Software Project 1 / 2 / 3

Lecture 2: Scrum Basics

20.9.2017

Page 2: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Agenda

• Scrum Basics / Prof. Casper Lassenius

• Applying Scrum on this course / Jari

Vanhanen

21.9.2016

Page 3: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Basics

Prof. Casper Lassenius

Aalto University

21.9.2016

Page 4: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Goals of This Lecture

• Teach you

– Why you need a process for working in your projects

– Basics of the Scrum process

• Roles

• Process steps

• Terminology

• After this lecture

– You are able to participate in the Scrum game

– You know the basics of Scrum

• This lecture is based on

– Scrum Primer

– (Scrum Guide)

21.9.2016

Page 5: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Why Process?

• In an organization?

• In a corporate project?

• In your project?

21.9.2016

Page 6: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Why Scrum?

21.9.2016

Page 7: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Process:

21.9.2016

Page 8: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Roles

21.9.2016

Page 9: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Team

Scrum team = Team + Scrum Master + Product Owner

21.9.2016

Page 10: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Product Owner

• Responsible for maximizing

return on investment, thus has

the final authority

• Identifies product features

• Prioritizes the features

• Interacts regularly with the

team, e.g. reviews the Sprint

results

• Product Owner ≈ Product

Manager ≈ Customer

21.9.2016

Page 11: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

The Team

• Develops the product and provides ideas to the Product Owner about how to make the product great

• 7 ± 2 people

• Is cross-functional (includes all expertise necessary to deliver a potentially shippable product each sprint)

• Is self-managing: high degree of autonomy and accountability

• Every team member is just a team member, no other roles

21.9.2016

Page 12: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Master

• Helps the product group learn and apply

Scrum to achieve business value

• Is part of the Scrum Team

• Is NOT the manager of the team

members, NOR a project manager OR

team lead

• Serves the team, e.g. helps to remove

impediments, protects from outside

interference

• Is a coach and teacher, especially Scrum

principles and practices

• Who is the project manager in Scrum??

21.9.2016

Page 13: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Process

21.9.2016

Page 14: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprint / Iteration

• Time-boxed development cycles

• No more than 4 weeks, 2 weeks most common

• Never extended: ends exactly when planned, contents give flexibility

• The output of every sprint is: “Potentially Shippable Product Increment”, which means that item chosen for that sprint are “Done” (according to the DoD = Definition of Done)– System is integrated

– Fully tested

– End-user documented

– Potentially shippable

21.9.2016

Page 15: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprints (CS-C2130)

• At least six Sprints

– 225h / 6 = 37.5h

• In the beginning of the project, plan for each sprint

– start and end dates

– effort allocation per person

• Guidelines for the content of Sprint 0 and Last Sprint

13.9.2017

See Project Manual

Page 16: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprint 0 (CS-C2130)

• Sprint goal

– “Set up the project so that everything is ready for starting sw development work

from the first day of the following Sprint.”

• Main tasks

– product vision and initial Product Backlog

– prototyping, selecting and studying technologies

– selecting work methods and tools (e.g. how Scrum events will be done)

• Results presented also to the Coach

13.9.2017

Page 17: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Last Sprint (CS-C2130)

• Focuses on finalizing the product for the final delivery to the PO

• Some tasks

– acceptance testing by the Client

– bug fixing and finalization (no more new features)

– preparing an excellent software demo for the project review

13.9.2017

Page 18: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Product Vision / Release Planning

• No instructions given by Scrum

• Needed especially in case of a new

product

• The Product Owner and Team shape

a Scrum Product Backlog, including

– Planning the contents of the release

– Estimating, refining estimates

– Prioritizing

• May take a few days or a week…

• Not needed in continuous product

development, done by product

backlog refinements in every sprint

21.9.2016

Page 19: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Product Vision (CS-C2130)

1. Why?

– explain why the product is being built (the business view)

2. What?

– list the main goals for the product

– include critical quality attributes that are difficult to include in the

Definition of Done

3. For Whom?

– characterize the end users

21.9.2016

Page 20: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Product Backlog

• Is a prioritized list of customer-centric features

• “Everything that could be done by the Team ever in order of priority”

• Includes “items”, e.g. new customer features, major engineering improvement goals, research work, (known defects)

• Includes effort estimates

• Is detailed appropriately

• Is regularly refined (“grooming”) = splitting, estimating, re-estimating items

21.9.2016

Page 21: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Backlog Item

• Often two types

– Epic

– User story

• Should be in a (real) backlog management tool

– Jira, Trello, Agilefant, VersionOne, …

• Product backlog

– Size estimates in story points

• Sprint backlog

– Effort estimates as hours (or story points)

– Rules for updating effort left

21.9.2016

Page 22: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

User Stories and Epics [1]

• User story

– Basic format: “As a [type of user] I [want/can/am able to/need to/etc.] so that [some reason].”

– Can be in other formats, as long as the above aspects are covered

– Works well for functional requirements, less well for quality attributes

– Can be implemented in one Sprint

• Epic

– Basically a “big user story”, i.e. cannot be implemented in a single sprint

– Usually broad in scope, short on details, and will commonly need to be split into multiple, smaller stories before the team can work on them

21.9.2016

[1] https://www.scrumalliance.org/community/spotlight/mike-cohn/march-2014/agile-user-stories-epics-and-themes

Page 23: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Scrum Board

21.9.2016

Page 24: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprint Planning I

• Participants: Product Owner,

Team, Scrum Master

• Goal: understanding WHAT

the Product Owner wants and

WHY they are needed

• Discussion of the goals

context of the highest priority

items

– PO explains

– Team asks questions

21.9.2016

Page 25: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprint Planning II

• Participants: Team, Scrum Master (Product Owner reachable for questions)

• Focus on HOW to implement the items the Team decides to take on– Team decides how much work it will

complete!

• May contain:– Estimating the team’s capacity for the next

sprint

– Overall design

– Selecting and splitting product backlog items into tasks – building sprint backlog!

– Estimating items/tasks

– Selecting as many items team estimates they can realistically complete: sprint “commitment” / forecast

21.9.2016

Page 26: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Daily Scrum Meeting

• Participants: Team, Scrum Master (Product Owner optional)

• Update and coordination between team members – not a status reporting to anybody else

• Max 15 min

• Each member report to the other team members:– What has been accomplished since the

last meeting?

– What will be done before the next meeting?

– What obstacles are in the way?

• If discussion needed: follow-up meetings agreed and held afterwards

21.9.2016

CS-C2130

• Once / week

• F2F preferable

• Synchronous online

possible

Page 27: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Definition of Done

• Defined what is needed for something

(e.g. task, backlog item, sprint) to be

considered “DONE”

• Sometimes people say it is ”done-done”

to mean it meets the criteria for DoD

• You must define your own DoD (and

follow it!)

• Often at several levels

– Task, User story, Sprint

• Typically things like

– Code is implemented, commented, integrated,

reviewed/tested

21.9.2016

CS-C2130, minimum DoD:

• unit testing

• functional system testing

• coding standard

Page 28: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprint Review

• Participants: Team, Product Owner,

Scrum Master, other stakeholders

invited by the Product Owner

• Inspection and adaption related to the

product increment of functionality

– What is going on with the product and team

– What is going on with the Product Owner

and the market

– In-depth conversation

– Includes hands-on inspection of the real

software running live

21.9.2016

Page 29: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Sprint Retrospective

• Inspection and adaption related to the process and environment

• Participants: Team, Scrum Master, Product Owner (optional)

– Team discusses what’s working and what’s not working and agree on changes to try

– Usually the Scrum Master facilitates

– Different techniques, try different ones!

21.9.2016

Page 30: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Being Efficient: Doing a Sprint Change

• In one sitting

– Sprint review

– Retrospective

– Sprint planning

• Ca 0,5 days

• Requires access to Product Owner

– Sprint review

– Sprint Planning I & III

21.9.2016

Page 31: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Tracking Progress

Burndown / burn-up charts

21.9.2016

Page 32: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Want to Know More?

• Google

– Scrum Guide

– Scrum Primer

21.9.2016

Page 33: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

QA & Testing

• Define and deliver minimum content agreed with

Product Owner

• Define and test quality attributes (non-functional

requirements)

• Peer testing (as defined by the course)

21.9.2016

Page 34: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

What if Scrum Does Not Work for Us?

• Try it (for real) first

• If you really need to change it

– Make a motivated proposal

– Try the changed version

21.9.2016

Page 35: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

End of Scrum Basics

21.9.2016

Page 36: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Additional requirements for the course

projects

• Project Reviews

• Process Overview Document

• Technical Overview Document

• Time Tracking

• Learning diary

13.9.2017

See Project Manual

Page 37: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Project Review (CS-C2130)

• December, February and April

• Participants– student team, coach, teacher, PO, and possibly other people (Accenture, guests)

• Team presents data on the project status and the results (software demo)– status of Sprint Goals and selected Product Backlog items

– main findings from Sprint retros

– software quality

– effort usage per person

• After each project review, PO and coach evaluate the project

13.9.2017

See the Progress report template

Page 38: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Document – Process Overview

(CS-C2130)• Document briefly the currently used work practices and tools so that

all stakeholders can understand how the team works

• Minimum content

– project schedule and effort

• Sprints

• other main events (Project Reviews, team work sessions)

– recurring events of the Sprints (how and when)

• Sprint Planning, Daily Scrums, team work sessions, Sprint Review, Sprint Retros

– other main practices and tools

• project work (backlogs, time tracking, communication etc.)

• development (version control, testing etc.)

13.9.2017

See the template

Page 39: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Document – Technical Overview

(CS-C2130)• General goals

– Helping the Scrum Team during the project, e.g., in communicating about the

design or in dividing responsibilities

– Meeting the Client's needs after the project

• Very project specific

• Minimum content

– Document briefly the most important architectural design decisions

– Document one or more relevant views of your architecture design

• see e.g. 4+1 architectural view model

13.9.2017

Page 40: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Time Tracking (CS-C2130)

• Total effort spent per student per each Sprint

– must be available to the Scrum team and Coach

– must be updated at least weekly

• impossible to remember what you did last week

• Some backlog management tools support time tracking

• Spreadsheet can work too

– if you are not interested in task level tracking

13.9.2017

See Google Sheet

example

Page 41: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Learning diary (CS-C2130)

• Write a new entry to your diary just before each Project Review

1) three educational observations related to the use of Scrum or other work

methods

2) a summary of your main contributions to the project since the previous entry

• Furthermore, write an entry about the Scrum Game immediately

after your participation

13.9.2017

Submitted individually

to MyCourses.

Page 42: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Summary of the required artifacts

(CS-C2130)• Product vision (see Template)

• Product backlog

• Sprint Goals of the current and completed Sprints

• Sprint Backlog of the current Sprint

• Definition of Done

• Test session charter(s) for peer testing (see Template)

• Allocated and spent effort per person per Sprint

• Process overview (see Template)

• Technical overview

• Progress report / Final report slides (see Template)

• Learning Diaries

13.9.2017

Send a link to the materials to the teacher, coach and PO

– 24 hours before each project review

Page 43: CS-C2130 / CS-C2140 / CS-E4910 Software Project 1 / 2 / 3 · – Basics of the Scrum process • Roles • Process steps • Terminology • After this lecture – You are able to

Next Steps

• CSM Training

• Scrum Game

– Scrum Masters will get a “game manual” by e-mail two days before their session

• Don’t give it to the team members!

– Session 3 (Fr 13.10.) cancelled

– Session 1 (Mo 2.10.) registrations immediately

• sandwiches etc. will be ordered tomorrow morning!

• Lecture on We 4.10. 16:15-18 in T4

– for Scrum Masters only

• Sending Team CVs to Clients 11.10. ->

21.9.2016