CPM(Network analysis)

Page 2: Critical Path Method(CPM)

Network analysis

Network models can be used as an aid in scheduling large

complex projects that consist of many activities.

If the duration of each activity is known with certainty, then

the critical path method (CPM) can be used to determine the

length of time required to complete a project.

CPM also can be used to determine how long each activity in

the project can be delayed without delaying the completion

of the project.

CPM was developed in the late 1950s by researchers at

DuPont and Sperry Rand.

Page 3: Critical Path Method(CPM)

CPM and PERT

If the duration of the activities is not known with certainty, the

Program Evaluation and Review Technique (PERT) can be used

to estimate the probability that the project will be completed

by a given deadline.

PERT was developed in the late 1950s by consultants working

on the development of the Polaris missile.

CPM and PERT were given a major share of the credit for the

fact that the Polaris missile was operational two years ahead

of schedule.

Page 4: Critical Path Method(CPM)

CPM and PERT applications

CPM and PERT have been successfully used in many

applications, including:

Scheduling construction projects such as office buildings,

highways, and swimming pools.

Installing a new computer system

Designing and marketing a new product

Building a ship

Page 5: Critical Path Method(CPM)

CPM rules

project network or project diagram) can be constructed by

using the following rules:

Node 1 represents the start of the project. An arc should lead

from node 1 to represent each activity that has no

predecessors.

A node (called the finish node) representing the completion

of the project should be included in the network.

Page 6: Critical Path Method(CPM)

CPM rules

Number the nodes in the network so that the node

representing the completion of an activity always has a larger

number than the node representing the beginning of an

activity.

An activity should not be represented by more than one arc in

the network.

Two nodes can be connected by at most one arc.

Page 7: Critical Path Method(CPM)

Finding a critical path of a project

Widgetco is about to introduce a new product (product

3). One unit of product 3 is produced by assembling 1

unit of product 1 and 1 unit of product 2. Before

production begins on either product 1 or 2, raw

materials must be purchased and workers must be

trained. Before products 1 and 2 can be assembled into

product 3, the finished product 2 must be inspected. A

list of activities and their predecessors and of the

duration of each activity is given in Table 12. Draw a

project diagram for this project.

Page 8: Critical Path Method(CPM)

Finding a critical path of a project

Page 9: Critical Path Method(CPM)

Finding a critical path of a project

Page 10: Critical Path Method(CPM)

Finding a critical path of a project Computation of Early Event Time:

The early event time for node i, represented by ET(i), is the earliest time at which the

event corresponding to node i can occur.

Page 11: Critical Path Method(CPM)

Finding a critical path of a project Computation of Late Event Time:

Page 12: Critical Path Method(CPM)

Finding a critical path of a project Free Float:

Page 13: Critical Path Method(CPM)

Finding a critical path of a project Critical Path:

Critical Path: 1–2–3–4–5–6