CRONOGRAMA DE OBRA VALORIZADO
OBRA
PROPIETARIO
CONSTRUCTOR
UBICACIÓN
ITEM DESCRIPCION PRESUPUESTO
VALORIZACION
MES 1 MES 2
1.00.00 OBRAS PROVISIONALES
1.01.00 CARTEL DE OBRA TRIPLAY Y MADERA 821.58 821.58
1.02.00 ALMACEN DE OBRA 408.36 408.36
2.00.00 OBRAS PRELIMINARES
2.01.00 LIMPIEZA PRELIMINAR DE OBRA MANUAL 116.44 116.44
2.02.00 TRAZO NIVEL Y REPLANTEO PRELIMINAR 167.56 167.56
3.00.00 MOVIMIENTO DE TIERRA
3.01.00 EXCAVACION MANUAL EN ROCA SUELTA 676.83 676.83
3.02.00 RELLENO MATERIAL PROPIO MANUAL 85.88 85.88
3.03.00 ELIMINACION MATERIAL EXCEDENTE MANUAL 269.26 269.26
4.00.00 OBRAS DE CONCRETO SIMPLE
4.01.00 CONCRETO 1:10 + 30% P.G. CIMIENTO CORRIDO 9704.52 9704.52
5.00.00 OBRAS DE CONCRETO ARMADO
5.01.00 SOBRECIMIENTO REFORZADO
5.01.01 CONCRETO F'c=175 Kg/cm2 SOBRECIMIENTO 2069.21 2069.21
5.01.02 ACERO DE REFUERZO F'y=4200 Kg/cm2 2550.19 2550.19
5.01.03 ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO 1991.42 1991.42
5.02.00 COLUMNAS
5.02.01 CONCRETO F'c=175 Kg/cm2 COLUMNAS 2173.82 2173.82
5.02.02 ACERO DE REFUERZO F'y=4200 Kg/cm2 10358.84 10358.84
5.02.03 ENCOFRADO Y DESENCOFRADO COLUMNAS 2743.81 2743.81
5.03.00 VIGAS
5.03.01 CONCRETO F'c=175 Kg/cm2 VIGAS 1194.41 1194.41
5.03.02 ACERO DE REFUERZO F'y=4200 Kg/cm2 3466.65 3466.65
5.03.03 ENCOFRADO Y DESENCOFRADO VIGAS 2045.53 2045.53
6.00.00 MUROS Y TABIQUES
6.01.00 MURO LADRILLO ARCILLA KK SOGA, 2CV Mo. Co. 1:5 10749.69 10749.69
6.02.00 MURO LADRILLO ARCILLA KK SOGA, 1CV Mo. Co. 1:5 4993.56 4993.56
7.00.00 REVOQUES Y ENLUCIDOS
7.01.00 TARRAJEO Co. FROTACHADO SOBRECIMIENTO 502.98 502.98
7.02.00 TARRAJEO Co. FROTACHADO COLUMNAS 1082.98 1082.98
7.03.00 TARRAJEO Co. FROTACHADO VIGAS 835.20 835.20
8.00.00 CARPINTERIA METALICA
8.01.00 PUERTA PERFIL Fe. PLANCHA Ao. CONTRAPLACADA 4281.70 4281.70
9.00.00 PINTURA
9.01.00 PINTURA LATEX MURO EXTERIOR C/BASE IMPRIMANTE 203.19 203.19
9.02.00 PINTURA LATEX MURO INTERIOR C/BASE IMPRIMANTE 499.62 499.62
9.03.00 PINTURA LATEX CIELO RASO C/BASE IMPRIMANTE 536.33 536.33
![Page 2: Cronograma de Obra Cerco Cei Cayarani](https://reader036.vdocuments.net/reader036/viewer/2022082505/55cf8fd1550346703ba025c8/html5/thumbnails/2.jpg)
9.04.00 PINTURA ESMALTE CARPINTERIA METALICA 165.70 165.70
ITEM DESCRIPCION PRESUPUESTO
VALORIZACION
MES 1 MES 2
10.00.00 VARIOS
10.01.00 TRANSPORTE 9918.20 9918.20
10.02.00 JUNTA DE CONSTRUCCION 17.48 17.48
10.03.00 LIMPIEZA FINAL DE OBRA 265.54 265.54
COSTO DIRECTO 74896.48 59816.65 15079.83
GASTOS GENERALES VARIABLES (10 %) 7489.65 5981.67 1507.98
TOTAL PRESUPUESTO 82386.13 65798.32 16587.81