Critical Path Analysis Presented by

Mushahid KhatriJaysinh Shukla

Nimish Doshi

Page 2: Critical path analysis11

“A project is a series of activities directed to accomplishment of a desired objective.”

Project

Plan your work first…..then work your plan

Page 3: Critical path analysis11

Each event has two important times associated with it :

Earliest time , Te , which is a calendar time when a event can occur when all the predecessor events completed at the earliest possible times

Latest time , TL , which is the latest time the event can occur without delaying the subsequent events and completion of project.

Difference between the latest time and the earliest time of an event is the slack time for that event

Activity Slack

Page 4: Critical path analysis11

Float

Negative Zero Positive

Floats

Page 5: Critical path analysis11

Node

Page 6: Critical path analysis11

Activity

Page 7: Critical path analysis11

Starting Event Completion Event

Activity

Page 8: Critical path analysis11

A

Activity A

Page 9: Critical path analysis11

A

Activity B must follow A

B

Page 10: Critical path analysis11

M.R(Mind Refreshment)

Page 11: Critical path analysis11

BLUE

Page 12: Critical path analysis11

RED

Page 13: Critical path analysis11

WHITE

Page 14: Critical path analysis11

BLACK

Page 15: Critical path analysis11

YELLOW

Page 16: Critical path analysis11

ORANGE

Page 17: Critical path analysis11

BLUE

Page 18: Critical path analysis11

RED

Page 19: Critical path analysis11

WHITE

Page 20: Critical path analysis11

BLACK

Page 21: Critical path analysis11

YELLOW

Page 22: Critical path analysis11

ORANGE

Page 23: Critical path analysis11

BLUE

Page 24: Critical path analysis11

RED

Page 25: Critical path analysis11

WHITE

Page 26: Critical path analysis11

BLACK

Page 27: Critical path analysis11

YELLOW

Page 28: Critical path analysis11

ORANGE

Page 29: Critical path analysis11

Activity

Description Predecessors

Duration (days)

A Organize sales office - 6B Hire salesmen A 4C Train salesmen B 7D Select advertising agency A 2E Plan advertising campaign D 4F Conduct advertising

campaignE 10

G Design package - 2H Setup packaging facilities G 10I Package initial stocks J,H 6J Order stock from

manufacturer- 13

K Select distributors A 9L Sell to distributors C,K 3M Ship stocks to distributors I,L 5

Example

Page 30: Critical path analysis11
Page 31: Critical path analysis11

1

4

3

2

7

8

10

5

6 9

A(6)

E(4)D(2)

F(10)

I(6)

M(5)

H(10)J(13)

G(2)

K(9)

B(4)

C(7)

L(3)

Page 32: Critical path analysis11

1

4

3

2

7

8

10

5

6 9

A(6)

E(4)D(2)

F(10)

I(6)

M(5)

H(10)J(13)

G(2)

K(9)

B(4)

C(7)

L(3)

E4=13L4=14

E1=0L1=0

E9=20L9=20

E3=2L3=4

E2=6L2=6

E5=10L5=10

E6=17L6=17

E7=8L7=11

E8=12L8=15

E10=25L10=25

Page 33: Critical path analysis11

1

4

3

2

7

8

10

5

6 9

A(6)

E(4)D(2)

F(10)

I(6)

M(5)

H(10)J(13)

G(2)

K(9)

B(4)

C(7)

L(3)

E4=13L4=14

E1=0L1=0

E9=20L9=20

E3=2L3=4

E2=6L2=6

E5=10L5=10

E6=17L6=17

E7=8L7=11

E8=12L8=15

E10=25L10=25

Page 34: Critical path analysis11

Useful at many stages of project management

Mathematically simple

Give critical path and slack time

Provide project documentation

Useful in monitoring costs

Benefits of CPM

Page 35: Critical path analysis11

Completion date?

On Schedule?

Within Budget?

Critical Activities?

How can the project be finished early at the least cost?

Questions Answered by CPM