cost estimates 2s bldg

72
Project : PROPOSED TWO (2) STOREY BUILDING (DUPLEX TYPE) Location : Lapasan, Cagayan de Oro City Owner : Mr. Rolando G. Gironella, III Item no. Description % Wt. I GENERAL REQUIREMENTS 1 Mobilization 2 Temporary Facilities item I sub-total 0.59 II EARTHWORKS 1 Site Clearing and Grubbing 2 Structural Excavation 3 Structural Backfill and Compaction 4 Earthfill and Compaction 5 Gravel Bedding item II sub-total 2.23 III CONCRETE WORKS 1 Footings 2 Wall Footings 3 Columns 4 Beams 5 Stairs 6 Interior Slab item III sub-total 7.71 IV REINFORCING STEEL BARS 1 16mmØ Deformed Bars Gr.40 2 10mmØ Deformed Bars Gr.33 3 20mmØ Deformed Bars Gr.40 4 12mmØ Deformed Bars Gr.33 5 Tie Wires item IV sub-total 12.31 V MASONRY WORKS 1 6" Machine Made CHB with Reinforcements 2 4" Machine Made CHB with Reinforcements 3 Plastering 4 Plain Cement Finish item V sub-total 16.26 VI FORMWORKS and SCAFFOLDINGS 1 Ordinary Plywood and Coco Lumber item VI sub-total 5.70 VII STRUCTURAL STEEL WORKS 1 1.5mm THK x 2" x 6" C-Purlins 2 1.5mm THK x 2" x 3" C-Purlins

Upload: alok-sarkar

Post on 22-Dec-2015

16 views

Category:

Documents


1 download

DESCRIPTION

Building Estimate

TRANSCRIPT

Page 1: Cost Estimates 2S BLDG

Project : PROPOSED TWO (2) STOREY BUILDING (DUPLEX TYPE)

Location : Lapasan, Cagayan de Oro City

Owner : Mr. Rolando G. Gironella, III

Item no. Description % Wt.

I GENERAL REQUIREMENTS1 Mobilization2 Temporary Facilities

item I sub-total 0.59

II EARTHWORKS1 Site Clearing and Grubbing2 Structural Excavation3 Structural Backfill and Compaction4 Earthfill and Compaction5 Gravel Bedding

item II sub-total 2.23

III CONCRETE WORKS1 Footings2 Wall Footings3 Columns4 Beams5 Stairs 6 Interior Slab

item III sub-total 7.71

IV REINFORCING STEEL BARS1 16mmØ Deformed Bars Gr.402 10mmØ Deformed Bars Gr.33 3 20mmØ Deformed Bars Gr.404 12mmØ Deformed Bars Gr.335 Tie Wires

item IV sub-total 12.31

V MASONRY WORKS1 6" Machine Made CHB with Reinforcements2 4" Machine Made CHB with Reinforcements3 Plastering4 Plain Cement Finish

item V sub-total 16.26

VI FORMWORKS and SCAFFOLDINGS1 Ordinary Plywood and Coco Lumber

item VI sub-total 5.70

VII STRUCTURAL STEEL WORKS1 1.5mm THK x 2" x 6" C-Purlins2 1.5mm THK x 2" x 3" C-Purlins

item VII sub-total 2.49

VIII THERMAL and MOISTURE PROTECTION1 Roofing and Accessories

Page 2: Cost Estimates 2S BLDG

( Ordinary Corr. Ga.22 Long Span Pre-painted )2 Insulation

( 10mm Thk. Double Foil Foam )3 Interior Slab Vapor Barrier

item VIII sub-total 4.31

IX DOORS and WINDOWS1 Doors and Windows

item IX sub-total 4.43

X CEILING WORKS1 4.5mm Thk. Hardiflex Board on Lite Metal Frames ( Two Sides )

item X sub-total 7.39

XI TILE WORKS1 300mm x 300mm Ceramic Floor Tiles2 200mm x 200mm Ceramic Floor Tiles3 200mm x 200mm Ceramic Wall Tiles ( 1.55m Ht. )

item XI sub-total 5.74

XII METAL WORKS1 Railings and Balustrades

item XV sub-total 2.25

XIII PAINTING WORKS1 Masonry Walls2 Ceiling

item XII sub-total 8.62

XIV ELECTRICAL WORKS1 Rough-in2 Fixtures

item XIII sub-total 9.48

XV PLUMBING WORKS1 Potable Water2 Waste Water Line & Storm Drainage3 Fixtures4 Septic Tank5 Catch Basin6 Grease Trap

item XIV sub-total 10.50

TOTAL AMOUNT 100.00

Page 3: Cost Estimates 2S BLDG

Unit Quantity Unit Price Amout ( P ) ( P )

lot 1.00 21,269.04 21,269.04 lot 1.00 21,560.76 21,560.76

42,829.80

sq.m. 294.00 14.12 4,150.38 cu.m. 77.90 1,277.74 99,529.56 cu.m. 8.03 1,325.01 10,634.52 cu.m. 44.10 665.10 29,331.12 cu.m. 15.00 1,150.08 17,251.26

160,896.84

cu.m. 9.94 4,947.14 49,154.82 cu.m. 8.56 4,947.14 42,352.50 cu.m. 16.50 4,947.14 81,627.87 cu.m. 12.76 4,947.14 63,113.19 cu.m. 0.96 4,947.14 4,749.26 cu.m. 63.60 4,947.14 314,638.34

555,635.97

lgth. 377.00 604.72 227,979.18 lgth. 1,716.00 183.81 315,426.23 lgth. 532.00 604.72 321,710.67 lgth. 156.00 60.18 9,388.08 kgs. 216.00 60.18 12,998.88

887,503.04

sq.m. 73.38 1,273.81 93,472.39 sq.m. 1,459.35 471.43 687,984.49 sq.m. 2,918.71 98.42 287,264.64 sq.m. 2,860.12 36.24 103,640.16

1,172,361.68

sq.m. 355.90 1,154.94 411,040.11 411,040.11

lgths. 23.00 2,631.76 60,530.57 lgths. 48.00 2,482.00 119,135.80

179,666.37

sq.m. 266.96 952.89 254,379.84

Page 4: Cost Estimates 2S BLDG

sq.m. 266.96 127.56 34,051.68

sq.m. 294.00 75.73 22,263.54 310,695.06

lot 1.00 319,300.80 319,300.80 319,300.80

sq.m. 533.91 997.94 532,813.32 532,813.32

sq.m. 375.80 775.91 291,587.40 sq.m. 25.20 1,046.17 26,363.48 sq.m. 117.18 818.46 95,906.93

413,857.81

li.m. 87.93 1,844.56 162,196.32 162,196.32

sq.m. 2,136.54 229.60 490,540.44 sq.m. 533.91 245.18 130,902.72

621,443.16

lot 1.00 431,817.20 431,817.20 lot 1.00 252,046.08 252,046.08

683,863.28

lot 1.00 112,935.42 112,935.42 lot 1.00 158,350.92 158,350.92 lot 1.00 321,687.60 321,687.60

units 2.00 45,605.00 91,210.00 units 8.00 6,087.25 48,698.00 units 4.00 6,062.00 24,248.00

757,129.94

7,211,233.51

Page 5: Cost Estimates 2S BLDG

Poject : PROPOSED TWO (2) STOREY BUILDING (DUPLEX TYPE)Locatio : Lapasan, Cagayan de Oro CityOwner : Mr. Rolando G. Gironella, III

I. GENERAL REQUIREME1) Mobilization and Demobilization

Quantity : 1.00 lotUnit Cost : P 21,269.04 '/lot

Equipment :1 '- Service Vehicle '- 4.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 8 '- Laborer '- 4.00 days @ P 220.00 '/day =

P

DIRECT COST :Equipment : P 4,000.00 Manpower : P 12,040.00

P 16,040.00

INDIRECT COST :15% OCM ': P 2,406.00 15% CP ': P 2,406.00 2% Tax ': P 417.04

P 5,229.04

TOTAL COST ': P 21,269.04 Unit Cost ': P 21,269.04 '/lot

2) Temporary FacilitiesQuantity : 1.00 lotUnit Cost : P 21,560.76 '/lot

Materials : 1.00 lot Miscellaenous Materials '@ P ### '/lot = P

P

Equipment :1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 4 '- Laborer '- 2.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 10,000.00 Equipment : P 2,000.00 Manpower : P 4,260.00

Page 6: Cost Estimates 2S BLDG

P 16,260.00

INDIRECT COST :15% OCM ': P 2,439.00 15% CP ': P 2,439.00 2% Tax ': P 422.76

P 5,300.76

TOTAL COST ': P 21,560.76 Unit Cost ': P 21,560.76 '/lot

II. EARTHWORKS1) Site Clearing and Grubbing

Quantity : 294.00 sq.m.Unit Cost : P 14.12 '/sq.m.

Equipment :1 '- Service Vehicle '- 1.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 1.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 1.00 days @ P 400.00 '/day = 1 '- Service Driver '- 1.00 days @ P 250.00 '/day = 4 '- Laborer '- 1.00 days @ P 220.00 '/day =

P

DIRECT COST :Equipment : P 1,000.00 Manpower : P 2,130.00

P 3,130.00

INDIRECT COST :15% OCM ': P 469.50 15% CP ': P 469.50 2% Tax ': P 81.38

P 1,020.38

TOTAL COST ': P 4,150.38 Unit Cost ': P 14.12 '/sq.

2) Structural ExcavationQuantity : 77.90 cu.m.Unit Cost : P 1,277.74 '/cu.m.

Equipment :1 '- Backho '- 6.00 days @ P 8,500.00 '/day = 1 '- Service Vehicle '- 6.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 1 '- Service Driver '- 6.00 days @ P 250.00 '/day = 8 '- Laborer '- 6.00 days @ P 220.00 '/day =

P

DIRECT COST :

Page 7: Cost Estimates 2S BLDG

Equipment : P 57,000.00 Manpower : P 18,060.00

P 75,060.00

INDIRECT COST :15% OCM ': P 11,259.00 15% CP ': P 11,259.00 2% Tax ': P 1,951.56

P 24,469.56

TOTAL COST ': P 99,529.56 Unit Cost ': P 1,277.74 '/cu.

3) Structural Backfill and CompactionQuantity : 8.03 cu.m.Unit Cost : P 1,325.01 '/cu.m.

Equipment :1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 8 '- Laborer '- 2.00 days @ P 220.00 '/day =

P

DIRECT COST :Equipment : P 2,000.00 Manpower : P 6,020.00

P 8,020.00

INDIRECT COST :15% OCM ': P 1,203.00 15% CP ': P 1,203.00 2% Tax ': P 208.52

P 2,614.52

TOTAL COST ': P 10,634.52 Unit Cost ': P 1,325.01 '/cu.

4) Earthfill and CompactionQuantity : 44.10 cu.m.Unit Cost : P 665.10 '/cu.m.

Equipment :1 '- Compactor '- 4.00 day @ P 2,400.00 '/day = 1 '- Service Vehicle '- 4.00 day @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 4.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 day @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 4 '- Laborer '- 4.00 day @ P 220.00 '/day =

P

DIRECT COST :

Page 8: Cost Estimates 2S BLDG

Equipment : P 13,600.00 Manpower : P 8,520.00

P 22,120.00

INDIRECT COST :15% OCM ': P 3,318.00 15% CP ': P 3,318.00 2% Tax ': P 575.12

P 7,211.12

TOTAL COST ': P 29,331.12 Unit Cost ': P 665.10 '/cu.

5) Gravel BeddingQuantity : 15.00 cu.m.Unit Cost : P 1,150.08 '/cu.m.

Materials : 15.00 cu.m. Gravel '@ P 450.00 '/cu.m.=

PEquipment :

1 '- Service Vehicle '- 2.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 2.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 day @ P 400.00 '/day = 1 '- Service Driver '- 2.00 day @ P 250.00 '/day = 4 '- Laborer '- 2.00 day @ P 220.00 '/day =

P

DIRECT COST :Materials : P 6,750.00 Equipment : P 2,000.00 Manpower : P 4,260.00

P 13,010.00

INDIRECT COST :15% OCM ': P 1,951.50 15% CP ': P 1,951.50 2% Tax ': P 338.26

P 4,241.26

TOTAL COST ': P 17,251.26 Unit Cost ': P 1,150.08 '/cu.

III. CONCRETE WORK1) Footings

Quantity : 9.94 cu.m.Unit Cost : P 4,947.14 '/cu.m.Materials : 10.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 5.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 90.00 bags Portland Cement '@ P 220.00 '/bag =

PEquipment :

1 '- Bagger Mixer '- 2.00 days @ P 750.00 '/day =

Page 9: Cost Estimates 2S BLDG

1 '- Concrete Vibrator '- 2.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 8 '- Laborer '- 2.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 26,550.00 Equipment : P 4,500.00 Manpower : P 6,020.00

P 37,070.00

INDIRECT COST :15% OCM ': P 5,560.50 15% CP ': P 5,560.50 2% Tax ': P 963.82

P 12,084.82

TOTAL COST ': P 49,154.82 Unit Cost ': P 4,947.14 '/cu.

2) Wall FootingsQuantity : 8.56 cu.m.Unit Cost : P 4,947.14 '/cu.m.

3) ColumnsQuantity : 16.50 cu.m.Unit Cost : P 4,947.14 '/cu.m.

4) BeamsQuantity : 12.76 cu.m.Unit Cost : P 4,947.14 '/cu.m.

5) StairsQuantity : 0.96 cu.m.Unit Cost : P 4,947.14 '/cu.m.

6) Interior SlabQuantity : 63.60 cu.m.Unit Cost : P 4,947.14 '/cu.m.

IV. REINFORCING STEEL BA1) 16mmØ Deformed Bars Gr.40

Quantity : 377.00 lgth.Unit Cost : P 604.72 '/lgth.

Materials : 377.00 lgths. 16mmØ x 6m Deformed Bars Gr.40 '@ P 240.00 '/lgth.= 5.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =

PEquipment :

1 '- Bar Cutter '- 15.00 days @ P 350.00 '/day =

Page 10: Cost Estimates 2S BLDG

1 '- Cut-off Machine '- 15.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 15.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 15.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 15.00 days @ P 400.00 '/day = 1 '- Service Driver '- 15.00 days @ P 250.00 '/day = 4 '- Steelmen '- 15.00 days @ P 300.00 '/day = 4 '- Laborer '- 15.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 94,230.00 Equipment : P 27,750.00 Manpower : P 49,950.00

P 171,930.00

INDIRECT COST :15% OCM ': P 25,789.50 15% CP ': P 25,789.50 2% Tax ': P 4,470.18

P 56,049.18

TOTAL COST ': P 227,979.18 Unit Cost ': P 604.72 '/lgth

2) 10mmØ Deformed Bars Gr.33 Quantity : 1,716.00 lgth.Unit Cost : P 183.81 '/lgth.

Materials : 1,716.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 1.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =

PEquipment :

1 '- Bar Cutter '- 10.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 10.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 10.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 10.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 10.00 days @ P 400.00 '/day = 1 '- Service Driver '- 10.00 days @ P 250.00 '/day = 4 '- Steelmen '- 10.00 days @ P 300.00 '/day = 4 '- Laborer '- 10.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 186,078.00 Equipment : P 18,500.00 Manpower : P 33,300.00

P 237,878.00

INDIRECT COST :15% OCM ': P 35,681.70 15% CP ': P 35,681.70 2% Tax ': P 6,184.83

Page 11: Cost Estimates 2S BLDG

P 77,548.23

TOTAL COST ': P 315,426.23 Unit Cost ': P 183.81 '/lgth

3) 20mmØ Deformed Bars Gr.40Quantity : 532.00 lgth.Unit Cost : P 604.72 '/lgth.

Materials : 532.00 lgths. 20mmØ x 6m Deformed Bars Gr.40 '@ P 320.00 '/lgth.= 10.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =

PEquipment :

1 '- Bar Cutter '- 12.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 12.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 12.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 1 '- Service Driver '- 12.00 days @ P 250.00 '/day = 4 '- Steelmen '- 12.00 days @ P 300.00 '/day = 4 '- Laborer '- 12.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 177,740.00 Equipment : P 22,200.00 Manpower : P 39,960.00

P 239,900.00

INDIRECT COST :15% OCM ': P 35,985.00 15% CP ': P 35,985.00 2% Tax ': P 6,237.40

P 78,207.40

TOTAL COST ': P 318,107.40 Unit Cost ': P 597.95 '/lgth

4) 12mmØ Deformed Bars Gr.33Quantity : 156.00 lgth.Unit Cost : P 60.18 '/lgth.

Materials : 156.00 lgths. 12mmØ x 6m Deformed Bars Gr.33 '@ P 166.00 '/lgth.= 2.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. =

PEquipment :

1 '- Bar Cutter '- 3.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 3.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 3.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 3.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 3.00 days @ P 400.00 '/day =

Page 12: Cost Estimates 2S BLDG

1 '- Service Driver '- 3.00 days @ P 250.00 '/day = 4 '- Steelmen '- 3.00 days @ P 300.00 '/day = 4 '- Laborer '- 3.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 27,396.00 Equipment : P 5,550.00 Manpower : P 9,990.00

P 42,936.00

INDIRECT COST :15% OCM ': P 6,440.40 15% CP ': P 6,440.40 2% Tax ': P 1,116.34

P 13,997.14

TOTAL COST ': P 56,933.14 Unit Cost ': P 364.96 '/lgth

5) Tie WiresQuantity : 216.00 kg.Unit Cost : P 60.18 '/kg.

Materials : 216.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =

PEquipment :

1 '- Bar Cutter '- 4.00 days @ P 350.00 '/day = 1 '- Cut-off Machine '- 4.00 days @ P 500.00 '/day = 1 '- Service Vehicle '- 4.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 1 '- Steelmen '- 4.00 days @ P 300.00 '/day = 4 '- Laborer '- 4.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 17,280.00 Equipment : P 7,400.00 Manpower : P 9,720.00

P 34,400.00

INDIRECT COST :15% OCM ': P 5,160.00 15% CP ': P 5,160.00 2% Tax ': P 894.40

P 11,214.40

TOTAL COST ': P 45,614.40 Unit Cost ': P 211.18 '/kg.

V. MASONRY WORKS

Page 13: Cost Estimates 2S BLDG

1) 6" Machine Made CHB with ReinforcementsQuantity : 73.38 sq.m.Unit Cost : P 1,273.81 '/sq.m.

Materials : 954.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 238.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth. = 6.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 94.00 bags Portland Cement '@ P 220.00 '/bag = 21.00 kgs. #16 Tie Wire '@ P 60.00 '/kg. =

PEquipment :

1 '- Bar Cutter '- 2.00 days @ P 350.00 '/day = 1 '- Bagger Mixer '- 2.00 days @ P 750.00 '/day = 1 '- Service Vehicle '- 2.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 2.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 2.00 days @ P 400.00 '/day = 1 '- Service Driver '- 2.00 days @ P 250.00 '/day = 2 '- Masons '- 2.00 days @ P 280.00 '/day = 2 '- Laborer '- 2.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 61,792.00 Equipment : P 4,200.00 Manpower : P 4,500.00

P 70,492.00

INDIRECT COST :15% OCM ': P 10,573.80 15% CP ': P 10,573.80 2% Tax ': P 1,832.79

P 22,980.39

TOTAL COST ': P 93,472.39 Unit Cost ': P 1,273.81 '/sq.

2) 4" Machine Made CHB with ReinforcementsQuantity : 1,459.35 sq.m.Unit Cost : P 471.43 '/sq.m.

Materials : 18,972.00 pcs. 4" Machine Made CHB '@ P 6.50 '/pc. = 1,038.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth. = 42.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 780.00 bags Portland Cement '@ P 220.00 '/bag = 59.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =

PEquipment :

1 '- Bar Cutter '- 12.00 days @ P 350.00 '/day = 1 '- Bagger Mixer '- 12.00 days @ P 750.00 '/day = 1 '- Service Vehicle '- 12.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 12.00 days @ P 600.00 '/day =

Page 14: Cost Estimates 2S BLDG

1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 1 '- Service Driver '- 12.00 days @ P 250.00 '/day = 8 '- Masons '- 12.00 days @ P 280.00 '/day = 8 '- Laborer '- 12.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 430,642.00 Equipment : P 25,200.00 Manpower : P 63,000.00

P 518,842.00

INDIRECT COST :15% OCM ': P 77,826.30 15% CP ': P 77,826.30 2% Tax ': P 13,489.89

P 169,142.49

TOTAL COST ': P 687,984.49 Unit Cost ': P 471.43 '/sq.

3) PlasteringQuantity : 2,918.71 sq.m.Unit Cost : P 98.42 '/sq.m.Materials : 30.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 287.00 bags Portland Cement '@ P 220.00 '/bag =

PEquipment :

1 '- Bagger Mixer '- 20.00 days @ P 750.00 '/day = 1 '- Service Vehicle '- 20.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 20.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 20.00 days @ P 400.00 '/day = 1 '- Service Driver '- 20.00 days @ P 250.00 '/day = 8 '- Masons '- 20.00 days @ P 280.00 '/day = 8 '- Laborer '- 20.00 days @ P 220.00 '/day =

PDIRECT COST :

Materials : P 76,640.00 Equipment : P 35,000.00 Manpower : P 105,000.00

P 216,640.00

INDIRECT COST :15% OCM ': P 32,496.00 15% CP ': P 32,496.00 2% Tax ': P 5,632.64

P 70,624.64

TOTAL COST ': P 287,264.64 Unit Cost ': P 98.42 '/sq.

4) Plain Cement FinishQuantity : 2,860.12 sq.m.Unit Cost : P 36.24 '/sq.m.

Page 15: Cost Estimates 2S BLDG

Materials : 128.00 bags Portland Cement '@ P 220.00 '/bag =

PEquipment :

1 '- Service Vehicle '- 8.00 days @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 8.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 8.00 days @ P 400.00 '/day = 1 '- Service Driver '- 8.00 days @ P 250.00 '/day = 8 '- Masons '- 8.00 days @ P 280.00 '/day = 8 '- Laborer '- 8.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 28,160.00 Equipment : P 8,000.00 Manpower : P 42,000.00

P 78,160.00

INDIRECT COST :15% OCM ': P 11,724.00 15% CP ': P 11,724.00 2% Tax ': P 2,032.16

P 25,480.16

TOTAL COST ': P 103,640.16 Unit Cost ': P 36.24 '/sq.

VI. FORMWORKS and SCAFFOLDINGS1) Ordinary Plywood and Coco Lumber

Quantity : 355.90 sq.m.Unit Cost : P 1,154.94 '/sq.m.

Materials : 9,082.00 bd. ft. 2" x 2" Coco Lumber '@ P 12.00 '/bd.ft. 2,853.00 bd. ft. 2" x 3" Coco Lumber '@ P 12.00 '/bd.ft. 124.00 shts. 6mm Thk. Ordinary Plywood '@ P 240.00 '/sht. = 5.00 box 4" Common Wire Nails '@ P 1,200.00 '/box = 5.00 box 1" Common Wire Nails '@ P 1,201.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 20.00 days @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 20.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 20.00 days @ P 400.00 '/day = 1 '- Service Driver '- 20.00 days @ P 250.00 '/day = 8 '- Carpenters '- 20.00 days @ P 280.00 '/day = 8 '- Laborer '- 20.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 184,985.00 Equipment : P 20,000.00

Page 16: Cost Estimates 2S BLDG

Manpower : P 105,000.00 P 309,985.00

INDIRECT COST :15% OCM ': P 46,497.75 15% CP ': P 46,497.75 2% Tax ': P 8,059.61

P 101,055.11

TOTAL COST ': P 411,040.11 Unit Cost ': P 1,154.94 '/sq.

VII. STRUCTURAL STEEL WO1) 1.5mm THK x 2" x 6" C-Purlins

Quantity : 23.00 lgths.Unit Cost : P 2,631.76 '/lgth.

Materials : 23.00 lgths. 1.5mm thk x 2" x 6" C-Purlins '@ P 633.00 '/lgth.= 5.00 kg Fuji Welding Electrode E6012 '@ P 78.00 '/kg = 1.00 tanks Acytelene '@ P 1,650.00 '/tank = 1.00 tanks Industrial Oxygen '@ P 880.00 '/tank = 1.00 gals. Epoxy Zinchromate Primer '@ P 750.00 '/gal. = 1.00 gals. Epoxy Top Coat Paint '@ P 780.00 '/gal. = 1.00 gals. Epoxy Reducer '@ P 490.00 '/gal. = 1.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. = 3.00 pcs. 4" Paint Brush '@ P 70.00 '/pc. = 3.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. =

PEquipment :

2 '- Welding Machines '- 3.00 days @ P 500.00 '/day = 1 '- Gas Cutter '- 3.00 days @ P 500.00 '/day = 1 '- Cut-off Machine '- 3.00 days @ P 500.00 '/day = 2 '- Grinder '- 3.00 days @ P 350.00 '/day = 1 '- Delivery Truck '- 1.00 trips @ P 500.00 '/trip = 1 '- Service Vehicle '- 3.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 3.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 3.00 days @ P 400.00 '/day = 1 '- Service Driver '- 3.00 days @ P 250.00 '/day = 6 '- Welder '- 3.00 days @ P 320.00 '/day = 6 '- Laborer '- 3.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 20,579.00 Equipment : P 11,600.00 Manpower : P 13,470.00

P 45,649.00

INDIRECT COST :15% OCM ': P 6,847.35 15% CP ': P 6,847.35 2% Tax ': P 1,186.87

P 14,881.57

Page 17: Cost Estimates 2S BLDG

TOTAL COST ': P 60,530.57 Unit Cost ': P 2,631.76 '/lgths.

2) 1.5mm THK x 2" x 3" C-PurlinsQuantity : 48.00 lgth.Unit Cost : P 2,482.00 '/lgth.

Materials : 48.00 lgths. 1.5mm thk x 2" x 3" C-Purlins '@ P 552.00 '/lgth.= 2.00 boxes Fuji Welding Electrode E6012 '@ P 1,700.00 '/box = 1.00 tanks Acytelene '@ P 1,650.00 '/tank = 1.00 tanks Industrial Oxygen '@ P 880.00 '/tank = 3.00 gals. Epoxy Zinchromate Primer '@ P 750.00 '/gal. = 3.00 gals. Epoxy Top Coat Paint '@ P 780.00 '/gal. = 3.00 gals. Epoxy Reducer '@ P 490.00 '/gal. = 2.00 pcs. 14"Ø Cut-off Blade '@ P 750.00 '/pc. = 2.00 pcs. 4" Paint Brush '@ P 70.00 '/pc. = 2.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. =

PEquipment :

2 '- Welding Machines '- 6.00 days @ P 500.00 '/day = 1 '- Gas Cutter '- 6.00 days @ P 500.00 '/day = 1 '- Cut-off Machine '- 6.00 days @ P 500.00 '/day = 2 '- Grinder '- 6.00 days @ P 350.00 '/day = 1 '- Delivery Truck '- 1.00 trips @ P 500.00 '/trip = 1 '- Service Vehicle '- 6.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 1 '- Service Driver '- 6.00 days @ P 250.00 '/day = 6 '- Welder '- 6.00 days @ P 320.00 '/day = 6 '- Laborer '- 6.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 40,206.00 Equipment : P 22,700.00 Manpower : P 26,940.00

P 89,846.00

INDIRECT COST :15% OCM ': P 13,476.90 15% CP ': P 13,476.90 2% Tax ': P 2,336.00

P 29,289.80

TOTAL COST ': P 119,135.80 Unit Cost ': P 2,482.00 '/lgth

VIII. THERMAL and MOISTURE PROTECTION1) Roofing and Accessories

Quantity : 266.96 sq.m.Unit Cost : P 952.89 '/sq.m.

Page 18: Cost Estimates 2S BLDG

Materials : 251.00 li.m. Ga.22 x 6' Ord. Corr. Pre-painted Roofing '@ P 350.00 '/li.m. = 5.00 pcs. Ga.22 x 24" Pre-painted Ridge Roll '@ P 940.00 '/pc. = 19.00 pcs. Ga.22 x 36" Pre-painted Spanish Gutter '@ P 1,395.00 '/pc. = 22.00 pcs. Ga.22 x 36" Pre-painted Side Flashing '@ P 1,395.00 '/pc. = 18.00 pcs. Ga.22 x 24" Pre-painted Wall Flashing '@ P 940.00 '/pc. = 1,004.00 pcs. 2½" Metal Tekscrew '@ P 3.00 '/pc. = 1,004.00 pcs. ⅛"Ø x ⅜" Blind Rivets '@ P 0.75 '/pc. = 4.00 tubes Silicon Sealant '@ P 175.00 '/tube = 1.00 qrt. Touch-up Paint '@ P 120.00 '/qrt. = 2.00 pcs. Paint Brush ½" '@ P 25.00 '/pc. = 2.00 pcs. ⅛"Ø Steel Drill Bit '@ P 50.00 '/pc. =

PEquipment :

2 '- Hand Drill '- 4.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 4.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 1 '- Service Driver '- 4.00 days @ P 250.00 '/day = 4 '- Roofing Installer '- 4.00 days @ P 320.00 '/day = 4 '- Laborer '- 4.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 171,400.00 Equipment : P 6,800.00 Manpower : P 13,640.00

P 191,840.00

INDIRECT COST :15% OCM ': P 28,776.00 15% CP ': P 28,776.00 2% Tax ': P 4,987.84

P 62,539.84

TOTAL COST ': P 254,379.84 Unit Cost ': P 952.89 '/sq.

2) InsulationQuantity : 266.96 sq.m.Unit Cost : P 127.56 '/sq.m.

Materials : 4.00 rolls 10mm x 1m x 50m Double Foil Foam '@ P 5,100.00 '/roll = 5.00 rolls 3" Packaging Tape '@ P 50.00 '/roll = 1.00 roll #16 Tie Wire '@ P 1,700.00 '/roll =

PEquipment :

1 '- Service Vehicle '- 1.00 days @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 1.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 1.00 days @ P 400.00 '/day = 1 '- Service Driver '- 1.00 days @ P 250.00 '/day = 2 '- Roofing Installer '- 1.00 days @ P 320.00 '/day =

Page 19: Cost Estimates 2S BLDG

2 '- Laborer '- 1.00 days @ P 220.00 '/day = P

DIRECT COST :Materials : P 22,350.00 Equipment : P 1,000.00 Manpower : P 2,330.00

P 25,680.00

INDIRECT COST :15% OCM ': P 3,852.00 15% CP ': P 3,852.00 2% Tax ': P 667.68

P 8,371.68

TOTAL COST ': P 34,051.68 Unit Cost ': P 127.56 '/sq.

3) Interior Slab Vapor BarrierQuantity : 294.00 sq.m.Unit Cost : P 75.73 '/sq.m.

Materials : 4.00 rolls 1.2m x 50m Polyprophelene '@ P 3,500.00 '/roll = 2.00 rolls 3" Packaging Tape '@ P 50.00 '/roll =

PEquipment :

1 '- Service Vehicle '- 1.00 days @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 1.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 1.00 days @ P 400.00 '/day = 1 '- Service Driver '- 1.00 days @ P 250.00 '/day = 2 '- Laborer '- 1.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 14,100.00 Equipment : P 1,000.00 Manpower : P 1,690.00

P 16,790.00

INDIRECT COST :15% OCM ': P 2,518.50 15% CP ': P 2,518.50 2% Tax ': P 436.54

P 5,473.54

TOTAL COST ': P 22,263.54 Unit Cost ': P 75.73 '/sq.

IX. DOORS and WINDOWS1) Doors and Windows

Quantity : 1.00 lotUnit Cost : P 319,300.80 '/lotMaterials : 4.00 sets 0.90m x 2.10m Panel Door '@ P 4,000.00 '/set =

Page 20: Cost Estimates 2S BLDG

18.00 sets 0.70m x 2.10m Hollow Core Door '@ P 2,000.00 '/set = 4.00 sets 0.80m x 2.10m Panel Door '@ P 2,500.00 '/set = 14.00 sets 0.60m x 2.10m PVC Door '@ P 1,800.00 '/set = 2.00 sets 0.60m x 2.10m Panel Door '@ P 2,900.00 '/set = 18.00 sets 2-Panel at 0.8m x 1.2m Casement Window '@ P 5,200.00 '/set =

8.00 sets 0.80m x 1.20m Casement Window '@ P 2,600.00 '/set = 2.00 sets 0.80m x 0.90m Casement Window '@ P 2,300.00 '/set =

PEquipment :

1 '- Hand Drill '- 8.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 8.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 8.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 8.00 days @ P 400.00 '/day = 1 '- Service Driver '- 8.00 days @ P 250.00 '/day = 2 '- Installer '- 8.00 days @ P 280.00 '/day = 2 '- Helper '- 8.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 212,000.00 Equipment : P 10,800.00 Manpower : P 18,000.00

P 240,800.00

INDIRECT COST :15% OCM ': P 36,120.00 15% CP ': P 36,120.00 2% Tax ': P 6,260.80

P 78,500.80

TOTAL COST ': P 319,300.80 Unit Cost ': P 319,300.80 '/sq.

X. CEILING WORK1) 4.5mm Thk. Hardiflex Board on Lite Metal Frames ( Two Sides )

Quantity : 533.91 sq.m.Unit Cost : P 997.94 '/sq.m.

Materials : 186.00 shts. 4.5mm thk. x 1.2m x 2.4m Hardiflex Board '@ P 425.00 '/sht . = 1,900.00 pcs. 1" Hardiflex Screw '@ P 1.50 '/pc. = 534.00 sq.m. Lite Metal Frames '@ P 480.00 '/sq.m.=

PEquipment :

3 '- Hand Drill '- 12.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 12.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 1 '- Service Driver '- 12.00 days @ P 250.00 '/day = 4 '- Installer '- 12.00 days @ P 280.00 '/day = 4 '- Helper '- 12.00 days @ P 220.00 '/day =

Page 21: Cost Estimates 2S BLDG

P

DIRECT COST :Materials : P 338,220.00 Equipment : P 24,600.00 Manpower : P 39,000.00

P 401,820.00

INDIRECT COST :15% OCM ': P 60,273.00 15% CP ': P 60,273.00 2% Tax ': P 10,447.32

P 130,993.32

TOTAL COST ': P 532,813.32 Unit Cost ': P 997.94 '/sq.

XI. TILE WORKS1) 300mm x 300mm Ceramic Floor Tiles

Quantity : 375.80 sq.m.Unit Cost : P 775.91 '/sq.m.

Materials : 4,176.00 pcs. 300mm x 300mm Ceramic Floor Tiles '@ P 25.00 '/pc. = 4.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 37.00 bags Portland Cement '@ P 220.00 '/bag = 20.00 kgs. ABC Grout '@ P 28.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 20.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 20.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 20.00 day @ P 400.00 '/day = 1 '- Service Driver '- 20.00 day @ P 250.00 '/day = 6 '- Mason '- 20.00 day @ P 280.00 '/day = 6 '- Helper '- 20.00 day @ P 220.00 '/day =

P

DIRECT COST :Materials : P 114,900.00 Equipment : P 20,000.00 Manpower : P 85,000.00

P 219,900.00

INDIRECT COST :15% OCM ': P 32,985.00 15% CP ': P 32,985.00 2% Tax ': P 5,717.40

P 71,687.40

TOTAL COST ': P 291,587.40 Unit Cost ': P 775.91 '/sq.

2) 200mm x 200mm Ceramic Floor TilesQuantity : 25.20 sq.m.

Page 22: Cost Estimates 2S BLDG

Unit Cost : P 1,046.17 '/sq.m.

Materials : 630.00 pcs. 200mm x 200mm Ceramic Floor Tiles '@ P 12.00 '/pc. = 1.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 3.00 bags Portland Cement '@ P 220.00 '/bag = 3.00 kgs. ABC Grout '@ P 28.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 6.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 6.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 day @ P 400.00 '/day = 1 '- Service Driver '- 6.00 day @ P 250.00 '/day = 6 '- Mason '- 6.00 day @ P 280.00 '/day = 6 '- Helper '- 6.00 day @ P 220.00 '/day =

P

DIRECT COST :Materials : P 8,754.00 Equipment : P 6,000.00 Manpower : P 25,500.00

P 40,254.00

INDIRECT COST :15% OCM ': P 6,038.10 15% CP ': P 6,038.10 2% Tax ': P 1,046.60

P 13,122.80

TOTAL COST ': P 53,376.80 Unit Cost ': P 51.02 '/sq.

3) 200mm x 200mm Ceramic Wall TilesQuantity : 117.18 sq.m.Unit Cost : P 818.46 '/sq.m.

Materials : 2,930.00 pcs. 200mm x 200mm Ceramic Wall Tiles '@ P 12.00 '/pc. = 2.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 12.00 bags Portland Cement '@ P 220.00 '/bag = 49.00 pcs. Tile Trim '@ P 40.00 '/pc. = 6.00 kgs. ABC Grout '@ P 28.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 6.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 6.00 day @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 day @ P 400.00 '/day = 1 '- Service Driver '- 6.00 day @ P 250.00 '/day = 6 '- Mason '- 6.00 day @ P 280.00 '/day = 6 '- Helper '- 6.00 day @ P 220.00 '/day =

P

Page 23: Cost Estimates 2S BLDG

DIRECT COST :Materials : P 40,828.00 Equipment : P 6,000.00 Manpower : P 25,500.00

P 72,328.00

INDIRECT COST :15% OCM ': P 10,849.20 15% CP ': P 10,849.20 2% Tax ': P 1,880.53

P 23,578.93

TOTAL COST ': P 95,906.93 Unit Cost ': P 818.46 '/sq.

XII. METAL WORKS1) Railings and Balustrades

Quantity : 87.93 li.m.Unit Cost : P 1,844.56 '/li.m.

Materials : 15.00 length 2"Ø G.I. Pipe Sch.20 '@ P 2,600.00 '/lgth. = 16.00 length 1½"Ø G.I. Pipe Sch.20 '@ P 1,400.00 '/lgth. = 28.00 length ¼" x 2" x 6m Flat Bar '@ P 410.00 '/lgth. = 2.00 box Welding Electrode E6012 '@ P 1,700.00 '/box = 2.00 gals. Epoxy Zinchromate Primer '@ P 750.00 '/gal. = 2.00 gals. Epoxy Top Coat '@ P 780.00 '/gal. = 2.00 gals. Epoxy Reducer '@ P 490.00 '/gal. = 6.00 pcs. Paint Brush '@ P 40.00 '/pc. = 3.00 pcs. 14"Ø Cut-off Wheel Blade '@ P 550.00 '/pc. = 6.00 pcs. 4"Ø Grinding Disc '@ P 75.00 '/pc. =

PEquipment :

2 '- Welding Machine '- 6.00 days @ P 500.00 '/day = 1 '- Cut-off Machine '- 6.00 days @ P 500.00 '/day = 2 '- Grinder '- 6.00 days @ P 350.00 '/day = 1 '- Service Vehicle '- 6.00 days @ P 1,000.00 '/day =

PManpower :

1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 1 '- Service Driver '- 6.00 days @ P 250.00 '/day = 4 '- Welder '- 6.00 days @ P 320.00 '/day = 4 '- Laborer '- 6.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 82,660.00 Equipment : P 19,200.00 Manpower : P 20,460.00

P 122,320.00

INDIRECT COST :15% OCM ': P 18,348.00 15% CP ': P 18,348.00 2% Tax ': P 3,180.32

Page 24: Cost Estimates 2S BLDG

P 39,876.32

TOTAL COST ': P 162,196.32 Unit Cost ': P 1,844.56 '/li.m

XIII. PAINTING WORKS1) Masonry Walls

Quantity : 2,136.54 sq.m.Unit Cost : P 229.60 '/sq.m.

Materials : 86.00 gals. Concrete Neutralizer '@ P 360.00 '/gal. = 107.00 gals. Concrete Primer '@ P 520.00 '/gal. = 10.00 gals. Concrete Putty '@ P 500.00 '/gal. = 292.00 gals. Semi-gloss Latex '@ P 480.00 '/gal. = 29.20 gals. Thinner '@ P 350.00 '/gal. = 12.00 pcs. 9" Paint Roller '@ P 90.00 '/pc. = 12.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. = 100.00 pcs. #120 sand Paper '@ P 14.00 '/pc. = 30.00 rolls Masking Tape 1" '@ P 28.00 '/roll = 8.00 pcs. Paint Tray '@ P 70.00 '/pc. =

PManpower :

1 '- Project Engineer '- 30.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 30.00 days @ P 400.00 '/day = 8 '- Painter '- 30.00 days @ P 280.00 '/day = 4 '- Laborer '- 30.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 246,340.00 Manpower : P 123,600.00

P 369,940.00

INDIRECT COST :15% OCM ': P 55,491.00 15% CP ': P 55,491.00 2% Tax ': P 9,618.44

P 120,600.44

TOTAL COST ': P 490,540.44 Unit Cost ': P 229.60 '/sq.

2) CeilingQuantity : 533.91 sq.m.Unit Cost : P 245.18 '/sq.m.

Materials : 27.00 gal. Concrete Primer '@ P 520.00 '/gal. = 1.00 gals. Concrete Putty '@ P 500.00 '/gal. = 73.00 gals. Flat Latex '@ P 480.00 '/gal. = 2.00 pcs. 9" Paint Roller '@ P 90.00 '/pc. = 2.00 pcs. 2" Paint Brush '@ P 40.00 '/pc. = 20.00 pcs. #120 sand Paper '@ P 14.00 '/pc. =

PManpower :

Page 25: Cost Estimates 2S BLDG

1 '- Project Engineer '- 15.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 15.00 days @ P 400.00 '/day = 8 '- Painter '- 15.00 days @ P 280.00 '/day =

P

DIRECT COST :Materials : P 50,120.00 Manpower : P 48,600.00

P 98,720.00

INDIRECT COST :15% OCM ': P 14,808.00 15% CP ': P 14,808.00 2% Tax ': P 2,566.72

P 32,182.72

TOTAL COST ': P 130,902.72 Unit Cost ': P 245.18 '/sq.

XIV.ELECTRICAL WOR1) Rough-in

Quantity : 1.00 lotUnit Cost : P 431,817.20 '/lot

Materials : 4.00 units 1 Main; 8-Branches Panel Boards '@ P 4,000.00 '/set = 10.00 units 1 Main; 4-Branches Panel Boards '@ P 2,800.00 '/set = 6.00 rolls 3.5 sq.mm. THW Wire '@ P 2,400.00 '/set = 4.00 rolls 5.5 sq.mm. THW Wire '@ P 3,200.00 '/set = 20.00 rolls Electrical Tape '@ P 30.00 '/roll = 18.00 pcs. 4" x 4" Junction Box '@ P 38.00 '/pc. = 144.00 pcs. 4" x 2" Utility Box '@ P 25.00 '/pc. = 14.00 sets 1"Ø Entrance Cap Assembly '@ P 3,000.00 '/lgth. = 28.00 lengths RSC Pipe 1"Ø '@ P 1,400.00 '/lgth. = 6.00 rolls Flexible Pipe ½"Ø '@ P 700.00 '/lgth. = 140.00 meters THW Wire No.6 '@ P 250.00 '/roll = 42.00 meters Bare Wire No.8 '@ P 85.00 '/roll =

PEquipment :

1 '- Service Vehicle '- 40.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 40.00 days @ P 600.00 '/day = 1 '- Electrical Engineer '- 40.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 40.00 days @ P 400.00 '/day = 1 '- Electrician '- 40.00 days @ P 320.00 '/day = 1 '- Helper '- 40.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 200,054.00 Equipment : P 40,000.00 Manpower : P 85,600.00

P 325,654.00

INDIRECT COST :

Page 26: Cost Estimates 2S BLDG

15% OCM ': P 48,848.10 15% CP ': P 48,848.10 2% Tax ': P 8,467.00

P 106,163.20

TOTAL COST ': P 431,817.20 Unit Cost ': P 431,817.20 '/lot

2) FixturesQuantity : 1.00 lotUnit Cost : P 252,046.08 '/lot

Materials : 14.00 sets Electric Power Meter '@ P 3,000.00 '/set = 14.00 sets 100A Circuit Breaker '@ P 1,200.00 '/set = 72.00 sets 20A Circuit Breaker '@ P 750.00 '/set = 112.00 sets Light Outlet w/ Incandescent Lamp '@ P 280.00 '/set = 18.00 sets A.C.U. Outlet '@ P 400.00 '/set = 4.00 sets Range Outlet '@ P 400.00 '/set = 14.00 sets 1 Gang Switch '@ P 90.00 '/set = 22.00 sets 2 Gang Switch '@ P 180.00 '/set = 18.00 sets 3 Gang Switch '@ P 220.00 '/set = 68.00 sets 2 Gang Convenience Outlet '@ P 180.00 '/set =

PEquipment :

1 '- Service Vehicle '- 5.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 5.00 days @ P 600.00 '/day = 1 '- Electrical Engineer '- 5.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 5.00 days @ P 400.00 '/day = 1 '- Electrician '- 5.00 days @ P 320.00 '/day = 1 '- Helper '- 5.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 174,380.00 Equipment : P 5,000.00 Manpower : P 10,700.00

P 190,080.00

INDIRECT COST :15% OCM ': P 28,512.00 15% CP ': P 28,512.00 2% Tax ': P 4,942.08

P 61,966.08

TOTAL COST ': P 252,046.08 Unit Cost ': P 252,046.08 '/lot

XV. PLUMBING WORKS1) Potable Water

Quantity : 1.00 lotUnit Cost : P 112,935.42 '/lot

Materials :

Page 27: Cost Estimates 2S BLDG

44.00 pcs. ½"Ø PVC Eslon Blue '@ P 560.00 '/lgth. = 30.00 pcs. ½"Ø PVC Tee '@ P 25.00 '/set = 22.00 pcs. ½"Ø PVC Elbow '@ P 25.00 '/pc. = 18.00 pcs. ½"Ø PVC Elbow w/ Thread '@ P 25.00 '/pc. = 24.00 pcs. ½"Ø PVC Elbow Coupling '@ P 25.00 '/pc. = 18.00 pcs. ½"Ø Male Adaptor '@ P 30.00 '/pc. = 6.00 pcs. ½"Ø Gate Valve '@ P 480.00 '/set = 6.00 pcs. ½"Ø Check Valve '@ P 620.00 '/set = 6.00 pcs. Water Meter '@ P 2,500.00 '/set = 8.00 cans Solvent Cement '@ P 180.00 '/can = 8.00 rolls Teflon Tape '@ P 35.00 '/roll =

PEquipment :

1 '- Service Vehicle '- 12.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 2 '- Plumbers '- 12.00 days @ P 320.00 '/day = 1 '- Helper '- 12.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 50,850.00 Equipment : P 12,000.00 Manpower : P 22,320.00

P 85,170.00

INDIRECT COST :15% OCM ': P 12,775.50 15% CP ': P 12,775.50 2% Tax ': P 2,214.42

P 27,765.42

TOTAL COST ': P 112,935.42 Unit Cost ': P 112,935.42 '/lot

2) Waste Water Line & Storm DrainageQuantity : 1.00 lotUnit Cost : P 158,350.92 '/lot

Materials : 42.00 pcs. 4"Ø PVC Sanitary Pipe '@ P 450.00 '/pc. = 28.00 pcs. 3"Ø PVC Sanitary Pipe '@ P 420.00 '/pc. = 42.00 pcs. 2"Ø PVC Sanitary Pipe '@ P 400.00 '/pc. = 24.00 pcs. 4"Ø x 4"Ø PVC Wye '@ P 65.00 '/pc. = 14.00 pcs. 4"Ø x 3"Ø PVC Wye '@ P 65.00 '/pc. = 14.00 pcs. 4"Ø x 2"Ø PVC Wye '@ P 65.00 '/pc. = 20.00 pcs. 4"Ø x 90° PVC Elbow '@ P 65.00 '/pc. = 10.00 pcs. 4"Ø x 45° PVC Elbow '@ P 65.00 '/pc. = 24.00 pcs. 3"Ø x 90° PVC Elbow '@ P 55.00 '/pc. = 18.00 pcs. 2"Ø x 90° PVC Elbow '@ P 55.00 '/pc. = 14.00 pcs. 2"Ø x 45° PVC Elbow '@ P 55.00 '/pc. = 22.00 pcs. 2"Ø PVC Tee '@ P 55.00 '/pc. = 14.00 pcs. 3"Ø P-Trap '@ P 90.00 '/pc. = 18.00 pcs. 4"Ø PVC Clean-out '@ P 65.00 '/pc. = 6.00 pcs. 4"Ø PVC Tee '@ P 65.00 '/pc. =

Page 28: Cost Estimates 2S BLDG

52.00 pcs. 6"Ø RC Pipe '@ P 450.00 '/pc. = 10.00 cans Solvent Cement '@ P 180.00 '/can =

PEquipment :

1 '- Service Vehicle '- 12.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 12.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 12.00 days @ P 400.00 '/day = 2 '- Plumbers '- 12.00 days @ P 320.00 '/day = 1 '- Helper '- 12.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 85,100.00 Equipment : P 12,000.00 Manpower : P 22,320.00

P 119,420.00

INDIRECT COST :15% OCM ': P 17,913.00 15% CP ': P 17,913.00 2% Tax ': P 3,104.92

P 38,930.92

TOTAL COST ': P 158,350.92 Unit Cost ': P 158,350.92 '/lot

3) FixturesQuantity : 1.00 lotUnit Cost : P 321,687.60 '/lot

Materials : 14.00 set '@ P 6,000.00 '/set =

4.00 set '@ P 4,500.00 '/set =

10.00 set Lavatory Counter Type '@ P 6,000.00 '/set = 4.00 set '@ P 4,500.00 '/set =

4.00 set Laundry Sink w/ P-Trap '@ P 3,000.00 '/set = 14.00 pcs. 4"Ø Floor Drain '@ P 200.00 '/pc. = 8.00 pcs. 3"Ø Basket Strainer (Doom Type) '@ P 200.00 '/pc. =

PEquipment :

1 '- Service Vehicle '- 15.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 15.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 15.00 days @ P 400.00 '/day = 2 '- Plumbers '- 15.00 days @ P 320.00 '/day = 2 '- Helper '- 15.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 196,400.00

Water Closet w/ Flexible Hose & Angle Valve

Lavatory (Wall Hang) w/ Flex. Hose, Angle Valve, Faucet & P-Trap

Kitchen Sink w/ Flex. Hose, Angle Valve, Faucet & P-Trap

Page 29: Cost Estimates 2S BLDG

Equipment : P 15,000.00 Manpower : P 31,200.00

P 242,600.00

INDIRECT COST :15% OCM ': P 36,390.00 15% CP ': P 36,390.00 2% Tax ': P 6,307.60

P 79,087.60

TOTAL COST ': P 321,687.60 Unit Cost ': P 321,687.60 '/lot

4) Septic TankQuantity : 2.00 unitsUnit Cost : P 45,605.00 '/unit

Materials : 5.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 6.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 100.00 bags Portland Cement '@ P 220.00 '/bag = 493.00 length 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 618.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 45.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 6.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 6.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 6.00 days @ P 400.00 '/day = 2 '- Plumbers/Masons '- 6.00 days @ P 320.00 '/day = 4 '- Helper '- 6.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 91,210.00 Equipment : P 6,000.00 Manpower : P 15,120.00

P 112,330.00

INDIRECT COST :15% OCM ': P 16,849.50 15% CP ': P 16,849.50 2% Tax ': P 2,920.58

P 36,619.58

TOTAL COST ': P 148,949.58 Unit Cost ': P 74,474.79 '/unit

4) Catch BasinQuantity : 8.00 unitsUnit Cost : P 6,087.25 '/unit

Materials : 1.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 2.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.=

Page 30: Cost Estimates 2S BLDG

28.00 bags Portland Cement '@ P 220.00 '/bag = 335.00 length 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 204.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 32.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 8.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 8.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 8.00 days @ P 400.00 '/day = 2 '- Plumbers/Masons '- 8.00 days @ P 320.00 '/day = 4 '- Helper '- 8.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 48,698.00 Equipment : P 8,000.00 Manpower : P 20,160.00

P 76,858.00

INDIRECT COST :15% OCM ': P 11,528.70 15% CP ': P 11,528.70 2% Tax ': P 1,998.31

P 25,055.71

TOTAL COST ': P 101,913.71 Unit Cost ': P 12,739.21 '/unit

5) Grease TrapQuantity : 4.00 unitsUnit Cost : P 6,062.00 '/unit

Materials : 1.00 cu.m. ¾"Ø Gravel '@ P 450.00 '/cu.m.= 3.00 cu.m. Washed Sand '@ P 450.00 '/cu.m.= 39.00 bags Portland Cement '@ P 220.00 '/bag = 83.00 lgths. 10mmØ x 6m Deformed Bars Gr.33 '@ P 108.00 '/lgth.= 362.00 pcs. 6" Machine Made CHB '@ P 12.00 '/pc. = 7.00 kgs. #16 Tie Wire '@ P 80.00 '/kg. =

PEquipment :

1 '- Service Vehicle '- 4.00 day @ P 1,000.00 '/day = P

Manpower :1 '- Project Engineer '- 4.00 days @ P 600.00 '/day = 1 '- Construction Foreman '- 4.00 days @ P 400.00 '/day = 2 '- Plumbers/Masons '- 4.00 days @ P 320.00 '/day = 4 '- Helper '- 4.00 days @ P 220.00 '/day =

P

DIRECT COST :Materials : P 24,248.00 Equipment : P 4,000.00 Manpower : P 10,080.00

P 38,328.00

Page 31: Cost Estimates 2S BLDG

INDIRECT COST :15% OCM ': P 5,749.20 15% CP ': P 5,749.20 2% Tax ': P 996.53

P 12,494.93

TOTAL COST ': P 50,822.93 Unit Cost ': P 12,705.73 '/unit

Page 32: Cost Estimates 2S BLDG

4,000.00 4,000.00

2,400.00 1,600.00 1,000.00 7,040.00 12,040.00

10,000.00 10,000.00

2,000.00 2,000.00

1,200.00 800.00 500.00 1,760.00 4,260.00

Page 33: Cost Estimates 2S BLDG

1,000.00 1,000.00

600.00 400.00 250.00 880.00 2,130.00

51,000.00 6,000.00 57,000.00

3,600.00 2,400.00 1,500.00 10,560.00 18,060.00

Page 34: Cost Estimates 2S BLDG

2,000.00 2,000.00

1,200.00 800.00 500.00 3,520.00 6,020.00

9,600.00 4,000.00 13,600.00

2,400.00 1,600.00 1,000.00 3,520.00 8,520.00

Page 35: Cost Estimates 2S BLDG

6,750.00 6,750.00

2,000.00 2,000.00

1,200.00 800.00 500.00 1,760.00 4,260.00

4,500.00 2,250.00 19,800.00 26,550.00

1,500.00

Page 36: Cost Estimates 2S BLDG

1,000.00 2,000.00 4,500.00

1,200.00 800.00 500.00 3,520.00 6,020.00

90,480.00 3,750.00 94,230.00

5,250.00

Page 37: Cost Estimates 2S BLDG

7,500.00 15,000.00 27,750.00

9,000.00 6,000.00 3,750.00 18,000.00 13,200.00 49,950.00

185,328.00 750.00 186,078.00

3,500.00 5,000.00 10,000.00 18,500.00

6,000.00 4,000.00 2,500.00 12,000.00 8,800.00 33,300.00

Page 38: Cost Estimates 2S BLDG

170,240.00 7,500.00 177,740.00

4,200.00 6,000.00 12,000.00 22,200.00

7,200.00 4,800.00 3,000.00 14,400.00 10,560.00 39,960.00

25,896.00 1,500.00 27,396.00

1,050.00 1,500.00 3,000.00 5,550.00

1,800.00 1,200.00

Page 39: Cost Estimates 2S BLDG

750.00 3,600.00 2,640.00 9,990.00

17,280.00 17,280.00

1,400.00 2,000.00 4,000.00 7,400.00

2,400.00 1,600.00 1,000.00 1,200.00 3,520.00 9,720.00

Page 40: Cost Estimates 2S BLDG

11,448.00 25,704.00 2,700.00 20,680.00 1,260.00 61,792.00

700.00 1,500.00 2,000.00 4,200.00

1,200.00 800.00 500.00 1,120.00 880.00 4,500.00

123,318.00 112,104.00 18,900.00 171,600.00 4,720.00 430,642.00

4,200.00 9,000.00 12,000.00 25,200.00

7,200.00

Page 41: Cost Estimates 2S BLDG

4,800.00 3,000.00 26,880.00 21,120.00 63,000.00

13,500.00 63,140.00 76,640.00

15,000.00 20,000.00 35,000.00

12,000.00 8,000.00 5,000.00 44,800.00 35,200.00 105,000.00

Page 42: Cost Estimates 2S BLDG

28,160.00 28,160.00

8,000.00 8,000.00

4,800.00 3,200.00 2,000.00 17,920.00 14,080.00 42,000.00

108,984.00 34,236.00 29,760.00 6,000.00 6,005.00 184,985.00

20,000.00 20,000.00

12,000.00 8,000.00 5,000.00 44,800.00 35,200.00 105,000.00

Page 43: Cost Estimates 2S BLDG

14,559.00 390.00 1,650.00 880.00 750.00 780.00 490.00 750.00 210.00 120.00 20,579.00

3,000.00 1,500.00 1,500.00 2,100.00 500.00 3,000.00 11,600.00

1,800.00 1,200.00 750.00 5,760.00 3,960.00 13,470.00

Page 44: Cost Estimates 2S BLDG

26,496.00 3,400.00 1,650.00 880.00 2,250.00 2,340.00 1,470.00 1,500.00 140.00 80.00 40,206.00

6,000.00 3,000.00 3,000.00 4,200.00 500.00 6,000.00 22,700.00

3,600.00 2,400.00 1,500.00 11,520.00 7,920.00 26,940.00

Page 45: Cost Estimates 2S BLDG

87,850.00 4,700.00 26,505.00 30,690.00 16,920.00 3,012.00 753.00 700.00 120.00 50.00 100.00 171,400.00

2,800.00 4,000.00 6,800.00

2,400.00 1,600.00 1,000.00 5,120.00 3,520.00 13,640.00

20,400.00 250.00 1,700.00 22,350.00

1,000.00 1,000.00

600.00 400.00 250.00 640.00

Page 46: Cost Estimates 2S BLDG

440.00 2,330.00

14,000.00 100.00 14,100.00

1,000.00 1,000.00

600.00 400.00 250.00 440.00 1,690.00

16,000.00

Page 47: Cost Estimates 2S BLDG

36,000.00 10,000.00 25,200.00 5,800.00 93,600.00

20,800.00 4,600.00 212,000.00

2,800.00 8,000.00 10,800.00

4,800.00 3,200.00 2,000.00 4,480.00 3,520.00 18,000.00

79,050.00 2,850.00 256,320.00 338,220.00

12,600.00 12,000.00 24,600.00

7,200.00 4,800.00 3,000.00 13,440.00 10,560.00

Page 48: Cost Estimates 2S BLDG

39,000.00

104,400.00 1,800.00 8,140.00 560.00 114,900.00

20,000.00 20,000.00

12,000.00 8,000.00 5,000.00 33,600.00 26,400.00 85,000.00

Page 49: Cost Estimates 2S BLDG

7,560.00 450.00 660.00 84.00 8,754.00

6,000.00 6,000.00

3,600.00 2,400.00 1,500.00 10,080.00 7,920.00 25,500.00

35,160.00 900.00 2,640.00 1,960.00 168.00 40,828.00

6,000.00 6,000.00

3,600.00 2,400.00 1,500.00 10,080.00 7,920.00 25,500.00

Page 50: Cost Estimates 2S BLDG

39,000.00 22,400.00 11,480.00 3,400.00 1,500.00 1,560.00 980.00 240.00 1,650.00 450.00 82,660.00

6,000.00 3,000.00 4,200.00 6,000.00 19,200.00

3,600.00 2,400.00 1,500.00 7,680.00 5,280.00 20,460.00

Page 51: Cost Estimates 2S BLDG

30,960.00 55,640.00 5,000.00 140,160.00 10,220.00 1,080.00 480.00 1,400.00 840.00 560.00 246,340.00

18,000.00 12,000.00 67,200.00 26,400.00 123,600.00

14,040.00 500.00 35,040.00 180.00 80.00 280.00 50,120.00

Page 52: Cost Estimates 2S BLDG

9,000.00 6,000.00 33,600.00 48,600.00

16,000.00 28,000.00 14,400.00 12,800.00 600.00 684.00 3,600.00 42,000.00 39,200.00 4,200.00 35,000.00 3,570.00 200,054.00

40,000.00 40,000.00

24,000.00 24,000.00 16,000.00 12,800.00 8,800.00 85,600.00

Page 53: Cost Estimates 2S BLDG

42,000.00 16,800.00 54,000.00 31,360.00 7,200.00 1,600.00 1,260.00 3,960.00 3,960.00 12,240.00 174,380.00

5,000.00 5,000.00

3,000.00 3,000.00 2,000.00 1,600.00 1,100.00 10,700.00

Page 54: Cost Estimates 2S BLDG

24,640.00 750.00 550.00 450.00 600.00 540.00 2,880.00 3,720.00 15,000.00 1,440.00 280.00 50,850.00

12,000.00 12,000.00

7,200.00 4,800.00 7,680.00 2,640.00 22,320.00

18,900.00 11,760.00 16,800.00 1,560.00 910.00 910.00 1,300.00 650.00 1,320.00 990.00 770.00 1,210.00 1,260.00 1,170.00 390.00

Page 55: Cost Estimates 2S BLDG

23,400.00 1,800.00 85,100.00

12,000.00 12,000.00

7,200.00 4,800.00 7,680.00 2,640.00 22,320.00

84,000.00

18,000.00

60,000.00 18,000.00

12,000.00 2,800.00 1,600.00 196,400.00

15,000.00 15,000.00

9,000.00 6,000.00 9,600.00 6,600.00 31,200.00

Page 56: Cost Estimates 2S BLDG

2,250.00 2,700.00 22,000.00 53,244.00 7,416.00 3,600.00 91,210.00

6,000.00 6,000.00

3,600.00 2,400.00 3,840.00 5,280.00 15,120.00

450.00 900.00

Page 57: Cost Estimates 2S BLDG

6,160.00 36,180.00 2,448.00 2,560.00 48,698.00

8,000.00 8,000.00

4,800.00 3,200.00 5,120.00 7,040.00 20,160.00

450.00 1,350.00 8,580.00 8,964.00 4,344.00 560.00 24,248.00

4,000.00 4,000.00

2,400.00 1,600.00 2,560.00 3,520.00 10,080.00

Page 58: Cost Estimates 2S BLDG

QTY B (m) H (m) THK (m) AREA (sq.m)LOT 2.00 10.00 14.70 2.00 x 10.00 x14.70 = 294.00

COLUMN FOOTINGSCF1 2.00 1.20 1.20 0.30CF2 2.00 1.20 2.40 0.30CF3 3.00 1.20 1.20 0.30

WF1 1.00 30.00 23.80 0.80

WALL TOTAL = 1459.35WF1 1.00 0.35 122.30 0.20 1.00 x 122.30 x 0.60 = 73.38WL1 1.00 122.30 3.00 1.00 x 122.30 x 3.00 = 366.90WL2 2.00 8.00 11.55 3.00 2.00 x 78.20 x 3.00 = 469.20WL3 1.00 57.50 39.70 2.70 1.00 x 194.40 x 2.70 = 524.88PARAPET 1.00 6.85 2.99 2.00 x 1.00 x 6.85 x 2.99 = 40.92

FIREWALLCF1 3.00 1.20 1.20 0.30CF2 1.00 1.20 2.40 0.30WL1 1.00 14.70 0.80WL3 1.00 13.70 2.70 1.00 x 13.70 x 2.70 = 36.99PARAPET 1.00 6.85 2.99 1.00 x 6.85 x 2.99 = 20.46C1ug 3.00 0.20 0.30 1.00C2ug 2.00 0.20 0.30 1.00C1 6.00 0.20 0.30 6.00C2 4.00 0.20 0.30 6.00B1 1.00 0.20 0.30 12.30

COLUMNSC1ug 2.00 0.20 0.30 1.00C2ug 4.00 0.20 0.30 1.00C3ug 3.00 0.20 0.30 1.00C1 2.00 0.20 0.30 6.00C2 8.00 0.20 0.30 6.00C3 6.00 0.20 0.30 6.00

FLOORINGEARTH 1.00 10.00 14.70 0.15GRAVEL 1.00 10.00 14.70 0.05SLAB1 1.00 10.00 14.70 0.10SLAB2 1.00 10.00 11.40 0.15

SVs & CBsSV 1.00 3.00 1.50 1.80 2.00 x 2.00 x 3.70 x 2.90 = 42.92CB 6.00 0.70 0.70 0.70 2.00 x 8.00 x 0.70 x 0.70 = 7.84GT 2.00 0.60 0.60 1.45 2.00 x 4.00 x 0.60 x 0.60 = 2.88

BEAMSB1 1.00 0.20 0.30 69.45B2 2.00 0.20 0.30 4.95B3 2.00 0.15 0.30 3.00B4 1.00 0.15 0.30 7.55CB1 2.00 0.20 0.30 2.95CB2 5.00 0.20 0.30 0.95

STAIRS 8.00 0.30 0.20 1.00

Page 59: Cost Estimates 2S BLDG

BEDBARS QTY B (m) QTY H (m)FOOTINGS

CF1 8.00 1.20 8.00 1.20CF2 16.00 1.20 8.00 2.40CF3 8.00 1.20 8.00 1.20

WF1 407.67 0.35 3.00 122.30SLAB

SLAB1 49.00 10.00 33.33 14.70SLAB2 91.20 10.00 80.00 11.40

WALLWF1 9.00 122.30 203.83 0.60WL1-2 5.00 200.50 501.25 3.00WL3 4.50 208.10 520.25 2.70PARAPET 4.98 13.70 34.25 2.99

SVCONCRETE 98.67 14.80 77.33 11.60MASONRY 3.00 26.40 66.00 1.80

CBCONCRETE 74.67 11.20 74.67 11.20MASONRY 1.17 22.40 56.00 0.70

GTCONCRETE 32.00 4.80 32.00 4.80MASONRY 2.42 19.20 48.00 1.45

DRBs QTY B (m) QTY H (m)COLUMNS

C1 402.00 1.00 4.00 67.00C2 780.00 1.00 4.00 130.00C3 684.00 1.00 4.00 114.00

BEAMSB1 163.20 1.00 2.00 151.20B2 35.80 1.00 2.00 19.80

BEAMSB3 28.00 0.90 2.00 12.00B4 23.10 0.90 2.00 15.10

CANTILIVERED BEAMSCB1 27.80 1.00 5.00 11.80CB2 49.50 1.00 5.00 9.50

STAIRS 32.00 1.00 32.00 8.00

TIE WIRES QTY QTY QTY 38101.27FOOTINGS

CF1 8.00 8.00 7.00 448.00CF2 16.00 8.00 5.00 640.00CF3 8.00 8.00 6.00 384.00

WF1 407.67 3.00 1.00 1223.00COLUMNS

C1 402.00 6.00 1.00 2412.00C2 780.00 6.00 1.00 4680.00C3 684.00 6.00 1.00 4104.00

BEAMSB1 163.20 10.00 1.00 1632.00B2 35.80 6.00 1.00 214.80B3 28.00 8.00 1.00 224.00B4 23.10 8.00 1.00 184.80

SLAB

Page 60: Cost Estimates 2S BLDG

SLAB1 49.00 33.33 2.00 3266.67SLAB2 91.20 80.00 2.00 14592.00

STAIRS 32.00 32.00 2.00 4096.00WALL 10376.78

WF1 9.00 203.83 1.00 3669.00WL1-2 5.00 501.25 1.00 5012.50WL3 4.50 520.25 1.00 4682.25PARAPET 4.98 34.25 2.00 682.03

SV 7828.22CONCRETE 98.67 77.33 1.00 7630.22MASONRY 3.00 66.00 1.00 198.00

CB 5640.44CONCRETE 74.67 74.67 1.00 5575.11 TOTAL = 1024.99MASONRY 1.17 56.00 1.00 65.33 1.00 x 311.00 / 2.00 = 155.50

GT 1140.00 1.00 x 192.30 / 2.00 = 96.15CONCRETE 32.00 32.00 1.00 1024.00 1.00 x 8.00 / 2.00 = 4.00MASONRY 2.42 48.00 1.00 116.00 10.00 x 26.10 / 2.00 = 130.50

122.30 x 0.60 / 2.00 = 36.69FORMS 200.50 x 3.00 / 2.00 = 300.75

COLUMNS 1.00 311.00 208.10 x 2.70 / 2.00 = 280.94BEAMS 1.00 192.30 13.70 x 2.99 / 2.00 = 20.46STAIRS 1.00 8.00SLAB 10.00 26.10WALLS 122.30 0.60

200.50 3.00208.10 2.70

13.70 2.99TOTAL = 375.80

ROOF 2.00 x 1.00 x 10.00 x 9.65 = 193.00MAIN 2.00 6.23 9.90 2.00 2.00 x 1.00 x 10.00 x10.40 = 208.00STAIRS 1.00 2.55 1.50 0.82 2.00 x 7.00 x 1.20 x 1.50 = 25.20RIDGE 1.00 9.90 2.00 x 7.00 x 5.40 x 1.55 = 117.18

TILES1F 1.00 10.00 9.652F 1.00 10.00 10.40T&B 7.00 1.20 1.50WALLS 7.00 5.40 1.55

DOORS & WINDOWS TOTAL = 212.52D1 4.00 0.90 2.10 0.90 x 2.10 x 4.00 = 7.56D2 18.00 0.70 2.10 0.70 x 2.10 x18.00 = 26.46D3 4.00 0.80 2.10 0.80 x 2.10 x 4.00 = 6.72D4 14.00 0.60 2.10 0.60 x 2.10 x14.00 = 17.64D5 2.00 1.00 2.10 1.00 x 2.10 x 2.00 = 4.20W1 18.00 1.60 1.20 1.60 x 1.20 x18.00 = 34.56W2 8.00 0.80 1.20 0.80 x 1.20 x 8.00 = 7.68W3 2.00 0.80 0.90 0.80 x 0.90 x 2.00 = 1.44

RAILINGS 87.93STAIRS 11.00 0.36 7.93FRONT 2.00 20.00 80.00BALUST. 77.67 0.60 93.20

Page 61: Cost Estimates 2S BLDG

VOLUME (cu.m) PERIMETER (m)2.00 x ( 10.00 + 14.70 )x ### =

TOTAL = 9.942.00 x 2.00 x 1.20 x 1.20 x 0.30 = 1.732.00 x 2.00 x 1.20 x 2.40 x 0.30 = 3.462.00 x 3.00 x 1.20 x 1.20 x 0.30 = 2.59

2.00 x 1.00 x 0.15 x 107.60 x 0.80 = 25.82 2.00 x ( 30.00 + 23.80 )x ### =

1.00 x 0.35 x 122.30 x 0.20 = 8.56

2.00 x ( 8.00 + 11.55 )x ### =2.00 x ( 57.50 + 39.70 )x ### =

HEIGHT3.00 x 1.20 x 1.20 x 0.30 = 1.301.00 x 1.20 x 2.40 x 0.30 = 0.861.00 x 0.15 x 14.70 x 0.80 = 1.76 ( 0.00 + 14.70 )x ### =

3.00 x 0.20 x 0.30 x 1.00 = 0.18 3.002.00 x 0.20 x 0.30 x 1.00 = 0.12 2.006.00 x 0.20 x 0.30 x 6.00 = 2.16 36.004.00 x 0.20 x 0.30 x 6.00 = 1.44 24.001.00 x 0.20 x 0.30 x12.30 = 0.74 12.30

TOTAL = 16.50 HEIGHT2.00 x 2.00 x 0.20 x 0.30 x 1.00 = 0.24 4.002.00 x 4.00 x 0.20 x 0.30 x 1.00 = 0.48 8.002.00 x 3.00 x 0.20 x 0.30 x 1.00 = 0.36 6.002.00 x 2.00 x 0.20 x 0.30 x 6.00 = 1.44 24.002.00 x 8.00 x 0.20 x 0.30 x 6.00 = 5.76 96.002.00 x 6.00 x 0.20 x 0.30 x 6.00 = 4.32 72.00

TOTAL = 63.602.00 x 1.00 x10.00 x 14.70 x 0.15 = 44.102.00 x 1.00 x10.00 x 14.70 x 0.05 = 14.702.00 x 1.00 x10.00 x 14.70 x 0.10 = 29.402.00 x 1.00 x10.00 x 11.40 x 0.15 = 34.20

TOTAL = 22.402.00 x 1.00 x 3.00 x 1.50 x 1.80 = 16.20 2.00 x ( 7.40 + 5.80 )x ### =2.00 x 6.00 x 0.70 x 0.70 x 0.70 = 4.12 2.00 x ( 1.40 + 1.40 )x ### =2.00 x 2.00 x 0.60 x 0.60 x 1.45 = 2.09 2.00 x ( 1.20 + 1.20 )x ### =

TOTAL = 12.76 HEIGHT2.00 x 1.00 x 0.20 x 0.30 x69.45 = 8.33 138.902.00 x 2.00 x 0.20 x 0.30 x 4.95 = 1.19 19.802.00 x 2.00 x 0.15 x 0.30 x 3.00 = 0.54 12.002.00 x 1.00 x 0.15 x 0.30 x 7.55 = 0.68 15.102.00 x 2.00 x 0.20 x 0.30 x 2.95 = 0.71 11.802.00 x 5.00 x 0.20 x 0.30 x 0.95 = 0.57 9.50

2.00 x 8.00 x 0.30 x 0.20 x 1.00 = 0.96 8.00

Page 62: Cost Estimates 2S BLDG

TOTAL =7.00 x ( 9.60 + 9.60 )x ### =5.00 x ( 19.20 + 19.20 )x ### =6.00 x ( 9.60 + 9.60 )x ### =1.00 x ( 142.68 +366.90 )x ### =

TOTAL =2.00 x ( 490.00 +490.00 )x ### =2.00 x ( 912.00 +912.00 )x ### =

TOTAL =### x 1.15 +122.30 x ### =### x 1.15 + ### x ### =

936.45 x 1.15 + ### x ### =68.20 x 1.15 +102.30 x ### =

TOTAL =( ### +897.07 )x ### =

79.20 x 1.15 +118.80 x ### =TOTAL =

( 836.27 +836.27 )x ### =26.13 x 1.15 + 39.20 x ### =

TOTAL =( 153.60 +153.60 )x ### =

46.40 x 1.15 + 69.60 x ### =

LATERAL TIES VERTICAL BARSTOTAL = 2145.90 TOTAL =

402.00 x 1.00 x 1.15 x 1.00 = 462.30 4.00 x ( 67.00 x 1.30 )x ### =780.00 x 1.00 x 1.15 x 1.00 = 897.00 4.00 x ( 130.00 x 1.30 )x ### =684.00 x 1.00 x 1.15 x 1.00 = 786.60 4.00 x ( 114.00 x 1.30 )x ### =

163.20 x 1.00 x 1.15 x 1.00 = 187.68 2.00 x ( 151.20 x 1.30 )x ### =35.80 x 1.00 x 1.15 x 1.00 = 41.17 2.00 x ( 19.80 x 1.30 )x ### =

TOTAL = 52.89 TOTAL =28.00 x 0.90 x 1.15 x 1.00 = 28.98 2.00 x ( 12.00 x 1.30 )x ### =23.10 x 0.90 x 1.15 x 1.00 = 23.91 2.00 x ( 15.10 x 1.30 )x ### =

TOTAL = 88.90 TOTAL =27.80 x 1.00 x 1.15 x 1.00 = 31.97 5.00 x ( 11.80 x 1.30 )x ### =49.50 x 1.00 x 1.15 x 1.00 = 56.93 5.00 x ( 9.50 x 1.30 )x ### =32.00 x 1.00 x 1.15 x 2.00 = 73.60 32.00 x ( 10.40 + 0.36 )x ### =

Page 63: Cost Estimates 2S BLDG

LATERAL TRUSS = 283.20 RAFTERS =2.00 x 7.00 x 9.90 x 2.00 = 277.20 2.00 x ( 4.00 x 6.54 )x ### =2.00 x 2.00 x 1.50 x 1.00 = 6.00 2.00 x ( 2.00 x 2.68 )x ### =2.00 x 1.00 x 9.90 x 1.00 = 19.80

Page 64: Cost Estimates 2S BLDG

PERIMETER (m)98.80

107.60

78.20194.40

14.70

26.4022.4019.20

Page 65: Cost Estimates 2S BLDG

507.84154.56220.80132.48586.02

6996.402254.004742.406222.171424.803107.752903.00

211.432956.452710.93

245.522004.431923.41

81.01497.12353.28143.84

VERTICAL BARS1617.20

348.40676.00592.80

393.1251.4870.4631.2039.26

138.4576.7061.75

119.99

Page 66: Cost Estimates 2S BLDG

115.33104.61

10.71

Page 67: Cost Estimates 2S BLDG

CONCRETE (Class A)Cement 9 bags/cu.m.Gravel 1 cu.m./cu.m.Sand 0.5 cu.m./cu.m.THK 0.1 m.

DRB 6 m./6 m.lngth.Hor. Splice 1.15 m./m.Ver. Splice 1.3 m./m.

TIE WIRES 0.00566 kg./pc.CHB 13 pcs/sq.m.

Cement, 6" THK 0.0982 bags/pc.Sand, 6" THK 0.0053 cu.m./pc.Cement, 4" THK 0.0411 bags/pc.Sand, 4" THK 0.0022 cu.m./pc.

PLASTER (Class A)THK 0.012 m.Cement 0.098 bags/sq.m.Sand 0.01 cu.m./sq.m.

PLYWOOD2.88 sq.m./pc.

FORMSfor columns 29.67 bd.ft./sq.m.

SCAFFOLDINGSfor ver. Columns 7 bd.ft./m.for hor. Columns 21 bd.ft./m.for bracing 11.7 bd.ft./m.for ver. Beams 6 bd.ft./m.for slab 9.1 bd.ft./sq.m.

NAILSper bd. Ft. 0.0186 pcs/bd.ft.4# 63 pcs/kg.

ROOF (32"x6")width 0.71 m.length 1.5 m.ridge & flashing 2.1 m./pc.wall flashing 0.65217 pcs./m.

HARDIFLEX 2.88 sq.m./pc.TILES

floor tiles 0.09 sq.m./pc.T&B tiles 0.04 sq.m./pc.tile trim 9 pcs./m.

ELECTRICALRSC 10 m./lgth.Flexible 50 m./rollTHW Wire 150 m./roll

PIPES 10 m./pc.PAINT

neutralizer 25 sq.m./gal.primer 20 sq.m./gal.latex 22 sq.m./gal.thinner 10 gal./gal

ROUND BARS 6 m./lgth.