Monthly Progress Report
Page | 1 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Cochin Smart Mission Limited
PMC to Implement
Area Based Development
Monthly
Progress
Report
May 2019
Kochi Smart City
Monthly Progress Report
Page | 2 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Cochin Smart Mission Limited, 10th Floor, Revenue Tower, KSHB, Opposite Ernakulam
Boat Jetty, Ernakulam
Monthly Progress Report
1565/MPR- 15(15/30)/May 2019/R0
Project Management Consultant (PMC)
to implement Area Based Development
Smart City Kochi
Cochin Smart Mission Limited, CSML
Monthly Progress Report
Page | 3 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 4 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
EXECUTIVE SUMMARY ..................................................................................................................................... 6
1 STATUS AS ON 31ST MAY 2019 .................................................................................................................. 9
1.1 STAKEHOLDER MEETINGS CONDUCTED ................................................................................................. 13
1.2 SITE VISITS .............................................................................................................................................. 16
1.3 BRIEF SUMMARY OF KEY MEETINGS ....................................................................................................... 20
2 STATUS OF ABD PROJECTS ...................................................................................................................... 29
2.1 STATUS OF ABD PROJECTS ...................................................................................................................... 29
2.1.1 DEVELOPMENT OF OTHER ROADS IN ERNAKULAM.......................................... 35
2.1.2 DEVELOPMENT OF SMART ROADS IN ERNAKULAM ......................................... 37
2.1.3 DEVELOPMENT OF SMART ROADS IN WEST KOCHI ......................................... 39
2.1.4 INTELLIGENT TRAFFIC MANAGEMENT SYSTEM(ITMS) ............................. 41
2.1.5 SOLAR ROOFTOP PROJECT IMPLEMENTATION PROGRESS ............................................................. 44
2.1.6 HOUSEHOLD BINS AND BINS IN PUBLIC PLACES ............................................................................. 48
2.1.7 PUBLIC BIKE SHARING IMPLEMENTATION PROGRESS .................................................................... 52
2.1.8 CANCER BLOCK- GENERAL HOSPITAL .............................................................................................. 59
2.1.9 E-HEALTH SOLUTION FOR GENERAL HOSPITAL ............................................................................... 60
2.1.10 INTEGRATED COMMAND CONTROL & COMMUNICATION CENTER ............................................ 66
2.2 NEW PROJECTS PROPOSED ..................................................................................................................... 68
2.3 UPDATED INTEGRATED PROJECTIVISATION ........................................................................................... 69
2.4 OVERALL PROGRESS ............................................................................................................................... 81
2.5 SECTOR PROGRESS ................................................................................................................................. 82
2.6 IMPLEMENTATION SCHEDULE ................................................................................................................ 83
3 WAY FORWARD .................................................................................................................................... 102
3.1 KEY CONCERNS ..................................................................................................................................... 102
3.2 ISSUES AND CONCERNS ........................................................................................................................ 102
3.3 ASSISTANCE REQUIRED ........................................................................................................................ 102
3.4 WAY FORWARD FOR FEW PROJECTS .................................................................................................... 104
3.5 OVERALL STAKEHOLDER ROLES & RESPONSIBILITIES ........................................................................... 105
4 SMART CITY PROJECTS IN MEDIA COVERAGE ........................................................................................ 108
ANNEXURES ................................................................................................................................................. 112
ANNEXURE 1: STAKEHOLDER MEMOS ............................................................................................................. 112
ANNEXURE 3: LIST OF PROJECTS UNDER IMPLEMENTATION BY SPV............................................................... 139
ANNEXURE 5: PROJECT PROGRESS .................................................................................................................. 142
List of Tables
TABLE OF CONTENTS
Monthly Progress Report
Page | 5 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
TABLE 1-1: STATUS OF PROJECTS IN PROGRESS ....................................................................................................... 9 TABLE 1-2: SUMMARY ON STAKEHOLDER CONSULTATIONS BY PMC TEAM DURING THE MONTH OF MAY 2019 ............... 13 TABLE 1-3 SUMMARY OF SITE VISITS CONDUCTED DURING THE MONTH OF MAY 2019 .................................................. 16 TABLE 1-4 SUMMARY OF SUPERVISION OF SITES CONDUCTED DURING THE MONTH OF MAY ......................................... 17 TABLE 2-1: ACTION FOR KMC TO ENABLE TENDERING BY END OF SEPTEMBER 2019 ................................................... 58 TABLE 3-1: PROJECTS REQUIRING STAKEHOLDER ASSISTANCE ................................................................................ 103 TABLE 3-2: PROJECTS PROPOSED TO BE DROPPED FROM CENTRAL MIS .............................................................. 104
LIST OF PHOTOGRAPHS
FIGURE 1-1 INSTALLATION OF SOLAR PANELS ......................................................................................................... 19 FIGURE 1-2 EXISTING TRUSS AT MAHARAJA BOYS HOSTEL ....................................................................................... 19 FIGURE 1-3 FORT KOCHI JAIL ................................................................................................................................ 20 FIGURE 1-4 AUTOMATED CAR PARKING FACILITY AT KALOOR ................................................................................... 20 FIGURE 1-5 JLN METRO STADIUM FOR SETUP OF COMMAND AND CONTROL CENTRE ................................................ 20 FIGURE 1-6 CRUSHER PLANT FOR CONTRACTOR- ROAD PROJECT .......................................................................... 20 FIGURE 1-7 EXISTING BRIDGES AT THURUTHY ....................................................................................................... 20 FIGURE 1-8 EXISTING ROAD CONDITION FROM JOS JN. TO CHITTOOR ROAD ............................................................ 20 FIGURE 1-6 KICK-OFF MEETING IC4 ...................................................................................................................... 21 FIGURE 1-7 CITY INNOVATION LAB- WORKSHOP ...................................................................................................... 22 FIGURE 1-8 KICK-OFF MEETING ITMS ................................................................................................................... 25 FIGURE 1-9 MEETING WITH ENGINEERING STAFF-KMC............................................................................................ 28 FIGURE 2-1 LOCATION MAP- SMART ROAD ERNAKULAM .......................................................................................... 39 FIGURE 2-2 SMART ROAD - WEST KOCHI ............................................................................................................... 41 FIGURE 2-3INSTALLATION OF SOLAR PANEL AT GENERAL HOSPITAL .......................................................................... 46 FIGURE 2-4SOLAR PANEL INSTALLATION WORK AT FIRE STATION, GANDHINAGAR ....................................................... 46 FIGURE 2-5 PANEL INSTALLATION OF TOWN HALL .................................................................................................... 46 FIGURE 2-6PANEL INSTALLATION OF CENTRAL OFFICE, KSEB ................................................................................. 47 FIGURE 2-7PANEL INSTALLATION OF CENTRAL OFFICE, KSEB ................................................................................. 47 FIGURE 2-8GOVT. HIGH SCHOOL, EDAPALLY .......................................................................................................... 47 FIGURE 2-9 COURT COMPLEX ERNAKULAM ............................................................................................................. 47 FIGURE 2-10 HOUSEHOLD BINS ............................................................................................................................. 49 FIGURE 2-11PBS LOCATIONS (BASE MAP BY PMC AND LOCATIONS PLOTTED BY SMART-SUT).................................... 54 FIGURE 2-12 ERNAKULAM MARKET REDEVELOPMENT – PROJECT PLANNING ............................................................. 57 FIGURE 2-13 ACTION TO BE TAKEN PRIOR TO TENDERING OF THE PROJECT ................................................................ 57 FIGURE 2-14 LOCATION OF PROPOSED CANCER BLOCK ........................................................................................... 60 FIGURE 2-15 STRUCTURAL OUTLINE OF E-HEALTH SOLUTION ................................................................................... 62 FIGURE 2-16 IDENTIFICATION OF TOURISM PROJECTS .............................................................................................. 65 FIGURE 2-17 INTEGRATION OF SMART SOLUTIONS WITH IC4 .................................................................................... 68
Monthly Progress Report
Page | 6 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
EXECUTIVE SUMMARY
The smart city proposal of Kochi submitted for Smart Cities Challenges aims at integrating the
Fort Kochi & Mattancherry area with Central City Area through Water Metro. Thematic areas
for interventions under smart cities mission in Kochi are
• Seamless Mobility
• Reconstitution of Urban Form
• World Class Urban Services & Inclusive Development
• Revival of Identity and Culture
The Smart City proposal of Kochi has adopted retrofitting as the strategy for development
under the Mission. The vision for Kochi is to transform Kochi, into a sustainable, inclusive and
economically vibrant city of opportunities with efficient urban services, traditional hospitality
and smart governance.
a) Area Based Development (ABD) projects
Area Based Development (ABD) as part of Smart City development consists of parts of five
wards west Kochi (1,2,3,4 and 5) and parts of three wards of mainland of KMC (62,66 & 67),
with a total area of 1024.16 acres. There are currently are 64 ABD projects under 18 modules
worth a total cost of Rs. 1323 Crores. Of these 15 projects are those where project scope is
being discussed and confirmed by the stakeholders
The overall status of ABD projects is as follows:
(Amount in INR Crore)
Source of funding / status Sum of Project Cost /SCP cost No of Projects
DPR Prepared 21.66 6
DPR Under Preparation 174.30 13
Tender Issued 276.69 11
Work order issued/Project Under Implementation 267.62 10
To be re-tendered 73.95 4
Fund Transfer 34.00 2
Project scope to be confirmed by stakeholders 156.95 14
SCM 1,005.17 60
DPR Prepared 1.00 1
Tender Issued 301.58 1
Work order issued/Project Under Implementation 10.00 1
PPP 312.58 3
DPR Under Preparation 83.75 10
Project Completed 4.78 2
Tender Issued 96.00 2
Work order issued/Project Under Implementation 55.34 5
Other Sources 239.87 19
Grand Total 1,557.62 82
Monthly Progress Report
Page | 7 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Note: Detailed list provided in annexure
*information as per data provided by Tourism dept. and KWA
Pan City projects
Pan city projects are convergence projects and being implemented by stakeholders. As part of SCP two projects
were proposed as Pan City projects. Smart Card - Kochi 1 is a PPP project and implemented by KMRL. 24 X 7
WATER SUPPLY is being taken up by KWA for implementation.
Source of Fund No of Projects Project Estimated Cost (If any) or SCP cost
PPP
Project Completed 1 25
Other Sources
DPR to be prepared 1 621
Grand Total 2 646
Note: * As data received from KWA
Status of Smart City Mission Kochi as on 31st May 2019
Total Project Cost- including convergence
Rs 2,203.62 cr
Central Assistance Released Rs. 196 cr
State Grant Released
Rs 200 cr
Central Assistance
Approved
Rs. 500 cr
Tender Issued (Ongoing)- SPV
Projects 12
Cost Rs. 578.28 cr
Work Order issued/Project yet to start - SPV
Projects 11
Cost Rs. 277.61 cr
Monthly Progress Report
Page | 8 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SUMMARY OF PROGRESS BY PMC IN THE MONTH OF MAY 2019
CUMMULATIVE DELIVERABLES SUBMITTED BY PMC AS ON 31ST MAY
Monthly Progress Report
(1 Report, April 2019)
Revised BoQ/Estimates
(1 Project)
EIA Report
(5 Projects)
Project (Stakeholder)
meetings (19 Nos)
Supervision - Site Visits
(20 Nos)
Situation Analysis Report
(1 Report)
Feasibility Reports
(48 Projects)
Monthly Progress Reports
(18 Reports)
Detailed Project Reports
(31 Projects)
RFP/Tender Submitted
(24 Projects)
EoI & related Reports
(2 Projects)
Tender Issued
(24 Projects)
Draft BERs prepared
(21 Projects)
Draft CERs prepared
(10 Projects)
Site Visits
(13 Nos)
Concept Note
(1 Project)
Monthly Progress Report
Page | 9 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
1 STATUS AS ON 31ST
MAY 2019
In the month of May, the Smart City team worked on Bid evaluation of the tendered projects,
In the month of May, the Smart City team worked on Bid evaluation of the tendered projects,
BoQ revision for the West Kochi Road and Tourism Projects. Environmental Impact
Assessment for Clavathy School, Fort Kochi taluk and Mattancherry Hospital, Open air
Theatre and Public Toilets has been prepared and submitted. Detailed Project Report for
Open Space, Anganwadi, Museum for Freedom Struggle along with several other projects
are in progress.
The status of projects under Smart City is given below;
Table 1-1: Status of Projects in progress
Sl No
Project Name Cost in INR Cr.
Status Date of Submission
of Feasibility
Report
Date of Submission
of DPR
1. Smart Water solutions - Smart Metering and smart valves for all connections in ABD
1.00 Feasibility report preparation under progress.
2. Rainwater structures in 13 Govt bldgs & Institutions
0.75 Feasibility Report submitted 21-03-2018 Now under convergence
3. Improvements to sewer collection system for West Kochi
154.50 Project Tendered 07-02-2018/ 11-09-2018
20-02-2019/ 28-02-2019/ 05-03-2019
4. Improvements to sewer collection system for Mainland
34.50 Renamed - As Elamkulam STP INR 13 Cr. taken up by KWA. Scope for mainland to be confirmed by KWA
5. Development of Other Roads in Ernakulam ABD
43.60 LOA issued on 9th April 2019 10-08-2018 30-08-2018
6. Development of Other Roads in West Kochi
60.20 Project Re-tendered 10-08-2018 30-08-2018
7. MLCP and at Kacheripady 6.16 Project to be re-tendered
06-02-2018/ 07-10-2018
07-02-2019
8. Commercial complex at Kacheripady
5.00 Scope to be confirmed by stakeholder
9. MLCP at GCDA 10.00 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin
07-10-2018
10. MLCP at KTDC 7.00 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin
07-10-2018
11. Smart Parking Solutions in ABD area
1.90 DPR under preparation 07-10-2018
12. Development of Smart Roads in Ernakulam
61.53 LOA issued on 9th April 2019 10-08-2018 30-08-2018
13. Development of Smart Roads in West Kochi
30.31 LOA issued on 9th April 2019 10-08-2018 30-08-2018
14. Intelligent Traffic Management Systems (ITMS)
26.90 Contract Agreement signed on 16th May 2019
02-02-2018
06-02-2018
15. Road Signages for ABD 2.40 DPR Submitted 15-02-2019 18-02-2019
16. FOBs - West Kochi (3 Nos) 2.15 DPR under preparation 27-09-2018
17. Development of Smart Roads electrical infrastructure in Ernakulam & West Kochi under Smart City Mission
63.40 Project to be re-tendered
10-08-2018 30-08-2018
Monthly Progress Report
Page | 10 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Project Name Cost in INR Cr.
Status Date of Submission
of Feasibility
Report
Date of Submission
of DPR
18. Implementation of Smart LED lighting in ABD
32.09 Tender published and bids submitted. Bid evaluation under progress
12-02-2018 17-02-2018
19. Intelligent Street Poles (PPP) 301.58 Tender has been floated. Technical Bid evaluation under progress
08-02-2018/ 01-03-2018
15-11-2018/ 08-02-2019
20. Solar panels in Govt. buildings 5.70 Contract awarded. Project under implementation.
02-02-2018
07-02-2018
21. Solar panels in canals and backwaters
0.50 Project to be developed with Canal project proposals
22. Smart & Improved Secondary Storage & Transportation of Solid Waste using Portable Compactor Technology
4.4 Project to be re-tendered. 14-02-2018
20-03-2019
23. Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area
1.00 DPR submitted 26-02-2018
28-02-2018
24. Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area
3.2 Project to be re-tendered. 20-03-2018
20-03-2018
25. Distribution of Household Bins & Street Litter Bins for improvement of waste segregation in ABD Area
0.67 LOA issued on 8th May 2019 07-02-2018
28-02-2018
26. Public toilets in West Kochi & Ernakulam
1.80 Tender issued Technical Bid evaluation under progress
27-09-2018
13-02-2019
27. Development of Open Space and Playground in ABD
2.50 DPR will be submitted by 20th June
26-03-2019
28. Improvements to Marine Drive Walkway Phase I
7.10 Tender issued 03-11-2018
11-11-2018/ 04-02-2019/ 27-02-2019
29. Mangalavanam Eco-restoration project
1 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin
30. Restoration of Mullassery canal - including linking of standardized area drains
1 DPR under preparation 02-03-2019
31. Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts
5 DPR under preparation 02-03-2019
32. Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features
20 DPR under preparation 02-03-2019
33. Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road
15 DPR under preparation 02-03-2019
34. Bicycle Sharing (PPP) 10 Contract awarded. Work under implementation
02-03-2018
35. Walkway from Ekm Jetty to Metro station
4.70 Word awarded Under implementaion
Monthly Progress Report
Page | 11 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Project Name Cost in INR Cr.
Status Date of Submission
of Feasibility
Report
Date of Submission
of DPR
36. Integrated Command, Control and Communication Centre (IC4)
64.5 LoA has been issued. Project kick off meeting took place on 6th May 2019
15-05-2018
20-05-2018
37. Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
0.60 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin
38. Standard Wifi Enabled Bus Stands With Commercial space development
3 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin
39. Integrated redevelopment of Slum housing
46.85 KMC to confirm scope. Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest.R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited.
40. Beneficiary LED Housing 13.00 KMC to confirm list of beneficiares. KMC to share gap funding required and final list of beneficiaries.
41. Construction & upgradation Thuruthy, Kalvathy & Konchery colony - Construction of Bridges
5.15 Bridge & social infrastructure project proposed under SCM. Feasibility report submitted.
In principle agreed in 1 December 18 meeting with DUA. Post approval of FR, DPR to be prepared
27-09-2018
42. Construction of First tower at Thuruthy
21.00 Scope is being finalised
43. Construction of Second tower at Thuruthy
35.00 KMC to confirm scope. Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest.R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited.
44. Broadway Street Pedestrianization
10 Feasibility report submitted
DPR under preparation. KMC to share list of hawkers and carry out R&R.
15-10-2018
45. Ernakulam Market Redevelopment+ Escalator
100 Feasibility report submitted
DPR under preparation. KMC to share list of vendors &
15-09-2018
Monthly Progress Report
Page | 12 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Project Name Cost in INR Cr.
Status Date of Submission
of Feasibility
Report
Date of Submission
of DPR
FOBs+ Elevated Walkways and Travelators
hawkers and also identify land for transit shops.
46. Mattancherry spice market Redevelopment
Scope under discussion with stakeholders. Soft improvements already proposed along with road project
47. Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"
5.60 Petti kada draft design ready KMC to share final list of licensed hawkers. The Hawker Zones Project is included under Fort Kochi Beach improvements project.
48. Scale up of GH into a Super- Specialty care centres (Cancer Ward)
26.00 LoA Issued to INKEL 10-07-2018
49. New Block at Fort Kochi Taluk Hospital
4.65 Tender issued 28-02-2018
17-03-2018/ 30-10-2018
50. New Block of Mattancherry Women & Children Hospital
4.57 Tender issued 28-02-2018
28-03-2018 13-11-2018
51. E-health solutions for selected hospitals
3.71 LoA issued. Contract Agreement to be signed
15-09-2018
20-12-2018/ 07-02-2019
52. Upgradation of Anganwadi Centres in West Kochi
2.00 DPR under preparation 06-04-2019
53. Higher secondary block, Central Calvathy GHSS, Fort Kochi
4.67 Project to be re-tendered 28-02-2018
15-07-2018/ 03-12-2018
54. Smart Classroom for 100 classrooms PAN city
4.90 Tendered cancelled 05-02-2018
09-02-2018
55. Safety & Security CCTV surveillance
14.56 DPR Submitted 21-01-2019 21-03-2019
56. Upgradation of Community Centre at Mattancherry with indoor sports facilities
1.00 As per KMC to community centre avaialbe requiring upgradation. Hence project may be dropped. KMC to confirm formally.
57. Open Air Theatre at Fort Kochi Zonal office
1.30 Tender issued 14-Aug-18 Rev- 10-Oct-18
06-02-2019
58. Development of Dutch palace node parking area and palace street entry
1.10 Tender issued
20-12-2018
20-02-2019
59. Fort Kochi Beach Front improvements - Part A Vasco Square
1.71 Project to be re-tendered
20-12-2018
28-02-2019
60. Museums of Freedom Struggle 1.20
Feasibility report Submitted.
20-12-2018
61. Museum of Spices 1.50 20-12-2018
62. Development of Ethnic Food Hub & Dutch Quay Upgradation
1.00 20-12-2018
28-02-2019
63. Fort Kochi Beach Front improvements - Part B Walkway & Beach
8.42 20-12-2018
Monthly Progress Report
Page | 13 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Project Name Cost in INR Cr.
Status Date of Submission
of Feasibility
Report
Date of Submission
of DPR
64. Mattancherry Walkway 11.00 20-12-2018
65. Art Installations in Kochi / Cultural Corridor- PT Usha Road
1.00 Feasibility report under preparation
66. Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres
0.40 Detailed Project Report submitted on 21st December 2018. KMC is taking up the project based on scope shared. KMC to tender the project at the earliest.
21-12-2018
1.1 STAKEHOLDER MEETINGS CONDUCTED
Stakeholder meetings conducted in the month of May are as follows:
Table 1-2: Summary on Stakeholder Consultations by PMC team during the month of May 2019
S. No
Date of Consultation
Module Content
Stakeholder Consultation
Concerned Person in the Department
Agenda Discussion by PMC Team
Remarks
1. 03/5/2019 SWM- Public Toilet
Fort Kochi Village Office
Official of the Fort Kochi Office
To collect Public Toilet Survey Sketches
Discussed regarding Public Toiler survey at Fort Kochi
2. 03/05/2019 Park and Open Space
KMC Ms. Shiny Mathew, Councillors Ms. Zeenath, Councillors
Upgradation of parks and open spaces in ward no: 1 and 2.
concept prepared were discussed with respective ward councillors
3. 04/05/2019 Park and Open Space
GCDA Mr. V. Saleem, Chairman, GCDA Mr. Rajesh, Senior Town Planner, GCDA (point of contact with GCDA) Representatives from various GCDA departments
Marine Drive Walkway proposal
CSML to forward an official letter to GCDA (within a week), along with a project brief and detailed drawings explaining the exact scope of intervention, and clarifications on maintenance of infrastructure, advertisement areas, potential revenue and issues post CSML’s maintenance period. Detailed MoM is attached in annexure 1.
4. 04/05/2019 Housing KMC Superintending Engineer
RAY Project Discussed with SE pertaining to the RAY project which is being implemented by KMC
5. 06/05/2019 Economy and Employment
Ernakulam Market Association
Ernakulam Market Stall Owner’s Association(EMSOA)
Understand the functioning of market and conclude on a suitable proposal for Market redevelopment
MD, CSML requested all the representatives of EMSOA to confirm and agree to the proposal of market redevelopment and assured that the proposal would only be having ground floor and
Monthly Progress Report
Page | 14 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Date of Consultation
Module Content
Stakeholder Consultation
Concerned Person in the Department
Agenda Discussion by PMC Team
Remarks
2 upper floors along with a basement. EMSOA expressed their support for the proposal and also confirmed that some stalls shall be shifted to the 1st floor in the new proposal which would include, Fish, meat, poultry and some other goods. EMSOA insisted that the ground floor plinth height be reduced in order to facilitate easy loading of goods by labour workers. CSML explained the use of push/pull carts and trolleys to be used within the market complex to assist the movement of goods. Detailed MoM is attached in annexure 1.
6. 7/5/2019 Others (IC4)
KMC Mr. Vysag Lenin Municipal Management System
Discussed about existing MMIS, digitization of older records
7. 8/05/2019 Parks & Open Space
KMC Ms. Shameena, Ward Councillor Ms. Bindu, Ward Councillor
Upgradation of Moomen’s park and Karippalam Park
Concept prepared were discussed with respective ward councillors
8. 13/05/2019 Economy and Employment
Ernakulam Market Association
Ernakulam Market Stall Owner’s Association(EMSOA)
Finalize the proposal for Market redevelopment
Market association shall discuss the proposal with all member and giving final decision on the layout while CSML shall share the revised layout based on the discussion. Detailed MoM is attached in annexure 1.
9. 13/05/2019 Energy Efficiency
KMC EE, AEE Installation of LED Lights
Discussion were held with EE and AEE of KMC pertaining to the installation of LED lights project.
10. 16/05/2019 Energy Efficiency
KMC Hon’ble Mayor, Councillors and other Officials of KMC
Implementation of Intelligent Street Pole at Kochi Under PPP on DBOOT model
Detailed presentation were made by PMC regarding the Project Proposal including revenue model. Mayor shows interest in the concept of Smart Pole project however, mention various challenges in executing the project discusses action plan. Detailed MoM is attached in the annexure 1.
Monthly Progress Report
Page | 15 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Date of Consultation
Module Content
Stakeholder Consultation
Concerned Person in the Department
Agenda Discussion by PMC Team
Remarks
11. 17/5/2019 Water Supply
KWA, Pallimukku
Mr. Ajith Kumar, A.E.E
Data collection for water supply projects implemented by KWA
Mr. Ajijt Kumar, AEE has directed to AE to provide all the relevant data.
12. 20/05/2019 Water Supply
KWA, Pallimukku
Ms. Jaya, A.E Data collection for water supply projects implemented by KWA
Ms. Jaya has provided the required data related to Project under Plan fund, KMC deposit work, Draught fund etc.
13. 20/05/2019 Tourism Tourism Department
Ms. Sabitha, Section Clerk, Tourism Department
Regarding initiatives of Tourism Department at Fort Kochi Beach Area
The detailed information pertaining to the project which is being implemented by Tourism department in Fort Kochi area has been taken
14. 21/05/2019 Park & Open Space
GCDA Jeby Jomy (Superintending Engineer) Rajesh T.N. (Town Planner) GCDA Team
To discuss on the submitted Marine Drive Walkway- Project Brief
The project details were briefed and project will be taken up for approval from GCDA Executive Council. Detailed MoM has b1een attached in annexure 1
15. 21/05/2019 Park & Open Space
GCDA GCDA Chairman To discuss on the submitted Marine Drive Walkway- Project Brief
Marine drive walkway progress was updated and further confirmation shall be provided by GCDA. Detailed MoM is attached in the annexure 1
16. 27/05/2019 Water Supply
KMC Mr. Peter, Councillor Ms. Elizabeth, Councillor
Automated Metering Infrastructure
Discussed the AMI projects with Councillors. The councillors agreed to do AMI project in their ward(i.e. Newly laid pipeline)
17. 28/05/2019 Water Supply
KWA, Hospital Road
Mr. Vinod AMI discussion, drawing collection
Mr. Vinod has given the connection details and specifications of the selected pipelines also he told that he will provide the drawings of the pipelines once he received.
18. 28/05/2019 Tourism Revenue divisional office, Fort Kochi
Mr. Snehil IAS, Sub-collector, Fort Kochi
Approval of the Proposed Freedom struggle Museum and other projects in Fort Kochi
The sub-collector was keen to get the projects implemented in fort Kochi and inquired about the status of tendered projects of Vasco square development. Sub-collector (SC) approved the proposal for Freedom struggle museum, and but informed that he had a proposal to build a single storey senior citizen counselling room building as an extension of RDO in the additional vacant land of 8 cents which
Monthly Progress Report
Page | 16 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Date of Consultation
Module Content
Stakeholder Consultation
Concerned Person in the Department
Agenda Discussion by PMC Team
Remarks
CSML is proposing to develop along with the Museum project. Sub Collector also reviews other projects related to Park & Open Space and Fort Kochi upgradation. Detailed MoM has been attached with the annexure 1.
19. 28/05/2019 Canal Restoration
KMRL Conference Room
Officials From KMRL, CSML, KMC, Irrigation Division, KWA, Water Transport
Stakeholder consultation to discuss Canal Rejuvenation finding based on feasibility report prepared by PMC
Action Points : Confirmation on length of Canal for improvement under Smart City. CSML to take relevant approvals and convey the same to PMC To be discussed with KMRL & CSML which agency shall take up Canal Rejuvenation of Market Canal Detailed MoM is attached with annexure1
1.2 SITE VISITS
In the month of April following site visits and supervision visits have been taken up by PMC:
Table 1-3 Summary of site visits conducted during the month of May 2019
S No
Date Site Visited Agenda for Site visit Location Notes from site visit
1. 04-05-2019 Fort Kochi Jail For the preparation of
an estimate Fort Kochi. Survey of sites has
been done for the purpose of cost estimation
2. 07-05-2019 Thuruthy Colony
and Chungam Bridge
To assess the site conditions for the proposed bridge projects
Fort Kochi Five sites were visited for 3 proposed minor bridges and two foot bridges
3. 08-05-201 Parks and open
spaces in Fort Koch
To Prepare a design Fort Kochi Survey of sites has been done for the purpose of preparation of site design
4. 15-05-2019 IC4 Survey of sites for
installation of video wall
JLN Stadium, Metro Station
Joint survey with Vendor and measurement has been taken for installation of video wall
5. 16-05-2019 He-man Robo
Park automated MLCP Facili
Facility Assessment by Transport Exper
Kaloor The automated parking facility accommodated 81 cars, along with ground parking along the periphery.
Monthly Progress Report
Page | 17 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
6. 17-05-2019 Fort Kochi -
Bellar - K B Jacob Road Junction, Parking in Tourist Area.
Assess the existing movement of traffic and associated activities at the junction
Fort Kochi Traffic movement and associated activities at the junction have been accessed.
7. 17-05-2019 Open spaces
and Play Grounds
To prepare the estimate
West Kochi Site survey has been done for the preparation of cost estimation.
8. 17-05-2019 Proposed Public
Toilets Site visit with Vendor TDLCCS
Fort Kochi Joint site with the vendor has been done for the construction of public toilets at fort kochi
9. 17-05-2019 Mullassery
Canal Site inspection Ernakulam Site inspection has
been done for Mulessery Canal from Park avenue road to T.D Road
10. 18-05-2019 Mullassery
Canal Measurement of the Site
Ernakulam Site visit to measure the details of Mullasssery canal from KSRTC junction to T.D Road
11. 20-05-2019 Jos Junction to
Chittoor Road Junction
Taking over the road stretch from DMRC for development of road under Cochin Smart Mission
Ernakulam Scope of works of DMRC for the RHS of the road stretch between Jos Junction and Chittoor road was completed and was taken over for development under CSML
12. 24.05.2019 Subhash Park Site inspection Ernakulam Site inspection has
been done for the preparation of cost estimation for taking up the remaining work.
13. 30.05.2019 Parks & Open
Space Site inspection West Kochi Site inspection has
been don at West Kochi Parks for preparation of cost estimation for electrical Work.
Table 1-4 Summary of supervision of sites conducted during the month of May
S No
Date Site Visited Agenda for Site visit Location Notes from site visit
1. 02-05-2019 PWD Rest
house, Dist. Ayurveda Hosp., Townhall, KSEB Central Section, GHSS
To update the progress of Solar Project
Ernakulam Physical progress of the projects at the locations has been supervised.
2. 03-05-201 GHS Panampilly
Nagar, Old Age Home Thevara, Town Hall Palluruthy, Govt. Hospital Karuvelippady,
To update the progress of Solar Project
Ernakulam and West Kochi
Physical progress of the projects at the locations has been supervised.
Monthly Progress Report
Page | 18 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S No
Date Site Visited Agenda for Site visit Location Notes from site visit
Govt. Hospital Fort Kochi
3. 13-05-2019 Deens Site
Office To assess the location found for establishing contractors site office
Kadavanthra Existing Building with some free land adjacent to it. Was found suitable for establishing Site office.
4. 17-05-201 Palluruthy
Hospital To check the structural stability of Truss work for Solar Project
Palluruth Survey work for structural stability of Truss for installation of Solar Panels has been done
5. 17-05-2019 Open spaces
and Play Grounds
To prepare the estimate
West Kochi Site survey has been done for the preparation of cost estimation.
6. 17-05-2019 West Kochi
Smart Roads Site Visit to supervise Contractors survey works
Fort Kochi To supervise the survey works which is being done by the Contractor
7. 17-05-2019 Abraham
Madamakkal Road
Joint site visit with Contractor to assess the site conditions and plan works accordingly
Ernakulam Road stretch from high court junction to Goshree bridge was visited.
8. 18-05-2019 West Kochi
Smart Roads Site Visit to supervise Contractors survey works
Fort Kochi To supervise the survey works which is being done by the Contractor
9. 20-05-2019 Deens Site office To see the Samples
for Kerb stones brought by the Contractor
Kadavanthra Tile Samples were found to be ok in visual inspection and contractor was asked to get the same tested from a NABL Accredited lab.
10. 21-05-201 West Kochi
Smart Roads Site Visit to supervise Contractors survey works
Fort Kochi To supervise the survey works which is being done by the Contractor
11. 21-05-2019 Deens Crusher
Plant Visited Contractors Crusher plant as a part of aggregate source approva
Kottapady, Kothamangalam
The quarry and plant was found to be satisfactory. Contractor was asked to submit the test reports pertaining to the aggregate properties at the earlies
12. 22-05-2019 Jos Junction to
Chittoor Road Junction
For fixing the location for laying electrical duct before the bitumen works are done
Chittoor Road Junction
DMRC has planned for bitumen works at the site and PMC along with Contractor visited the site for assessing the feasibility of laying ducts before the works
13. 24-05-2019 West Kochi
Smart Roads Site Visit to supervise Contractors survey works
Fort Kochi To supervise the survey works which is being done by the Contractor
Monthly Progress Report
Page | 19 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S No
Date Site Visited Agenda for Site visit Location Notes from site visit
14. 24-05-2019 Abraham
Madamakkal Road
Supervising the initial level Survey works at Site
Ernakulam Traverse closing was not completed for the road. Contractor was instructed to complete the same before starting the initial level survey
15. 24-05-2019 Deens - Base
Camp Visit to the proposed base camp and batching plant location of Deens Group
Edayar The proposed location was found to be suitable for establishing contractors base camp
16. 24-05-2019 West Kochi
Smart Roads Site Visit to supervise Contractors survey works
Fort Kochi To supervise the survey works which is being done by the Contractor
17. 27-05-2019 West Kochi
Smart Roads Site Visit to supervise Contractors survey works
Fort Kochi To supervise the survey works which is being done by the Contractor
18. 28-05-2019 Jos Junction Joint Site visit with
CSML, KMRL, Deens and PMC
Ernakulam Joint site visit has been done at Jos Junction for Road project with Officials from CSML & KMRL and the Contractor
19. 30-05-2019 Maharaja’s Boys
Hostel, GGHSS Ernakulam, Fort Kochi Taluk Hospital
To check the structural stability of Truss work for Solar Project and to check the leakage in ongoing Solar Project.
Fort Kochi, Ernakulam
Survey of structural stability of Truss Work for installation of solar project has done. Also the inspection of leakage which is reported due to installation of Solar Panels.
20. 30-05-2019 ABC Builders’
Site Office and Plant
Visit to ABC Builders proposed site office and Batching Plant
Fort Kochi The proposed building and land was found suitable for site office and Plant respectively.
Photographs for existing conditions of the sites visited.
Figure 1-1 Installation of Solar Panels Figure 1-2 Existing truss at Maharaja Boys Hostel
Monthly Progress Report
Page | 20 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Figure 1-3 Fort Kochi Jail Figure 1-4 Automated Car Parking Facility at Kaloor
Figure 1-5 JLN Metro Stadium for setup of Command and Control Centre
Figure 1-6 Crusher Plant for Contractor- Road Project
Figure 1-7 Existing Bridges at Thuruthy Figure 1-8 Existing Road condition from Jos Jn. To
Chittoor Road
1.3 BRIEF SUMMARY OF KEY MEETINGS
1. Kick-Off Meeting for Integrated Command and Control and Communication
Center on 6th May, 2019
The work for IC4 has been awarded to M/s Fluentgrid in consortium with Bharat Electronics
Limited at a cost of Rs 64.50 cr. In this regard, a Kick of Meeting was organised in which,
detailed structure of the project, high level project architecture and plan, scope of work,
project team and other aspect of technologies were discussed with various Stakeholders.
Monthly Progress Report
Page | 21 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
At the outset of the meeting M/s Fluentgrid team introduced the project and welcomed
Managing Director, CSM along with other Officials from department and other
Stakeholders. A detailed presentation was made for project overview, objective of the IC4,
smart solutions, Architecture of the project, Implementation Schedule, Networking and
cloud based DC & DR. The Fluentgrid informed that, they have sign agreement with BSNL
as a Network partner and for DC& DR, it is Amazon Web Services. M/s Fluentgrid inform
that a Mobile App will also be developed for the Citizens.
Followed by presentation, detailed discussion with other Stakeholder, PMC and CSML
Official were held for integration of different smart solutions for the respective departments.
The Technical Team of M/s Fluentgrid informed that the smart solutions for any department
can be integrated through API which should be provided by the respective department.
Detail Minutes of the Meeting has been attached in the annexure.
Figure 1-9 Kick-Off Meeting IC4
2. Workshop on Smart City Innovation Lab by Fraunhofer
Kochi Smart City Lab Kochi Smart City Innovation Lab, a joint venture between Cochin
Smart Mission Limited and Fraunhofer - a German government-backed research
organization has organised a workshop for the project which will be implemented by the
Organisation. The General Manager, CSML welcome the participants and gave the brief
introduction about the Cochin Smart City Mission Limited and activities of it. Mr. Marius
Mohr from Fraunhofer gave the introduction of Smart City Innovation Lab and made a
detailed presentation on project structure, approach and identified focus area.
Monthly Progress Report
Page | 22 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Mr. Mohr has informed that the Fraunhofer will support CSML in implementation of the
project from Disaster Management, Housing, Energy Efficiency, and Environmental
Protection/Water sector. He informed that the whole programme has been divided into three
phases that is understanding phase, co-creation phase and transformation phase.
The duration of the implementation of the project will be 3 years. He informed that integrated
drainage and canal system rejuvenation and management plan has been identified as focus
area by the organisation.
Managing Director, CSML has discussed the details of financial assistance for the project
(Smart City, PPP, convergence) along with external aid for projects under identified sectors.
He requested Officials to bring up innovative ideas/project to be assist by KFW/Fraunhofer.
Followed by presentation, detail discussion was held for the challenges in implementation
of the projects, capacity building, acceptance of the project, affordable housing for low
income group, plan for disaster management and waste management.
Figure 1-10 City Innovation Lab- Workshop
3. Kick-Off Meeting for 3 Roads packages was held on 16th May, 2019
The work for 2 Road Packages that is Development of Other Roads in Ernakulam ABD at
a cost of Rs 43.60 cr, Development of Smart Roads in Ernakulam ABD at a cost of Rs 61.53
cr has been awarded to M/s. Deens Group and M/s. Deens Group in Consortium with
Deens Constructions respectively. The work for Development of Smart Roads in West
Kochi in ABD at a cost of Rs. 30.31 cr has been awarded to M/s. ABC Builders. In this
regard kick off meeting were organised on 16th May 2019 in which project specific details
were discussed.
The key points of the discussion were general requirement of which is to be complied by
the contractor such as:
• Bank Guarantee for performance security
• Agreement Signing
• Baseline Work Schedule
• Mobilization
• Site Office
Monthly Progress Report
Page | 23 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
• Laboratories
• Plants & Equipments
• Statutory Clearances
• Labour License
• Insurance
• Key personnel
• Sub-Contracts Finalization (if any)
• Preliminary Survey and Preparation of Working Drawings
• Procurement Schedule
• Quality Assurance Plan
• Material Source Selection and Approval
• Preparation of Job Mix Designs and Approval
• Health, Safety and Environment Plans
• Traffic Management Plan
The suggestions were made to the contractor that they needs to assess the local condition
and also setting up of plants and machineries shall not be too far from the site. The batching
plant location shall have good accessibility. The finalisation of the sub-contract shall be
conducted at the earliest. The CSML instructed to appoint a full time project manager and
support staff matching with the credentials in the tender and also the contractor shall
appoint electrical contractor with Class A registration and experience in similar works for
utility shifting The finalization of location for the site office and laboratory for testing of the
materials shall be done after due inspection and approval by the PMC and CMSL.
The road contractors were informed regarding other parallel project ongoing under Smart
City and need for integration
- Intelligent Traffic Management System Pan city (Kochi Municipal Corporation area)
- Smart poles pan city
- Smart LED lighting
M/s ABC builders which is the contractor for the Development of Smart Roads in West
Kochi in ABD has informed that they will bring the labour from outside the State hence the
contractor was instructed to set up a labour camp with all standard facilities.
Detailed Minutes of the Meeting is attached in the annexure 1
4. Kick-Off Meeting for Intelligent Traffic and Management System (ITMS) on 18th
May, 2019.
The work for ITMS project has been awarded to KELTRON at a cost of Rs 26.90 cr. In this
regard, a Kick of Meeting was organised on 18th May 2019 which was attended by the
KMRL, Police Department, PMC to the Smart City, GIDA and other Stakeholders. At the
outset of the meeting CSML introduced the project and welcomed everyone. A detailed
discussion was held between the stakeholders regarding execution of the projects. The key
points of discussion were:
Monthly Progress Report
Page | 24 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
➢ KELTRON during the meeting submitted PBG, contract document, solution document.
KELTRON added that the solution document is to be revised based on site visits to be
conducted. CSML mentioned that a revised solution document is to be submitted by
KELTRON with 5 modified locations, locations which require dismantling of street
furniture and detail of the project team, Staff schedule and detailed implementation
schedule.
➢ Proposed joint site visit along with members from PWD, Police, KMC, GIDA, GCDA
etc.
➢ Based on the site visit, there are lot of street furniture’s to be dismantled and removed
– CSML replied that, stakeholders will be identified, and request will be made for the
same. CSML requested to have the stakeholders and list required to be added in the
revised solution document
➢ Request for space for storing of equipment – CSML responded that the SPV does not
have any asset hence the material to be stored in space available with KELTRON.
➢ CSML also pointed out that till commissioning supply material is to be taken care of by
the vendor. KELTRON agreed to the same
➢ Keltron stated that, Aroor manufacturing plant can be utilised for storing the equipment.
KELTRON to share facility detail.
➢ To manage delay, the implementation schedule is modified as 6+1 months.
➢ For connectivity, MPLS VPN through OFC and as per proposal, the network partner is
BSNL.
➢ The structural details of poles are provided with solution document.
The detailed Minutes of the Meeting is attached in the annexure 1
Monthly Progress Report
Page | 25 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Figure 1-11 Kick-Off Meeting ITMS
5. Review Meeting – Development of Smart and Other Roads in Ernakulam
The agenda was to assess and discussed the status of pre-implementation process which
are supposed to be completed by the contractor. The following key points were discussed:
a) Bank Guarantee and Agreement Signing : The contractor informed that PBG will be
submitted as per the timeline committed during the Kick Off Meeting
b) Baseline work Schedule: Shortfalls of the submitted work schedule was explained to
the contractor. The contractor was instructed to discuss with same with Engineer’s
representative.
c) Status of Mobilisation: The contractor informed that they have identified the location
for establishing the office, laboratory and batching plant. A joint visit with PMC and
contractor is scheduled in this regard.
d) Subcontractor for Electrical Utility Works: The contractor expressed difficulty in
finding the suitable subcontractor of electrical utility works. It was informed to the
contractor that Engineer will provide the necessary clarification for electrical works and
will help the contractor to find suitable subcontractor for the same.
e) Commencement of Piling Works: Piling works for the proposed bridges at Abraham
Madamakkal Road were discussed during the review meeting. The contractor was
instructed that for piling work RMC may be used upon submission and approval of mix
designs. Kerb, Paver Tiles etc may be procured from local market which company will
all quality requirement and test from a NABL accredited lab. Also mounted Kerb will be
examined by the KMRL.
Detailed MoM is attached in the annexure 1.
6. Combined stakeholder meeting for Canal projects was held on 28 May 2019
Based on the Feasibility report prepared by Project Management Consultant, a combined
stakeholders meeting were organised to discuss Canal Rejuvenation projects. At the outset
of the meeting CSML welcomed all the participants and then detailed presentation were
made. The key points of the discussion were:
➢ Current situation of the canals under ABD area was discussed and the presentation on
the feasibility report submitted was explained by Pradyumna Machhkhand, Canal
Monthly Progress Report
Page | 26 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Expert, PMC. Current situation, navigability and other constraints like social and
environmental issues regarding the rejuvenation of the canal were elaborated.
➢ Ernakulam Market Re-development - the plan for constructing the Multi storied building
for the Market shops was explained. The possibility of navigability of the market canal
was discussed.
➢ Kalvathy-Rameswarm Canals – the bridges constructed over the canal would be
hinderance to navigability of the canal. It was pointed out that houses and shops were
found constructed at the edges of the canal side wall especially along the Mullasserry
canal and the Kalvathy canal.
➢ Alternative methods for rejuvenation and controlling of the storm water, sewerage and
other wastes flowing to the canals were also discussed. The alternative methods
suggested were: (1) New trunk Sewer System with a proposal of STP. The site of STP
may be proposed at the GCA parting area near the mouth of the canal. (2) New Trunk
Sewer System to be integrated with the existing sewer network.
➢ The hydrological study for all the three canals within the ABD catchment area was
carried out and raising the side wall was recommended in the Feasibility Report. The
construction of sheet piles at the boundaries of the existing walls of the canals was
suggested for avoiding the damages of the side walls. The cost (excluding the urban
designs, sewerage and other miscellaneous cost) for this construction is also
mentioned in the feasibility report.
The presentation was concluded with a note for improvement and additions to the feasibility
report.
The detailed Minutes of the Meeting is attached in the annexure1.
7. Introduction and discussion of Smart City Mission Project with Engineering
Wing of KMC on 29.05.2019.
The agenda of the meeting was to appraise the engineering staff of the KMC about projects
undertaken by CSML and implement the projects with guidance & active assistance from
engineering wing. Detailed presentation was made pertaining to status and project proposal
under various sectors.
a) Urban Mobility and Road Projects
a) Smart and other roads
b) Public bike sharing system
c) Parking management
During the discussion the engineering staff were made some suggestions such as Carriage
way of Hospital road seems to be reduced, No provision for Two-Wheeler parking, Subway
as alternative option for pedestrian crossing. CSML/PMC has given the clarifications for the
issues/observations raised by the engineering staff. Followed by the discussion GIZ also
made a presentation on Street design which includes Re-organization of under-utilized
streets and promotion of NMT & Public Transport.
b) Open Spaces and Tourism Projects
Following projects were discussed during the Meeting:
a) Improvements to Marine Drive walkway
b) Vasco Square at Fort Kochi
c) Open Air Theatre at Fort Kochi
Monthly Progress Report
Page | 27 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
d) Parks improvement
e) Fort Kochi Beach upgradation
f) Museums
g) Public walkway at Mattancherry
c) Canal Projects
The 4 Restoration of Canal project were discussed which includes Cleaning and
maintaining water quality, Side wall development urban design aspects along the canal
stretch. The Officials informed that in West Kochi, Calvathy-Rameshwaram Canal work on
desilting & side wall protection has been taken up as part of AMRUT also Restoration of
Calvathy-Rameshwaram & Mullassery canal within ABD alone will not be suffice. They
suggested to integrate the work to be undertaken under AMRUT funds for Calvathy-
Rameshwaram canal.
d) Market projects
Following projects were discussed in the Meeting
a) Ernakulam market development
b) Broadway street upgradation
e) Housing projects
The projects discussed in the meeting were:
a) Bridges construction
b) Thuruthy colony – 1st Tower
c) Integrated development of Slum housing
d) Beneficiary Led housing schemes
During the discussion, the Official suggested that any Vacant space for new construction/
relocation or slums that can be redeveloped to be considered and discussed further for
redevelopment of slums component also CSML can initiate proposal for construction of 2nd
tower for Thuruthy and independent slum redevelopment of specific slums, once KMC
provides consent and necessary details to proceed with the work.
f) LED streetlight and electrical infrastructure, Solar projects
The Projects discussed were:
a) Smart LED street light
b) Solar project
Engineering wing opined that while replacing existing light fixtures with LED light fixtures
and controllers, Poles may also be replaced and maintain lux level requirements of each
roads. The LED light and pole design to be considered as a whole for efficient design. The
Officials informed that there is leak in Fort Kochi Govt. building found after solar panel
installation which is needs to be rectified.
g) ICT – IC4, ITMS, e-health
Detail discussion regarding ITMS project such as Traffic enforcement and management
through VA signals, Pelican Signals, variable message boards, red light violation were
discussed. It was informed that Traffic management command centre will be at North police
station Telecom - Smart Poles
Monthly Progress Report
Page | 28 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
h) Other Projects
Presentations were also made for the IC4, Smart Poles, Cancer block for General Hospital.
The Team Leader clarified the issues raised by the members of Engineering wing and
others. The General Manager concluded the meeting thanking the members attending the
meeting and with the decision to further conduct, sector wise detailed discussion with
concerned officials
Figure 1-12 Meeting with Engineering Staff-KMC
8. Review Meeting for The Road Project:- Development of Smart Road in West
Kochi ABD
The CSML noticed that the contractor has not submitted the general document which was
committed during the Kickoff Meeting. The Contractor committed to submit the PBG on 6th
June 2019 and Agreement signing on 7th June, 2019. The CSML instructed the contractor
to arrange the safety measure as per the contract documents. The CSML instructed the
contractor to start casting precast drains. During the review meeting, the contractor was
informed to mobilize the Key personnel for the project as per tender requirement. Also the
contractor was instructed to start clearing works at KB Jacob Road.
Detailed MoM is attached in the annexure1
Monthly Progress Report
Page | 29 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
2 STATUS OF ABD PROJECTS
2.1 STATUS OF ABD PROJECTS
This chapter provides an overview of all 80 projects listed in SCP for ABD. As envisioned
in SCP only part funding is met from Smart Cities mission fund. Remaining projects to be
funded from various sources such as convergence, PPP, CSR, loans etc. The status of
projects under convergence and under SPV are provided below. All costs provided are in
INR lakhs in this section.
Module 1 Water supply
There were total of 14 projects identified under this module with serial number 1.1 to 1.14.
Based on the meetings conducted with Kerala Water Authority in initial phase of the project
it was suggested by the authority that KWA will implement all projects. Therefore, these
projects are categorized as convergence projects. In the Stakeholder’s meeting, KWA has
requested to take up Smart Meter project for selected area as pilot basis. Hence only one
project Smart Water Meter project is under scope of SPV implementation. The project scope
is under discussion with KWA. It has been noted that under AMRUT RainWater Harvesting
project has been taken up.
1.1 Karuvelipady Pump house – Pumping augmentation
S. No
Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.1 Karuvelipady Pump house – Pumping augmentation
100
To be taken up by KWA only after the sump and pump house/pumping mains in Karuvelipady is completed under AMRUT scheme and TS committee constituted. The AMRUT work will be completed within 15 months
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.2 West Kochi - Extension of pipelines from Maradu to Island to be extended to
West Kochi to supply 12 MLD
S. No Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.2
West Kochi - Extension of pipelines from Maradu to Island to be extended to West Kochi to supply 12 MLD
55
30
Taken up under state plan and the works are completed. Work Completed. Total Financial Progress: Rs 27.00 lakh
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list. The KWA has reported that the project has been completed.
Monthly Progress Report
Page | 30 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
1.3 West Kochi - Replacement of pipelines from Perumanoor to Thevara and
Thoppumpady bridge to Karuvelipady
S. No Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.3
West Kochi - Replacement of pipe lines from Perumanoor to Thevara and Thoppumpady bridge to Karuvelipady
1100
448
The reach from Thoppumpady bridge to Karuvekipady is taken up under state plan and the works are completed. Due to Road cutting issues, the reach from Perumanoor to Thevara has not been taken up by KWA. Work order issued for Rs 448.00 Work Completed. Total Financial Progress: Rs 365.00 lakh
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.4 West Kochi - Dedicated pumping main
S. No
Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.4 West Kochi - Dedicated pumping main
350
Pumping main from Karuvelipadi pump house to Kovampadam OHT will be taken up under AMRUT and the works have been awarded during Feb 2018. The work will be completed within 15 months. Work under implementation.
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5
million litres
S. No Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5 million litres
800 288
Taken up under AMRUT. Work awarded on Feb 2018. 36% physical progress has been made. Financial Progress: 112.00 lakh
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.6 West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort
Kochi and Koovapadam)
Monthly Progress Report
Page | 31 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.6
West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort Kochi and Koovapadam)
75
Will be included in 24 X 7 water supply proposal for which KWA is preparing document
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes
including Road cutting charges
S. No
Proposed interventions SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes including Road cutting charges
3500
Will be included in 24 X 7 water supply proposal for which KWA is preparing document
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.8 West Kochi - Replacement of Household connections (last mile) for across
10,000 HSCs with Smart Metering and isolation valves
S. No
Proposed interventions SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.8
West Kochi - Replacement of Household connections (last mile) for across 10,000 HSCs with Smart Metering and isolation valves
2500
Will be included in 24 X 7 water supply proposal for which KWA is preparing document
This project has been classified as convergence project as the project in being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading
S. No
Proposed interventions SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading
100 Will be included in 24 X 7 water
supply proposal for which KWA is preparing document
This project has been classified as convergence project as the project in being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
Monthly Progress Report
Page | 32 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
1.10 Mainland - Rider line for increased water supply
S. No
Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.10 Mainland - Rider line for increased water supply
1000
223 KWA has been taken up this project. Work order issued for Rs 223 lakh. Pipelines have been supplied. Road cutting sanction yet to obtain.
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near
Ernakulam Ground
S. No
Proposed interventions SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near Ernakulam Ground
300
Will be included in 24 X 7 water supply proposal for which KWA is preparing document
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.12 Replacement of connections (last mile) for across 10,000 HSCs (Commercial
and Domestic) with Smart Metering and isolation valves- Mainland
S. No
REVISED Name of Project SCP
Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
1.12
Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves
Replacement of connections (last mile) for across HSCs (Commercial and Domestic) with Smart Metering and isolation valves for selected Area
2000 100
Project scope for project being finalised in consultation with KWA. CSML to fix a meeting with KWA to finalise scope. Also issue a letter in this regard..
In the Stakeholders meeting held on 19th September 2018 with Chief Engineer, KWA, it is
decided that the Smart Water Meter project for selected area will be taken up as on pilot
basis. A detail presentation was made regarding the various modules and the technologies
involved in Smart Water Management to KWA. The balance work of Smart Water Meter for
ABD will be taken up after the implementation of Pilot project.
1.13 Mainland - Bulk Meters and Isolation valves with remote meter reading
Monthly Progress Report
Page | 33 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions SCP Cost
Clubbed / Segregated/
Estimated Cost
Remarks
1.13 Mainland - Bulk Meters and Isolation valves with remote meter reading
150 Will be included in 24 X 7 water
supply proposal for which KWA is preparing document
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list.
1.14 General - Rainwater structures in ~5000 households
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/
Estimated Cost Remarks
1.14
General - Rainwater structures in ~5000 households
Rainwater harvesting structures in 13 Govt. buildings
1125 75
Renamed due to Scope change. KMC and other stakeholders suggested that the project may be done for Govt buildings instead of households Later it was found that RWH project has been implemented by KWA.
PAN City Project- 24x7 Water Supply
S. No
Proposed interventions
SCP Cost
Clubbed / Segregated/
Estimated Cost Remarks
24 X 7 WATER SUPPLY
62100
Being taken up by KWA. Has been included in 24 X 7 water supply proposal for which KWA has submitted a concept paper. The funding is yet to be decided (ADB / KIIFB) Detailed Project Report under progress.
This project has been classified as convergence project as the project is being
implemented by KWA. CSML/PMC will continue taking status from KWA regarding the
progress made for the project as project is part of overall projects identified under SCP
project list. However, it is being proposed by MoHUA that as 24x7 is a huge project and its
implementation timelines will not match Smart City timelines hence same may be removed
from central MIS.
Module 2 UGSS
There were total of 3 projects identified under this module with serial number 2.1 to 2.3.
Based on the meetings conducted with Kerala Water Authority and Kochi Municipal
Corporation 2 projects are under scope of SPV implementation. Further the project
“Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)”
has been segregated in two projects. The project “Improvement to Elamkulam STP” has
been taken up by KWA.
Monthly Progress Report
Page | 34 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
2.1
Decentralized Treatment and collection system for West Kochi under ADB (Mundamveli)
Sewerage System for West Kochi
2200
15450
The Sub Module 2.1 and 2.2 will be planned together as the small-bore sewer for on-site sanitation is part of sewer collection system. These two components will not be separated as two different works for design as well as execution. The project under the module would focus on ward nos. from 1 to 5 of Kochi Corporation Tender has been floated
2.2
Small bore sewer/ Vacuum system for onsite sanitation - Includes storage facility for treated water use for landscaping
11000
2.3
Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)
Improvements to sewer collection system for Mainland
7000
5700
The module 2.3 involves mainly sewer collection system at mainland (central Kochi) and Improvements to Elamkulam STP. Under AMRUT fund, Project Tendered. CSML to write letter to KWA & KMC for confirmation on scope area to be covered for provision of Sewer lines Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. With limited SCM duration. Confirmation on scope needs to be expedited.
Improvement to Elamkulam STP
1370
Module 3 NMT Roads and Pedestrianized areas
There were total of 4 projects identified under this module with serial number 3.1 to 3.4
Three projects Relaying of roads, Standard Footpaths including signages and Restoration/
Rehabilitation of Storm water drains in the proposed area have been combined as these
components are part of right of way of the road itself and for coordinated implementation
need to be done together.
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/
Estimated Cost Remarks
3.1 Relaying of roads Development of Other Roads in Ernakulam under Smart City Mission
4200
4360 LoA issued on 9th April, 2019 to M/s Deens Group
3.2 Standard Footpaths including signages
Development of Other Roads in West Kochi under Smart City Mission
2853
6020 Project re-tendered. 3.3 Restoration/
Rehabilitation of Stormwater drains in the proposed area
2360
Monthly Progress Report
Page | 35 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/
Estimated Cost Remarks
3.4 MLCP and Commercial complex at Kacheripady
MLCP at Kacheripady
5000 615
No bids received. Project to be re tendered
MLCP at GCDA land at Marine Drive
10.0
Project scope to be confirmed by stakeholder. Post that DPR preparation will be taken up
MLCP at KTDC complex at Maneka
7.0
Project scope to be confirmed by stakeholder. Post that DPR preparation will be taken up
Smart Parking solutions at various location in ABD
1.90 DPR under preparation
Scope – Access Roads
The existing internal roads are to be developed as Access roads between the smart roads
for improved traffic flow within the ABD area. The scope of works in Access roads are mainly
but not limited to upgradation of drainage facilities by construction of new drains, Irish drains
and restoration of existing drains as per site requirements, provision of footpath (as per
standards and space available) and surface improvement wherever required. The CSML
intends to develop 39 Roads in Ernakulam central area (14.439 Km) and 87 Roads in Fort
Kochi (30.141 Km). Landscape, hardscape and cycle lane. The various components
included (but not limited to) in this area – wide footpaths, landscape corridor with trees, bus
bays, on-street parking, road markings, median, improved junctions, table tops, universal
accessible design by introduction of ramps, benches and planting beds, etc.
Progress of the Project:
2.1.1 DEVELOPMENT OF OTHER ROADS IN ERNAKULAM
Project Profile/ Components:
Projects aims at providing Seamless mobility where possible and Safe pedestrian
movement.
❖ Other roads covered:
• Ernakulam – 40 roads – 13.32 km
Other Roads project involves construction of:
❖ Drainage – Reconstruction/repair of drain on both sides of roads as per
requirements
❖ Concrete Trench –as per availability of space by the side of drainage to
accommodate utilities.
❖ Footpath- Both side of roads 1 to 1.5m wide footpath.
❖ Landscaping – As per availability of space
❖ Streetlight – Foundation
❖ Provision of HDPE duct
❖ Surface Laying –
• BM BC road as per requirements.
Monthly Progress Report
Page | 36 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
• Interlocking tiles proposed for roads with width less than 7m (as per
requirements)
Project cost: INR 43.60 Crores Duration: 15 Months
Project Start date: 09 April 2019 End date (expected): 09 July 2019
Contractor: M/s Deens Group
Current status:
❖ Surveys started
❖ Survey in Progress at Narakathara Road, Convent Road and Sheshadri Road
Any Challenges to be discussed:
❖ Handing over roads by the stakeholders to the Contractor.
Module 4 Main roads
There were total of 5 projects identified under this module related to roads with serial
number 4.1 to 4.3. Projects 4.4 & 4.5 will be separate project.
S. No
Proposed interventions REVISED Name
of Project SCP Cost
Clubbed /
Segregated/
Estimated Cost
Remarks
4.1 World class Arterial roads -- KB Jacob & Amravati Road/ Bellar Road in West/ -- Avenue, MG Rd, DH Rd, Banerjee Rd, Abraham Madamakkal road in Central city
Development of Smart Roads Ernakulam
5,287
6153
LoA issued on 9th April, 2019 to M/s Deens Group in Consortium with Deens Constructions
4.2 Relaying of roads, Aesthetic and improved Urban design Pedestrian facilities with Street furniture, Boulevards and urban greenery
Development of Smart Roads in West Kochi
1650
3031 LoA issued on 9th April, 2019 to M/s ABC Builders
4.3 Utility ducting for SWD, Water supply, Sewerage, OFC etc
3300
4.4 Signages, Junction improvement with Intelligent Traffic management
Signages 97
240
Segregated as signages & ITMS have separate projects. Junction improvement taken up under Roads combined project. DPR has been submitted for Approval.
Integrated Traffic Management System
2690
Contract Agreement signed on 16th May, 2019. Work commenced
4.5 Escalator FOBs 240
DPR under preparation for FOBs in Thuruthy
Smart Roads: Construction, operation and maintenance of Smart Roads
CSML intends to develop 5 roads in Ernakulam central area (4.9 Km) and 5 Roads in west
Kochi (3.2 Km) as smart roads. The scope of work includes developing the existing roads
mentioned above by upgradation and augmentation of foot path, provision of cycle lanes ,
Monthly Progress Report
Page | 37 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
providing Road Markings, Street Furniture, Bus bays, Street Landscaping works, utility
trenching/ducting works, Construction of new drains and restoration of existing drains as
per site requirements, shifting of utilities to underground trenches, foundation for street light
poles, monopoles and smart poles, installation of compact substations, individual
connections through feeder pillars, smart elements and other Miscellaneous works along
with operation maintenance of landscaping works.
Discussions have been held with Kerala Water Authority (KWA) and it has been requested
that any related work to the 24x7 water supply project must be in sync with Roads project.
Progress of the projects:
2.1.2 DEVELOPMENT OF SMART ROADS IN ERNAKULAM
Project Profile/ Components:
Roads covered
❖ Ernakulam Mainland: 5.41 Km Smart roads.
1. Banerji Road 0.91 km
2. Shanmugham Road & Park Avenue Road 2.36 km
3. Durbar Hall Road 0.53 km
4. Abraham Madamakkal Road 1.11 km
5. Swami Chinmayananda Road & South Railway Station Road 0.50 km
Projects aims are creating equitable organised safer roads space for all road users.
Smart Roads project involves construction of:
❖ Drainage – Reconstruction of drain on both sides of roads as per design for the free
flow of stormwater, to avoid water stagnation
❖ Construction of underground utility trench - Concrete or HDPE for all electrical cables,
data cables and future provision for water supply distribution line.
❖ Footpath – On either side of the road, there will be footpath of 2m to 3m width, for
safe and comfortable movement of pedestrians and vulnerable road users.
❖ Cycle lane – dedicated cycle lane in Shanmugham Road, Abraham Madamakkal
Road and Swami Chinmayananda Road & South Railway Station Road on either side.
Cycle lane marked on the carriage way of Banerji Road and D.H.Road.
❖ Streetlight provision– Foundation for Street light poles.
❖ Landscaping – proposed in Abraham Madamakkal road, Shanmugham Road, Durbar
Hall Road and Swami Chinmayananda Road & South Railway Station Road.
❖ Bus bays – Shanmugham Road and Abraham Madamakkal Road
❖ Hawker Zone – Shanmugham Road
❖ Median- Shanmugham Road, Abraham Madamakkal Road and Banerji Road
Monthly Progress Report
Page | 38 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Surface Laying – road formation – road levelling by WMM and BM BC as per design
requirements.
❖ Electrical/Street Light Components – New HT/LT Cables, providing New Smart
transformers, compact substations, RMU, feeder pillars, smart metering
❖ Provision of HDPE Under Ground Utility duct.
Project cost: INR 61.53 Crores Duration: 15 Months
Project Start date: 09 April 2019 End date (expected): 09 July 2019
Contractor: M/s Deens Group in Consortium with Deens Constructions
Current status:
❖ Contractor’s Temporary Site office (Container) established near the Proposed Bridge
in AM Road
❖ Location for Plant and Casting Yard identified; site clearance and development work
in progress. PMC made a visit to the location and was found suitable for establishing
the facilities.
❖ Aggregate Source at Kottapady was visited and the contractor was asked to submit
the quality reports of various aggregates from an NABL accredited lab. The contractor
is yet to submit the details.
❖ Contractor has submitted the implementation schedule for Smart roads. The shortfalls
of the submitted schedule was communicated to the contractor and a revised
schedule is to be submitted.
Piling
❖ Started mobilization of Sub Contractor and Equipment for Piling works
❖ Location for test pile identified and installation to be started.
❖ Area clearance completed including shifting of electric pole and cable.
❖ GAD and detailed drawings given to Contractor for setting out and starting piling
works
❖ Fabrication of liner and reinforcement cage commenced.
Survey
❖ Topo survey completed and initial levels taken at 10m interval for Abraham
Madamakkal Road and drawings including cross sections submitted.
❖ Topo Survey completed and drawings submitted for Jos Junction to Chittoor Junction
road. The GAD for the same is prepared.
❖ Topo Survey works for other roads in progress.
Material Selection and Approval
❖ Kerb stone and Paver tile samples submitted by Contractor was approved by PMC’s
Architect and are send for testing at NABL Accredited lab. Reports for Kerb was
received and the item was approved.
Monthly Progress Report
Page | 39 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Mix design from RMC Plant till commissioning of contractor’s batching plant for Piling
expected from Contractor by 24th June 2019.
❖ Barricading board of approved size and design ready and 15nos brought to site.
❖ Random checking of supplied kerb stone; submitted on 15/06/2019 (to be tested at
GCDA lab)
Challenges to be discussed:
❖ Underground and overhead utilities (KSEB, KWA & BSNL)
❖ Handing over roads by the stakeholders to the Contractor.
Location map
Figure 2-1 Location Map- Smart Road Ernakulam
2.1.3 DEVELOPMENT OF SMART ROADS IN WEST KOCHI
Monthly Progress Report
Page | 40 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Project Profile/ Components:
Roads covered
❖ Fort Kochi & Mattancherry (West Kochi) 3.24 Km of Smart roads
❖ KB Jacob Road 1.08 km
❖ Bellar Road & River road 0.44 km
❖ Amaravathi Road & T M Muhammed Road 1.08 km
❖ Calvathy Road 0.64 km
Projects aims are creating equitable organised safer roads space for all road users.
Smart Roads project involves construction of:
❖ Drainage – Reconstruction of drain on both sides of roads as per design for the free
flow of stormwater, to avoid water stagnation
❖ Construction of underground utility trench - Concrete or HDPE for all electrical cables,
data cables and future provision for water supply distribution line.
❖ Footpath – On either side of the road, there will be footpath of 2m to 3m width, for
safe and comfortable movement of pedestrians and vulnerable road users.
❖ Cycle lane – dedicated cycle lane on one side of K.B .Jacob Road.
❖ Streetlight provision– Foundation for Street light poles.
❖ Landscaping – proposed in K.B.Jacob Road.
❖ Surface Laying – road formation – road levelling by WMM and BM, BC as per design
requirements.
❖ Electrical/Street Light Components – New HT/LT Cables, providing New Smart
transformers, compact substations, RMU, feeder pillars, smart metering
❖ Provision of HDPE Under Ground Utility duct.
Project cost: INR 30.31 Crores Duration: 15 Months
Project Start date: 09 April 2019 End date (expected): 09 July 2019
Contractor: M/s ABC Builders
Current status:
❖ Topo Survey works completed
❖ Center line marking completed at KB Jacob Road
❖ Mix design submitted for concrete from RMC Plan. The tests were witnessed and
were found ok and hence approved.
❖ Site mobilization under progress
❖ Started desilting of drains in KB Jacob road (20.06.2019)
Challenges to be discussed:
❖ Underground and overhead utilities (KSEB, KWA & BSNL)
Monthly Progress Report
Page | 41 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Handing over roads by the stakeholders to the Contractor.
Location map
Figure 2-2 Smart Road - West Kochi
2.1.4 INTELLIGENT TRAFFIC MANAGEMENT SYSTEM(ITMS)
Project Profile:
❖ ITMS project was reconstituted as a pan city project as it would be effective only if it
was focused to a larger network than just few junctions and locations ABD.
❖ Based on the reconnaissance surveys, traffic data and discussions with the traffic
police, the locations were identified
❖ ITMS consists of several electronic equipment that work towards improving safety,
enforcement and traffic management
❖ ITMS can be segmented into 2 broad elements - Enforcement, and Traffic
Management.
❖ Enforcement deals with violation detection and fining
❖ Traffic Management deals with flow detection and optimization of signal controls.
❖ The other benefits that would accrue out of ITMS includes incident management and
better Information Dissemination.
❖ The Scope of Work Includes providing, installation, testing and Commissioning of
ITMS Components and setting up the Traffic Control center.
❖ Components
• ITMS
• Vehicle Actuated Signals
• Pelican Signals
• Variable Message Boards with Gantry
Monthly Progress Report
Page | 42 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
• Red Light Violation System
• IP based PTZ and Traffic violation cameras with night vision
• Traffic Management Center (TMC components are as follows)
- Receiving real time information/data from VA traffic feeds including storage of
the same
- Provide control of traffic signal controller from the Control Center to enable
corridor management/ATCS overrides
- Processing of ANPR camera images
- Traffic Surveillance camera – Beaming live images to allow for manual
capture of violations,
- A video wall for observation and discussion of traffic management, violations
and incidents for appropriate actions
- Provide controls for the PTZ camera’s
- RLVD traffic violation data processing and storage
- VMS to give real time traffic information to public
- Run the ATCS software to optimize traffic flow
- Challaning of Violations
Project cost: INR 26.90 Crores Duration: 12 Months
Project Start date: 18 May 2019 End date (expected, excl. O&M): 17 May
2020
Contractor: M/s KELTRON
Current status:
❖ Agreement Signed, Bank Guarantee received, kick off meeting and Solution
document submitted on 18th May 2019
❖ Joint Site visit along with KELTRON officials and CSML PMC officials Completed on
27th and 28th May 2019.
❖ Along with KELTRON team, PMC where present during the site visit.
❖ Road cutting locations, Signal pole locations, VMS locations, Control box locations
and Camera pole locations, Pelican Signal locations, have been identified.
❖ Based on the site visit and observations a revised solution document will be submitted
KELTRON.
❖ Once the solution document is received, a detailed site inspection along with
respective stakeholders will be carried out once again
❖ Informed about Jose Jn to South Railway Station Smart road work to Keltron. Asked
to provide HDPE ducting for proposed Traffic Signal pole at Jos Jn. Keltron Kochi
Monthly Progress Report
Page | 43 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
office (civil works) came and did the site inspection. Informed to provide the HDPE
duct to Road contractor before the paver works.
Any Issues/ Challenges to be discussed:
❖ Timely permissions from relevant stakeholders for ITMS components installation
which will require tasks such as road cutting.
Project components
Module 5 Energy Supply
There were total of 16 projects identified under this module with serial number 5.1 to 5.16.
Based on the meetings conducted with KMC, KSEB and PWD these all projects have been
combined into one as it will be implemented along with Smart Roads.
S. No
Proposed interventions REVISED Name of
Project SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
5.1 – 5.16
Compact Secondary Substation (990 KVA) Underground HT Line Underground LT Line LT UG for Streetlights AMR Metering - Single phase AMR Metering - Three phase AMR Metering - HT RMU with Remote terminal units Distribution panel board Installation of feeder pillars Underground Cabling - 11 KV LT UG Cabling Installation of Transformers (Compact Sub-stations) Installation of Ring Main Units with Remote terminal units
Development of Electrical Infrastructure in ABD Area
12,253
6349
All projects have been clubbed The project has been re-tendered. Technical Bid evaluation is completed and submitted to the CSML along with Shortfall letter.
Monthly Progress Report
Page | 44 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions REVISED Name of
Project SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
Smart Meters (AMR) Installation of feeder pillars
The scope of projects is to implement System Improvement & Augmentation Scheme for
existing Electrical Network in various Smart Road area. The contractor’s scope of work
includes but not limited to: Survey, network design, manufacturing, Working testing,
inspection, packing, dispatching, loading, unloading and storage at site, transit/storage and
construction insurance, assembly, erection, civil structural work, complete pre-
commissioning checks, testing & commissioning at site, obtaining statutory clearance &
certification from State Electrical Inspectorate, Kerala State Electricity Board, Kochi
Municipal Corporation etc. and handing over to the Owner after satisfactory commissioning
of complete augmentation of existing Electrical Network in Cochin Smart Mission Limited
Project ABD.
Module 6 Energy efficiency
There were total of 2 projects identified under this module with serial number 6.1 to 6.2.
Based on the meetings conducted with Kerala State Electricity Board and Kochi Municipal
Corporation all projects are under scope of SPV implementation.
S. No
Proposed interventions REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
6.1 Solar based LED with Smart poles
Smart LED Lights in ABD area
1,250 3230 Segregated as lighting & Telecom projects Technical Bid evaluation completed and submitted to the CSML. There are shortfalls in the document submitted.
Intelligent Street Poles in Kochi
30160 (PPP) DPR submitted Technical Bid evaluation under progress
6.2 Solar panels in Households and Institutions - Grid connected
Solar panels in Govt. buildings
1,758 570 Work awarded on Nomination basis to BHEL. Work under implementation.
Solar panels in public places
1178 Project proposed to be taken up along with Canal project.
In module 6: Solar based LED with Smart poles has been mentioned as one single project.
Smart Pole & Solar LED are two different entities hence should be considered as two
different projects. Smart poles are proposed to be implemented as a PPP project.
Progress of the Projects
2.1.5 SOLAR ROOFTOP PROJECT IMPLEMENTATION PROGRESS
The Contract agreement for the implementation of the project has signed on 24th
September 2018. The BHEL started site feasibility study and other paper works in the month
Monthly Progress Report
Page | 45 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
of December 2018. Clearance for installation of Solar panels has been given to BHEL for
26 buildings. The total capacity of solar panels in these buildings is 1010 KWp.
Project Profile/ Components:
❖ 26 government buildings selected pan city, for implementation of Solar Roof Top
project.
❖ Design, development and supply of all components of the SPV power system
❖ Supply, transportation, unloading, installation, testing and commissioning of 1000
KWp grid connected solar roof system in various government buildings in Kochi
Municipality. The buildings are either with flat roof concrete structure or slope roof
GI structure.
❖ The scope includes minor strengthening of slope roof structure at additional cost to
install solar roof top system and access to roof top for maintenance.
❖ All clearance / approval required from KSEB / Electrical inspectorate or any
statutory Authorities shall be obtained by the contractor.
❖ Installation and commissioning of SPV Power system up to AC distribution board
along with Net metering with necessary arrangement for integration grid and
protection during absence of grid supply.
❖ Five years Warrantee from handing over of the Solar Roof Top System.
❖ Remote Operation and Maintenance including periodic cleaning of modules, and
with quarterly visit for five years from the date of handing over of the solar Roof
System.
❖ Training of the staffs of client/owner.
Project cost: INR 5.70 Crores Duration: 6 months + 2 months EOT
Project Start date: 24 September 2018 End date (expected, excl. O&M): 31
August 2019
Contractor: M/s BHEL
Current status:
❖ M/s BHEL has completed installation of 670KWp solar panels out of total 1000KWp.
Balance installation works are under progress.
❖ Liaising works with KSEBL and Electrical Inspectorate under progress for the
commissioning of the completed facilities
Any Issues/ Challenges to be discussed:
❖ Supply of balance materials like 200KWp inverter, 330KWp mounting structure etc
and Shortage of work force by BHEL.
❖ Contract period of 6 months and EOT of 2 months completed on 24/05/2019. BHEL
requested EOT upto 31/08/ 2019.
❖ Approval for Dwg and site inspection from Electrical Inspectorate (EI).
Monthly Progress Report
Page | 46 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Ladder with openable door installation for maintenance and EI inspection.
❖ Additional DB shall be installed for conversion of single phase to three phase
system for Paramara and Perumbotta Ground Buildings as a variation item.
Permanent electrical connection to be obtained by Excise Department for
completion of Solar System.
❖ Inadequate site supervision/ Frequent replacement of Site in charge by BHEL.
❖ For 14 buildings, the connected load is less than installed Solar capacity. Hence
Service wire need to be changed as extra item.
Way forward
❖ BHEL to increase the staff strength of the implementation team.
❖ BHEL to do rigorous follow-up with EI.
❖ Presence of BHEL’s experienced Site in charge till the completion of the Project
❖ Monthly project review Meeting between senior management team of BHEL with
CSML and PMC.
❖ EOT may be approved considering approvals required from EI.
Project photographs
Figure 2-3Installation of Solar Panel at General Hospital
Figure 2-4Solar Panel installation Work at Fire station, Gandhinagar
Figure 2-5 Panel Installation of Town Hall
Monthly Progress Report
Page | 47 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Figure 2-6Panel Installation of Central Office, KSEB
Figure 2-7Panel Installation of Central Office, KSEB
Figure 2-8Govt. High School, Edapally Figure 2-9 Court Complex Ernakulam
Detail progress at each location is attached as annexure 4.
Module 7 Solid waste and Sanitation
There were total of 4 projects identified under this module with serial number 7.1 to 7.4.
Based on the meetings conducted with Kochi Municipal Corporation all projects are under
scope of CSML implementation. Only one project was proposed to be dropped by KMC as
it was not successful in earlier attempts made by Govt. Authorities.
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
7.1 Equipment including Smart Street sweepers/ GPS enabled Vehicles/compactors
600 Segregated
Supply, Operation and Maintenance of Portable Compactor for Secondary Storage & Transportation of Solid Waste
440 Tender Cancelled due to technical disqualification of bidder
Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West
100 DPR submitted KMC concurrence awaited to proceed with tendering
Monthly Progress Report
Page | 48 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
Kochi & Ernakulam in ABD Area
Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area
320 Tender Cancelled due to technical disqualification of bidder
7.2 Bio-composting in all Government institutions
5 Dropped as based on previous experience KMC proposed not to take up the listed project as it was implemented at few locations and was not successful. CSML to request for formal confirmation from KMC
7.3 Household segregated bins for Organic and inorganic wastes
74 67 Bid Evaluation completed. LOA issued to M/s Nilkamal on 8th May, 2019
7.4 Public toilets with Fit-in Treatment facility for Decentralized STP in West Kochi
Renovation and Upgradation of existing Public Toilet Facilities in ABD area
10 180 DPR Submitted. Tender has been floated. Technical Bid evaluation under progress.
Progress of the Projects
2.1.6 HOUSEHOLD BINS AND BINS IN PUBLIC PLACES
Project Profile/ Components:
Project includes procurement & supply of bins by the successful vendor for households
and public spaces.
• Stainless steel bins for public spaces - 75
• Total number of beneficiaries - 20081
• Number of bins per beneficiary - 2
• Material of bins - HM HDPE
❖ Intermediate storage of receipt bins by KMC
❖ Distribution of bins shall take place by the KMC in consultation with ward sanitation
committee which includes ward councillor, junior health inspectors in coordination
with RWA & Kudumbashree
❖ Installation & fixation of street litter bins at reasonable distance of 40-80 m,
depending upon the footfall density across prominent public places of Fort-Kochi,
Parks, Marine Drive walkway for use by pedestrians
Monthly Progress Report
Page | 49 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Street Litter Bins shall be in a pair of 2 – with proper display information in both
local and regional language, easily rotatable with each of then having capacity of
60 litres
Project cost: INR 0.67 Crores Duration: 3 Months
Project Start date: 06 May 2019 End date (expected): 02 October 2019
Contractor: M/s Nilkamal Limited
Current status:
❖ Household Bin sample submitted
❖ Contractor to start supply of bins with changes proposed.
Any Challenges to be discussed:
❖ KMC to share final list of beneficiaries
❖ KMC to provide location for Storage of bins
❖ Distribution of bins shall take place by the KMC in consultation with ward sanitation
committee which includes ward councilor, junior health inspectors in coordination
with RWA & Kudumbashree
❖ Household Bin distribution to take place in ward sabha meetings.
❖ Designated employee from KMC to confirm location of street bins in parks and
beach.
Photograph
Figure 2-10 Household Bins
Module 8 Parks and Open spaces
There were total of 4 projects identified under this module with serial number 8.1 to 8.4.
Based on the meetings conducted with Kochi Municipal Corporation, Tourism Department
and forest Department all projects are under scope of SPV implementation except 8.1 which
is already taken up for implementation by Tourism Dept.
Monthly Progress Report
Page | 50 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Remarks
8.1 Upgradation of Nehru Park
200
Convergence - project undertaken by Tourism Department. The project is under implementation by Tourism Department.
8.2 Development of open spaces
30 960 Feasibility report submitted on 26th
March 2019
8.3
Development of open spaces and playgrounds - Maharajas Ground
500
Feasibility report under preparation.
8.4
Marine Drive walkway phase I
90
710 Feasibility Report is submitted on 3rd November 2018. Revised DPR has been submitted on 4th Feb and 28th March 2019 Tender has been issued. Technical Bid evaluation under progress.
Marine Drive walkway phase II
690 Combined DPR has been submitted on 8th November 2018. For Phase II DPR will be revised after stakeholder’s consultation.
8.5 Mangalavanam Eco-restoration project
100 Proposed concept shared with
KMC & Forest Dept. Concurrence awaited on concept proposed
Module 9 Canal Restoration
There were total of 4 projects identified under this module with serial number 9.1 to 9.4.
Based on the meetings conducted with Kochi Municipal Corporation all projects are under
scope of SPV implementation.
S. No
Proposed interventions REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Status
9.1 Restoration of Mullassery canal - including linking of standardized area drains
100 Feasibility report submitted on 2nd March, 2019
9.2 Restoration of Market canal - Walkways and Market square around the canal pond, Solar panelled roofs, LED Lighting, Light posts
500 Feasibility report submitted on 2nd March, 2019
9.3 Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features
2,000 Feasibility report submitted on 2nd March 2019
9.4 Restoration of Rameswaram-Kalvathy canal - Up to Cochin college – Walkways and Linking the Canal Bank Road
1,500
Based on combined stakeholder meeting held on 28 May 2019 for Canal project it has been
suggested by all stakeholders (KWA, KMC, Irrigation dept, Water metro) that entre stretch
Monthly Progress Report
Page | 51 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
of Canal may be taken for development. CSML to conduct surveys for stretches beyond
ABD and post that Feasibility report to be updated.
Module 10 Urban mobility
There were total of 9 projects identified under this module with serial number 10.1 to 10.9.
Based on the meetings conducted with Kochi Metro Rail Limited and Kochi Municipal
Corporation 5 projects are under scope of SPV implementation and remaining 4 with KMRL
– Water Metro project.
S. No
Proposed interventions REVISED Name of Project
SCP Cost
Estimated Cost
Status
10.1 Water transport infrastructure (around 12 100 Pax boats)
4,200 5600
Convergence - Project under implementation by by Water Metro. Project tendered. Bid evaluation under progress
10.2 Electric Feeders, Bicycle Sharing, Elevated Walkways and Travellators
1,148
Segregated
Electric Feeders
1148 Convergence undertaken by KMRL. Feeders also proposed as part of Broadway Street pedestrianisation.
Bicycle Sharing
1000 (PPP) Locations approved by KMC. Contract to be signed
Elevated Walkways and Travellators
Part of Ernakulam market project
10.3 Walkway from Ekm Jetty to Metro station
900
470 Under implementation
10.4 Jetty improvement
800
4000
Convergence - Being undertaken by Water Metro. Bid evaluation under progress
10.5 Property development along jetties
720
10.6 Boatyard and Command & Control Centre
Boatyard
2,000
10.7 Dredging cost Marina 1,000 2000 Concept Stage
10.8
Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
60
Prateeksha has been given the project of bus shelters on a 15-year lease (duration to be confirmed by stakeholder) for PWD roads. West Kochi bus shelters have not been covered. In West Kochi bus shelters are sponsored for improvement by various stakeholders. Currently the bus shelters are not wifi enabled. In order to develop these as smart bus shelters CSML may write to relevant authorities
Monthly Progress Report
Page | 52 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions REVISED Name of Project
SCP Cost
Estimated Cost
Status
for confirmation on project scope/call for combined meeting.
10.9 Standard Wifi Enabled Bus Stands with Commercial space development
300
Combined stakeholder meeting & letter to stakeholders needed to confirm the scope of project to be taken up under Smart City
Progress of the Project
2.1.7 PUBLIC BIKE SHARING IMPLEMENTATION PROGRESS
Project Profile/ Components:
Cochin Smart City Mission Limited (CSML) along with KMRL are implementing the Kochi
Bicycle Sharing Scheme project in ABD (Area Based Development extent) and 2 km on
either side of the metro alignment from Aluva to Petta along a 25.6 km stretch. Capital
Cost and Operation Cost of the project will be borne by the service provider. Operations
contract will be issued to service providers for a period of 3 years. During this period
Service provider is entitled to collect Fare box revenue and Advertisement Revenue from
the given space for the system. Project to be implemented in two phases. Phase I
locations for docking stations identified
❖ Dock based or dock less system
❖ 1000 cycles
❖ Minimum 50 docking stations
❖ GPS Enabled Bicycles
❖ App based bicycle identification and management.
❖ Towing Vehicles for Redistribution
❖ Maintenance Center
Project cost: INR 10.00 Crores (PPP) Duration: 3 months
Project Start date: 14 March 2019 End date (expected, excl. O&M): 14
November 2019
Contractor: M/s Hero Youon Pvt. Ltd. (JV of Hero Cycles Ltd & Youon Technology
Pvt. Ltd.)
Current status:
❖ 15 docking locations identified & approved by KMC. Of these 13 locations are in
West Kochi and 3 in mainland
❖ Hexi has supplied 200 cycles.
❖ Prefabrication of docking stations is in progress
Monthly Progress Report
Page | 53 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ 2nd Phase 206 Locations approved by KMC. Detailed location Inspection under
progress. Phase 2 out of 206 locations 100 locations detailed inspection has been
completed by Hexi
Any Issues/ Challenges to be discussed:
❖ Approval and finalisation of docking stations
❖ Implementation duration was expected to be 3 months. However, considering all
approvals required project is expected to complete by November 2019
❖ Integration with ongoing projects.
Location map/ project maps/project design/ pictures
Monthly Progress Report
Page | 54 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Figure 2-11PBS locations (Base map by PMC and locations plotted by Smart-SUT)
Module 11 Housing
There were total of 3 projects identified under this module with serial number 11.1 to 11.3.
Based on the meetings conducted with Kochi Municipal Corporation and other stakeholders
below mentioned projects are under scope of SPV implementation. KMC has proposed to
take up some other project in place of Upgradation of infrastructure in Housing through
Credit linked schemes. The fund available under housing module is INR 100 Crores.
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Revised Estimated
Cost
Status
11.1
Integrated redevelopment of Slum housing
14,140
4685 Awaiting Confirmation for scope of work from KMC KMC to provide final list of beneficiaries and slums to be taken up under SCM Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited by KMC.
11.2
Upgradation of infrastructure in Housing through Credit linked schemes
Beneficiary Led Housing
2,435 1300 KMC proposing to revise the scope of component to “Beneficiary Led housing”.
Monthly Progress Report
Page | 55 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No
Proposed interventions
REVISED Name of Project
SCP Cost
Revised Estimated
Cost
Status
CSML has allocated Rs 13 cr. out of which Rs 1.02 Cr has been disbursed.
11.3
Construction & upgradation of 755 DUs in Thuruthy, Kalvathy & Konchery colony
Construction of first tower at Thuruthy
7,424 2100 As per discussion held on on 26th Dec 2018 for CSML to assist KMC in completing the construction of tower 1 under RAY scheme by Gap funding only. Gap funding to be disbursed by CSML only after KMC provides revised administrative sanction from LSGD and tender out the sewage treatment facilities and waste management
Construction of Second tower at Thuruthy
3500 CSML to write letter to KMC for confirmation on project scope to be taken up under smart City. Project preparation will require time. Minimum 3 months for DPR & Tender preparation. Hence to enable tendering confirmation to be shared at the earliest by KMC along with all data to start design process.
Construction & upgradation Thuruthy, Kalvathy & Konchery colony - Construction of Bridges
515 Feasibility Report Submitted on 27th September 2018 for bridges construction. DPR under preparation
11.4
Construction & upgradation of 755 DUs in Thuruthy, Kalvathy & Konchery colony -KMC
47.91 Convergence – Project Under Implementation by KMC
Module 12 Economy and Employment
There were total of 2 projects identified under this module with serial number 12.1 & 12.2.
Based on the meetings conducted with Kochi Municipal Corporation, KMCC, Market
association and other stakeholders all projects are under scope of SPV implementation.
S. No Proposed interventions
REVISED Name of Project SCP Cost
Estimated Cost
Status
12.1 Broadway Market and Ernakulam market Redevelopment and Mattancherry spice market
11,000
Broadway Street pedestrianisation
1000 Feasibility report submitted on 15th October 2018 DPR Stage. KMC to share list of
Monthly Progress Report
Page | 56 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No Proposed interventions
REVISED Name of Project SCP Cost
Estimated Cost
Status
approved licensed hawkers to be accommodated along multi utility zone proposed.
Ernakulam Market Redevelopment
10000 Feasibility report submitted. DPR Stage. KMC to approve initiate R&R asap.
Mattancherry spice market Redevelopment
Segregated - Streetscape improvement covered under road project
12.2 Standard Hawker zones in Fort Kochi
Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"
500 560 Segregated - Feasibility stage. KMC to share list of approved licensed hawkers Hawker zone included as part of Fort Kochi Beach upgradation.
Pedestrianisation of Broadway Street & other improvements: The proposal:
Pedestrianisation of Broadway Street for approx. 500m stretch.
Broadway Street Upgradation proposals proposes for a time bound
Pedestrianization of 500m stretch at an estimated cost of INR 10.0 Crores with other
supporting projects including pick up/drop off facility e-vehicles from Bus stops, metro,
water metro and MLCPs to offer smooth transition from parking to no parking zone.
Project proposal includes Pedestrianization of the Broadway street stretch in a time bound
manner from 12.00 pm to 8.00 pm allowing only E-rickshaw & emergency vehicle
movement. Pedestrian oriented street with partial canopy covering with regulated vehicular
access. Street is proposed as no parking zone.
Assistance required from KMC:
KMC to share final list of eligible hawkers to enable Smart City team to accommodate the
licensed hawkers along multi utility zone with cart size requirement. Approval of traffic
management plan from beneficiaries, Co-ordination with all beneficiaries.
i. Final approved list of hawkers to be shared with smart city team at the earliest to enable
Smart city team to do detailing of the designs that include allocation of hawkers in Multi
utility zone.
ii. KMC to hold public consultation with the shop keepers along Broadway and take formal
approval for the proposed project and finalize design detail such as the canopy and road
design.
Ernakulam Market redevelopment: The proposal
Ernakulam Market redevelopment proposal at an estimated cost of INR 100 Crores was
presented that proposed for development of Market area with a G+3 building, Basement
Monthly Progress Report
Page | 57 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
floor for parking, Developing market square in to a Multilevel car parking space, Solid waste
compactor, Banana Auction area, etc and solid waste compactor facilities, widening of an
existing bridge over market canal connecting to the market square and Skywalk.
Assistance required from KMC:
KMC to share final list of eligible shopkeepers with shop size requirement. Suggest on
Transit shelter strategy including confirmation on alternate land for relocation, expenditure
during relocation period, revision of rental rates for new building and negotiations, approval
of revised traffic management plan from beneficiaries, Co-ordination with all beneficiaries.
i. KMC to verify and compile final list of vendors and hawkers and share with smart city
team at the earliest to enable Smart city team to do detailing of the designs
ii. Confirmation for land for transit shelters at the earliest.
iii. KMC to confirm allotment of shops by zoning. Smart city to design accordingly
Figure 2-12 Ernakulam Market Redevelopment – Project Planning
Figure 2-13 Action to be taken prior to Tendering of the project
Monthly Progress Report
Page | 58 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Source: PMC
Table 2-1: Action for KMC to enable tendering by end of September 2019
TASK May June July August Sept Oct Nov
Final list of vendors & consultations
Finalization of proposal by CSML
Land for rehabilitation
Agreements with vendors by KMC
Relocation & rehabilitation
Tender by CSML
Site clearance by KMC & handover to CSML
Contract award by CSML
Construction period begins
18 months
Source: PMC
Module 13 Health
There were total of 2 projects identified under this module with serial number 13.1 & 13.2.
Based on the meetings conducted with Kochi Municipal Corporation, DMO and other
keyholders all projects are under scope of SPV implementation and have been segregated
into 4 projects
S. No Proposed interventions REVISED Name of Project
SCP Cost
Estimated Cost
Status
13.1 Scale up of GH into a Super-speciality care centres
Cancer Extension Block, General Hospital.
3,000 2600 (Phase I)
LoA to INKEL has been issued. Negotiation with INKEL in on going for the estimated cost as
Monthly Progress Report
Page | 59 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
submitted bu INKEL.
E-health solution for General Hospital
371
Segregated - Revised DPR has been submitted on 7th February. LoA has been issued. to M/s Keltron
13.2 Integrated development of 4 Hospitals in West Kochi - Excellence in Secondary care
Outpatient & Admin block, Fort Kochi taluk Hospital
1,000 465 Revised DPR, Detailed Estimate and Drawings submitted. Tender issued Technical bid evaluation completed
Outpatient & Admin block, Women & Child Hospital, Mattancherry
457 Revised DPR submitted on 13th November 2108. Revised BoQ and drawings have been submitted. Tender issued Technical bid evaluation under progress
Progress of Projects:
2.1.8 CANCER BLOCK- GENERAL HOSPITAL
Project Profile/ Components:
The nature of upgradation required for General Hospital was identified by CSML & PMC
in numerous meetings conducted with KMC & DMO & GH team. During these meetings
the hospital management committee requested Smart City to construct a dedicated
Cancer Ward block as an extension for cancer centre adjacent to the existing cancer
LINAC block building with following facilities.
❖ Chemotherapy wards,
❖ Male & Female Oncology wards,
❖ ICU, Neutropenia ward,
❖ Stand-by dormitories
Projects intends to provide a dedicated cancer specialty ward block as an annex to the
Existing LINAC building under implementation by INKEL & General hospital. Considering
the above requirement, it is currently proposed to construct a 7 storeyed (1 Basement +
Ground floor + 6 floors) building with approximate plinth area of 4500 square meters and
a total of 109 beds and 32 beds for dormitories.
❖ Male ward of 33 beds
❖ Female ward of 34 beds
Monthly Progress Report
Page | 60 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Chemotherapy ward of 24 beds
❖ Neutropenia ward of 9 beds
❖ ICU of 9 beds
❖ Dormitories (M&F of 16 beds each)
Project cost: INR 26.0 Crores Duration: 12 months
Project Start date: 27 February 2019 End date (expected): 27 February 2020
Contractor: M/s INKEL Limited
Current status:
❖ INKEL shared broad cost estimate with revised proposal (of plinth area, beds and
facilities to be provided). The proposal was reviewed and INKEL is requested to
provide revised proposal with block estimate of complete project.
❖ Final capacity including number beds and of number of floors to be shared by
INKEL in the revised proposal such that foundation design is proposed for the
maximum number of floors permissible as per municipal rules but finishing work
(including interior and medical equipment) shall be proposed based on the fund
availability for the project module. Post approval of proposal the contract will be
signed
Any Issues/ Challenges to be discussed:
❖ Project scope to be finaliszed based on fund available. Project cost would include
cost of construction, centage charges for M/s. INKEL, GST and tender excess by
contractor.
Location map
Figure 2-14 Location of proposed Cancer Block
2.1.9 E-HEALTH SOLUTION FOR GENERAL HOSPITAL
Monthly Progress Report
Page | 61 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Project Profile/ Components:
General Hospital at Ernakulam is one of the reputed Government Hospital which provides
effective medical care to the citizens of the Kochi Corporation and surrounding areas.
General Hospital has a very old and ineffective IT infrastructure which is an impediment
to its efficient functioning. This requires urgent upgradation. Concurrently e Health
solution is being developed and implemented by state Health department which
integrates all departments and government hospitals into an efficient Hospital Information
and Management system. It’s thus panned to upgrade the IT infrastructure of General
Hospital under the smart city mission project. The project includes two broad
components.
❖ Multiprotocol Label Switching (MPLS) Virtual Private Network (VPN) with
Redundancy to e- Health server hosted in Cloud.
❖ Workstations and Computer Hardware for e- Health implementation
The detail of these components is as follows:
• MPLS VPN with Redundancy to e-Health server Hosted in State Data Center:
This involves the following:
- Passive Optical Fibre Network Internal LAN with IPPBX- The internal network
will be combination of LAN and with Wi-Fi- Optical Fibre Cable (OFC) backbone.
- MPSL VPN – Transfer of EMR (Electronic Medical Records) requires higher
bandwidth; accordingly, a high-speed internet line using Optical Fibre (Gigabit-
capable Passive Optical Networks (GPON)) is best suitable.
• Local Sever, Workstations and other Computer Hardware
- E- Health solutions requires additional Workstations, Printers, Scanners,
Biometric readers and other Computer Hardware for implementing the solution.
Project cost: INR 3.71 Crores Duration: 4 Months
Project Start date: 14 June, 2019 End date (expected, excl. O&M): 30 September 2019
Contractor: M/s KELTRON
Current status:
❖ KELTRON is finalising the contract for procurement of GPON Network and will
award the contract to BSNL by 7 June 2019.
❖ Procurement of Computer Hardware is in tendering stage.
Any Issues/ Challenges to be discussed:
❖ The second part of the project, which is procurement of Hardware is still under
tendering stage, which is delayed.
❖ KELTRON to expedite the tendering
❖ Delay from Keltron in taking timely action
Monthly Progress Report
Page | 62 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Project design
Figure 2-15 Structural outline of e-Health Solution
Module 14 Education
There were total of 3 projects identified under this module with serial number 14.1 & 14.2.
Tenders were floated, and bids received from the bidders for the Smart class room project.
However, KITE Mission of Government of Kerala informed that a similar project is being
implemented by them on State Level thus the SPV should not continue with the selection
process. Therefore, the project is now cancelled and revised number of projects I 2.
S. No
Proposed interventions REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Status
14.1 Upgradation of Anganwadis
100 300 Feasibility Report submitted on 06-04-2019. Preparation of DPR ongoing
14.2 Upgradation of facilities - Basic services, Digital classrooms, Libraries, Eco-toilets, Sports kits, Biogas plant, Urban farming etc Higher Educational institutions
Higher secondary block, Central Calvathy GHSS, Fort Kochi
450 467 DPR Submitted on 13.11.2108. Project to re-tendered.
Smart Classroom for 100 classrooms PAN city
490 Segregated. Tender has been cancelled by the authority.
Monthly Progress Report
Page | 63 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
The project will include rejuvenation of AWC in Fort Kochi & Mattancherry with state-of-the-
art facility for Preschool training with Mother & Child care. List of 52 AWC identified in Fort
Kochi & Mattancherry from CDPO. The proposal includes following components:
• Tangible (physical) upgradation in quality of environment for AWC functioning
in Govt premises,
• IT infrastructure for Smart class rooms at AWCs.
Calvathy School project intends to provide a higher secondary block for about 240 pupils
along with the labs and ancillary facilities required. The building would also provide admin
office required for lower primary section.
• The proposal includes following components:
• 4 classrooms of 60 capacity each and one digital classroom
• Chemistry, Physics and computer labs
• Staff rooms, admin rooms, for higher secondary & lower primary section.
• Auditorium of 250 capacity.
• Building would be a 4-story structure of total area of 1500 sq.mt built after demolishing an existing single story old structure which is currently used as a common activity area.
The Smart education project aims to bring in state of the art education to students through
classroom revolution which is to innovate education, teaching and evaluation methods, and
educational environments using information Technology.
Module 15 Safety and Security
There were total of 2 projects identified under this module with serial number 15.1 & 15.2.
Based on the meetings conducted with Kochi Municipal Corporation and other
stakeholders, all projects are under scope of SPV implementation.
S. No Proposed interventions
REVISED Name of Project
SCP Cost
Clubbed / Segregated/
Estimated Cost
Status
15.1 5 Rapid response boats for water transport safety
Water Ambulance
50 Convergence. Formal confirmation from authority required
15.2 Drone Surveillance Intelligent surveillance System for Kochi
30 1456 Feasibility report for CCTV has been submitted on 21st January 2019. DPR submitted.
Since it is learnt that KSINC is operating water ambulance (Rapid response boat), the
project is part of convergence.
Module 16 Other Social Infrastructure
There were total of 2 projects identified under this module with serial number 16.1 & 16.2.
Based on the meetings conducted with Kochi Municipal Corporation, all projects are under
scope of SPV implementation.
S. No Proposed interventions SCP Cost
Clubbed / Segregated/
Status
Monthly Progress Report
Page | 64 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Estimated Cost
16.1 Upgradation of Community Centre at Mattancherry with indoor sports facilities
100 Discussed with KMC various times. As there is no Community centre available in Mattancherry for upgradation KMC to confirm dropping of the project
16.2 Standardize structures for "Petti Kada"
60 Clubbed - with Hawker zone.
The scope of project at 16.1 is yet to be clarified by KMC.
Project 16.2 has been clubbed with project number 12.2 as petti kadas will be provided for
Hawker Zones identified. Broad designs have been made. After the hawkers are identified,
implementation of this project will be taken up accordingly.
Module 17 Identity and Culture
1 project identified under this module with serial number 17.1.
S. No Proposed interventions
REVISED Name of Project SCP Cost
Clubbed / Segregated/ Estimated
Cost
Status
17.1 Fort Kochi and Mattancherry region Master plan for Tourism
3,000 Project not preparation of Master plan as its already prepared. Project is to implement individual tourism projects
Open Air Theatre (OAT) at Fort Kochi Zonal office
110 Tender has been issued. Technical Bid evaluation under progress
Development of Dutch palace node parking area and palace street entry
110 Tender has been issued. Technical Bid evaluation under progress
Fort Kochi Beach Front improvements - Part A Vasco Square
158 Project to be re-tendered
Development of Ethnic Food Hub & Dutch Quay Upgradation
100(PPP) DPR Submitted
Museum of Freedom Struggle
120 Feasibility report submitted on 20th December 2018 Museum of Spices history 150
Fort Kochi Beach Front improvements - Part B Walkway & Beach
800
Mattancherry Walkway 1100
Cultural Corridor – PT Usha Road
100 Concept Stage
The project mentioned in the SCP project list is Master plan for Tourism. Tourism Project
will be taken up individually identified in the Tourism Master plan. Based on the meetings
Monthly Progress Report
Page | 65 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
conducted with Department of Tourism, KMC and other stakeholders the projects have
been identified.
Figure 2-16 Identification of Tourism Projects
Source: PMC
Module 18 Others
There was 1 project identified under this module with serial number 18.1. Based on the
meetings conducted with MoHUA, KMC, Town Planning Dept and other stakeholders the
project is under scope of SPV implementation. This project will be integrated with IC4
project.
S. No
Proposed interventions REVISED Name of Project
SCP Cost
Clubbed / Segregated/ Estimated
Cost
Status
18.1
Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres
Base Map updation for ABD Areas
1,500 40 DPR have been submitted on 20th December, 2018. scope submitted to enable KMC to tender at the earliest
18.2
Integrated Command, Control and Communication Centre (IC4)
6450 LoA issued. Contract agreement to be signed.
Base Map Updation: The main objective of the project is to develop an updated detailed
GIS Base map on a scale of 1:1,000 for the Project area. The preliminary interpreted map
should be ground verified and the final map is to be prepared by incorporating the ground
truth data. These detailed maps consisting of the planimetric details, Plot boundaries micro
level Land use and utility services underground utilities as available from line departments
need to be generated by contact ground truth collection, updating of map and data linking.
Available data at CSML will be integrated with the Base Map in GIS during the survey
preparation of base map. The data will be collected in proper field data sheet format. The
Monthly Progress Report
Page | 66 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
base map prepared through on-screen digitization of imagery will be used for survey for the
updating purpose and finalization of layer wise Base Map with the attributes.
Final base map is to be prepared incorporating the data collected from survey and the data
for different entities. Hard copy base maps are to be prepared at 1: 1000 scale ward wise/
ABD area wise. The base maps will be prepared in various layers for ease of operation in
GIS. Layer and data structures can be modified depending on the local requirements of
CSML.
KMC has proposed to implement the project. Scope of work based on DPR prepared by
CSML has been shared with KMC & Town Planning department for further action. KMC to
tender the project at the earliest.
Progress of the Project
2.1.10 INTEGRATED COMMAND CONTROL & COMMUNICATION CENTER
Project Profile/ Components:
IC4 is the brain of the smart city, which gathers all the information of smart solutions of
different departments of the city using ICT (Information and communication technology).
IC4 is where information from different departments and various applications is collected
and analyzed for better planning of the city. It has Business Intelligence and Artificial
Intelligence (AI) engine which will process all the information and generate insights.
These insights will be helpful in managing incidents across the city and do a better
planning for the development. It also plays the role of decision support system.
Accordingly, CSML has embarked to implement the project.
Major Components of the IC4 Solution
❖ Cloud Service Provider (CSP)
❖ Internet of Infrastructure (IoI) which is an IOT platform which integrates all solutions
and facilitates, aggregation of data, big data analysis, visualization, Management,
Reporting, etc.
❖ Design and develop the Mobile app.
❖ Design and Development of Multi City Mobility Card (MCMC)
❖ Development of GIS based citizen Portal.
❖ Development of Smart Application for Solid waste Management.
❖ Development of Project Management Services along with Email Server.
❖ Aadhaar Integration
❖ Integration with Akshaya.
❖ Design and Construction of the City Command Control Room.
Overview of the Scope of MSI are as below:
❖ The MSI will conduct a detail assessment
Monthly Progress Report
Page | 67 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
❖ Design a comprehensive technical architecture and project plan.
❖ Design and development of comprehensive Internet of Infrastructure (IoI) for city
command and control operations.
❖ IoI platform would have facility of comprehensive viewing and performing operations
there will be a provision for generating configurable reports through dashboard and
also real time monitoring.
❖ Design and develop the Mobile app.
❖ Design and Development of Multi City Mobility Card (MCMC)
❖ Development of GIS based citizen Portal.
❖ Development of Smart Application for Solid waste Management.
❖ Development of Project Management Services along with Email Server.
❖ Aadhaar Integration
❖ Integration with Akshaya.
❖ Design and Construction of the City Command Control Room
Different Applications for Integration with IC4. There are different Applications of
smart city which are to be integrated to optimize the system.
❖ Applications hosted on cloud.
❖ SaaS based Applications.
❖ Existing solutions of Departments like e-Health of Kerala state, IT@school of
education Dept., Municipal information system, e-district application, Surveillance
system of Police etc.
❖ Command, Control and Communication Room (CCR).
❖ Some applications like citizen portal, mobile app, payment gateway, etc.
Project cost: INR 64.50 Crores Duration: 8 Months
Project Start date: 27 May 2019 End date (expected, excl. O&M): 27 January 2020
Contractor: M/s Fluentgrid Limited in consortium with Bharat Electronics Limited (BEL)
Current status:
❖ Offsite work started by MSI.
❖ MSI has submitted the design of Command and Control room layout. Comments on
the layout and alternative has been shared by PMC with MSI.
❖ Implementation of IC4 involves creation of respective application by each
department and extending API for integration.
❖ MSI has sent a list of different stakeholders, who will be interacting with MSI for
integration of the respective departments. For this purpose, stakeholder meeting is
essential. Stakeholder meeting is expected to start after mobilisation of MSI team.
Monthly Progress Report
Page | 68 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Any Issues/ Challenges to be discussed:
❖ Bank guarantee format changed by the bank. Issue being resolved.
❖ On site project team yet to be mobilised post contract signing
❖ MSI to identify all SPOCs and share Identification of SPOC by stakeholders with
CMSL for confirmation
❖ Procurement of GIS map by CSML for pan city
Project features
Figure 2-17 Integration of Smart Solutions with IC4
2.2 NEW PROJECTS PROPOSED
Following few projects have been proposed by stakeholders to be taken up under smart
city. These will only be taken up after council approval and based on fund availability after
all identified projects under Smart City are taken up. Also, the new projects need to be as
per Smart City guidelines. Those have been considered for following reason.
Project Name Reason for inclusion
1. Multilevel Car
parking at
GCDA ground
on
Shanmugham
Road & at
KTDC
2. Smart parking
solutions
• Already mention in SCP but not in List of projects.
• For supporting proposal of pedestrianisation parking at various
other locations are must to support parking free Broadway
street. For success of Browed Street improvement this parking is
very much required to support proposed Broadway Street
pedestrianisation and Ernakulam Market development
• GCDA amenable to provide land. Location within ABD area.
• Urban mobility already identified theme under SCP can be taken
up under same
Monthly Progress Report
Page | 69 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
2.3 UPDATED INTEGRATED PROJECTIVISATION
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
1 KER-KOC-008
1 Water Supply 1.1 West Kochi - Karuvelipady Pump house – Pumping augmentation
Convergence 100 Concept stage
2 KER-KOC-009
1 Water Supply 1.2 West Kochi - Extension of pipelines from Maradu to Island to be extended to West Kochi to supply 12 MLD
Convergence 55 30 Work completed Financial Progress : 0.27 cr
3 KER-KOC-010
1 Water Supply 1.3 West Kochi - Replacement of pipe lines from Perumanoor to Thevara and Thoppumpady bridge to Karuvelipady
Convergence 1100 448 Work completed Financial Progress : 3.65 cr
4 KER-KOC-011
1 Water Supply 1.4 West Kochi - Dedicated pumping main
Convergence 350 Concept stage
5 KER-KOC-012
1 Water Supply 1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5 million litres
Convergence 800 288 36% Physical Progress. Financial Porgress: Rs 1.12 cr.
6 KER-KOC-013
1 Water Supply 1.6 West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort Kochi and Koovapadam);
Convergence 75 DPR Stage (part of 24x7 Water supply project)
7 KER-KOC-014
1 Water Supply 1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes including Road cutting charges
Convergence 3500
8 KER-KOC-015
1 Water Supply 1.8 West Kochi - Replacement of Household connections (last mile) for across 10,000 HSCs with Smart Metering and isolation valves
Convergence 2500
9 KER-KOC-016
1 Water Supply 1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading
Convergence 100
Monthly Progress Report
Page | 70 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
10 KER-KOC-017
1 Water Supply 1.1 Mainland - Rider line for increased water supply
Convergence 1000 223 Under implementation
11 KER-KOC-018
1 Water Supply 1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near Ernakulam Ground
Convergence 300 DPR Stage (part of 24x7 Water supply project)
12 KER-KOC-019
1 Water Supply 1.12 Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves
Smart Water 1 Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves
2000 100 Project scope for project being finalised in consultation with KWA. Concept prepared. CSML to fix a meeting with KWA to finalise scope.Also issue a letter in this regard.
13 KER-KOC-020
1 Water Supply 1.13 Mainland - Bulk Meters and Isolation valves with remote meter reading
Convergence 150 DPR Stage
14 KER-KOC-021
1 Water Supply 1.14 General - Rainwater structures in ~5000 households
Convergence Rainwater harvesting structures in 13 Govt bldgs & Institutions
1125 75 Feasiblity report submitted. Project has been taken uo by KWA under Convergence
15 KER-KOC-022
2 UGSS 2.1 Decentralized Treatment and collection system for West Kochi under ADB (Mundamveli)
Waste Water & Reuse
2 Vacuum Sewer Network With House Connections and Sewage Treatment Plant
2200 15450 Tendered
16 KER-KOC-023
2 UGSS 2.2 Small bore sewer/ Vacuum system for onsite sanitation - Includes storage facility for treated water use for landscaping
11000
17 KER-KOC-024
2 UGSS 2.3 Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)
Waste Water & Reuse
3 Improvements to Sewer collection system for Mainland
7000 3450 Project scope to be confirmed with stakeholders (KWA)
Monthly Progress Report
Page | 71 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
Convergence Elamkulam STP 1300
18 KER-KOC-025
3 NMT Roads and Pedestrianized areas
3.1 Relaying of roads Improvement of Roads
4 Development of Other Roads in Ernakulam
4200 4360 Awarded
19 KER-KOC-026
3 NMT Roads and Pedestrianized areas
3.2 Standard Footpaths including signages
5 Development of Other Roads in West Kochi
2853 6020 To be retendered
20 KER-KOC-027
3 NMT Roads and Pedestrianized areas
3.3 Restoration/ Rehabilitation of Stormwater drains in the proposed area
2360
21 KER-KOC-028
3 NMT Roads and Pedestrianized areas
3.4 MLCP and Commercial complex at Kacheripady
Transport 6 Parking management plan for ABD area & Development of Multi Level Car Parking at Kacheripady
5000 690 EOI Published. No EOI received. Retendered. 2nd time again no bid received. Project to be re-tendered
Transport 7 MLCP at GCDA land at Marine Drive
19.9 Feasibility report prepared. DPR preparation ongoing. CSML Board & stakeholders approval required to enable tendering
8 MLCP at KTDC complex at Maneka
9 Smart Parking solutions at various location in ABD area
10 Commercial complex at Kacheripady
500
22 KER-KOC-029
4 Main Roads 4.1 World class Arterial roads -- KB Jacob & Amravati Road/ Bazaar Road in West/ -- Avenue, MG Rd, DH Rd, Banerjee Rd in Central city
Smart Street Features
11 Development of Smart Roads in Ernakulam under Smart City Mission
5287 6153 Re-tendered into 5 packages (initially 2 packages)
23 KER-KOC-030
4 Main Roads 4.2 Relaying of roads, Aesthetic and improved Urban design Pedestrian facilities with
12 Development of Smart Roads in West Kochi under Smart City Mission
1650 3031
Monthly Progress Report
Page | 72 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
Street furniture, Boulevards and urban greenery
24 KER-KOC-031
4 Main Roads 4.3 Utility ducting for SWD, Water supply, Sewerage, OFC etc
3300
25 KER-KOC-032
4 Main Roads 4.4 Signages, Junction improvement with Intelligent Traffic management
13 Integrated Traffic Management Systems (ITMS)
97 2690 Awarded
KER-KOC-086
14 Road Signages 240 DPR submitted. To be tendered post initiation of road construction work
26 KER-KOC-033
4 Main Roads 4.5 Escalator FOBs Smart Street Features
15 FOBs - West Kochi (3 Nos) 240 215 Project scope being finalised in consultation with stakeholders
27 KER-KOC-049
5 Energy Supply 5.1 Compact Secondary Substation (990 KVA)
Smart Street Features
16 Development of Roads electrical infrastructure in Ernakulam & West Kochi
180 6340 Re-tendered into 5 packages (initially 2 packages). Bids submitted under evaluation
43 KER-KOC-050
6 Energy Efficiency
6.1 Solar based LED with Smart poles
Smart Street Features
17 Implementation of Smart LED lighting
1250
3209 Re-Tendered. Under evaluation
KER-KOC-088
Smart Telecom 18 Intelligent Street Poles 30160 PPP. Tendered
44 KER-KOC-051
6 Energy Efficiency
6.2 Solar panels in Households and Institutions - Grid connected
Solar 19 Solar panels in Govt. buildings
1758
570 Contract Awarded. Work on-going
Solar 20 Solar panels in public places (Canals, parks etc)
Concept Stage. May be clubbed with Canals project.
45 KER-KOC-052
7 Solid waste and Sanitation
7.1 Equipments including Smart Street sweepers/ GPS enabled Vehicles/compactors
Equipments including Smart Street sweepers/ GPS enabled Vehicles/compactors
600
Monthly Progress Report
Page | 73 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
Solid Waste Management
21 Smart & Improved Secondary Storage & Transportation of Solid Waste using Portable Compactor Technology
440 To be retendered post discussions with KMC
Solid Waste Management
22 Smart & Improved Battery Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area
100 DPR submitted. To be tendered post KMC approval
KER-KOC-087
Solid Waste Management
23 Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area
320 To be retendered post discussions with KMC
46 KER-KOC-053
7 Solid waste and Sanitation
7.2 Bio-composting in all Government institutions
Solid Waste Management
5
47 KER-KOC-054
7 Solid waste and Sanitation
7.3 Household segregated bins for Organic and inorganic wastes
Solid Waste Management
24 Distribution of Household Bins & Street Litter Bins for improvement of waste segregation in ABD
74 67 Awarded
48 KER-KOC-055
7 Solid waste and Sanitation
7.4 Public toilets with Fit-in Treatment facility for Decentralized STP in West kochi
Other social Infrastructure
25 Renovation and Upgradation of Existing Public Toilet Facilities in West Kochi & Ernakulam Market.
10 180 Tendered
49 KER-KOC-056
8 Parks and Open spaces
8.1 Upgradation of Nehru Park Convergence 200 200 Under implementation
50 KER-KOC-057
8 Parks and Open spaces
8.2 Development of open spaces and playgrounds
Smart Placemaking
26 Development of Open spaces and playgrounds
30 250 DPR Stage
51 KER-KOC-058
8 Parks and Open spaces
8.3 Open space corridor linking DH Ground to Mangalavanam (depends on ecological sensitivity)
Smart Placemaking
27 Improvements to Marine Drive walkway phase I
90 710 Tendered
52 KER-KOC-059
8 Parks and Open spaces
8.4 Mangalavanam Eco-restoration project
Smart Placemaking
28 Mangalavanam Eco-restoration project
100 100 Concept shared with forest department. Multiple discussions held. Confirmation
Monthly Progress Report
Page | 74 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
awaited from stakeholder on scope of work to start work on Feasibiltiy report.
53 KER-KOC-060
9 Canal Restoration
9.1 Restoration of Mullassery canal - including linking of standardized area drains
Smart Placemaking
29 Restoration of Mullassery canal - including linking of standardized area drains
100 100 Based on stakeholder discussions held on 28 May 2019, CSML to confirm scope of project (extended of the canal under smart city scope) for feasibility report revision
54 KER-KOC-061
9 Canal Restoration
9.2 Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts
Smart Placemaking
30 Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts
500 500 KMRL & CSML to confirm whether CSML or KMRL to take up market canal works. Thereafter FR will be revised accordingly
55 KER-KOC-062
9 Canal Restoration
9.3 Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features
Smart Placemaking
31 Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features
2000 2000 Based on stakeholder discussions held on 28 May 2019, CSML to confirm scope of project (extended of the canal under smart city scope) for feasibility report revision
56 KER-KOC-063
9 Canal Restoration
9.4 Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road
Smart Placemaking
32 Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road
1500 1500
57 KER-KOC-064
10 Urban mobility (Multi Modal Transport)
10.1 Water transport infrastructure (around 12 100 pax boats)
Convergence 4200 5600 Tender stage
Monthly Progress Report
Page | 75 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
58 KER-KOC-065
10 Urban mobility (Multi Modal Transport)
10.2 Electric Feeders, Bicycle Sharing, Elevated Walkways and Travelators
Convergence Electric Feeders 1148 1148 Taken up by KMRL. Also propsoed as part of Broadway project
KER-KOC-003
Transport 33 Public Bicycle Sharing 1000 Contract Awarded. Work on-going
Elevated Walkways and Travelators clubbed with Ernakulam Market. Scope to be finalised by stakeholders
59 KER-KOC-002
10 Urban mobility (Multi Modal Transport)
10.3 Walkway from Ekm Jetty to Metro station
Smart Street Features
34 Walkway from Ekm Jetty to Metro station
900 470 Under Implementation
60 KER-KOC-007
10 Urban mobility (Multi Modal Transport)
10.4 Jetty improvement Convergence 800 4000 DPR stage
61 KER-KOC-066
10 Urban mobility (Multi Modal Transport)
10.5 Property development along jetties
Convergence 720 DPR stage
62 KER-KOC-067
10 Urban mobility (Multi Modal Transport)
10.6 Boatyard and Command & Control Centre
Convergence 2000
63 KER-KOC-068
10 Urban mobility (Multi Modal Transport)
10.7 Dredging cost Transport Marina 1000 2000 Concept shared based on discussed hwld on 14 Feeb 19 with all stakeholders. CSML to provide approval to proceed with Feasiblity preparation.
Monthly Progress Report
Page | 76 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
64 KER-KOC-069
10 Urban mobility (Multi Modal Transport)
10.8 Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
Integrated Command and Control Centre/ Master Integrator
35 Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
60 60 Combined stakeholder meeting & letter to stakeholders for confirmation on project to be taken up under Smart City or not
65 KER-KOC-070
10 Urban mobility (Multi Modal Transport)
10.9 Standard Wifi Enabled Bus Stands With Commercial space development
Integrated Command and Control Centre/ Master Integrator
36 Standard Wifi Enabled Bus Stands With Commercial space development
300 300 Combined stakeholder meeting & letter to stakeholders for confirmation on project to be taken up under Smart City or not
66 KER-KOC-071
11 Housing (Urban Planning)
11.1 Integrated redevelopment of Slum housing
Affordable Housing
37 Integrated redevelopment of Slum housing
14140 4685 Letter to KMC to be sent from CSML Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. R&R will require additional time. With limited SCM duration.
Monthly Progress Report
Page | 77 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
Confirmation on scope needs to be expedited.
67 KER-KOC-072
11 Housing (Urban Planning)
11.2 Upgradation of infrastructure in Housing through Credit linked schemes
Affordable Housing
38 Beneficiary Led housing scheme 2435 1300 CSML Transferring funds to KMC
68 KER-KOC-073
11 Housing (Urban Planning)
11.3 Construction & upgradation of 755 DUs in Thuruthy, Kalvathy & Konchery colony
Affordable Housing
39 Construction & upgradation of infrastructure in Thuruthy - BRIDGES
7424
515 DPR Stage. Soil test conducted. Broad Estiamte shared with KMRL. Soil test conducted Structural dwgs under preparation.
40 Construction of Second tower at Thuruthy
3500 DPR to be prepared post approval from KMC.
41 Construction of First tower at Thuruthy
2100 CSML Transferring funds to KMC
69 KER-KOC-074
12 Economy and Employment
12.1 Broadway Market and Ernakulam market Redevelopment and Mattancherry spice market
Smart Placemaking & PPP
42 Broadway Street 1000 1000 Feasibility report submitted. DPR Stage
43 Ernakulam Market Redevelopment+Escalator FOBs+Elevated Walkways and Travelators
10000 10240 Feasibility report submitted. DPR Stage. KMC to approve initiate R&R asap. KMC to share final list of eligible shopkeepers with shop size requirement. Suggest on Transit shelter strategy including confirmation on alternate land for
Monthly Progress Report
Page | 78 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
relocation, expenditure during relocation period, revision of rental rates for new building and negotiations, approval of revised traffic management plan from beneficiaries, Co-ordination with all beneficiaries. i. KMC to verify and compile final list of vendors and hawkers and share with smart city team at the earliest to enable Smart city team to do detailing of the designs ii. Confirmation for land for transit shelters at the earliest. iii. KMC to confirm allotment of shops by zoning. Smart city to design accordingly
Smart Placemaking
Mattancherry spice market Redevelopment
Taken under streetscape improvement as part of road project
70 KER-KOC-075
12 Economy and Employment (Central City
12.2 Standard Hawker zones in Fort Kochi
Smart Placemaking
44 Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"
500 560 Feasibility Stage
Monthly Progress Report
Page | 79 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
Urban Renewal & Mkt Dev)
71 KER-KOC-076
13 Health 13.1 Scale up of GH into a Super-speciality care centres
Health 45 Extension of Cancer Speciality Block for General Hospital.
3000 2600 Awarded
KER-KOC-090
E-Health 46 E-health solutions for selected hospitals
371 Awarded
72 KER-KOC-077
13 Health 13.2 Integrated development of 4 Hospitals in West Kochi - Excellence in Secondary care
Health 47 Out Patient & Admin block, Fort Kochi taluk Hospital
1000 465 Tendered
KER-KOC-089
Health 48 Out Patient & Admin block, Women & Child Hospital, Mattancherry
457 Tendered
73 KER-KOC-079
14 Education 14.1 Anganwadis and public schools Upgradation of facilities - Basic services, Digital classrooms, Libraries, Eco-toilets, Sports kits , Biogas plant, Urban farming etc
Education 49 CIVIL - Anganwadis and public schools
450 200 Feasibility Stage
74 KER-KOC-080
14 Education 14.2 Higher Educational institutions Upgradation of facilities - Basic services, Digital classrooms, Libraries, Eco-toilets, Sports kits , Biogas plant, Urban farming etc
Education 50 Higher secondary block, Central Calvathy GHSS, Fort Kochi
100 467 Tendered
Education CIVIL 1 - Mattancherry School - Higher Educational institutions
Education Maharajas Ground 500 Concept tage
Education SRV School 800 Outside ABD. CSML to provide approval for the project to be taken up.
Monthly Progress Report
Page | 80 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
E- Learning 51 Smart Classroom for 100 classrooms PAN city
490 Tendered. Cancelled
75 KER-KOC-081
15 Safety and Security
15.1 5 Rapid response boats for water transport safety
Convergence 50 CSML to confirm with KMRL
76 KER-KOC-082
15 Safety and Security
15.2 Drone Surveillance Integrated Command and Control Centre/ Master Integrator
52 Safety & Security CCTV Surveillance
30 1436 DPR stage
77 16 Other Social Infrastructure
16.1 Upgradation of Community Centre at Mattancherry with indoor sports facilities
Other Social Infrastructure
53 Upgradation of Community Centre at Mattancherry with indoor sports facilities
100 100 Clarification on scope needed from KMC
78 16 Other Social Infrastructure
16.2 Standardize structures for "Petti Kada"
60
79 KER-KOC-083
17 Identity and Culture (Heritage & Tourism Development)
17.1 Fortkochi and Mattanchery region Master plan for Tourism
Smart Placemaking
Implementation of identified Tourism related projects in Fort Kochi & Mattancherry
3000 3000
17.1.1 54 Open Air Theatre at Fort Kochi Zonal office
110 Tendered
55 Museum of Freedom Struggle 120 DPR stage
56 Museum of Spices history 150 Formal confirmation on location required from KMC
17.3 57 Development of Ethnic Food Hub
KER-KOC-092
58 Development of Dutch palace node parking area and palace street entry
110 Tendered
KER-KOC-091
59 Fort Kochi Beach Front improvements - Vasco Square
171 Tendered
60 Fort Kochi Beach Front improvements - Phase II
829 DPR stage
61 Mattancherry Walkway 1100 Put on hold by CSML till required approvals are received
Monthly Progress Report
Page | 81 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
SCP S. No.
Project Code as per Central MIS
Module No.
Module Name SCP Project No.
SCP Project Name Category (as per MoHUA)
Revised S. No.
Revised Name of Project Original Project Cost as per SCP
Estimated Cost (if any)
Stage of project (for Convergence projects status has been provided by respective stakeholder)
17.2 Developing a Water & Adventure sports center at Marine drive
110 DPR stage
62 Cultural Corridor PT Usha Road 100 Feasibility stage
17.1.9 Multimedia based Light & Sound show
Put on hold by CSML till required approvals are received
80 KER-KOC-084
18 Others 18.1 Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres
Convergence 63 Base map upgradation for ABD area
1500 50 DPR submitted and scope submitted to enable KMC to tender at the earliest
KER-KOC-004
Integrated Command and Control Centre/ Master Integrator
64 Integrated Command, Control and Communication Centre (IC4)
6450 Awarded
2.4 OVERALL PROGRESS
Sl No
Source of Funds
No of Projects as per SCP
Cost as Per SCP ( Rs in
Cr
No of Revise
d Projec
ts
Revised Cost
( Rs in Cr)
No of As
Issued
As issued- Amount
No. of TS
Issued
Amount of TS
issued
No of Tender
ed Projec
ts*
Amount of
Tendered
No of Work
Awarded
Amount of Work Awarded
No of Work Completed
Expenditure
1 SPV 80 1347.5
60 1005.17 27 565.09 25 541.68 22 573.21 10.00 258.62 5.50
2 PPP 4 336.58 3 336.58 3 336.58 3 336.58 2.00 35.00 26.80
3 Convergence 2 646.000 20 860.27 0 0.00 8 155.79 8 155.79 6.00 59.79 2 6.70
Note * Total - Tendered Number & Amount: Projects not included which are awarded on nomination basis
Monthly Progress Report
Page | 82 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
2.5 SECTOR PROGRESS
Sl No Name of the Sector
No of Projects as per SCP
Cost as Per SCP ( Rs in
Cr)
No of Revised Projects
under SCP
Revised Cost
( Rs in Cr)
No. of Technical Sanction Issued
Technical Sanction Issued - Amount
Total Tendered (Number)
*
Total - Tendered Amount (Rs in
Crore)*
Work Awarded - Number
Work Awarded - Amount (Rs in cr)
Work Completed
Total - Expenditure ( Rs in crore)
A. ABD AREA PROJECTS SPV
1 Water Supply 1 11.25 1 1 0 0 0 0.0 0.0 0.0
2 UGSS 3 202.00 2 189 1 143.3 1 143.3 0.0 0.0
3 NMT Roads 4 44.13 7 133.85 3 103 3 103.0 1.0 43.6
4 Main Roads 5 106.04 5 123.30 3 103.9 3 106.9 3.0 118.7
5 Energy Supply 16 122.44 1 63.4 1 0 1 63.4 0.0 0.0
6 Energy Efficiency
2 30.08 4 339.87 3 343.28 2 333.7 1.0 5.7 3
7 Solid Waste and Sanitation
4 6.89 5 11.07 4 10.37 4 10.4 1.0 0.7
8 Park & Open Space
4 2.20
3 10.6 1 7.1 1 7.1 0.0 0.0
9 Canal Restoration
4 41.00
4 41 0 0 0 0 0 0
10 Urban Mobility 4 24.08 4 18.3 2 19 2 14.7 2 14.7 4.3
11 Housing 3 239.99 5 121 0 0 0 0 0 0
12 Economy and Employment
2 115.00
3 115.6 0 0 0 0 0 0
13 Health 2 40.00 4 38.93 4 30.17 2 9.22 2 20.71
14 Education 2 5.50 2 7.67 1 4.67 1 4.67 0 0
15 Safety and Security
2 0.80
1 14.56 0 0 0 0 0 0
16 Other Social Infrastructure
2 1.60
1 0 0 0 0 0 0 0
17 Identity and Culture
1 30.00
9 24.11 3 3.78 3 3.78 0 0
18 Others 1 15.00 2 64.5 1 84.69 1 84.7 1 64.5
Total -A 62 1138 63 1317.75 27 853.26 24 884.79 11 268.62 0 7.3
B- Project Under Convergence
19 Water Supply 13 120.3 13 80.64 4 9.88 4 9.88 4 9.88 2 5.04
20 UGSS 1 13.00 0 0 0 0 0 0
21 Park & Open Space
1 2.00 1 2.00 1 2 1 2 1 2 1.66
22 Urban Mobility 4 87.2 3 96.32 2 96 2 96 0 0
23 Housing 1 47.91 1 47.91 1 47.91 1 47.91
Monthly Progress Report
Page | 83 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No Name of the Sector
No of Projects as per SCP
Cost as Per SCP ( Rs in
Cr)
No of Revised Projects
under SCP
Revised Cost
( Rs in Cr)
No. of Technical Sanction Issued
Technical Sanction Issued - Amount
Total Tendered (Number)
*
Total - Tendered Amount (Rs in
Crore)*
Work Awarded - Number
Work Awarded - Amount (Rs in cr)
Work Completed
Total - Expenditure ( Rs in crore)
Total- B 18 209.5 19 239.87 8 155.79 8 155.79 6 59.79 2 6.7
C- PAN City Project
24 Water Supply 1 621 1 621
25 INTEGRATED CITY APP
1 25 1 25 1 25 1 25 1 25.00 1 25.00
Total -C 2 646 2 646 1 25 1 25 1 25.00 1 25.00
Grand Total -(A+B+C)
82 1993.5 84 2203.62 36 1034.05 33 1065.58 18 353.41 3 39
Note * Total - Tendered Number & Amount: Projects not included which are awarded on nomination
2.6 IMPLEMENTATION SCHEDULE
Based on the scope of the work which is being finalised by consultation with stakeholders, PMC has assessed the timeline for submitting the
reports. The final timeline will be given for the projects once the scope of work will finalised. The implementation schedule for the projects is given
below:
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Replacement of connections (last mile) for across 550 HSCs (Commercial and Domestic) with Smart Metering and isolation valves
2000 100
Scope of work is being clarified with consultation with Stake holders
30 days post confirmation of Scope of Work
25 days post confirmation of Feasibility Report
15 days post confirmation of DPR
60 days after issuance of tender
Project scope for project being finalised in consultation with KWA. Concept prepared. CSML to fix a meeting with KWA to finalise scope.
Monthly Progress Report
Page | 84 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Also issue a letter in this regard.
Improvements to sewer collection system for West Kochi
13200 15450 Tender issued 7-Feb-18 Revised- 11-Sep-18
20-Feb-2019/ 28-Feb-2019/ 05-Mar-2019
-
08-Mar-2019 15-July-2019
Improvements to sewer collection system for Mainland
7000
3450 Feasibility Stage
30 days post confirmation of Scope of Work
30 days post confirmation of Feasibility Report
30 days post approval of DPR
60 days post tender
Project scope to be confirmed with stakeholders (KWA & KMC)
Development of Other Roads in Ernakulam under Smart City Mission
4200
4360 LoA issued on 9th April
10-Aug-18 30-Aug-18
11-Oct-18/ 14-Feb-2019
09-April-2019
2853
2360
Development of Other Roads in West Kochi under Smart City Mission
6020 Project re-tendered.
10-Aug-18
30-Aug-18
11-Oct-18/ 15-Feb-2019
15-Oct-2019
Project to be re- tendered
MLCP at Kacheripady
5000
616 Tender issued
26-Feb-18 Revised FR – 07-Oct-18
08-Feb-2019 08-March-2019 15-Oct-2019
Project to be re-tendered
Commercial complex at Kacheripady
500
Combined Feasibility report submitted–Scope of work to be finalised with stake holders consultation
7-Oct-2018
30 days post confirmation of scope of work and land availability
15 days post approval of DPR
60 days post tender
Scope is being finalised with Stakeholders
MLCP at KTDC & GCDA land at Marine Drive
1700 7-Oct-2018
30 days post confirmation of scope of work and land availability
15 days post approval of DPR
60 days post tender
Scope is being finalised with Stakeholders
Monthly Progress Report
Page | 85 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Smart Parking Solutions in ABD area
190 DPR stage 7-Oct-2018 15-June-2019 15-July-2019 30-Sept-2019
DPR under preparation
Development of Smart Roads in Ernakulam under Smart City Mission
5287 6153 LoA issued on 9th April
10-Aug-18
30-Aug-18
11-Oct-18/ 14-Feb-19
09-April-2019
Development of Smart Roads in West Kochi
1650 3031
LoA issued on 9th April
10-Aug-18
30-Aug-18
11-Oct-18/ 16-Feb-19
09-April-2019
3300
Development of Smart Roads electrical infrastructure in Ernakulam & West Kochi
12253 6340
Project re-tendered Bid evaluation under progress
10-Aug-18
30-Aug-18
11-Oct-18/ 16-Feb-19
30-June-2019
Integrated Traffic Management Systems (ITMS)
97
2690 LoA issued 2-Feb-18
6-Feb-18
24-Feb-18
22-Feb-2019
-
Roads Signages 240 DPR submitted 15-Feb-19
28-Feb-2019 -
15-June-2019 14-Aug-2019
-
FoBs(3 nos) –West Kochi
215
Combined Feasibility Report submitted Thuruthy Project. Project scope being finalised in consultation with stakeholders
27-Sept-2019
30 days post confirmation of the scope of work
15 days post approval of DPR
90 days post tender
Implementation of Smart LED Lighting in ABD
1250 3209 Project Re-tendered.
12-Feb-18
17-Feb-18
24-Feb-18 Re tendered- 26-12-18
30-June-2019
Monthly Progress Report
Page | 86 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Under evaluation
Intelligent Street Poles 30158 Tender issued. 8-Feb-18
15-Nov-2018/ 08-Feb-2019
07-Mar-2019 15-July-2019
Solar Panels in Govt. Buildings
1758 570 Project under implementation.
2-Feb-18 7-Feb-18 24-Sep-18 - -
Supply, Operation and Maintenance of Portable Compactor for Secondary Storage & Transportation of Solid Waste
600
440
Tender cancelled. Project to be re-tendered
14-Feb-18
20-Mar-18
04-Apr-18 Project to be retendered by 30th July, 2019
30-Sept-19
-
Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area
100 DPR Submitted
26-Feb-18
28-Feb-18
30 days post approval of KMC
60 Days post tender
Approval awaited from KMC
Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area
320
Tender cancelled. Project to be re-tendered
20-Mar-18
20-Mar-18
04-Apr-18 Project to be retendered by 30th July, 2019
30-Sept-19
-
Distribution of Household Bins & Street Litter Bins for improvement of waste segregation in ABD
74 67 LoA issued on 8th May, 2019
7-Feb-18
28-Feb-18
04-Apr-18 08-May-19
-
Monthly Progress Report
Page | 87 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Public toilets in West Kochi & Ernakulam Market
10 180 Tender issued 27-Sept-18 -
13-Feb-2019 -
08-March-2019 15-June-2019
-
Development of open spaces and playgrounds
30 250 Feasibility report Submitted
26-Mar-2019
30-May-2019
20-June-2019
11-June-19 30-July-19
30-Sept-2019
Marine Drive Walkway Phase I
90 710 DPR Submitted
03-Nov-18
11-Nov-18 04-Feb-19 27-Mar-2019
08-Mar-2019 15-June-2019
Mangalavanam Eco-restoration project
100 100
Conceptualization Stage. Various discussions held. Confirmation awaited from stakeholder on scope of work
30 days post approval on concept shared
20 days post approval of Feasibility Report
20 days post approval of DPR
60 days post tender
Confirmation awaited from stakeholder on scope of work
Restoration of Mullassery canal - including linking of standardized area drains
100 100 Feasibility Stage
02-Mar-2019/ Rev- 30-July-2019
30-Sept-2019 30 –Oct-2019 30-Dec-2019
Feasibility report to be revised post confirmation on additional canal stretch and surveys by CSML
Restoration of Market canal - Walkways and Market square around the canal pond, Solar
500 500 Feasibility Stage
02-Mar-2019/ Rev- 30-July-2019
30-Sept-2019 30 –Oct-2019 30-Dec-2019
Feasibility report to be revised post confirmation on additional canal
Monthly Progress Report
Page | 88 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
paneled roofs, LED Lighting, Light posts
stretch and surveys by CSML
Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features
2000 2000 Feasibility Stage
02-Mar-2019/ Rev- 30-July-2019
30-Sept-2019 30 –Oct-2019 30-Dec-2019
Feasibility report to be revised post confirmation on additional canal stretch and surveys by CSML
Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road
1500 1500 Feasibility Stage
02-Mar-2019/ Rev- 30-July-2019
30-Sept-2019 30 –Oct-2019 30-Dec-2019
Feasibility report to be revised post confirmation on additional canal stretch and surveys by CSML
Bicycle Sharing 1148 1000 Work under implementation
- 2-Mar-18 06-Mar-2018 15-Nov-18
-
Walkway from Ekm Jetty to Metro station
900 900 Under Implementation
30-Mar-17
Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
60 60
Concept Stage. Scope being finalised with KMC
30 days post confirmation of scope of work
30 days post approval of feasibility report
15 days post approval of DPR
60 days post tender Scope is being
finalised with Stakeholders
Monthly Progress Report
Page | 89 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Standard Wifi Enabled Bus Stands with Commercial space development
300 300
Concept Stage. Scope being finalised with KMC
30 days post confirmation of scope of work
30 days post approval of feasibility report
15 days post approval of DPR
60 days post tender
Scope is being finalised with Stake Holders
Integrated redevelopment of Slum housing
14140 4685 Scope to be finalised by KMC
30 days post approval of Concept report
90 days post approval of feasibility report
20 days post approval of DPR
60 days post tender
Scope to be finalised by KMC
Construction of First tower at Thuruthy
7424
2100
Transfer of fund by CSML. No scope for PMC
Construction of Second tower at Thuruthy
3500 Scope being finalised with KMC
30 days post approval of Concept report
90 days post approval of feasibility report
20 days post approval of DPR
60 days post tender
Scope to be finalised by KMC
Construction & upgradation of Infrastructure in Thuruthy, Construction of Bridges
515 Feasibility report submitted
27-Sept-2019
30-May-2019
15-June-2019
15-June-2019
15-July-2019
30-Sept-2019
Location approval awaited
Broadway Street 11000 1000 Feasibility Report Submitted.
15-Oct-18 -
15-June-2019
30-July-2019
15-July-2019
14-Aug-2019
14-Oct-2019
R&R assistance required from KMC to complete DPR
Ernakulam Market Redevelopment+Escalator FOBs+Elevated Walkways and Travelator
10000 Feasibility Report Submitted,
19-Sep-18
30-April-2019
15-June-2019
22-June -2019
15-July-2019
16-Sept-2019
R&R assistance required from KMC to complete DPR
Standard Hawker zones in Fort Kochi +
500 560 Concept Stage 30-May-2019 15-July-2019
15-July-2019
30-July-2019
30-July-2019
30-Nov-2019
Scope of the work is being finalised
Monthly Progress Report
Page | 90 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Standardize structures for "Petti Kada"
Cancer Extension Block, General Hospital.
3000 2600
LoA Issued to INKEL on nomination basis
10-Jul-18
Contract given on nomination basis
Out Patient & Admin block, Fort Kochi taluk Hospital
1000 467 Tender issued 28-Feb-18
17-Mar-18 Rev- 30-Oct-18
07-Mar-2019 15-June-2019
Out Patient & Admin block, Women & Child Hospital, Mattancherry
457 Tender issued 28-Feb-18 27-Jul-18 Rev- 13-Nov-18
07-Mar-2019 15-June-2019
E-health solutions for selected hospitals
371 LoA issued 15-Sep-18 20-Dec-18/ 07-Feb-19
-
27-Feb-2019
Contract to be awarded on nomination basis
Upgradation of Anganwadis
450 300 DPR under progress
06-Apr-2019
30-Mar-2019
30-May-2019
30-Apr-2019
30-June-2019
30-Aug-2019
Higher secondary block, Central Calvathy GHSS, Fort Kochi
100 467 Tender issued Submitted on 28-Feb-18 -
15-07-2018/ 03-12-2018 -
07-Mar-2019 30-Sept-2019
Project to be re- tender
Smart Classroom for 100 classrooms PAN city
490 Tender cancelled
5-Feb-18
9-Feb-18
24-Feb-18 - -
Intelligent Crime Surveillance system
30 1456 DPR Submitted
21-Jan-2019 -
21-Mar-2019 -
30-May-2019
30-July-2019
16-Sept-2019
Upgradation of Community Centre at Mattancherry with indoor sports facilities
100 100 Clarification on scope needed from KMC.
30 days post confirmation of scope of work
30 days post approval of Feasibility report
20 days post approval of DPR
60 days post tender
KMC proposed to drop the project. Formal confirmation needed
Monthly Progress Report
Page | 91 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Implementation of identified Tourism related projects in Fort Kochi & Mattancherry
3000 3000 Master plan for Tourism Projects
Open Air theatre at Fort Kochi
110 Tender issued 20-Aug-18 Rev- 10-Oct-18/ Rev- 06-Feb-2019
02-Feb-2019
07-Mar-2019 30-Jun-2019
Museums of Freedom Struggle Jail
120 Feasibility Report submitted
20-Dec-2018
30-May-2019
30-May-2019
01-June-2019
30-June-2019
30-Aug-2019
RFP under preparation
Museums of spices 150 Feasibility Report submitted
20-Dec-2018
15-June-2019
15-June-2019
01-June-2019
15-July-2019
30-July-2019
Building confirmation awaited
Development of Ethnic Food Hub
(PPP) Feasibility Report submitted
20-Dec-2018 20-Feb-2019
Development of Dutch palace node parking area and palace street entry
110 Tender issued 20-Dec-2018
20-Feb-2019
7-Mar-2019 30-June-2019
Fort Kochi Beach Front improvements - Vasco Square
158 Tender issued
20-Dec-2018
28-Feb-2019
07-Mar-2019 30-Sept-2019
Project to be re- tender
Fort Kochi Beach Front improvements - Phase II
500
Feasibility report Submitted
28-Feb-2019
01-June-2019
30 June-2019
30-Aug-2019
Mattancherry Walkway 1100
Feasibility report Submitted
20-Dec-2018
15-June-2019
15-July-2019
15-July-2019
14-Aug-2019
14-Oct-2019
Approval awaited. Stakeholder consultations to be conducted
Monthly Progress Report
Page | 92 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Name of Project - REVISED SCP Projectivisation
Original Project Cost as per SCP (Rs. in Lakh)
Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)
Stage of project
Submission/Timeline Feasibility Report
Submission/Timeline DPR
Submission/Timeline Tender Proposed
Contract Award timeline
Remarks As per April 2019
Proposed Revised Timeline
As per April 2019
Proposed Revised - Timeline
As per April 2019
Proposed Revised Timeline
Cultural Corridor - PT Usha Road
100 Feasibility Stage
30-May-2019
30-June-2019
15-June-2019
15-July-2019
15-July-2019
14-Aug-2019
30-Oct-2019
Scope is being finalised
Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres
1500 50 DPR Submitted
- 21-Dec-2018
- To be tender by KMC
Integrated Command, Control and Communication Centre (IC4)
10000 6450 LoA issued 15-May-18
20-May-18
26-Apr-18
28-Feb-2019
23- May-2018 28-Feb 2019
Monthly Progress Report
Page | 93 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Project planning
Monthly Progress Report
Page | 94 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 95 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 96 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 97 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 98 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 99 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 100 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 101 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 102 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
3 WAY FORWARD
3.1 KEY CONCERNS
• KMC to start with confirmation of land for rehabilitation and agreements with
vendors Ernakulam market area
• Confirmation from KMC regarding Broadway market project
• No progress made by KMC regarding housing project. Smart city has limited time
for implementation hence same needs to be expedited by KMC.
3.2 ISSUES AND CONCERNS
3.3 ASSISTANCE REQUIRED
Finalisation of project scope. As we will be entering another year of SCM we need to
expedite project scope with stakeholders at the earliest.
List of projects requiring CSML assistance in finalizing the scope and conducting
stakeholder meetings
•Projects & scope not yet identified
•PMC to carry out multiple meetings to identify & finalise scope of projects
Identification of Project
•Once broad scope is identified stakeholders are informed
•Delayed response
•Continuous chasing required
•Change in project scope many times
•Multiple stakeholders within same organisation
Stakeholder management
•List of beneficiaries
•List of hawkers
•List of slums
•Timely Site clearances
KMC approvals & data
•Process for taking permisisons requere purchase of forms, stamp papers foraffidavit. CSML to purchse these forms as other stakeholders have nottendered thep rojects thus, unable show such costs
•Key agencies yet to appoint nodal person
•Nodal person to assist in provision of data, scope and approvals
•CSML to include nodal officers from key staekholder (owner of the project fromthe signing of the contract so that hand over at time of completion is easy andknown to owner.
Tendered projects & to be awarded
Monthly Progress Report
Page | 103 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Table 3-1: Projects requiring stakeholder assistance
Project name Approx. Broad cost INR CR.
Assistance required
PROJECTS UNDER PROGRESS (FEASIBLITY REPORT / DPRS UNDER PREAPRATION) Smart water solutions - smart metering and smart valves for all connections in ABD
1.00 CSML to share letter with KWA requesting meeting to finalise scope.
Restoration of Mullassery Canal - including linking of standardized area drains
1.00 Confirmation on stretch of Canal to be taken up under Smart City scope. Surveys for additional stretch to be carried by SPV. Restoration of Market Canal - walkways and
market square around the canal pond, solar paneled roofs, led lighting, light posts
5.00
Restoration of Kalvathy Canal and area drain improvement - open spaces, street furniture and landscaping features
20.00
Restoration of Rameswaram-Kalvathy canal - upto cochin college – walkways and linking the canal bank road
15.00
Broadway street upgradation 10.00 CSML conducting various meetings. Ernakulam market redevelopment 100.00 CSML conducting various meetings. KMC to
lead with R&R Standard hawker zones in Fort Kochi + standardize structures for "petti kada"
5.60 Feasibility report to be submitted by 30 June 2019. Based on FR submitted combined stakeholder meeting to be conducted
MLCP at KTDC 7.00 Letter and meetings with stakeholders to finalise locations for tendering
Museum of freedom struggle 1.20 Letter to KMC & Stakeholders regarding scope of project formulated by CSML
Museum of spices history 1.50 Letter to KMC requesting for confirmation on space.
Mattancherry walkway 11.00 Combined stakeholder meeting Cultural corridor - Pt Usha road 0.50 Letter to KMC regarding scope of project
formulated by CSML Fort Kochi beach front improvements - part B walkway & beach
5.00 Combined stakeholder meeting & letter to stakeholders
Construction & upgradation Thuruthy, Kalvathy & Konchery colony - construction of bridges
5.15 Letter to KMC for confirmation on scope and location of Bridges.
Development of open spaces 2.50 Letter to KMC for confirmation and approval of open spaces and parks selected and proposals
Anganwadis 3.00 Letter to KMC & ICDS Combined stakeholder meeting for confirmation and approval of selected Anganwadis and proposals
PROJECTS REQUIRING STAKEHOLDER MEETINGS & CONFIRMATION ON SCOPE FOR FURTHER ACTION (PREPARATION OF REPORTS UNDER SCM)
Standard wifi enabled bus stands with commercial space development
3.00 Combined stakeholder meeting & letter to stakeholders
Construction of Second Tower at Thuruthy 35.00 Letter to KMC. Project preparation will require time. Minimum 3 months for DPR & tender preparation. Hence to enable tendering confirmation regarding project scope to be shared at the earliest.
Integrated redevelopment of slum housing 47.00 Letter to KMC Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM
Monthly Progress Report
Page | 104 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
duration confirmation on scope to be shared by KMC at the earliest. R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited.
Spatial mapping of assets 0.35 (ABD) Letter to KMC. DPR shared, scope shared. KMC to tender the project at the earliest. CSML to follow. As of now no meeting required.
Smart & improved battery-operated tricycles for primary waste collection at West Kochi & Ernakulam in ABD area
1.00 Letter to KMC on further action required
Improvements to sewer collection system for mainland
35.00 Letter to KWA & KMC Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. With limited SCM duration. Confirmation on scope needs to be expedited.
Kacheripady commercial complex 5.00 Letter to KMC. Option 1: Existing building to be upgraded for commercial development Option 2: demolition of existing building and new commercial structure. Option can be assessed based on KMC’s requirement.
Mangalavanam eco-restoration project 1.00 Combined stakeholder meeting & letter to stakeholders
Extend ‘Smart wi-fi bus shelters’ with led bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
0.60 Combined stakeholder meeting & letter to stakeholders
Mattancherry spice market redevelopment
Combined stakeholder meeting & letter to stakeholders
Upgradation of community centre at Mattancherry with indoor sports facilities
1.00 Combined stakeholder meeting & letter to stakeholders regarding further action required on this project.
CSML to provide way forward on projects to be taken up based on funds available.
3.4 WAY FORWARD FOR FEW PROJECTS
Following convergence & SCM projects are proposed to be dropped from Central MIS
maintained by MoHUA.
Table 3-2: Projects proposed to be dropped from CENTRAL MIS
Project name SCP cost INR CR.
Suggestion
24 X 7 WATER SUPPLY - PAN CITY 621 Based on input received from MoHUA during Video conference held for 100 Smart Cities, it is proposed that as implementation duration for 24x7 water supply project will not be in sync with Smart City implementation duration hence
Monthly Progress Report
Page | 105 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
the project may be dropped and formal approval may be taken from all associated stakeholders.
Water supply projects in ABD proposed to be implemented by KWA under 24x7 water supply project
Approx. 90 Cr.
Water supply projects in ABD proposed to be implemented by KWA under 24x7 water supply project
Upgradation of community centre at Mattancherry with indoor sports facilities
1 As per KMC there is no community centre at Mattancherry requiring upgradation. Hence the project may be dropped. KMC to share final confirmation.
3.5 OVERALL STAKEHOLDER ROLES & RESPONSIBILITIES
S. No. Stakeholder Responsibility
1. Kochi Municipal Corporation
(KMC)
► Council approval including review and suggestion on
proposal
► Provision of rehabilitation land
► Conduct public consultations
► Relocation & rehabilitation (R&R) of existing vendors
► Carry out O&M post construction
► Event management
► Appointment of Nodal Officer for the Project
2. Cochin Port Trust ► Approval for the navigational area, as it should not interfere
with inland water routes etc.
► Approval for the projects within the jurisdiction of Cochin Port
Trust
3. District Collector ► Suggestions and approval of related projects
4. Police Department ► Suggestions and approval of related projects
5. Kerala Water Authority ► Integrating the proposed water metering & Sewerage system
with KWA SCADA software
6. Kerala State Electricity Board ► Approval of projects as applicable
► Approval and support in integrating the KSEB control room
(APIs) with IC4 project
► Inspection during implementation of net meters
7. RTO – Transport Department ► Sanctioning of permit and intermediate inspections
8. District Tourism Promotion
Council
► Promotion of tourism projects and open spaces projects
9. State Water Transport
Department
► Permission to go ahead with the pedestrian link between
Ernakulam Jetty and Subhash Park
10. Revenue Department ► Suggestions and approval of related projects within the
jurisdiction of Department
11. KMRL - Water Metro ► To incorporate continuous walkway through proposed boat
jetties
12. Kerala Irrigation Department ► Approval for utilizing canal surface for pumping stations
► Approval for discharging treated water into canal
13. Cochin Heritage Zone
Conservation Society
► Suggestion and approvals as required
14. Fire & Rescue Department ► Sanctioning of permit and intermediate inspections
Monthly Progress Report
Page | 106 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
S. No. Stakeholder Responsibility
15. Public, Residential Welfare
Associations, NGOs, Social
workers
► Public Participation in events organized.
16. Food Safety and Standards
Authority of India (FSSAI)
► Sanctioning of permit and intermediate inspections
17. District Child Welfare Society ► Permission to go ahead with construction activity in Indira
Priyadarshini Children's Park
18. Vendor Associations ► Assistance with relocation & rehabilitation
Monthly Progress Report
Page | 107 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 108 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
4 SMART CITY PROJECTS IN MEDIA COVERAGE
Following table provides an overview of projects and locations in ABD covered in media.
Sl
No
Date News Paper Headlines Link Screenshot
1 07.05.2019 The Hindu Consortium
selected to set up
IC4 under Smart
Mission
https://www.thehindu.com/new
s/cities/Kochi/consortium-
selected-to-set-up-ic4-under-
smart-
mission/article27052521.ece
2 14.05.2019 Indian
Express
Rajiv Awas
Yojana: Their
dream for a house
in limbo
http://www.newindianexpress.c
om/cities/kochi/2019/may/12/raj
iv-awas-yojana-their-dream-for-
a-house-in-limbo-1975975.html
Monthly Progress Report
Page | 109 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl
No
Date News Paper Headlines Link Screenshot
2 22.05.2019 Times of
India
Kochi kids flock to hi-tech anganwadis
https://timesofindia.indiatimes.c
om/city/kochi/kids-flock-to-hi-
tech-
anganwadis/articleshow/69435
937.cms
3 27.05.019 Times of
India
Litterbugs to come under surveillance
https://timesofindia.indiatimes.c
om/city/kochi/litterbugs-to-
come-under-
surveillance/articleshow/69510
141.cms
Monthly Progress Report
Page | 110 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl
No
Date News Paper Headlines Link Screenshot
4 29.05.2019 Times of
India
Corporation to demolish unauthorised building extensions at broadway
https://timesofindia.indiatimes.c
om/city/kochi/corp-to-demolish-
unauthorized-bldg-extensions-
at-
broadway/articleshow/6954980
0.cms
5 30.05.2019 Malayal
Manorama
Broadway Operation
https://localnews.manoramaonli
ne.com/ernakulam/local-
news/2019/05/29/ernakulam-
broadway.html
Monthly Progress Report
Page | 111 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl
No
Date News Paper Headlines Link Screenshot
7 31.05.2019 Times of
India
Shopowners at Broadway continue to violate rules
https://timesofindia.indiatimes.c
om/city/kochi/shopowners-at-
broadway-continue-to-violate-
rules/articleshow/69589006.cm
s
Monthly Progress Report
Page | 112 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
ANNEXURES
ANNEXURE 1: STAKEHOLDER MEMOS
Date 04.05.2019
Office Visited Greater Cochin Development Authority (GCDA), Kochi
Need / Reason
for Site visit
• To discuss the Marine Drive walkway project proposed by CSML and to ensure its effective implementation.
Location • The Greater Cochin Development Authority (GCDA), Ernakulam, Kochi
Stakeholders
met
• Mr. V. Saleem, Chairman, GCDA
• Mr. Rajesh, Senior Town Planner, GCDA (point of contact with GCDA)
• Representatives from various GCDA departments
Important
discussion
points
• CSML presented the Marine Drive Walkway proposal to the GCDA team. Proposals
identified two stretches – High Court Junction to Tata Canal (Stretch 1) and High Court
Junction to KSRTC/ Boat Jetty area (Stretch 2). Stretch 1: involves landscape proposals,
planters/seating around new trees, new coping stone and relaying of old coping stone
as surface finish for existing retaining wall, relaying and levelling of around 50% surface
area using the concrete pavers. Stretch 2: provision of new lighting, relaying of existing
tiles with concrete pavers, streetscaping, landscape and lighting.
• Discussions centred around the extent of intervention, clarifications on execution
timeline, maintenance, management of existing advertising contracts, electrical costs
and revenue issues.
• Mr Rajesh, Senior Town Planner of GCDA, was appointed as the point of contact for
further interactions with GCDA on the project. Co-ordination with various GCDA teams
will be done through Mr Rajesh.
Action Points • CSML to forward an official letter to GCDA (within a week), along with a project brief and
detailed drawings explaining the exact scope of intervention, and clarifications on
maintenance of infrastructure, advertisement areas, potential revenue and issues post
CSML’s maintenance period.
• Further to study and clarifications of the above project brief, GCDA will give their formal
reply.
List of Attendees
from CSML/ PMC
1. Clipson Mathew, Deputy General Manager, Cochin Smart Mission Ltd. 2. Anitha, Environmental Engineer, Cochin Smart Mission Ltd. 3. Abhishek Xavier, Urban Designer, IPE Global, Kochi Smart City PMC 4. Ramanujam S, Associate Architect, IPE Global, Kochi Smart City PMC
Memo No: Ernakulam Market
DIVISION
/LOCATION Ernakulam Market Stall Owner’s Association(EMSOA), Basin Road
DATE AND
TIME 06.05.2018, 12:00 AM
ATTENDEES
1 Shri. APM Mohammed
Hanish IAS
MD, CSML
2 Mr. George EMSOA, President
3 Mr. Shageer Mohd KMCC, General secretary
4 Ms. Raji R GM, CSML
5 Mr. Ajayakumar Team Leader, PMC- CSML
Monthly Progress Report
Page | 113 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
6 Other officials from CSML & PMC, and Market associations
AGENDA Understand the functioning of market and conclude on a suitable proposal for Market
redevelopment
SUMMARY All the suggestions by Market association members shall be incorporated and the final
proposal shall be discussed in the next meeting in same venue on 13th May 2019 @ 3 pm.
Brief of Site visit:
• A Site visit was conducted by the Ernakulam Market stall owners Association (EMSOA) president along with other members of association to explain the current functioning of the market to MD of CSML and other officers of CSML and PMC.
• The visit started from Market road moving around the Ernakulam market, inside the existing market, the market square, auction area, banana stalls and other roadside vendors along basin road.
• Representatives of the Ernakulam Market explained all the activities and movement pattern to MD and other staff in detail at all the locations.
• Upon completing the site visit, MD, CSML took an overview of the locations of all the critical areas and the activities involved and decided to review the CSML proposal in detail in EMSOA office in Basin road.
Brief of Meeting:
• MD, CSML requested all the representatives of EMSOA to confirm and agree to the proposal of market redevelopment and assured that the proposal would only be having ground floor and 2 upper floors along with a basement.
• EMSOA expressed their support for the proposal and also confirmed that some stalls shall be shifted to the 1st floor in the new proposal which would include, Fish, meat, poultry and some other goods.
• EMSOA insisted that the ground floor plinth height be reduced in order to facilitate easy loading of goods by labour workers. CSML explained the use of push/pull carts and trolleys to be used within the market complex to assist the movement of goods.
• EMSOA were supportive with the provisions of internal truck loading bays within the proposed complex but expressed a concern that it would affect and reduce the internal shop area.
• It was suggested by EMSOA president and agreed by MD, CSML that the proposal will try to adjust the maximum number of stalls on the ground floor.
• It was decided that the level drop adjacent to canal and behind the hawkers sitting on basin road shall be raised up to road level and increase the road width in basin road. Also, it was suggested the hawkers would be allowed to sit only on the canal side of basin road with a fence between the road and hawking area to restrict encroachment.
• The stalls seated on the market square shall be incorporated in the square itself and mostly be shifted to upper floor on market square which is acting a bridge between market square and complex.
• The proposed development comprises of the following components a. Market complex (B+G+2), b. Market square with MLCP, compactor, goods lift and truck parking, c. Skywalk from Marine drive to Market, d. Canal rejuvenation, and B e. Vehicular Bridge connecting kuttapayi road to Basin road across canal.
Among these, Skywalk, Canal, and road bridge are to be taken up separately under other modules in smart city.
• The EMSOA president suggested to modify the proposals as per their requirements and discussions but give a detailed plan with all shops and areas mentioned.
• It was decided by MD, CSML and agreed by all market association members that the Sizes of shops allotted to each shop keeper shall be standardized into 3 types of modules, viz., small, medium and large units. The detailed shop sizes shall be formulated by CSML and shared in next meeting.
• The next meeting is scheduled for 13th May 2019 at 3 pm with the Market association members to discuss the final proposal and finalize the design. After which the proposal shall be shown to Mayor, Collector and GCDA chairman to get the approval and consent to use GCDA ground as temporary rehabilitation land during the construction of the complex.
• Once the proposal if confirmed by all the concerned stakeholders, the proposal shall be discussed in an open forum with all stall owners of the market.
Site visit images:
Monthly Progress Report
Page | 114 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
PROJECT & VENDOR: VENUE:
Taj Gateway,
Ernakulam
Integrated Command Control and Communication Centre:
Fluentgrid limited in consortium with BEL
SUBJECT: Kick off Meeting for Integrated Command Control and Communication Centre : Fluentgrid limited
in consortium with BEL
PRESENT
CSML / PMC KMRL KSEB/KWA/ CONTRACTOR
1. Shri APM .Mohammed
Hanish MD,CSML
1. Sagar M,
SIGNAL &
TELECOMMUN
ICATION
CONSULTANT
1 Usha Mol P A,
Assistant Engineer,
KWA
1 Mr Vinod
Srivastava, SVP
Sales, Fluentgrid
2. Mr.Clipson Mathew
,DGM CSML
2 Anoop Mohan
KMRL
2 Mohammed Kasim,
EE, KSEB
2. Mr Vikas Narahari,
VP Account
Management,
Fluentgrid
3. Mrs.Binnya Joseph, IT
Manager CSML
3 Mr. Sunil D, GM
, OP& ST,
KMRL
3 R Rajash, EE, KSEB 3. Mr Ravi T, VP,
Delivery,Fluentgrid
4. Mr.Ajay Kumar
TL,PMC
4 James M , Chief
Engineer, KSEB
4
.
Mr. Sudheer
Nagireddy, Senior
Manager, Sales,
Fluentgrid
5. Surabhi Kureel
PM,PMC
Dennis Rajan,
Asst.EE, KSEB
5 Mr Hari Krishna B.,
Solution Architect,
Fluentgrid
Monthly Progress Report
Page | 115 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
6. Mr.Koreth V Mathew,
IT Consultant PMC
6 Mrs. Sanjya Vyda,
Project Manager,
Fluentgrid
7. Riby Mathew,
Urban Planner, CSML
7 Mr. Praveen K,
GIS manager,
Fluentgrid
8. Anitha Mohan,
Environmental
Engg.Dept, CSML
8 Mr. Siva Rao,
Sr.Engagement
Manager,
Fluentgrid
9. Benty VA, CFO,CSML
10. Rajath R, IT Associate,
CSML
11. Soubhagya
Procurement Expert ,
PMC
12. Arun Savi
Sr.Manager, PMC
13. Karunakaran MN
Energy Expert, PMC
14. K K Paily
Road Engineer,PMC
15. Renuka K
Construction Manager,
PMC
16. Shafeena
Research
Associate,PMC
17. Manish
MIS Expert, PMC
18. Balamurugan
Solution Architect,
PMC
SL
N
O.
POINTS DISCUSSED
ACTI
ON
BY
TARGET
DATE
1. Agenda:
Kick off meeting for IC4 project was organized on 6 May 2019.
Same was attended by the implementing agency, KMRL, KSEB, KWA and PMC.
At the outset of the meeting Fluentgrid team introduced the project and welcomed
everyone present.
2. Key points of internal discussions:
a) Fluentgrid Team welcomes MD, CSML and all the officials from CSML & PMC
and other stakeholders who were attended in the kickoff meeting.
b) Mr. Vikas Narahari, V.P sales & Client Engagement started the presentation by
given an overview about various Smart City Projects done by Fluentgrid and also
introduce the team members who are working for Kochi IC4 Project.
Monthly Progress Report
Page | 116 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
c) Mrs. Sanjya Vyda, P.M explained about the implementation schedule and action
plan for Kochi IC4 Project
d) Mr. Vikas Narahari, give the detailed presentation about the project objectives,
also he informed that they are going to use BSNL as the network partner. He
encourage the cloud based DC & DR for IC4 and informed that they are going to
use Amazon Cloud for cloud scalability.
e) Mr. Ravi explained the overall solution architecture of the project, Integration
architecture. Also explained how smart elements are going to integrate with IC4
application. Also he explained about the network architecture and data security
at all levels like API manager, Basic authentication, IP blacklist & IP whitelist,
Logging, Time restricted access etc.
f) Mr. Vikas explained about the high level project plan with time limits for setting
up the command control room with common cloud based DC & DR also he
explained about the list of deliverables like inception report, Detailed project plan,
orientation workshop and feasibility report for IC4 physical site.
g) The Fluentgrid team will be develop a Mobile app for the citizen services as
additional scope of work
Stakeholders Interaction
3. The KSEB officials interacted with Fluentgrid team as well as PMC team for
integration of their SCADA system. The Fluentgrid team explained that the SCADA,
Smart grid, Bill Payment system and Grievance Management can be integrated by
providing the API of their smart solution.
4. Mrs. Usha Mol, Asst. Engineer , KWA interacted with Fluentgrid team as well as PMC
team regarding water SCADA, The Fluentgrid team explained that the water SCADA
system is possible by implementing IoT devices to the entire water network structure,
and based on the inputs coming from the IoT devices the water consumption analytics
can be calculated.
Memo No: Ernakulam Market
DIVISION
/LOCATION
Ernakulam Market Stall Owner’s Association (EMSOA), Basin Road
DATE AND
TIME
13.05.2019, 03:00 PM
ATTENDEES
1 Shri. APM Mohammed
Hanish IAS
MD, CSML
2 Mr. George EMSOA, President
3 Mr. Shageer Mohd KMCC, General secretary
4 Ms. Raji R GM, CSML
5 Mr. Ajayakumar Team Leader, PMC- CSML
6 Other officials from CSML & PMC, and Market associations
AGENDA Finalize the proposal for Market redevelopment
SUMMARY Market association shall discuss the proposal with all member and giving final decision on
the layout while CSML shall share the revised layout based on the discussion.
Monthly Progress Report
Page | 117 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Brief of Meeting:
• MD, CSML clarified that currently there is funding available for the complete development of the market to its full potential under smart city projects, but funds for this project may not be available for its redevelopment in future under any scheme.
• MD, CSML specified that the upper 2 floors above the 2 floor of existing Ernakulam market would be beneficial to the shopkeepers and there would be a need to provide office spaces, banks, storage, and facilities like e-commerce would be a common factor for the business development of the market.
• MD mentioned that the skywalk would benefit more pedestrian access into the market and enhance the business potential of the market.
• EMSOA expressed their support for the proposal and also confirmed that some stalls shall be shifted to the 1st floor in the new proposal which would include, Fish, meat, poultry and some other goods.
• CSML proposed a layout incorporating all the stalls in market within 2 floors (ground and first) having standard modules of 50, 100, 150, & 200 square feet area.
• Market association insisted on having all the stalls on the ground floor itself, to which CSML clarified that if al the stalls are required on ground floor, then the shop area of shop shall be further reduced and standardized with most of getting 100 square feet area.
• MD, CSML, suggested that all shop owners can be provided space on ground floor with smaller shop area, and any individual who has more area presently, shall be provided the additional area on the 1st floor which can be used for storage of goods or other functions.
• Market association suggested the existing shops on roadside would need to be provided on the roadside itself, and they can be provided with a mezzanine level within the shops.
• MD, CSML added that CSML shall provide 2 options of the layout with either smaller shops on ground with additional on upper floors or standard shop areas divided across 2 floors.
• Regarding rehabilitation land, MD suggested that the proposal shall be discussed with the councillor, Collector, and Mayor and finalize on the transit land.
• MD suggested the market association to discuss the project with GCDA chairman, about the transit land for during the construction period, but Marine drive cannot be guaranteed as an option. Meanwhile CSML shall also present the proposal to GCDA chairman and finalize land options.
• The revised proposal with shop areas shall be provided by CSML to market association.
• President of the market association requested time to discuss the project with all members and conclude on the final proposal, but requested MD, CSML to convene a meeting with all the shopkeepers to get a fruitful result.
Implementation of Intelligent Street Pole at Kochi under PPP on DBOOT model under Smart City Mission,
Kochi
Minutes of Meeting with Mayor and Council Members
DIVISION /LOCATION Mayor ‘s Chamber ,Ernakulum
DATE AND TIME 16-05-2019,11.30 am
Personnel met Mrs. Soumini Jain, Mayor along with council members and Secretary KMC.
AGENDA Implementation of Intelligent Street Pole at Kochi Under PPP on DBOOT model
SUMMARY Mayor shows interest in the concept of Smart Pole project however, mention various
challenges in executing the project discusses action plan
1. Project Background: The project was formulated on Public Private Partnership (PPP) mode and based on in-
principle approval from Worshipful Mayor, EOI was floated. The pre-bid meeting of the EOI with various operators
and was chaired by KMC, Standing Committee Chairman of Works – Mr. Harris. There was interest from five
different concessionaires and is presently in RFP stage. To proceed further with project implementation stage,
support from KMC and its members are a necessity. In this regard, a meeting was conducted under the
chairmanship of Worshipful Mayor and other council members to discuss about the support required from KMC.
2. PMC CSML briefly explained the scope and benefits of the Smart pole project as follows.
3. Scope of the Project.
a. Optimized Telecom Network for 4G and above using Intelligent Street Poles- Inter se distance of 400M.
Monthly Progress Report
Page | 118 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
b. 400 Kms of Optical fibre interconnecting the pole will provide a fail proof super-fast data backbone for the
City.
c. Integrated Wi-Fi network with a minimum speed of 10 Mbps.
d. Smart Billboards for mass communication. Smart billboard will also earn advertisement revenue.
e. PA system for announcements and recorded messages pan city to be controlled from the Command and
control centre.
f. Pollution sensors will indicate the condition of the environment and broadcast environmental parameters.
g. SOS application (panic button) for citizen to communicate with command and control Room.
4. Revenue Benefits from the Project: There are two modes of revenue stream from this project as mentioned
below.
a. A fixed premium of Rs.12000 per pole per year for 9m – 12m poles with 10% escalation (minimum 600
poles).
b. A fixed premium of Rs.50000 per pole per year for 25m-30m poles with 10% escalation every year.
c. A fixed annual gross revenue share of 3%.
5. Infrastructure and other Benefits to the City
a. 10 Core OFC for use for the government ( minimum 400 KM)
b. One 40mm HDPE PLB Telecom Duct for laying OFC( min-400 Km)
c. Billboard – 10 minutes per hour for government messages.
d. PA system covering Pan City centrally operated from command and control Room.
e. SOS button for citizens to contact command control centre
f. 30 minutes of free Wi-Fi per day.
g. Free Wi-Fi for browsing Govt websites.
6. Support Required from KMC :KMC Support for the project is paramount for the success of the Project
a. KMC should not give any further license for any installation of any new Telecom tower.
b. Single Window Clearance.
c. ROW for laying the Optical Fibre Cable (OFC) has to be granted by IT Dept., GoK.
d. Waiver of permit fee and Road Restoration fee.
e. Relaxation of KMBR rule with respect to setback limits for poles.
f. Support for providing Electric Power connection to the Smart pole.
7. Points raised by Mayor and Council Members and suggested solutions are discussed below
Points from Mayor and Council Members Solutions and suggestions discussed
1 Removal of existing towers
Mayor enquired about what will happen to the
existing towers (2G/3G).
It was mentioned that together with the old telecom
poles and new smart poles the beauty of the city
will be affected.
So CSML has to take initiatives to remove the old
poles.
• The smart poles will ensure best telecom
coverage in the city with minimum number of
telecom towers. The smart pole being hi-tech
and uniformly designed will add to the beauty of
the city.
• With advent of 4G and higher technology
existing towers shall become redundant. All
operators will get a readymade, state of the art
pan city telecom infrastructure with smart pole
project.
• There will be no need to rely on primitive
technology. Operators are likely to shift onto
smart pole network voluntarily.
• The existing towers can be decommissioned and
removed in a phased manner by not renewing
the license.
2 Mayor wanted a meeting of the telecom operators
providing 2G/3G to ensure coordination in the
transition to smart pole and removal of old telecom
poles
• The meeting of the telecom operators may be
convened by KMC or CSML
Monthly Progress Report
Page | 119 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
3 Mayor mentioned that they have already gave
permission to Reliance Services to lay poles
across the entire Ernakulam city two months back
and they are likely to start their work inside the city
• It was requested not to allow any other operator
to construct new towers in KMC area as the
same shall be provided by the concessionaire.
• This is paramount for the success of the project.
• No exclusivity is required for OFC.
4 During the implementation of Smart pole project
road excavation to be minimized and damage
whatsoever should be repaired
• Concessionaire will use HDD technology for
laying the Fiber especially for crossing the roads.
• Only in exceptional conditions, surface will be cut
open (permission will be sought)
• After laying the Fiber, Concessionaire shall be
responsible for road restoration of the cuts if any
made in the road.
5 Revenue Share : Mayor was not clear about the
revenue share arrangement with KMC
• CSML shall inform the details about the revenue
share in consultation with MD CSML.
6 Wavier of road restoration charges: Mayor stated
that the concessionaire will have to pay the road
restoration charges even when the work is done by
Concessionaire.
It may be difficult to get the exemption through
council approval from KMC as it is one of the major
revenue source.
• CSML shall try to get the exemption from
Government of Kerala
7 Advertisement:
As it is PAN city, and only the concessionaire will
be benefited from the advertisements. Also, the
revenue from advertisement to be with KMC
• No exclusivity for advertisement is provided. So,
other agencies can also place advertisement
boards in the KMC area.
• The revenue from the advertisement board will
with concessionaire and shall share with KMC as
fixed revenue share
Attendees from Kochi Municipal Corporation
S. No.
Name Designation and Organization
1 Smt. Soumini Jain Worshipful Mayor, KMC
2 Sri. P M Harris Standing Committee Chairperson, Works
3 Smt. Shiny Mathew Standing Committee Chairperson, Town Planning
4 Sri. K V P Krishnakumar Standing Committee Chairperson, Tax Appeal
5 Sri. C B Sabu Standing Committee Chairperson, Welfare
6 Sri. David Parambithara Councillor, Ward 61
7 Sri. R. Rahesh Kumar Additional Secretary, KMC
8 Sri. Titus Executive Engineer, KMC
Attendees from CSML and PMC
S. No.
Name Designation and Organization
1 Mrs. Binnya Joseph IT Manager, CSML
2 Mr. Rajath Assistant Manager, CSML
3 Mr. Korath Mathew E-Governance and IT Expert, IPE Global, Kochi Smart City PMC
4 Mr. Arun Savi Senior Manager, IPE Global, Kochi Smart City PMC
5 Mrs. Renuka Construction Manager, IPE Global, Kochi Smart City PMC
6 Mr. Balamurugan Solution Expert, IPE Global, Kochi Smart City PMC
7 Mr. Manish MIS Expert, IPE Global, Kochi Smart City PMC
8 Mrs. Shefeena KS Research Associate, IPE Global, Kochi Smart City PMC
Monthly Progress Report
Page | 120 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
REF NO.:
PROJECT & VENDOR: VENUE: KRML Conference room 8th Floor, Revenue Tower
Intelligent Traffic Management Systems (ITMS): Kerala State Electronics Development Corporation Limited (KELTRON)
SUBJECT: Kick off Meeting for Intelligent Traffic Management Systems (ITMS): Kerala State Electronics Development Corporation Limited (KELTRON)
PRESENT
CSML / PMC KMRL KSEB/GIDA/Police CONTRACTOR
19. Shri APM .Mohammed Hanish MD,CSML
4. Mr.Abdul Kalam DGM KMRL
1 KR Rajeev,Town Planner ,GIDA
1 Binsun N.T Asst Manager,Keltron
20. Mr.Clipson Mathew ,DGM CSML
2 Anoop Mohan KMRL
2 Nazeer M.A ACP,Traffic West
5. Gopakumar S.P Head,Keltron Communication Division
21. Mrs.Binnya Joseph, IT Manager CSML
3 Gokulnath .k ,KMRL
3 Vinod C.S ACP,Traffic East
6. Vijeesh .V Sr.Engineer Keltron,Traffic
22. Mr.Ajay Kumar TL,PMC
4 Sivan N.K MVI-RTO-EKM
4. Srijith C.S Sr.Engineer Keltron,Traffic
23. Surabhi Kureel PM,PMC
Bijumon SP MVI-RTO-EKM
5 Lal.P Sr.Engineer Keltron,Traffic
24. Mr.Koreth V Mathew, IT Consultant PMC
6 Hameed A.A Sr.Engineer Keltron,Traffic
25. M.Imtiyaz Ahamed Transport Planner,PMC
SL NO.
POINTS DISCUSSED ACTION
BY TARGET
DATE
5. Agenda: Kick off meeting for ITMS project was organized on 18 May 2019. Same was attended by the implementing agency, KMRL, Traffic Police, GIDA, PMC and the Contractor. At the outset of the meeting CSML introduced the project and welcomed everyone present.
6. Key points of internal discussions: KELTRON
Monthly Progress Report
Page | 121 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
➢ KELTRON during the meeting submitted PBG, contract document, solution document. KELTRON added that the solution document is to be revised based on site visits to be conducted. CSML mentioned that a revised solution document is to be submitted by KELTRON with 5 modified locations, locations which require dismantling of street furniture and detail of the project team, Staff schedule and detailed implementation schedule.
➢ Proposed joint site visit along with members from PWD, Police, KMC, GIDA, GCDA etc.
➢ Based on the site visit, there are lot of street furniture’s to be dismantled and removed – CSML replied that, stakeholders will be identified, and request will be made for the same. CSML requested to have the stakeholders and list required to be added in the revised solution document
➢ Request for space for storing of equipment – CSML responded that the SPV does not have any asset hence the material to be stored in space available with KELTRON.
➢ CSML also pointed out that till commissioning supply material is to be taken care of by the vendor. KELTRON agreed to the same
➢ Keltron stated that, Aroor manufacturing plant can be utilised for storing the equipment. KELTRON to share facility detail
➢ To manage delay, the implementation schedule is modified as 6+1 months ➢ For connectivity, MPLS VPN through OFC and as per proposal, the network
partner is BSNL ➢ The structural details of poles are provided with solution document.
7. CSML requested KELTRON to share recurring expense for ITMS project post completion of O&M period for submission to Traffic Police
KELTRON 30 May 2019
8. CSML requested the vendor to submit the following at the earliest to enable smooth implementation initiation of the project. ➢ Organization set up & CVs (Along with detailed contact information) ➢ Communication Matrix ➢ Date for initiating the project ➢ Implementation schedule ➢ Meeting schedule to be finalized and adhered upon. Meeting must be
conducted Fortnightly/Monthly basis. ➢ Another important aspect stressed upon was Health & Safety during
implementation for all aspects.
9. Material testing will be carried out by KELTRON as a routine exercise for all the components and the test certificates for the same will be submitted by KELTRON to PMC.
10. KELTRON requested for date for joint site visit. CSML suggest KELTRON to prepare detailed agenda for site visits including grouping of sites stakeholder wise Later during joint stakeholder discussion, 27th & 28th of May 2019 were proposed by stakeholders for joint site visit.
11. KELTRON was informed regarding other parallel project ongoing under Smart City and need for integration if any
- Sewerage in ward 1,2,3,4 &5 in West Kochi - Intelligent Traffic Management System Pan city (Kochi Municipal
Corporation area) - Smart poles pan city - Smart LED lighting
Coordination and planning for these projects is key to successful delivery of all projects.
12. Action points for KELTRON is provided in table 1
13. Key contacts for communication with CSML & PMC hared in annexure 1
14. Communication channel for the project shared in annexure 2 Contractor to share updated overall communication flow.
15. Letter to be submitted stating reasons for delay in submission of PBG with reference letters from Bank
From 1200 hours joint stakeholder meeting started
16. Traffic police confirmed that location now proposed are confirmed.
17. CSML requested traffic police to handover Control Centre location KELTRON to share detailed plan by when the same will be required
18. Meeting ended with Thanks to the Chair and all present.
Monthly Progress Report
Page | 122 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Memo No: Department Name: KMC
VENUE KMC
DATE AND TIME 20.05.2019, 12:00 AM
NAME OF PERSON MET Ms. Sabitha, Section Clerk, Tourism Department (as directed by Ms. Kamalamma, Tourism Deputy Director)
AGENDA Regarding initiatives of Tourism Department at Fort Kochi Beach Area
Brief: The projects around Fort Kochi area, currently under timeline of Tourism department are:
1. Museum of Cultural Mosaic, Mattancherry 2. Development of Kochi Tourist Destination – Regarding the construction of sea wall at Fort Kochi
South beach where walkway and beachside got impacted during sea attack. The project worth 1.78 Cr is submitted to working group committee through Irrigation Department
3. Protection of Chinese Fishing Nets 4. Nehru park and Food Court, Fort Kochi 5. Information Centre, Fort Kochi etc.
Redevelopment of Sea Wall Project Project Name: Reformation of sunken seawall for a length of 65M from the boundary of INS Dhronacharya towards Fort Kochi including the restoration of side wall of walkway with Geo textile tubes between CP stone 1066 and 1068 (200m) at Fort Kochi Location Map:
Detailed Drawing:
List of Participants:
Monthly Progress Report
Page | 123 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
1. Anu. K. Soman
Memo No:
DIVISION /LOCATION Greater Cochin Development Authority Office
DATE AND TIME 21-05-2019, 03:00 PM
Personnel met Jeby Jomy (Superintending Engineer) Rajesh T.N. (Town Planner) GCDA Team
AGENDA • To discuss on the submitted Marine Drive Walkway- Project Brief
SUMMARY The project details were briefed and project will be taken up for approval from GCDA Executive Council
Brief of meeting: Major Discussion Points:
• Project components and Maintenance measures were explained by the PMC.
• Electric charges for 104 street lights and 20 bollards were discussed, which is approximately Rupees 1.5 lakh/ annum.
• GCDA shall confirm whether railings are required along the walkway. However, it was confirmed that existing railings were installed to provide limited access to boating facility and not for safety of the visitors.
• GCDA confirmed that provision or renovation of existing or new kiosks would require provision of new license numbers from KMC
• CSML/PMC shall confirm whether provision of new license numbers is possible from KMC.
• GCDA further confirmed that the walkway shall not be covered.
• GCDA confirmed that Ar. Kuldeep Singh who has prepared the Master Plan for Marine Drive, in principle opposed the concept of MLCP in the area as it would not be environment friendly.
• Since, the proposal mainly includes streetscaping measures. GCDA shall further confirm whether an actual confirmation is required from Ar. Kuldeep Singh for the proposed development.
• CSML/PMC mentioned the tendering dates for the Marine Drive Walkway project.
• GCDA informed to prepare a construction schedule in consultation with the bidder so that the convenience of visitors and vendors can be maintained.
• GCDA shall confirm with the existing advertisement vendor about the advertisement arrangements and revert back.
Action Points:
• GCDA and CSML/PMC shall confirm the respective required details
• GCDA shall further take up the project for approval from the Executive Council.
List of Attendees from Cochin Smart Mission Limited (CSML) Team:
S. No. Name Designation and Organization
1 Clipson Mathew DGM, CSML
2 Abhishek Xavier Urban Designer, IPE Global, CSML PMC
3 Anitha Mohandas Environmental Engineer, CSML
4 Davesh Sharma Analyst, IPE Global, CSML PMC
Memo No:
DIVISION /LOCATION Greater Cochin Development Authority Office
DATE AND TIME 21-05-2019, 05:00 PM
Personnel met GCDA Chairman
AGENDA • To discuss on the submitted Marine Drive Walkway- Project Brief
SUMMARY Marine drive walkway progress was updated and further confirmation shall be provided by
GCDA.
Brief of meeting: Major Discussion Points:
• Progress on the Marine Drive walkway was discussed.
• The Chairman expressed interest to organize the existing haphazard boat mooring facility along the walkway as another project.
• The PMC presented the Marina proposal in brief and the Chairman expressed interest to take up the project.
Monthly Progress Report
Page | 124 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
• The Ernakulam market project and issues to be faced during rehabilitation were also discussed. Action Points:
• GCDA shall provide confirmation and further actions for the above mentioned project.
List of Attendees from Cochin Smart Mission Limited (CSML) Team:
S. No. Name Designation and Organization
1 Jeby Jomy Superintending Engineer, GCDA
2 Clipson Mathew DGM, CSML
3 Abhishek Xavier Urban Designer, IPE Global, CSML PMC
4 Anitha Mohandas Environmental Engineer, CSML
5 Davesh Sharma Analyst, IPE Global, CSML PMC
Monthly Progress Report
Page | 125 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 126 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 127 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Memo No:
DIVISION /LOCATION
Revenue divisional office, Fort Kochi
Date & Time 28.05.2019, 03:00 pm
Personnel met Mr. Snehil IAS, Sub-collector, Fort Kochi
Agenda Approval of the Proposed Freedom struggle Museum and other projects in Fort Kochi
Brief of meeting: Freedom Struggle Museum:
• The sub-collector was keen to get the projects implemented in fort Kochi and inquired about the status of tendered projects of Vasco square development.
• Sub-collector (SC) approved the proposal for Freedom struggle museum, and but informed that he had a proposal to build a single storey senior citizen counseling room building as an extension of RDO in the additional vacant land of 8 cents which CSML is proposing to develop along with the Museum project.
• PMC clarified that constructing a building in that land would require approval from Archaeological survey of India as it is within 300 meters from ASI protected monument of St. Francis Church. Hence, CSML may not be in a position to propose construction of that building.
• But CSML agreed to revise the existing proposal such that a sufficient space allotted for a small building to be constructed in future by RDO.
• SC confirmed that he shall issue a letter from revenue department confirming the proposal and usage of additional land for the Museum project.
Other projects:
• With regards to parks and open spaces project, Sub collector reviewed the proposal and mentioned that he has some suggestions of outdoor gym furniture which can be added in the proposal.
• Regarding Beach upgradation proposal, PMC requested SC to coordinate or inform if the Irrigation department would be interested to take up the construction of sea wall all along the fort Kochi water edge under smart city funding.
• SC agreed to coordinate with irrigation department and inform about the possibility of construction of sea wall.
• PMC clarified, that CSML can proceed with the beach upgradation project only if the seawall construction taken by another agency.
List of Attendees from Kochi Smart City Team
S. No. Name Designation and Organization
1 Anand Nair Associate Architect, IPE Global, Kochi smart city PMC
2 Jishnu Pillai Asst. Construction Manager, IPE Global, Kochi smart city PMC
PROJECT & VENDOR: VENUE: KRML Conference room 8th Floor, Revenue Tower
Rejuvenation of Canals In Kochi
SUBJECT: Stakeholder consultation on the Rejuvenation of Canals in Kochi – ABD Area
PRESENT
CSML / PMC KMRL IRRIGATION DEPT/ KWA/KMC/AMRUT/
JNNURM
NIUA
26. Riby R Mathew 7. Mr.Abdul Kalam AGM KMRL
1 Radhakrishnan.K; Ex.E, Irrigation Division, Ekm
1. Priyanka Mehra Research Associate
27. Mr.Ajay Kumar TL,PMC
2 Ajith.A.Nair, AGM, KMRL
2 Santhosh A.K Urban Planner, AMRUT
2. Dr.Debjani Ghosh Associate Professor
28. Surabhi Kureel PM,PMC
3 Abdullakutty.K.K Chief Project Consultant Water Transport
3 Joachan Joseph Executive Engineer, JNNURM
3. Asif Raza Research Associate
29. Dr.N.Balasubramanian, Infrastructure Specialist, PMC
4 Girija; Sr. Consultant - Civil
4 Vibin Kumar, Overseer, KWA (Sewerage)
Monthly Progress Report
Page | 128 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
30. Renuka.K, Construction Manager, PMC
5 Shibu A.J, AE, KWA Sewerage
31. Pradyumna Mackchand, Canal Expert, PMC
32. Anitha Mohandas; Environmental Engineer
SL NO. POINTS DISCUSSED ACTION
BY
TARGET
DATE
1. Agenda:
Stakeholder consultation to discuss Canal Rejuvenation finding based on
feasibility report prepared by PMC. At the outset of the meeting CSML
introduced the project and welcomed everyone present.
2. Key points of internal discussions:
➢ Current situation of the canals under ABD area was discussed and the presentation of the feasibility report submitted was explained by Pradyumna Machhkhand, Canal Expert, PMC. Current situation, navigability and other constraints like social and environmental issues regarding the rejuvenation of the canal were elaborated.
➢ Regarding the Ernakulam Market Redevelopment Abhishek Xavier- PMC, explained the plan for constructing the Multi storied building for the Market shops. Navigability of the market canal was also discussed
➢ Regarding the Kalvathy Rameswarm Canals – the bridges formed over the canal was a topic of discussion. It was pointed out that many constructions including houses and shops were found to be constructed at the edges of the canal side wall especially the Mullasserry canal and the Kalvathy canal.
➢ Alternative methods of the rejuvenation and controlling of the storm water, sewerage and other wastes flowing to the canals was also a topic of discussion. Suggested alternative methods were (1) New trunk Sewer System with a proposal of STP. The site of STP may be proposed at the GCA parting area near the mouth of the canal. (2) New Trunk Sewer System to be integrated with the existing sewer network.
➢ Had carried out the hydrological study for all the three canals within the ABD catchment area and recommended for raising the side wall in the Feasibility Report. Also suggested the sheet piles construction at the boundaries of the existing walls of the canals for avoiding the damages of the side walls. The construction cost (excluding the urban designs, sewerage and other miscellaneous cost) for this construction is also mentioned in the feasibility report.
➢ Concluded the presentation with a note of improvement and additions to the feasibility report.
PMC
3. CSML requested the stakeholders for the suggestions and queries if any on
the report presentation.
4. Mr. Abdul Kalam, KMRL and Mr. Ajith, Mr.Abdullakutty K.K Water Metro
suggested the below points
1. Mention the width of the canals in the Feasibility report. 2. A holistic development with a combined system (STP and New trunk
system has to be combined and considered) 3. Water metro, suggested for pile and slab construction for the walls for
the canals. CSML & KMRL suggested to evaluate value for money engineering solutions.
4. How the construction of walls along the canal will be done should be detailed in the DPR.
5. Also informed Rameswaram canal renovation is put in consideration of the tourism project. And advised CSML to take forward with the Kalvathy and Mullassery Canal.
6. Social issues to be taken care with consulting the approving agencies 7. The catchment area must include the sewerage network area
considering with the storm water area and whole area of the canals for
KMRL
and Water
Metro
Monthly Progress Report
Page | 129 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
the study purpose and proposal has to be submitted for the rejuvenation of the canals.
8. CSML mentioned that external agencies such as GIZ are keen to support CSML in funding for surveys. Detailed survey of canal including for that outside ABD covering entire canal stretch can be taken up by GIZ
9. Navigation of small tourist boats should also be proposed after the rejuvenation of the canals
10. The sewerage flowing to the canals has to be prevented and the alternatives has to be considered and discussed.
11. The Market Canal is already under the water metro project. For this 36 houses needed to be rehabilitated. It has to be confirmed whether design and implementation of Market Canal is to be taken up under Smart City or Water Metro.
12. Enhance the existing sewer system not required as the 50% of the pumping is only in use.
5. Suggestion from KMC AMRUT team
1. Catchment area to be taken into consideration including the drainage systems attached to the canal. Sewerage network area should also be considered along with the storm water area.
2. Reconstruction and protection of walls and residential areas near the canal has to be considered
3. How the sewerage coming to the canal can be stopped to be planned
6. KWA Sewerage: Asked what action or support has to be taken from their
side. If so, it may be discussed with the ExE. Hours of pumping at present
is 16 Hours not continuous.
KWA enquired whether planting or gardening is planned on the sides of the
canal for the recycling of canal water.
7. Irrigation Department
Present width has to be increased as the present width is not the actual
width for navigation.
Encroached areas has to be taken over.
What measures are taken to safeguard the canal and what operational
mechanism is referred after the redevelopment of the project?
CSML informed that land acquisition and associated tasks such as
encroachment removal is not under purview of Smart City. As per Smart city
guidelines same is to be taken up by ULBs
Name of organisation met: Engineering wing VENUE: Banquet Hall, 2nd floor, Govt. Guest House
AGENDA : Introduction and discussion of SCM and project status
ORGANISATION
1. Engineering wing
2. CSML
3. GIZ
4. PMC for Smart City
S. NO. POINTS DISCUSSED Clarification sought /
Suggestion from Eng. wing Clarification/Request by CSML/PMC
1. The agenda of the meeting was to appraise the engineering staff of the KMC about projects undertaken by
CSML and implement the projects with guidance & active assistance from Engineering wing.
Projects for discussion:
The projects from various sectors:
1. Urban Mobility and Road Projects
2. Open Spaces and Tourism Projects
3. Canal Projects
Monthly Progress Report
Page | 130 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
4. Market projects
5. Housing projects
6. LED streetlight and electrical infrastructure, Solar projects
7. ICT – IC4, ITMS, e-health
8. Telecom - Smart Poles
9. Other projects
2. Urban Mobility and Road
Projects:
Projects discussed:
a) Smart and other
roads
b) Public bike sharing
system
c) Parking
management
1. Carriage way of Hospital
road seems to be reduced.
2. No two-wheeler parking
provision.
3. ROW seems to be
reduced
4. Subway as alternative
option for pedestrian
crossing.
1. Primary concept is to develop roads for
all types of road users and not just Cars.
Hence pedestrian friendly streets to be
developed.
2. Need to regularise & restrict vehicular
traffic rather than excessive expansion of
carriage way. Authorities may carry
separate parking study to understand why
this unauthorised parking on footpath is
taking place. Footpath is meant for
pedestrians.
3. Effective re-organisation of under-
utilised existing streets (most of the roads
with wider widths is taken up by
haphazard on-street parking). The space
is being reorganised considering various
criteria; one being Non-motorised user’s
needs.
4. Subway option not considered due to
factors like:
- perception an unsafe environment
- High ground water table level
- Not friendly to pedestrian and vulnerable
road user.
3. GIZ Presentation on Street
design:
The key objective is to design
safer and equitable streets for
all.
Re-organization of under-
utilized streets and promotion
of NMT & Public Transport.
Proposed principles for
improved streets:
a) Safer speed
b) Re-configure space
c) Accommodate
diverse users
d) Context based
solutions
e) Ensure universal
accessibility
f) Small solutions with
larger impacts
Proposed principles for
improved junctions:
g) Design compact
intersections
h) Simplify geometry
Monthly Progress Report
Page | 131 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
i) Analyze networks
Use of Street Calming
Elements and Tactical
Urbanism ideas to build safer
streets. Physical and
physiological calming
measures to control vehicle
speed.
4. Open Spaces and Tourism:
Projects discussed:
a) Improveme
nts to
Marine
Drive
walkway
b) Vasco Square at Fort
Kochi
c) Open Air Theatre at Fort
Kochi
d) Parks improvement
e) Fort Kochi Beach
upgradation
f) Museums
g) Public walkway at
Mattancherry
5. Canal Projects:
Restoration of four canals:
a) Market canal
b) Mullassery canal
c) Calvathy –
Rameshwaram canal
Restoration involves:
a) Cleaning and
maintaining water quality
b) Side wall development
c) Urban design aspects
along the canal stretch
1. Officials informed
that in West Kochi, Calvathy-
Rameshwaram Canal work
on desilting & side wall
protection was taken up as
part of AMRUT
2. Restoration of
Calvathy-Rameshwaram &
Mullassery canal within ABD
alone will not suffice.
3. Integrate the work to
be undertaken with AMRUT
funds for Calvathy-
Rameshwaram canal
1. CSML requested for detail on Canal
work carried out under AMRUT, in
order to avoid any overlapping of
work.
2. CSML informed that taking up of entire
stretch of Canal is under consideration
and will be further discussed with
other stakeholders
3. Public awareness required for proper
restoration of canals and requested for
assistance of Engineering wing
6. Market projects:
The projects mentioned were:
a) Ernakulam market
development
b) Broadway street
upgradation
CSML requested Engineering wing to
assist KMC to initiate the following at the
earliest:
1. Formation of joint committee
2. Complete list of registered vendors to
be issued by KMC.
3. Land (1.5 Acre) to rehabilitate vendors
during construction phase to be identified
and finalisation of land for rehabilitation.
4. Legal agreement on rehabilitation of
vendors to be issued by KMC to vendors.
5. Detail of hawkers/ street vendors
6. Agreement with site owner
7. Site clearance
8. Agreement with PAPs by KMC
9. Relocation of existing vendors
Monthly Progress Report
Page | 132 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
10. Way forward on Un-registered
vendors
All the above activities to be completed by
KMC latest by September 2019 to enable
tendering by October 2019.
7. Housing projects:
Projects discussed:
a) Bridges construction
b) Thuruthy colony – 1st
Tower
c) Integrated development
of Slum housing
d) Beneficiary Led housing
schemes
1. Any Vacant space for new
construction/ relocation or
slums that can be
redeveloped to be
considered and discussed
further for redevelopment of
slums component.
2. CSML can initiate
proposal for construction of
2nd tower for Thuruthy and
independent slum
redevelopment of specific
slums, once KMC provides
consent and necessary
details to proceed with the
work.
1. Vacant space besides Tower-1 of RAY scheme along with Mehboob Park, if acquired, CSML can propose and implement the construction of Tower-2 to relocate households. 2. Prioritisation / identification of the most vulnerable slums/ cluster to be specified by KMC so that CSML can prepare proposal accordingly. Engineering wing to assist KMC in finalising the same
3. CSML received request for development of slums from ward 5 which is a feasible proposal, but confirmed list of slums from all wards are requested from KMC to initiate the process formally
4. Analysing the credibility of land ownership document is a challenge.
5. Data base on slum housing project to be shared by concerned authority or new data base has to be developed with KMC. Engineering wing to assist..
6. Once the scope of all housing projects to be taken up under Smart City for implementation is finalised by KMC all project proposals & designs will be as per KMBR. Fire safety will be taken care off.
8. Other projects:
a. Healthcare:
Projects discussed :
a) Fort Kochi Hospital
b) Mattancherry
Hospital
b. Education:
Projects discussed :
a) Calvathy School
1. L.P Block of
Calvathy School requires
upgradation.
1. Assistance required for the fast
track demolition work of digital library and
toilet block of Calvathy School.
2. Calvathy School, L.P Block
upgradation can be done in development
phase – 2 considering temporary
relocation of current classrooms to the
new High school block built in phase -1.
CSML requested Engineering wing to
assist KMC to start the process of
demolition of existing building proposed to
be renovated
9. Sewerage & Solid waste &
sanitation:
Projects discussed:
a) Vacuum based
sewerage system for
West Kochi
b) Household waste bin
c) Public toilets
1. Engineering wing to assist KMC to
issue the beneficiary list and carry out
Household bin distribution
2. Engineering wing to assist KMC to
provide bin storage location
Monthly Progress Report
Page | 133 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
10. ITMS:
Traffic enforcement and
management through VA
signals, Pelican Signals,
variable message boards, red
light violation.
Traffic management centre
above North police station
1. Permission for cutting roads under
KMC authority to be granted. Engineering
wing to assist KMC in sharing the same.
11. LED streetlight and
electrical infrastructure:
Projects discussed:
a) Smart LED street
light
b) Solar project
1. Implementation of
LED lights in – Pan City area
on PPP mode ( Energy
Saving Model) - Engineering
wing opined that while
replacing existing light
fixtures with LED light
fixtures and controllers, Poles
may also be replaced and
maintain lux level
requirements of each roads.
2. LED light and pole
design to be considered as a
whole for efficient design.
3. Leak in Fort Kochi
Govt. building found after
solar panel installation and
needs to be rectified.
1. In PPP mode, usually, LED fixtures
along with controllers and minor wiring is
done and O&M of LED fixtures for a fixed
tenure say 7 years be done in Energy
saving mode and all the cost are met from
the energy saving and duration is
dependent on the cost benefit analysis.
2. Cost of replacing poles and brackets
etc will be additional cost in the PPP
(energy saving mode). And the number of
poles required will be more than the
present quantity as the lighting design
may reduce the spacing between poles.
3. Currently, CSML is doing the LED
project in Capex mode (in ABD) and in the
project, the new LED fixtures, control
panels and poles are provided in smart
roads. In access roads, LED lights along
with GI poles suitable to carry Arial Bunch
cables are provided. The pole spacing and
size of the poles are based on lighting
design.
4. Technical assistance regarding new
proposal with new pole design can be
provided for pan city area for LED lighting
along roads
5. In the electrical infra project,
undergrounding of 11 KV and 415 volt
lines are done in ABD area along with
installation of Compact Substations,
Feeder pillars and smart Meters.
6. CSML has installed about 1000 KWp
grid connected solar roof top system in
government and Corporation buildings
(total 27 nos) in Kochi Municipal area.
Water leak reported by KMC in Fort Kochi
government hospital building will be
inspected and accordingly. BHEL will be
instructed to rectify the leak due to solar
panel installation at the earliest.
Monthly Progress Report
Page | 134 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
12. Other important projects
discussed:
1. Integrated command
control and
communication centre
2. Smart poles
3. Cancer block for General
Hospital
1. KMC enquired regarding
location of Smart poles
1. CSML explained that two type of poles
shall be used based on their height. Smart
poles shall be placed along the roads but
taller poles shall be placed elsewhere
depending upon the availability of space.
2. Locations will be finalised jointly with
CSML & KMC and Engineering wing.
3. CSML requested Engineering wing to
assist KMC to share information on
existing number of mobile towers within
KMC limit.
4. City gas project status to be updated
in order to avoid cutting after road
development.
13. The Team Leader clarified the issues raised by the members of Engineering wing and others. The General
manager concluded the meeting thanking the members attending the meeting and with the decision to
further conduct, sector wise detailed discussion with concerned officials.
Monthly Progress Report
Page | 135 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 136 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 137 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 138 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Monthly Progress Report
Page | 139 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
ANNEXURE 3: LIST OF PROJECTS UNDER IMPLEMENTATION BY SPV
S No
Category
Module No.
Module Source of Fund
Project Name Project / SCP cost
Status
1. ABD 10 Urban Mobility SCM Walkway from Ekm Jetty to Metro station
4.70 Work order issued/Project Under Implementation
2. ABD 6 Energy
Efficiency SCM Solar panels in Govt. buildings 5.70
Work order issued/Project Under Implementation
3. ABD 10 Urban Mobility PPP Public Bicycle Sharing (PBS) 10.00 Work order issued/Project Under Implementation
4. ABD 4 Main Roads SCM Intelligent Traffic Management Systems (ITMS)
26.90 Work order issued/Project Under Implementation
5. ABD 13 Health SCM E-health solution for General Hospital
3.71 Work order issued/Project Under Implementation
6. ABD 13 Health SCM Cancer Extension Block, General Hospital
26.00 Work order issued/Project Under Implementation
7. ABD 18 Others SCM Integrated Command, Control and Communication Centre (IC4)
64.50 Work order issued/Project Under Implementation
8. ABD 3 NMT Roads SCM Development of Other Roads in Ernakulam
43.60 Work order issued/Project Under Implementation
9. ABD 4 Main Roads SCM Development of Smart Roads in Ernakulam
61.53 Work order issued/Project Under Implementation
10. ABD 4 Main Roads SCM Development of Smart Roads in West Kochi
30.31 Work order issued/Project Under Implementation
11. ABD 7 Solid Waste
and Sanitation SCM
Household and Street Bins for Segregation of Organic and Inorganic wastes
0.67 Work order issued/Project Under Implementation
12. ABD 6 Energy
Efficiency SCM
Implementation of Smart LED lighting
32.09 Tender Issued
13. ABD 7 Solid Waste
and Sanitation SCM
Smart & Improved Secondary Storage & Transportation of Solid Waste using Portable Compactor Technology
4.40 To be re-tendered
14. ABD 7 Solid Waste
and Sanitation SCM
Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area
3.20 To be re-tendered
15. ABD 3 NMT Roads SCM Development of Other Roads in West Kochi
60.20 To be re-tendered
16. ABD 5 Energy Supply SCM Development of Electrical Infrastructure in ABD
63.40 Tender Issued
17. ABD 17 Identity and
Culture SCM
Upgradation of Dutch Palace Entry Area
1.10 Tender Issued
18. ABD 17 Identity and
Culture SCM
Beach Front Upgradation at Vasco Square in Fort Kochi - Part A
1.71 Tender Issued
19. ABD 17 Identity and
Culture SCM
Open Air Theatre (OAT) at Fort Kochi
1.10 Tender Issued
20. ABD 13 Health SCM New Block at Fort Kochi Taluk Hospital
4.65 Tender Issued
21. ABD 13 Health SCM New Block of Mattancherry Women & Children Hospital
4.57 Tender Issued
Monthly Progress Report
Page | 140 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
22. ABD 6 Energy
Efficiency PPP Intelligent Street Pole 301.58 Tender Issued
23. ABD 2 UGSS SCM
Construction of Vacuum Sewer Network with House Connections and Sewer Treatment Plant
154.50 Tender Issued
24. ABD 7 Solid Waste
and Sanitation SCM Public Toilets in ABD area 1.80 Tender Issued
25. ABD 8 Park and Open
Space SCM
Improvements to Marine Drive walkway - Phase I
7.10 Tender Issued
26. ABD 14 Education SCM Higher Secondary Block, Central Calvathy GHSS, Fort Kochi
4.67 Tender Issued
27. ABD 3 NMT Roads SCM Development of Multi Level Car Parking at Kacheripady
6.15 To be re-tendered
28. ABD 4 Main Roads SCM Road Signages for ABD area 2.40 DPR Prepared
29. ABD 17 Identity and
Culture PPP
Development of Ethnic Food Hub
1.00 DPR Prepared
30. ABD 15 Safety and
Security SCM
Safety & security - Intelligent Crime Surveillance System
14.56 DPR Prepared
31. ABD 8 Park and Open
Space SCM Development of open spaces 2.50 DPR Prepared
32. ABD 17 Identity and
Culture SCM
Museum of Freedom Struggle 1.20 DPR Prepared
33. ABD 9 Canal
Restoration SCM
Restoration of Mullassery canal - including linking of standardized area drains
1.00 DPR Under Preparation
34. ABD 9 Canal
Restoration SCM
Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts
5.00 DPR Under Preparation
35. ABD 9 Canal
Restoration SCM
Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features
20.00 DPR Under Preparation
36. ABD 9 Canal
Restoration SCM
Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road
15.00 DPR Under Preparation
37. ABD 12 Economy and Employment
SCM Broadway Street Upgradation 10.00 DPR Under Preparation
38. ABD 12 Economy and Employment
SCM Ernakulam Market Redevelopment
100.00 DPR Under Preparation
39. ABD 12 Economy and Employment
SCM Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"
5.60 DPR Under Preparation
40. ABD 3 NMT Roads SCM Smart Parking Solutions in ABD area
1.90 DPR Under Preparation
41. ABD 4 Main Roads SCM FOBs - West Kochi (3 Nos) 2.15 DPR Under Preparation
42. ABD 17 Identity and
Culture SCM
Cultural Corridor - PT Usha Road
0.50 DPR Under Preparation
43. ABD 17 Identity and
Culture SCM
Fort Kochi Beach Front improvements - Part B Walkway & Beach
5.00 DPR Under Preparation
44. ABD 11 Housing SCM
Construction & upgradation Thuruthy, Kalvathy & Konchery colony - Construction of Bridges
5.15 DPR Under Preparation
45. ABD 14 Education SCM Anganwadis 3.00 DPR Under Preparation
Monthly Progress Report
Page | 141 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
46. ABD 11 Housing SCM Construction of Second tower at Thuruthy
35.00 Project scope to be confirmed by stakeholders
47. ABD 12 Housing SCM Construction of First tower at Thuruthy
21.00 Fund Transfer by SPV
48. ABD 11 Housing SCM Integrated redevelopment of Slum housing
46.85 Project scope to be confirmed by stakeholders
49. ABD 11 Housing SCM Beneficiary led housing 13.00 Fund Transfer by SPV
50. ABD 18 Others SCM Spatial Mapping of assets 0.00 DPR Prepared
51. ABD 7 Solid Waste
and Sanitation SCM
Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area
1.00 DPR Prepared
52. ABD 1 Water Supply SCM Smart Water solutions - Smart Metering and smart valves for all connections in ABD
1.00 Project scope to be confirmed by stakeholders
53. ABD 3 NMT Roads SCM MLCP at KTDC 7.00 Project scope to be confirmed by stakeholders
54. ABD 3 NMT Roads SCM MLCP at GCDA 10.00 Project scope to be confirmed by stakeholders
55. ABD 2 UGSS SCM Improvements to Sewer collection system for Mainland
34.50 Project scope to be confirmed by stakeholders
56. ABD 3 NMT Roads SCM Kacheripady commercial complex
5.00 Project scope to be confirmed by stakeholders
57. ABD 6 Energy
Efficiency SCM
Solar panels in canals and backwaters
0.50 Project scope to be confirmed by stakeholders
58. ABD 10 Urban Mobility SCM Standard Wifi Enabled Bus Stands With Commercial space development
3.00 Project scope to be confirmed by stakeholders
59. ABD 17 Identity and
Culture SCM Museum of Spices history 1.50
Project scope to be confirmed by stakeholders
60. ABD 17 Identity and
Culture SCM Mattancherry Walkway 11.00
Project scope to be confirmed by stakeholders
61. ABD 8 Park and Open
Space SCM
Mangalavanam Eco-restoration project
1.00 Project scope to be confirmed by stakeholders
62. ABD 10 Urban Mobility SCM
Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units
0.60 Project scope to be confirmed by stakeholders
63. ABD 16 Other Social Infrastructure
SCM Upgradation of Community Centre at Mattancherry with indoor sports facilities
1.00 Project scope to be confirmed by stakeholders
Monthly Progress Report
Page | 142 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
ANNEXURE 5: PROJECT PROGRESS
1. Detail physical progress of solar panels in govt. Buildings
Sl No
Name of Building
Capacity In KWp
Roof Type
KSEB Feasibility
Solar Panel Installation
Inverter Installation
AC cabling
DC Cabling
Installation AC DB/ DC DB
Lightning Arrestor Installation.
Earthing
Net Meter Registration
Net Meter installation
Solar Meter installation
Drawing submission to EI
Drawing approval from EI
Access to Solar system is available or not.
Final approval from EI
Supply and installation of energy meters
Testing of Solar system by KSEB
Status
Remark
1
Fire station Gandhi Nagar
40 RCC Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done
Done Obtained
Yes 85%
EI inspection done. Precommissioning test to be carried out
2
General Hospital, Ernakulam
70 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done
Done Obtained
80%
EI inspection Pending. Will provide temporary ladder for inspection
3 Town Hall, Ernakulam
80 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done 70%
EI inspection Pending. Can be done without ladder
Monthly Progress Report
Page | 143 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Name of Building
Capacity In KWp
Roof Type
KSEB Feasibility
Solar Panel Installation
Inverter Installation
AC cabling
DC Cabling
Installation AC DB/ DC DB
Lightning Arrestor Installation.
Earthing
Net Meter Registration
Net Meter installation
Solar Meter installation
Drawing submission to EI
Drawing approval from EI
Access to Solar system is available or not.
Final approval from EI
Supply and installation of energy meters
Testing of Solar system by KSEB
Status
Remark
4
Central Section Office, KSEB. Semitheri Mukku.
20 RCC Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Completed
Done Done Yes 65%
5
Government Ayurveda Hospital, Kacheripady.
15 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done 70%
6
Government Hospital, Fort Kochi.
30 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done 70%
7
Government Higher Secondary School, Panampilly Nagar
25 Roofing Sheet
Obtained
Completed
Pending
Pending
Pending
Pending
Pending
Pending
Done Done 40%
8
Government Girls HSS, Ernakulam South
30 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done Yes 70%
Monthly Progress Report
Page | 144 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Name of Building
Capacity In KWp
Roof Type
KSEB Feasibility
Solar Panel Installation
Inverter Installation
AC cabling
DC Cabling
Installation AC DB/ DC DB
Lightning Arrestor Installation.
Earthing
Net Meter Registration
Net Meter installation
Solar Meter installation
Drawing submission to EI
Drawing approval from EI
Access to Solar system is available or not.
Final approval from EI
Supply and installation of energy meters
Testing of Solar system by KSEB
Status
Remark
9 Old Age Home, Thevara
20 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Completed
Done Done 65%
10 Town Hall, Palluruthy
20 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Completed
Done Done 65%
11 Vennala High School
40 Roofing Sheet
Obtained
Completed
Completed
Pending
Pending
Completed
Pending
Pending
Done Done 45%
12
PWD Rest House, Park Avenue Road.
60 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Completed
Done Done Yes 65%
13
Elamakkara Govt Higher Secondary School (Punnackal)
40 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Pending
45%
14
Government Hospital, Karuvalipady.
40 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Completed
Done Done 65%
15
Government High School, Edakochi.
45 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Completed
Done Done 65%
Monthly Progress Report
Page | 145 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Name of Building
Capacity In KWp
Roof Type
KSEB Feasibility
Solar Panel Installation
Inverter Installation
AC cabling
DC Cabling
Installation AC DB/ DC DB
Lightning Arrestor Installation.
Earthing
Net Meter Registration
Net Meter installation
Solar Meter installation
Drawing submission to EI
Drawing approval from EI
Access to Solar system is available or not.
Final approval from EI
Supply and installation of energy meters
Testing of Solar system by KSEB
Status
Remark
16
Government High School, Edapally.
35 Roofing Sheet
Obtained
Completed
Completed
Completed
Pending
Completed
Pending
Completed
Done Done 60%
Govt Girls High School, Ernakulam
Roofing Sheet
Obtained
Dropped due to structural stability problem
17
Court Complex Ernakulam
40 RCC Obtained
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Done Done Obtained
80%
18
Paramara Building, Ernakulam North
60 Roofing Sheet
Permission otained from KSEB
5%
Approval for converting 1 Ph to 3Ph received from KSEB
19 Advocate General Office
20 Roofing Sheet
Obtained
5%
Monthly Progress Report
Page | 146 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Name of Building
Capacity In KWp
Roof Type
KSEB Feasibility
Solar Panel Installation
Inverter Installation
AC cabling
DC Cabling
Installation AC DB/ DC DB
Lightning Arrestor Installation.
Earthing
Net Meter Registration
Net Meter installation
Solar Meter installation
Drawing submission to EI
Drawing approval from EI
Access to Solar system is available or not.
Final approval from EI
Supply and installation of energy meters
Testing of Solar system by KSEB
Status
Remark
20 Building in Perumbotta ground.
30 Roofing Sheet
Permission otained from KSEB
5%
Approval for converting 1 Ph to 3Ph received from KSEB
21
New Excise Office, Ernakulam
40 RCC
Permission otained from KSEB
5%
Permanent connection to be obtained from KSEB
22
Kunnumpuram High School, Edapally
40 Roofing Sheet
Obtained
Mobilised
5%
23
Corporation Office, Ernakulam
20 Roofing Sheet
Obtained
Mobilised
Completed
Completed
20%
24
Maharajas College Britto Building
20 Roofing Sheet
Obtained
Completed
Completed
Completed
Completed
Completed
Pending
Pending
40%
25 Maharajas College
50 Roofing Sheet
Submitted
Monthly Progress Report
Page | 147 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi
Sl No
Name of Building
Capacity In KWp
Roof Type
KSEB Feasibility
Solar Panel Installation
Inverter Installation
AC cabling
DC Cabling
Installation AC DB/ DC DB
Lightning Arrestor Installation.
Earthing
Net Meter Registration
Net Meter installation
Solar Meter installation
Drawing submission to EI
Drawing approval from EI
Access to Solar system is available or not.
Final approval from EI
Supply and installation of energy meters
Testing of Solar system by KSEB
Status
Remark
Boys Hostel
26 Palluruthy Hospital.
70 Roofing Sheet
Obtained
Mobilised
5%
Total (KW)
1000
Total Completed (KW)
670
Physical Progress
48%