cost estimating post hurricanes: a review of the challenges karl d. bartholomew, p.e., asa director...
TRANSCRIPT
Cost Estimating Post Hurricanes:
A Review of the Challenges
Karl D. Bartholomew, P.E., ASA
Director
September 2006
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 2
Process Industries Cost Escalation
A review of pre-hurricane construction
How did the hurricanes impact costs?
What’s happening now?
Were Hurricanes Katrina and Rita responsible for cost escalation for onshore process facilities today?
Lessons for the future: levels of cost estimate accuracy
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 3
What was happening pre-hurricane?
Materials and resources were already being strained– Number of announced projects in pipeline for engineering and
front-end work in refining and petrochemicals ($95 B in North American refining alone)
Rising costs not limited to just U.S. Gulf Coast– Cost overruns in Alberta Oil Sands; Middle East petrochemicals
Refinery construction cost indices up 11% Jan 2004 vs. Jan 2006
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 4
What was happening pre-hurricane?
Bulk commodities, steel prices were up – In large part to China, India, U.S.
Freight costs much higher due to higher oil prices
Cost escalation pressures were already in place before Katrina and Rita
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 5
The hurricanes hit – how did that impact costs?
Immediate draw on commodity resources– Lumber, cement, drywall, cleaning materials
Onshore process operations impacted by both water and wind damage
Costs incurred to restore process operations:– Debris cleanup
– Inspection & replacement of damaged rotating equipment, electrical, instrumentation
– Inspection and repair of steel (corrosion)
– Repair of damaged vessels, insulation
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 6
Cost Impact of hurricanes
Labor market saw biggest change– Quick rise in bare labor rates– Living costs– Added benefits (per diems)
2 stories of hurricane impact:
– Barber quits cutting hair, buys dump truck, contracts with FEMA at 000s/week to haul debris
– Laborers changing job sites if offers catered meals vs. box lunches
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 7
More hurricane impact
Draw on specialty craft labor from Corpus Christi up to Midwest– Insulators, scaffolding see 2X increase in rates
Contractors throwing $ at the problem trying to fix everything for everyone
Another story – refiner’s concern wasn’t getting scaffolding up, but getting it down if another storm hit
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 8
Some costs were unexpected
Extended living costs over a long time was something nobody anticipated
Some vendors used warranty issues to force full replacements even if the item worked
– Rotating equipment, control systems
Facilities that didn’t have up to date drawings & specs of what was actually at their plants incurred substantial engineering & design costs
– Some facilities in better shape on this due to OSHA requirements
Some facilities took this as opportune time to improve/upgrade their plants (“urban renewal”)
– Has led to some contract coverage issues
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 9
Outlook for next year
Most E&C companies have full shops– due to major expansion wave underway in refining
Steel & fabrication shops essentially full
Bidding war for experienced staff
Labor rates continue to escalate but at lower rate
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 10
Where are we today?
Biggest impact we see is on delivery schedules– Lead times for major forged reactor vessels have gone from 24
months to 40+ months (for high pressure processes)– Engineering front end design schedules increasing by 2X
Hurricanes gave us a new ‘set point’ which appears to be stabilizing at much higher labor rates– Expectation that rate growth will flatten before resuming typical
growth
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 11
Equipment Lead Time
REFINING PROJECTSLEAD TIME FOR EQUIPMENT
0
20
40
60
80
100
120
140
160
180
200
REACTORS-FR +
V
COKE DRUM
S
REACTORS/SEPARATORS (<
6")
HP S&T X
CHGRS ALLOY/C
LAD
HP S&T X
CHGRS C.S
.
PUMPS (H
YDRAULIC D
ECOKING)
CENT. COM
PRESSOR
API MULTI-S
TAGE CENTRIF
UGAL P
UMPS
HP TOW
ER (KCS)
DELTA VALVES
RECIP. C
OM
PRESSOR
HP PRESSURE V
ESSELS (<3"
)
LARGE DIA
METER P
RESSURE VESSELS
TOW
ER (SS)
FIRED H
EATERS (9 C
HROME)
GENERAL SERVIC
E API C
ENTRIFUG
AL PUM
PS
GENERAL SERVIC
E S&T E
XCHANGERS
AIR C
OOLED HEAT E
XCHANGERS
GENERAL SERVIC
E PRESSURE V
ESSELS
03/05 Delivery (ExWorks)
03/06 Delivery (ExWorks)
WE
EK
S A
RO
42
32
22
12
2
MO
NT
HS
AR
O
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 12
Equipment Escalation
REFINING PROJECTSPRICE ESCALATION FOR EQUIPMENT
0%
5%
10%
15%
20%
25%
30%
REACTORS-FR +
V
COKE DRUM
S
REACTORS/SEPARATORS (<
6")
HP S&T X
CHGRS ALLOY/C
LAD
HP S&T X
CHGRS C.S
.
PUMPS (H
YDRAULIC D
ECOKING)
CENT. COM
PRESSOR
API MULTI-S
TAGE CENTRIF
UGAL P
UMPS
HP TOW
ER (KCS)
DELTA VALVES
RECIP. C
OM
PRESSOR
HP PRESSURE V
ESSELS (<3"
)
LARGE D
IAM
ETER PRESSURE V
ESSELS
TOW
ER (SS)
FIRED H
EATERS (9 C
HROME)
GENERAL SERVIC
E API C
ENTRIFUG
AL PUM
PS
GENERAL SERVIC
E S&T E
XCHANGERS
AIR C
OOLED HEAT E
XCHANGERS
GENERAL SERVIC
E PRESSURE V
ESSELS
03/05 Price Escalation
03/06 Price Escalation
WE
EK
S A
RO
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 13
Were the hurricanes the main culprits?
For the onshore process industry – NO
Cost pressures already building up
Katrina/Rita kicked down the door of building escalation not only in the Gulf Coast but has created impacts around the world, particularly for experienced engineering, construction and operating resources.
Cost pressures will continue for next several years, but not at the extreme post-hurricane growth
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 14
Accuracy of Cost Estimates
Accuracy of estimate is directly related to level of effort (time) spent
Association of Advancement of Cost Engineering (AACE) provides guidelines for accuracy vs. work effort
Estimate Class V Class IV Class III Class II Class IType (Order of Magnitude) (Study Estimate) (Early Phase III Estimate) (Control Estimate) (Construction Estimate)
EstimateQuality > or = to +/- 50% +/- 30% to 40% +/- 20% to 30% +/- 10% to 15% +/- 5%Range
EngineeringDesign > or = to 1 % 1% to 5% 5% to 10% 25% to 30% 80% to 95%
Complete
Use Long Range Capital Budgets, Concept Studies, Prelim. Appropriations, Final Appropriations, Change Evaluation,for Feasibility Studies, Feasibility Studies, Evaluation of Alternates, Detailed Project Sub Pkg. Check Estimate,
Estimates Screening Studies Scope Decisions and Prelim. Controls Control Estimate Lump Sum Bid Tender
$ $$ $$$ $$$$ $$$$$$$$
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 15
Level of Work for Cost Estimates
Estimate Class V Class IV Class III Class II Class IType (Order of Magnitude) (Study Estimate) (Early Phase III Estimate) (Control Estimate) (Construction Estimate)
EstimateQuality > or = to +/- 50% +/- 30% to 40% +/- 20% to 30% +/- 10% to 15% +/- 5%Range
EngineeringDesign > or = to 1 % 1% to 5% 5% to 10% 25% to 30% 80% to 95%
CompleteNew Construction - ISBL
Method Factor TIC from Historical Factor ISBL TIC from verbal Factor Direct Costs for Detail take-offs on all scope Detail take-offs on all project
Relationship factors such or historical Major Equipment each piece of Major Equipment that can be quantified. scope. Use small amount of
as " Capacity Ratios ". costs based on " As-built " based on vendor verified equipment Design Allowance for remaining
or " Definitive Estimate " prices. Historical percentages (%) for engineering work.
Percentage (%) other plant cost history. Revamp Construction - ISBL minor scope items not being
costs such as: Develop preliminary quantity quantified. Bid tab quotations for Major
- Utilities Rough T/O of OSBL w/ gross take-offs for calculating equipment Equipment, Bulk materials and
- Environmental TIC unit prices. bulk materials, labor and subcontracts. Subcontract costs.
- General Offsites Use historical $ & mhs per major
account. Use heavy Design
Allowances with these take-offs.
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 16
Work effort for +/- 20%-30%
5%-10% of engineering design is complete– For $100 million project ~ $0.8-1.5 million
Factored estimate based on major equipment
Vendor verified major equipment prices
Preliminary allowances for offsites (utilities, infrastructure)
Historical % for professional services, indirects
J ACOBSCONSULTANCYJ ACOBSCONSULTANCY
slide 17
Cost Estimate Deliverables
The AACE International Recommended Practice for Cost Estimate Classification, Joint Cost Management Societies Proceedings, Larry R. Dysert, CCC
S = StartedP = PreliminaryC = Complete