csf - 002
DESCRIPTION
99TRANSCRIPT
-
CONSOLIDATED CONSTRCUTION CONSORTIUM LTD FORMAT NO.: CSF - 002
REV. NO. 1 DATE : 19-01-2010
HAZARD IDENTIFICATION AND RISK ASSESSMENT PAGE 1 OF 2
Project Name: Date: Project Code:
HAZARD IDENTIFICATION & EVALUATION SECTION / DEPARTMENT: ACTIVITY :
SUB ACTIVITY HAZARD
HI No LEGAL
SEVERITY
OCCURRENCE I =S*O
MAJOR RISK (Y/N)
MP/ OCP
(HI No.- Hazard Identification Number; I = S*O - Score for Hazard Impact; MP/OCP- whether could be addressed through Management Programme or Operational Control Procedures) (Note: 1. Severity and Occurrence Ratings could be: 1, 3, and 5. 2. If I = S*O is greater than or equal to 9, then the Hazard is a Major Risk)
-
CONSOLIDATED CONSTRCUTION CONSORTIUM LTD FORMAT NO.: CSF - 002
REV. NO. 1 DATE : 19-01-2010
HAZARD IDENTIFICATION AND RISK ASSESSMENT PAGE 2 OF 2
RESIDUAL RISK ANALYSIS
Major Risk Activity
Hazard Consequence
Current Risk Control
Measures HORCM*
Proposed Risk Control
Measures Residual Risk
I =S*O
I- Impact Score, S- Severity, O- Occurrence * HORCM : Hierarchy of Risk Control Measures
This can be any of the following Elimination (ELI) Substitution (SUB) Isolation (ISO) Engineering Control (ENC) Administrative Control including Signage (AC) Personal Protective Equipment (PPE)