior SlabQuantity : 63.60 cu.m.Unit Cost : P 4,947.14 '/cu.m.
IV. REINFORCING STEEL BA1) 16mmØ Deformed Bars Gr.40
Quantity : 377.00 lgth.Unit Cost : P 604.72 '/lgth.
Materials : 377.00 lgths. 16mmØ x 6m Deformed Bars Gr.40 '@ P 240.00 '/lgth.= 5.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =
PEquipment :
1 '- Bar Cutter '- 15.00 days @ P 350.00 '/day =
1 '- Cut-off Machine '- 15.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 15.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 15.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 15.00 days @ P 400.00 '/day = 1 '- Service Driver '- 15.00 days @ P 250.00 '/day = 4 '- Steelmen '- 15.00 days @ P 300.00 '/day = 4 '- Laborer '- 15.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 94,230.00 Equipment : P 27,750.00 Manpower : P 49,950.00
P 171,930.00
INDIRECT COST :15% OCM ': P 25,789.50 15% CP ': P 25,789.50 2% Tax ': P 4,470.18
P 56,049.18
TOTAL COST ': P 227,979.18 Unit Cost ': P 604.72 '/lgth
2) 10mmØ Deformed Bars Gr.33 Quantity : 1,716.00 lgth.Unit Cost : P 183.81 '/lgth.
Materials : 1,716.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 1.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =
PEquipment :
1 '- Bar Cutter '- 10.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 10.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 10.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 10.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 10.00 days @ P 400.00 '/day = 1 '- Service Driver '- 10.00 days @ P 250.00 '/day = 4 '- Steelmen '- 10.00 days @ P 300.00 '/day = 4 '- Laborer '- 10.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 186,078.00 Equipment : P 18,500.00 Manpower : P 33,300.00
P 237,878.00
INDIRECT COST :15% OCM ': P 35,681.70 15% CP ': P 35,681.70 2% Tax ': P 6,184.83
P 77,548.23
TOTAL COST ': P 315,426.23 Unit Cost ': P 183.81 '/lgth
3) 20mmØ Deformed Bars Gr.40Quantity : 532.00 lgth.Unit Cost : P 604.72 '/lgth.
Materials : 532.00 lgths. 20mmØ x 6m Deformed Bars Gr.40 '@ P 320.00 '/lgth.= 10.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =
PEquipment :
1 '- Bar Cutter '- 12.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 12.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 12.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 1 '- Service Driver '- 12.00 days @ P 250.00 '/day = 4 '- Steelmen '- 12.00 days @ P 300.00 '/day = 4 '- Laborer '- 12.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 177,740.00 Equipment : P 22,200.00 Manpower : P 39,960.00
P 239,900.00
INDIRECT COST :15% OCM ': P 35,985.00 15% CP ': P 35,985.00 2% Tax ': P 6,237.40
P 78,207.40
TOTAL COST ': P 318,107.40 Unit Cost ': P 597.95 '/lgth
4) 12mmØ Deformed Bars Gr.33Quantity : 156.00 lgth.Unit Cost : P 60.18 '/lgth.
Materials : 156.00 lgths. 12mmØ x 6m Deformed Bars Gr.33 '@ P 166.00 '/lgth.= 2.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =
PEquipment :
1 '- Bar Cutter '- 3.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 3.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 3.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 3.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 3.00 days @ P 400.00 '/day =
1 '- Service Driver '- 3.00 days @ P 250.00 '/day = 4 '- Steelmen '- 3.00 days @ P 300.00 '/day = 4 '- Laborer '- 3.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 27,396.00 Equipment : P 5,550.00 Manpower : P 9,990.00
P 42,936.00
INDIRECT COST :15% OCM ': P 6,440.40 15% CP ': P 6,440.40 2% Tax ': P 1,116.34
P 13,997.14
TOTAL COST ': P 56,933.14 Unit Cost ': P 364.96 '/lgth
5) Tie WiresQuantity : 216.00 kg.Unit Cost : P 60.18 '/kg.
Materials : 216.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =
PEquipment :
1 '- Bar Cutter '- 4.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 4.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 4.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 1 '- Steelmen '- 4.00 days @ P 300.00 '/day = 4 '- Laborer '- 4.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 17,280.00 Equipment : P 7,400.00 Manpower : P 9,720.00
P 34,400.00
INDIRECT COST :15% OCM ': P 5,160.00 15% CP ': P 5,160.00 2% Tax ': P 894.40
P 11,214.40
TOTAL COST ': P 45,614.40 Unit Cost ': P 211.18 '/kg.
V. MASONRY WORKS
1) 6" Machine Made CHB with ReinforcementsQuantity : 73.38 sq.m.Unit Cost : P 1,273.81 '/sq.m.
Materials : 954.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 238.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth. = 6.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 94.00 bags Portland Cement '@ P 220.00 '/bag = 21.00 kgs. #16 Tie Wire '@ P 60.00 '/kg. =
PEquipment :
1 '- Bar Cutter '- 2.00 days @ P 350.00 '/day = 1 '- Bagger Mixer '- 2.00 days @ P 750.00 '/day = 1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 2 '- Masons '- 2.00 days @ P 280.00 '/day = 2 '- Laborer '- 2.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 61,792.00 Equipment : P 4,200.00 Manpower : P 4,500.00
P 70,492.00
INDIRECT COST :15% OCM ': P 10,573.80 15% CP ': P 10,573.80 2% Tax ': P 1,832.79
P 22,980.39
TOTAL COST ': P 93,472.39 Unit Cost ': P 1,273.81 '/sq.
2) 4" Machine Made CHB with ReinforcementsQuantity : 1,459.35 sq.m.Unit Cost : P 471.43 '/sq.m.
Materials : 18,972.00 pcs. 4" Machine Made CHB '@ P 6.50 '/pc. = 1,038.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth. = 42.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 780.00 bags Portland Cement '@ P 220.00 '/bag = 59.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =
PEquipment :
1 '- Bar Cutter '- 12.00 days @ P 350.00 '/day = 1 '- Bagger Mixer '- 12.00 days @ P 750.00 '/day = 1 '- Service Vehicle '- 12.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 12.00 days @ P 600.00 '/day =
1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 1 '- Service Driver '- 12.00 days @ P 250.00 '/day = 8 '- Masons '- 12.00 days @ P 280.00 '/day = 8 '- Laborer '- 12.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 430,642.00 Equipment : P 25,200.00 Manpower : P 63,000.00
P 518,842.00
INDIRECT COST :15% OCM ': P 77,826.30 15% CP ': P 77,826.30 2% Tax ': P 13,489.89
P 169,142.49
TOTAL COST ': P 687,984.49 Unit Cost ': P 471.43 '/sq.
3) PlasteringQuantity : 2,918.71 sq.m.Unit Cost : P 98.42 '/sq.m.Materials : 30.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 287.00 bags Portland Cement '@ P 220.00 '/bag =
PEquipment :
1 '- Bagger Mixer '- 20.00 days @ P 750.00 '/day = 1 '- Service Vehicle '- 20.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 20.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 20.00 days @ P 400.00 '/day = 1 '- Service Driver '- 20.00 days @ P 250.00 '/day = 8 '- Masons '- 20.00 days @ P 280.00 '/day = 8 '- Laborer '- 20.00 days @ P 220.00 '/day =
PDIRECT COST :
Materials : P 76,640.00 Equipment : P 35,000.00 Manpower : P 105,000.00
P 216,640.00
INDIRECT COST :15% OCM ': P 32,496.00 15% CP ': P 32,496.00 2% Tax ': P 5,632.64
P 70,624.64
TOTAL COST ': P 287,264.64 Unit Cost ': P 98.42 '/sq.
4) Plain Cement FinishQuantity : 2,860.12 sq.m.Unit Cost : P 36.24 '/sq.m.
Materials : 128.00 bags Portland Cement '@ P 220.00 '/bag =
PEquipment :
1 '- Service Vehicle '- 8.00 days @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 8.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 8.00 days @ P 400.00 '/day = 1 '- Service Driver '- 8.00 days @ P 250.00 '/day = 8 '- Masons '- 8.00 days @ P 280.00 '/day = 8 '- Laborer '- 8.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 28,160.00 Equipment : P 8,000.00 Manpower : P 42,000.00
P 78,160.00
INDIRECT COST :15% OCM ': P 11,724.00 15% CP ': P 11,724.00 2% Tax ': P 2,032.16
P 25,480.16
TOTAL COST ': P 103,640.16 Unit Cost ': P 36.24 '/sq.
VI. FORMWORKS and SCAFFOLDINGS1) Ordinary Plywood and Coco Lumber
Quantity : 355.90 sq.m.Unit Cost : P 1,154.94 '/sq.m.
Materials : 9,082.00 bd. ft. 2" x 2" Coco Lumber '@ P 12.00 '/bd.ft. 2,853.00 bd. ft. 2" x 3" Coco Lumber '@ P 12.00 '/bd.ft. 124.00 shts. 6mm Thk. Ordinary Plywood '@ P 240.00 '/sht. = 5.00 box 4" Common Wire Nails '@ P 1,200.00 '/box = 5.00 box 1" Common Wire Nails '@ P 1,201.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 20.00 days @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 20.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 20.00 days @ P 400.00 '/day = 1 '- Service Driver '- 20.00 days @ P 250.00 '/day = 8 '- Carpenters '- 20.00 days @ P 280.00 '/day = 8 '- Laborer '- 20.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 184,985.00 Equipment : P 20,000.00
Manpower : P 105,000.00 P 309,985.00
INDIRECT COST :15% OCM ': P 46,497.75 15% CP ': P 46,497.75 2% Tax ': P 8,059.61
P 101,055.11
TOTAL COST ': P 411,040.11 Unit Cost ': P 1,154.94 '/sq.
VII. STRUCTURAL STEEL WO1) 1.5mm THK x 2" x 6" C-Purlins
Quantity : 23.00 lgths.Unit Cost : P 2,631.76 '/lgth.
Materials : 23.00 lgths. 1.5mm thk x 2" x 6" C-Purlins '@ P 633.00 '/lgth.= 5.00 kg Fuji Welding Electrode E6012 '@ P 78.00 '/kg = 1.00 tanks Acytelene '@ P 1,650.00 '/tank = 1.00 tanks Industrial Oxygen '@ P 880.00 '/tank = 1.00 gals. Epoxy Zinchromate Primer '@ P 750.00 '/gal. = 1.00 gals. Epoxy Top Coat Paint '@ P 780.00 '/gal. = 1.00 gals. Epoxy Reducer '@ P 490.00 '/gal. = 1.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. = 3.00 pcs. 4" Paint Brush '@ P 70.00 '/pc. = 3.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. =
PEquipment :
2 '- Welding Machines '- 3.00 days @ P 500.00 '/day = 1 '- Gas Cutter '- 3.00 days @ P 500.00 '/day = 1 '- Cut-off Machine '- 3.00 days @ P 500.00 '/day = 2 '- Grinder '- 3.00 days @ P 350.00 '/day = 1 '- Delivery Truck '- 1.00 trips @ P 500.00 '/trip = 1 '- Service Vehicle '- 3.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 3.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 3.00 days @ P 400.00 '/day = 1 '- Service Driver '- 3.00 days @ P 250.00 '/day = 6 '- Welder '- 3.00 days @ P 320.00 '/day = 6 '- Laborer '- 3.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 20,579.00 Equipment : P 11,600.00 Manpower : P 13,470.00
P 45,649.00
INDIRECT COST :15% OCM ': P 6,847.35 15% CP ': P 6,847.35 2% Tax ': P 1,186.87
P 14,881.57
TOTAL COST ': P 60,530.57 Unit Cost ': P 2,631.76 '/lgths.
2) 1.5mm THK x 2" x 3" C-PurlinsQuantity : 48.00 lgth.Unit Cost : P 2,482.00 '/lgth.
Materials : 48.00 lgths. 1.5mm thk x 2" x 3" C-Purlins '@ P 552.00 '/lgth.= 2.00 boxes Fuji Welding Electrode E6012 '@ P 1,700.00 '/box = 1.00 tanks Acytelene '@ P 1,650.00 '/tank = 1.00 tanks Industrial Oxygen '@ P 880.00 '/tank = 3.00 gals. Epoxy Zinchromate Primer '@ P 750.00 '/gal. = 3.00 gals. Epoxy Top Coat Paint '@ P 780.00 '/gal. = 3.00 gals. Epoxy Reducer '@ P 490.00 '/gal. = 2.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. = 2.00 pcs. 4" Paint Brush '@ P 70.00 '/pc. = 2.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. =
PEquipment :
2 '- Welding Machines '- 6.00 days @ P 500.00 '/day = 1 '- Gas Cutter '- 6.00 days @ P 500.00 '/day = 1 '- Cut-off Machine '- 6.00 days @ P 500.00 '/day = 2 '- Grinder '- 6.00 days @ P 350.00 '/day = 1 '- Delivery Truck '- 1.00 trips @ P 500.00 '/trip = 1 '- Service Vehicle '- 6.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 1 '- Service Driver '- 6.00 days @ P 250.00 '/day = 6 '- Welder '- 6.00 days @ P 320.00 '/day = 6 '- Laborer '- 6.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 40,206.00 Equipment : P 22,700.00 Manpower : P 26,940.00
P 89,846.00
INDIRECT COST :15% OCM ': P 13,476.90 15% CP ': P 13,476.90 2% Tax ': P 2,336.00
P 29,289.80
TOTAL COST ': P 119,135.80 Unit Cost ': P 2,482.00 '/lgth
VIII. THERMAL and MOISTURE PROTECTION1) Roofing and Accessories
Quantity : 266.96 sq.m.Unit Cost : P 952.89 '/sq.m.
Materials : 251.00 li.m. Ga.22 x 6' Ord. Corr. Pre-painted Roofing '@ P 350.00 '/li.m. = 5.00 pcs. Ga.22 x 24" Pre-painted Ridge Roll '@ P 940.00 '/pc. = 19.00 pcs. Ga.22 x 36" Pre-painted Spanish Gutter '@ P 1,395.00 '/pc. = 22.00 pcs. Ga.22 x 36" Pre-painted Side Flashing '@ P 1,395.00 '/pc. = 18.00 pcs. Ga.22 x 24" Pre-painted Wall Flashing '@ P 940.00 '/pc. = 1,004.00 pcs. 2½" Metal Tekscrew '@ P 3.00 '/pc. = 1,004.00 pcs. ⅛"Ø x ⅜" Blind Rivets '@ P 0.75 '/pc. = 4.00 tubes Silicon Sealant '@ P 175.00 '/tube = 1.00 qrt. Touch-up Paint '@ P 120.00 '/qrt. = 2.00 pcs. Paint Brush ½" '@ P 25.00 '/pc. = 2.00 pcs. ⅛"Ø Steel Drill Bit '@ P 50.00 '/pc. =
PEquipment :
2 '- Hand Drill '- 4.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 4.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 4 '- Roofing Installer '- 4.00 days @ P 320.00 '/day = 4 '- Laborer '- 4.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 171,400.00 Equipment : P 6,800.00 Manpower : P 13,640.00
P 191,840.00
INDIRECT COST :15% OCM ': P 28,776.00 15% CP ': P 28,776.00 2% Tax ': P 4,987.84
P 62,539.84
TOTAL COST ': P 254,379.84 Unit Cost ': P 952.89 '/sq.
2) InsulationQuantity : 266.96 sq.m.Unit Cost : P 127.56 '/sq.m.
Materials : 4.00 rolls 10mm x 1m x 50m Double Foil Foam '@ P 5,100.00 '/roll = 5.00 rolls 3" Packaging Tape '@ P 50.00 '/roll = 1.00 roll #16 Tie Wire '@ P 1,700.00 '/roll =
PEquipment :
1 '- Service Vehicle '- 1.00 days @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 1.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 1.00 days @ P 400.00 '/day = 1 '- Service Driver '- 1.00 days @ P 250.00 '/day = 2 '- Roofing Installer '- 1.00 days @ P 320.00 '/day =
2 '- Laborer '- 1.00 days @ P 220.00 '/day = P
DIRECT COST :Materials : P 22,350.00 Equipment : P 1,000.00 Manpower : P 2,330.00
P 25,680.00
INDIRECT COST :15% OCM ': P 3,852.00 15% CP ': P 3,852.00 2% Tax ': P 667.68
P 8,371.68
TOTAL COST ': P 34,051.68 Unit Cost ': P 127.56 '/sq.
3) Interior Slab Vapor BarrierQuantity : 294.00 sq.m.Unit Cost : P 75.73 '/sq.m.
Materials : 4.00 rolls 1.2m x 50m Polyprophelene '@ P 3,500.00 '/roll = 2.00 rolls 3" Packaging Tape '@ P 50.00 '/roll =
PEquipment :
1 '- Service Vehicle '- 1.00 days @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 1.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 1.00 days @ P 400.00 '/day = 1 '- Service Driver '- 1.00 days @ P 250.00 '/day = 2 '- Laborer '- 1.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 14,100.00 Equipment : P 1,000.00 Manpower : P 1,690.00
P 16,790.00
INDIRECT COST :15% OCM ': P 2,518.50 15% CP ': P 2,518.50 2% Tax ': P 436.54
P 5,473.54
TOTAL COST ': P 22,263.54 Unit Cost ': P 75.73 '/sq.
IX. DOORS and WINDOWS1) Doors and Windows
Quantity : 1.00 lotUnit Cost : P 319,300.80 '/lotMaterials : 4.00 sets 0.90m x 2.10m Panel Door '@ P 4,000.00 '/set =
18.00 sets 0.70m x 2.10m Hollow Core Door '@ P 2,000.00 '/set = 4.00 sets 0.80m x 2.10m Panel Door '@ P 2,500.00 '/set = 14.00 sets 0.60m x 2.10m PVC Door '@ P 1,800.00 '/set = 2.00 sets 0.60m x 2.10m Panel Door '@ P 2,900.00 '/set = 18.00 sets 2-Panel at 0.8m x 1.2m Casement Window '@ P 5,200.00 '/set =
8.00 sets 0.80m x 1.20m Casement Window '@ P 2,600.00 '/set = 2.00 sets 0.80m x 0.90m Casement Window '@ P 2,300.00 '/set =
PEquipment :
1 '- Hand Drill '- 8.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 8.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 8.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 8.00 days @ P 400.00 '/day = 1 '- Service Driver '- 8.00 days @ P 250.00 '/day = 2 '- Installer '- 8.00 days @ P 280.00 '/day = 2 '- Helper '- 8.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 212,000.00 Equipment : P 10,800.00 Manpower : P 18,000.00
P 240,800.00
INDIRECT COST :15% OCM ': P 36,120.00 15% CP ': P 36,120.00 2% Tax ': P 6,260.80
P 78,500.80
TOTAL COST ': P 319,300.80 Unit Cost ': P 319,300.80 '/sq.
X. CEILING WORK1) 4.5mm Thk. Hardiflex Board on Lite Metal Frames ( Two Sides )
Quantity : 533.91 sq.m.Unit Cost : P 997.94 '/sq.m.
Materials : 186.00 shts. 4.5mm thk. x 1.2m x 2.4m Hardiflex Board '@ P 425.00 '/sht . = 1,900.00 pcs. 1" Hardiflex Screw '@ P 1.50 '/pc. = 534.00 sq.m. Lite Metal Frames '@ P 480.00 '/sq.m.=
PEquipment :
3 '- Hand Drill '- 12.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 12.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 1 '- Service Driver '- 12.00 days @ P 250.00 '/day = 4 '- Installer '- 12.00 days @ P 280.00 '/day = 4 '- Helper '- 12.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 338,220.00 Equipment : P 24,600.00 Manpower : P 39,000.00
P 401,820.00
INDIRECT COST :15% OCM ': P 60,273.00 15% CP ': P 60,273.00 2% Tax ': P 10,447.32
P 130,993.32
TOTAL COST ': P 532,813.32 Unit Cost ': P 997.94 '/sq.
XI. TILE WORKS1) 300mm x 300mm Ceramic Floor Tiles
Quantity : 375.80 sq.m.Unit Cost : P 775.91 '/sq.m.
Materials : 4,176.00 pcs. 300mm x 300mm Ceramic Floor Tiles '@ P 25.00 '/pc. = 4.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 37.00 bags Portland Cement '@ P 220.00 '/bag = 20.00 kgs. ABC Grout '@ P 28.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 20.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 20.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 20.00 day @ P 400.00 '/day = 1 '- Service Driver '- 20.00 day @ P 250.00 '/day = 6 '- Mason '- 20.00 day @ P 280.00 '/day = 6 '- Helper '- 20.00 day @ P 220.00 '/day =
P
DIRECT COST :Materials : P 114,900.00 Equipment : P 20,000.00 Manpower : P 85,000.00
P 219,900.00
INDIRECT COST :15% OCM ': P 32,985.00 15% CP ': P 32,985.00 2% Tax ': P 5,717.40
P 71,687.40
TOTAL COST ': P 291,587.40 Unit Cost ': P 775.91 '/sq.
2) 200mm x 200mm Ceramic Floor TilesQuantity : 25.20 sq.m.
Unit Cost : P 1,046.17 '/sq.m.
Materials : 630.00 pcs. 200mm x 200mm Ceramic Floor Tiles '@ P 12.00 '/pc. = 1.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 3.00 bags Portland Cement '@ P 220.00 '/bag = 3.00 kgs. ABC Grout '@ P 28.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 6.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 6.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 day @ P 400.00 '/day = 1 '- Service Driver '- 6.00 day @ P 250.00 '/day = 6 '- Mason '- 6.00 day @ P 280.00 '/day = 6 '- Helper '- 6.00 day @ P 220.00 '/day =
P
DIRECT COST :Materials : P 8,754.00 Equipment : P 6,000.00 Manpower : P 25,500.00
P 40,254.00
INDIRECT COST :15% OCM ': P 6,038.10 15% CP ': P 6,038.10 2% Tax ': P 1,046.60
P 13,122.80
TOTAL COST ': P 53,376.80 Unit Cost ': P 51.02 '/sq.
3) 200mm x 200mm Ceramic Wall TilesQuantity : 117.18 sq.m.Unit Cost : P 818.46 '/sq.m.
Materials : 2,930.00 pcs. 200mm x 200mm Ceramic Wall Tiles '@ P 12.00 '/pc. = 2.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 12.00 bags Portland Cement '@ P 220.00 '/bag = 49.00 pcs. Tile Trim '@ P 40.00 '/pc. = 6.00 kgs. ABC Grout '@ P 28.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 6.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 6.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 day @ P 400.00 '/day = 1 '- Service Driver '- 6.00 day @ P 250.00 '/day = 6 '- Mason '- 6.00 day @ P 280.00 '/day = 6 '- Helper '- 6.00 day @ P 220.00 '/day =
P
DIRECT COST :Materials : P 40,828.00 Equipment : P 6,000.00 Manpower : P 25,500.00
P 72,328.00
INDIRECT COST :15% OCM ': P 10,849.20 15% CP ': P 10,849.20 2% Tax ': P 1,880.53
P 23,578.93
TOTAL COST ': P 95,906.93 Unit Cost ': P 818.46 '/sq.
XII. METAL WORKS1) Railings and Balustrades
Quantity : 87.93 li.m.Unit Cost : P 1,844.56 '/li.m.
Materials : 15.00 length 2"Ø G.I. Pipe Sch.20 '@ P 2,600.00 '/lgth. = 16.00 length 1½"Ø G.I. Pipe Sch.20 '@ P 1,400.00 '/lgth. = 28.00 length ¼" x 2" x 6m Flat Bar '@ P 410.00 '/lgth. = 2.00 box Welding Electrode E6012 '@ P 1,700.00 '/box = 2.00 gals. Epoxy Zinchromate Primer '@ P 750.00 '/gal. = 2.00 gals. Epoxy Top Coat '@ P 780.00 '/gal. = 2.00 gals. Epoxy Reducer '@ P 490.00 '/gal. = 6.00 pcs. Paint Brush '@ P 40.00 '/pc. = 3.00 pcs. 14"Ø Cut-off Wheel Blade '@ P 550.00 '/pc. = 6.00 pcs. 4"Ø Grinding Disc '@ P 75.00 '/pc. =
PEquipment :
2 '- Welding Machine '- 6.00 days @ P 500.00 '/day = 1 '- Cut-off Machine '- 6.00 days @ P 500.00 '/day = 2 '- Grinder '- 6.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 6.00 days @ P 1,000.00 '/day =
PManpower :
1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 1 '- Service Driver '- 6.00 days @ P 250.00 '/day = 4 '- Welder '- 6.00 days @ P 320.00 '/day = 4 '- Laborer '- 6.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 82,660.00 Equipment : P 19,200.00 Manpower : P 20,460.00
P 122,320.00
INDIRECT COST :15% OCM ': P 18,348.00 15% CP ': P 18,348.00 2% Tax ': P 3,180.32
P 39,876.32
TOTAL COST ': P 162,196.32 Unit Cost ': P 1,844.56 '/li.m
XIII. PAINTING WORKS1) Masonry Walls
Quantity : 2,136.54 sq.m.Unit Cost : P 229.60 '/sq.m.
Materials : 86.00 gals. Concrete Neutralizer '@ P 360.00 '/gal. = 107.00 gals. Concrete Primer '@ P 520.00 '/gal. = 10.00 gals. Concrete Putty '@ P 500.00 '/gal. = 292.00 gals. Semi-gloss Latex '@ P 480.00 '/gal. = 29.20 gals. Thinner '@ P 350.00 '/gal. = 12.00 pcs. 9" Paint Roller '@ P 90.00 '/pc. = 12.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. = 100.00 pcs. #120 sand Paper '@ P 14.00 '/pc. = 30.00 rolls Masking Tape 1" '@ P 28.00 '/roll = 8.00 pcs. Paint Tray '@ P 70.00 '/pc. =
PManpower :
1 '- Project Engineer '- 30.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 30.00 days @ P 400.00 '/day = 8 '- Painter '- 30.00 days @ P 280.00 '/day = 4 '- Laborer '- 30.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 246,340.00 Manpower : P 123,600.00
P 369,940.00
INDIRECT COST :15% OCM ': P 55,491.00 15% CP ': P 55,491.00 2% Tax ': P 9,618.44
P 120,600.44
TOTAL COST ': P 490,540.44 Unit Cost ': P 229.60 '/sq.
2) CeilingQuantity : 533.91 sq.m.Unit Cost : P 245.18 '/sq.m.
Materials : 27.00 gal. Concrete Primer '@ P 520.00 '/gal. = 1.00 gals. Concrete Putty '@ P 500.00 '/gal. = 73.00 gals. Flat Latex '@ P 480.00 '/gal. = 2.00 pcs. 9" Paint Roller '@ P 90.00 '/pc. = 2.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. = 20.00 pcs. #120 sand Paper '@ P 14.00 '/pc. =
PManpower :
1 '- Project Engineer '- 15.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 15.00 days @ P 400.00 '/day = 8 '- Painter '- 15.00 days @ P 280.00 '/day =
P
DIRECT COST :Materials : P 50,120.00 Manpower : P 48,600.00
P 98,720.00
INDIRECT COST :15% OCM ': P 14,808.00 15% CP ': P 14,808.00 2% Tax ': P 2,566.72
P 32,182.72
TOTAL COST ': P 130,902.72 Unit Cost ': P 245.18 '/sq.
XIV.ELECTRICAL WOR1) Rough-in
Quantity : 1.00 lotUnit Cost : P 431,817.20 '/lot
Materials : 4.00 units 1 Main; 8-Branches Panel Boards '@ P 4,000.00 '/set = 10.00 units 1 Main; 4-Branches Panel Boards '@ P 2,800.00 '/set = 6.00 rolls 3.5 sq.mm. THW Wire '@ P 2,400.00 '/set = 4.00 rolls 5.5 sq.mm. THW Wire '@ P 3,200.00 '/set = 20.00 rolls Electrical Tape '@ P 30.00 '/roll = 18.00 pcs. 4" x 4" Junction Box '@ P 38.00 '/pc. = 144.00 pcs. 4" x 2" Utility Box '@ P 25.00 '/pc. = 14.00 sets 1"Ø Entrance Cap Assembly '@ P 3,000.00 '/lgth. = 28.00 lengths RSC Pipe 1"Ø '@ P 1,400.00 '/lgth. = 6.00 rolls Flexible Pipe ½"Ø '@ P 700.00 '/lgth. = 140.00 meters THW Wire No.6 '@ P 250.00 '/roll = 42.00 meters Bare Wire No.8 '@ P 85.00 '/roll =
PEquipment :
1 '- Service Vehicle '- 40.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 40.00 days @ P 600.00 '/day = 1 '- Electrical Engineer '- 40.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 40.00 days @ P 400.00 '/day = 1 '- Electrician '- 40.00 days @ P 320.00 '/day = 1 '- Helper '- 40.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 200,054.00 Equipment : P 40,000.00 Manpower : P 85,600.00
P 325,654.00
INDIRECT COST :
15% OCM ': P 48,848.10 15% CP ': P 48,848.10 2% Tax ': P 8,467.00
P 106,163.20
TOTAL COST ': P 431,817.20 Unit Cost ': P 431,817.20 '/lot
2) FixturesQuantity : 1.00 lotUnit Cost : P 252,046.08 '/lot
Materials : 14.00 sets Electric Power Meter '@ P 3,000.00 '/set = 14.00 sets 100A Circuit Breaker '@ P 1,200.00 '/set = 72.00 sets 20A Circuit Breaker '@ P 750.00 '/set = 112.00 sets Light Outlet w/ Incandescent Lamp '@ P 280.00 '/set = 18.00 sets A.C.U. Outlet '@ P 400.00 '/set = 4.00 sets Range Outlet '@ P 400.00 '/set = 14.00 sets 1 Gang Switch '@ P 90.00 '/set = 22.00 sets 2 Gang Switch '@ P 180.00 '/set = 18.00 sets 3 Gang Switch '@ P 220.00 '/set = 68.00 sets 2 Gang Convenience Outlet '@ P 180.00 '/set =
PEquipment :
1 '- Service Vehicle '- 5.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 5.00 days @ P 600.00 '/day = 1 '- Electrical Engineer '- 5.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 5.00 days @ P 400.00 '/day = 1 '- Electrician '- 5.00 days @ P 320.00 '/day = 1 '- Helper '- 5.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 174,380.00 Equipment : P 5,000.00 Manpower : P 10,700.00
P 190,080.00
INDIRECT COST :15% OCM ': P 28,512.00 15% CP ': P 28,512.00 2% Tax ': P 4,942.08
P 61,966.08
TOTAL COST ': P 252,046.08 Unit Cost ': P 252,046.08 '/lot
XV. PLUMBING WORKS1) Potable Water
Quantity : 1.00 lotUnit Cost : P 112,935.42 '/lot
Materials :
44.00 pcs. ½"Ø PVC Eslon Blue '@ P 560.00 '/lgth. = 30.00 pcs. ½"Ø PVC Tee '@ P 25.00 '/set = 22.00 pcs. ½"Ø PVC Elbow '@ P 25.00 '/pc. = 18.00 pcs. ½"Ø PVC Elbow w/ Thread '@ P 25.00 '/pc. = 24.00 pcs. ½"Ø PVC Elbow Coupling '@ P 25.00 '/pc. = 18.00 pcs. ½"Ø Male Adaptor '@ P 30.00 '/pc. = 6.00 pcs. ½"Ø Gate Valve '@ P 480.00 '/set = 6.00 pcs. ½"Ø Check Valve '@ P 620.00 '/set = 6.00 pcs. Water Meter '@ P 2,500.00 '/set = 8.00 cans Solvent Cement '@ P 180.00 '/can = 8.00 rolls Teflon Tape '@ P 35.00 '/roll =
PEquipment :
1 '- Service Vehicle '- 12.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 2 '- Plumbers '- 12.00 days @ P 320.00 '/day = 1 '- Helper '- 12.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 50,850.00 Equipment : P 12,000.00 Manpower : P 22,320.00
P 85,170.00
INDIRECT COST :15% OCM ': P 12,775.50 15% CP ': P 12,775.50 2% Tax ': P 2,214.42
P 27,765.42
TOTAL COST ': P 112,935.42 Unit Cost ': P 112,935.42 '/lot
2) Waste Water Line & Storm DrainageQuantity : 1.00 lotUnit Cost : P 158,350.92 '/lot
Materials : 42.00 pcs. 4"Ø PVC Sanitary Pipe '@ P 450.00 '/pc. = 28.00 pcs. 3"Ø PVC Sanitary Pipe '@ P 420.00 '/pc. = 42.00 pcs. 2"Ø PVC Sanitary Pipe '@ P 400.00 '/pc. = 24.00 pcs. 4"Ø x 4"Ø PVC Wye '@ P 65.00 '/pc. = 14.00 pcs. 4"Ø x 3"Ø PVC Wye '@ P 65.00 '/pc. = 14.00 pcs. 4"Ø x 2"Ø PVC Wye '@ P 65.00 '/pc. = 20.00 pcs. 4"Ø x 90° PVC Elbow '@ P 65.00 '/pc. = 10.00 pcs. 4"Ø x 45° PVC Elbow '@ P 65.00 '/pc. = 24.00 pcs. 3"Ø x 90° PVC Elbow '@ P 55.00 '/pc. = 18.00 pcs. 2"Ø x 90° PVC Elbow '@ P 55.00 '/pc. = 14.00 pcs. 2"Ø x 45° PVC Elbow '@ P 55.00 '/pc. = 22.00 pcs. 2"Ø PVC Tee '@ P 55.00 '/pc. = 14.00 pcs. 3"Ø P-Trap '@ P 90.00 '/pc. = 18.00 pcs. 4"Ø PVC Clean-out '@ P 65.00 '/pc. = 6.00 pcs. 4"Ø PVC Tee '@ P 65.00 '/pc. =
52.00 pcs. 6"Ø RC Pipe '@ P 450.00 '/pc. = 10.00 cans Solvent Cement '@ P 180.00 '/can =
PEquipment :
1 '- Service Vehicle '- 12.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 2 '- Plumbers '- 12.00 days @ P 320.00 '/day = 1 '- Helper '- 12.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 85,100.00 Equipment : P 12,000.00 Manpower : P 22,320.00
P 119,420.00
INDIRECT COST :15% OCM ': P 17,913.00 15% CP ': P 17,913.00 2% Tax ': P 3,104.92
P 38,930.92
TOTAL COST ': P 158,350.92 Unit Cost ': P 158,350.92 '/lot
3) FixturesQuantity : 1.00 lotUnit Cost : P 321,687.60 '/lot
Materials : 14.00 set '@ P 6,000.00 '/set =
4.00 set '@ P 4,500.00 '/set =
10.00 set Lavatory Counter Type '@ P 6,000.00 '/set = 4.00 set '@ P 4,500.00 '/set =
4.00 set Laundry Sink w/ P-Trap '@ P 3,000.00 '/set = 14.00 pcs. 4"Ø Floor Drain '@ P 200.00 '/pc. = 8.00 pcs. 3"Ø Basket Strainer (Doom Type) '@ P 200.00 '/pc. =
PEquipment :
1 '- Service Vehicle '- 15.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 15.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 15.00 days @ P 400.00 '/day = 2 '- Plumbers '- 15.00 days @ P 320.00 '/day = 2 '- Helper '- 15.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 196,400.00
Water Closet w/ Flexible Hose & Angle Valve
Lavatory (Wall Hang) w/ Flex. Hose, Angle Valve, Faucet & P-Trap
Kitchen Sink w/ Flex. Hose, Angle Valve, Faucet & P-Trap
Equipment : P 15,000.00 Manpower : P 31,200.00
P 242,600.00
INDIRECT COST :15% OCM ': P 36,390.00 15% CP ': P 36,390.00 2% Tax ': P 6,307.60
P 79,087.60
TOTAL COST ': P 321,687.60 Unit Cost ': P 321,687.60 '/lot
4) Septic TankQuantity : 2.00 unitsUnit Cost : P 45,605.00 '/unit
Materials : 5.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 6.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 100.00 bags Portland Cement '@ P 220.00 '/bag = 493.00 length 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 618.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 45.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 6.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 2 '- Plumbers/Masons '- 6.00 days @ P 320.00 '/day = 4 '- Helper '- 6.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 91,210.00 Equipment : P 6,000.00 Manpower : P 15,120.00
P 112,330.00
INDIRECT COST :15% OCM ': P 16,849.50 15% CP ': P 16,849.50 2% Tax ': P 2,920.58
P 36,619.58
TOTAL COST ': P 148,949.58 Unit Cost ': P 74,474.79 '/unit
4) Catch BasinQuantity : 8.00 unitsUnit Cost : P 6,087.25 '/unit
Materials : 1.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 2.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.=
28.00 bags Portland Cement '@ P 220.00 '/bag = 335.00 length 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 204.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 32.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 8.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 8.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 8.00 days @ P 400.00 '/day = 2 '- Plumbers/Masons '- 8.00 days @ P 320.00 '/day = 4 '- Helper '- 8.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 48,698.00 Equipment : P 8,000.00 Manpower : P 20,160.00
P 76,858.00
INDIRECT COST :15% OCM ': P 11,528.70 15% CP ': P 11,528.70 2% Tax ': P 1,998.31
P 25,055.71
TOTAL COST ': P 101,913.71 Unit Cost ': P 12,739.21 '/unit
5) Grease TrapQuantity : 4.00 unitsUnit Cost : P 6,062.00 '/unit
Materials : 1.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 3.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 39.00 bags Portland Cement '@ P 220.00 '/bag = 83.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 362.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 7.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =
PEquipment :
1 '- Service Vehicle '- 4.00 day @ P 1,000.00 '/day = P
Manpower :1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 2 '- Plumbers/Masons '- 4.00 days @ P 320.00 '/day = 4 '- Helper '- 4.00 days @ P 220.00 '/day =
P
DIRECT COST :Materials : P 24,248.00 Equipment : P 4,000.00 Manpower : P 10,080.00
P 38,328.00
INDIRECT COST :15% OCM ': P 5,749.20 15% CP ': P 5,749.20 2% Tax ': P 996.53
P 12,494.93
TOTAL COST ': P 50,822.93 Unit Cost ': P 12,705.73 '/unit
4,000.00 4,000.00
2,400.00 1,600.00 1,000.00 7,040.00 12,040.00
10,000.00 10,000.00
2,000.00 2,000.00
1,200.00 800.00 500.00 1,760.00 4,260.00
1,000.00 1,000.00
600.00 400.00 250.00 880.00 2,130.00
51,000.00 6,000.00 57,000.00
3,600.00 2,400.00 1,500.00 10,560.00 18,060.00
2,000.00 2,000.00
1,200.00 800.00 500.00 3,520.00 6,020.00
9,600.00 4,000.00 13,600.00
2,400.00 1,600.00 1,000.00 3,520.00 8,520.00
6,750.00 6,750.00
2,000.00 2,000.00
1,200.00 800.00 500.00 1,760.00 4,260.00
4,500.00 2,250.00 19,800.00 26,550.00
1,500.00
1,000.00 2,000.00 4,500.00
1,200.00 800.00 500.00 3,520.00 6,020.00
90,480.00 3,750.00 94,230.00
5,250.00
7,500.00 15,000.00 27,750.00
9,000.00 6,000.00 3,750.00 18,000.00 13,200.00 49,950.00
185,328.00 750.00 186,078.00
3,500.00 5,000.00 10,000.00 18,500.00
6,000.00 4,000.00 2,500.00 12,000.00 8,800.00 33,300.00
170,240.00 7,500.00 177,740.00
4,200.00 6,000.00 12,000.00 22,200.00
7,200.00 4,800.00 3,000.00 14,400.00 10,560.00 39,960.00
25,896.00 1,500.00 27,396.00
1,050.00 1,500.00 3,000.00 5,550.00
1,800.00 1,200.00
750.00 3,600.00 2,640.00 9,990.00
17,280.00 17,280.00
1,400.00 2,000.00 4,000.00 7,400.00
2,400.00 1,600.00 1,000.00 1,200.00 3,520.00 9,720.00
11,448.00 25,704.00 2,700.00 20,680.00 1,260.00 61,792.00
700.00 1,500.00 2,000.00 4,200.00
1,200.00 800.00 500.00 1,120.00 880.00 4,500.00
123,318.00 112,104.00 18,900.00 171,600.00 4,720.00 430,642.00
4,200.00 9,000.00 12,000.00 25,200.00
7,200.00
4,800.00 3,000.00 26,880.00 21,120.00 63,000.00
13,500.00 63,140.00 76,640.00
15,000.00 20,000.00 35,000.00
12,000.00 8,000.00 5,000.00 44,800.00 35,200.00 105,000.00
28,160.00 28,160.00
8,000.00 8,000.00
4,800.00 3,200.00 2,000.00 17,920.00 14,080.00 42,000.00
108,984.00 34,236.00 29,760.00 6,000.00 6,005.00 184,985.00
20,000.00 20,000.00
12,000.00 8,000.00 5,000.00 44,800.00 35,200.00 105,000.00
14,559.00 390.00 1,650.00 880.00 750.00 780.00 490.00 750.00 210.00 120.00 20,579.00
3,000.00 1,500.00 1,500.00 2,100.00 500.00 3,000.00 11,600.00
1,800.00 1,200.00 750.00 5,760.00 3,960.00 13,470.00
26,496.00 3,400.00 1,650.00 880.00 2,250.00 2,340.00 1,470.00 1,500.00 140.00 80.00 40,206.00
6,000.00 3,000.00 3,000.00 4,200.00 500.00 6,000.00 22,700.00
3,600.00 2,400.00 1,500.00 11,520.00 7,920.00 26,940.00
87,850.00 4,700.00 26,505.00 30,690.00 16,920.00 3,012.00 753.00 700.00 120.00 50.00 100.00 171,400.00
2,800.00 4,000.00 6,800.00
2,400.00 1,600.00 1,000.00 5,120.00 3,520.00 13,640.00
20,400.00 250.00 1,700.00 22,350.00
1,000.00 1,000.00
600.00 400.00 250.00 640.00
440.00 2,330.00
14,000.00 100.00 14,100.00
1,000.00 1,000.00
600.00 400.00 250.00 440.00 1,690.00
16,000.00
36,000.00 10,000.00 25,200.00 5,800.00 93,600.00
20,800.00 4,600.00 212,000.00
2,800.00 8,000.00 10,800.00
4,800.00 3,200.00 2,000.00 4,480.00 3,520.00 18,000.00
79,050.00 2,850.00 256,320.00 338,220.00
12,600.00 12,000.00 24,600.00
7,200.00 4,800.00 3,000.00 13,440.00 10,560.00
39,000.00
104,400.00 1,800.00 8,140.00 560.00 114,900.00
20,000.00 20,000.00
12,000.00 8,000.00 5,000.00 33,600.00 26,400.00 85,000.00
7,560.00 450.00 660.00 84.00 8,754.00
6,000.00 6,000.00
3,600.00 2,400.00 1,500.00 10,080.00 7,920.00 25,500.00
35,160.00 900.00 2,640.00 1,960.00 168.00 40,828.00
6,000.00 6,000.00
3,600.00 2,400.00 1,500.00 10,080.00 7,920.00 25,500.00
39,000.00 22,400.00 11,480.00 3,400.00 1,500.00 1,560.00 980.00 240.00 1,650.00 450.00 82,660.00
6,000.00 3,000.00 4,200.00 6,000.00 19,200.00
3,600.00 2,400.00 1,500.00 7,680.00 5,280.00 20,460.00
30,960.00 55,640.00 5,000.00 140,160.00 10,220.00 1,080.00 480.00 1,400.00 840.00 560.00 246,340.00
18,000.00 12,000.00 67,200.00 26,400.00 123,600.00
14,040.00 500.00 35,040.00 180.00 80.00 280.00 50,120.00
9,000.00 6,000.00 33,600.00 48,600.00
16,000.00 28,000.00 14,400.00 12,800.00 600.00 684.00 3,600.00 42,000.00 39,200.00 4,200.00 35,000.00 3,570.00 200,054.00
40,000.00 40,000.00
24,000.00 24,000.00 16,000.00 12,800.00 8,800.00 85,600.00
42,000.00 16,800.00 54,000.00 31,360.00 7,200.00 1,600.00 1,260.00 3,960.00 3,960.00 12,240.00 174,380.00
5,000.00 5,000.00
3,000.00 3,000.00 2,000.00 1,600.00 1,100.00 10,700.00
24,640.00 750.00 550.00 450.00 600.00 540.00 2,880.00 3,720.00 15,000.00 1,440.00 280.00 50,850.00
12,000.00 12,000.00
7,200.00 4,800.00 7,680.00 2,640.00 22,320.00
18,900.00 11,760.00 16,800.00 1,560.00 910.00 910.00 1,300.00 650.00 1,320.00 990.00 770.00 1,210.00 1,260.00 1,170.00 390.00
23,400.00 1,800.00 85,100.00
12,000.00 12,000.00
7,200.00 4,800.00 7,680.00 2,640.00 22,320.00
84,000.00
18,000.00
60,000.00 18,000.00
12,000.00 2,800.00 1,600.00 196,400.00
15,000.00 15,000.00
9,000.00 6,000.00 9,600.00 6,600.00 31,200.00
2,250.00 2,700.00 22,000.00 53,244.00 7,416.00 3,600.00 91,210.00
6,000.00 6,000.00
3,600.00 2,400.00 3,840.00 5,280.00 15,120.00
450.00 900.00
6,160.00 36,180.00 2,448.00 2,560.00 48,698.00
8,000.00 8,000.00
4,800.00 3,200.00 5,120.00 7,040.00 20,160.00
450.00 1,350.00 8,580.00 8,964.00 4,344.00 560.00 24,248.00
4,000.00 4,000.00
2,400.00 1,600.00 2,560.00 3,520.00 10,080.00
QTY B (m) H (m) THK (m) AREA (sq.m)LOT 2.00 10.00 14.70 2.00 x 10.00 x14.70 = 294.00
COLUMN FOOTINGSCF1 2.00 1.20 1.20 0.30CF2 2.00 1.20 2.40 0.30CF3 3.00 1.20 1.20 0.30
WF1 1.00 30.00 23.80 0.80
WALL TOTAL = 1459.35WF1 1.00 0.35 122.30 0.20 1.00 x 122.30 x 0.60 = 73.38WL1 1.00 122.30 3.00 1.00 x 122.30 x 3.00 = 366.90WL2 2.00 8.00 11.55 3.00 2.00 x 78.20 x 3.00 = 469.20WL3 1.00 57.50 39.70 2.70 1.00 x 194.40 x 2.70 = 524.88PARAPET 1.00 6.85 2.99 2.00 x 1.00 x 6.85 x 2.99 = 40.92
FIREWALLCF1 3.00 1.20 1.20 0.30CF2 1.00 1.20 2.40 0.30WL1 1.00 14.70 0.80WL3 1.00 13.70 2.70 1.00 x 13.70 x 2.70 = 36.99PARAPET 1.00 6.85 2.99 1.00 x 6.85 x 2.99 = 20.46C1ug 3.00 0.20 0.30 1.00C2ug 2.00 0.20 0.30 1.00C1 6.00 0.20 0.30 6.00C2 4.00 0.20 0.30 6.00B1 1.00 0.20 0.30 12.30
COLUMNSC1ug 2.00 0.20 0.30 1.00C2ug 4.00 0.20 0.30 1.00C3ug 3.00 0.20 0.30 1.00C1 2.00 0.20 0.30 6.00C2 8.00 0.20 0.30 6.00C3 6.00 0.20 0.30 6.00
FLOORINGEARTH 1.00 10.00 14.70 0.15GRAVEL 1.00 10.00 14.70 0.05SLAB1 1.00 10.00 14.70 0.10SLAB2 1.00 10.00 11.40 0.15
SVs & CBsSV 1.00 3.00 1.50 1.80 2.00 x 2.00 x 3.70 x 2.90 = 42.92CB 6.00 0.70 0.70 0.70 2.00 x 8.00 x 0.70 x 0.70 = 7.84GT 2.00 0.60 0.60 1.45 2.00 x 4.00 x 0.60 x 0.60 = 2.88
BEAMSB1 1.00 0.20 0.30 69.45B2 2.00 0.20 0.30 4.95B3 2.00 0.15 0.30 3.00B4 1.00 0.15 0.30 7.55CB1 2.00 0.20 0.30 2.95CB2 5.00 0.20 0.30 0.95
STAIRS 8.00 0.30 0.20 1.00
BEDBARS QTY B (m) QTY H (m)FOOTINGS
CF1 8.00 1.20 8.00 1.20CF2 16.00 1.20 8.00 2.40CF3 8.00 1.20 8.00 1.20
WF1 407.67 0.35 3.00 122.30SLAB
SLAB1 49.00 10.00 33.33 14.70SLAB2 91.20 10.00 80.00 11.40
WALLWF1 9.00 122.30 203.83 0.60WL1-2 5.00 200.50 501.25 3.00WL3 4.50 208.10 520.25 2.70PARAPET 4.98 13.70 34.25 2.99
SVCONCRETE 98.67 14.80 77.33 11.60MASONRY 3.00 26.40 66.00 1.80
CBCONCRETE 74.67 11.20 74.67 11.20MASONRY 1.17 22.40 56.00 0.70
GTCONCRETE 32.00 4.80 32.00 4.80MASONRY 2.42 19.20 48.00 1.45
DRBs QTY B (m) QTY H (m)COLUMNS
C1 402.00 1.00 4.00 67.00C2 780.00 1.00 4.00 130.00C3 684.00 1.00 4.00 114.00
BEAMSB1 163.20 1.00 2.00 151.20B2 35.80 1.00 2.00 19.80
BEAMSB3 28.00 0.90 2.00 12.00B4 23.10 0.90 2.00 15.10
CANTILIVERED BEAMSCB1 27.80 1.00 5.00 11.80CB2 49.50 1.00 5.00 9.50
STAIRS 32.00 1.00 32.00 8.00
TIE WIRES QTY QTY QTY 38101.27FOOTINGS
CF1 8.00 8.00 7.00 448.00CF2 16.00 8.00 5.00 640.00CF3 8.00 8.00 6.00 384.00
WF1 407.67 3.00 1.00 1223.00COLUMNS
C1 402.00 6.00 1.00 2412.00C2 780.00 6.00 1.00 4680.00C3 684.00 6.00 1.00 4104.00
BEAMSB1 163.20 10.00 1.00 1632.00B2 35.80 6.00 1.00 214.80B3 28.00 8.00 1.00 224.00B4 23.10 8.00 1.00 184.80
SLAB
SLAB1 49.00 33.33 2.00 3266.67SLAB2 91.20 80.00 2.00 14592.00
STAIRS 32.00 32.00 2.00 4096.00WALL 10376.78
WF1 9.00 203.83 1.00 3669.00WL1-2 5.00 501.25 1.00 5012.50WL3 4.50 520.25 1.00 4682.25PARAPET 4.98 34.25 2.00 682.03
SV 7828.22CONCRETE 98.67 77.33 1.00 7630.22MASONRY 3.00 66.00 1.00 198.00
CB 5640.44CONCRETE 74.67 74.67 1.00 5575.11 TOTAL = 1024.99MASONRY 1.17 56.00 1.00 65.33 1.00 x 311.00 / 2.00 = 155.50
GT 1140.00 1.00 x 192.30 / 2.00 = 96.15CONCRETE 32.00 32.00 1.00 1024.00 1.00 x 8.00 / 2.00 = 4.00MASONRY 2.42 48.00 1.00 116.00 10.00 x 26.10 / 2.00 = 130.50
122.30 x 0.60 / 2.00 = 36.69FORMS 200.50 x 3.00 / 2.00 = 300.75
COLUMNS 1.00 311.00 208.10 x 2.70 / 2.00 = 280.94BEAMS 1.00 192.30 13.70 x 2.99 / 2.00 = 20.46STAIRS 1.00 8.00SLAB 10.00 26.10WALLS 122.30 0.60
200.50 3.00208.10 2.70
13.70 2.99TOTAL = 375.80
ROOF 2.00 x 1.00 x 10.00 x 9.65 = 193.00MAIN 2.00 6.23 9.90 2.00 2.00 x 1.00 x 10.00 x10.40 = 208.00STAIRS 1.00 2.55 1.50 0.82 2.00 x 7.00 x 1.20 x 1.50 = 25.20RIDGE 1.00 9.90 2.00 x 7.00 x 5.40 x 1.55 = 117.18
TILES1F 1.00 10.00 9.652F 1.00 10.00 10.40T&B 7.00 1.20 1.50WALLS 7.00 5.40 1.55
DOORS & WINDOWS TOTAL = 212.52D1 4.00 0.90 2.10 0.90 x 2.10 x 4.00 = 7.56D2 18.00 0.70 2.10 0.70 x 2.10 x18.00 = 26.46D3 4.00 0.80 2.10 0.80 x 2.10 x 4.00 = 6.72D4 14.00 0.60 2.10 0.60 x 2.10 x14.00 = 17.64D5 2.00 1.00 2.10 1.00 x 2.10 x 2.00 = 4.20W1 18.00 1.60 1.20 1.60 x 1.20 x18.00 = 34.56W2 8.00 0.80 1.20 0.80 x 1.20 x 8.00 = 7.68W3 2.00 0.80 0.90 0.80 x 0.90 x 2.00 = 1.44
RAILINGS 87.93STAIRS 11.00 0.36 7.93FRONT 2.00 20.00 80.00BALUST. 77.67 0.60 93.20
VOLUME (cu.m) PERIMETER (m)2.00 x ( 10.00 + 14.70 )x ### =
TOTAL = 9.942.00 x 2.00 x 1.20 x 1.20 x 0.30 = 1.732.00 x 2.00 x 1.20 x 2.40 x 0.30 = 3.462.00 x 3.00 x 1.20 x 1.20 x 0.30 = 2.59
2.00 x 1.00 x 0.15 x 107.60 x 0.80 = 25.82 2.00 x ( 30.00 + 23.80 )x ### =
1.00 x 0.35 x 122.30 x 0.20 = 8.56
2.00 x ( 8.00 + 11.55 )x ### =2.00 x ( 57.50 + 39.70 )x ### =
HEIGHT3.00 x 1.20 x 1.20 x 0.30 = 1.301.00 x 1.20 x 2.40 x 0.30 = 0.861.00 x 0.15 x 14.70 x 0.80 = 1.76 ( 0.00 + 14.70 )x ### =
3.00 x 0.20 x 0.30 x 1.00 = 0.18 3.002.00 x 0.20 x 0.30 x 1.00 = 0.12 2.006.00 x 0.20 x 0.30 x 6.00 = 2.16 36.004.00 x 0.20 x 0.30 x 6.00 = 1.44 24.001.00 x 0.20 x 0.30 x12.30 = 0.74 12.30
TOTAL = 16.50 HEIGHT2.00 x 2.00 x 0.20 x 0.30 x 1.00 = 0.24 4.002.00 x 4.00 x 0.20 x 0.30 x 1.00 = 0.48 8.002.00 x 3.00 x 0.20 x 0.30 x 1.00 = 0.36 6.002.00 x 2.00 x 0.20 x 0.30 x 6.00 = 1.44 24.002.00 x 8.00 x 0.20 x 0.30 x 6.00 = 5.76 96.002.00 x 6.00 x 0.20 x 0.30 x 6.00 = 4.32 72.00
TOTAL = 63.602.00 x 1.00 x10.00 x 14.70 x 0.15 = 44.102.00 x 1.00 x10.00 x 14.70 x 0.05 = 14.702.00 x 1.00 x10.00 x 14.70 x 0.10 = 29.402.00 x 1.00 x10.00 x 11.40 x 0.15 = 34.20
TOTAL = 22.402.00 x 1.00 x 3.00 x 1.50 x 1.80 = 16.20 2.00 x ( 7.40 + 5.80 )x ### =2.00 x 6.00 x 0.70 x 0.70 x 0.70 = 4.12 2.00 x ( 1.40 + 1.40 )x ### =2.00 x 2.00 x 0.60 x 0.60 x 1.45 = 2.09 2.00 x ( 1.20 + 1.20 )x ### =
TOTAL = 12.76 HEIGHT2.00 x 1.00 x 0.20 x 0.30 x69.45 = 8.33 138.902.00 x 2.00 x 0.20 x 0.30 x 4.95 = 1.19 19.802.00 x 2.00 x 0.15 x 0.30 x 3.00 = 0.54 12.002.00 x 1.00 x 0.15 x 0.30 x 7.55 = 0.68 15.102.00 x 2.00 x 0.20 x 0.30 x 2.95 = 0.71 11.802.00 x 5.00 x 0.20 x 0.30 x 0.95 = 0.57 9.50
2.00 x 8.00 x 0.30 x 0.20 x 1.00 = 0.96 8.00
TOTAL =7.00 x ( 9.60 + 9.60 )x ### =5.00 x ( 19.20 + 19.20 )x ### =6.00 x ( 9.60 + 9.60 )x ### =1.00 x ( 142.68 +366.90 )x ### =
TOTAL =2.00 x ( 490.00 +490.00 )x ### =2.00 x ( 912.00 +912.00 )x ### =
TOTAL =### x 1.15 +122.30 x ### =### x 1.15 + ### x ### =
936.45 x 1.15 + ### x ### =68.20 x 1.15 +102.30 x ### =
TOTAL =( ### +897.07 )x ### =
79.20 x 1.15 +118.80 x ### =TOTAL =
( 836.27 +836.27 )x ### =26.13 x 1.15 + 39.20 x ### =
TOTAL =( 153.60 +153.60 )x ### =
46.40 x 1.15 + 69.60 x ### =
LATERAL TIES VERTICAL BARSTOTAL = 2145.90 TOTAL =
402.00 x 1.00 x 1.15 x 1.00 = 462.30 4.00 x ( 67.00 x 1.30 )x ### =780.00 x 1.00 x 1.15 x 1.00 = 897.00 4.00 x ( 130.00 x 1.30 )x ### =684.00 x 1.00 x 1.15 x 1.00 = 786.60 4.00 x ( 114.00 x 1.30 )x ### =
163.20 x 1.00 x 1.15 x 1.00 = 187.68 2.00 x ( 151.20 x 1.30 )x ### =35.80 x 1.00 x 1.15 x 1.00 = 41.17 2.00 x ( 19.80 x 1.30 )x ### =
TOTAL = 52.89 TOTAL =28.00 x 0.90 x 1.15 x 1.00 = 28.98 2.00 x ( 12.00 x 1.30 )x ### =23.10 x 0.90 x 1.15 x 1.00 = 23.91 2.00 x ( 15.10 x 1.30 )x ### =
TOTAL = 88.90 TOTAL =27.80 x 1.00 x 1.15 x 1.00 = 31.97 5.00 x ( 11.80 x 1.30 )x ### =49.50 x 1.00 x 1.15 x 1.00 = 56.93 5.00 x ( 9.50 x 1.30 )x ### =32.00 x 1.00 x 1.15 x 2.00 = 73.60 32.00 x ( 10.40 + 0.36 )x ### =
LATERAL TRUSS = 283.20 RAFTERS =2.00 x 7.00 x 9.90 x 2.00 = 277.20 2.00 x ( 4.00 x 6.54 )x ### =2.00 x 2.00 x 1.50 x 1.00 = 6.00 2.00 x ( 2.00 x 2.68 )x ### =2.00 x 1.00 x 9.90 x 1.00 = 19.80
PERIMETER (m)98.80
107.60
78.20194.40
14.70
26.4022.4019.20
507.84154.56220.80132.48586.02
6996.402254.004742.406222.171424.803107.752903.00
211.432956.452710.93
245.522004.431923.41
81.01497.12353.28143.84
VERTICAL BARS1617.20
348.40676.00592.80
393.1251.4870.4631.2039.26
138.4576.7061.75
119.99
115.33104.61
10.71
CONCRETE (Class A)Cement 9 bags/cu.m.Gravel 1 cu.m./cu.m.Sand 0.5 cu.m./cu.m.THK 0.1 m.
DRB 6 m./6 m.lngth.Hor. Splice 1.15 m./m.Ver. Splice 1.3 m./m.
TIE WIRES 0.00566 kg./pc.CHB 13 pcs/sq.m.
Cement, 6" THK 0.0982 bags/pc.Sand, 6" THK 0.0053 cu.m./pc.Cement, 4" THK 0.0411 bags/pc.Sand, 4" THK 0.0022 cu.m./pc.
PLASTER (Class A)THK 0.012 m.Cement 0.098 bags/sq.m.Sand 0.01 cu.m./sq.m.
PLYWOOD2.88 sq.m./pc.
FORMSfor columns 29.67 bd.ft./sq.m.
SCAFFOLDINGSfor ver. Columns 7 bd.ft./m.for hor. Columns 21 bd.ft./m.for bracing 11.7 bd.ft./m.for ver. Beams 6 bd.ft./m.for slab 9.1 bd.ft./sq.m.
NAILSper bd. Ft. 0.0186 pcs/bd.ft.4# 63 pcs/kg.
ROOF (32"x6")width 0.71 m.length 1.5 m.ridge & flashing 2.1 m./pc.wall flashing 0.65217 pcs./m.
HARDIFLEX 2.88 sq.m./pc.TILES
floor tiles 0.09 sq.m./pc.T&B tiles 0.04 sq.m./pc.tile trim 9 pcs./m.
ELECTRICALRSC 10 m./lgth.Flexible 50 m./rollTHW Wire 150 m./roll
PIPES 10 m./pc.PAINT
neutralizer 25 sq.m./gal.primer 20 sq.m./gal.latex 22 sq.m./gal.thinner 10 gal./gal
ROUND BARS 6 m./lgth.