cost management
TRANSCRIPT
Cost ManagementDr. Mostafa ElgamalaPMP-ITIL-IBDL-LDP8
RHCE-MCSA-CCNA/CCAI-CSCU
Project cost management: 1- Estimate costs (planning)2- Determine budget (planning)3- Control costs (monitor & control)
Estimate costsDeveloping an approximation of the monetary
resources needed to complete project activities.
Inputs
• Scope baseline
• Project schedule
• Human resource plan
• Risk register • OPA• EEF
Tools & techniques
• Expert judgment
• Analogous estimate
• Parametric estimate
• Three points estimate
• Project management estimating software
• Cost of quality• Vendor bid
analysis
Outputs
• Activity cost estimate
• Basis of estimate
• Project documents updates
Estimate costs tools & techniquesExpert judgment Analogous estimating (top down estimate) Parametric estimating Three point estimating Project management estimating software Cost of qualityVendor analysis.
Estimate costs outputs
Activity cost estimate Basis of estimates: assumption made.
Project document updates.
2- Determine budgetProcess of aggregating the estimated
costs of individual activities or work packages to establish an authorized cost baseline.
Inputs • Activity cost
estimate • Basis of
estimates • Scope baseline • Project
schedule • Resource
calendars • Contracts • OPA
Tools & techniques
• Cost aggregation
• Reserve analysis
• Expert judgment
• Funding limits reconciliation
Outputs • Cost
performance baseline
• Project funding requirements
• Project docuemnts updates
Cost aggregation: cost estimates are aggregated by work packages in accordance with WBS then work packages cost estimate aggregated for higher component level such as control account.
Reserve analysis: contingency reserve & management reserve
Determine budget tools & techniques:
Expert judgment Funding limit reconciliation: expenditure
of funds should be reconciled with any funding limits.
Determine budget output: Cost performance baseline: is an authorized time
phased budget at completion used to measure, monitor & control overall cost performance an the project.
Cost baseline = project estimate + contingency reserve
Cost budget = cost baseline + management reserve
3- Control costsProcess of monitoring the status of the
expenditure and managing changes to the cost baseline.
Inputs • Project
management plan
• Project funding requirements
• Work performance information
• OPA
Tools & techniques
• Earned value management
• Forecasting • Performance
reviews • Variance
analysis • Project
management software
Outputs •Work performance measurements •Budget forecasts •Organizational process assets updates •Change requests •Project management plan updates •Project documents updates
Control cost tools & techniques: Earned value management EVM: Used method
of performance measurements with three key dimension.
Planned value PV: is the authorized budget assigned to the work to be accomplished.
Earned value EV: is the value of work performed
Actual costs AC: the actual cost actually incurred & recorded in accomplishing work performed .
Earned value management formulas:
Schedule variance SV = EV – PV
Cost variance CV = EV – AC
Schedule performance index SPI = EV/PV
Cost performance index CPI= EV/AC
SV (-ve , behind schedule - +ve , ahead of schedule)
CV (-ve, over budget - +ve , under budget)
example10 building in 10 months (each cost is 1
million)At the fifth monthPV = 5 mEV = 7 m (7 building)AC = 8 m
SV = EV - PV = 7-5 = 2 (ahead of schedule)CV= EV - AC = 7-8 = -1 (over budget)
Forecasting: forecast for the estimate at completion EAC
EAC = AC + ETC
Variance at completion VAC = BAC – EAC
Performance reviews: reviews to compare performance over time.
Project management software
Control costs outputsWork performance measurements.
Budget forecasts
Change requests
Organizational process assets update
Project management plan updates
Project document updates.
Thanks