CS Capital Programme
Peter ColenuttHead of Strategic Development
2015/16 – 2017/18
![Page 3: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/3.jpg)
• National funding policy – Basic Need and Capital Maintenance
• Approved by County Council 19 February 2015
• Role of Local Authority to strategically plan school places and capital investment
Children’s Services Capital Programme
• Exciting investment £229m
![Page 4: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/4.jpg)
Children’s Services Capital Programme (continued)
• Where appropriate, alignment of Capital Maintenance
• 11,000 new primary places across Hampshire (Secondary to follow)
• Potential basic need projects listed-Table 5
![Page 5: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/5.jpg)
Priority Investment Areas
• New School Places• Maintenance of Existing Buildings• Education Centres• Special Education Needs• Children’s Homes• Proposed 3 year programme-Table 6
![Page 6: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/6.jpg)
3 Year Capital Funding Summary
• New School Places - £124m
• Capital Maintenance - £55m
• School Devolved Formula Capital allocation – £10m
![Page 7: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/7.jpg)
Schools’ Devolved Formula Capital Allocation
2015/16 Formula(assumed)
Allocation per school £ p.a.
Per nursery/primary pupil
11.25
Per secondary pupil 16.88
Per special school or education centre pupil
33.75
Lump sum (all schools)
4,000.00
![Page 8: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/8.jpg)
Pressures on the Capital Programme
• Sufficient resources to fund 3 year programme
• Ongoing Primary places until at least 2018/19
• Secondary places – report July 2015
• Inflation in construction market
• Size of programme
• CIL
![Page 9: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/9.jpg)
Design Issues
• Low Cost Schools
- 2 storey solutions - Reduced floor area - Common design and
specification - Core landscape and external
works - Constructing in batches• Still good quality, built to last
![Page 10: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/10.jpg)
![Page 11: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/11.jpg)
Barncroft Primary School, Hampshire
(Before) (After)
![Page 12: CS Capital Programme Peter Colenutt Head of Strategic Development 2015/16 – 2017/18](https://reader036.vdocuments.net/reader036/viewer/2022062313/56649d755503460f94a552f8/html5/thumbnails/12.jpg)
Current and Future Years Programmes
• Projects listed Section 14-17
• Recommendations Section 19