crr model building process bradley bell crr engineer
TRANSCRIPT
CRR Model Building CRR Model Building ProcessProcess
Bradley BellCRR Engineer
Intro: Model Building Intro: Model Building ProcessProcess
Model Building EnvironmentModel Building TimetableBuilding Contingency FileOutages / Outage Selection
ProcessRunning Topology ProcessorPost Processing Model
OverviewOverview
NMMS Database
Topology Processor
Transmission Outages
CRR Model
Model Building Model Building EnvironmentEnvironmentCRR Model Building Server
◦- IMM◦- TP
Snapshot of NMMS modelOne instance of NMMS model
Timeline (Monthly Model) Timeline (Monthly Model) PROCESS HOURS
Build Contingency File 16 hours
Outage Selection 3-8 hours
Run Topology Processor 24 hours
Post Process Model 16 hours
• Model building process will start 6-8 business days before model posting date on CRR calendar.
Outage Pull DateOutage Pull DateMonthly Auction Outage Pull Date
Dec 2010 10/ 6 /2010
Jan 2011 11/16/2010
Feb 2011 12/14/2010
Mar 2011 1/25/2011
Apr 2011 2/19/2011
May 2011 3/11/2011
Jun 2011 3/30/2011
Jul 2011 5/27/2011
Timeline (Annual Auction) Timeline (Annual Auction) 1st Model HOURS
Build Contingency File 16 hours
Outage Selection 3-8 hours
Run Topology Processor 24 hours
Post Process Model 16 hours
2nd – Nth Model HOURS
Build Contingency File 16 hours
Outage Selection 0 hours
Run Topology Processor 3 hours
Post Process Model 16 hours
Create Contingency FileCreate Contingency File
NMMS Model CIM Model
Contingency
Building Program
CIM Model Including
Contingencies
Create NOMCR containing CIM
Model w/contingenci
es
OUTAGESOUTAGES
Outage QueryOutage QueryWHERE outage.CATEGORY = 'Transmission‘ AND outage.planned_end_date >=
(ADD_MONTHS (TRUNC (LAST_DAY (SYSDATE) + 1), 1)) -- this gives you the current month plus 2 AND outage.planned_start_date <=
(ADD_MONTHS (TRUNC (LAST_DAY (SYSDATE) + 1), 2))-- this gives you the
current month plus 3 AND outage.status IN ('Apprv', 'Accpt')
OR ( outage.status = 'Withd’) AND outage.planned_end_date >= (ADD_MONTHS (TRUNC (LAST_DAY (SYSDATE) + 1), 1)) -- this
gives you the current month plus 2
AND outage.planned_start_date <= (ADD_MONTHS (TRUNC (LAST_DAY (SYSDATE) + 1), 2)) -- this
gives you the current month plus 3
AND outage.actual_start_date IS NOT NULL AND outage.actual_end_date IS NULL AND outage.CATEGORY = 'Transmission');
Outages / Outage Selection Outages / Outage Selection ProcessProcess Nodal Operating Guides 5.5(6): System Modeling Information
(6) Congestion Revenue Right (CRR) Network Model Outage determination uses network topology of the CRR Network Model identified by ERCOT. This must include Planned Outages of Transmission Elements approved by ERCOT at the time the CRR Network Model is being built and that demonstrate significant impact to the transfer capability during the effective period. ERCOT will consider including Outages in the CRR Network Model that are scheduled to occur in the relevant time period and meet one or more of the following criteria:
(a) Consecutive or continuous approved Outages greater than or equal to five days;
(b) Approved Outages which include Transmission Elements included in
the definition of a Hub; (c) Approved Outages which include Transmission Elements in a 345
kV Transmission Facility; (d) Approved Outages that require the use of a Block Load Transfer
(BLT); and (e) Any other approved Outage that has been determined by ERCOT to
carry a substantial risk of causing significant congestion.
Gantt ChartGantt Chart
Gantt ChartGantt Chart
Outage DatesOutage Dates
Nov. 6 outages Nov 12. outages
Line A 138kV Line A 138kV
Line B 138kV Line X 138kV
Line C 345kV Line Y 345kV
Line D 69kV Line Z 69kV
Outage Date SelectionOutage Date SelectionMarket Operator (MO) uses the base case
flows in the On-Peak SSWG case for the appropriate year and season to qualitatively estimate the severity of the outaged lines.
MO chooses the worst day of the month based on the evaluation from the step above as well as special consideration given to (in descending order) outages involving:◦ Lines in the W->N constraint ◦ Lines in the N->H constraint◦ Lines involved in other 2010 CSCs/CREs
MO imports the outages into TP the and builds the network model based on those outages.
Topology ProcessorTopology Processor
Create a basecase model and a model with outages
Insert dynamic ratings for each weather zone from 10 year historical average
Create RAW file and CRR output files
Post Process ModelPost Process ModelManually Create
◦Flowgate rights list and definition◦Contingency list and definition◦Non-Thermal Constraints list and
definition◦Monitored Lines and Transformers◦CRR to Operations name mapping
document◦Model Comparisons
QUESTIONS?QUESTIONS?