Costo Marginal Térmico Horario
Fecha Hora PrecioN ($/MW) OfertanteN OfertanteC PrecioCS ($/MW)
01-oct-17 0 76.649 LUT LUT 76.649
01-oct-17 1 76.649 LUT LUT 76.649
01-oct-17 2 76.649 LUT LUT 76.649
01-oct-17 3 76.648 ENR ENR 76.648
01-oct-17 4 76.648 ENR ENR 76.648
01-oct-17 5 76.648 ENR ENR 76.648
01-oct-17 6 76.648 ENR ENR 76.648
01-oct-17 7 76.648 ENR ENR 76.648
01-oct-17 8 76.648 ENR ENR 76.648
01-oct-17 9 76.648 ENR ENR 76.648
01-oct-17 10 76.648 ENR ENR 76.648
01-oct-17 11 76.648 ENR ENR 76.648
01-oct-17 12 76.649 LUT LUT 76.649
01-oct-17 13 76.649 LUT LUT 76.649
01-oct-17 14 76.649 LUT LUT 76.649
01-oct-17 15 76.649 LUT LUT 76.649
01-oct-17 16 76.649 LUT LUT 76.649
01-oct-17 17 78.159 ENR ENR 78.159
01-oct-17 18 94.543 ELC ELC 94.543
01-oct-17 19 94.543 ELC ELC 94.543
01-oct-17 20 94.543 ELC ELC 94.543
01-oct-17 21 78.159 ENR ENR 78.159
01-oct-17 22 76.649 LUT LUT 76.649
01-oct-17 23 76.649 LUT LUT 76.649
02-oct-17 0 76.648 ENR ENR 76.648
02-oct-17 1 76.648 ENR ENR 76.648
02-oct-17 2 76.648 ENR ENR 76.648
02-oct-17 3 76.648 ENR ENR 76.648
02-oct-17 4 76.648 ENR ENR 76.648
02-oct-17 5 76.648 ENR ENR 76.648
02-oct-17 6 76.648 ENR ENR 76.648
02-oct-17 7 76.648 ENR ENR 76.648
02-oct-17 8 78.159 ENR LUT 76.649
02-oct-17 9 78.159 ENR LUT 76.649
02-oct-17 10 78.159 ENR LUT 76.649
02-oct-17 11 94.543 ELC LUT 76.649
02-oct-17 12 94.543 ELC LUT 76.649
02-oct-17 13 94.543 ELC LUT 76.649
02-oct-17 14 94.543 ELC LUT 76.649
02-oct-17 15 94.543 ELC LUT 76.649
02-oct-17 16 94.543 ELC LUT 76.649
02-oct-17 17 94.543 ELC ELC 94.543
02-oct-17 18 94.543 ELC ELC 94.543
02-oct-17 19 94.543 ELC ELC 94.543
02-oct-17 20 94.543 ELC ELC 94.543
02-oct-17 21 94.543 ELC ELC 94.543
02-oct-17 22 78.159 ENR ENR 78.159
Centro SurNorte
02-oct-17 23 76.649 LUT LUT 76.649
03-oct-17 0 76.648 ENR ENR 76.648
03-oct-17 1 76.648 ENR ENR 76.648
03-oct-17 2 76.648 ENR ENR 76.648
03-oct-17 3 76.648 ENR ENR 76.648
03-oct-17 4 76.648 ENR ENR 76.648
03-oct-17 5 76.648 ENR ENR 76.648
03-oct-17 6 76.648 ENR ENR 76.648
03-oct-17 7 76.649 LUT LUT 76.649
03-oct-17 8 78.159 ENR LUT 76.649
03-oct-17 9 94.543 ELC LUT 76.649
03-oct-17 10 94.543 ELC LUT 76.649
03-oct-17 11 94.543 ELC LUT 76.649
03-oct-17 12 94.543 ELC LUT 76.649
03-oct-17 13 94.543 ELC LUT 76.649
03-oct-17 14 94.543 ELC LUT 76.649
03-oct-17 15 94.543 ELC LUT 76.649
03-oct-17 16 94.543 ELC ELC 94.543
03-oct-17 17 112.396 ECH ECH 112.396
03-oct-17 18 112.396 ECH ECH 112.396
03-oct-17 19 112.396 ECH ECH 112.396
03-oct-17 20 112.396 ECH ECH 112.396
03-oct-17 21 94.543 ELC ELC 94.543
03-oct-17 22 78.159 ENR ENR 78.159
03-oct-17 23 76.649 LUT LUT 76.649
04-oct-17 0 76.649 LUT LUT 76.649
04-oct-17 1 76.648 ENR ENR 76.648
04-oct-17 2 76.648 ENR ENR 76.648
04-oct-17 3 76.648 ENR ENR 76.648
04-oct-17 4 76.648 ENR ENR 76.648
04-oct-17 5 76.649 LUT LUT 76.649
04-oct-17 6 76.649 LUT LUT 76.649
04-oct-17 7 76.649 LUT LUT 76.649
04-oct-17 8 78.159 ENR LUT 76.649
04-oct-17 9 92.578 ENRex LUT 76.649
04-oct-17 10 92.578 ENRex LUT 76.649
04-oct-17 11 92.578 ENRex LUT 76.649
04-oct-17 12 92.578 ENRex LUT 76.649
04-oct-17 13 78.159 ENR LUT 76.649
04-oct-17 14 78.159 ENR LUT 76.649
04-oct-17 15 78.159 ENR LUT 76.649
04-oct-17 16 78.159 ENR LUT 76.649
04-oct-17 17 78.159 ENR ENR 78.159
04-oct-17 18 112.396 ECH ECH 112.396
04-oct-17 19 112.396 ECH ECH 112.396
04-oct-17 20 112.396 ECH ECH 112.396
04-oct-17 21 92.578 ENRex ENRex 92.578
04-oct-17 22 78.159 ENR ENR 78.159
04-oct-17 23 76.648 ENR ENR 76.648
05-oct-17 0 76.648 ENR ENR 76.648
05-oct-17 1 76.648 ENR ENR 76.648
05-oct-17 2 76.648 ENR ENR 76.648
05-oct-17 3 76.648 ENR ENR 76.648
05-oct-17 4 76.648 ENR ENR 76.648
05-oct-17 5 76.648 ENR ENR 76.648
05-oct-17 6 76.648 ENR ENR 76.648
05-oct-17 7 76.648 ENR ENR 76.648
05-oct-17 8 76.648 ENR ENR 76.648
05-oct-17 9 76.648 ENR ENR 76.648
05-oct-17 10 76.648 ENR ENR 76.648
05-oct-17 11 78.159 ENR LUT 76.649
05-oct-17 12 78.159 ENR LUT 76.649
05-oct-17 13 78.159 ENR LUT 76.649
05-oct-17 14 78.159 ENR LUT 76.649
05-oct-17 15 78.159 ENR LUT 76.649
05-oct-17 16 78.159 ENR ENR 78.159
05-oct-17 17 93.108 LUTex LUTex 93.108
05-oct-17 18 94.543 ELC ELC 94.543
05-oct-17 19 94.543 ELC ELC 94.543
05-oct-17 20 94.543 ELC ELC 94.543
05-oct-17 21 78.159 ENR ENR 78.159
05-oct-17 22 76.649 LUT LUT 76.649
05-oct-17 23 76.648 ENR ENR 76.648
06-oct-17 0 76.648 ENR ENR 76.648
06-oct-17 1 76.648 ENR ENR 76.648
06-oct-17 2 76.648 ENR ENR 76.648
06-oct-17 3 76.648 ENR ENR 76.648
06-oct-17 4 76.648 ENR ENR 76.648
06-oct-17 5 76.648 ENR ENR 76.648
06-oct-17 6 76.648 ENR ENR 76.648
06-oct-17 7 76.648 ENR ENR 76.648
06-oct-17 8 76.648 ENR ENR 76.648
06-oct-17 9 76.648 ENR ENR 76.648
06-oct-17 10 76.648 ENR ENR 76.648
06-oct-17 11 78.159 ENR LUT 76.649
06-oct-17 12 78.159 ENR LUT 76.649
06-oct-17 13 78.159 ENR LUT 76.649
06-oct-17 14 78.159 ENR LUT 76.649
06-oct-17 15 78.159 ENR LUT 76.649
06-oct-17 16 78.159 ENR ENR 78.159
06-oct-17 17 78.159 ENR ENR 78.159
06-oct-17 18 112.396 ECH ECH 112.396
06-oct-17 19 112.396 ECH ECH 112.396
06-oct-17 20 78.159 ENR ENR 78.159
06-oct-17 21 78.159 ENR ENR 78.159
06-oct-17 22 76.649 LUT LUT 76.649
06-oct-17 23 76.648 ENR ENR 76.648
07-oct-17 0 76.648 ENR ENR 76.648
07-oct-17 1 76.648 ENR ENR 76.648
07-oct-17 2 76.648 ENR ENR 76.648
07-oct-17 3 76.648 ENR ENR 76.648
07-oct-17 4 76.648 ENR ENR 76.648
07-oct-17 5 76.648 ENR ENR 76.648
07-oct-17 6 76.648 ENR ENR 76.648
07-oct-17 7 76.648 ENR ENR 76.648
07-oct-17 8 76.648 ENR ENR 76.648
07-oct-17 9 76.648 ENR ENR 76.648
07-oct-17 10 78.159 ENR LUT 76.649
07-oct-17 11 78.159 ENR LUT 76.649
07-oct-17 12 78.159 ENR LUT 76.649
07-oct-17 13 78.159 ENR LUT 76.649
07-oct-17 14 78.159 ENR LUT 76.649
07-oct-17 15 78.159 ENR LUT 76.649
07-oct-17 16 78.159 ENR ENR 78.159
07-oct-17 17 78.159 ENR ENR 78.159
07-oct-17 18 94.543 ELC ELC 94.543
07-oct-17 19 94.543 ELC ELC 94.543
07-oct-17 20 94.543 ELC ELC 94.543
07-oct-17 21 78.159 ENR ENR 78.159
07-oct-17 22 76.649 LUT LUT 76.649
07-oct-17 23 76.649 LUT LUT 76.649
08-oct-17 0 76.648 ENR ENR 76.648
08-oct-17 1 76.648 ENR ENR 76.648
08-oct-17 2 76.648 ENR ENR 76.648
08-oct-17 3 76.648 ENR ENR 76.648
08-oct-17 4 76.648 ENR ENR 76.648
08-oct-17 5 76.648 ENR ENR 76.648
08-oct-17 6 76.648 ENR ENR 76.648
08-oct-17 7 76.648 ENR ENR 76.648
08-oct-17 8 76.648 ENR ENR 76.648
08-oct-17 9 76.648 ENR ENR 76.648
08-oct-17 10 76.648 ENR ENR 76.648
08-oct-17 11 76.648 ENR ENR 76.648
08-oct-17 12 76.648 ENR ENR 76.648
08-oct-17 13 76.648 ENR ENR 76.648
08-oct-17 14 76.648 ENR ENR 76.648
08-oct-17 15 76.648 ENR ENR 76.648
08-oct-17 16 76.649 LUT LUT 76.649
08-oct-17 17 78.159 ENR ENR 78.159
08-oct-17 18 112.396 ECH ECH 112.396
08-oct-17 19 112.396 ECH ECH 112.396
08-oct-17 20 112.396 ECH ECH 112.396
08-oct-17 21 94.543 ELC ELC 94.543
08-oct-17 22 93.108 LUTex LUTex 93.108
08-oct-17 23 76.649 LUT LUT 76.649
09-oct-17 0 76.649 LUT LUT 76.649
09-oct-17 1 76.649 LUT LUT 76.649
09-oct-17 2 76.649 LUT LUT 76.649
09-oct-17 3 76.649 LUT LUT 76.649
09-oct-17 4 76.648 ENR ENR 76.648
09-oct-17 5 76.649 LUT LUT 76.649
09-oct-17 6 76.649 LUT LUT 76.649
09-oct-17 7 76.649 LUT LUT 76.649
09-oct-17 8 78.159 ENR LUT 76.649
09-oct-17 9 78.159 ENR LUT 76.649
09-oct-17 10 94.543 ELC LUT 76.649
09-oct-17 11 94.543 ELC LUT 76.649
09-oct-17 12 94.543 ELC LUT 76.649
09-oct-17 13 94.543 ELC LUT 76.649
09-oct-17 14 94.543 ELC LUT 76.649
09-oct-17 15 94.543 ELC LUT 76.649
09-oct-17 16 94.543 ELC ELC 94.543
09-oct-17 17 112.396 ECH ECH 112.396
09-oct-17 18 112.396 LUV LUV 112.396
09-oct-17 19 112.396 LUV LUV 112.396
09-oct-17 20 112.396 LUV LUV 112.396
09-oct-17 21 94.543 ELC ELC 94.543
09-oct-17 22 78.159 ENR ENR 78.159
09-oct-17 23 76.648 ENR ENR 76.648
10-oct-17 0 76.648 ENR ENR 76.648
10-oct-17 1 76.648 ENR ENR 76.648
10-oct-17 2 76.648 ENR ENR 76.648
10-oct-17 3 76.648 ENR ENR 76.648
10-oct-17 4 76.648 ENR ENR 76.648
10-oct-17 5 76.648 ENR ENR 76.648
10-oct-17 6 76.648 ENR ENR 76.648
10-oct-17 7 76.649 LUT LUT 76.649
10-oct-17 8 94.543 ELC LUT 76.649
10-oct-17 9 94.543 ELC LUT 76.649
10-oct-17 10 94.543 ELC LUT 76.649
10-oct-17 11 94.543 ELC LUT 76.649
10-oct-17 12 94.543 ELC LUT 76.649
10-oct-17 13 94.543 ELC LUT 76.649
10-oct-17 14 94.543 ELC LUT 76.649
10-oct-17 15 94.543 ELC LUT 76.649
10-oct-17 16 94.543 ELC ELC 94.543
10-oct-17 17 112.396 ECH ECH 112.396
10-oct-17 18 112.396 ECH ECH 112.396
10-oct-17 19 112.396 ECH ECH 112.396
10-oct-17 20 112.396 ECH ECH 112.396
10-oct-17 21 94.543 ELC ELC 94.543
10-oct-17 22 78.159 ENR ENR 78.159
10-oct-17 23 76.648 ENR ENR 76.648
11-oct-17 0 76.648 ENR ENR 76.648
11-oct-17 1 76.648 ENR ENR 76.648
11-oct-17 2 76.648 ENR ENR 76.648
11-oct-17 3 76.648 ENR ENR 76.648
11-oct-17 4 76.648 ENR ENR 76.648
11-oct-17 5 76.648 ENR ENR 76.648
11-oct-17 6 76.648 ENR ENR 76.648
11-oct-17 7 76.648 ENR ENR 76.648
11-oct-17 8 78.159 ENR LUT 76.649
11-oct-17 9 78.159 ENR LUT 76.649
11-oct-17 10 78.159 ENR LUT 76.649
11-oct-17 11 78.159 ENR LUT 76.649
11-oct-17 12 78.159 ENR LUT 76.649
11-oct-17 13 78.159 ENR LUT 76.649
11-oct-17 14 78.159 ENR LUT 76.649
11-oct-17 15 78.159 ENR LUT 76.649
11-oct-17 16 78.159 ENR LUT 76.649
11-oct-17 17 78.159 ENR ENR 78.159
11-oct-17 18 112.396 ECH ECH 112.396
11-oct-17 19 112.396 ECH ECH 112.396
11-oct-17 20 112.396 ECH ECH 112.396
11-oct-17 21 94.543 ELC ELC 94.543
11-oct-17 22 78.159 ENR ENR 78.159
11-oct-17 23 76.648 ENR ENR 76.648
12-oct-17 0 76.648 ENR ENR 76.648
12-oct-17 1 76.648 ENR ENR 76.648
12-oct-17 2 76.648 ENR ENR 76.648
12-oct-17 3 76.648 ENR ENR 76.648
12-oct-17 4 76.648 ENR ENR 76.648
12-oct-17 5 76.648 ENR ENR 76.648
12-oct-17 6 76.648 ENR ENR 76.648
12-oct-17 7 76.648 ENR ENR 76.648
12-oct-17 8 78.159 ENR LUT 76.649
12-oct-17 9 78.159 ENR LUT 76.649
12-oct-17 10 78.159 ENR LUT 76.649
12-oct-17 11 78.159 ENR LUT 76.649
12-oct-17 12 78.159 ENR LUT 76.649
12-oct-17 13 78.159 ENR LUT 76.649
12-oct-17 14 78.159 ENR LUT 76.649
12-oct-17 15 78.159 ENR LUT 76.649
12-oct-17 16 78.159 ENR ENR 78.159
12-oct-17 17 112.396 ECH ECH 112.396
12-oct-17 18 112.396 ECH ECH 112.396
12-oct-17 19 112.396 ECH ECH 112.396
12-oct-17 20 94.543 ELC ELC 94.543
12-oct-17 21 92.578 ENRex ENRex 92.578
12-oct-17 22 78.159 ENR ENR 78.159
12-oct-17 23 76.648 ENR ENR 76.648
13-oct-17 0 76.648 ENR ENR 76.648
13-oct-17 1 76.648 ENR ENR 76.648
13-oct-17 2 76.648 ENR ENR 76.648
13-oct-17 3 76.648 ENR ENR 76.648
13-oct-17 4 76.648 ENR ENR 76.648
13-oct-17 5 76.648 ENR ENR 76.648
13-oct-17 6 76.648 ENR ENR 76.648
13-oct-17 7 76.648 ENR ENR 76.648
13-oct-17 8 78.159 ENR LUT 76.649
13-oct-17 9 78.159 ENR LUT 76.649
13-oct-17 10 78.159 ENR LUT 76.649
13-oct-17 11 78.159 ENR LUT 76.649
13-oct-17 12 78.159 ENR LUT 76.649
13-oct-17 13 78.159 ENR LUT 76.649
13-oct-17 14 78.159 ENR LUT 76.649
13-oct-17 15 78.159 ENR LUT 76.649
13-oct-17 16 78.159 ENR ENR 78.159
13-oct-17 17 112.396 ECH ECH 112.396
13-oct-17 18 112.396 ECH ECH 112.396
13-oct-17 19 112.396 ECH ECH 112.396
13-oct-17 20 94.543 ELC ELC 94.543
13-oct-17 21 92.578 ENRex ENRex 92.578
13-oct-17 22 78.159 ENR ENR 78.159
13-oct-17 23 76.648 ENR ENR 76.648
14-oct-17 0 76.648 ENR ENR 76.648
14-oct-17 1 76.648 ENR ENR 76.648
14-oct-17 2 76.648 ENR ENR 76.648
14-oct-17 3 76.648 ENR ENR 76.648
14-oct-17 4 76.648 ENR ENR 76.648
14-oct-17 5 76.648 ENR ENR 76.648
14-oct-17 6 76.648 ENR ENR 76.648
14-oct-17 7 76.648 ENR ENR 76.648
14-oct-17 8 76.648 ENR ENR 76.648
14-oct-17 9 76.648 ENR ENR 76.648
14-oct-17 10 76.648 ENR ENR 76.648
14-oct-17 11 78.159 ENR LUT 76.649
14-oct-17 12 78.159 ENR LUT 76.649
14-oct-17 13 78.159 ENR LUT 76.649
14-oct-17 14 78.159 ENR LUT 76.649
14-oct-17 15 78.159 ENR LUT 76.649
14-oct-17 16 78.159 ENR ENR 78.159
14-oct-17 17 78.159 ENR ENR 78.159
14-oct-17 18 94.543 ELC ELC 94.543
14-oct-17 19 94.543 ELC ELC 94.543
14-oct-17 20 94.543 ELC ELC 94.543
14-oct-17 21 78.159 ENR ENR 78.159
14-oct-17 22 78.159 ENR ENR 78.159
14-oct-17 23 76.648 ENR ENR 76.648
15-oct-17 0 76.648 ENR ENR 76.648
15-oct-17 1 76.648 ENR ENR 76.648
15-oct-17 2 76.648 ENR ENR 76.648
15-oct-17 3 76.648 ENR ENR 76.648
15-oct-17 4 76.648 ENR ENR 76.648
15-oct-17 5 76.648 ENR ENR 76.648
15-oct-17 6 76.648 ENR ENR 76.648
15-oct-17 7 76.648 ENR ENR 76.648
15-oct-17 8 76.648 ENR ENR 76.648
15-oct-17 9 76.648 ENR ENR 76.648
15-oct-17 10 76.648 ENR ENR 76.648
15-oct-17 11 76.648 ENR ENR 76.648
15-oct-17 12 76.648 ENR ENR 76.648
15-oct-17 13 76.648 ENR ENR 76.648
15-oct-17 14 76.648 ENR ENR 76.648
15-oct-17 15 76.648 ENR ENR 76.648
15-oct-17 16 76.648 ENR ENR 76.648
15-oct-17 17 94.543 ELC ELC 94.543
15-oct-17 18 94.543 ELC ELC 94.543
15-oct-17 19 94.543 ELC ELC 94.543
15-oct-17 20 94.543 ELC ELC 94.543
15-oct-17 21 78.159 ENR ENR 78.159
15-oct-17 22 76.648 ENR ENR 76.648
15-oct-17 23 76.648 ENR ENR 76.648
16-oct-17 0 76.648 ENR ENR 76.648
16-oct-17 1 76.648 ENR ENR 76.648
16-oct-17 2 76.648 ENR ENR 76.648
16-oct-17 3 76.648 ENR ENR 76.648
16-oct-17 4 76.648 ENR ENR 76.648
16-oct-17 5 76.648 ENR ENR 76.648
16-oct-17 6 76.648 ENR ENR 76.648
16-oct-17 7 76.648 ENR ENR 76.648
16-oct-17 8 78.159 ENR LUT 76.649
16-oct-17 9 78.159 ENR LUT 76.649
16-oct-17 10 78.159 ENR LUT 76.649
16-oct-17 11 94.543 ELC LUT 76.649
16-oct-17 12 94.543 ELC LUT 76.649
16-oct-17 13 94.543 ELC LUT 76.649
16-oct-17 14 94.543 ELC LUT 76.649
16-oct-17 15 94.543 ELC LUT 76.649
16-oct-17 16 94.543 ELC LUT 76.649
16-oct-17 17 112.396 LUV LUV 112.396
16-oct-17 18 112.396 LUV LUV 112.396
16-oct-17 19 112.396 LUV LUV 112.396
16-oct-17 20 112.396 LUV LUV 112.396
16-oct-17 21 94.543 ELC ELC 94.543
16-oct-17 22 76.649 LUT LUT 76.649
16-oct-17 23 76.649 LUT LUT 76.649
17-oct-17 0 76.648 ENR ENR 76.648
17-oct-17 1 76.648 ENR ENR 76.648
17-oct-17 2 76.648 ENR ENR 76.648
17-oct-17 3 76.648 ENR ENR 76.648
17-oct-17 4 76.648 ENR ENR 76.648
17-oct-17 5 76.649 LUT LUT 76.649
17-oct-17 6 76.649 LUT LUT 76.649
17-oct-17 7 76.649 LUT LUT 76.649
17-oct-17 8 78.159 ENR LUT 76.649
17-oct-17 9 78.159 ENR LUT 76.649
17-oct-17 10 78.159 ENR LUT 76.649
17-oct-17 11 94.543 ELC LUT 76.649
17-oct-17 12 94.543 ELC LUT 76.649
17-oct-17 13 94.543 ELC LUT 76.649
17-oct-17 14 94.543 ELC LUT 76.649
17-oct-17 15 94.543 ELC LUT 76.649
17-oct-17 16 94.543 ELC ELC 94.543
17-oct-17 17 112.396 ECH ECH 112.396
17-oct-17 18 112.396 LUV LUV 112.396
17-oct-17 19 112.396 LUV LUV 112.396
17-oct-17 20 112.396 LUV LUV 112.396
17-oct-17 21 112.396 LUV LUV 112.396
17-oct-17 22 78.159 ENR ENR 78.159
17-oct-17 23 76.649 LUT LUT 76.649
18-oct-17 0 76.648 ENR ENR 76.648
18-oct-17 1 76.648 ENR ENR 76.648
18-oct-17 2 76.648 ENR ENR 76.648
18-oct-17 3 76.648 ENR ENR 76.648
18-oct-17 4 76.648 ENR ENR 76.648
18-oct-17 5 76.648 ENR ENR 76.648
18-oct-17 6 76.648 ENR ENR 76.648
18-oct-17 7 76.648 ENR ENR 76.648
18-oct-17 8 78.159 ENR LUT 76.649
18-oct-17 9 94.543 ELC LUT 76.649
18-oct-17 10 94.543 ELC LUT 76.649
18-oct-17 11 94.543 ELC LUT 76.649
18-oct-17 12 94.543 ELC LUT 76.649
18-oct-17 13 94.543 ELC LUT 76.649
18-oct-17 14 94.543 ELC LUT 76.649
18-oct-17 15 94.543 ELC LUT 76.649
18-oct-17 16 94.543 ELC LUT 76.649
18-oct-17 17 94.543 ELC ELC 94.543
18-oct-17 18 94.543 ELC ELC 94.543
18-oct-17 19 94.543 ELC ELC 94.543
18-oct-17 20 94.543 ELC ELC 94.543
18-oct-17 21 94.543 ELC ELC 94.543
18-oct-17 22 76.648 ENR ENR 76.648
18-oct-17 23 76.648 ENR ENR 76.648
19-oct-17 0 76.648 ENR ENR 76.648
19-oct-17 1 76.648 ENR ENR 76.648
19-oct-17 2 76.648 ENR ENR 76.648
19-oct-17 3 76.648 ENR ENR 76.648
19-oct-17 4 76.648 ENR ENR 76.648
19-oct-17 5 76.648 ENR ENR 76.648
19-oct-17 6 76.648 ENR ENR 76.648
19-oct-17 7 76.648 ENR ENR 76.648
19-oct-17 8 78.159 ENR LUT 76.649
19-oct-17 9 78.159 ENR LUT 76.649
19-oct-17 10 78.159 ENR LUT 76.649
19-oct-17 11 78.159 ENR LUT 76.649
19-oct-17 12 78.159 ENR LUT 76.649
19-oct-17 13 78.159 ENR LUT 76.649
19-oct-17 14 94.543 ELC LUT 76.649
19-oct-17 15 94.543 ELC LUT 76.649
19-oct-17 16 94.543 ELC ELC 94.543
19-oct-17 17 94.543 ELC ELC 94.543
19-oct-17 18 94.543 ELC ELC 94.543
19-oct-17 19 94.543 ELC ELC 94.543
19-oct-17 20 94.543 ELC ELC 94.543
19-oct-17 21 92.578 ENRex ENRex 92.578
19-oct-17 22 76.648 ENR ENR 76.648
19-oct-17 23 76.648 ENR ENR 76.648
20-oct-17 0 76.648 ENR ENR 76.648
20-oct-17 1 76.648 ENR ENR 76.648
20-oct-17 2 76.648 ENR ENR 76.648
20-oct-17 3 76.648 ENR ENR 76.648
20-oct-17 4 76.648 ENR ENR 76.648
20-oct-17 5 92.578 ENRex ENRex 92.578
20-oct-17 6 92.578 ENRex ENRex 92.578
20-oct-17 7 76.648 ENR ENR 76.648
20-oct-17 8 78.159 ENR LUT 76.649
20-oct-17 9 78.159 ENR LUT 76.649
20-oct-17 10 78.159 ENR LUT 76.649
20-oct-17 11 78.159 ENR LUT 76.649
20-oct-17 12 78.159 ENR LUT 76.649
20-oct-17 13 94.543 ELC LUT 76.649
20-oct-17 14 94.543 ELC LUT 76.649
20-oct-17 15 94.543 ELC LUT 76.649
20-oct-17 16 94.543 ELC ELC 94.543
20-oct-17 17 94.543 ELC ELC 94.543
20-oct-17 18 94.543 ELC ELC 94.543
20-oct-17 19 94.543 ELC ELC 94.543
20-oct-17 20 92.578 ENRex ENRex 92.578
20-oct-17 21 78.159 ENR ENR 78.159
20-oct-17 22 76.648 ENR ENR 76.648
20-oct-17 23 76.648 ENR ENR 76.648
21-oct-17 0 76.648 ENR ENR 76.648
21-oct-17 1 76.648 ENR ENR 76.648
21-oct-17 2 76.648 ENR ENR 76.648
21-oct-17 3 76.648 ENR ENR 76.648
21-oct-17 4 76.648 ENR ENR 76.648
21-oct-17 5 76.648 ENR ENR 76.648
21-oct-17 6 76.648 ENR ENR 76.648
21-oct-17 7 76.648 ENR ENR 76.648
21-oct-17 8 76.648 ENR ENR 76.648
21-oct-17 9 76.648 ENR ENR 76.648
21-oct-17 10 78.159 ENR LUT 76.649
21-oct-17 11 78.159 ENR LUT 76.649
21-oct-17 12 92.578 ENRex LUT 76.649
21-oct-17 13 92.578 ENRex LUT 76.649
21-oct-17 14 92.578 ENRex LUT 76.649
21-oct-17 15 92.578 ENRex LUT 76.649
21-oct-17 16 92.578 ENRex LUT 76.649
21-oct-17 17 112.396 ECH ECH 112.396
21-oct-17 18 112.396 ECH ECH 112.396
21-oct-17 19 112.396 ECH ECH 112.396
21-oct-17 20 94.543 ELC ELC 94.543
21-oct-17 21 92.578 ENRex ENRex 92.578
21-oct-17 22 78.159 ENR ENR 78.159
21-oct-17 23 76.649 LUT LUT 76.649
22-oct-17 0 76.649 LUT LUT 76.649
22-oct-17 1 76.649 LUT LUT 76.649
22-oct-17 2 76.649 LUT LUT 76.649
22-oct-17 3 76.649 LUT LUT 76.649
22-oct-17 4 76.649 LUT LUT 76.649
22-oct-17 5 76.649 LUT LUT 76.649
22-oct-17 6 76.649 LUT LUT 76.649
22-oct-17 7 76.648 ENR ENR 76.648
22-oct-17 8 76.648 ENR ENR 76.648
22-oct-17 9 76.648 ENR ENR 76.648
22-oct-17 10 76.648 ENR ENR 76.648
22-oct-17 11 76.648 ENR ENR 76.648
22-oct-17 12 76.649 LUT LUT 76.649
22-oct-17 13 76.649 LUT LUT 76.649
22-oct-17 14 76.648 ENR ENR 76.648
22-oct-17 15 76.649 LUT LUT 76.649
22-oct-17 16 76.649 LUT LUT 76.649
22-oct-17 17 94.543 ELC ELC 94.543
22-oct-17 18 94.543 ELC ELC 94.543
22-oct-17 19 94.543 ELC ELC 94.543
22-oct-17 20 94.543 ELC ELC 94.543
22-oct-17 21 76.649 LUT LUT 76.649
22-oct-17 22 76.649 LUT LUT 76.649
22-oct-17 23 76.648 ENR ENR 76.648
23-oct-17 0 76.648 ENR ENR 76.648
23-oct-17 1 76.648 ENR ENR 76.648
23-oct-17 2 76.648 ENR ENR 76.648
23-oct-17 3 76.648 ENR ENR 76.648
23-oct-17 4 76.648 ENR ENR 76.648
23-oct-17 5 76.648 ENR ENR 76.648
23-oct-17 6 76.648 ENR ENR 76.648
23-oct-17 7 76.648 ENR ENR 76.648
23-oct-17 8 76.649 LUT LUT 76.649
23-oct-17 9 92.578 ENRex LUT 76.649
23-oct-17 10 92.578 ENRex LUT 76.649
23-oct-17 11 92.578 ENRex LUT 76.649
23-oct-17 12 92.578 ENRex LUT 76.649
23-oct-17 13 92.578 ENRex LUT 76.649
23-oct-17 14 92.578 ENRex LUT 76.649
23-oct-17 15 92.578 ENRex LUT 76.649
23-oct-17 16 92.578 ENRex ENRex 92.578
23-oct-17 17 112.396 LUV LUV 112.396
23-oct-17 18 112.396 LUV LUV 112.396
23-oct-17 19 112.396 LUV LUV 112.396
23-oct-17 20 112.396 LUV LUV 112.396
23-oct-17 21 112.396 LUV LUV 112.396
23-oct-17 22 76.649 LUT LUT 76.649
23-oct-17 23 76.649 LUT LUT 76.649
24-oct-17 0 76.648 ENR ENR 76.648
24-oct-17 1 76.648 ENR ENR 76.648
24-oct-17 2 76.648 ENR ENR 76.648
24-oct-17 3 76.648 ENR ENR 76.648
24-oct-17 4 76.648 ENR ENR 76.648
24-oct-17 5 76.648 ENR ENR 76.648
24-oct-17 6 76.648 ENR ENR 76.648
24-oct-17 7 76.648 ENR ENR 76.648
24-oct-17 8 76.649 LUT LUT 76.649
24-oct-17 9 78.159 ENR LUT 76.649
24-oct-17 10 78.159 ENR LUT 76.649
24-oct-17 11 78.159 ENR LUT 76.649
24-oct-17 12 78.159 ENR LUT 76.649
24-oct-17 13 92.578 ENRex LUT 76.649
24-oct-17 14 92.578 ENRex LUT 76.649
24-oct-17 15 93.108 LUTex LUTex 93.108
24-oct-17 16 93.108 LUTex LUTex 93.108
24-oct-17 17 94.543 ELC ELC 94.543
24-oct-17 18 94.543 ELC ELC 94.543
24-oct-17 19 94.543 ELC ELC 94.543
24-oct-17 20 94.543 ELC ELC 94.543
24-oct-17 21 78.159 ENR ENR 78.159
24-oct-17 22 76.648 ENR ENR 76.648
24-oct-17 23 76.648 ENR ENR 76.648
25-oct-17 0 76.648 ENR ENR 76.648
25-oct-17 1 76.648 ENR ENR 76.648
25-oct-17 2 76.648 ENR ENR 76.648
25-oct-17 3 76.648 ENR ENR 76.648
25-oct-17 4 76.648 ENR ENR 76.648
25-oct-17 5 76.648 ENR ENR 76.648
25-oct-17 6 76.648 ENR ENR 76.648
25-oct-17 7 76.649 LUT LUT 76.649
25-oct-17 8 76.649 LUT LUT 76.649
25-oct-17 9 78.159 ENR LUT 76.649
25-oct-17 10 78.159 ENR LUT 76.649
25-oct-17 11 78.159 ENR LUT 76.649
25-oct-17 12 78.159 ENR LUT 76.649
25-oct-17 13 78.159 ENR LUT 76.649
25-oct-17 14 78.159 ENR LUT 76.649
25-oct-17 15 78.159 ENR LUT 76.649
25-oct-17 16 78.159 ENR LUT 76.649
25-oct-17 17 78.159 ENR ENR 78.159
25-oct-17 18 78.159 ENR ENR 78.159
25-oct-17 19 78.159 ENR ENR 78.159
25-oct-17 20 78.159 ENR ENR 78.159
25-oct-17 21 78.159 ENR ENR 78.159
25-oct-17 22 76.648 ENR ENR 76.648
25-oct-17 23 76.648 ENR ENR 76.648
26-oct-17 0 76.648 ENR ENR 76.648
26-oct-17 1 76.648 ENR ENR 76.648
26-oct-17 2 76.648 ENR ENR 76.648
26-oct-17 3 76.648 ENR ENR 76.648
26-oct-17 4 76.648 ENR ENR 76.648
26-oct-17 5 76.648 ENR ENR 76.648
26-oct-17 6 76.648 ENR ENR 76.648
26-oct-17 7 76.648 ENR ENR 76.648
26-oct-17 8 76.648 ENR ENR 76.648
26-oct-17 9 78.159 ENR LUT 76.649
26-oct-17 10 78.159 ENR LUT 76.649
26-oct-17 11 78.159 ENR LUT 76.649
26-oct-17 12 78.159 ENR LUT 76.649
26-oct-17 13 78.159 ENR LUT 76.649
26-oct-17 14 78.159 ENR LUT 76.649
26-oct-17 15 78.159 ENR LUT 76.649
26-oct-17 16 78.159 ENR LUT 76.649
26-oct-17 17 78.159 ENR ENR 78.159
26-oct-17 18 78.159 ENR ENR 78.159
26-oct-17 19 78.159 ENR ENR 78.159
26-oct-17 20 78.159 ENR ENR 78.159
26-oct-17 21 78.159 ENR ENR 78.159
26-oct-17 22 76.648 ENR ENR 76.648
26-oct-17 23 76.648 ENR ENR 76.648
27-oct-17 0 76.648 ENR ENR 76.648
27-oct-17 1 76.648 ENR ENR 76.648
27-oct-17 2 76.648 ENR ENR 76.648
27-oct-17 3 76.648 ENR ENR 76.648
27-oct-17 4 76.648 ENR ENR 76.648
27-oct-17 5 76.648 ENR ENR 76.648
27-oct-17 6 76.648 ENR ENR 76.648
27-oct-17 7 76.648 ENR ENR 76.648
27-oct-17 8 76.648 ENR ENR 76.648
27-oct-17 9 78.159 ENR LUT 76.649
27-oct-17 10 78.159 ENR LUT 76.649
27-oct-17 11 78.159 ENR LUT 76.649
27-oct-17 12 78.159 ENR LUT 76.649
27-oct-17 13 78.159 ENR LUT 76.649
27-oct-17 14 78.159 ENR LUT 76.649
27-oct-17 15 78.159 ENR LUT 76.649
27-oct-17 16 78.159 ENR LUT 76.649
27-oct-17 17 78.159 ENR ENR 78.159
27-oct-17 18 78.159 ENR ENR 78.159
27-oct-17 19 78.159 ENR ENR 78.159
27-oct-17 20 78.159 ENR ENR 78.159
27-oct-17 21 78.159 ENR ENR 78.159
27-oct-17 22 76.648 ENR ENR 76.648
27-oct-17 23 76.648 ENR ENR 76.648
28-oct-17 0 76.648 ENR ENR 76.648
28-oct-17 1 76.648 ENR ENR 76.648
28-oct-17 2 76.648 ENR ENR 76.648
28-oct-17 3 76.648 ENR ENR 76.648
28-oct-17 4 76.648 ENR ENR 76.648
28-oct-17 5 76.648 ENR ENR 76.648
28-oct-17 6 76.648 ENR ENR 76.648
28-oct-17 7 76.648 ENR ENR 76.648
28-oct-17 8 76.648 ENR ENR 76.648
28-oct-17 9 76.648 ENR ENR 76.648
28-oct-17 10 76.649 LUT LUT 76.649
28-oct-17 11 76.649 LUT LUT 76.649
28-oct-17 12 78.159 ENR LUT 76.649
28-oct-17 13 78.159 ENR LUT 76.649
28-oct-17 14 78.159 ENR LUT 76.649
28-oct-17 15 78.159 ENR LUT 76.649
28-oct-17 16 78.159 ENR LUT 76.649
28-oct-17 17 78.159 ENR ENR 78.159
28-oct-17 18 78.159 ENR ENR 78.159
28-oct-17 19 78.159 ENR ENR 78.159
28-oct-17 20 78.159 ENR ENR 78.159
28-oct-17 21 78.159 ENR ENR 78.159
28-oct-17 22 76.648 ENR ENR 76.648
28-oct-17 23 76.648 ENR ENR 76.648
29-oct-17 0 76.648 ENR ENR 76.648
29-oct-17 1 76.648 ENR ENR 76.648
29-oct-17 2 76.648 ENR ENR 76.648
29-oct-17 3 76.648 ENR ENR 76.648
29-oct-17 4 76.648 ENR ENR 76.648
29-oct-17 5 76.648 ENR ENR 76.648
29-oct-17 6 76.648 ENR ENR 76.648
29-oct-17 7 76.648 ENR ENR 76.648
29-oct-17 8 76.648 ENR ENR 76.648
29-oct-17 9 76.648 ENR ENR 76.648
29-oct-17 10 76.648 ENR ENR 76.648
29-oct-17 11 76.648 ENR ENR 76.648
29-oct-17 12 76.648 ENR ENR 76.648
29-oct-17 13 76.648 ENR ENR 76.648
29-oct-17 14 76.648 ENR ENR 76.648
29-oct-17 15 76.648 ENR ENR 76.648
29-oct-17 16 76.648 ENR ENR 76.648
29-oct-17 17 78.159 ENR ENR 78.159
29-oct-17 18 78.159 ENR ENR 78.159
29-oct-17 19 78.159 ENR ENR 78.159
29-oct-17 20 78.159 ENR ENR 78.159
29-oct-17 21 76.648 ENR ENR 76.648
29-oct-17 22 76.648 ENR ENR 76.648
29-oct-17 23 76.648 ENR ENR 76.648
30-oct-17 0 76.648 ENR ENR 76.648
30-oct-17 1 76.648 ENR ENR 76.648
30-oct-17 2 76.648 ENR ENR 76.648
30-oct-17 3 76.648 ENR ENR 76.648
30-oct-17 4 76.648 ENR ENR 76.648
30-oct-17 5 76.648 ENR ENR 76.648
30-oct-17 6 76.648 ENR ENR 76.648
30-oct-17 7 76.648 ENR ENR 76.648
30-oct-17 8 76.648 ENR ENR 76.648
30-oct-17 9 76.648 ENR ENR 76.648
30-oct-17 10 76.648 ENR ENR 76.648
30-oct-17 11 78.159 ENR LUT 76.649
30-oct-17 12 78.159 ENR LUT 76.649
30-oct-17 13 78.159 ENR LUT 76.649
30-oct-17 14 78.159 ENR LUT 76.649
30-oct-17 15 78.159 ENR LUT 76.649
30-oct-17 16 78.159 ENR ENR 78.159
30-oct-17 17 94.543 ELC ELC 94.543
30-oct-17 18 94.543 ELC ELC 94.543
30-oct-17 19 94.543 ELC ELC 94.543
30-oct-17 20 94.543 ELC ELC 94.543
30-oct-17 21 78.159 ENR ENR 78.159
30-oct-17 22 76.648 ENR ENR 76.648
30-oct-17 23 76.648 ENR ENR 76.648
31-oct-17 0 76.648 ENR ENR 76.648
31-oct-17 1 76.648 ENR ENR 76.648
31-oct-17 2 76.648 ENR ENR 76.648
31-oct-17 3 76.648 ENR ENR 76.648
31-oct-17 4 76.648 ENR ENR 76.648
31-oct-17 5 76.648 ENR ENR 76.648
31-oct-17 6 76.648 ENR ENR 76.648
31-oct-17 7 76.648 ENR ENR 76.648
31-oct-17 8 76.648 ENR ENR 76.648
31-oct-17 9 76.648 ENR ENR 76.648
31-oct-17 10 76.648 ENR ENR 76.648
31-oct-17 11 78.159 ENR LUT 76.649
31-oct-17 12 78.159 ENR LUT 76.649
31-oct-17 13 78.159 ENR LUT 76.649
31-oct-17 14 78.159 ENR LUT 76.649
31-oct-17 15 78.159 ENR LUT 76.649
31-oct-17 16 78.159 ENR LUT 76.649
31-oct-17 17 94.543 ELC ELC 94.543
31-oct-17 18 94.543 ELC ELC 94.543
31-oct-17 19 94.543 ELC ELC 94.543
31-oct-17 20 78.159 ENR ENR 78.159
31-oct-17 21 78.159 ENR ENR 78.159
31-oct-17 22 76.648 ENR ENR 76.648
31-oct-17 23 76.648 ENR ENR 76.648
Valor Maximo 112.396
Valor Minimo 76.648
70
75
80
85
90
95
100
0 5 10 15 20 25
Costos Marginales Domingo
Costos MarginalesNorte Costos Marginales Sur
95
100
105
110
Costos Marginales Lunes
70
75
80
85
90
95
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Norte Costos Marginales Sur
70
75
80
85
90
95
100
105
110
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Martes
Costos Marginales Norte Costos Marginales Sur
70
75
80
85
90
95
100
105
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Miercoles
Costos Marginales Norte Costos Marginales Sur
70
75
80
85
90
95
100
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Jueves
70
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Norte Costo Marginal Sur
70
75
80
85
90
95
100
105
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Viernes
Costos Marginales Norte Costos Marginales Sur
70
75
80
85
90
95
100
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Costos Marginales Sabado
Costos Marginales Norte Costos Marginales Sur