CROSSROADSCONNECTIONS

&TIGER Discretionary Grant Application

FY 2015 National Infrastructure InvestmentsThe University of Illinois at Chicago

TOTAL PROJECT COST: $29,274,091TIGER FUNDING REQUESTED: $17,223,391

MATCHING FUNDS: $12,050,700

TABLE OF CONTENTS:

PROJECT DESCRIPTION 1SUPPORTING PLANS AND ALTERNATIVES 2PROJECT LOCATION 3EXISTING TRANSPORTATION RESOURCES MAP 4SCOPE MAP 5UNIVERSITY GATEWAY 7COMMUNITY CROSSROADS 8MEDICAL DISTRICT CONNECTIONS 9HEALTH SCIENCES STUDENT SERVICES 10HOSPITAL AND HEALTH SCIENCES 11HARRISON STREET STUDENT SERVICES 12TAYLOR STREET CONNECTIONS 13ROOSEVELT ROAD CONNECTIONS 14HALSTED STREET STUDENT LIFE 15UNIVERSITY VILLAGE MARKETPLACE 16CAMPUS-WIDE IMPROVEMENTS 17PROJECT PARTIES AND GRANT FUNDS 18SELECTION CRITERIA OVERVIEW 20STATE OF GOOD REPAIR 21ECONOMIC COMPETITIVENESS 22QUALITY OF LIFE 23ACCESSIBILITY MAP 24ENVIRONMENTAL SUSTAINABILITY 25SAFETY 26INNOVATION AND PARTNERSHIP 27CONCEPTUAL PROJECT RENDERINGS 28RESULT OF BENEFIT-COST ANALYSIS 29PROJECT READINESS 30APPENDIX i-ix

Benefit-Cost Analysis iiFederal Wage Rate Certificate ix

PROJECT DESCRIPTION

Crossroads and Connections is the University of Illinois at Chicago’s investment in facilitating safe and accessible travel throughout the campus and adjacent Chicago communities. Positioned at the junction of the largest transportation network in Chicago, Crossroads and Connections will provide transformative transportation improvements to better connect neighborhoods, schools, hospitals, research centers and business districts. The initiative enhances 10 major activity hubs and the multi-modal corridors that connect the hubs. Crossroads and Connections will:

• Reinforce Safe Circulation• Enhance the Sense of Place• Connect Hubs of Activity• Integrate Campus and Community

As a public institution and one of Chicago’s biggest employers, UIC is committed to advancing Ladders of Opportunity. Users of all transportation modes will benefit from safety, environmental and acces-sibility benefits that enrich the economy and quality of life of the community. Travelers in and around the campus area will benefit from protected intersection and mid-block crossings, roadway enhance-ments, improved access to reconstructed CTA rail stations, eco-friendly parking facilities, convenient and affordable transportation options, new bicycle routes and a campus-wide wayfinding system.

Modal Improvements• Pedestrians – improvements to high-risk intersections and crossings, improved paths and side-

walks leading to transit and local destinations• Bicyclists – New bike facilities for cross-campus and city wide travel, easier access to Chicago’s

Divvy bike sharing system• Drivers – reconstructed parking facilities with eco-friendly pavements, improved security, brighter

lighting, and a new campus-wide payment system• Transit Riders – enhanced bus stops for UIC, Pace and CTA buses, and safer access to CTA Pink

and Blue rail lines• Travelers with Disabilities – Roadway crossings designed for people of all abilities, better access

to transit, and more convenient and affordable transportation options

MILLENIUMPARK

GRANTPARK

CHICAG

O RIVER

CHICAGO RIVER

LAKE MICHIGAN

HARRISON

HALSTED

ROOSEVELT

CERMAK

JACKSON

MADISON

LAKE

GRAND

CHICAGO

WESTERN

DAM

EN

ASHLAN

D

18TH ST

MICH

IGAN

AVENU

E

RACINE

MO

RGAN

LAKE SHORE D

RIVE

OGDEN

UIC

O’HARE INTERNATIONALAIRPORT

MIDWAY AIRPORT

290

94

90

DWIGHT D. EISENHOWER EXPY

KENNEDY EXPY

DOWNTOWNCHICAGO:

“THE LOOP”

MAGNIFICENTMILE

ILLINOIS MEDICAL DISTRICT

LITTLE ITALY

UNIVERSITYVILLAGEMARKETPLACE

GREEKTOWN

PILSEN

SOUTHLOOP

WESTLOOP

UKRAINIANVILLAGE

EASTGARFIELD

PARK

PRAIRIEDISTRICT

42 RESTAURANTS

30 BUSINESSES

675 DAILY EMPLOYEES

29,000 EMPLOYEES AND50,000 DAILY VISITORS

EMPLOYS 9,898 FACULTY & STAFF ANDHAS ENROLLMENT OF 27,890 STUDENTS

28 RESTAURANTS

JANE BYRNE INTERCHANGE

NAVY PIER

WILLIS TOWER

ART INSTITUTEUNITED CENTER

FBI HEADQUARTERS

UIC PAVILION

UIC FORUM

JOHN HANCOCKOBSERVATORY

FIELD MUSEUM ADLERPLANETARIUM

SOLDIER FIELD

SHEDD AQUARIUM

0m 1000m 2000m

0MILE

1.25MILE

0’ 2000’ 4000’ 6000’

1

SUPPORTING PLANS AND ALTERNATIVES

Crossroads and Connections implements UIC’s 2010 Campus Master Plan and 2015 Multimodal Transportation Plan. The proposed projects also advance the goals and objectives of these additional university and local plans.

Supporting PlansUIC Accessibility Planning GuideUIC Climate Action PlanChicago Metropolitan Agency for Planning GO TO 2040 Regional PlanSustainable Chicago 2015Chicago Streets for Cycling PlanCTA Transit Friendly Development GuideChicago Sustainable Urban Infrastructure GuideChicago Streetscape Design GuidelinesChicago Pedestrian PlanChicago Complete Streets Design Guidelines

UIC extensively researched alternative strategies to this proposal in conjunction with the development of the Multimodal Transportation Plan. The selected projects best fulfill UIC’s needs while advancing the goals of the TIGER program. The full alternatives analysis can be found in the Benefit-Cost Analy-sis. The following table summarizes the analyzed alternatives.

Table: AlternativesNo Build Low-Cost Alternative Preferred Alternative

Crosswalks & Intersec-tions

Remain in current condition with limited pedestrian safety

Repainted crosswalks Safe Crossings at all key intersections and crossings

Pedestrian & Traffic Signals

No changes to current signals – most uncoordinated

Coordinated traffic signals on priority route

Accessible signals along all key routes

Transit & Wayfinding No changes to service or facilities, minimal directional signage to major destinations and parking

Additional real-time transit screens, improvements to wayfinding network

Real-time travel informa-tion screens in key campus facilities, new bus stops, multimodal and ADA-acces-sible wayfinding network

Pedestrian Experience Plaza and gateways remain in current mix of under-de-veloped or closed conditions, deteriorated sidewalks and minimal amenities

Amenity improvements, no enhancements to capac-ity or environment, spot improvements for critically deficient sidewalks

Enhanced capacity, eco-friendly features, im-proved safety, replacement of deficient sidewalks, coor-dinated street furniture

Bicycle Network Remain in current condition with minimal connectivity

Sign the bikeways, minimal bike parking

Complete bikeways and bike parking network

Parking Facilities Resurfaced parking lots with minimal safety improvements

Resurfaced and enhanced parking lots, minimal eco-friendly re-surfacing

Reconstructed parking lots with environmental and safety improvements

2

PROJECT LOCATION

UIC is Chicago’s only research university and it is a major regional destination located three miles west of Chicago’s Downtown Loop. It is bounded by the Eisenhower Expressway (I-290) on the north and by route I-90/94 on the east, with over 150,000 vehicles accessing or traveling on these highways in the UIC area on a daily basis. Major arterial roads bisect campus (Ashland, Halsted and Roosevelt) and experience average traffic volumes of 17,000 to 44,700 vehicles per day. The university’s main campus is physically divided; with health sciences colleges on the west side and other colleges and university functions located 1/2 mile to the east. UIC shares the community with numerous other major employers and destinations. These locales are linked by an extensive multimodal transportation network.

A Popular DestinationEach day up to 100,000 people visit the university area for their jobs, health care or academics. UIC shares its campus area with bustling neighborhoods of residences, businesses and entertainment. Destinations within one mile of the area include Greektown, Little Italy, the United Center which is home to the Chicago Bulls and Blackhawks, the Jane Addams Hull House Museum, and the UIC Pavil-ion and UIC Forum, both of which house major events of up to 10,000 people.

A Solid InvestmentFederal assistance for Crossroads and Connections is an investment in Chicago’s promising neighbor-hoods. The initiative connects 10 hubs of activity with multimodal improvements that provide reliable and affordable transit options. The surrounding neighborhoods of University Village, Tri-Taylor and the Near-West Side are major employment centers providing jobs that advance Ladders of Opportunity.

Complementary ProjectsCrossroads and Connections leverages recent and ongoing investments to create a more harmonious community. The project reopens campus spaces to the community, connects UIC to adjacent business districts and facilitates use of multimodal transportation options. Specifically, Crossroads and Con-nections builds off of these projects:

Jane Byrne Interchange This ongoing four year project is rebuilding the nation’s busiest urban highway interchange. The Illinois Department of Transportation (IDOT) is also improving local roads and bridges to enhance multimodal accessibility, safety and improved travel times. Crossroads and Connections extends the benefits of the project to connecting roads and campus spaces.

CTA Rail ImprovementsChicago Transit Authority (CTA) is busy rebuilding two of its most heavily used rail stations that both serve the UIC campus. The new stations will feature better safety, improved passenger amenities and newly accessible entrances. Crossroads and Connections will improve walkways and intersections leading to the stations.

Illinois Medical DistrictThe Illinois Medical District (IMD) directly neighbors UIC. As the largest healthcare district in the nation, it houses UIC and Rush University health colleges, four hospitals including a VA Hospital, numerous clinics and a burgeoning biomedical industrial campus. The IMD has over 80,000 daily visitors who use the various nearby transportation facilities. Crossroads and Connections enhances multimodal access to these employment centers and to adjacent neighborhoods

3

ADD

AMS

PARK

FOSC

O P

ARK

LIVI

NG

STO

NFI

ELD

PAR

KAR

RIG

O P

ARK

VERN

ON

PAR

K

GAR

IBAL

DI

PARK

SHER

IDAN

PAR

K

MIL

LER

PARK

WO

OD

STR

EET

PARK

ING

STR

UCT

URE

LOT

B4

WO

OD

STR

EET

MET

ERED

LO

T

LOT

E4

LOT

E

LOT

E1

LOT

N1

LOT

F

LOT

G

LOT

M

LOT

G4

LOT

K

LOT

J

UIC METER LOT LOT

H

LOT

F4

LOT

C4

LOT L

LOT

A3

LOT

B2

LOT

A4

LOT

W5

PAU

LIN

AST

REET

PARK

ING

ST

RUCT

URE

LOT

C1

C1

LOT

OLO

T O

MA

B

LOT

18A

HA

RRIS

ON

ST.

PARK

ING

STRU

CTU

RELO

T 9

LOT

8

LOT

1BLO

T 1A

LOT

10

LOT

5

LOT

5C

LOT

6

HA

LSTE

D S

TPA

RKIN

GST

RUCT

URE

LOT

4

MA

XW

ELL

ST.

PARK

ING

STR

UCT

URE

LOT

11

LOT

14

LOT

20

LOT

12

ACT

B(F

UTU

RE C

ON

STRU

CTIO

N)

RECR

EATI

ON

FIEL

DRE

CREA

TIO

NFI

ELD

SOFT

BALL

LES

MIL

LER

FIEL

D

CURT

IS G

RAN

DER

SON

STA

DIU

M

SOCC

ER

SKYS

PACE

EARL

NEA

LPL

AZA

TEN

NIS

&BA

SKET

BALL

FLA

MES

TEN

NIS

FAC

ILIT

Y

CHIC

AGO

CIR

CLE

MEM

ORI

AL

GRO

VE

THE

QU

AD

THE PARK LIVINGSTON HEALTH WALK

ATKI

NS

GA

RDEN

COLL

EGE

OF

MED

ICIN

ECO

URT

YARD

MED

ICA

L SC

IEN

CES

COU

RTYA

RD

HA

RRIS

ON

FIE

LD

W H

ARR

ISO

N S

TREE

T

W V

ERN

ON

PA

RK P

LACE

W R

OO

SEVE

LT R

OA

D

ROCH

FORD

STR

EET

W M

AXW

ELL

STRE

ET

W L

IBER

TY S

TREE

T

W 1

4TH

PLA

CE

W P

OLK

STR

EET

S PEORIA STREET

S HALSTED STREETS HALSTED STREET

S MORGAN STREET

W C

ON

GRE

SS P

ARK

WAY

S RACINE AVENUE

S CAMPUS PARKWAY

S UNION AVENUE

S NEWBERRY AVENUE

S MORGAN STREET

S GR

EEN S

TREE

T

S TI

LDEN

STR

EET

W 1

4TH

STR

EET S EMERALD AVENUE

S BLUE ISLAND AVENUE

S THROOP STREET

W C

ON

GRE

SS P

ARK

WAY

W T

ILD

EN S

TREE

T

W 1

5TH

STR

EET

W M

AXW

ELL

STRE

ET

W G

REN

SHAW

STR

EET

W D

E KO

VEN

STR

EET

W C

ABR

INI S

TREE

T

W P

OLK

STR

EET

W L

EXIN

GTO

N S

TREE

T

W V

ERN

ON

PA

RK P

LACE

W H

ARR

ISO

N S

TREE

T

W 1

4TH

STR

EET

W 1

4TH

PLA

CE

W 1

5TH

PLA

CE

S PEORIA STREET

S SANGAMON STREET

W 1

5TH

STR

EET

W 1

4TH

PLA

CE

W 1

4TH

STR

EET

S ABERDEEN STREET

S RACINE AVENUE

W M

AXW

ELL

STRE

ET

RUBLE STREET

W W

ASH

BURN

E AV

ENU

E

W 1

4TH

STR

EET

W 1

4TH

STR

EET

S THROOP STREET

S LOOMIS STREETS LOOMIS STREET

S LOOMIS STREET

S THROOP STREET

W H

AST

ING

S ST

REET

W H

AST

ING

S ST

REET

W 1

3TH

STR

EET

W C

ON

GRE

SS P

ARK

WAY

W H

ARR

ISO

N S

TREE

T

W F

LOU

RNO

Y ST

REET

W P

OLK

STR

EET

W R

OO

SEVE

LT R

OA

D

W G

REN

SHAW

STR

EET

S W

INCH

ESTE

R AV

ENU

E

S HOYNE AVE.

S DAMEN AVENUE

S HERMITAGE AVENUE

W F

LOU

RNO

Y ST

W F

ILLM

ORE

STR

EET

S WOLCOTT AVENUE

S WOOD STREET

S PAULINA STREET

S MARSHFIELD AVENUE

S ASHLAND AVENUE

S HAMILTON AVENUE

S HOYNE AVENUE

W BOWLER STREET

S SEELEY AVENUE

W F

ILLM

ORE

STR

EET

W G

REN

SHAW

STR

EET

S LYTLE STREET

W C

ABR

INI S

TREE

T

W A

RTH

ING

TON

STR

EET

S MAY STREET

W P

OLK

STR

EET

W C

ABR

INI S

TREE

T

W L

EXIN

GTO

N S

TREE

T

W F

LOU

RNO

Y ST

REET

S LYTLE STREET

W R

OO

SEVE

LT R

OA

DW MILLER STREET

W V

AN

BU

REN

STR

EET

W TA

YLO

R ST

REET

W F

LOU

RNO

Y ST

REET

S LAFLIN STREET

S LAFLIN STREET

S JEFFERSON STREET

S CLINTON STREET

S CANAL STREET

S CLINTON STREET

S DESPLAINES STREET

S ASHLAND AVENUE

S ASHLAND AVENUE

W TA

YLO

R ST

REET

S PAULINA STREET

S PAULINA STREET

W H

ARR

ISO

N S

TREE

TW

HA

RRIS

ON

STR

EET

S WOOD STREETS WOOD STREET

W 1

4TH

PLA

CE

W 1

5TH

STR

EET

W 1

5TH

STR

EET

W 1

5TH

STR

EETW

RO

OSE

VELT

RO

AD

W R

OO

SEVE

LT R

OA

DW

RO

OSE

VELT

RO

AD

W W

ASH

BURN

E AV

ENU

E

W 1

3TH

STR

EET

W 1

4TH

PLA

CE

W 1

4TH

STR

EET

W W

ASH

BURN

E AV

ENU

E

W P

OLK

STR

EET

W P

OLK

STR

EET

W P

OLK

STR

EET

W L

EXIN

GTO

N S

TREE

T

W OGDEN AVENUE

W TA

YLO

R ST

REET

W TA

YLO

R ST

REET

W TA

YLO

R ST

REET

S LEAVITT STREET

S DAMEN AVENUES DAMEN AVENUE

S DAMEN AVENUE

W R

OO

SEVE

LT R

OA

D

W 1

4TH

STR

EET

W H

AST

ING

S ST

REET

W 1

5TH

STR

EET

W 1

4TH

PLA

CE

W G

REN

SHAW

STR

EET

S HERMITAGE AVENUE

S WOOD STREETS WOOD STREET

S HALSTED STREETS HALSTED STREET

S MORGAN STREETS MORGAN STREET

S BLUE ISLAND AVENUE

S DESPLAINES STREET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W H

ARR

ISO

N S

TREE

T

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AYD

WIG

HT

D. E

ISEN

HO

WER

EXP

RESS

WAY

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AY

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AY

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AY

DAN RYAN EXPRESSWAYDAN RYAN EXPRESSWAY

DAN RYAN EXPRESSWAY

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T C

TA S

TATI

ON

DA

MEN

AVE

.C

TA S

TATI

ON

RACI

NE

AVE.

CTA

STA

TIO

N

UIC

/HA

LSTE

DC

TA S

TATI

ON

UIC

/HA

LSTE

DC

TA S

TATI

ON

UIC

/HA

LSTE

DC

TA S

TATI

ON

78P

448

P

78P

56P

94P

249

P

78P

25P

115

P

133

P

25P

210

P1,

536

P

2,55

7P

24P

638

P

54P

70P

462

P

122

P

1,41

8P

277

P

14P

3P

4P

210

P

15P

HA

LSTE

D S

TREE

T:17

,000

-32,

100

ROO

SEVE

LT R

OA

D:

24,7

00-3

2,10

0

DA

MEN

AVE

NU

E:32

,100

-44,

700

HA

RRIS

ON

STR

EET:

9,

000-

17,0

00

ASH

LAN

D A

VEN

UE:

32,1

00-4

4,70

0

BUS

ROU

TE 5

0: 8

,426

BUS

ROU

TE 9

: 23,

831

BUS

ROU

TE 8

: 18,

470

BUS

ROU

TE 1

8: 3

,376

BUS

ROU

TE 7

: 5,7

78BU

S RO

UTE

: 60:

8,7

86

BUS

ROU

TE 1

57: 5

,827

BUS

ROU

TE 1

2: 1

2,18

2

BUS

ROU

TE 1

26: 5

,207

INTR

ACA

MPU

S: 4

64IN

TRAC

AM

PUS

WEE

KEN

D: 1

9

SEM

ESTE

R EX

PRES

S: 2

37EA

ST R

OU

TE: 2

81

PACE

BU

S: 2

62

Jess

e Br

own

VAM

edic

al C

ente

r

John

H. S

trog

er H

ospi

tal

Rush

Uni

vers

ity M

edic

al C

ente

r

UIC

-HA

LSTE

D: 4

,644

RACI

NE:

2,0

76

POLK

STR

EET

CTA

STA

TIO

N

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T: 2

,898

POLK

: 2,6

24

19.7

7

20.1

1

17.7

1

38.5

3

28.5

0

18.5

6

17.2

6

11.9

9

20.1

3 24

.61

21.1

8

20.4

1

23.2

5

25.9

6

27.8

9

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T:

80,0

00 D

AIL

Y VI

SITO

RS

9490

9490

9429

090

290

290

P

AVER

AGE

DA

ILY

CTA

“L” S

TATI

ON

EN

TRA

NCE

S (2

014)

BICY

CLE

LAN

E (2

012)

CAR

COLL

ISIO

NS

WIT

H P

EDES

TRIA

NS

(200

8-20

12)

NU

MBE

R O

F D

AIL

Y VI

SITO

RS T

O T

HE

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T

UIC

PA

RKIN

G P

ASS

ES S

OLD

AN

NU

ALL

Y (2

013)

UIC

BU

ILD

ING

S

MA

JOR

PED

ESTR

IAN

CO

NN

ECTO

RS

EXPR

ESSW

AYS

AVER

AGE

DA

ILY

TRA

FFIC

CO

UN

T (2

006)

CTA

/PAC

E BU

S AV

ERAG

E D

AIL

Y RI

DER

SHIP

(201

4)

UIC

SH

UTT

LE B

US

AVER

AGE

DA

ILY

RID

ERSH

IP (2

014)

AVER

AGE

DA

ILY

DIV

VY T

RIPS

(JU

N 2

013-

AUG

201

4)

MA

P KE

Y

UIC

| 20

15

TIG

EREx

istin

g Tr

ansp

orta

tion

Infr

astr

uctu

re

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T C

TA S

TATI

ON

DA

MEN

AVE

.EN

TRA

NCE

RACI

NE

AVE.

CTA

STA

TIO

N

PEO

RIA

ST.

ENTR

AN

CEM

ORG

AN

ST.

ENTR

AN

CE

UIC

/HA

LSTE

DC

TA S

TATI

ON

PAU

LIN

A S

T.EN

TRA

NCE

LOO

MIS

ST.

ENTR

AN

CE

EXISTING TRANSPORTATION RESOURCES MAP

4

ADDAMS PARK

FOSCO PARK

LIVINGSTONFIELD PARK

ARRIGO PARK

VERNON PARK

GARIBALDIPARK

SHERIDAN PARK

MILLERPARK

WOOD STREETPARKING STRUCTURE

LOTB4

WOOD STREETMETERED LOT

LOT E4

LOT E

LOT E1

LOT N1

LOT F

LOT G

LOT M

LOT G4

LOT K

LOT J

UIC

MET

ER L

OT

LOT H

LOT F4

LOTC4

LOT

LLOT A3

LOT B2

LOT A4

LOT W5

PAULINASTREET

PARKING STRUCTURE

LOT C1

C1

LOT OLOT O

MAB

LOT18A

HARRISON ST.PARKING

STRUCTURELOT 9

LOT 8

LOT 1B LOT 1A

LOT 10

LOT 5

LOT 5C

LOT 6

HALSTED STPARKING

STRUCTURE

LOT 4

MAXWELL ST.PARKING

STRUCTURE

LOT 11

LOT 14

LOT20

LOT 12

ACTB(FUTURE CONSTRUCTION)

RECREATIONFIELD

RECREATIONFIELD

SOFTBALL

LES MILLER FIELD

CURTIS GRANDERSONSTADIUM

SOCCER

SKYSPACE

EARL NEALPLAZA

TENNIS &BASKETBALL

FLAMES TENNIS FACILITY

CHICAGO CIRCLEMEMORIAL GROVE

THE QUAD

THE PA

RK LIVING

STON

HEA

LTH W

ALK

ATKINSGARDEN

COLLEGE OF MEDICINECOURTYARD

MEDICAL SCIENCESCOURTYARD

HARRISON FIELD

W HARRISON STREET

W VERNON PARK PLACE

W ROOSEVELT ROAD

ROCHFORD STREET

W MAXWELL STREET

W LIBERTY STREET

W 14TH PLACE

W POLK STREET

S PEORIA

STREET

S HA

LSTED STREET

S HA

LSTED STREETS M

ORG

AN

STREET

W CONGRESS PARKWAY

S RACINE AVEN

UE

S CAM

PUS PA

RKWAY

S UN

ION

AVENU

E

S N

EWBE

RRY

AVEN

UE

S MO

RGA

N STREET

S GREEN STREET

S TILDEN STREET

W 14TH STREET

S EMERA

LD AVEN

UE

S BLU

E ISL

AND AVE

NUE

S THRO

OP STREET

W CONGRESS PARKWAY

W TILDEN STREET

W 15TH STREET

W MAXWELL STREET

W GRENSHAW STREET

W DE KOVEN STREET

W CABRINI STREET

W POLK STREET

W LEXINGTON STREET

W VERNON PARK PLACE

W HARRISON STREET

W 14TH STREET

W 14TH PLACE

W 15TH PLACE

S PEORIA

STREET

S SAN

GA

MO

N STREET

W 15TH STREET

W 14TH PLACE

W 14TH STREET

S ABERD

EEN STREET

S RACINE AVEN

UE

W MAXWELL STREET

RUBLE STREET

W WASHBURNE AVENUE

W 14TH STREETW 14TH STREET

S THRO

OP STREET

S LOO

MIS STREET

S LOO

MIS STREET

S LOO

MIS STREET

S THRO

OP STREET

W HASTINGS STREETW HASTINGS STREET

W 13TH STREET

W CONGRESS PARKWAY

W HARRISON STREET

W FLOURNOY STREET

W POLK STREET

W ROOSEVELT ROAD

W GRENSHAW STREET

S WINCHESTER AVENUE

W O

GDEN AVENUE

S LEAVITT STREET

S HO

YNE AVE.

S DA

MEN

AVENU

E

S HERM

ITAGE AVEN

UE

W FLOURNOY ST

W FILLMORE STREET

S WO

LCOTT AVEN

UE

S WO

OD

STREET

S PAULIN

A STREET

S MA

RSHFIELD

AVENU

E

S ASH

LAN

D AVEN

UE

W CAMPBELL PARK DRIVE

S HA

MILTO

N AVEN

UE

S HO

YNE AVEN

UE

W BOW

LER STREET

S SEELEY AVENU

E

S LEAVITT STREET

W WASHBURNE AVENUE

W FILLMORE STREET

W GRENSHAW STREET

S LYTLE STREET

W CABRINI STREET

W ARTHINGTON STREET

S MAY STREET

W POLK STREET

W CABRINI STREET

W LEXINGTON STREET

W FLOURNOY STREET

S LYTLE STREET

W ROOSEVELT ROAD

W M

ILLER STREET

W VAN BUREN STREET

W TAYLOR STREET

W FLOURNOY STREETS LAFLIN

STREET

S LAFLIN

STREET

S JEFFERSON

STREET

S CLINTO

N STREET

S CAN

AL STREET

S CLINTO

N STREET

S DESPLA

INES STREET

S ASH

LAN

D AVEN

UE

S ASH

LAN

D AVEN

UE

W TAYLOR STREET

S PAULIN

A STREET

S PAULIN

A STREET

W HARRISON STREETW HARRISON STREET

S WO

OD

STREETS W

OO

D STREET

W 14TH PLACE

W 15TH STREETW 15TH STREET W 15TH STREET

W ROOSEVELT ROADW ROOSEVELT ROAD

W ROOSEVELT ROAD

W ROOSEVELT ROAD

W WASHBURNE AVENUE

W 13TH STREET

W 14TH PLACE

W 14TH STREET

W WASHBURNE AVENUE

W POLK STREETW POLK STREET

W POLK STREET

W LEXINGTON STREET

W O

GDEN AVENUE

W TAYLOR STREET

W TAYLOR STREETW TAYLOR STREET

S LEAVITT STREET

S DA

MEN

AVENU

ES D

AM

EN AVEN

UE

S DA

MEN

AVENU

EW ROOSEVELT ROAD

W 14TH STREET

W HASTINGS STREET

W 15TH STREET

W 14TH PLACE

W GRENSHAW STREET

S HERM

ITAGE AVEN

UE

S WO

OD

STREETS W

OO

D STREET

S HA

LSTED STREET

S HA

LSTED STREET

S MO

RGA

N STREET

S MO

RGA

N STREET

S BLU

E ISL

AND AVE

NUE

S DESPLA

INES STREET

W VAN BUREN STREETW VAN BUREN STREET

W VAN BUREN STREETW VAN BUREN STREET

W VAN BUREN STREET

W HARRISON STREET

DWIGHT D. EISENHOWER EXPRESSWAY DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

DA

N RYA

N EXPRESSW

AYD

AN

RYAN

EXPRESSWAY

DA

N RYA

N EXPRESSW

AY

ILLINOIS MEDICAL DISTRICT

CTA STATIONDAMEN AVE.CTA STATION

RACINE AVE.CTA STATION

UIC/HALSTEDCTA STATION

UIC/HALSTEDCTA STATION

UIC/HALSTEDCTA STATION

Jesse Brown VAMedical Center

John H. Stroger Hospital

Rush University Medical Center

TO CANAL ST.

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

4627

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CDOT PROPOSED BICYCLE LANE (2012)

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)

MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total)

MAJOR UNIVERSITY GATEWAY ENTRANCES

UIC BUILDINGSTIGER PROPOSED BIKE LANES

UIC | 2015TIGER Scope Map | Overview

ILLINOIS MEDICAL DISTRICT

CTA STATIONDAMEN AVE.ENTRANCE

RACINE AVE.CTA STATION

PEORIA ST.ENTRANCE

MORGAN ST.ENTRANCE

UIC/HALSTEDCTA STATION

PAULINA ST.ENTRANCE

LOOMIS ST.ENTRANCE

POLK STREETCTA STATION

HEALTH SCIENCESSTUDENT SERVICES

7 COLLISIONS

MEDICAL DISTRICTCONNECTIONS

49 COLLISIONS

HARRISON STREETSTUDENT SERVICES

7 COLLISIONS

HALSTED STREETSTUDENT LIFE

11 COLLISIONS

UNIVERSITY VILLAGEMARKET PLACE

10 COLLISIONS

HOSPITAL & HEALTH SCIENCES

31 COLLISIONS

TAYLOR STREETCONNECTIONS

42 COLLISIONS

COMMUNITYCROSSROADS

ROOSEVELT ROADCONNECTIONS

85 COLLISIONS

UNIVERSITYGATEWAY4 COLLISIONS

UNIVERSITY GATEWAY

COMMUNITYPLAZA

GATEWAY

CITYGATEWAY

HEALTHSCIENCESGATEWAY

290

90

90 94

94

290

SCOPE MAP

5

ADDAMS PARK

FOSCO PARK

LIVINGSTONFIELD PARK

ARRIGO PARK

VERNON PARK

GARIBALDIPARK

SHERIDAN PARK

MILLERPARK

WOOD STREETPARKING STRUCTURE

LOTB4

WOOD STREETMETERED LOT

LOT E4

LOT E

LOT E1

LOT N1

LOT F

LOT G

LOT M

LOT G4

LOT K

LOT J

UIC

MET

ER L

OT

LOT H

LOT F4

LOTC4

LOT

LLOT A3

LOT B2

LOT A4

LOT W5

PAULINASTREET

PARKING STRUCTURE

LOT C1

C1

LOT OLOT O

MAB

LOT18A

HARRISON ST.PARKING

STRUCTURELOT 9

LOT 8

LOT 1B LOT 1A

LOT 10

LOT 5

LOT 5C

LOT 6

HALSTED STPARKING

STRUCTURE

LOT 4

MAXWELL ST.PARKING

STRUCTURE

LOT 11

LOT 14

LOT20

LOT 12

ACTB(FUTURE CONSTRUCTION)

RECREATIONFIELD

RECREATIONFIELD

SOFTBALL

LES MILLER FIELD

CURTIS GRANDERSONSTADIUM

SOCCER

SKYSPACE

EARL NEALPLAZA

TENNIS &BASKETBALL

FLAMES TENNIS FACILITY

CHICAGO CIRCLEMEMORIAL GROVE

THE QUAD

THE PA

RK LIVING

STON

HEA

LTH W

ALK

ATKINSGARDEN

COLLEGE OF MEDICINECOURTYARD

MEDICAL SCIENCESCOURTYARD

HARRISON FIELD

W HARRISON STREET

W VERNON PARK PLACE

W ROOSEVELT ROAD

ROCHFORD STREET

W MAXWELL STREET

W LIBERTY STREET

W 14TH PLACE

W POLK STREET

S PEORIA

STREET

S HA

LSTED STREET

S HA

LSTED STREETS M

ORG

AN

STREET

W CONGRESS PARKWAY

S RACINE AVEN

UE

S CAM

PUS PA

RKWAY

S UN

ION

AVENU

E

S N

EWBE

RRY

AVEN

UE

S MO

RGA

N STREET

S GREEN STREET

S TILDEN STREET

W 14TH STREET

S EMERA

LD AVEN

UE

S BLU

E ISL

AND AVE

NUE

S THRO

OP STREET

W CONGRESS PARKWAY

W TILDEN STREET

W 15TH STREET

W MAXWELL STREET

W GRENSHAW STREET

W DE KOVEN STREET

W CABRINI STREET

W POLK STREET

W LEXINGTON STREET

W VERNON PARK PLACE

W HARRISON STREET

W 14TH STREET

W 14TH PLACE

W 15TH PLACE

S PEORIA

STREET

S SAN

GA

MO

N STREET

W 15TH STREET

W 14TH PLACE

W 14TH STREET

S ABERD

EEN STREET

S RACINE AVEN

UE

W MAXWELL STREET

RUBLE STREET

W WASHBURNE AVENUE

W 14TH STREETW 14TH STREET

S THRO

OP STREET

S LOO

MIS STREET

S LOO

MIS STREET

S LOO

MIS STREET

S THRO

OP STREET

W HASTINGS STREETW HASTINGS STREET

W 13TH STREET

W CONGRESS PARKWAY

W HARRISON STREET

W FLOURNOY STREET

W POLK STREET

W ROOSEVELT ROAD

W GRENSHAW STREET

S WINCHESTER AVENUE

W O

GDEN AVENUE

S LEAVITT STREET

S HO

YNE AVE.

S DA

MEN

AVENU

E

S HERM

ITAGE AVEN

UE

W FLOURNOY ST

W FILLMORE STREET

S WO

LCOTT AVEN

UE

S WO

OD

STREET

S PAULIN

A STREET

S MA

RSHFIELD

AVENU

E

S ASH

LAN

D AVEN

UE

W CAMPBELL PARK DRIVE

S HA

MILTO

N AVEN

UE

S HO

YNE AVEN

UE

W BOW

LER STREET

S SEELEY AVENU

E

S LEAVITT STREET

W WASHBURNE AVENUE

W FILLMORE STREET

W GRENSHAW STREET

S LYTLE STREET

W CABRINI STREET

W ARTHINGTON STREET

S MAY STREET

W POLK STREET

W CABRINI STREET

W LEXINGTON STREET

W FLOURNOY STREET

S LYTLE STREET

W ROOSEVELT ROAD

W M

ILLER STREET

W VAN BUREN STREET

W TAYLOR STREET

W FLOURNOY STREETS LAFLIN

STREET

S LAFLIN

STREET

S JEFFERSON

STREET

S CLINTO

N STREET

S CAN

AL STREET

S CLINTO

N STREET

S DESPLA

INES STREET

S ASH

LAN

D AVEN

UE

S ASH

LAN

D AVEN

UE

W TAYLOR STREET

S PAULIN

A STREET

S PAULIN

A STREET

W HARRISON STREETW HARRISON STREET

S WO

OD

STREETS W

OO

D STREET

W 14TH PLACE

W 15TH STREETW 15TH STREET W 15TH STREET

W ROOSEVELT ROADW ROOSEVELT ROAD

W ROOSEVELT ROAD

W ROOSEVELT ROAD

W WASHBURNE AVENUE

W 13TH STREET

W 14TH PLACE

W 14TH STREET

W WASHBURNE AVENUE

W POLK STREETW POLK STREET

W POLK STREET

W LEXINGTON STREET

W O

GDEN AVENUE

W TAYLOR STREET

W TAYLOR STREETW TAYLOR STREET

S LEAVITT STREET

S DA

MEN

AVENU

ES D

AM

EN AVEN

UE

S DA

MEN

AVENU

E

W ROOSEVELT ROAD

W 14TH STREET

W HASTINGS STREET

W 15TH STREET

W 14TH PLACE

W GRENSHAW STREET

S HERM

ITAGE AVEN

UE

S WO

OD

STREETS W

OO

D STREET

S HA

LSTED STREET

S HA

LSTED STREET

S MO

RGA

N STREET

S MO

RGA

N STREET

S BLU

E ISL

AND AVE

NUE

S DESPLA

INES STREET

W VAN BUREN STREETW VAN BUREN STREET

W VAN BUREN STREETW VAN BUREN STREET

W VAN BUREN STREET

W HARRISON STREET

DWIGHT D. EISENHOWER EXPRESSWAY DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

DA

N RYA

N EXPRESSW

AYD

AN

RYAN

EXPRESSWAY

DA

N RYA

N EXPRESSW

AY

ILLINOIS MEDICAL DISTRICT

CTA STATIONDAMEN AVE.CTA STATION

RACINE AVE.CTA STATION

UIC/HALSTEDCTA STATION

UIC/HALSTEDCTA STATION

UIC/HALSTEDCTA STATION

Jesse Brown VAMedical Center

John H. Stroger Hospital

Rush University Medical Center

TO CANAL ST.

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

4627

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CDOT PROPOSED BICYCLE LANE (2012)

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)

MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total)

MAJOR UNIVERSITY GATEWAY ENTRANCES

UIC BUILDINGSTIGER PROPOSED BIKE LANES

UIC | 2015TIGER Scope Map | Overview

ILLINOIS MEDICAL DISTRICT

CTA STATIONDAMEN AVE.ENTRANCE

RACINE AVE.CTA STATION

PEORIA ST.ENTRANCE

MORGAN ST.ENTRANCE

UIC/HALSTEDCTA STATION

PAULINA ST.ENTRANCE

LOOMIS ST.ENTRANCE

POLK STREETCTA STATION

HEALTH SCIENCESSTUDENT SERVICES

7 COLLISIONS

MEDICAL DISTRICTCONNECTIONS

49 COLLISIONS

HARRISON STREETSTUDENT SERVICES

7 COLLISIONS

HALSTED STREETSTUDENT LIFE

11 COLLISIONS

UNIVERSITY VILLAGEMARKET PLACE

10 COLLISIONS

HOSPITAL & HEALTH SCIENCES

31 COLLISIONS

TAYLOR STREETCONNECTIONS

42 COLLISIONS

COMMUNITYCROSSROADS

ROOSEVELT ROADCONNECTIONS

85 COLLISIONS

UNIVERSITYGATEWAY4 COLLISIONS

UNIVERSITY GATEWAY

COMMUNITYPLAZA

GATEWAY

CITYGATEWAY

HEALTHSCIENCESGATEWAY

290

90

90 94

94

290

6

UNIVERSITY GATEWAY

Location: Peoria Street between Van Buren Street and Vernon Park Place

Summary:Currently, the Illinois Department of Transportation is engaged in the Jane Byrne Interchange project to improve traffic flow in the crossing of the Kennedy Expressway/Dan Ryan Expressway (I-90/I-94), Congress Parkway and Eisenhower Expressway (I-290). These roads form the eastern and northern edges of the UIC campus. Simultaneously, several local bridges and intersections are being rebuilt. UIC will leverage these projects to Integrate Campus and Community.

The University Gateway will serve as an open connection between the campus and adjacent neigh-borhoods such as Greektown and West Loop. This plaza will reclaim a former electrical substation site for public use in an eco-friendly environment with permeable pavers and natural plantings. University Gateway is an important connection to Chicago’s rapid transit and cross-town bikeway networks.

Conflict:There have been four pedestrian-vehicle crashes within the small boundaries of the project hub due to heavy pedestrian traffic, narrow roadways and inadequate crossings. Persons with disabilities are bur-dened by the lack of accessible crossings and cyclists have only limited campus access from Harrison Street.

Planned Improvements:• Deconstruction of existing facility• Development of eco-friendly gateway• Accessible crossing to access rail station and adjoining neighborhoods• New wayfinding system • Improved pedestrian experience with more seating, trash receptacles and landscaping• Reconstructed parking facilities with new eco-friendly pavements, improved safety and faster exit

lanes

LOT 9

LOT 8

TENNIS &BASKETBALL

HARRISON FIELD

S PEORIA

STREET

S HA

LSTED STREET

S GREEN STREET

W VAN BUREN STREETW VAN BUREN STREET

W HARRISON STREET

UIC/HALSTEDCTA STATION

UIC/HALSTEDCTA STATIONPEORIA ST.

ENTRANCE

UIC/HALSTEDCTA STATION

UNIVERSITYGATEWAY4 COLLISIONS

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

7

COMMUNITY CROSSROADS

Location: Morgan Street from Taylor Street to Vernon Park Place and west on Vernon Park Place to Racine Avenue

Summary:UIC’s east and west sides of campus are separated by the residential and commercial Little Italy neigh-borhood. Utilizing Chicago’s grid system, UIC proposes to establish better connections between its two sides of campus for those of all transportation needs and abilities.

Community Crossroads repurposes existing space to facilitate multimodal transportation. Commu-nity Crossroads radiates out from a plaza formed from two cul-de-sac streets that will be ideal for pedestrians and bicyclists.

Community Crossroads will encourage healthy, active transportation for travel to Little Italy and be-tween UIC’s east and west campuses. The project will facilitate State of Good Repair, revive a Sense of Place, and Enhance the Pedestrian Experience.

Conflict:Obstructed and confusing pedestrian pathways intersect with two vehicle cul-de-sacs and a loading dock access street that services the Richard J. Daley Library. This creates an unsafe pedestrian envi-ronment connecting the library with the largest classroom building on campus.

Planned Improvements:• New curb cuts to allow wheelchair and bicycle access between plazas, sidewalks and roadways• Modified cul-de-sacs to separate pedestrians from vehicles and retain residential driveway access• New bicycle route• Sidewalk replacement along Morgan Street with new tactile strips• Customized street furniture including seating and bike parking• Spot improvements to sidewalk on Polk Street leading to an existing “pocket park”• New wayfinding system

VERNON PARK

SHERIDAN PARK

MILLERPARK

LOT 1B LOT 1A

CHICAGO CIRCLEMEMORIAL GROVE

W VERNON PARK PLACES RACIN

E AVENU

E

W CABRINI STREET

W ARTHINGTON STREET

W POLK STREET

W CABRINI STREET W M

ILLER STREET

COMMUNITYCROSSROADS

COMMUNITYPLAZA

GATEWAY

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

8

MEDICAL DISTRICT CONNECTIONS

Location: Damen Avenue between Van Buren Street and Ogden Avenue, Harrison Street between Damen Avenue and Ashland Avenue

Summary:Medical District Connections links UIC’s health science colleges with city and regional transit sys-tems. Centered on the Illinois Medical District rail station, the improvements enhance safety and ac-cessibility for multimodal travel. The IMD Blue Line station is currently undergoing a reconstruction to enhance its capacity and accessibility. The IMD station is also a key stop on the Pace Route 755 which is one of the Chicago area’s innovative express bus routes operating on the shoulder of I-55.

The IMD has the nation’s densest concentration of specialized healthcare centers for people with dis-abilities (see Accessibility map in the Quality of Life section). Medical District Connections projects will ensure that intersections are Safe Crossings that are accessible for pedestrians of all abilities.

Conflict:Damen Street is particularly challenging for pedestrians because of its dangerous and unclear inter-sections. The eastern portion of the hub is also challenging due to vehicles travelling from I-290 and to Rush University Medical Center. Transit riders exiting the IMD Station are faced with narrow crosswalks and poorly timed crossing signals. These conditions caused 49 vehicle collisions with pedestrians and bicyclists between 2008-2012. One of these crashes resulted in a pedestrian death.

Planned Improvements:• Accessible crossings including high-visibility crosswalks, customized paving, tactile pads, Leading

Pedestrian Intervals, and countdown signals with audible features• Bus stops relocated for better reliability• New bus shelters with seating and shelters• Coordinated traffic signal timing on popular bus routes• New wayfinding system

LOT N1

W CONGRESS PARKWAY

W HARRISON STREET

W FLOURNOY STREETS WINCHESTER AVENUE

W O

GDEN AVENUE

S HO

YNE AVE.

S HERM

ITAGE AVEN

UE

W FLOURNOY ST

W VAN BUREN STREET

S ASH

LAN

D AVEN

UE

W HARRISON STREET

S DA

MEN

AVENU

E S WO

OD

STREET

W VAN BUREN STREET

DWIGHT D. EISENHOWER EXPRESSWAY

DWIGHT D. EISENHOWER EXPRESSWAY

ILLINOIS MEDICAL DISTRICT

CTA STATIONDAMEN AVE.CTA STATION

John H. Stroger Hospital

Rush University Medical Center

ILLINOIS MEDICAL DISTRICT

CTA STATIONDAMEN AVE.ENTRANCE

PAULINA ST.ENTRANCE

MEDICAL DISTRICTCONNECTIONS

49 COLLISIONS 290

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

9

HEALTH SCIENCES STUDENT SERVICES

Location: Damen Avenue to Ashland Avenue, and Polk Street to Grenshaw Street

Summary:Health Sciences Student Services is the center of campus life for UIC’s West Side and the adjoining institutions in the Illinois Medical District. The planned improvements will enhance the Sense of Place, facilitate Safe Crossings, and improve accessibility for the more than 80,000 daily visitors to this dense concentration of healthcare institutions. Place making projects include plazas and customized paving while multimodal improvements include next-generation bikeways, Safe Crossings, and up-graded facilities to a State of Good Repair.

Conflict:This busy pedestrian zone includes multiple unprotected mid-block crossings and intersections lacking accessibility features. Signal timings are uncoordinated, often leaving pedestrians stranded in the middle of the intersection. The Arthington Mall Plaza, which connects UIC’s veteran students with the Jesse Brown VA Medical Center, is currently closed due to dangerous walking conditions. Parking facilities are heavily used and deteriorating. Minimal facilities in the area are accessible to people with disabilities.

Planned Improvements:• Intersection safety and accessibility improvements including customized paving, high-visibility

crosswalks and lighting• Pedestrian countdown signals with audible features • Rebuilt Arthington Mall Plaza with eco-friendly surface, enhanced accessibility and new pedestrian

amenities, landscaping and lighting• New wayfinding system • Dedicated bike facility through Illinois Medical District and continuing into Tri-Taylor neighborhood• New bus shelters• Digital screens for transit tracker at key locations• Rebuilt parking facilities with new eco-friendly pavements, improved safety and faster exit lanes

LOTB4

LOTC4

LOT A3

LOT B2

LOT A4

LOT W5

LOT C1

W POLK STREET

W GRENSHAW STREET

W O

GDEN AVENUE

S HO

YNE AVE.

S DA

MEN

AVENU

E

S WO

LCOTT AVEN

UE

S HO

YNE AVEN

UE

S SEELEY AVENU

E

W TAYLOR STREET

S DA

MEN

AVENU

E

W GRENSHAW STREET

Jesse Brown VAMedical Center

HEALTH SCIENCESSTUDENT SERVICES

7 COLLISIONS

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

10

HOSPITAL AND HEALTH SCIENCES

Location: Wolcott Avenue to Ashland Avenue, and Polk Street to Taylor Street

Summary:Hospital and Health Sciences houses UIC’s health sciences colleges. Also located nearby are four hospitals, Northern Illinois headquarters for the FBI, and Chicago’s juvenile courts and detention fa-cilities. The planned improvements will facilitate access around these major employers and neighbor-hood businesses.

This hub of activity is unique in its extreme density of workers and students. The improvements will re-spond to the needs of both of these groups whose schedules and commuting patterns differ. The hos-pitals and clinics generate a large number of motorists who occupy about 80% of the area’s parking capacity. To facilitate State of Good Repair, several of these lots will be rebuilt with eco-friendly pave-ments, better safety, and brighter lighting. Intersection and sidewalk improvements will ease access to the busy CTA Polk Pink Line rail station which welcomes over 2,500 users daily. The area is also served by multiple CTA bus routes and Pace Express Route 755. New bikeways will promote cross-campus travel and promote use of Chicago’s existing bike share system: Divvy.

Conflict:The landscape surrounding these high-density facilities lacks inviting and comfortable places for people to walk through and relax in. Parking and building entrances with mid-block locations encour-age dangerous pedestrian crossings. Many pedestrians commuting between UIC’s academic facilities and the Tri-Taylor neighborhood must cross Ashland Avenue. Ashland Avenue is a major arterial road with average daily traffic of 44,000 vehicles. The poorly marked crossings and wide intersection cause a dangerous zone for pedestrians and bicyclists to travel through. High volume roads, high pedestri-an traffic and outworn crossings led to 31 vehicle collisions with pedestrians and bicyclists between 2008 and 2012.

Planned Improvements:• Intersection safety and accessibility enhancements including high-visibility crosswalks, curb bump

outs, widened crosswalks, customized paving, Leading Pedestrian Intervals, and brighter lighting• Restriped lanes to provide center turning lane and shortened pedestrian crossing• Rebuilt parking facilities with new eco-friendly pavements, improved safety and faster exit lanes • Strategic mid-block crossings to facilitate access between major destinations and along in-

ner-block pathways• New bike facilities connecting Hospital and Health Sciences to UIC’s east side• New and reconstructed sidewalks• Bus stops relocated for better reliability• New wayfinding system

WOOD STREETPARKING STRUCTURE

LOTB4

WOOD STREETMETERED LOT

LOT E4

LOT E

LOT E1

LOT F

LOT G

LOT G4

LOT K

LOT J

UIC

MET

ER L

OT

LOT H

LOT F4

LOTC4

LOT

L

LOT B2

PAULINASTREET

PARKING STRUCTURE

LOT C1

C1

MAB

THE PA

RK LIVING

STON

HEA

LTH W

ALK

ATKINSGARDEN

COLLEGE OF MEDICINECOURTYARD

MEDICAL SCIENCESCOURTYARD

W POLK STREET

W GRENSHAW STREET

S HERM

ITAGE AVEN

UE

W FILLMORE STREET

S WO

LCOTT AVEN

UE

S WO

OD

STREET

S PAULIN

A STREET

S MA

RSHFIELD

AVENU

E

S ASH

LAN

D AVEN

UE

W FILLMORE STREET

W ROOSEVELT ROAD

W TAYLOR STREET

S PAULIN

A STREET

S WO

OD

STREET

W POLK STREETW POLK STREET

S HERM

ITAGE AVEN

UE

POLK STREETCTA STATION

HOSPITAL & HEALTH SCIENCES

31 COLLISIONS

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

11

HARRISON STREET STUDENT SERVICES

Location: Harrison Street between Morgan Street and Racine Avenue

Summary:Harrison Street connects UIC’s east side to Chicago’s major commuter rail stations and downtown Loop. Harrison Street separates UIC from the I-290 Eisenhower Expressway and the CTA Blue Line tracks. Immediately to the north is the booming West Loop neighborhood, the Chicago Police Educa-tion and Training Division, and the United Center. Harrison Street will benefit from improvements to better Integrate Campus and Community.

Within this area is the UIC Pavilion: the campus basketball arena and event facility which attracts up to 10,000 visitors per event, as well as the UIC Theatre and School of Music. The largest UIC classroom building and the Student Services Building are located nearby on Harrison Street. Improved multi-modal conditions will facilitate safer access to these destinations and many more areas on and around campus

Conflict:The primary obstacles to safe travel in this corridor are busy crossings exacerbated by the many turning vehicles accessing UIC’s main parking facilities that border I-290. Upgraded sidewalks, intersections and crossings will increase pedestrian safety and access to transit. Rebuilt eco-friendly parking lots will improve environmental conditions, safety and accessibility.

Planned Improvements:• Gateway at crossing between UIC campus and West Loop neighborhood• Intersection safety enhancements including high-visibility crosswalks, flashing crosswalk warn-

ing signs, customized paving, Leading Pedestrian Intervals, and countdown timers with audible features

• New traffic signal to facilitate safer turns for vehicles• Consolidated mid-block crossing• Relocated and upgraded bus stops (for CTA, Pace, and university buses)• In-pavement lighting at busy crossings • Improved access to UIC-Halsted and Racine CTA Blue Line stations• New wayfinding system• Rebuilt parking facilities with new eco-friendly pavements, improved safety and faster exit lanes

LOT18A

HARRISON ST.PARKING

STRUCTURELOT 9

LOT 1B LOT 1A

LOT 11

W HARRISON STREET

W CONGRESS PARKWAY

S MO

RGA

N STREET

S TILDEN STREETS TH

ROO

P STREET

W HARRISON STREETW HARRISON STREET

DWIGHT D. EISENHOWER EXPRESSWAY

RACINE AVE.CTA STATION

UIC/HALSTEDCTA STATION

RACINE AVE.CTA STATION

MORGAN ST.ENTRANCE

HARRISON STREETSTUDENT SERVICES

7 COLLISIONS

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

12

TAYLOR STREET CONNECTIONS

Location: Taylor Street between Ashland Avenue and Halsted Street

Summary:Taylor Street, the east and west campus connecting path, is the heart of the thriving Tri-Taylor neigh-borhood that is also home to Chicago’s Little Italy. At the eastern edge of this area is the new Chicago Circle Memorial Grove and at the west campus border, the proposed Health Sciences Gateway.

Taylor Street Connections is one element in UIC’s commitment to advancing Ladders of Opportunity. The projects Integrate Campus and Community to spark neighborhood revitalization, which builds economic opportunity for small, locally owned businesses.

Taylor Street Connections will rehabilitate and improve key intersections to create Safe Crossings and improve the State of Good Repair. The improvements will also benefit the university bus system and a popular CTA bus route connecting the campus to commuter rail, Chicago’s downtown Loop, and Magnificent Mile business centers. UIC proposes to improve bicycle transportation on Taylor Street to facilitate travel to eastern neighborhoods including Chicago’s downtown Loop.

Conflict: Tri-Taylor benefits from an urban environment which welcomes visitors and encourages pedestrian traffic. However, critical crossings are dangerous and in need of vital improvement and bicycle infra-structure is limited to a faded bike lane. Run-down bicycle paths and intersection crossings contribut-ed to the 42 vehicle collisions with pedestrians and bicyclists from 2008 to 2012.

Planned Improvements:• Gateway at crossing between UIC campus and Tri-Taylor neighborhood• Intersection safety enhancements including high-visibility crosswalks, customized pavement, and

pedestrian countdown timers with audible crossing features• Rebuilt sidewalk adjacent to Chicago Circle Memorial Grove • New bus shelters• Bus stops relocated for better reliability• A consolidated mid-block crossing with customized paving and a HAWK signal to serve the sci-

ence buildings • Advanced pedestrian crossing signs in high pedestrian traffic areas• Upgraded bike lane with weather-resistant markings in business area, protected bike lane continu-

ing east to Chicago’s downtown• Coordinated traffic signal timings on popular bus route• New wayfinding system

VERNON PARK

MILLERPARK

LOT G

LOT K

LOT 10

LOT 5 LOT 6

HALSTED STPARKING

STRUCTURE

LOT20

ACTB

CHICAGO CIRCLEMEMORIAL GROVE

S RACINE AVEN

UE

S BLU

E ISL

AND AVE

NUE W GRENSHAW STREET

W DE KOVEN STREETS THRO

OP STREET

S LOO

MIS STREET

S ASH

LAN

D AVEN

UE

W FILLMORE STREET

S LYTLE STREET

W ARTHINGTON STREET

S MAY STREET

W M

ILLER STREET

W TAYLOR STREET

S CLINTO

N STREET

W TAYLOR STREET W TAYLOR STREETW TAYLOR STREET

S HA

LSTED STREET

S MO

RGA

N STREET

S DESPLA

INES STREET

DA

N RYA

N EXPRESSW

AY

TO CANAL ST.TAYLOR STREETCONNECTIONS

42 COLLISIONS

HEALTHSCIENCESGATEWAY

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

13

ROOSEVELT ROAD CONNECTIONS

Location: Roosevelt Road between Damen Avenue and Clinton Street

Summary:Roosevelt Road is a state road (IL 38) that extends from Lake Michigan to the western suburbs. At UIC’s eastern edge, Roosevelt Road separates the east campus from the athletic facilities. Safe Crossings along Roosevelt Road will provide better access to the new Curtis Granderson Stadium and adjacent fields. Continuing west, the roadway serves as the southern edge of the campus and Illinois Medical District. Improvements in this area will enhance pedestrian and transit rider access from Roosevelt Road into UIC’s campus. As Roosevelt Road is an important employee access strip, improving this roadway will advance Ladders of Opportunity.

Conflict:In the UIC area, Roosevelt Road is a busy roadway with a popular CTA bus route providing late night connections to CTA rail and Metra commuter rail. Roosevelt Road is designed primarily for cars, trucks and transit vehicles with little pedestrian priority, which leads to the highest number of vehicle-pedes-trian crashes in the area. The intersections of Roosevelt Road with connecting arterials are particularly dangerous. From 2008 to 2012, there were 85 vehicle collisions with pedestrians and bicyclists. One of these crashes resulted in a pedestrian fatality.

Planned Improvements:• Intersection safety and accessibility enhancements including high-visibility crosswalks, custom-

ized pavement, pedestrian countdown timers with audible crossings, and Leading Pedestrian Intervals

• Consolidation of mid-block crossings• In-pavement lighting, overhead flashing pedestrian crosswalk warning signs, or Rapid Rectangular

Flashing Beacons• Coordinated traffic signal timing to improve bus travel times and reliability• Bus stops relocated for better reliability• Lighting improvements within parking structure• New wayfinding system

WOOD STREETPARKING STRUCTURE

LOTB4

WOOD STREETMETERED LOT

LOT E4

LOT M

LOT G4

LOT K

UIC

MET

ER L

OT

LOT H

LOT F4

LOTC4

LOT OLOT O

LOT 5

LOT 5C

LOT 6

LOT 14

ACTB(FUTURE CONSTRUCTION)

LES MILLER FIELD

CURTIS GRANDERSONSTADIUM

SKYSPACE

EARL NEALPLAZA

W ROOSEVELT ROAD

ROCHFORD STREET

S HA

LSTED STREETS M

ORG

AN

STREET

S UN

ION

AVENU

E

S N

EWBE

RRY

AVEN

UE

S BLU

E ISL

AND AVE

NUE W GRENSHAW STREET

RUBLE STREET

W WASHBURNE AVENUE

S THRO

OP STREET

S LOO

MIS STREET

W ROOSEVELT ROAD

W GRENSHAW STREET

W FILLMORE STREET

S SEELEY AVENU

E

W FILLMORE STREET

W GRENSHAW STREET

S LYTLE STREET

S MAY STREET

W ROOSEVELT ROAD S JEFFERSON

STREET

S CLINTO

N STREET

S PAULIN

A STREET

S PAULIN

A STREET

S WO

OD

STREET

W ROOSEVELT ROADW ROOSEVELT ROAD

W ROOSEVELT ROAD

W WASHBURNE AVENUE

W WASHBURNE AVENUE

S DA

MEN

AVENU

E W ROOSEVELT ROAD

S HERM

ITAGE AVEN

UE

S HA

LSTED STREET

S MO

RGA

N STREET

S DESPLA

INES STREET

DA

N RYA

N EXPRESSW

AYROOSEVELT ROADCONNECTIONS

85 COLLISIONS

CITYGATEWAY

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

14

HALSTED STREET STUDENT LIFE

Location: Halsted Street between Harrison Street and Taylor Street

Summary:UIC’s main residential and student life facilities are situated along Halsted Street. These include dormitories, one of the two student centers, indoor and outdoor recreation facilities, parking, and the Jane Addams Hull House Museum. Halsted Street is a busy road with travel to Greektown, multiple bus routes, and access to UIC’s south campus.

Halsted Street Student Life projects are focused on Safe Crossings to facilitate access to these pop-ular destinations. Strategically located crossings will shorten travel times, improve pedestrian visibility, and ease access to bus stops.

Conflict:UIC facilities are located on both the east and west sides of Halsted Street which is connected only by grade level crossings. This populated passageway sees 25,000 – 32,000 vehicles per day; many of them travelling at high speeds especially during evening hours. Pedestrians travelling across Halsted Street may use unprotected crossings to reach campus destinations along the roadway, which caused 11 collisions from 2008 to 2012.

Planned Improvements:• Consolidated mid-block crossings• Intersection safety and accessibility improvements including customized paving, high-visibility

crosswalks and lighting• Safe Crossings to Student Recreation Facility, recreation fields and parking facillities• In-pavement lighting, overhead pedestrian crossing signs, or use of Rapid Rectangular Flashing

Beacons• Removal of a portion of existing median to allow for new crossing• Install HAWK signal• Bus stops relocated for better reliability• Digital screens for transit tracker at key locations• New wayfinding system

HALSTED STPARKING

STRUCTURE

LOT 4

TENNIS &BASKETBALL

HARRISON FIELD

W POLK STREET

S HA

LSTED STREET

S DESPLA

INES STREET

DA

N RYA

N EXPRESSW

AY

UIC/HALSTEDCTA STATIONUIC/HALSTEDCTA STATION

HALSTED STREETSTUDENT LIFE

11 COLLISIONS

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

15

UNIVERSITY VILLAGE MARKETPLACE

Location: Halsted Street between Roosevelt Road and 14th Street

Summary:At the intersection of Roosevelt Road and Union Avenue is the proposed City Gateway. This important location will be a visually prominent point of entry to UIC’s east and south campuses. The project will facilitate travel to better Integrate Campus and Community and provide Safe Crossings. It will also enhance access to the UIC Forum, a site of many community events.

City Gateway will increase pedestrian capacity at the critical crossing of Roosevelt Road and Union Avenue and also improve access to the multiple CTA bus routes by using the adjoining roadways. The gateway and intersection enhancements are coordinated with the Roosevelt Road Connections proj-ects to facilitate safe travel throughout the Roosevelt Road corridor. These projects will provide safer access to and from the Halsted Street Student Life area

Conflict:Crossing between UIC’s east side and the new south campus is dangerous as the main roadway, Halst-ed Street, has a daily traffic count of over 30,000 vehicles, which has created a conflict of 10 collisions with pedestrians and bicyclists. Despite its strategic location, the current space for the City Gateway lacks prominence.

Planned Improvements:• High-visibility crosswalks and additional intersection safety improvements• Prominent gateway• Customized paving reflecting unique community design• In-pavement lighting, overhead pedestrian signals or Rectangular Rapid Flashing Beacons• Overhead pedestrian crossing signs in high pedestrian traffic areas• New wayfinding system

MAXWELL ST.PARKING

STRUCTURE

LOT 14

SOFTBALL

LES MILLER FIELD

CURTIS GRANDERSONSTADIUM

SKYSPACE

EARL NEALPLAZA

ROCHFORD STREET

W MAXWELL STREET

W LIBERTY STREET

S HA

LSTED STREET

S UN

ION

AVENU

E

S N

EWBE

RRY

AVEN

UE

RUBLE STREET

UNIVERSITY VILLAGEMARKET PLACE

10 COLLISIONS

S LAFLIN

STREET

S WO

OD

STREET

W 15TH STREETW 15TH STREET

W 15TH STREET

INTERSECTION MODIFICATIONPROPOSED PROJECTS

PROJECT KEY PROJECT IMPROVEMENTS MAP KEY

46 27

16

4

8

2 IN-PROGRESSPROJECTS

MID-BLOCK CROSSING

BICYCLE PATHS

PLAZAS + GATEWAYS + ACCESSWAYS

PARKING PROJECTS

5 COMPLEMENTARYNON-UIC PROJECTS

CAR COLLISIONS WITH PEDESTRIANS & CYCLISTS (2008-2012)MAJOR PEDESTRIAN CONNECTORS

PROJECT HUBS (10 total) MAJOR UNIVERSITY GATEWAY ENTRANCESUIC BUILDINGS TIGER PROPOSED BIKE LANES

16

CAMPUS-WIDE IMPROVEMENTS

17

Transit The UIC community area is well served by public transit. Over 13 bus routes, including the UIC shut-tle, CTA buses, and Pace (an express regional service route), and two CTA train lines run through the campus and surrounding neighborhoods. One challenge for transit riders is the lack of information on real-time arrivals. To remedy this, UIC will install digital screens displaying transit information in key campus locations. Additionally, survey feedback provided in the Multimodal Transportation Plan revealed that many users feel unsafe or uncomfortable riding transit because of the lack of bus shelters and benches. Crossroads and Connections will provide new shelters with benches at key locations resulting in safer and more desirable transit facilities.

Wayfinding Successful navigation is a result of a well-planned sign system. The current UIC wayfinding is limited in scope, lacks distance information and does not conform to building and ADA accessibility codes. Crossroads and Connections will develop a campus-wide wayfinding program that will address accessibility and public safety while promoting student, pedestrian and business productivity through more efficient time saving travel routes around campus and to existing transportation facilities and major community destinations. This unified, ADA-compliant sign program will benefit users of all trans-portation modes by clearly and consistently conveying location information throughout the campus. It will allow users to easily travel the most direct and safe route to their destination. The project scope will consist of three gateway entrance markers and approximately 135 building entrance signs, 39 parking and garage signs, 30 pedestrian signs as well as 23 “You Are Here” pedestal maps.

ParkingCrossroads and Connections will rehabilitate popular yet critically deficient parking areas (indicated in the individual hub descriptions). Strategic locations will receive new eco-friendly and durable pave-ment. Parking areas with inadequate or energy-inefficient lighting will receive upgrades. New security cameras will be installed in critical locations and campus parking lots will receive new payment sys-tems to ensure better reliability and speedier exit lanes, thus increasing capacity. As part of its environ-mental commitment, UIC will not increase the number of parking spaces. Capacity management will be achieved through faster exit lanes, fewer areas blocked off because of poor surfaces, better snow control, and promotion of active transportation.

Bicycle NetworkUIC lacks a campus-wide bicycle network, so bicyclists are forced to use undesignated routes to travel through campus. This has led to hazardous conflict zones with pedestrians and vehicles resulting in collisions. The new bikeway network will include multiple designated safe routes for bicyclists of all ages and abilities. The network will be integrated with City of Chicago’s bikeways and Divvy stations, Chicago’s public bike share system. UIC will also significantly expand bike parking at key locations.

PROJECT PARTIES AND GRANT FUNDS

18

PROJECT PARTIES

UIC is the sole applicant of Crossroads and Connections. While this is not a joint application, the basis of this project originates from the collaboration of many organizations. Please see page 27 for more details about the partnership of this project.

GRANT FUNDSCrossroads and Connections will create long-term improvements to UIC’s and the greater Chicago transportation network. The project will receive a 41% project match by UIC Parking Services. The project match will fund all parking facility improvements including rehabilitation of existing lots and structures, sustainable pavement and lighting systems, security camera retrofits, sustainable land-scaping and a new state of the art campus-wide payment system. 59% of the total project cost will be requested of TIGER funding. Requested TIGER funds will be used to increase safety for pedestrians and bicyclists, maximize access to UIC parking facilities and Chicago public transportation services, increase easy pedestrian access throughout the project area, add routes to the city’s bicycle network, and provide more feasible transportation options.

TIGER funds will complete the overall funding package to improve the network of transportation sur-rounding UIC and nearby neighborhoods, hospitals, and business districts. Project fund distribution has changed since the 2015 TIGER pre-application due to a change in indirect costs. Project funds will be used to complete both pre-construction and construction activities. TIGER funds will be obligated by September 30, 2017. No TIGER funds will be expended after September 30, 2022. The full budget and commitment of this project match can be found in the appendix. This is UIC’s first request for Fed-eral funding for Crossroads and Connections.

PROJECT PARTIES AND GRANT FUNDS

19

Project Type Construction

Project Management for Design and Construction

Architectural and

Engineering Services

Administrative Costs TOTAL Costs

Percent of Total Costs

Crosswalks and Intersections

High vis ibi l i ty crosswalks , consol idation of mid-block cross ings , s top s igns , curb and median cuts , customized paving with thermoplastic overlay

Pedestrian and Traffic SignalsPedestrian countdown timers with audible and access ible features , Leading Pedestrian Interva l (LPI), HAWK s ignal , 5-head traffic s ignal , advanced pedestrian warning s igns , in-pavement l ighting, overhead flashing pedestrian s ignal , Rectangular Rapid Flashing Beacons (RRFB), optimization of traffic s ignals

Transit and WayfindingRelocation of bus s tops , new bus shel ters with high-qual i ty amenities , digi ta l screens for trans i t trackers , campus-wide multimodal wayfinding system

Pedestrian ExperienceLighting at cross ings , tacti le pads , s idewalk repairs , pedestrian path and plaza rehabi l i tation, removal of cul -de-sac, pedestrian ameniti tes within project hubs

Bicycle FacilitiesNew bicycle paths , new buffered bicycle route, neighborhood greenway, restriping of exis ting bicycle paths , and bicycle parking

Parking FacilitiesRehabi l i tation of parking lots and s tructures , new campus-wide electronic payment system, securi ty camera insta l lation, permeable pavers and new susta inable l ighting

Percent of Funds

TOTAL Project CostTotal TIGER Requested Funds (59%) 59%Total Project Match (41%) 41%

41%

11%

12%

10%

25%

1%

$2,620,063 $297,343 $238,543 $15,780 $3,171,729

$13,906$2,403,644 $163,300 $214,300 $2,795,150

$2,779,829 $325,800 $291,000 $16,983 $3,413,612

$324,997 $37,099 $29,811 $1,960 $393,867

$6,434,273 $400,000 $577,700 $37,060 $7,449,033

$29,274,091$17,223,391$12,050,700

$10,717,619 $483,636 $795,857 $53,588 $12,050,700

* Project budget has changed since pre-application due to changes in the indirect costs

SELECTION CRITERIA OVERVIEW

Selection Criteria Overview Crossroads and Connections is a strategic investment in 10 major activity hubs and the multimodal corridors that connect the hubs. Projects were prioritized for the initiative that would provide long-term benefits related to safety, economic competitiveness, state of good repair, environmental sustainability and quality of life for UIC and adjoining communities. The resulting network is a study in innovation and partnership.

Crossroads and Connections provides a multitude of transportation choices. Regardless of transit mode, all users will benefit from new routes, facilities and amenities. Multiple routes are optimized for the needs of users based on their travel modes and desired travel times. People with disabilities will especially benefit from enhancements to accessibility that will facilitate their access to jobs, entertain-ment, shopping and daily life.

Table: Selection Criteria Summary

Selection Criteria Impacts and Benefits ReferenceState of Good Repair Parking areas, transit facilities, bikeways and pedestrian

network all brought to a State of Good Repair. Page 21

Economic Competitiveness Improved access to business districts and event centers, reduced travel times, reduced travel costs, new access to jobs for people with disabilities, improved Housing & Trans-portation Index.

Page 22

Quality of Life Accessibility enhancements for all travel modes, increased use of active transportation, improved access ways to cam-pus and community destinations.

Page 23

Environmental Sustainability Reduced greenhouse gas emissions, eco-friendly construc-tion, improved energy efficiency, stormwater capture.

Page 25

Safety Over 40 intersections and mid-block crossings receive safety improvements reducing the number, rate and conse-quences of vehicle crashes with pedestrians and bicyclists; lighting and security camera enhancements improve safety and accessibility for pedestrians, bicyclists and drivers; designated bicycle routes provide safe mode of travel for cyclists.

Page 26

Innovation Cutting edge accessibility and roadway improvements. Page 27Partnership Benefits for university area, adjoining neighborhoods and

users visiting the study area; collaboration with non-Univer-sity entities.

Page 27

20

Project Type Construction

Project Management for Design and Construction

Architectural and

Engineering Services

Administrative Costs TOTAL Costs

Percent of Total Costs

Crosswalks and Intersections

High vis ibi l i ty crosswalks , consol idation of mid-block cross ings , s top s igns , curb and median cuts , customized paving with thermoplastic overlay

Pedestrian and Traffic SignalsPedestrian countdown timers with audible and access ible features , Leading Pedestrian Interva l (LPI), HAWK s ignal , 5-head traffic s ignal , advanced pedestrian warning s igns , in-pavement l ighting, overhead flashing pedestrian s ignal , Rectangular Rapid Flashing Beacons (RRFB), optimization of traffic s ignals

Transit and WayfindingRelocation of bus s tops , new bus shel ters with high-qual i ty amenities , digi ta l screens for trans i t trackers , campus-wide multimodal wayfinding system

Pedestrian ExperienceLighting at cross ings , tacti le pads , s idewalk repairs , pedestrian path and plaza rehabi l i tation, removal of cul -de-sac, pedestrian ameniti tes within project hubs

Bicycle FacilitiesNew bicycle paths , new buffered bicycle route, neighborhood greenway, restriping of exis ting bicycle paths , and bicycle parking

Parking FacilitiesRehabi l i tation of parking lots and s tructures , new campus-wide electronic payment system, securi ty camera insta l lation, permeable pavers and new susta inable l ighting

Percent of Funds

TOTAL Project CostTotal TIGER Requested Funds (59%) 59%Total Project Match (41%) 41%

41%

11%

12%

10%

25%

1%

$2,620,063 $297,343 $238,543 $15,780 $3,171,729

$13,906$2,403,644 $163,300 $214,300 $2,795,150

$2,779,829 $325,800 $291,000 $16,983 $3,413,612

$324,997 $37,099 $29,811 $1,960 $393,867

$6,434,273 $400,000 $577,700 $37,060 $7,449,033

$29,274,091$17,223,391$12,050,700

$10,717,619 $483,636 $795,857 $53,588 $12,050,700

STATE OF GOOD REPAIR

21

The UIC campus is situated in a dense environment within Chicago’s grid network of streets. The UIC community extensively uses public roadways to travel within and beyond the campus. The projects included in Crossroads and Connections were carefully selected to leverage existing transportation assets and fill in gaps in the existing network. The program rebuilds heavily used but decaying trans-portation assets. Achieving a State of Good Repair for these assets is a sound investment in both UIC and the City of Chicago.

Parking SystemThe strategic improvements to parking facilities will improve their efficiency, capacity and lifetime without increasing space allocated to parking. Parking lots will receive new eco-friendly, long lasting pavement, upgrades to security and energy efficient lighting improvements. Upgrades will result in a longer life expectancy for parking facilities.

MotoristsMotorists will benefit from intersection improvements that facilitate smoother traffic flow. Key in-tersections will have their traffic signals upgraded and pavement rehabilitated. The consolidation of mid-block crossings will also improve conditions for vehicles. IDOT is currently improving roads and expressways in the UIC area through the Jane Byrne Interchange Project. Crossroads and Connec-tions leverages these investments and extends their benefits.

Bicycling NetworkCrossroads and Connections utilizes Chicago’s street grid to create multiple bike routes appropriate for people of all abilities. Street upgrades in Community Crossroads and other next-generation bike facilities advance US DOT’s Safer People, Safer Streets objectives.

Pedestrian NetworkSidewalks that need improvements were strategically selected. Sidewalks leading to transit and parking transportation facilities were prioritized in alignment with the US DOT Road Safety for Transit Patrons initiative. Sidewalk segments with accessibility problems were also prioritized. These seg-ments were then accessed with the PAVER rating system with those receiving failing scores selected for improvement. Plazas are also included in the project due to their critical role on UIC’s campus in helping to facilitate the high levels of pedestrian traffic. One of the existing plazas is currently closed, , and will benefit from new paving, access ways, and pedestrian amenities.

TransitCrossroads and Connections leverages CTA and IDOT’s ongoing investments in CTA rail stations serv-ing the UIC campus. Intersection improvements along bus routes will enhance reliability and comfort of these services.

ECONOMIC COMPETITIVENESS

Investing in Crossroads and Connections is to invest in the economic future of Chicago. UIC adds $4.0 billion to the economy of the Chicago region, most of which comes from UIC’s impact on educational attainment in the state.

By making the system accessible, people with disabilities gain access to new jobs and advance Lad-ders of Opportunity. For example, the Illinois Tollway operates its primary call center from the UIC campus. The employees are people with visual impairments. Crossroads and Connections will facili-tate safer access to the call center by rail, bus and walking.

UIC is proud to be included on the 2014 Military Friendly Schools list. UIC is ranked as one of the Top 15% of US colleges that support veterans. UIC also shares its health campus with the Jesse Brown VA Medical Center, where more than 60,000 local veterans depend on UIC and Jesse Brown VA Medical Center for their services. Crossroads and Connections will advance Ladders of Opportunities for America’s heroes.

Crossroads and Connections facilitates easier access between UIC and adjoining neighborhoods like two of Chicago’s most vibrant areas: Little Italy and Greektown. University Village is one of the city’s newer communities, arising from a public-private partnership. Each of these communities is dominated by independent, locally-owned businesses.

Residents of the UIC area encounter a Housing + Transportation Index of about 50% (i.e. they spend just over 50% of their income on housing and transportation). Investing in the efficient transportation assets around UIC will lower transportation costs.

With about 27,000 students, the University of Illinois at Chicago is the city’s largest higher education institution and Chicago’s only public research university. The campus is also a major destination for events. Crossroads and Connections will facilitate multimodal access to the new Curtis Granderson Stadium, UIC Pavilion and UIC Forum.

Major Employers in University Area University of Illinois at ChicagoRegional Headquarters for Federal Bureau of InvestigationRush UniversityVeterans AdministrationCook County Health and Hospitals SystemChicago BullsChicago BlackhawksIllinois State Police Forensic Science LaboratoriesIllinois Department of Public Health LaboratoriesCity Colleges of Chicago Chicago Police Education and Training DivisionChicago Fire Department Training Academy

22

QUALITY OF LIFE

23

UIC strives to offer a unique and superb quality of life. With its location in the heart of Chicago, UIC boasts of unparalleled connections to the city, region and beyond. Crossroads and Connections enhances the links between UIC and the surrounding community.

A Multimodal NetworkCrossroads and Connections will develop a complete multimodal transportation network serving UIC and adjacent neighborhoods. This network is integrated into the City of Chicago’s award winning bicy-cling and pedestrian system. Students, employees and visitors will travel along fully accessible pedes-trian ways, new bike facilities, frequent transit routes, or the brand-new Jane Byrne Interchange flyover. Upon reaching their destination they will park in rebuilt eco-friendly lots or the new campus-wide bike-parking network.

AccessibilityUIC‘s health sciences colleges and hospital share the Illinois Medical District with three other hospitals and numerous facilities serving people with disabilities. Crossroads and Connections ensures that all routes leading to these destinations are accessible to everyone. Intersections with audible features and illuminated pavement transform hazards to assets. Pedestrian amenities at strategic locations (including new plazas) provide accommodation for those who need a break. These routes in turn lead to UIC’s extensive collection of accessible buildings and transit facilities that are newly practicable for persons of all abilities. The accessible network will greatly expand Ladders of Opportunity for people with disabilities.

Access to Campus SpacesUIC features an urban campus that is increasingly open to the public. The new Chicago Circle Memorial Grove removed previous fences to allow uninhibited access to this open space. Crossroads and Con-nections will open new plazas to the public and reopen an existing closed plaza. New Safe Crossings will allow better access to UIC’s athletic facilities including the new Curtis Granderson Stadium.

Being a Good NeighborThe new wayfinding system will help people in the UIC community explore adjacent neighborhoods (Little Italy, University Village, Greektown, Pilsen). Safe Crossings provide access to these important business districts. Travel along the commercial corridors is facilitated by better transit and enhanced intersections.

UIC doesn’t rest on its laurels. We are proud to be a Bronze Level Bicycle Friendly University, certified Tree Campus USA institution and recipient of the Governor’s Sustainability Award. Crossroads and Connections will enhance our ability to be a good neighbor, environmental steward and resource for innovation in transportation.

ADD

AMS

PARK

FOSC

O P

ARK

LIVI

NG

STO

NFI

ELD

PAR

KAR

RIG

O P

ARK

VERN

ON

PAR

K

GAR

IBAL

DI

PARK

SHER

IDAN

PAR

K

MIL

LER

PARK

WO

OD

STR

EET

PARK

ING

STR

UCT

URE

LOT

B4

WO

OD

STR

EET

MET

ERED

LO

T

LOT

E4

LOT

E

LOT

E1

LOT

N1

LOT

F

LOT

G

LOT

M

LOT

G4

LOT

K

LOT

J

UIC METER LOT LOT

H

LOT

F4

LOT

C4

LOT L

LOT

A3

LOT

B2

LOT

A4

LOT

W5

PAU

LIN

AST

REET

PARK

ING

ST

RUCT

URE

LOT

C1

C1

LOT

OLO

T O

SCWSR

H

NU

RS

SFC

SSR

PSRH

BGRC

AH

SB

LIER

IEE

I

OCC

NPI

UIH

PHA

RMAO

BO

TMCM

WT

CMW

CMET

MSB CO

MRB

BRL

MCA

CSN

NM

RLCS

B

PSB

EHSO

DH

SPSPH

PI

CFSB

DEN

TM

BRB

LHS

HRB

SPH

W

WRO

B

LWB

MSH

C

OCC

ILF2242

MA

B

LOT

18A

HA

RRIS

ON

ST.

PARK

ING

STRU

CTU

RELO

T 9

LOT

8

LOT

1BLO

T 1A

LOT

10

LOT

5

LOT

5C

LOT

6

HA

LSTE

D S

TPA

RKIN

GST

RUCT

URE

LOT

4 MA

XW

ELL

ST.

PARK

ING

STRU

CTU

RE

LOT

11

LOT

14

LOT

20

LOT

12

ACT

B(F

UTU

RE C

ON

STRU

CTIO

N)

AD

S

SRCC SCRS

SRCN

SRF

SCET

SCE

BSB

UH

HH

JHSR

CW

GH

DH

LH LCB

LCE

LCC

LCD

LCA

LCF

LIBSH

TH

BHA

HSE

O

SELW

SELE ER

F

SES

PRL

RRB

FORU

M

JJST

TBH

MRH

PEB

FAC

1333

SH

722W

M

1253

SH

1309

SH

UTB

PPB

CGF

SSB

PAV

ETM

SW

UIC

T

AEH

CUPP

AH

JAH

JAH

D

TFPS

CEB

TSB

RECR

EATI

ON

FIEL

DRE

CREA

TIO

NFI

ELD

SOFT

BALL

LES

MIL

LER

FIEL

D

CURT

IS G

RAN

DER

SON

STA

DIU

M

SOCC

ER

SKYS

PACE

EARL

NEA

LPL

AZA

TEN

NIS

&BA

SKET

BALL

FLA

MES

TEN

NIS

FAC

ILIT

Y

CHIC

AGO

CIR

CLE

MEM

ORI

AL

GRO

VE

THE

QU

AD

THE PARK LIVINGSTON HEALTH WALK

ATKI

NS

GA

RDEN

COLL

EGE

OF

MED

ICIN

ECO

URT

YARD

MED

ICA

L SC

IEN

CES

COU

RTYA

RD

HA

RRIS

ON

FIE

LD

W H

ARR

ISO

N S

TREE

T

W V

ERN

ON

PA

RK P

LACE

W R

OO

SEVE

LT R

OA

D

ROCH

FORD

STR

EET

W M

AXW

ELL

STRE

ET

W L

IBER

TY S

TREE

T

W 1

4TH

PLA

CE

W P

OLK

STR

EET

S PEORIA STREET

S HALSTED STREETS HALSTED STREET

S MORGAN STREET

W C

ON

GRE

SS P

ARK

WAY

S RACINE AVENUE

S CAMPUS PARKWAY

S UNION AVENUE

S NEWBERRY AVENUE

S MORGAN STREET

S GR

EEN S

TREE

T

S TI

LDEN

STR

EET

W 1

4TH

STR

EET S EMERALD AVENUE

S BLUE ISLAND AVENUE

S THROOP STREET

W C

ON

GRE

SS P

ARK

WAY

W T

ILD

EN S

TREE

T

W 1

5TH

STR

EET

W M

AXW

ELL

STRE

ET

W G

REN

SHAW

STR

EET

W D

E KO

VEN

STR

EET

W C

ABR

INI S

TREE

T

W P

OLK

STR

EET

W L

EXIN

GTO

N S

TREE

T

W V

ERN

ON

PA

RK P

LACE

W H

ARR

ISO

N S

TREE

T

W 1

4TH

STR

EET

W 1

4TH

PLA

CE

W 1

5TH

PLA

CE

S PEORIA STREET

S SANGAMON STREET

W 1

5TH

STR

EET

W 1

4TH

PLA

CE

W 1

4TH

STR

EET

S ABERDEEN STREET

S RACINE AVENUEW

MAX

WEL

L ST

REET

RUBLE STREET

W W

ASH

BURN

E AV

ENU

E

W 1

4TH

STR

EET

W 1

4TH

STR

EET

S THROOP STREET

S LOOMIS STREETS LOOMIS STREET

S LOOMIS STREET

S THROOP STREET

W H

AST

ING

S ST

REET

W H

AST

ING

S ST

REET

W 1

3TH

STR

EET

W C

ON

GRE

SS P

ARK

WAY

W H

ARR

ISO

N S

TREE

T

W F

LOU

RNO

Y ST

REET

W P

OLK

STR

EET

W R

OO

SEVE

LT R

OA

D

W G

REN

SHAW

STR

EET

S W

INCH

ESTE

R AV

ENU

E

W OGDEN AVENUE

S HOYNE AVE.

S DAMEN AVENUE

S HERMITAGE AVENUE

W F

LOU

RNO

Y ST

W F

ILLM

ORE

STR

EET

S WOLCOTT AVENUE

S WOOD STREET

S PAULINA STREET

S MARSHFIELD AVENUE

S ASHLAND AVENUE

S HAMILTON AVENUE

S HOYNE AVENUE

W BOWLER STREET

S SEELEY AVENUE

W F

ILLM

ORE

STR

EET

W G

REN

SHAW

STR

EET

S LYTLE STREET

W C

ABR

INI S

TREE

T

W A

RTH

ING

TON

STR

EET

S MAY STREET

W P

OLK

STR

EET

W C

ABR

INI S

TREE

T

W L

EXIN

GTO

N S

TREE

T

W F

LOU

RNO

Y ST

REET

S LYTLE STREET

W R

OO

SEVE

LT R

OA

D

W MILLER STREET

W V

AN

BU

REN

STR

EET

W TA

YLO

R ST

REET

W F

LOU

RNO

Y ST

REET

S LAFLIN STREET

S LAFLIN STREET

S JEFFERSON STREET

S CLINTON STREET

S CANAL STREET

S CLINTON STREET

S DESPLAINES STREET

S ASHLAND AVENUE

S ASHLAND AVENUE

W TA

YLO

R ST

REET

S PAULINA STREET

S PAULINA STREET

W H

ARR

ISO

N S

TREE

TW

HA

RRIS

ON

STR

EET

S WOOD STREETS WOOD STREET

W 1

4TH

PLA

CE

W 1

5TH

STR

EET

W 1

5TH

STR

EET

W 1

5TH

STR

EETW

RO

OSE

VELT

RO

AD

W R

OO

SEVE

LT R

OA

DW

RO

OSE

VELT

RO

AD

W W

ASH

BURN

E AV

ENU

E

W 1

3TH

STR

EET

W 1

4TH

PLA

CE

W 1

4TH

STR

EET

W W

ASH

BURN

E AV

ENU

E

W P

OLK

STR

EET

W P

OLK

STR

EET

W P

OLK

STR

EET

W L

EXIN

GTO

N S

TREE

T

W OGDEN AVENUE

W TA

YLO

R ST

REET

W TA

YLO

R ST

REET

W TA

YLO

R ST

REET

S LEAVITT STREET

S DAMEN AVENUES DAMEN AVENUE

S DAMEN AVENUE

W R

OO

SEVE

LT R

OA

D

W 1

4TH

STR

EET

W H

AST

ING

S ST

REET

W 1

5TH

STR

EET

W 1

4TH

PLA

CE

W G

REN

SHAW

STR

EET

S HERMITAGE AVENUE

S WOOD STREETS WOOD STREET

S HALSTED STREETS HALSTED STREET

S MORGAN STREETS MORGAN STREET

S BLUE ISLAND AVENUE

S DESPLAINES STREET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W V

AN

BU

REN

STR

EET

W H

ARR

ISO

N S

TREE

T

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AYD

WIG

HT

D. E

ISEN

HO

WER

EXP

RESS

WAY

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AY

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AY

DW

IGH

T D

. EIS

ENH

OW

ER E

XPRE

SSW

AY

DAN RYAN EXPRESSWAY DAN RYAN EXPRESSWAY

DAN RYAN EXPRESSWAY

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T C

TA S

TATI

ON

DA

MEN

AVE

.C

TA S

TATI

ON

RACI

NE

AVE.

CTA

STA

TIO

N

UIC

/HA

LSTE

DC

TA S

TATI

ON

UIC

/HA

LSTE

DC

TA S

TATI

ON

UIC

/HA

LSTE

DC

TA S

TATI

ON

Jess

e Br

own

VAM

edic

al C

ente

r

John

H. S

trog

er H

ospi

tal

Rush

Uni

vers

ity M

edic

al C

ente

r

ILLI

NO

IS M

EDIC

AL

DIS

TRIC

T C

TA S

TATI

ON

DA

MEN

AVE

.EN

TRA

NCE

RACI

NE

AVE.

CTA

STA

TIO

N

PEO

RIA

ST.

ENTR

AN

CEM

ORG

AN

ST.

ENTR

AN

CE

UIC

/HA

LSTE

DC

TA S

TATI

ON

PAU

LIN

A S

T.EN

TRA

NCE

LOO

MIS

ST.

ENTR

AN

CE

POLK

STR

EET

CTA

STA

TIO

N

SSB

UIH

OCC

UIC

DIS

ABI

LITY

RES

OU

RCE

CEN

TER

UIC

STU

DEN

T CE

NTE

R EA

ST

ILLI

NO

IS C

ENTE

R FO

RRE

HA

BILI

TATI

ON

& E

DU

CATI

ON

UIC

DIS

ABI

LITY

, HEA

LTH

AN

D S

OCI

AL

POLI

CY B

UIL

DIN

G

MO

NTE

FIO

RE S

PECI

AL

ELEM

ENTA

RY S

CHO

OL

PRO

POSE

D S

ITE

FOR

SPEC

IAL

OLY

MPI

CS C

HIC

AG

O

RUSH

DAY

SCH

OO

LRU

SH U

NIV

ERSI

TY M

EDIC

AL

CEN

TER

JOH

N H

. STR

OG

ER H

OSP

ITA

L

JESS

E BR

OW

N

VA M

EDIC

AL

CEN

TER

EAST

ER S

EALS

TH

ERA

PEU

TIC

SCH

OO

L

ILLI

NO

IS C

ENTE

R FO

RRE

HA

BILI

TATI

ON

& E

DU

CATI

ON

CHIC

AG

O L

IGH

THO

USE

FO

R PE

OPL

E W

HO

ARE

BLI

ND

OR

VIS

UA

LLY

IMPA

IRED

UIC

UN

IVER

SITY

OF

ILLI

NO

ISH

OSP

ITA

L &

HEA

LTH

SCI

ENCE

S

UIC

EYE

& E

AR

INFI

RMA

RY

HO

LY T

RIN

ITY

SCH

OO

L FO

R TH

E D

EAF

MA

P KE

Y

BUIL

DIN

GS

SERV

ICIN

G IN

DIV

IDU

ALS

WIT

H D

ISA

BILI

TIES

PRO

POSE

D B

UIL

DIN

GS/

SITE

S SE

RVIC

ING

IND

IVID

UA

LS W

ITH

DIS

ABI

LITI

ES

UIC

BU

ILD

ING

S

PERC

ENT

OF

RESI

DEN

TS W

ITH

A D

ISA

BILI

TY B

Y CE

NSU

S TR

ACT

(200

9 - 2

013)

025

UIC

| 20

15

TIG

ERAc

cess

ibilit

y M

ap

5%-8

%

8%-1

1%

18%

-25%

11%

-18%

18%

-25%

3%-5

%

ACCESSIBILITY MAP

24

ENVIRONMENTAL SUSTAINABILITY

25

UIC is committed to being a climate-forward institution. Through smart investments, UIC is protect-ing the environment. Crossroads and Connections strategically invests in eco-friendly transportation assets. Each of the project elements work together to create a successful multimodal transportation network.

UIC benefits from a widespread existing network of multimodal transportation facilities. The univer-sity community uses all of these modes of transportation. Crossroads and Connections will facilitate easier multimodal travel. The resulting network provides safe corridors for travelers of any mode. This will result in more active transportation and only necessary driving. Reductions in VMT will result in preventing the emission of over 55,380 pounds of noxious emissions.

Crossroads and Connections will support the eco-friendly rejuvenation of UIC’s 50-year old campus. Plazas will have more than 50% of their land area covered in permeable materials. Parking lots will be rebuilt with sustainable construction materials. Lighting will be replaced with long lasting LED lights. Native landscaping will be added to all plazas. All roadway projects will be constructed within exist-ing right of way to minimize harmful construction. These projects will result in 81% of stormwater diverted at project sites and 1,237,395 annual kilowatt hours saved.

20%

25%

8%13%

20%

14%

Which mode do you use most often to get to and from campus?

Drive

CTA Bus

Walk

CTA Train

Metra Train

Bicycle

SAFETY

26

ProblemCurrent transportation facilities in the project area have resulted in dangerous vehicle collisions with pedestrians and bicyclists. Many of the surrounding roads have daily traffic volumes of 44,700 vehi-cles, some of which have intersection widths of up to 7 lanes. High vehicle speeds and wide intersec-tions create hazardous environments where pedestrians and bicyclists are left stranded in the cross-ing. Faded, outdated, and poorly lit crosswalks make it difficult for vehicle drivers to see pedestrians and bicyclists in the crosswalks, thus contributing to the crashes. In some cases, scattered mid-block crossings encourage pedestrians to cross the high-traffic roadways in unmarked areas, creating pedestrian crossing danger zones. Outdated pedestrian signals that lack audible and accessibility features, countdown timers and/or Leading Pedestrian Intervals make it impossible for persons with disabilities to safely cross high-traffic intersections and crossings. Absence of pedestrian and bicycle warning features and specified bicycle lanes occur throughout the study area, also causing vehicle collisions with pedestrians and bicyclists.

Vehicle Collisions with Pedestrians and BicyclistsOutmoded and unsafe intersections and mid-block crossings have led to a high number of vehicle col-lisions with pedestrians and bicyclists. Data provided by the Illinois Department of Transportation from 2008-2012 indicates 253 vehicle collisions with pedestrians and bicyclists within the Crossroads and Connections hubs. 177 of vehicle collisions are with pedestrians and 76 are with bicyclists. Of these crashes, the leading cause of collision was failure to yield, totaling 80. During this time there were 3 fatalities within a quarter mile of campus, and 37 high-risk injuries resulting in the victim’s inability to walk, drive or normally perform activities he or she was capable of performing before the crash. All 253 crashes that occurred from 2008-2012 have cost the university and surrounding neighborhoods $57,653,884 in property damage, injuries and death.

Project ImprovementsCrash reduction factors provided by the Federal Highway Administration (FHWA) were used to estimate the expected crashes after roadway improvements. All intersections and crossings in the project area will receive high-visibility striping crossing treatments, which according to the FHWA, will reduce colli-sions by 40%. Cutting edge customized paving, as well as new lighting and tactile pads will be placed at key locations. All major intersections will receive countdown pedestrian signals with audible fea-tures and vibrotactile walk indicators. Countdown pedestrian signals will reduce crashes in the area by an expected 55% according to the FHWA. HAWK pedestrian signals and Leading Pedestrian Interval (LPI) will also be placed at designated locations. Mid-block crossings in high-traffic areas will receive the above-mentioned improvements, as well as advanced pedestrian warning signals, overhead flash-ing pedestrian warning signals, in-pavement lighting, or Rapid Rectangular Flashing Beacons (RRFB). Newly designated bicycle lanes will also provide a safe and specified area of the roadway for bicyclists. All combined intersection and crossing improvements will reduce the total number of vehicle crashes with pedestrians and bicyclists by 62%.

INNOVATION AND PARTNERSHIP

27

INNOVATION

UIC is a premier urban research institution. As such, we invest in innovation. Crossroads and Connections utilizes new and existing infrastructure to create a dynamic transportation system. Innovation is embedded in each of the project’s elements.

Parking Lots It isn’t enough to replace deteriorating assets; so instead we are investing in improvements that extend the life of and enhance the efficiency of our transportation network. Parking lots will receive new security and lighting systems along with new and innovative payment systems that will allow for faster vehicle exits and provide more accurate lot usage data.

Transit Full time UIC students already receive monthly passes for CTA travel through their mandatory student fees. Now we will make transit the preferred option for travel to and within UIC’s campus by adding transit tracker screens with real time arrival information provided by CTA and Pace transit services. These tracker screens will also incorporate UIC’s internal bus systems with the corresponding web based tracker.

SustainabilityAs an academic institution, we are committed to tracking our progress. Project areas will be construct-ed using the very best in water and energy conserving materials. We plan to utilize the existing sustain-ability performance tracking and rating system to monitor our developments.

AccessibilityCrossroads and Connections enhances UIC’s existing accessible transportation network and with in-novative technology improvements, it will create safer crossings and pathways for people with disabil-ities. These efforts will lead to employment and job training which furthers their Ladders of Opportu-nity. Pending design approvals, innovative solutions include accessible pedestrian countdown signals with audible features and vibrotactile walk indicators. Identified mid-block crossings will receive in-pavement lighting to further draw motorists attention to pedestrian crossings. The use of overhead flashing pedestrian warning signals may also be implemented at particular crossings.

PARTNERSHIPCrossroads and Connections is the implementation of the UIC 2010 Master Plan and the 2015 Multimodal Transportation Plan. The Campus Master Plan envisioned a cohesive campus of integrat-ed transportation corridors, buildings and open spaces. It was established using feedback received during seven town hall meetings, in which one hundred and sixty two local organizations were includ-ed. The Multimodal Plan recommended strategic improvements to improve the flow of pedestrians, cyclists and vehicles in and around campus. UIC, Chicago Metropolitan Agency for Planning (CMAP), Chicago Department of Transportation (CDOT), Illinois Department of Transportation (IDOT), and the Chicago Transit Authority (CTA) authored the Multimodal Plan in collaboration. Both plans received a combined 1,499 online survey responses regarding existing transportation conditions in the project area. All of the above organizations have worked in cohesion with one another to provide guidance in developing the recommendations set forth in Crossroads and Connections.

CONCEPTUAL PROJECT RENDERINGSHALSTED S

TREET

HALSTED STREET

ROOSEVELTROAD

WOOD S

TREET

TAYLOR STREET

VERNON PARK PLACE

MORGAN S

TREET

LIBRARY

ROOSEVELT ROAD & HALSTED STREET INTERSECTION

HIGH-VISIBILITYCROSSINGS

CUSTOMIZEDPAVING AT

CROSSWALKS

PEDESTRIANCOUNTDOWN

SIGNALS

LEADINGPEDESTRIAN

INTERVAL

RELOCATEBUS STOP

TAYLOR STREET & WOOD STREET INTERSECTION

HALSTED NORTH OF POLK

MORGAN STREET & VERNON PARK PLACE

HIGH-VISIBILITYCROSSINGS

HIGH-VISIBILITYCROSSINGS

CUSTOMIZEDPAVING AT

CROSSWALKS

RE-STRIP TAYLORPROVIDE LEFT-

TURN LANE

TRAFFIC SIGNAL

PEDESTRIANCOUNTDOWN

SIGNALS

LEADINGPEDESTRIAN

INTERVAL

RELOCATEBUS STOP

CURB BUMP-OUTS

NORTH-SOUTHNEIGHBORHOOD

GREENWAY(BIKE-ROUTE)

PEDESTRIANPLAZA

PERMEABLEPAVERS

LANDSCAPING,BENCHES,

LIGHTING, ETC.

4 CRASH COUNTS

4 CRASH COUNTS

18 CRASH COUNTS

MODIFYCUL-DE-SAC

(RETAIN RESIDENTIALDRIVEWAY ACCESS)

MODIFYCUL-DE-SAC

LIGHTING ATCROSSING

PERMEABLEPAVERS

CUT MEDIAN

IN-PAVEMENTLIGHTING

INSTALL HAWKSIGNALS

CURB CUTHALSTED

28

RESULT OF BENEFIT-COST ANALYSIS

Crossroads and Connections is a strategic investment in 10 major activity hubs and the multimodal corridors that connect the hubs. The initiative Reinforces Safe Circulation, Enhances the Sense of Place, Connects Hubs of Activity, and Integrates Campus and Community. The implemented proj-ects will enhance the safety, economic competitiveness, environmental sustainability and quality of life of UIC and adjoining communities. Crossroads and Connections will result in significant advancement in Ladders of Opportunity.

A benefit-cost analysis of Crossroads and Connections demonstrates that the selected strategies re-sult in significant positive gains for the UIC campus area. A benefit-cost analysis documents a positive net ratio at both a 3% and 7% discount rate.

Summary of Benefit-Cost Analysis

The presented benefit-cost analysis is a conservative estimate of the expected benefits for the project. The analysis was conducted using estimates of population growth, mode shift, and growth factors for operating costs. The analysis also assumes a low annualized growth factor for population (1.0047) which impacts several factors.

Crossroads and Connections projects result in benefits that span the spectrum of goals for the TIGER program. Additionally, the project advances university, local and regional goals.

State of Good Repair:• Improved facility lifespan: $3,033 saved annually from increased life expectancy• Lower operating costs: reduction in operating costs by $122,966 annually

Economic Competitiveness:• Cost savings from energy improvements• Value of travel time savings: $6,520,052 saved annually in travel time savings• Reduced travel costs: $1,921,588 saved annually in travel costs

Quality of Life:• Newly accessible destinations and modes of travel: access to 12 public transit routes, and 3 UIC

shuttle routes

Environmental Sustainability:• Water savings: 81% of water diverted from the combined sewer system• Lower emissions from mode diversion: reduced GHG emissions by 55,380 pounds• Energy Savings: 1,237,395 kWh saved annually

Safety:• Lives saved: 1 life saved over a five-year period• Injuries avoided: 157 injuries avoided over a five-year period

29

7% Discount Rate 3% Discount RatePresent Value of Total Benefits $205,165,876 $241,775,357Present Value of Total Costs $25,608,156 $27,601,676Net Benefit (Benefits-Costs) $179,557,720 $214,173,681Benefit-Cost Ratio 8.01:1 8.76:1Internal Rate of Return 49% 49%

PROJECT READINESS

30

** All TIGER-funded pre-construction activities will be completed (and contracts awarded) by September 30, 2017. All TIGER-provided funds will be spent prior to September 30, 2022.

Technical & Financial FeasibilityThe technical feasibility of Crossroads and Connections is evident in our illustrated maps, renderings, basis of design, cost estimates, project schedule, and budget-risk mitigations. Crossroads and Con-nections is a financially viable project. Page 19 illustrates the use of grant funds, and the full budget is attached in the appendix. UIC is experienced and capable to manage grant funds. UIC has committed a 41% match to fund this project. Appropriate capital operating funds and contingency reserves were considered in formulating the project budget.

Required ApprovalsUIC will have completed all required Federal, State and local environmental permits and reviews, including completion of the NEPA process prior to any construction activities and before September 30, 2017. There are no foreseen legislative approvals needed for the completion of Crossroads and Connections. UIC will receive state and local planning approvals prior to September 30, 2107. The goals of Crossroads and Connections are consistent with those of CMAP’s FFY 2014-19 Transporta-tion Improvement Plan (TIP). Given CMAP’s direct involvement in the Multimodal Plan and this project, we anticipate successful inclusion of Crossroads and Connections in the TIP.

Project ScheduleA detailed project schedule is provided below. All components of the project will begin immediately upon receipt of TIGER funding. Prior to any roadway construction, UIC will work with CDOT and IDOT to receive the required right-of-way permits. Any non-roadway work is within UIC’s property and does not require any approvals.

APPENDIX

i

7% Discount Rate 3% Discount RatePresent Value of Total Benefits $205,165,876 $241,775,357Present Value of Total Costs $25,608,156 $27,601,676Net Benefit (Benefits-Costs) $179,557,720 $214,173,681Benefit-Cost Ratio 8.01:1 8.76:1Internal Rate of Return 49% 49%

ii

Benefit-Cost Analysis

EXECUTIVE SUMMARYCrossroads and Connections is a strategic investment in 10 major activity hubs and the multimodal corridors that connect the hubs. The implemented projects will enhance the safety, economic compet-itiveness, environmental sustainability and quality of life at UIC and in adjoining communities. A ben-efit-cost analysis documents a positive net ratio at both a 3% and 7% discount rate. Crossroads and Connections will result in significant advancement in Ladders of Opportunity.

Tables: Summary of Benefit-Cost Analysis

Crosswalks & Intersections

Current Status Base-line & Problem to be Addressed

Change to Baseline/

Alternatives

Type of Impacts

Population Affected by Impacts

Economic Benefits

Summary of Results

Page/Table Reference in BCA

Intersections and mid-block crossings on routes providing access to transit are dangerous to pedestri-ans and bicyclists and inaccessible to persons with limited mobility

High-vis-ibility crosswalks, customized paving with-in cross-ings at key locations, in-pavement lighting

Accessible crossings with lon-ger lasting surfaces, reduced crashes due to higher visibility crossings

All pe-destrians, especially those with disabilities (5,501 with-in ¼ mile of campus)

Monetized value of reduced travel costs due to mode shift

$36,175,363 in net value for mode shift at pres-ent value

Mode shift for accessi-bility table

iii

Pedestrian & Traffic Signals

Transit & Wayfinding

Current Status Baseline & Problem to be Addressed

Change to Baseline/

Alternatives

Type of Impacts

Population Affected by Impacts

Economic Benefits

Summary of Results

Page/Table Reference in BCA

High rates of vehicle crash-es involving pedestrians and cyclists due to most signals being uncoor-dinated and lacking pedes-trian timers with accessibili-ty features

Optimized traffic sig-nals, pedes-trian count-down timers with audible features, HAWK sig-nals, Leading Pedestrian Interval, Rectangular Rapid Flash-ing Beacon

Less con-gestion, less queuing, more acces-sible routes, reduced rate of vehicle crashes with pedestrians and bicy-clists

All pedes-trians and bicyclists, personal vehicles, public tran-sit buses and UIC shuttle buses

Monetized value of lower travel times for motorists and monetized value of lives saved

$95,139,677 in net savings for driving time reduction, and $109,983,052 in savings for safety benefits

Driving time savings table, safety table

Current Sta-tus Baseline & Problem to be Addressed

Change to Baseline/

Alternatives

Type of Impacts

Population Affected by Impacts

Economic Benefits

Summary of Results

Page/Table Reference in BCA

Minimal direc-tional signage and transit travel information, uncoordinated timings on bus routes

Cam-pus-wide ADA com-pliant, multimodal wayfinding system, screens with real-time transit arrivals in key campus facilities, im-proved bus stops with shelters and amenities

Easier multimodal navigation, improved reliability, safer public transporta-tion travel

Weekday CTA and UIC bus ridership of 3,538

Monetized value of lower travel times

$13,918,930 in net savings for transit time reductions

Transit time savings table

iv

Pedestrian Experience

Bicycle Network

Current Sta-tus Baseline & Problem to be Addressed

Change to Baseline/

Alternatives

Type of Im-pacts

Population Affected by Impacts

Economic Benefits

Summary of Results

Page/Table Reference in BCA

Current plazas and adjacent sidewalks are damaged and present dangers to users with disabilities

Repaired sidewalks, improved campus paths and plazas, pedestrian amenities, eco-friendly materials

Environmental enhancements, improved ac-cess to existing transportation facilities, cam-pus and local destinations

Full campus area population including visi-tors (approxi-mately 100,000 persons daily)

Monetized value of wa-ter savings, improved lifespan of surface im-provements

$95,416 in net savings for water benefit, and $60,664 in amortized savings for lifespan

Water sav-ings table, lifespan table

Current Sta-tus Baseline & Problem to be Addressed

Change to Baseline/

Alternatives

Type of Im-pacts

Population Affected by Impacts

Economic Benefits

Summary of Results

Page/Table Reference in BCA

Only one existing cross-cam-pus route which is a faded tradi-tional bike lane, lack of connections to city bike network

New cross-cam-pus desig-nated bicycle routes, pro-tected bike lane connect-ing campus to downtown Chicago, new bicycle facilities

Reduced vehicle col-lisions with bicyclists, reduction in emissions from cur-rent drivers switching to bicycle travel

All bicyclists (about 5.2% of cam-pus-area population)

Monetized value of low-er emissions from mode shift

$452,667 in net savings for mode shift from automobiles to bicycles

Mode shift environmen-tal benefits table

v

Parking Facilities

BENEFIT-COST ANALYSIS NARRATIVECrossroads and Connections creates a multimodal network throughout the UIC campus and onwards to neighboring communities. The network provides users with multiple choices of routes and modes that are optimized for safety, accessibility, travel time and environmental impact. The initiative Rein-forces Safe Circulation, Enhances the Sense of Place, Connects Hubs of Activity, and Integrates Campus and Community. It results in long-term economic and social benefits.

The benefit-cost analysis was conducted for a 20-year timeframe. The construction period is either 24 or 36 months, depending on the project. All project costs were assigned to the construction time pe-riod except for minor ongoing operating costs. Limited benefits for parking improvements will accrue during the construction period due to early implementation of the new payment system.

LONG TERM OUTCOME TYPES OF SOCIETAL BENEFITSState of Good Repair Increased facility life spans, lower operation costsEconomic Competitiveness Cost savings from energy improvements, value of

travel time savings, reduced travel costsQuality of Life Newly accessible destinations with options incorpo-

rating various modes of travelEnvironmental Sustainability Water savings, lower emissions from mode diver-

sionSafety Reduced crashes leading to lives saved and injuries

avoided

Current Status Baseline & Problem to be Addressed

Change to Baseline/

Alternatives

Type of Impacts

Population Affected by Impacts

Economic Ben-efits

Summary of Results

Page/Table Reference in BCA

Deteriorated pavement, no cam-pus-wide payment system, inadequate lighting and safety con-cerns

Eco-friendly pavement, rehabilitated surfaces, campus-wide payment system, long-lasting LED lighting, safety cam-eras

Safer, more eco-friendly parking lots, Reduced congestion and travel times

All mo-torists on campus (more than 7,000 at peak times)

Monetized value of cost savings from energy im-provements, lower operat-ing costs, travel time savings from new pay-ment system

$686,842 in net savings for energy im-provements, $16,999,862 for savings from lower waiting times, and $2,987,762 in net savings for reduction in parking operat-ing costs

Energy costs for parking ta-ble, parking lot waiting time reduc-tions table, operating costs for parking table

vi

PROJECT COSTSThe project costs include construction labor and materials. “Hard” and “soft” construction costs have all been monetized and incorporated into the relevant years of the analysis. Operating costs were included only for the individual factors that result in changes in operating costs.

The construction activities should pose minimal impact on adjacent communities. Roadway improve-ments are to be conducted within current right-of-way and the work can be completed with only minimal lane closures. Parking lot and structure improvements have been scheduled for nonpeak times during the campus summer session. Plaza construction will require some temporary closures to account for public safety but construction impact is sufficiently minimal therefore no calculations were made at this time.

PROJECT BENEFITSThe project benefits are evident in each of the primary TIGER selection criteria and benefits for all projects were considered with the “no-build” alternative. The included tables demonstrate the differ-ence in the monetized values that represent the benefits. The analysis was conducted using conser-vative estimates for population growth, mode shift, and growth factors for operating costs. Population growth factors were determined using CMAP’s GO TO 2040 population projections. The annualized growth factor for population is 1.0047. Growth factors used for operating costs were obtained using regional electricity rate information. Conservative assumptions were also used for elements specific to the individual benefits calculations.

The project locations and project elements were selected to ensure maximum value for people of all abilities travelling via many modes of transportation. The project improvements result in significant changes that will enhance state of good repair, foster environmental sustainability, enrich quality of life, and promote economic competiveness.

The benefit-cost analysis does not include any transfers or economic impacts. We do expect that the project will have positive economic impact from improved access to local businesses, events and em-ployment. The analysis only includes societal benefits.

References for assumed benefit and cost calculations are included in the individual tables. Data limita-tions and assumptions for individual calculations are also included in the attached tables.

State of Good RepairThe Lifespans and Energy Savings tables outline project features with amortized capital costs. Chang-es in operating costs were included before calculating the net annual savings. The build cost is the expected costs for the planned improvements. The cost foregone is the expected cost that would have been incurred for the baseline alternative. The benefits included are the net benefits after accounting for the amortized capital costs.

Crossroads and Connections project results in two primary State of Good Repair benefits:

•Improvedfacilitylifespan•Loweroperatingcosts

vii

Economic CompetitivenessCrossroads and Connections improves numerous intersections by optimizing traffic signals. The routes were selected to benefit the busiest university, local and regional bus lines. The improved in-tersections will result in more reliable and faster travel times. The benefit-cost analysis, which utilizes conservative ridership estimates, includes the impact on UIC, CTA and Pace bus riders. For CTA riders, the ridership is based on the number of weekday boardings in each respective activity hub. It does not include riders already onboard before the bus enters the area, nor weekend riders. Pace and UIC rider-ship was measured by the number of onboard customers and was limited to weekday riders. Motorists also benefit from optimized traffic signals resulting in shorter travel times. Average daily traffic counts were used to estimate number of motorists affected. The value for freight traffic was not monetized due to insufficient data. Two of the optimized corridors are primary truck routes.

Three parking structures will receive full lighting retrofits. All structures currently have high-pressure sodium lamps that are inefficient and need to be replaced every three years. All lamps will be replaced with energy efficient LED bulbs that will save energy, electricity costs and provide a longer life span. Parking facilities will receive a new payment system that reduces waiting time and increases capacity. The payment system also allows for a significant decrease in operating costs.

The economic competiveness of Crossroads and Connections can be established by:• Costsavingsfromenergyimprovements• Valueoftraveltimesavings• Reducedtravelcosts

Quality of Life Crossroads and Connections Integrates Campus and Community. By rehabilitating sidewalks and paths, providing new bicycle routes, and accessible intersection and mid-block crossings, the project opens up campus spaces to visitors and area residents. It provides the university community easier access to neighborhood amenities including parks, business districts, schools and museums. The enhanced access cannot be easily monetized, but is certainly significant.

The human experience is significantly enhanced by this initiative. The campus community gains access to new plazas, seating, accessible pedestrian paths, landscaping and wayfinding. These elements can-not be monetized on their own, but they result in a fully integrated campus and community.

People with disabilities are burdened by poor sidewalks, inaccessible intersection signals and facilities, wayfinding that lacks ADA compliance, and busy roadways. Crossroads and Connections ensures that all key routes leading to transit are accessible. This opens up a wider set of travel modes and desti-nations to people with disabilities. There are 5,501 persons with disabilities currently living within ¼ mile of the UIC campus. The total daily campus area disability population is significantly higher due to uncounted transient population at the four area hospitals (i.e. people with disabilities going to medical appointments) and UIC lacking a campus-wide tally of students and employees with disabilities.

The Accessibility table outlines the expected benefits for elderly and people with disabilities in gaining safe access to transit. The National Household Travel Survey figures were used to estimate travel pat-terns for the population of elderly and persons with disabilities near UIC. This population will shift mode of travel from personal vehicle to transit when roadway improvements, identical to those proposed in Crossroads and Connections, are implemented. The calculations assume a conservative 2% shift of travel by the subpopulation to transit, and results in significant reductions in travel expenses.The Quali-ty of Life in the university area is enhanced by:

• Newly accessible destinations and modes of travel

viii

Environmental Sustainability UIC is committed to being a climate-forward institution. Two parking lots and three plazas will receive porous concrete or permeable pavers. Water benefits accrue from the replacement of concrete and asphalt with porous material. This results in the significant savings of more than 1.7 million gallons of water per year. Due to the efficient Chicago-area water treatment system, the monetized costs are minor. Water savings monetization was conducted using marginal costs assuming that the quantity of water diverted was small enough to not require the use of full costs. The amount of heat emitted from parking areas and plazas will be reduced with the use of eco-friendly surfaces. However, we could not find an accurate estimate of the climate impact of this improvement.

Crossroads and Connections encourages people to use active transportation for trips within the uni-versity campus and to adjoining neighborhoods. The Multimodal Transportation Plan: Existing Condi-tions Report included a survey in which 28% of respondents revealed that they did not feel safe riding a bicycle on campus. Crossroads and Connections will address this issue by providing next-genera-tion bicycle facilities and intersections optimized for safety. The Multimodal Transportation Plan doc-umented that 14% of campus users drive a personal vehicle to and from campus. We assume that at most 28% of the 14% (=28% of 14%= 3.92%) of current drivers may switch from personal vehicle to bicycle after project improvements are completed. In efforts to calculate conservatively, we conduct-ed the benefit-cost analysis assuming only 1.96% of drivers will switch from car to bicycle (½ of the 3.92% high factor). The mode shift from driving to cycling results in savings from lower greenhouse gas emissions.

Crossroads and Connections projects result in these monetized environmental benefits:• Watersavings• Loweremissionsfrommodaldiversion

SafetyAt a monetized value, safety improvements account for the largest share of benefits resulting from Crossroads and Connections. Over 40 intersections and mid-block crossings will receive specific improvements to better pedestrian safety. High risk intersections and crossings were chosen after receiving vehicle crash data from 2008-2012 from the Illinois Department of Transportation (IDOT). Vehicle crashes with pedestrians and bicyclists were mapped and analyzed based on crash type, injury severity and cause of crash. After converting these crashes from KABCO format to Abbreviated Injury Scale (AIS), crash reduction factors from the Federal Highway Administration were used to determine the expected percent reduction in crashes. It is calculated that all of the proposed improvements will reduce vehicle crashes with pedestrians and bicyclists by 62%. The reduced crashes were then mone-tized using TIGER guidance based on injury severity and property damage. The attached spreadsheets illustrate the KABCO to AIS conversion, crash reduction factors and the value of crash savings.

The safety calculations are conservative in that they only include crashes involving pedestrians and bicyclists. It is likely that some additional crashes will also be avoided on the streets receiving new roadway improvements.

Safety enhancements result in these monetized benefits:• Livessaved• Injuriesavoided

ix

Letters of SupportPlease find evidence of community support and commitment of matching funds for Crossroads and Connections by visiting our TIGER website.

Federal Wage Rate Certificate