Monthly Progress Report Page | 1 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi Cochin Smart Mission Limited PMC to Implement Area Based Development Monthly Progress Report May 2019 Kochi Smart City

Upload: others

Post on 12-Jul-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 1 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Cochin Smart Mission Limited

PMC to Implement

Area Based Development

Monthly

Progress

Report

May 2019

Kochi Smart City

Page 2: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 2 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Cochin Smart Mission Limited, 10th Floor, Revenue Tower, KSHB, Opposite Ernakulam

Boat Jetty, Ernakulam

Monthly Progress Report

1565/MPR- 15(15/30)/May 2019/R0

Project Management Consultant (PMC)

to implement Area Based Development

Smart City Kochi

Cochin Smart Mission Limited, CSML

Page 3: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 3 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 4: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 4 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

EXECUTIVE SUMMARY ..................................................................................................................................... 6

1 STATUS AS ON 31ST MAY 2019 .................................................................................................................. 9

1.1 STAKEHOLDER MEETINGS CONDUCTED ................................................................................................. 13

1.2 SITE VISITS .............................................................................................................................................. 16

1.3 BRIEF SUMMARY OF KEY MEETINGS ....................................................................................................... 20

2 STATUS OF ABD PROJECTS ...................................................................................................................... 29

2.1 STATUS OF ABD PROJECTS ...................................................................................................................... 29

2.1.1 DEVELOPMENT OF OTHER ROADS IN ERNAKULAM.......................................... 35

2.1.2 DEVELOPMENT OF SMART ROADS IN ERNAKULAM ......................................... 37

2.1.3 DEVELOPMENT OF SMART ROADS IN WEST KOCHI ......................................... 39

2.1.4 INTELLIGENT TRAFFIC MANAGEMENT SYSTEM(ITMS) ............................. 41

2.1.5 SOLAR ROOFTOP PROJECT IMPLEMENTATION PROGRESS ............................................................. 44

2.1.6 HOUSEHOLD BINS AND BINS IN PUBLIC PLACES ............................................................................. 48

2.1.7 PUBLIC BIKE SHARING IMPLEMENTATION PROGRESS .................................................................... 52

2.1.8 CANCER BLOCK- GENERAL HOSPITAL .............................................................................................. 59

2.1.9 E-HEALTH SOLUTION FOR GENERAL HOSPITAL ............................................................................... 60

2.1.10 INTEGRATED COMMAND CONTROL & COMMUNICATION CENTER ............................................ 66

2.2 NEW PROJECTS PROPOSED ..................................................................................................................... 68

2.3 UPDATED INTEGRATED PROJECTIVISATION ........................................................................................... 69

2.4 OVERALL PROGRESS ............................................................................................................................... 81

2.5 SECTOR PROGRESS ................................................................................................................................. 82

2.6 IMPLEMENTATION SCHEDULE ................................................................................................................ 83

3 WAY FORWARD .................................................................................................................................... 102

3.1 KEY CONCERNS ..................................................................................................................................... 102

3.2 ISSUES AND CONCERNS ........................................................................................................................ 102

3.3 ASSISTANCE REQUIRED ........................................................................................................................ 102

3.4 WAY FORWARD FOR FEW PROJECTS .................................................................................................... 104

3.5 OVERALL STAKEHOLDER ROLES & RESPONSIBILITIES ........................................................................... 105

4 SMART CITY PROJECTS IN MEDIA COVERAGE ........................................................................................ 108

ANNEXURES ................................................................................................................................................. 112

ANNEXURE 1: STAKEHOLDER MEMOS ............................................................................................................. 112

ANNEXURE 3: LIST OF PROJECTS UNDER IMPLEMENTATION BY SPV............................................................... 139

ANNEXURE 5: PROJECT PROGRESS .................................................................................................................. 142

List of Tables

TABLE OF CONTENTS

Page 5: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 5 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

TABLE 1-1: STATUS OF PROJECTS IN PROGRESS ....................................................................................................... 9 TABLE 1-2: SUMMARY ON STAKEHOLDER CONSULTATIONS BY PMC TEAM DURING THE MONTH OF MAY 2019 ............... 13 TABLE 1-3 SUMMARY OF SITE VISITS CONDUCTED DURING THE MONTH OF MAY 2019 .................................................. 16 TABLE 1-4 SUMMARY OF SUPERVISION OF SITES CONDUCTED DURING THE MONTH OF MAY ......................................... 17 TABLE 2-1: ACTION FOR KMC TO ENABLE TENDERING BY END OF SEPTEMBER 2019 ................................................... 58 TABLE 3-1: PROJECTS REQUIRING STAKEHOLDER ASSISTANCE ................................................................................ 103 TABLE 3-2: PROJECTS PROPOSED TO BE DROPPED FROM CENTRAL MIS .............................................................. 104

LIST OF PHOTOGRAPHS

FIGURE 1-1 INSTALLATION OF SOLAR PANELS ......................................................................................................... 19 FIGURE 1-2 EXISTING TRUSS AT MAHARAJA BOYS HOSTEL ....................................................................................... 19 FIGURE 1-3 FORT KOCHI JAIL ................................................................................................................................ 20 FIGURE 1-4 AUTOMATED CAR PARKING FACILITY AT KALOOR ................................................................................... 20 FIGURE 1-5 JLN METRO STADIUM FOR SETUP OF COMMAND AND CONTROL CENTRE ................................................ 20 FIGURE 1-6 CRUSHER PLANT FOR CONTRACTOR- ROAD PROJECT .......................................................................... 20 FIGURE 1-7 EXISTING BRIDGES AT THURUTHY ....................................................................................................... 20 FIGURE 1-8 EXISTING ROAD CONDITION FROM JOS JN. TO CHITTOOR ROAD ............................................................ 20 FIGURE 1-6 KICK-OFF MEETING IC4 ...................................................................................................................... 21 FIGURE 1-7 CITY INNOVATION LAB- WORKSHOP ...................................................................................................... 22 FIGURE 1-8 KICK-OFF MEETING ITMS ................................................................................................................... 25 FIGURE 1-9 MEETING WITH ENGINEERING STAFF-KMC............................................................................................ 28 FIGURE 2-1 LOCATION MAP- SMART ROAD ERNAKULAM .......................................................................................... 39 FIGURE 2-2 SMART ROAD - WEST KOCHI ............................................................................................................... 41 FIGURE 2-3INSTALLATION OF SOLAR PANEL AT GENERAL HOSPITAL .......................................................................... 46 FIGURE 2-4SOLAR PANEL INSTALLATION WORK AT FIRE STATION, GANDHINAGAR ....................................................... 46 FIGURE 2-5 PANEL INSTALLATION OF TOWN HALL .................................................................................................... 46 FIGURE 2-6PANEL INSTALLATION OF CENTRAL OFFICE, KSEB ................................................................................. 47 FIGURE 2-7PANEL INSTALLATION OF CENTRAL OFFICE, KSEB ................................................................................. 47 FIGURE 2-8GOVT. HIGH SCHOOL, EDAPALLY .......................................................................................................... 47 FIGURE 2-9 COURT COMPLEX ERNAKULAM ............................................................................................................. 47 FIGURE 2-10 HOUSEHOLD BINS ............................................................................................................................. 49 FIGURE 2-11PBS LOCATIONS (BASE MAP BY PMC AND LOCATIONS PLOTTED BY SMART-SUT).................................... 54 FIGURE 2-12 ERNAKULAM MARKET REDEVELOPMENT – PROJECT PLANNING ............................................................. 57 FIGURE 2-13 ACTION TO BE TAKEN PRIOR TO TENDERING OF THE PROJECT ................................................................ 57 FIGURE 2-14 LOCATION OF PROPOSED CANCER BLOCK ........................................................................................... 60 FIGURE 2-15 STRUCTURAL OUTLINE OF E-HEALTH SOLUTION ................................................................................... 62 FIGURE 2-16 IDENTIFICATION OF TOURISM PROJECTS .............................................................................................. 65 FIGURE 2-17 INTEGRATION OF SMART SOLUTIONS WITH IC4 .................................................................................... 68

Page 6: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 6 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

EXECUTIVE SUMMARY

The smart city proposal of Kochi submitted for Smart Cities Challenges aims at integrating the

Fort Kochi & Mattancherry area with Central City Area through Water Metro. Thematic areas

for interventions under smart cities mission in Kochi are

• Seamless Mobility

• Reconstitution of Urban Form

• World Class Urban Services & Inclusive Development

• Revival of Identity and Culture

The Smart City proposal of Kochi has adopted retrofitting as the strategy for development

under the Mission. The vision for Kochi is to transform Kochi, into a sustainable, inclusive and

economically vibrant city of opportunities with efficient urban services, traditional hospitality

and smart governance.

a) Area Based Development (ABD) projects

Area Based Development (ABD) as part of Smart City development consists of parts of five

wards west Kochi (1,2,3,4 and 5) and parts of three wards of mainland of KMC (62,66 & 67),

with a total area of 1024.16 acres. There are currently are 64 ABD projects under 18 modules

worth a total cost of Rs. 1323 Crores. Of these 15 projects are those where project scope is

being discussed and confirmed by the stakeholders

The overall status of ABD projects is as follows:

(Amount in INR Crore)

Source of funding / status Sum of Project Cost /SCP cost No of Projects

DPR Prepared 21.66 6

DPR Under Preparation 174.30 13

Tender Issued 276.69 11

Work order issued/Project Under Implementation 267.62 10

To be re-tendered 73.95 4

Fund Transfer 34.00 2

Project scope to be confirmed by stakeholders 156.95 14

SCM 1,005.17 60

DPR Prepared 1.00 1

Tender Issued 301.58 1

Work order issued/Project Under Implementation 10.00 1

PPP 312.58 3

DPR Under Preparation 83.75 10

Project Completed 4.78 2

Tender Issued 96.00 2

Work order issued/Project Under Implementation 55.34 5

Other Sources 239.87 19

Grand Total 1,557.62 82

Page 7: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 7 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Note: Detailed list provided in annexure

*information as per data provided by Tourism dept. and KWA

Pan City projects

Pan city projects are convergence projects and being implemented by stakeholders. As part of SCP two projects

were proposed as Pan City projects. Smart Card - Kochi 1 is a PPP project and implemented by KMRL. 24 X 7

WATER SUPPLY is being taken up by KWA for implementation.

Source of Fund No of Projects Project Estimated Cost (If any) or SCP cost

PPP

Project Completed 1 25

Other Sources

DPR to be prepared 1 621

Grand Total 2 646

Note: * As data received from KWA

Status of Smart City Mission Kochi as on 31st May 2019

Total Project Cost- including convergence

Rs 2,203.62 cr

Central Assistance Released Rs. 196 cr

State Grant Released

Rs 200 cr

Central Assistance

Approved

Rs. 500 cr

Tender Issued (Ongoing)- SPV

Projects 12

Cost Rs. 578.28 cr

Work Order issued/Project yet to start - SPV

Projects 11

Cost Rs. 277.61 cr

Page 8: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 8 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SUMMARY OF PROGRESS BY PMC IN THE MONTH OF MAY 2019

CUMMULATIVE DELIVERABLES SUBMITTED BY PMC AS ON 31ST MAY

Monthly Progress Report

(1 Report, April 2019)

Revised BoQ/Estimates

(1 Project)

EIA Report

(5 Projects)

Project (Stakeholder)

meetings (19 Nos)

Supervision - Site Visits

(20 Nos)

Situation Analysis Report

(1 Report)

Feasibility Reports

(48 Projects)

Monthly Progress Reports

(18 Reports)

Detailed Project Reports

(31 Projects)

RFP/Tender Submitted

(24 Projects)

EoI & related Reports

(2 Projects)

Tender Issued

(24 Projects)

Draft BERs prepared

(21 Projects)

Draft CERs prepared

(10 Projects)

Site Visits

(13 Nos)

Concept Note

(1 Project)

Page 9: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 9 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

1 STATUS AS ON 31ST

MAY 2019

In the month of May, the Smart City team worked on Bid evaluation of the tendered projects,

In the month of May, the Smart City team worked on Bid evaluation of the tendered projects,

BoQ revision for the West Kochi Road and Tourism Projects. Environmental Impact

Assessment for Clavathy School, Fort Kochi taluk and Mattancherry Hospital, Open air

Theatre and Public Toilets has been prepared and submitted. Detailed Project Report for

Open Space, Anganwadi, Museum for Freedom Struggle along with several other projects

are in progress.

The status of projects under Smart City is given below;

Table 1-1: Status of Projects in progress

Sl No

Project Name Cost in INR Cr.

Status Date of Submission

of Feasibility

Report

Date of Submission

of DPR

1. Smart Water solutions - Smart Metering and smart valves for all connections in ABD

1.00 Feasibility report preparation under progress.

2. Rainwater structures in 13 Govt bldgs & Institutions

0.75 Feasibility Report submitted 21-03-2018 Now under convergence

3. Improvements to sewer collection system for West Kochi

154.50 Project Tendered 07-02-2018/ 11-09-2018

20-02-2019/ 28-02-2019/ 05-03-2019

4. Improvements to sewer collection system for Mainland

34.50 Renamed - As Elamkulam STP INR 13 Cr. taken up by KWA. Scope for mainland to be confirmed by KWA

5. Development of Other Roads in Ernakulam ABD

43.60 LOA issued on 9th April 2019 10-08-2018 30-08-2018

6. Development of Other Roads in West Kochi

60.20 Project Re-tendered 10-08-2018 30-08-2018

7. MLCP and at Kacheripady 6.16 Project to be re-tendered

06-02-2018/ 07-10-2018

07-02-2019

8. Commercial complex at Kacheripady

5.00 Scope to be confirmed by stakeholder

9. MLCP at GCDA 10.00 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin

07-10-2018

10. MLCP at KTDC 7.00 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin

07-10-2018

11. Smart Parking Solutions in ABD area

1.90 DPR under preparation 07-10-2018

12. Development of Smart Roads in Ernakulam

61.53 LOA issued on 9th April 2019 10-08-2018 30-08-2018

13. Development of Smart Roads in West Kochi

30.31 LOA issued on 9th April 2019 10-08-2018 30-08-2018

14. Intelligent Traffic Management Systems (ITMS)

26.90 Contract Agreement signed on 16th May 2019

02-02-2018

06-02-2018

15. Road Signages for ABD 2.40 DPR Submitted 15-02-2019 18-02-2019

16. FOBs - West Kochi (3 Nos) 2.15 DPR under preparation 27-09-2018

17. Development of Smart Roads electrical infrastructure in Ernakulam & West Kochi under Smart City Mission

63.40 Project to be re-tendered

10-08-2018 30-08-2018

Page 10: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 10 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Project Name Cost in INR Cr.

Status Date of Submission

of Feasibility

Report

Date of Submission

of DPR

18. Implementation of Smart LED lighting in ABD

32.09 Tender published and bids submitted. Bid evaluation under progress

12-02-2018 17-02-2018

19. Intelligent Street Poles (PPP) 301.58 Tender has been floated. Technical Bid evaluation under progress

08-02-2018/ 01-03-2018

15-11-2018/ 08-02-2019

20. Solar panels in Govt. buildings 5.70 Contract awarded. Project under implementation.

02-02-2018

07-02-2018

21. Solar panels in canals and backwaters

0.50 Project to be developed with Canal project proposals

22. Smart & Improved Secondary Storage & Transportation of Solid Waste using Portable Compactor Technology

4.4 Project to be re-tendered. 14-02-2018

20-03-2019

23. Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area

1.00 DPR submitted 26-02-2018

28-02-2018

24. Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area

3.2 Project to be re-tendered. 20-03-2018

20-03-2018

25. Distribution of Household Bins & Street Litter Bins for improvement of waste segregation in ABD Area

0.67 LOA issued on 8th May 2019 07-02-2018

28-02-2018

26. Public toilets in West Kochi & Ernakulam

1.80 Tender issued Technical Bid evaluation under progress

27-09-2018

13-02-2019

27. Development of Open Space and Playground in ABD

2.50 DPR will be submitted by 20th June

26-03-2019

28. Improvements to Marine Drive Walkway Phase I

7.10 Tender issued 03-11-2018

11-11-2018/ 04-02-2019/ 27-02-2019

29. Mangalavanam Eco-restoration project

1 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin

30. Restoration of Mullassery canal - including linking of standardized area drains

1 DPR under preparation 02-03-2019

31. Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts

5 DPR under preparation 02-03-2019

32. Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features

20 DPR under preparation 02-03-2019

33. Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road

15 DPR under preparation 02-03-2019

34. Bicycle Sharing (PPP) 10 Contract awarded. Work under implementation

02-03-2018

35. Walkway from Ekm Jetty to Metro station

4.70 Word awarded Under implementaion

Page 11: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 11 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Project Name Cost in INR Cr.

Status Date of Submission

of Feasibility

Report

Date of Submission

of DPR

36. Integrated Command, Control and Communication Centre (IC4)

64.5 LoA has been issued. Project kick off meeting took place on 6th May 2019

15-05-2018

20-05-2018

37. Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

0.60 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin

38. Standard Wifi Enabled Bus Stands With Commercial space development

3 Scope to be confirmed by stakeholder. Post confirmation on scope work on proposal shall begin

39. Integrated redevelopment of Slum housing

46.85 KMC to confirm scope. Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest.R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited.

40. Beneficiary LED Housing 13.00 KMC to confirm list of beneficiares. KMC to share gap funding required and final list of beneficiaries.

41. Construction & upgradation Thuruthy, Kalvathy & Konchery colony - Construction of Bridges

5.15 Bridge & social infrastructure project proposed under SCM. Feasibility report submitted.

In principle agreed in 1 December 18 meeting with DUA. Post approval of FR, DPR to be prepared

27-09-2018

42. Construction of First tower at Thuruthy

21.00 Scope is being finalised

43. Construction of Second tower at Thuruthy

35.00 KMC to confirm scope. Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest.R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited.

44. Broadway Street Pedestrianization

10 Feasibility report submitted

DPR under preparation. KMC to share list of hawkers and carry out R&R.

15-10-2018

45. Ernakulam Market Redevelopment+ Escalator

100 Feasibility report submitted

DPR under preparation. KMC to share list of vendors &

15-09-2018

Page 12: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 12 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Project Name Cost in INR Cr.

Status Date of Submission

of Feasibility

Report

Date of Submission

of DPR

FOBs+ Elevated Walkways and Travelators

hawkers and also identify land for transit shops.

46. Mattancherry spice market Redevelopment

Scope under discussion with stakeholders. Soft improvements already proposed along with road project

47. Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"

5.60 Petti kada draft design ready KMC to share final list of licensed hawkers. The Hawker Zones Project is included under Fort Kochi Beach improvements project.

48. Scale up of GH into a Super- Specialty care centres (Cancer Ward)

26.00 LoA Issued to INKEL 10-07-2018

49. New Block at Fort Kochi Taluk Hospital

4.65 Tender issued 28-02-2018

17-03-2018/ 30-10-2018

50. New Block of Mattancherry Women & Children Hospital

4.57 Tender issued 28-02-2018

28-03-2018 13-11-2018

51. E-health solutions for selected hospitals

3.71 LoA issued. Contract Agreement to be signed

15-09-2018

20-12-2018/ 07-02-2019

52. Upgradation of Anganwadi Centres in West Kochi

2.00 DPR under preparation 06-04-2019

53. Higher secondary block, Central Calvathy GHSS, Fort Kochi

4.67 Project to be re-tendered 28-02-2018

15-07-2018/ 03-12-2018

54. Smart Classroom for 100 classrooms PAN city

4.90 Tendered cancelled 05-02-2018

09-02-2018

55. Safety & Security CCTV surveillance

14.56 DPR Submitted 21-01-2019 21-03-2019

56. Upgradation of Community Centre at Mattancherry with indoor sports facilities

1.00 As per KMC to community centre avaialbe requiring upgradation. Hence project may be dropped. KMC to confirm formally.

57. Open Air Theatre at Fort Kochi Zonal office

1.30 Tender issued 14-Aug-18 Rev- 10-Oct-18

06-02-2019

58. Development of Dutch palace node parking area and palace street entry

1.10 Tender issued

20-12-2018

20-02-2019

59. Fort Kochi Beach Front improvements - Part A Vasco Square

1.71 Project to be re-tendered

20-12-2018

28-02-2019

60. Museums of Freedom Struggle 1.20

Feasibility report Submitted.

20-12-2018

61. Museum of Spices 1.50 20-12-2018

62. Development of Ethnic Food Hub & Dutch Quay Upgradation

1.00 20-12-2018

28-02-2019

63. Fort Kochi Beach Front improvements - Part B Walkway & Beach

8.42 20-12-2018

Page 13: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 13 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Project Name Cost in INR Cr.

Status Date of Submission

of Feasibility

Report

Date of Submission

of DPR

64. Mattancherry Walkway 11.00 20-12-2018

65. Art Installations in Kochi / Cultural Corridor- PT Usha Road

1.00 Feasibility report under preparation

66. Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres

0.40 Detailed Project Report submitted on 21st December 2018. KMC is taking up the project based on scope shared. KMC to tender the project at the earliest.

21-12-2018

1.1 STAKEHOLDER MEETINGS CONDUCTED

Stakeholder meetings conducted in the month of May are as follows:

Table 1-2: Summary on Stakeholder Consultations by PMC team during the month of May 2019

S. No

Date of Consultation

Module Content

Stakeholder Consultation

Concerned Person in the Department

Agenda Discussion by PMC Team

Remarks

1. 03/5/2019 SWM- Public Toilet

Fort Kochi Village Office

Official of the Fort Kochi Office

To collect Public Toilet Survey Sketches

Discussed regarding Public Toiler survey at Fort Kochi

2. 03/05/2019 Park and Open Space

KMC Ms. Shiny Mathew, Councillors Ms. Zeenath, Councillors

Upgradation of parks and open spaces in ward no: 1 and 2.

concept prepared were discussed with respective ward councillors

3. 04/05/2019 Park and Open Space

GCDA Mr. V. Saleem, Chairman, GCDA Mr. Rajesh, Senior Town Planner, GCDA (point of contact with GCDA) Representatives from various GCDA departments

Marine Drive Walkway proposal

CSML to forward an official letter to GCDA (within a week), along with a project brief and detailed drawings explaining the exact scope of intervention, and clarifications on maintenance of infrastructure, advertisement areas, potential revenue and issues post CSML’s maintenance period. Detailed MoM is attached in annexure 1.

4. 04/05/2019 Housing KMC Superintending Engineer

RAY Project Discussed with SE pertaining to the RAY project which is being implemented by KMC

5. 06/05/2019 Economy and Employment

Ernakulam Market Association

Ernakulam Market Stall Owner’s Association(EMSOA)

Understand the functioning of market and conclude on a suitable proposal for Market redevelopment

MD, CSML requested all the representatives of EMSOA to confirm and agree to the proposal of market redevelopment and assured that the proposal would only be having ground floor and

Page 14: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 14 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Date of Consultation

Module Content

Stakeholder Consultation

Concerned Person in the Department

Agenda Discussion by PMC Team

Remarks

2 upper floors along with a basement. EMSOA expressed their support for the proposal and also confirmed that some stalls shall be shifted to the 1st floor in the new proposal which would include, Fish, meat, poultry and some other goods. EMSOA insisted that the ground floor plinth height be reduced in order to facilitate easy loading of goods by labour workers. CSML explained the use of push/pull carts and trolleys to be used within the market complex to assist the movement of goods. Detailed MoM is attached in annexure 1.

6. 7/5/2019 Others (IC4)

KMC Mr. Vysag Lenin Municipal Management System

Discussed about existing MMIS, digitization of older records

7. 8/05/2019 Parks & Open Space

KMC Ms. Shameena, Ward Councillor Ms. Bindu, Ward Councillor

Upgradation of Moomen’s park and Karippalam Park

Concept prepared were discussed with respective ward councillors

8. 13/05/2019 Economy and Employment

Ernakulam Market Association

Ernakulam Market Stall Owner’s Association(EMSOA)

Finalize the proposal for Market redevelopment

Market association shall discuss the proposal with all member and giving final decision on the layout while CSML shall share the revised layout based on the discussion. Detailed MoM is attached in annexure 1.

9. 13/05/2019 Energy Efficiency

KMC EE, AEE Installation of LED Lights

Discussion were held with EE and AEE of KMC pertaining to the installation of LED lights project.

10. 16/05/2019 Energy Efficiency

KMC Hon’ble Mayor, Councillors and other Officials of KMC

Implementation of Intelligent Street Pole at Kochi Under PPP on DBOOT model

Detailed presentation were made by PMC regarding the Project Proposal including revenue model. Mayor shows interest in the concept of Smart Pole project however, mention various challenges in executing the project discusses action plan. Detailed MoM is attached in the annexure 1.

Page 15: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 15 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Date of Consultation

Module Content

Stakeholder Consultation

Concerned Person in the Department

Agenda Discussion by PMC Team

Remarks

11. 17/5/2019 Water Supply

KWA, Pallimukku

Mr. Ajith Kumar, A.E.E

Data collection for water supply projects implemented by KWA

Mr. Ajijt Kumar, AEE has directed to AE to provide all the relevant data.

12. 20/05/2019 Water Supply

KWA, Pallimukku

Ms. Jaya, A.E Data collection for water supply projects implemented by KWA

Ms. Jaya has provided the required data related to Project under Plan fund, KMC deposit work, Draught fund etc.

13. 20/05/2019 Tourism Tourism Department

Ms. Sabitha, Section Clerk, Tourism Department

Regarding initiatives of Tourism Department at Fort Kochi Beach Area

The detailed information pertaining to the project which is being implemented by Tourism department in Fort Kochi area has been taken

14. 21/05/2019 Park & Open Space

GCDA Jeby Jomy (Superintending Engineer) Rajesh T.N. (Town Planner) GCDA Team

To discuss on the submitted Marine Drive Walkway- Project Brief

The project details were briefed and project will be taken up for approval from GCDA Executive Council. Detailed MoM has b1een attached in annexure 1

15. 21/05/2019 Park & Open Space

GCDA GCDA Chairman To discuss on the submitted Marine Drive Walkway- Project Brief

Marine drive walkway progress was updated and further confirmation shall be provided by GCDA. Detailed MoM is attached in the annexure 1

16. 27/05/2019 Water Supply

KMC Mr. Peter, Councillor Ms. Elizabeth, Councillor

Automated Metering Infrastructure

Discussed the AMI projects with Councillors. The councillors agreed to do AMI project in their ward(i.e. Newly laid pipeline)

17. 28/05/2019 Water Supply

KWA, Hospital Road

Mr. Vinod AMI discussion, drawing collection

Mr. Vinod has given the connection details and specifications of the selected pipelines also he told that he will provide the drawings of the pipelines once he received.

18. 28/05/2019 Tourism Revenue divisional office, Fort Kochi

Mr. Snehil IAS, Sub-collector, Fort Kochi

Approval of the Proposed Freedom struggle Museum and other projects in Fort Kochi

The sub-collector was keen to get the projects implemented in fort Kochi and inquired about the status of tendered projects of Vasco square development. Sub-collector (SC) approved the proposal for Freedom struggle museum, and but informed that he had a proposal to build a single storey senior citizen counselling room building as an extension of RDO in the additional vacant land of 8 cents which

Page 16: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 16 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Date of Consultation

Module Content

Stakeholder Consultation

Concerned Person in the Department

Agenda Discussion by PMC Team

Remarks

CSML is proposing to develop along with the Museum project. Sub Collector also reviews other projects related to Park & Open Space and Fort Kochi upgradation. Detailed MoM has been attached with the annexure 1.

19. 28/05/2019 Canal Restoration

KMRL Conference Room

Officials From KMRL, CSML, KMC, Irrigation Division, KWA, Water Transport

Stakeholder consultation to discuss Canal Rejuvenation finding based on feasibility report prepared by PMC

Action Points : Confirmation on length of Canal for improvement under Smart City. CSML to take relevant approvals and convey the same to PMC To be discussed with KMRL & CSML which agency shall take up Canal Rejuvenation of Market Canal Detailed MoM is attached with annexure1

1.2 SITE VISITS

In the month of April following site visits and supervision visits have been taken up by PMC:

Table 1-3 Summary of site visits conducted during the month of May 2019

S No

Date Site Visited Agenda for Site visit Location Notes from site visit

1. 04-05-2019 Fort Kochi Jail For the preparation of

an estimate Fort Kochi. Survey of sites has

been done for the purpose of cost estimation

2. 07-05-2019 Thuruthy Colony

and Chungam Bridge

To assess the site conditions for the proposed bridge projects

Fort Kochi Five sites were visited for 3 proposed minor bridges and two foot bridges

3. 08-05-201 Parks and open

spaces in Fort Koch

To Prepare a design Fort Kochi Survey of sites has been done for the purpose of preparation of site design

4. 15-05-2019 IC4 Survey of sites for

installation of video wall

JLN Stadium, Metro Station

Joint survey with Vendor and measurement has been taken for installation of video wall

5. 16-05-2019 He-man Robo

Park automated MLCP Facili

Facility Assessment by Transport Exper

Kaloor The automated parking facility accommodated 81 cars, along with ground parking along the periphery.

Page 17: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 17 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

6. 17-05-2019 Fort Kochi -

Bellar - K B Jacob Road Junction, Parking in Tourist Area.

Assess the existing movement of traffic and associated activities at the junction

Fort Kochi Traffic movement and associated activities at the junction have been accessed.

7. 17-05-2019 Open spaces

and Play Grounds

To prepare the estimate

West Kochi Site survey has been done for the preparation of cost estimation.

8. 17-05-2019 Proposed Public

Toilets Site visit with Vendor TDLCCS

Fort Kochi Joint site with the vendor has been done for the construction of public toilets at fort kochi

9. 17-05-2019 Mullassery

Canal Site inspection Ernakulam Site inspection has

been done for Mulessery Canal from Park avenue road to T.D Road

10. 18-05-2019 Mullassery

Canal Measurement of the Site

Ernakulam Site visit to measure the details of Mullasssery canal from KSRTC junction to T.D Road

11. 20-05-2019 Jos Junction to

Chittoor Road Junction

Taking over the road stretch from DMRC for development of road under Cochin Smart Mission

Ernakulam Scope of works of DMRC for the RHS of the road stretch between Jos Junction and Chittoor road was completed and was taken over for development under CSML

12. 24.05.2019 Subhash Park Site inspection Ernakulam Site inspection has

been done for the preparation of cost estimation for taking up the remaining work.

13. 30.05.2019 Parks & Open

Space Site inspection West Kochi Site inspection has

been don at West Kochi Parks for preparation of cost estimation for electrical Work.

Table 1-4 Summary of supervision of sites conducted during the month of May

S No

Date Site Visited Agenda for Site visit Location Notes from site visit

1. 02-05-2019 PWD Rest

house, Dist. Ayurveda Hosp., Townhall, KSEB Central Section, GHSS

To update the progress of Solar Project

Ernakulam Physical progress of the projects at the locations has been supervised.

2. 03-05-201 GHS Panampilly

Nagar, Old Age Home Thevara, Town Hall Palluruthy, Govt. Hospital Karuvelippady,

To update the progress of Solar Project

Ernakulam and West Kochi

Physical progress of the projects at the locations has been supervised.

Page 18: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 18 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S No

Date Site Visited Agenda for Site visit Location Notes from site visit

Govt. Hospital Fort Kochi

3. 13-05-2019 Deens Site

Office To assess the location found for establishing contractors site office

Kadavanthra Existing Building with some free land adjacent to it. Was found suitable for establishing Site office.

4. 17-05-201 Palluruthy

Hospital To check the structural stability of Truss work for Solar Project

Palluruth Survey work for structural stability of Truss for installation of Solar Panels has been done

5. 17-05-2019 Open spaces

and Play Grounds

To prepare the estimate

West Kochi Site survey has been done for the preparation of cost estimation.

6. 17-05-2019 West Kochi

Smart Roads Site Visit to supervise Contractors survey works

Fort Kochi To supervise the survey works which is being done by the Contractor

7. 17-05-2019 Abraham

Madamakkal Road

Joint site visit with Contractor to assess the site conditions and plan works accordingly

Ernakulam Road stretch from high court junction to Goshree bridge was visited.

8. 18-05-2019 West Kochi

Smart Roads Site Visit to supervise Contractors survey works

Fort Kochi To supervise the survey works which is being done by the Contractor

9. 20-05-2019 Deens Site office To see the Samples

for Kerb stones brought by the Contractor

Kadavanthra Tile Samples were found to be ok in visual inspection and contractor was asked to get the same tested from a NABL Accredited lab.

10. 21-05-201 West Kochi

Smart Roads Site Visit to supervise Contractors survey works

Fort Kochi To supervise the survey works which is being done by the Contractor

11. 21-05-2019 Deens Crusher

Plant Visited Contractors Crusher plant as a part of aggregate source approva

Kottapady, Kothamangalam

The quarry and plant was found to be satisfactory. Contractor was asked to submit the test reports pertaining to the aggregate properties at the earlies

12. 22-05-2019 Jos Junction to

Chittoor Road Junction

For fixing the location for laying electrical duct before the bitumen works are done

Chittoor Road Junction

DMRC has planned for bitumen works at the site and PMC along with Contractor visited the site for assessing the feasibility of laying ducts before the works

13. 24-05-2019 West Kochi

Smart Roads Site Visit to supervise Contractors survey works

Fort Kochi To supervise the survey works which is being done by the Contractor

Page 19: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 19 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S No

Date Site Visited Agenda for Site visit Location Notes from site visit

14. 24-05-2019 Abraham

Madamakkal Road

Supervising the initial level Survey works at Site

Ernakulam Traverse closing was not completed for the road. Contractor was instructed to complete the same before starting the initial level survey

15. 24-05-2019 Deens - Base

Camp Visit to the proposed base camp and batching plant location of Deens Group

Edayar The proposed location was found to be suitable for establishing contractors base camp

16. 24-05-2019 West Kochi

Smart Roads Site Visit to supervise Contractors survey works

Fort Kochi To supervise the survey works which is being done by the Contractor

17. 27-05-2019 West Kochi

Smart Roads Site Visit to supervise Contractors survey works

Fort Kochi To supervise the survey works which is being done by the Contractor

18. 28-05-2019 Jos Junction Joint Site visit with

CSML, KMRL, Deens and PMC

Ernakulam Joint site visit has been done at Jos Junction for Road project with Officials from CSML & KMRL and the Contractor

19. 30-05-2019 Maharaja’s Boys

Hostel, GGHSS Ernakulam, Fort Kochi Taluk Hospital

To check the structural stability of Truss work for Solar Project and to check the leakage in ongoing Solar Project.

Fort Kochi, Ernakulam

Survey of structural stability of Truss Work for installation of solar project has done. Also the inspection of leakage which is reported due to installation of Solar Panels.

20. 30-05-2019 ABC Builders’

Site Office and Plant

Visit to ABC Builders proposed site office and Batching Plant

Fort Kochi The proposed building and land was found suitable for site office and Plant respectively.

Photographs for existing conditions of the sites visited.

Figure 1-1 Installation of Solar Panels Figure 1-2 Existing truss at Maharaja Boys Hostel

Page 20: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 20 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Figure 1-3 Fort Kochi Jail Figure 1-4 Automated Car Parking Facility at Kaloor

Figure 1-5 JLN Metro Stadium for setup of Command and Control Centre

Figure 1-6 Crusher Plant for Contractor- Road Project

Figure 1-7 Existing Bridges at Thuruthy Figure 1-8 Existing Road condition from Jos Jn. To

Chittoor Road

1.3 BRIEF SUMMARY OF KEY MEETINGS

1. Kick-Off Meeting for Integrated Command and Control and Communication

Center on 6th May, 2019

The work for IC4 has been awarded to M/s Fluentgrid in consortium with Bharat Electronics

Limited at a cost of Rs 64.50 cr. In this regard, a Kick of Meeting was organised in which,

detailed structure of the project, high level project architecture and plan, scope of work,

project team and other aspect of technologies were discussed with various Stakeholders.

Page 21: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 21 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

At the outset of the meeting M/s Fluentgrid team introduced the project and welcomed

Managing Director, CSM along with other Officials from department and other

Stakeholders. A detailed presentation was made for project overview, objective of the IC4,

smart solutions, Architecture of the project, Implementation Schedule, Networking and

cloud based DC & DR. The Fluentgrid informed that, they have sign agreement with BSNL

as a Network partner and for DC& DR, it is Amazon Web Services. M/s Fluentgrid inform

that a Mobile App will also be developed for the Citizens.

Followed by presentation, detailed discussion with other Stakeholder, PMC and CSML

Official were held for integration of different smart solutions for the respective departments.

The Technical Team of M/s Fluentgrid informed that the smart solutions for any department

can be integrated through API which should be provided by the respective department.

Detail Minutes of the Meeting has been attached in the annexure.

Figure 1-9 Kick-Off Meeting IC4

2. Workshop on Smart City Innovation Lab by Fraunhofer

Kochi Smart City Lab Kochi Smart City Innovation Lab, a joint venture between Cochin

Smart Mission Limited and Fraunhofer - a German government-backed research

organization has organised a workshop for the project which will be implemented by the

Organisation. The General Manager, CSML welcome the participants and gave the brief

introduction about the Cochin Smart City Mission Limited and activities of it. Mr. Marius

Mohr from Fraunhofer gave the introduction of Smart City Innovation Lab and made a

detailed presentation on project structure, approach and identified focus area.

Page 22: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 22 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Mr. Mohr has informed that the Fraunhofer will support CSML in implementation of the

project from Disaster Management, Housing, Energy Efficiency, and Environmental

Protection/Water sector. He informed that the whole programme has been divided into three

phases that is understanding phase, co-creation phase and transformation phase.

The duration of the implementation of the project will be 3 years. He informed that integrated

drainage and canal system rejuvenation and management plan has been identified as focus

area by the organisation.

Managing Director, CSML has discussed the details of financial assistance for the project

(Smart City, PPP, convergence) along with external aid for projects under identified sectors.

He requested Officials to bring up innovative ideas/project to be assist by KFW/Fraunhofer.

Followed by presentation, detail discussion was held for the challenges in implementation

of the projects, capacity building, acceptance of the project, affordable housing for low

income group, plan for disaster management and waste management.

Figure 1-10 City Innovation Lab- Workshop

3. Kick-Off Meeting for 3 Roads packages was held on 16th May, 2019

The work for 2 Road Packages that is Development of Other Roads in Ernakulam ABD at

a cost of Rs 43.60 cr, Development of Smart Roads in Ernakulam ABD at a cost of Rs 61.53

cr has been awarded to M/s. Deens Group and M/s. Deens Group in Consortium with

Deens Constructions respectively. The work for Development of Smart Roads in West

Kochi in ABD at a cost of Rs. 30.31 cr has been awarded to M/s. ABC Builders. In this

regard kick off meeting were organised on 16th May 2019 in which project specific details

were discussed.

The key points of the discussion were general requirement of which is to be complied by

the contractor such as:

• Bank Guarantee for performance security

• Agreement Signing

• Baseline Work Schedule

• Mobilization

• Site Office

Page 23: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 23 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

• Laboratories

• Plants & Equipments

• Statutory Clearances

• Labour License

• Insurance

• Key personnel

• Sub-Contracts Finalization (if any)

• Preliminary Survey and Preparation of Working Drawings

• Procurement Schedule

• Quality Assurance Plan

• Material Source Selection and Approval

• Preparation of Job Mix Designs and Approval

• Health, Safety and Environment Plans

• Traffic Management Plan

The suggestions were made to the contractor that they needs to assess the local condition

and also setting up of plants and machineries shall not be too far from the site. The batching

plant location shall have good accessibility. The finalisation of the sub-contract shall be

conducted at the earliest. The CSML instructed to appoint a full time project manager and

support staff matching with the credentials in the tender and also the contractor shall

appoint electrical contractor with Class A registration and experience in similar works for

utility shifting The finalization of location for the site office and laboratory for testing of the

materials shall be done after due inspection and approval by the PMC and CMSL.

The road contractors were informed regarding other parallel project ongoing under Smart

City and need for integration

- Intelligent Traffic Management System Pan city (Kochi Municipal Corporation area)

- Smart poles pan city

- Smart LED lighting

M/s ABC builders which is the contractor for the Development of Smart Roads in West

Kochi in ABD has informed that they will bring the labour from outside the State hence the

contractor was instructed to set up a labour camp with all standard facilities.

Detailed Minutes of the Meeting is attached in the annexure 1

4. Kick-Off Meeting for Intelligent Traffic and Management System (ITMS) on 18th

May, 2019.

The work for ITMS project has been awarded to KELTRON at a cost of Rs 26.90 cr. In this

regard, a Kick of Meeting was organised on 18th May 2019 which was attended by the

KMRL, Police Department, PMC to the Smart City, GIDA and other Stakeholders. At the

outset of the meeting CSML introduced the project and welcomed everyone. A detailed

discussion was held between the stakeholders regarding execution of the projects. The key

points of discussion were:

Page 24: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 24 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

➢ KELTRON during the meeting submitted PBG, contract document, solution document.

KELTRON added that the solution document is to be revised based on site visits to be

conducted. CSML mentioned that a revised solution document is to be submitted by

KELTRON with 5 modified locations, locations which require dismantling of street

furniture and detail of the project team, Staff schedule and detailed implementation

schedule.

➢ Proposed joint site visit along with members from PWD, Police, KMC, GIDA, GCDA

etc.

➢ Based on the site visit, there are lot of street furniture’s to be dismantled and removed

– CSML replied that, stakeholders will be identified, and request will be made for the

same. CSML requested to have the stakeholders and list required to be added in the

revised solution document

➢ Request for space for storing of equipment – CSML responded that the SPV does not

have any asset hence the material to be stored in space available with KELTRON.

➢ CSML also pointed out that till commissioning supply material is to be taken care of by

the vendor. KELTRON agreed to the same

➢ Keltron stated that, Aroor manufacturing plant can be utilised for storing the equipment.

KELTRON to share facility detail.

➢ To manage delay, the implementation schedule is modified as 6+1 months.

➢ For connectivity, MPLS VPN through OFC and as per proposal, the network partner is

BSNL.

➢ The structural details of poles are provided with solution document.

The detailed Minutes of the Meeting is attached in the annexure 1

Page 25: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 25 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Figure 1-11 Kick-Off Meeting ITMS

5. Review Meeting – Development of Smart and Other Roads in Ernakulam

The agenda was to assess and discussed the status of pre-implementation process which

are supposed to be completed by the contractor. The following key points were discussed:

a) Bank Guarantee and Agreement Signing : The contractor informed that PBG will be

submitted as per the timeline committed during the Kick Off Meeting

b) Baseline work Schedule: Shortfalls of the submitted work schedule was explained to

the contractor. The contractor was instructed to discuss with same with Engineer’s

representative.

c) Status of Mobilisation: The contractor informed that they have identified the location

for establishing the office, laboratory and batching plant. A joint visit with PMC and

contractor is scheduled in this regard.

d) Subcontractor for Electrical Utility Works: The contractor expressed difficulty in

finding the suitable subcontractor of electrical utility works. It was informed to the

contractor that Engineer will provide the necessary clarification for electrical works and

will help the contractor to find suitable subcontractor for the same.

e) Commencement of Piling Works: Piling works for the proposed bridges at Abraham

Madamakkal Road were discussed during the review meeting. The contractor was

instructed that for piling work RMC may be used upon submission and approval of mix

designs. Kerb, Paver Tiles etc may be procured from local market which company will

all quality requirement and test from a NABL accredited lab. Also mounted Kerb will be

examined by the KMRL.

Detailed MoM is attached in the annexure 1.

6. Combined stakeholder meeting for Canal projects was held on 28 May 2019

Based on the Feasibility report prepared by Project Management Consultant, a combined

stakeholders meeting were organised to discuss Canal Rejuvenation projects. At the outset

of the meeting CSML welcomed all the participants and then detailed presentation were

made. The key points of the discussion were:

➢ Current situation of the canals under ABD area was discussed and the presentation on

the feasibility report submitted was explained by Pradyumna Machhkhand, Canal

Page 26: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 26 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Expert, PMC. Current situation, navigability and other constraints like social and

environmental issues regarding the rejuvenation of the canal were elaborated.

➢ Ernakulam Market Re-development - the plan for constructing the Multi storied building

for the Market shops was explained. The possibility of navigability of the market canal

was discussed.

➢ Kalvathy-Rameswarm Canals – the bridges constructed over the canal would be

hinderance to navigability of the canal. It was pointed out that houses and shops were

found constructed at the edges of the canal side wall especially along the Mullasserry

canal and the Kalvathy canal.

➢ Alternative methods for rejuvenation and controlling of the storm water, sewerage and

other wastes flowing to the canals were also discussed. The alternative methods

suggested were: (1) New trunk Sewer System with a proposal of STP. The site of STP

may be proposed at the GCA parting area near the mouth of the canal. (2) New Trunk

Sewer System to be integrated with the existing sewer network.

➢ The hydrological study for all the three canals within the ABD catchment area was

carried out and raising the side wall was recommended in the Feasibility Report. The

construction of sheet piles at the boundaries of the existing walls of the canals was

suggested for avoiding the damages of the side walls. The cost (excluding the urban

designs, sewerage and other miscellaneous cost) for this construction is also

mentioned in the feasibility report.

The presentation was concluded with a note for improvement and additions to the feasibility

report.

The detailed Minutes of the Meeting is attached in the annexure1.

7. Introduction and discussion of Smart City Mission Project with Engineering

Wing of KMC on 29.05.2019.

The agenda of the meeting was to appraise the engineering staff of the KMC about projects

undertaken by CSML and implement the projects with guidance & active assistance from

engineering wing. Detailed presentation was made pertaining to status and project proposal

under various sectors.

a) Urban Mobility and Road Projects

a) Smart and other roads

b) Public bike sharing system

c) Parking management

During the discussion the engineering staff were made some suggestions such as Carriage

way of Hospital road seems to be reduced, No provision for Two-Wheeler parking, Subway

as alternative option for pedestrian crossing. CSML/PMC has given the clarifications for the

issues/observations raised by the engineering staff. Followed by the discussion GIZ also

made a presentation on Street design which includes Re-organization of under-utilized

streets and promotion of NMT & Public Transport.

b) Open Spaces and Tourism Projects

Following projects were discussed during the Meeting:

a) Improvements to Marine Drive walkway

b) Vasco Square at Fort Kochi

c) Open Air Theatre at Fort Kochi

Page 27: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 27 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

d) Parks improvement

e) Fort Kochi Beach upgradation

f) Museums

g) Public walkway at Mattancherry

c) Canal Projects

The 4 Restoration of Canal project were discussed which includes Cleaning and

maintaining water quality, Side wall development urban design aspects along the canal

stretch. The Officials informed that in West Kochi, Calvathy-Rameshwaram Canal work on

desilting & side wall protection has been taken up as part of AMRUT also Restoration of

Calvathy-Rameshwaram & Mullassery canal within ABD alone will not be suffice. They

suggested to integrate the work to be undertaken under AMRUT funds for Calvathy-

Rameshwaram canal.

d) Market projects

Following projects were discussed in the Meeting

a) Ernakulam market development

b) Broadway street upgradation

e) Housing projects

The projects discussed in the meeting were:

a) Bridges construction

b) Thuruthy colony – 1st Tower

c) Integrated development of Slum housing

d) Beneficiary Led housing schemes

During the discussion, the Official suggested that any Vacant space for new construction/

relocation or slums that can be redeveloped to be considered and discussed further for

redevelopment of slums component also CSML can initiate proposal for construction of 2nd

tower for Thuruthy and independent slum redevelopment of specific slums, once KMC

provides consent and necessary details to proceed with the work.

f) LED streetlight and electrical infrastructure, Solar projects

The Projects discussed were:

a) Smart LED street light

b) Solar project

Engineering wing opined that while replacing existing light fixtures with LED light fixtures

and controllers, Poles may also be replaced and maintain lux level requirements of each

roads. The LED light and pole design to be considered as a whole for efficient design. The

Officials informed that there is leak in Fort Kochi Govt. building found after solar panel

installation which is needs to be rectified.

g) ICT – IC4, ITMS, e-health

Detail discussion regarding ITMS project such as Traffic enforcement and management

through VA signals, Pelican Signals, variable message boards, red light violation were

discussed. It was informed that Traffic management command centre will be at North police

station Telecom - Smart Poles

Page 28: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 28 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

h) Other Projects

Presentations were also made for the IC4, Smart Poles, Cancer block for General Hospital.

The Team Leader clarified the issues raised by the members of Engineering wing and

others. The General Manager concluded the meeting thanking the members attending the

meeting and with the decision to further conduct, sector wise detailed discussion with

concerned officials

Figure 1-12 Meeting with Engineering Staff-KMC

8. Review Meeting for The Road Project:- Development of Smart Road in West

Kochi ABD

The CSML noticed that the contractor has not submitted the general document which was

committed during the Kickoff Meeting. The Contractor committed to submit the PBG on 6th

June 2019 and Agreement signing on 7th June, 2019. The CSML instructed the contractor

to arrange the safety measure as per the contract documents. The CSML instructed the

contractor to start casting precast drains. During the review meeting, the contractor was

informed to mobilize the Key personnel for the project as per tender requirement. Also the

contractor was instructed to start clearing works at KB Jacob Road.

Detailed MoM is attached in the annexure1

Page 29: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 29 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

2 STATUS OF ABD PROJECTS

2.1 STATUS OF ABD PROJECTS

This chapter provides an overview of all 80 projects listed in SCP for ABD. As envisioned

in SCP only part funding is met from Smart Cities mission fund. Remaining projects to be

funded from various sources such as convergence, PPP, CSR, loans etc. The status of

projects under convergence and under SPV are provided below. All costs provided are in

INR lakhs in this section.

Module 1 Water supply

There were total of 14 projects identified under this module with serial number 1.1 to 1.14.

Based on the meetings conducted with Kerala Water Authority in initial phase of the project

it was suggested by the authority that KWA will implement all projects. Therefore, these

projects are categorized as convergence projects. In the Stakeholder’s meeting, KWA has

requested to take up Smart Meter project for selected area as pilot basis. Hence only one

project Smart Water Meter project is under scope of SPV implementation. The project scope

is under discussion with KWA. It has been noted that under AMRUT RainWater Harvesting

project has been taken up.

1.1 Karuvelipady Pump house – Pumping augmentation

S. No

Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.1 Karuvelipady Pump house – Pumping augmentation

100

To be taken up by KWA only after the sump and pump house/pumping mains in Karuvelipady is completed under AMRUT scheme and TS committee constituted. The AMRUT work will be completed within 15 months

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.2 West Kochi - Extension of pipelines from Maradu to Island to be extended to

West Kochi to supply 12 MLD

S. No Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.2

West Kochi - Extension of pipelines from Maradu to Island to be extended to West Kochi to supply 12 MLD

55

30

Taken up under state plan and the works are completed. Work Completed. Total Financial Progress: Rs 27.00 lakh

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list. The KWA has reported that the project has been completed.

Page 30: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 30 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

1.3 West Kochi - Replacement of pipelines from Perumanoor to Thevara and

Thoppumpady bridge to Karuvelipady

S. No Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.3

West Kochi - Replacement of pipe lines from Perumanoor to Thevara and Thoppumpady bridge to Karuvelipady

1100

448

The reach from Thoppumpady bridge to Karuvekipady is taken up under state plan and the works are completed. Due to Road cutting issues, the reach from Perumanoor to Thevara has not been taken up by KWA. Work order issued for Rs 448.00 Work Completed. Total Financial Progress: Rs 365.00 lakh

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.4 West Kochi - Dedicated pumping main

S. No

Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.4 West Kochi - Dedicated pumping main

350

Pumping main from Karuvelipadi pump house to Kovampadam OHT will be taken up under AMRUT and the works have been awarded during Feb 2018. The work will be completed within 15 months. Work under implementation.

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5

million litres

S. No Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5 million litres

800 288

Taken up under AMRUT. Work awarded on Feb 2018. 36% physical progress has been made. Financial Progress: 112.00 lakh

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.6 West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort

Kochi and Koovapadam)

Page 31: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 31 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.6

West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort Kochi and Koovapadam)

75

Will be included in 24 X 7 water supply proposal for which KWA is preparing document

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes

including Road cutting charges

S. No

Proposed interventions SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes including Road cutting charges

3500

Will be included in 24 X 7 water supply proposal for which KWA is preparing document

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.8 West Kochi - Replacement of Household connections (last mile) for across

10,000 HSCs with Smart Metering and isolation valves

S. No

Proposed interventions SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.8

West Kochi - Replacement of Household connections (last mile) for across 10,000 HSCs with Smart Metering and isolation valves

2500

Will be included in 24 X 7 water supply proposal for which KWA is preparing document

This project has been classified as convergence project as the project in being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading

S. No

Proposed interventions SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading

100 Will be included in 24 X 7 water

supply proposal for which KWA is preparing document

This project has been classified as convergence project as the project in being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

Page 32: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 32 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

1.10 Mainland - Rider line for increased water supply

S. No

Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.10 Mainland - Rider line for increased water supply

1000

223 KWA has been taken up this project. Work order issued for Rs 223 lakh. Pipelines have been supplied. Road cutting sanction yet to obtain.

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near

Ernakulam Ground

S. No

Proposed interventions SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near Ernakulam Ground

300

Will be included in 24 X 7 water supply proposal for which KWA is preparing document

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.12 Replacement of connections (last mile) for across 10,000 HSCs (Commercial

and Domestic) with Smart Metering and isolation valves- Mainland

S. No

REVISED Name of Project SCP

Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

1.12

Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves

Replacement of connections (last mile) for across HSCs (Commercial and Domestic) with Smart Metering and isolation valves for selected Area

2000 100

Project scope for project being finalised in consultation with KWA. CSML to fix a meeting with KWA to finalise scope. Also issue a letter in this regard..

In the Stakeholders meeting held on 19th September 2018 with Chief Engineer, KWA, it is

decided that the Smart Water Meter project for selected area will be taken up as on pilot

basis. A detail presentation was made regarding the various modules and the technologies

involved in Smart Water Management to KWA. The balance work of Smart Water Meter for

ABD will be taken up after the implementation of Pilot project.

1.13 Mainland - Bulk Meters and Isolation valves with remote meter reading

Page 33: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 33 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions SCP Cost

Clubbed / Segregated/

Estimated Cost

Remarks

1.13 Mainland - Bulk Meters and Isolation valves with remote meter reading

150 Will be included in 24 X 7 water

supply proposal for which KWA is preparing document

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list.

1.14 General - Rainwater structures in ~5000 households

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/

Estimated Cost Remarks

1.14

General - Rainwater structures in ~5000 households

Rainwater harvesting structures in 13 Govt. buildings

1125 75

Renamed due to Scope change. KMC and other stakeholders suggested that the project may be done for Govt buildings instead of households Later it was found that RWH project has been implemented by KWA.

PAN City Project- 24x7 Water Supply

S. No

Proposed interventions

SCP Cost

Clubbed / Segregated/

Estimated Cost Remarks

24 X 7 WATER SUPPLY

62100

Being taken up by KWA. Has been included in 24 X 7 water supply proposal for which KWA has submitted a concept paper. The funding is yet to be decided (ADB / KIIFB) Detailed Project Report under progress.

This project has been classified as convergence project as the project is being

implemented by KWA. CSML/PMC will continue taking status from KWA regarding the

progress made for the project as project is part of overall projects identified under SCP

project list. However, it is being proposed by MoHUA that as 24x7 is a huge project and its

implementation timelines will not match Smart City timelines hence same may be removed

from central MIS.

Module 2 UGSS

There were total of 3 projects identified under this module with serial number 2.1 to 2.3.

Based on the meetings conducted with Kerala Water Authority and Kochi Municipal

Corporation 2 projects are under scope of SPV implementation. Further the project

“Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)”

has been segregated in two projects. The project “Improvement to Elamkulam STP” has

been taken up by KWA.

Page 34: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 34 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

2.1

Decentralized Treatment and collection system for West Kochi under ADB (Mundamveli)

Sewerage System for West Kochi

2200

15450

The Sub Module 2.1 and 2.2 will be planned together as the small-bore sewer for on-site sanitation is part of sewer collection system. These two components will not be separated as two different works for design as well as execution. The project under the module would focus on ward nos. from 1 to 5 of Kochi Corporation Tender has been floated

2.2

Small bore sewer/ Vacuum system for onsite sanitation - Includes storage facility for treated water use for landscaping

11000

2.3

Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)

Improvements to sewer collection system for Mainland

7000

5700

The module 2.3 involves mainly sewer collection system at mainland (central Kochi) and Improvements to Elamkulam STP. Under AMRUT fund, Project Tendered. CSML to write letter to KWA & KMC for confirmation on scope area to be covered for provision of Sewer lines Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. With limited SCM duration. Confirmation on scope needs to be expedited.

Improvement to Elamkulam STP

1370

Module 3 NMT Roads and Pedestrianized areas

There were total of 4 projects identified under this module with serial number 3.1 to 3.4

Three projects Relaying of roads, Standard Footpaths including signages and Restoration/

Rehabilitation of Storm water drains in the proposed area have been combined as these

components are part of right of way of the road itself and for coordinated implementation

need to be done together.

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/

Estimated Cost Remarks

3.1 Relaying of roads Development of Other Roads in Ernakulam under Smart City Mission

4200

4360 LoA issued on 9th April, 2019 to M/s Deens Group

3.2 Standard Footpaths including signages

Development of Other Roads in West Kochi under Smart City Mission

2853

6020 Project re-tendered. 3.3 Restoration/

Rehabilitation of Stormwater drains in the proposed area

2360

Page 35: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 35 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/

Estimated Cost Remarks

3.4 MLCP and Commercial complex at Kacheripady

MLCP at Kacheripady

5000 615

No bids received. Project to be re tendered

MLCP at GCDA land at Marine Drive

10.0

Project scope to be confirmed by stakeholder. Post that DPR preparation will be taken up

MLCP at KTDC complex at Maneka

7.0

Project scope to be confirmed by stakeholder. Post that DPR preparation will be taken up

Smart Parking solutions at various location in ABD

1.90 DPR under preparation

Scope – Access Roads

The existing internal roads are to be developed as Access roads between the smart roads

for improved traffic flow within the ABD area. The scope of works in Access roads are mainly

but not limited to upgradation of drainage facilities by construction of new drains, Irish drains

and restoration of existing drains as per site requirements, provision of footpath (as per

standards and space available) and surface improvement wherever required. The CSML

intends to develop 39 Roads in Ernakulam central area (14.439 Km) and 87 Roads in Fort

Kochi (30.141 Km). Landscape, hardscape and cycle lane. The various components

included (but not limited to) in this area – wide footpaths, landscape corridor with trees, bus

bays, on-street parking, road markings, median, improved junctions, table tops, universal

accessible design by introduction of ramps, benches and planting beds, etc.

Progress of the Project:

2.1.1 DEVELOPMENT OF OTHER ROADS IN ERNAKULAM

Project Profile/ Components:

Projects aims at providing Seamless mobility where possible and Safe pedestrian

movement.

❖ Other roads covered:

• Ernakulam – 40 roads – 13.32 km

Other Roads project involves construction of:

❖ Drainage – Reconstruction/repair of drain on both sides of roads as per

requirements

❖ Concrete Trench –as per availability of space by the side of drainage to

accommodate utilities.

❖ Footpath- Both side of roads 1 to 1.5m wide footpath.

❖ Landscaping – As per availability of space

❖ Streetlight – Foundation

❖ Provision of HDPE duct

❖ Surface Laying –

• BM BC road as per requirements.

Page 36: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 36 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

• Interlocking tiles proposed for roads with width less than 7m (as per

requirements)

Project cost: INR 43.60 Crores Duration: 15 Months

Project Start date: 09 April 2019 End date (expected): 09 July 2019

Contractor: M/s Deens Group

Current status:

❖ Surveys started

❖ Survey in Progress at Narakathara Road, Convent Road and Sheshadri Road

Any Challenges to be discussed:

❖ Handing over roads by the stakeholders to the Contractor.

Module 4 Main roads

There were total of 5 projects identified under this module related to roads with serial

number 4.1 to 4.3. Projects 4.4 & 4.5 will be separate project.

S. No

Proposed interventions REVISED Name

of Project SCP Cost

Clubbed /

Segregated/

Estimated Cost

Remarks

4.1 World class Arterial roads -- KB Jacob & Amravati Road/ Bellar Road in West/ -- Avenue, MG Rd, DH Rd, Banerjee Rd, Abraham Madamakkal road in Central city

Development of Smart Roads Ernakulam

5,287

6153

LoA issued on 9th April, 2019 to M/s Deens Group in Consortium with Deens Constructions

4.2 Relaying of roads, Aesthetic and improved Urban design Pedestrian facilities with Street furniture, Boulevards and urban greenery

Development of Smart Roads in West Kochi

1650

3031 LoA issued on 9th April, 2019 to M/s ABC Builders

4.3 Utility ducting for SWD, Water supply, Sewerage, OFC etc

3300

4.4 Signages, Junction improvement with Intelligent Traffic management

Signages 97

240

Segregated as signages & ITMS have separate projects. Junction improvement taken up under Roads combined project. DPR has been submitted for Approval.

Integrated Traffic Management System

2690

Contract Agreement signed on 16th May, 2019. Work commenced

4.5 Escalator FOBs 240

DPR under preparation for FOBs in Thuruthy

Smart Roads: Construction, operation and maintenance of Smart Roads

CSML intends to develop 5 roads in Ernakulam central area (4.9 Km) and 5 Roads in west

Kochi (3.2 Km) as smart roads. The scope of work includes developing the existing roads

mentioned above by upgradation and augmentation of foot path, provision of cycle lanes ,

Page 37: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 37 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

providing Road Markings, Street Furniture, Bus bays, Street Landscaping works, utility

trenching/ducting works, Construction of new drains and restoration of existing drains as

per site requirements, shifting of utilities to underground trenches, foundation for street light

poles, monopoles and smart poles, installation of compact substations, individual

connections through feeder pillars, smart elements and other Miscellaneous works along

with operation maintenance of landscaping works.

Discussions have been held with Kerala Water Authority (KWA) and it has been requested

that any related work to the 24x7 water supply project must be in sync with Roads project.

Progress of the projects:

2.1.2 DEVELOPMENT OF SMART ROADS IN ERNAKULAM

Project Profile/ Components:

Roads covered

❖ Ernakulam Mainland: 5.41 Km Smart roads.

1. Banerji Road 0.91 km

2. Shanmugham Road & Park Avenue Road 2.36 km

3. Durbar Hall Road 0.53 km

4. Abraham Madamakkal Road 1.11 km

5. Swami Chinmayananda Road & South Railway Station Road 0.50 km

Projects aims are creating equitable organised safer roads space for all road users.

Smart Roads project involves construction of:

❖ Drainage – Reconstruction of drain on both sides of roads as per design for the free

flow of stormwater, to avoid water stagnation

❖ Construction of underground utility trench - Concrete or HDPE for all electrical cables,

data cables and future provision for water supply distribution line.

❖ Footpath – On either side of the road, there will be footpath of 2m to 3m width, for

safe and comfortable movement of pedestrians and vulnerable road users.

❖ Cycle lane – dedicated cycle lane in Shanmugham Road, Abraham Madamakkal

Road and Swami Chinmayananda Road & South Railway Station Road on either side.

Cycle lane marked on the carriage way of Banerji Road and D.H.Road.

❖ Streetlight provision– Foundation for Street light poles.

❖ Landscaping – proposed in Abraham Madamakkal road, Shanmugham Road, Durbar

Hall Road and Swami Chinmayananda Road & South Railway Station Road.

❖ Bus bays – Shanmugham Road and Abraham Madamakkal Road

❖ Hawker Zone – Shanmugham Road

❖ Median- Shanmugham Road, Abraham Madamakkal Road and Banerji Road

Page 38: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 38 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Surface Laying – road formation – road levelling by WMM and BM BC as per design

requirements.

❖ Electrical/Street Light Components – New HT/LT Cables, providing New Smart

transformers, compact substations, RMU, feeder pillars, smart metering

❖ Provision of HDPE Under Ground Utility duct.

Project cost: INR 61.53 Crores Duration: 15 Months

Project Start date: 09 April 2019 End date (expected): 09 July 2019

Contractor: M/s Deens Group in Consortium with Deens Constructions

Current status:

❖ Contractor’s Temporary Site office (Container) established near the Proposed Bridge

in AM Road

❖ Location for Plant and Casting Yard identified; site clearance and development work

in progress. PMC made a visit to the location and was found suitable for establishing

the facilities.

❖ Aggregate Source at Kottapady was visited and the contractor was asked to submit

the quality reports of various aggregates from an NABL accredited lab. The contractor

is yet to submit the details.

❖ Contractor has submitted the implementation schedule for Smart roads. The shortfalls

of the submitted schedule was communicated to the contractor and a revised

schedule is to be submitted.

Piling

❖ Started mobilization of Sub Contractor and Equipment for Piling works

❖ Location for test pile identified and installation to be started.

❖ Area clearance completed including shifting of electric pole and cable.

❖ GAD and detailed drawings given to Contractor for setting out and starting piling

works

❖ Fabrication of liner and reinforcement cage commenced.

Survey

❖ Topo survey completed and initial levels taken at 10m interval for Abraham

Madamakkal Road and drawings including cross sections submitted.

❖ Topo Survey completed and drawings submitted for Jos Junction to Chittoor Junction

road. The GAD for the same is prepared.

❖ Topo Survey works for other roads in progress.

Material Selection and Approval

❖ Kerb stone and Paver tile samples submitted by Contractor was approved by PMC’s

Architect and are send for testing at NABL Accredited lab. Reports for Kerb was

received and the item was approved.

Page 39: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 39 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Mix design from RMC Plant till commissioning of contractor’s batching plant for Piling

expected from Contractor by 24th June 2019.

❖ Barricading board of approved size and design ready and 15nos brought to site.

❖ Random checking of supplied kerb stone; submitted on 15/06/2019 (to be tested at

GCDA lab)

Challenges to be discussed:

❖ Underground and overhead utilities (KSEB, KWA & BSNL)

❖ Handing over roads by the stakeholders to the Contractor.

Location map

Figure 2-1 Location Map- Smart Road Ernakulam

2.1.3 DEVELOPMENT OF SMART ROADS IN WEST KOCHI

Page 40: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 40 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Project Profile/ Components:

Roads covered

❖ Fort Kochi & Mattancherry (West Kochi) 3.24 Km of Smart roads

❖ KB Jacob Road 1.08 km

❖ Bellar Road & River road 0.44 km

❖ Amaravathi Road & T M Muhammed Road 1.08 km

❖ Calvathy Road 0.64 km

Projects aims are creating equitable organised safer roads space for all road users.

Smart Roads project involves construction of:

❖ Drainage – Reconstruction of drain on both sides of roads as per design for the free

flow of stormwater, to avoid water stagnation

❖ Construction of underground utility trench - Concrete or HDPE for all electrical cables,

data cables and future provision for water supply distribution line.

❖ Footpath – On either side of the road, there will be footpath of 2m to 3m width, for

safe and comfortable movement of pedestrians and vulnerable road users.

❖ Cycle lane – dedicated cycle lane on one side of K.B .Jacob Road.

❖ Streetlight provision– Foundation for Street light poles.

❖ Landscaping – proposed in K.B.Jacob Road.

❖ Surface Laying – road formation – road levelling by WMM and BM, BC as per design

requirements.

❖ Electrical/Street Light Components – New HT/LT Cables, providing New Smart

transformers, compact substations, RMU, feeder pillars, smart metering

❖ Provision of HDPE Under Ground Utility duct.

Project cost: INR 30.31 Crores Duration: 15 Months

Project Start date: 09 April 2019 End date (expected): 09 July 2019

Contractor: M/s ABC Builders

Current status:

❖ Topo Survey works completed

❖ Center line marking completed at KB Jacob Road

❖ Mix design submitted for concrete from RMC Plan. The tests were witnessed and

were found ok and hence approved.

❖ Site mobilization under progress

❖ Started desilting of drains in KB Jacob road (20.06.2019)

Challenges to be discussed:

❖ Underground and overhead utilities (KSEB, KWA & BSNL)

Page 41: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 41 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Handing over roads by the stakeholders to the Contractor.

Location map

Figure 2-2 Smart Road - West Kochi

2.1.4 INTELLIGENT TRAFFIC MANAGEMENT SYSTEM(ITMS)

Project Profile:

❖ ITMS project was reconstituted as a pan city project as it would be effective only if it

was focused to a larger network than just few junctions and locations ABD.

❖ Based on the reconnaissance surveys, traffic data and discussions with the traffic

police, the locations were identified

❖ ITMS consists of several electronic equipment that work towards improving safety,

enforcement and traffic management

❖ ITMS can be segmented into 2 broad elements - Enforcement, and Traffic

Management.

❖ Enforcement deals with violation detection and fining

❖ Traffic Management deals with flow detection and optimization of signal controls.

❖ The other benefits that would accrue out of ITMS includes incident management and

better Information Dissemination.

❖ The Scope of Work Includes providing, installation, testing and Commissioning of

ITMS Components and setting up the Traffic Control center.

❖ Components

• ITMS

• Vehicle Actuated Signals

• Pelican Signals

• Variable Message Boards with Gantry

Page 42: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 42 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

• Red Light Violation System

• IP based PTZ and Traffic violation cameras with night vision

• Traffic Management Center (TMC components are as follows)

- Receiving real time information/data from VA traffic feeds including storage of

the same

- Provide control of traffic signal controller from the Control Center to enable

corridor management/ATCS overrides

- Processing of ANPR camera images

- Traffic Surveillance camera – Beaming live images to allow for manual

capture of violations,

- A video wall for observation and discussion of traffic management, violations

and incidents for appropriate actions

- Provide controls for the PTZ camera’s

- RLVD traffic violation data processing and storage

- VMS to give real time traffic information to public

- Run the ATCS software to optimize traffic flow

- Challaning of Violations

Project cost: INR 26.90 Crores Duration: 12 Months

Project Start date: 18 May 2019 End date (expected, excl. O&M): 17 May

2020

Contractor: M/s KELTRON

Current status:

❖ Agreement Signed, Bank Guarantee received, kick off meeting and Solution

document submitted on 18th May 2019

❖ Joint Site visit along with KELTRON officials and CSML PMC officials Completed on

27th and 28th May 2019.

❖ Along with KELTRON team, PMC where present during the site visit.

❖ Road cutting locations, Signal pole locations, VMS locations, Control box locations

and Camera pole locations, Pelican Signal locations, have been identified.

❖ Based on the site visit and observations a revised solution document will be submitted

KELTRON.

❖ Once the solution document is received, a detailed site inspection along with

respective stakeholders will be carried out once again

❖ Informed about Jose Jn to South Railway Station Smart road work to Keltron. Asked

to provide HDPE ducting for proposed Traffic Signal pole at Jos Jn. Keltron Kochi

Page 43: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 43 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

office (civil works) came and did the site inspection. Informed to provide the HDPE

duct to Road contractor before the paver works.

Any Issues/ Challenges to be discussed:

❖ Timely permissions from relevant stakeholders for ITMS components installation

which will require tasks such as road cutting.

Project components

Module 5 Energy Supply

There were total of 16 projects identified under this module with serial number 5.1 to 5.16.

Based on the meetings conducted with KMC, KSEB and PWD these all projects have been

combined into one as it will be implemented along with Smart Roads.

S. No

Proposed interventions REVISED Name of

Project SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

5.1 – 5.16

Compact Secondary Substation (990 KVA) Underground HT Line Underground LT Line LT UG for Streetlights AMR Metering - Single phase AMR Metering - Three phase AMR Metering - HT RMU with Remote terminal units Distribution panel board Installation of feeder pillars Underground Cabling - 11 KV LT UG Cabling Installation of Transformers (Compact Sub-stations) Installation of Ring Main Units with Remote terminal units

Development of Electrical Infrastructure in ABD Area

12,253

6349

All projects have been clubbed The project has been re-tendered. Technical Bid evaluation is completed and submitted to the CSML along with Shortfall letter.

Page 44: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 44 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions REVISED Name of

Project SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

Smart Meters (AMR) Installation of feeder pillars

The scope of projects is to implement System Improvement & Augmentation Scheme for

existing Electrical Network in various Smart Road area. The contractor’s scope of work

includes but not limited to: Survey, network design, manufacturing, Working testing,

inspection, packing, dispatching, loading, unloading and storage at site, transit/storage and

construction insurance, assembly, erection, civil structural work, complete pre-

commissioning checks, testing & commissioning at site, obtaining statutory clearance &

certification from State Electrical Inspectorate, Kerala State Electricity Board, Kochi

Municipal Corporation etc. and handing over to the Owner after satisfactory commissioning

of complete augmentation of existing Electrical Network in Cochin Smart Mission Limited

Project ABD.

Module 6 Energy efficiency

There were total of 2 projects identified under this module with serial number 6.1 to 6.2.

Based on the meetings conducted with Kerala State Electricity Board and Kochi Municipal

Corporation all projects are under scope of SPV implementation.

S. No

Proposed interventions REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

6.1 Solar based LED with Smart poles

Smart LED Lights in ABD area

1,250 3230 Segregated as lighting & Telecom projects Technical Bid evaluation completed and submitted to the CSML. There are shortfalls in the document submitted.

Intelligent Street Poles in Kochi

30160 (PPP) DPR submitted Technical Bid evaluation under progress

6.2 Solar panels in Households and Institutions - Grid connected

Solar panels in Govt. buildings

1,758 570 Work awarded on Nomination basis to BHEL. Work under implementation.

Solar panels in public places

1178 Project proposed to be taken up along with Canal project.

In module 6: Solar based LED with Smart poles has been mentioned as one single project.

Smart Pole & Solar LED are two different entities hence should be considered as two

different projects. Smart poles are proposed to be implemented as a PPP project.

Progress of the Projects

2.1.5 SOLAR ROOFTOP PROJECT IMPLEMENTATION PROGRESS

The Contract agreement for the implementation of the project has signed on 24th

September 2018. The BHEL started site feasibility study and other paper works in the month

Page 45: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 45 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

of December 2018. Clearance for installation of Solar panels has been given to BHEL for

26 buildings. The total capacity of solar panels in these buildings is 1010 KWp.

Project Profile/ Components:

❖ 26 government buildings selected pan city, for implementation of Solar Roof Top

project.

❖ Design, development and supply of all components of the SPV power system

❖ Supply, transportation, unloading, installation, testing and commissioning of 1000

KWp grid connected solar roof system in various government buildings in Kochi

Municipality. The buildings are either with flat roof concrete structure or slope roof

GI structure.

❖ The scope includes minor strengthening of slope roof structure at additional cost to

install solar roof top system and access to roof top for maintenance.

❖ All clearance / approval required from KSEB / Electrical inspectorate or any

statutory Authorities shall be obtained by the contractor.

❖ Installation and commissioning of SPV Power system up to AC distribution board

along with Net metering with necessary arrangement for integration grid and

protection during absence of grid supply.

❖ Five years Warrantee from handing over of the Solar Roof Top System.

❖ Remote Operation and Maintenance including periodic cleaning of modules, and

with quarterly visit for five years from the date of handing over of the solar Roof

System.

❖ Training of the staffs of client/owner.

Project cost: INR 5.70 Crores Duration: 6 months + 2 months EOT

Project Start date: 24 September 2018 End date (expected, excl. O&M): 31

August 2019

Contractor: M/s BHEL

Current status:

❖ M/s BHEL has completed installation of 670KWp solar panels out of total 1000KWp.

Balance installation works are under progress.

❖ Liaising works with KSEBL and Electrical Inspectorate under progress for the

commissioning of the completed facilities

Any Issues/ Challenges to be discussed:

❖ Supply of balance materials like 200KWp inverter, 330KWp mounting structure etc

and Shortage of work force by BHEL.

❖ Contract period of 6 months and EOT of 2 months completed on 24/05/2019. BHEL

requested EOT upto 31/08/ 2019.

❖ Approval for Dwg and site inspection from Electrical Inspectorate (EI).

Page 46: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 46 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Ladder with openable door installation for maintenance and EI inspection.

❖ Additional DB shall be installed for conversion of single phase to three phase

system for Paramara and Perumbotta Ground Buildings as a variation item.

Permanent electrical connection to be obtained by Excise Department for

completion of Solar System.

❖ Inadequate site supervision/ Frequent replacement of Site in charge by BHEL.

❖ For 14 buildings, the connected load is less than installed Solar capacity. Hence

Service wire need to be changed as extra item.

Way forward

❖ BHEL to increase the staff strength of the implementation team.

❖ BHEL to do rigorous follow-up with EI.

❖ Presence of BHEL’s experienced Site in charge till the completion of the Project

❖ Monthly project review Meeting between senior management team of BHEL with

CSML and PMC.

❖ EOT may be approved considering approvals required from EI.

Project photographs

Figure 2-3Installation of Solar Panel at General Hospital

Figure 2-4Solar Panel installation Work at Fire station, Gandhinagar

Figure 2-5 Panel Installation of Town Hall

Page 47: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 47 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Figure 2-6Panel Installation of Central Office, KSEB

Figure 2-7Panel Installation of Central Office, KSEB

Figure 2-8Govt. High School, Edapally Figure 2-9 Court Complex Ernakulam

Detail progress at each location is attached as annexure 4.

Module 7 Solid waste and Sanitation

There were total of 4 projects identified under this module with serial number 7.1 to 7.4.

Based on the meetings conducted with Kochi Municipal Corporation all projects are under

scope of CSML implementation. Only one project was proposed to be dropped by KMC as

it was not successful in earlier attempts made by Govt. Authorities.

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

7.1 Equipment including Smart Street sweepers/ GPS enabled Vehicles/compactors

600 Segregated

Supply, Operation and Maintenance of Portable Compactor for Secondary Storage & Transportation of Solid Waste

440 Tender Cancelled due to technical disqualification of bidder

Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West

100 DPR submitted KMC concurrence awaited to proceed with tendering

Page 48: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 48 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

Kochi & Ernakulam in ABD Area

Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area

320 Tender Cancelled due to technical disqualification of bidder

7.2 Bio-composting in all Government institutions

5 Dropped as based on previous experience KMC proposed not to take up the listed project as it was implemented at few locations and was not successful. CSML to request for formal confirmation from KMC

7.3 Household segregated bins for Organic and inorganic wastes

74 67 Bid Evaluation completed. LOA issued to M/s Nilkamal on 8th May, 2019

7.4 Public toilets with Fit-in Treatment facility for Decentralized STP in West Kochi

Renovation and Upgradation of existing Public Toilet Facilities in ABD area

10 180 DPR Submitted. Tender has been floated. Technical Bid evaluation under progress.

Progress of the Projects

2.1.6 HOUSEHOLD BINS AND BINS IN PUBLIC PLACES

Project Profile/ Components:

Project includes procurement & supply of bins by the successful vendor for households

and public spaces.

• Stainless steel bins for public spaces - 75

• Total number of beneficiaries - 20081

• Number of bins per beneficiary - 2

• Material of bins - HM HDPE

❖ Intermediate storage of receipt bins by KMC

❖ Distribution of bins shall take place by the KMC in consultation with ward sanitation

committee which includes ward councillor, junior health inspectors in coordination

with RWA & Kudumbashree

❖ Installation & fixation of street litter bins at reasonable distance of 40-80 m,

depending upon the footfall density across prominent public places of Fort-Kochi,

Parks, Marine Drive walkway for use by pedestrians

Page 49: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 49 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Street Litter Bins shall be in a pair of 2 – with proper display information in both

local and regional language, easily rotatable with each of then having capacity of

60 litres

Project cost: INR 0.67 Crores Duration: 3 Months

Project Start date: 06 May 2019 End date (expected): 02 October 2019

Contractor: M/s Nilkamal Limited

Current status:

❖ Household Bin sample submitted

❖ Contractor to start supply of bins with changes proposed.

Any Challenges to be discussed:

❖ KMC to share final list of beneficiaries

❖ KMC to provide location for Storage of bins

❖ Distribution of bins shall take place by the KMC in consultation with ward sanitation

committee which includes ward councilor, junior health inspectors in coordination

with RWA & Kudumbashree

❖ Household Bin distribution to take place in ward sabha meetings.

❖ Designated employee from KMC to confirm location of street bins in parks and

beach.

Photograph

Figure 2-10 Household Bins

Module 8 Parks and Open spaces

There were total of 4 projects identified under this module with serial number 8.1 to 8.4.

Based on the meetings conducted with Kochi Municipal Corporation, Tourism Department

and forest Department all projects are under scope of SPV implementation except 8.1 which

is already taken up for implementation by Tourism Dept.

Page 50: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 50 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Remarks

8.1 Upgradation of Nehru Park

200

Convergence - project undertaken by Tourism Department. The project is under implementation by Tourism Department.

8.2 Development of open spaces

30 960 Feasibility report submitted on 26th

March 2019

8.3

Development of open spaces and playgrounds - Maharajas Ground

500

Feasibility report under preparation.

8.4

Marine Drive walkway phase I

90

710 Feasibility Report is submitted on 3rd November 2018. Revised DPR has been submitted on 4th Feb and 28th March 2019 Tender has been issued. Technical Bid evaluation under progress.

Marine Drive walkway phase II

690 Combined DPR has been submitted on 8th November 2018. For Phase II DPR will be revised after stakeholder’s consultation.

8.5 Mangalavanam Eco-restoration project

100 Proposed concept shared with

KMC & Forest Dept. Concurrence awaited on concept proposed

Module 9 Canal Restoration

There were total of 4 projects identified under this module with serial number 9.1 to 9.4.

Based on the meetings conducted with Kochi Municipal Corporation all projects are under

scope of SPV implementation.

S. No

Proposed interventions REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Status

9.1 Restoration of Mullassery canal - including linking of standardized area drains

100 Feasibility report submitted on 2nd March, 2019

9.2 Restoration of Market canal - Walkways and Market square around the canal pond, Solar panelled roofs, LED Lighting, Light posts

500 Feasibility report submitted on 2nd March, 2019

9.3 Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features

2,000 Feasibility report submitted on 2nd March 2019

9.4 Restoration of Rameswaram-Kalvathy canal - Up to Cochin college – Walkways and Linking the Canal Bank Road

1,500

Based on combined stakeholder meeting held on 28 May 2019 for Canal project it has been

suggested by all stakeholders (KWA, KMC, Irrigation dept, Water metro) that entre stretch

Page 51: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 51 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

of Canal may be taken for development. CSML to conduct surveys for stretches beyond

ABD and post that Feasibility report to be updated.

Module 10 Urban mobility

There were total of 9 projects identified under this module with serial number 10.1 to 10.9.

Based on the meetings conducted with Kochi Metro Rail Limited and Kochi Municipal

Corporation 5 projects are under scope of SPV implementation and remaining 4 with KMRL

– Water Metro project.

S. No

Proposed interventions REVISED Name of Project

SCP Cost

Estimated Cost

Status

10.1 Water transport infrastructure (around 12 100 Pax boats)

4,200 5600

Convergence - Project under implementation by by Water Metro. Project tendered. Bid evaluation under progress

10.2 Electric Feeders, Bicycle Sharing, Elevated Walkways and Travellators

1,148

Segregated

Electric Feeders

1148 Convergence undertaken by KMRL. Feeders also proposed as part of Broadway Street pedestrianisation.

Bicycle Sharing

1000 (PPP) Locations approved by KMC. Contract to be signed

Elevated Walkways and Travellators

Part of Ernakulam market project

10.3 Walkway from Ekm Jetty to Metro station

900

470 Under implementation

10.4 Jetty improvement

800

4000

Convergence - Being undertaken by Water Metro. Bid evaluation under progress

10.5 Property development along jetties

720

10.6 Boatyard and Command & Control Centre

Boatyard

2,000

10.7 Dredging cost Marina 1,000 2000 Concept Stage

10.8

Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

60

Prateeksha has been given the project of bus shelters on a 15-year lease (duration to be confirmed by stakeholder) for PWD roads. West Kochi bus shelters have not been covered. In West Kochi bus shelters are sponsored for improvement by various stakeholders. Currently the bus shelters are not wifi enabled. In order to develop these as smart bus shelters CSML may write to relevant authorities

Page 52: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 52 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions REVISED Name of Project

SCP Cost

Estimated Cost

Status

for confirmation on project scope/call for combined meeting.

10.9 Standard Wifi Enabled Bus Stands with Commercial space development

300

Combined stakeholder meeting & letter to stakeholders needed to confirm the scope of project to be taken up under Smart City

Progress of the Project

2.1.7 PUBLIC BIKE SHARING IMPLEMENTATION PROGRESS

Project Profile/ Components:

Cochin Smart City Mission Limited (CSML) along with KMRL are implementing the Kochi

Bicycle Sharing Scheme project in ABD (Area Based Development extent) and 2 km on

either side of the metro alignment from Aluva to Petta along a 25.6 km stretch. Capital

Cost and Operation Cost of the project will be borne by the service provider. Operations

contract will be issued to service providers for a period of 3 years. During this period

Service provider is entitled to collect Fare box revenue and Advertisement Revenue from

the given space for the system. Project to be implemented in two phases. Phase I

locations for docking stations identified

❖ Dock based or dock less system

❖ 1000 cycles

❖ Minimum 50 docking stations

❖ GPS Enabled Bicycles

❖ App based bicycle identification and management.

❖ Towing Vehicles for Redistribution

❖ Maintenance Center

Project cost: INR 10.00 Crores (PPP) Duration: 3 months

Project Start date: 14 March 2019 End date (expected, excl. O&M): 14

November 2019

Contractor: M/s Hero Youon Pvt. Ltd. (JV of Hero Cycles Ltd & Youon Technology

Pvt. Ltd.)

Current status:

❖ 15 docking locations identified & approved by KMC. Of these 13 locations are in

West Kochi and 3 in mainland

❖ Hexi has supplied 200 cycles.

❖ Prefabrication of docking stations is in progress

Page 53: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 53 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ 2nd Phase 206 Locations approved by KMC. Detailed location Inspection under

progress. Phase 2 out of 206 locations 100 locations detailed inspection has been

completed by Hexi

Any Issues/ Challenges to be discussed:

❖ Approval and finalisation of docking stations

❖ Implementation duration was expected to be 3 months. However, considering all

approvals required project is expected to complete by November 2019

❖ Integration with ongoing projects.

Location map/ project maps/project design/ pictures

Page 54: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 54 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Figure 2-11PBS locations (Base map by PMC and locations plotted by Smart-SUT)

Module 11 Housing

There were total of 3 projects identified under this module with serial number 11.1 to 11.3.

Based on the meetings conducted with Kochi Municipal Corporation and other stakeholders

below mentioned projects are under scope of SPV implementation. KMC has proposed to

take up some other project in place of Upgradation of infrastructure in Housing through

Credit linked schemes. The fund available under housing module is INR 100 Crores.

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Revised Estimated

Cost

Status

11.1

Integrated redevelopment of Slum housing

14,140

4685 Awaiting Confirmation for scope of work from KMC KMC to provide final list of beneficiaries and slums to be taken up under SCM Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited by KMC.

11.2

Upgradation of infrastructure in Housing through Credit linked schemes

Beneficiary Led Housing

2,435 1300 KMC proposing to revise the scope of component to “Beneficiary Led housing”.

Page 55: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 55 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No

Proposed interventions

REVISED Name of Project

SCP Cost

Revised Estimated

Cost

Status

CSML has allocated Rs 13 cr. out of which Rs 1.02 Cr has been disbursed.

11.3

Construction & upgradation of 755 DUs in Thuruthy, Kalvathy & Konchery colony

Construction of first tower at Thuruthy

7,424 2100 As per discussion held on on 26th Dec 2018 for CSML to assist KMC in completing the construction of tower 1 under RAY scheme by Gap funding only. Gap funding to be disbursed by CSML only after KMC provides revised administrative sanction from LSGD and tender out the sewage treatment facilities and waste management

Construction of Second tower at Thuruthy

3500 CSML to write letter to KMC for confirmation on project scope to be taken up under smart City. Project preparation will require time. Minimum 3 months for DPR & Tender preparation. Hence to enable tendering confirmation to be shared at the earliest by KMC along with all data to start design process.

Construction & upgradation Thuruthy, Kalvathy & Konchery colony - Construction of Bridges

515 Feasibility Report Submitted on 27th September 2018 for bridges construction. DPR under preparation

11.4

Construction & upgradation of 755 DUs in Thuruthy, Kalvathy & Konchery colony -KMC

47.91 Convergence – Project Under Implementation by KMC

Module 12 Economy and Employment

There were total of 2 projects identified under this module with serial number 12.1 & 12.2.

Based on the meetings conducted with Kochi Municipal Corporation, KMCC, Market

association and other stakeholders all projects are under scope of SPV implementation.

S. No Proposed interventions

REVISED Name of Project SCP Cost

Estimated Cost

Status

12.1 Broadway Market and Ernakulam market Redevelopment and Mattancherry spice market

11,000

Broadway Street pedestrianisation

1000 Feasibility report submitted on 15th October 2018 DPR Stage. KMC to share list of

Page 56: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 56 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No Proposed interventions

REVISED Name of Project SCP Cost

Estimated Cost

Status

approved licensed hawkers to be accommodated along multi utility zone proposed.

Ernakulam Market Redevelopment

10000 Feasibility report submitted. DPR Stage. KMC to approve initiate R&R asap.

Mattancherry spice market Redevelopment

Segregated - Streetscape improvement covered under road project

12.2 Standard Hawker zones in Fort Kochi

Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"

500 560 Segregated - Feasibility stage. KMC to share list of approved licensed hawkers Hawker zone included as part of Fort Kochi Beach upgradation.

Pedestrianisation of Broadway Street & other improvements: The proposal:

Pedestrianisation of Broadway Street for approx. 500m stretch.

Broadway Street Upgradation proposals proposes for a time bound

Pedestrianization of 500m stretch at an estimated cost of INR 10.0 Crores with other

supporting projects including pick up/drop off facility e-vehicles from Bus stops, metro,

water metro and MLCPs to offer smooth transition from parking to no parking zone.

Project proposal includes Pedestrianization of the Broadway street stretch in a time bound

manner from 12.00 pm to 8.00 pm allowing only E-rickshaw & emergency vehicle

movement. Pedestrian oriented street with partial canopy covering with regulated vehicular

access. Street is proposed as no parking zone.

Assistance required from KMC:

KMC to share final list of eligible hawkers to enable Smart City team to accommodate the

licensed hawkers along multi utility zone with cart size requirement. Approval of traffic

management plan from beneficiaries, Co-ordination with all beneficiaries.

i. Final approved list of hawkers to be shared with smart city team at the earliest to enable

Smart city team to do detailing of the designs that include allocation of hawkers in Multi

utility zone.

ii. KMC to hold public consultation with the shop keepers along Broadway and take formal

approval for the proposed project and finalize design detail such as the canopy and road

design.

Ernakulam Market redevelopment: The proposal

Ernakulam Market redevelopment proposal at an estimated cost of INR 100 Crores was

presented that proposed for development of Market area with a G+3 building, Basement

Page 57: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 57 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

floor for parking, Developing market square in to a Multilevel car parking space, Solid waste

compactor, Banana Auction area, etc and solid waste compactor facilities, widening of an

existing bridge over market canal connecting to the market square and Skywalk.

Assistance required from KMC:

KMC to share final list of eligible shopkeepers with shop size requirement. Suggest on

Transit shelter strategy including confirmation on alternate land for relocation, expenditure

during relocation period, revision of rental rates for new building and negotiations, approval

of revised traffic management plan from beneficiaries, Co-ordination with all beneficiaries.

i. KMC to verify and compile final list of vendors and hawkers and share with smart city

team at the earliest to enable Smart city team to do detailing of the designs

ii. Confirmation for land for transit shelters at the earliest.

iii. KMC to confirm allotment of shops by zoning. Smart city to design accordingly

Figure 2-12 Ernakulam Market Redevelopment – Project Planning

Figure 2-13 Action to be taken prior to Tendering of the project

Page 58: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 58 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Source: PMC

Table 2-1: Action for KMC to enable tendering by end of September 2019

TASK May June July August Sept Oct Nov

Final list of vendors & consultations

Finalization of proposal by CSML

Land for rehabilitation

Agreements with vendors by KMC

Relocation & rehabilitation

Tender by CSML

Site clearance by KMC & handover to CSML

Contract award by CSML

Construction period begins

18 months

Source: PMC

Module 13 Health

There were total of 2 projects identified under this module with serial number 13.1 & 13.2.

Based on the meetings conducted with Kochi Municipal Corporation, DMO and other

keyholders all projects are under scope of SPV implementation and have been segregated

into 4 projects

S. No Proposed interventions REVISED Name of Project

SCP Cost

Estimated Cost

Status

13.1 Scale up of GH into a Super-speciality care centres

Cancer Extension Block, General Hospital.

3,000 2600 (Phase I)

LoA to INKEL has been issued. Negotiation with INKEL in on going for the estimated cost as

Page 59: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 59 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

submitted bu INKEL.

E-health solution for General Hospital

371

Segregated - Revised DPR has been submitted on 7th February. LoA has been issued. to M/s Keltron

13.2 Integrated development of 4 Hospitals in West Kochi - Excellence in Secondary care

Outpatient & Admin block, Fort Kochi taluk Hospital

1,000 465 Revised DPR, Detailed Estimate and Drawings submitted. Tender issued Technical bid evaluation completed

Outpatient & Admin block, Women & Child Hospital, Mattancherry

457 Revised DPR submitted on 13th November 2108. Revised BoQ and drawings have been submitted. Tender issued Technical bid evaluation under progress

Progress of Projects:

2.1.8 CANCER BLOCK- GENERAL HOSPITAL

Project Profile/ Components:

The nature of upgradation required for General Hospital was identified by CSML & PMC

in numerous meetings conducted with KMC & DMO & GH team. During these meetings

the hospital management committee requested Smart City to construct a dedicated

Cancer Ward block as an extension for cancer centre adjacent to the existing cancer

LINAC block building with following facilities.

❖ Chemotherapy wards,

❖ Male & Female Oncology wards,

❖ ICU, Neutropenia ward,

❖ Stand-by dormitories

Projects intends to provide a dedicated cancer specialty ward block as an annex to the

Existing LINAC building under implementation by INKEL & General hospital. Considering

the above requirement, it is currently proposed to construct a 7 storeyed (1 Basement +

Ground floor + 6 floors) building with approximate plinth area of 4500 square meters and

a total of 109 beds and 32 beds for dormitories.

❖ Male ward of 33 beds

❖ Female ward of 34 beds

Page 60: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 60 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Chemotherapy ward of 24 beds

❖ Neutropenia ward of 9 beds

❖ ICU of 9 beds

❖ Dormitories (M&F of 16 beds each)

Project cost: INR 26.0 Crores Duration: 12 months

Project Start date: 27 February 2019 End date (expected): 27 February 2020

Contractor: M/s INKEL Limited

Current status:

❖ INKEL shared broad cost estimate with revised proposal (of plinth area, beds and

facilities to be provided). The proposal was reviewed and INKEL is requested to

provide revised proposal with block estimate of complete project.

❖ Final capacity including number beds and of number of floors to be shared by

INKEL in the revised proposal such that foundation design is proposed for the

maximum number of floors permissible as per municipal rules but finishing work

(including interior and medical equipment) shall be proposed based on the fund

availability for the project module. Post approval of proposal the contract will be

signed

Any Issues/ Challenges to be discussed:

❖ Project scope to be finaliszed based on fund available. Project cost would include

cost of construction, centage charges for M/s. INKEL, GST and tender excess by

contractor.

Location map

Figure 2-14 Location of proposed Cancer Block

2.1.9 E-HEALTH SOLUTION FOR GENERAL HOSPITAL

Page 61: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 61 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Project Profile/ Components:

General Hospital at Ernakulam is one of the reputed Government Hospital which provides

effective medical care to the citizens of the Kochi Corporation and surrounding areas.

General Hospital has a very old and ineffective IT infrastructure which is an impediment

to its efficient functioning. This requires urgent upgradation. Concurrently e Health

solution is being developed and implemented by state Health department which

integrates all departments and government hospitals into an efficient Hospital Information

and Management system. It’s thus panned to upgrade the IT infrastructure of General

Hospital under the smart city mission project. The project includes two broad

components.

❖ Multiprotocol Label Switching (MPLS) Virtual Private Network (VPN) with

Redundancy to e- Health server hosted in Cloud.

❖ Workstations and Computer Hardware for e- Health implementation

The detail of these components is as follows:

• MPLS VPN with Redundancy to e-Health server Hosted in State Data Center:

This involves the following:

- Passive Optical Fibre Network Internal LAN with IPPBX- The internal network

will be combination of LAN and with Wi-Fi- Optical Fibre Cable (OFC) backbone.

- MPSL VPN – Transfer of EMR (Electronic Medical Records) requires higher

bandwidth; accordingly, a high-speed internet line using Optical Fibre (Gigabit-

capable Passive Optical Networks (GPON)) is best suitable.

• Local Sever, Workstations and other Computer Hardware

- E- Health solutions requires additional Workstations, Printers, Scanners,

Biometric readers and other Computer Hardware for implementing the solution.

Project cost: INR 3.71 Crores Duration: 4 Months

Project Start date: 14 June, 2019 End date (expected, excl. O&M): 30 September 2019

Contractor: M/s KELTRON

Current status:

❖ KELTRON is finalising the contract for procurement of GPON Network and will

award the contract to BSNL by 7 June 2019.

❖ Procurement of Computer Hardware is in tendering stage.

Any Issues/ Challenges to be discussed:

❖ The second part of the project, which is procurement of Hardware is still under

tendering stage, which is delayed.

❖ KELTRON to expedite the tendering

❖ Delay from Keltron in taking timely action

Page 62: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 62 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Project design

Figure 2-15 Structural outline of e-Health Solution

Module 14 Education

There were total of 3 projects identified under this module with serial number 14.1 & 14.2.

Tenders were floated, and bids received from the bidders for the Smart class room project.

However, KITE Mission of Government of Kerala informed that a similar project is being

implemented by them on State Level thus the SPV should not continue with the selection

process. Therefore, the project is now cancelled and revised number of projects I 2.

S. No

Proposed interventions REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Status

14.1 Upgradation of Anganwadis

100 300 Feasibility Report submitted on 06-04-2019. Preparation of DPR ongoing

14.2 Upgradation of facilities - Basic services, Digital classrooms, Libraries, Eco-toilets, Sports kits, Biogas plant, Urban farming etc Higher Educational institutions

Higher secondary block, Central Calvathy GHSS, Fort Kochi

450 467 DPR Submitted on 13.11.2108. Project to re-tendered.

Smart Classroom for 100 classrooms PAN city

490 Segregated. Tender has been cancelled by the authority.

Page 63: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 63 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

The project will include rejuvenation of AWC in Fort Kochi & Mattancherry with state-of-the-

art facility for Preschool training with Mother & Child care. List of 52 AWC identified in Fort

Kochi & Mattancherry from CDPO. The proposal includes following components:

• Tangible (physical) upgradation in quality of environment for AWC functioning

in Govt premises,

• IT infrastructure for Smart class rooms at AWCs.

Calvathy School project intends to provide a higher secondary block for about 240 pupils

along with the labs and ancillary facilities required. The building would also provide admin

office required for lower primary section.

• The proposal includes following components:

• 4 classrooms of 60 capacity each and one digital classroom

• Chemistry, Physics and computer labs

• Staff rooms, admin rooms, for higher secondary & lower primary section.

• Auditorium of 250 capacity.

• Building would be a 4-story structure of total area of 1500 sq.mt built after demolishing an existing single story old structure which is currently used as a common activity area.

The Smart education project aims to bring in state of the art education to students through

classroom revolution which is to innovate education, teaching and evaluation methods, and

educational environments using information Technology.

Module 15 Safety and Security

There were total of 2 projects identified under this module with serial number 15.1 & 15.2.

Based on the meetings conducted with Kochi Municipal Corporation and other

stakeholders, all projects are under scope of SPV implementation.

S. No Proposed interventions

REVISED Name of Project

SCP Cost

Clubbed / Segregated/

Estimated Cost

Status

15.1 5 Rapid response boats for water transport safety

Water Ambulance

50 Convergence. Formal confirmation from authority required

15.2 Drone Surveillance Intelligent surveillance System for Kochi

30 1456 Feasibility report for CCTV has been submitted on 21st January 2019. DPR submitted.

Since it is learnt that KSINC is operating water ambulance (Rapid response boat), the

project is part of convergence.

Module 16 Other Social Infrastructure

There were total of 2 projects identified under this module with serial number 16.1 & 16.2.

Based on the meetings conducted with Kochi Municipal Corporation, all projects are under

scope of SPV implementation.

S. No Proposed interventions SCP Cost

Clubbed / Segregated/

Status

Page 64: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 64 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Estimated Cost

16.1 Upgradation of Community Centre at Mattancherry with indoor sports facilities

100 Discussed with KMC various times. As there is no Community centre available in Mattancherry for upgradation KMC to confirm dropping of the project

16.2 Standardize structures for "Petti Kada"

60 Clubbed - with Hawker zone.

The scope of project at 16.1 is yet to be clarified by KMC.

Project 16.2 has been clubbed with project number 12.2 as petti kadas will be provided for

Hawker Zones identified. Broad designs have been made. After the hawkers are identified,

implementation of this project will be taken up accordingly.

Module 17 Identity and Culture

1 project identified under this module with serial number 17.1.

S. No Proposed interventions

REVISED Name of Project SCP Cost

Clubbed / Segregated/ Estimated

Cost

Status

17.1 Fort Kochi and Mattancherry region Master plan for Tourism

3,000 Project not preparation of Master plan as its already prepared. Project is to implement individual tourism projects

Open Air Theatre (OAT) at Fort Kochi Zonal office

110 Tender has been issued. Technical Bid evaluation under progress

Development of Dutch palace node parking area and palace street entry

110 Tender has been issued. Technical Bid evaluation under progress

Fort Kochi Beach Front improvements - Part A Vasco Square

158 Project to be re-tendered

Development of Ethnic Food Hub & Dutch Quay Upgradation

100(PPP) DPR Submitted

Museum of Freedom Struggle

120 Feasibility report submitted on 20th December 2018 Museum of Spices history 150

Fort Kochi Beach Front improvements - Part B Walkway & Beach

800

Mattancherry Walkway 1100

Cultural Corridor – PT Usha Road

100 Concept Stage

The project mentioned in the SCP project list is Master plan for Tourism. Tourism Project

will be taken up individually identified in the Tourism Master plan. Based on the meetings

Page 65: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 65 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

conducted with Department of Tourism, KMC and other stakeholders the projects have

been identified.

Figure 2-16 Identification of Tourism Projects

Source: PMC

Module 18 Others

There was 1 project identified under this module with serial number 18.1. Based on the

meetings conducted with MoHUA, KMC, Town Planning Dept and other stakeholders the

project is under scope of SPV implementation. This project will be integrated with IC4

project.

S. No

Proposed interventions REVISED Name of Project

SCP Cost

Clubbed / Segregated/ Estimated

Cost

Status

18.1

Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres

Base Map updation for ABD Areas

1,500 40 DPR have been submitted on 20th December, 2018. scope submitted to enable KMC to tender at the earliest

18.2

Integrated Command, Control and Communication Centre (IC4)

6450 LoA issued. Contract agreement to be signed.

Base Map Updation: The main objective of the project is to develop an updated detailed

GIS Base map on a scale of 1:1,000 for the Project area. The preliminary interpreted map

should be ground verified and the final map is to be prepared by incorporating the ground

truth data. These detailed maps consisting of the planimetric details, Plot boundaries micro

level Land use and utility services underground utilities as available from line departments

need to be generated by contact ground truth collection, updating of map and data linking.

Available data at CSML will be integrated with the Base Map in GIS during the survey

preparation of base map. The data will be collected in proper field data sheet format. The

Page 66: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 66 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

base map prepared through on-screen digitization of imagery will be used for survey for the

updating purpose and finalization of layer wise Base Map with the attributes.

Final base map is to be prepared incorporating the data collected from survey and the data

for different entities. Hard copy base maps are to be prepared at 1: 1000 scale ward wise/

ABD area wise. The base maps will be prepared in various layers for ease of operation in

GIS. Layer and data structures can be modified depending on the local requirements of

CSML.

KMC has proposed to implement the project. Scope of work based on DPR prepared by

CSML has been shared with KMC & Town Planning department for further action. KMC to

tender the project at the earliest.

Progress of the Project

2.1.10 INTEGRATED COMMAND CONTROL & COMMUNICATION CENTER

Project Profile/ Components:

IC4 is the brain of the smart city, which gathers all the information of smart solutions of

different departments of the city using ICT (Information and communication technology).

IC4 is where information from different departments and various applications is collected

and analyzed for better planning of the city. It has Business Intelligence and Artificial

Intelligence (AI) engine which will process all the information and generate insights.

These insights will be helpful in managing incidents across the city and do a better

planning for the development. It also plays the role of decision support system.

Accordingly, CSML has embarked to implement the project.

Major Components of the IC4 Solution

❖ Cloud Service Provider (CSP)

❖ Internet of Infrastructure (IoI) which is an IOT platform which integrates all solutions

and facilitates, aggregation of data, big data analysis, visualization, Management,

Reporting, etc.

❖ Design and develop the Mobile app.

❖ Design and Development of Multi City Mobility Card (MCMC)

❖ Development of GIS based citizen Portal.

❖ Development of Smart Application for Solid waste Management.

❖ Development of Project Management Services along with Email Server.

❖ Aadhaar Integration

❖ Integration with Akshaya.

❖ Design and Construction of the City Command Control Room.

Overview of the Scope of MSI are as below:

❖ The MSI will conduct a detail assessment

Page 67: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 67 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

❖ Design a comprehensive technical architecture and project plan.

❖ Design and development of comprehensive Internet of Infrastructure (IoI) for city

command and control operations.

❖ IoI platform would have facility of comprehensive viewing and performing operations

there will be a provision for generating configurable reports through dashboard and

also real time monitoring.

❖ Design and develop the Mobile app.

❖ Design and Development of Multi City Mobility Card (MCMC)

❖ Development of GIS based citizen Portal.

❖ Development of Smart Application for Solid waste Management.

❖ Development of Project Management Services along with Email Server.

❖ Aadhaar Integration

❖ Integration with Akshaya.

❖ Design and Construction of the City Command Control Room

Different Applications for Integration with IC4. There are different Applications of

smart city which are to be integrated to optimize the system.

❖ Applications hosted on cloud.

❖ SaaS based Applications.

❖ Existing solutions of Departments like e-Health of Kerala state, IT@school of

education Dept., Municipal information system, e-district application, Surveillance

system of Police etc.

❖ Command, Control and Communication Room (CCR).

❖ Some applications like citizen portal, mobile app, payment gateway, etc.

Project cost: INR 64.50 Crores Duration: 8 Months

Project Start date: 27 May 2019 End date (expected, excl. O&M): 27 January 2020

Contractor: M/s Fluentgrid Limited in consortium with Bharat Electronics Limited (BEL)

Current status:

❖ Offsite work started by MSI.

❖ MSI has submitted the design of Command and Control room layout. Comments on

the layout and alternative has been shared by PMC with MSI.

❖ Implementation of IC4 involves creation of respective application by each

department and extending API for integration.

❖ MSI has sent a list of different stakeholders, who will be interacting with MSI for

integration of the respective departments. For this purpose, stakeholder meeting is

essential. Stakeholder meeting is expected to start after mobilisation of MSI team.

Page 68: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 68 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Any Issues/ Challenges to be discussed:

❖ Bank guarantee format changed by the bank. Issue being resolved.

❖ On site project team yet to be mobilised post contract signing

❖ MSI to identify all SPOCs and share Identification of SPOC by stakeholders with

CMSL for confirmation

❖ Procurement of GIS map by CSML for pan city

Project features

Figure 2-17 Integration of Smart Solutions with IC4

2.2 NEW PROJECTS PROPOSED

Following few projects have been proposed by stakeholders to be taken up under smart

city. These will only be taken up after council approval and based on fund availability after

all identified projects under Smart City are taken up. Also, the new projects need to be as

per Smart City guidelines. Those have been considered for following reason.

Project Name Reason for inclusion

1. Multilevel Car

parking at

GCDA ground

on

Shanmugham

Road & at

KTDC

2. Smart parking

solutions

• Already mention in SCP but not in List of projects.

• For supporting proposal of pedestrianisation parking at various

other locations are must to support parking free Broadway

street. For success of Browed Street improvement this parking is

very much required to support proposed Broadway Street

pedestrianisation and Ernakulam Market development

• GCDA amenable to provide land. Location within ABD area.

• Urban mobility already identified theme under SCP can be taken

up under same

Page 69: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 69 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

2.3 UPDATED INTEGRATED PROJECTIVISATION

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

1 KER-KOC-008

1 Water Supply 1.1 West Kochi - Karuvelipady Pump house – Pumping augmentation

Convergence 100 Concept stage

2 KER-KOC-009

1 Water Supply 1.2 West Kochi - Extension of pipelines from Maradu to Island to be extended to West Kochi to supply 12 MLD

Convergence 55 30 Work completed Financial Progress : 0.27 cr

3 KER-KOC-010

1 Water Supply 1.3 West Kochi - Replacement of pipe lines from Perumanoor to Thevara and Thoppumpady bridge to Karuvelipady

Convergence 1100 448 Work completed Financial Progress : 3.65 cr

4 KER-KOC-011

1 Water Supply 1.4 West Kochi - Dedicated pumping main

Convergence 350 Concept stage

5 KER-KOC-012

1 Water Supply 1.5 West Kochi - Storage capacity augmentation in Karuvelipady sump by 1.5 million litres

Convergence 800 288 36% Physical Progress. Financial Porgress: Rs 1.12 cr.

6 KER-KOC-013

1 Water Supply 1.6 West Kochi - Rejuvenation of the Three OH Tanks in the region (Modibath, Fort Kochi and Koovapadam);

Convergence 75 DPR Stage (part of 24x7 Water supply project)

7 KER-KOC-014

1 Water Supply 1.7 West Kochi - Replacement of 20 kms of Distribution line with D.I. pipes including Road cutting charges

Convergence 3500

8 KER-KOC-015

1 Water Supply 1.8 West Kochi - Replacement of Household connections (last mile) for across 10,000 HSCs with Smart Metering and isolation valves

Convergence 2500

9 KER-KOC-016

1 Water Supply 1.9 West Kochi - Bulk Meters and Isolation valves with remote meter reading

Convergence 100

Page 70: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 70 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

10 KER-KOC-017

1 Water Supply 1.1 Mainland - Rider line for increased water supply

Convergence 1000 223 Under implementation

11 KER-KOC-018

1 Water Supply 1.11 Mainland - Overhead Storage Reservoir + 1 Million Litre Sump + pump near Ernakulam Ground

Convergence 300 DPR Stage (part of 24x7 Water supply project)

12 KER-KOC-019

1 Water Supply 1.12 Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves

Smart Water 1 Mainland - Replacement of connections (last mile) for across 10,000 HSCs (Commercial and Domestic) with Smart Metering and isolation valves

2000 100 Project scope for project being finalised in consultation with KWA. Concept prepared. CSML to fix a meeting with KWA to finalise scope.Also issue a letter in this regard.

13 KER-KOC-020

1 Water Supply 1.13 Mainland - Bulk Meters and Isolation valves with remote meter reading

Convergence 150 DPR Stage

14 KER-KOC-021

1 Water Supply 1.14 General - Rainwater structures in ~5000 households

Convergence Rainwater harvesting structures in 13 Govt bldgs & Institutions

1125 75 Feasiblity report submitted. Project has been taken uo by KWA under Convergence

15 KER-KOC-022

2 UGSS 2.1 Decentralized Treatment and collection system for West Kochi under ADB (Mundamveli)

Waste Water & Reuse

2 Vacuum Sewer Network With House Connections and Sewage Treatment Plant

2200 15450 Tendered

16 KER-KOC-023

2 UGSS 2.2 Small bore sewer/ Vacuum system for onsite sanitation - Includes storage facility for treated water use for landscaping

11000

17 KER-KOC-024

2 UGSS 2.3 Improvements to Elamkulam STP and collection system Mainland (JNNURM scheme)

Waste Water & Reuse

3 Improvements to Sewer collection system for Mainland

7000 3450 Project scope to be confirmed with stakeholders (KWA)

Page 71: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 71 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

Convergence Elamkulam STP 1300

18 KER-KOC-025

3 NMT Roads and Pedestrianized areas

3.1 Relaying of roads Improvement of Roads

4 Development of Other Roads in Ernakulam

4200 4360 Awarded

19 KER-KOC-026

3 NMT Roads and Pedestrianized areas

3.2 Standard Footpaths including signages

5 Development of Other Roads in West Kochi

2853 6020 To be retendered

20 KER-KOC-027

3 NMT Roads and Pedestrianized areas

3.3 Restoration/ Rehabilitation of Stormwater drains in the proposed area

2360

21 KER-KOC-028

3 NMT Roads and Pedestrianized areas

3.4 MLCP and Commercial complex at Kacheripady

Transport 6 Parking management plan for ABD area & Development of Multi Level Car Parking at Kacheripady

5000 690 EOI Published. No EOI received. Retendered. 2nd time again no bid received. Project to be re-tendered

Transport 7 MLCP at GCDA land at Marine Drive

19.9 Feasibility report prepared. DPR preparation ongoing. CSML Board & stakeholders approval required to enable tendering

8 MLCP at KTDC complex at Maneka

9 Smart Parking solutions at various location in ABD area

10 Commercial complex at Kacheripady

500

22 KER-KOC-029

4 Main Roads 4.1 World class Arterial roads -- KB Jacob & Amravati Road/ Bazaar Road in West/ -- Avenue, MG Rd, DH Rd, Banerjee Rd in Central city

Smart Street Features

11 Development of Smart Roads in Ernakulam under Smart City Mission

5287 6153 Re-tendered into 5 packages (initially 2 packages)

23 KER-KOC-030

4 Main Roads 4.2 Relaying of roads, Aesthetic and improved Urban design Pedestrian facilities with

12 Development of Smart Roads in West Kochi under Smart City Mission

1650 3031

Page 72: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 72 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

Street furniture, Boulevards and urban greenery

24 KER-KOC-031

4 Main Roads 4.3 Utility ducting for SWD, Water supply, Sewerage, OFC etc

3300

25 KER-KOC-032

4 Main Roads 4.4 Signages, Junction improvement with Intelligent Traffic management

13 Integrated Traffic Management Systems (ITMS)

97 2690 Awarded

KER-KOC-086

14 Road Signages 240 DPR submitted. To be tendered post initiation of road construction work

26 KER-KOC-033

4 Main Roads 4.5 Escalator FOBs Smart Street Features

15 FOBs - West Kochi (3 Nos) 240 215 Project scope being finalised in consultation with stakeholders

27 KER-KOC-049

5 Energy Supply 5.1 Compact Secondary Substation (990 KVA)

Smart Street Features

16 Development of Roads electrical infrastructure in Ernakulam & West Kochi

180 6340 Re-tendered into 5 packages (initially 2 packages). Bids submitted under evaluation

43 KER-KOC-050

6 Energy Efficiency

6.1 Solar based LED with Smart poles

Smart Street Features

17 Implementation of Smart LED lighting

1250

3209 Re-Tendered. Under evaluation

KER-KOC-088

Smart Telecom 18 Intelligent Street Poles 30160 PPP. Tendered

44 KER-KOC-051

6 Energy Efficiency

6.2 Solar panels in Households and Institutions - Grid connected

Solar 19 Solar panels in Govt. buildings

1758

570 Contract Awarded. Work on-going

Solar 20 Solar panels in public places (Canals, parks etc)

Concept Stage. May be clubbed with Canals project.

45 KER-KOC-052

7 Solid waste and Sanitation

7.1 Equipments including Smart Street sweepers/ GPS enabled Vehicles/compactors

Equipments including Smart Street sweepers/ GPS enabled Vehicles/compactors

600

Page 73: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 73 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

Solid Waste Management

21 Smart & Improved Secondary Storage & Transportation of Solid Waste using Portable Compactor Technology

440 To be retendered post discussions with KMC

Solid Waste Management

22 Smart & Improved Battery Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area

100 DPR submitted. To be tendered post KMC approval

KER-KOC-087

Solid Waste Management

23 Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area

320 To be retendered post discussions with KMC

46 KER-KOC-053

7 Solid waste and Sanitation

7.2 Bio-composting in all Government institutions

Solid Waste Management

5

47 KER-KOC-054

7 Solid waste and Sanitation

7.3 Household segregated bins for Organic and inorganic wastes

Solid Waste Management

24 Distribution of Household Bins & Street Litter Bins for improvement of waste segregation in ABD

74 67 Awarded

48 KER-KOC-055

7 Solid waste and Sanitation

7.4 Public toilets with Fit-in Treatment facility for Decentralized STP in West kochi

Other social Infrastructure

25 Renovation and Upgradation of Existing Public Toilet Facilities in West Kochi & Ernakulam Market.

10 180 Tendered

49 KER-KOC-056

8 Parks and Open spaces

8.1 Upgradation of Nehru Park Convergence 200 200 Under implementation

50 KER-KOC-057

8 Parks and Open spaces

8.2 Development of open spaces and playgrounds

Smart Placemaking

26 Development of Open spaces and playgrounds

30 250 DPR Stage

51 KER-KOC-058

8 Parks and Open spaces

8.3 Open space corridor linking DH Ground to Mangalavanam (depends on ecological sensitivity)

Smart Placemaking

27 Improvements to Marine Drive walkway phase I

90 710 Tendered

52 KER-KOC-059

8 Parks and Open spaces

8.4 Mangalavanam Eco-restoration project

Smart Placemaking

28 Mangalavanam Eco-restoration project

100 100 Concept shared with forest department. Multiple discussions held. Confirmation

Page 74: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 74 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

awaited from stakeholder on scope of work to start work on Feasibiltiy report.

53 KER-KOC-060

9 Canal Restoration

9.1 Restoration of Mullassery canal - including linking of standardized area drains

Smart Placemaking

29 Restoration of Mullassery canal - including linking of standardized area drains

100 100 Based on stakeholder discussions held on 28 May 2019, CSML to confirm scope of project (extended of the canal under smart city scope) for feasibility report revision

54 KER-KOC-061

9 Canal Restoration

9.2 Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts

Smart Placemaking

30 Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts

500 500 KMRL & CSML to confirm whether CSML or KMRL to take up market canal works. Thereafter FR will be revised accordingly

55 KER-KOC-062

9 Canal Restoration

9.3 Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features

Smart Placemaking

31 Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features

2000 2000 Based on stakeholder discussions held on 28 May 2019, CSML to confirm scope of project (extended of the canal under smart city scope) for feasibility report revision

56 KER-KOC-063

9 Canal Restoration

9.4 Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road

Smart Placemaking

32 Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road

1500 1500

57 KER-KOC-064

10 Urban mobility (Multi Modal Transport)

10.1 Water transport infrastructure (around 12 100 pax boats)

Convergence 4200 5600 Tender stage

Page 75: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 75 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

58 KER-KOC-065

10 Urban mobility (Multi Modal Transport)

10.2 Electric Feeders, Bicycle Sharing, Elevated Walkways and Travelators

Convergence Electric Feeders 1148 1148 Taken up by KMRL. Also propsoed as part of Broadway project

KER-KOC-003

Transport 33 Public Bicycle Sharing 1000 Contract Awarded. Work on-going

Elevated Walkways and Travelators clubbed with Ernakulam Market. Scope to be finalised by stakeholders

59 KER-KOC-002

10 Urban mobility (Multi Modal Transport)

10.3 Walkway from Ekm Jetty to Metro station

Smart Street Features

34 Walkway from Ekm Jetty to Metro station

900 470 Under Implementation

60 KER-KOC-007

10 Urban mobility (Multi Modal Transport)

10.4 Jetty improvement Convergence 800 4000 DPR stage

61 KER-KOC-066

10 Urban mobility (Multi Modal Transport)

10.5 Property development along jetties

Convergence 720 DPR stage

62 KER-KOC-067

10 Urban mobility (Multi Modal Transport)

10.6 Boatyard and Command & Control Centre

Convergence 2000

63 KER-KOC-068

10 Urban mobility (Multi Modal Transport)

10.7 Dredging cost Transport Marina 1000 2000 Concept shared based on discussed hwld on 14 Feeb 19 with all stakeholders. CSML to provide approval to proceed with Feasiblity preparation.

Page 76: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 76 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

64 KER-KOC-069

10 Urban mobility (Multi Modal Transport)

10.8 Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

Integrated Command and Control Centre/ Master Integrator

35 Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

60 60 Combined stakeholder meeting & letter to stakeholders for confirmation on project to be taken up under Smart City or not

65 KER-KOC-070

10 Urban mobility (Multi Modal Transport)

10.9 Standard Wifi Enabled Bus Stands With Commercial space development

Integrated Command and Control Centre/ Master Integrator

36 Standard Wifi Enabled Bus Stands With Commercial space development

300 300 Combined stakeholder meeting & letter to stakeholders for confirmation on project to be taken up under Smart City or not

66 KER-KOC-071

11 Housing (Urban Planning)

11.1 Integrated redevelopment of Slum housing

Affordable Housing

37 Integrated redevelopment of Slum housing

14140 4685 Letter to KMC to be sent from CSML Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. R&R will require additional time. With limited SCM duration.

Page 77: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 77 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

Confirmation on scope needs to be expedited.

67 KER-KOC-072

11 Housing (Urban Planning)

11.2 Upgradation of infrastructure in Housing through Credit linked schemes

Affordable Housing

38 Beneficiary Led housing scheme 2435 1300 CSML Transferring funds to KMC

68 KER-KOC-073

11 Housing (Urban Planning)

11.3 Construction & upgradation of 755 DUs in Thuruthy, Kalvathy & Konchery colony

Affordable Housing

39 Construction & upgradation of infrastructure in Thuruthy - BRIDGES

7424

515 DPR Stage. Soil test conducted. Broad Estiamte shared with KMRL. Soil test conducted Structural dwgs under preparation.

40 Construction of Second tower at Thuruthy

3500 DPR to be prepared post approval from KMC.

41 Construction of First tower at Thuruthy

2100 CSML Transferring funds to KMC

69 KER-KOC-074

12 Economy and Employment

12.1 Broadway Market and Ernakulam market Redevelopment and Mattancherry spice market

Smart Placemaking & PPP

42 Broadway Street 1000 1000 Feasibility report submitted. DPR Stage

43 Ernakulam Market Redevelopment+Escalator FOBs+Elevated Walkways and Travelators

10000 10240 Feasibility report submitted. DPR Stage. KMC to approve initiate R&R asap. KMC to share final list of eligible shopkeepers with shop size requirement. Suggest on Transit shelter strategy including confirmation on alternate land for

Page 78: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 78 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

relocation, expenditure during relocation period, revision of rental rates for new building and negotiations, approval of revised traffic management plan from beneficiaries, Co-ordination with all beneficiaries. i. KMC to verify and compile final list of vendors and hawkers and share with smart city team at the earliest to enable Smart city team to do detailing of the designs ii. Confirmation for land for transit shelters at the earliest. iii. KMC to confirm allotment of shops by zoning. Smart city to design accordingly

Smart Placemaking

Mattancherry spice market Redevelopment

Taken under streetscape improvement as part of road project

70 KER-KOC-075

12 Economy and Employment (Central City

12.2 Standard Hawker zones in Fort Kochi

Smart Placemaking

44 Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"

500 560 Feasibility Stage

Page 79: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 79 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

Urban Renewal & Mkt Dev)

71 KER-KOC-076

13 Health 13.1 Scale up of GH into a Super-speciality care centres

Health 45 Extension of Cancer Speciality Block for General Hospital.

3000 2600 Awarded

KER-KOC-090

E-Health 46 E-health solutions for selected hospitals

371 Awarded

72 KER-KOC-077

13 Health 13.2 Integrated development of 4 Hospitals in West Kochi - Excellence in Secondary care

Health 47 Out Patient & Admin block, Fort Kochi taluk Hospital

1000 465 Tendered

KER-KOC-089

Health 48 Out Patient & Admin block, Women & Child Hospital, Mattancherry

457 Tendered

73 KER-KOC-079

14 Education 14.1 Anganwadis and public schools Upgradation of facilities - Basic services, Digital classrooms, Libraries, Eco-toilets, Sports kits , Biogas plant, Urban farming etc

Education 49 CIVIL - Anganwadis and public schools

450 200 Feasibility Stage

74 KER-KOC-080

14 Education 14.2 Higher Educational institutions Upgradation of facilities - Basic services, Digital classrooms, Libraries, Eco-toilets, Sports kits , Biogas plant, Urban farming etc

Education 50 Higher secondary block, Central Calvathy GHSS, Fort Kochi

100 467 Tendered

Education CIVIL 1 - Mattancherry School - Higher Educational institutions

Education Maharajas Ground 500 Concept tage

Education SRV School 800 Outside ABD. CSML to provide approval for the project to be taken up.

Page 80: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 80 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

E- Learning 51 Smart Classroom for 100 classrooms PAN city

490 Tendered. Cancelled

75 KER-KOC-081

15 Safety and Security

15.1 5 Rapid response boats for water transport safety

Convergence 50 CSML to confirm with KMRL

76 KER-KOC-082

15 Safety and Security

15.2 Drone Surveillance Integrated Command and Control Centre/ Master Integrator

52 Safety & Security CCTV Surveillance

30 1436 DPR stage

77 16 Other Social Infrastructure

16.1 Upgradation of Community Centre at Mattancherry with indoor sports facilities

Other Social Infrastructure

53 Upgradation of Community Centre at Mattancherry with indoor sports facilities

100 100 Clarification on scope needed from KMC

78 16 Other Social Infrastructure

16.2 Standardize structures for "Petti Kada"

60

79 KER-KOC-083

17 Identity and Culture (Heritage & Tourism Development)

17.1 Fortkochi and Mattanchery region Master plan for Tourism

Smart Placemaking

Implementation of identified Tourism related projects in Fort Kochi & Mattancherry

3000 3000

17.1.1 54 Open Air Theatre at Fort Kochi Zonal office

110 Tendered

55 Museum of Freedom Struggle 120 DPR stage

56 Museum of Spices history 150 Formal confirmation on location required from KMC

17.3 57 Development of Ethnic Food Hub

KER-KOC-092

58 Development of Dutch palace node parking area and palace street entry

110 Tendered

KER-KOC-091

59 Fort Kochi Beach Front improvements - Vasco Square

171 Tendered

60 Fort Kochi Beach Front improvements - Phase II

829 DPR stage

61 Mattancherry Walkway 1100 Put on hold by CSML till required approvals are received

Page 81: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 81 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

SCP S. No.

Project Code as per Central MIS

Module No.

Module Name SCP Project No.

SCP Project Name Category (as per MoHUA)

Revised S. No.

Revised Name of Project Original Project Cost as per SCP

Estimated Cost (if any)

Stage of project (for Convergence projects status has been provided by respective stakeholder)

17.2 Developing a Water & Adventure sports center at Marine drive

110 DPR stage

62 Cultural Corridor PT Usha Road 100 Feasibility stage

17.1.9 Multimedia based Light & Sound show

Put on hold by CSML till required approvals are received

80 KER-KOC-084

18 Others 18.1 Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres

Convergence 63 Base map upgradation for ABD area

1500 50 DPR submitted and scope submitted to enable KMC to tender at the earliest

KER-KOC-004

Integrated Command and Control Centre/ Master Integrator

64 Integrated Command, Control and Communication Centre (IC4)

6450 Awarded

2.4 OVERALL PROGRESS

Sl No

Source of Funds

No of Projects as per SCP

Cost as Per SCP ( Rs in

Cr

No of Revise

d Projec

ts

Revised Cost

( Rs in Cr)

No of As

Issued

As issued- Amount

No. of TS

Issued

Amount of TS

issued

No of Tender

ed Projec

ts*

Amount of

Tendered

No of Work

Awarded

Amount of Work Awarded

No of Work Completed

Expenditure

1 SPV 80 1347.5

60 1005.17 27 565.09 25 541.68 22 573.21 10.00 258.62 5.50

2 PPP 4 336.58 3 336.58 3 336.58 3 336.58 2.00 35.00 26.80

3 Convergence 2 646.000 20 860.27 0 0.00 8 155.79 8 155.79 6.00 59.79 2 6.70

Note * Total - Tendered Number & Amount: Projects not included which are awarded on nomination basis

Page 82: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 82 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

2.5 SECTOR PROGRESS

Sl No Name of the Sector

No of Projects as per SCP

Cost as Per SCP ( Rs in

Cr)

No of Revised Projects

under SCP

Revised Cost

( Rs in Cr)

No. of Technical Sanction Issued

Technical Sanction Issued - Amount

Total Tendered (Number)

*

Total - Tendered Amount (Rs in

Crore)*

Work Awarded - Number

Work Awarded - Amount (Rs in cr)

Work Completed

Total - Expenditure ( Rs in crore)

A. ABD AREA PROJECTS SPV

1 Water Supply 1 11.25 1 1 0 0 0 0.0 0.0 0.0

2 UGSS 3 202.00 2 189 1 143.3 1 143.3 0.0 0.0

3 NMT Roads 4 44.13 7 133.85 3 103 3 103.0 1.0 43.6

4 Main Roads 5 106.04 5 123.30 3 103.9 3 106.9 3.0 118.7

5 Energy Supply 16 122.44 1 63.4 1 0 1 63.4 0.0 0.0

6 Energy Efficiency

2 30.08 4 339.87 3 343.28 2 333.7 1.0 5.7 3

7 Solid Waste and Sanitation

4 6.89 5 11.07 4 10.37 4 10.4 1.0 0.7

8 Park & Open Space

4 2.20

3 10.6 1 7.1 1 7.1 0.0 0.0

9 Canal Restoration

4 41.00

4 41 0 0 0 0 0 0

10 Urban Mobility 4 24.08 4 18.3 2 19 2 14.7 2 14.7 4.3

11 Housing 3 239.99 5 121 0 0 0 0 0 0

12 Economy and Employment

2 115.00

3 115.6 0 0 0 0 0 0

13 Health 2 40.00 4 38.93 4 30.17 2 9.22 2 20.71

14 Education 2 5.50 2 7.67 1 4.67 1 4.67 0 0

15 Safety and Security

2 0.80

1 14.56 0 0 0 0 0 0

16 Other Social Infrastructure

2 1.60

1 0 0 0 0 0 0 0

17 Identity and Culture

1 30.00

9 24.11 3 3.78 3 3.78 0 0

18 Others 1 15.00 2 64.5 1 84.69 1 84.7 1 64.5

Total -A 62 1138 63 1317.75 27 853.26 24 884.79 11 268.62 0 7.3

B- Project Under Convergence

19 Water Supply 13 120.3 13 80.64 4 9.88 4 9.88 4 9.88 2 5.04

20 UGSS 1 13.00 0 0 0 0 0 0

21 Park & Open Space

1 2.00 1 2.00 1 2 1 2 1 2 1.66

22 Urban Mobility 4 87.2 3 96.32 2 96 2 96 0 0

23 Housing 1 47.91 1 47.91 1 47.91 1 47.91

Page 83: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 83 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No Name of the Sector

No of Projects as per SCP

Cost as Per SCP ( Rs in

Cr)

No of Revised Projects

under SCP

Revised Cost

( Rs in Cr)

No. of Technical Sanction Issued

Technical Sanction Issued - Amount

Total Tendered (Number)

*

Total - Tendered Amount (Rs in

Crore)*

Work Awarded - Number

Work Awarded - Amount (Rs in cr)

Work Completed

Total - Expenditure ( Rs in crore)

Total- B 18 209.5 19 239.87 8 155.79 8 155.79 6 59.79 2 6.7

C- PAN City Project

24 Water Supply 1 621 1 621

25 INTEGRATED CITY APP

1 25 1 25 1 25 1 25 1 25.00 1 25.00

Total -C 2 646 2 646 1 25 1 25 1 25.00 1 25.00

Grand Total -(A+B+C)

82 1993.5 84 2203.62 36 1034.05 33 1065.58 18 353.41 3 39

Note * Total - Tendered Number & Amount: Projects not included which are awarded on nomination

2.6 IMPLEMENTATION SCHEDULE

Based on the scope of the work which is being finalised by consultation with stakeholders, PMC has assessed the timeline for submitting the

reports. The final timeline will be given for the projects once the scope of work will finalised. The implementation schedule for the projects is given

below:

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Replacement of connections (last mile) for across 550 HSCs (Commercial and Domestic) with Smart Metering and isolation valves

2000 100

Scope of work is being clarified with consultation with Stake holders

30 days post confirmation of Scope of Work

25 days post confirmation of Feasibility Report

15 days post confirmation of DPR

60 days after issuance of tender

Project scope for project being finalised in consultation with KWA. Concept prepared. CSML to fix a meeting with KWA to finalise scope.

Page 84: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 84 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Also issue a letter in this regard.

Improvements to sewer collection system for West Kochi

13200 15450 Tender issued 7-Feb-18 Revised- 11-Sep-18

20-Feb-2019/ 28-Feb-2019/ 05-Mar-2019

-

08-Mar-2019 15-July-2019

Improvements to sewer collection system for Mainland

7000

3450 Feasibility Stage

30 days post confirmation of Scope of Work

30 days post confirmation of Feasibility Report

30 days post approval of DPR

60 days post tender

Project scope to be confirmed with stakeholders (KWA & KMC)

Development of Other Roads in Ernakulam under Smart City Mission

4200

4360 LoA issued on 9th April

10-Aug-18 30-Aug-18

11-Oct-18/ 14-Feb-2019

09-April-2019

2853

2360

Development of Other Roads in West Kochi under Smart City Mission

6020 Project re-tendered.

10-Aug-18

30-Aug-18

11-Oct-18/ 15-Feb-2019

15-Oct-2019

Project to be re- tendered

MLCP at Kacheripady

5000

616 Tender issued

26-Feb-18 Revised FR – 07-Oct-18

08-Feb-2019 08-March-2019 15-Oct-2019

Project to be re-tendered

Commercial complex at Kacheripady

500

Combined Feasibility report submitted–Scope of work to be finalised with stake holders consultation

7-Oct-2018

30 days post confirmation of scope of work and land availability

15 days post approval of DPR

60 days post tender

Scope is being finalised with Stakeholders

MLCP at KTDC & GCDA land at Marine Drive

1700 7-Oct-2018

30 days post confirmation of scope of work and land availability

15 days post approval of DPR

60 days post tender

Scope is being finalised with Stakeholders

Page 85: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 85 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Smart Parking Solutions in ABD area

190 DPR stage 7-Oct-2018 15-June-2019 15-July-2019 30-Sept-2019

DPR under preparation

Development of Smart Roads in Ernakulam under Smart City Mission

5287 6153 LoA issued on 9th April

10-Aug-18

30-Aug-18

11-Oct-18/ 14-Feb-19

09-April-2019

Development of Smart Roads in West Kochi

1650 3031

LoA issued on 9th April

10-Aug-18

30-Aug-18

11-Oct-18/ 16-Feb-19

09-April-2019

3300

Development of Smart Roads electrical infrastructure in Ernakulam & West Kochi

12253 6340

Project re-tendered Bid evaluation under progress

10-Aug-18

30-Aug-18

11-Oct-18/ 16-Feb-19

30-June-2019

Integrated Traffic Management Systems (ITMS)

97

2690 LoA issued 2-Feb-18

6-Feb-18

24-Feb-18

22-Feb-2019

-

Roads Signages 240 DPR submitted 15-Feb-19

28-Feb-2019 -

15-June-2019 14-Aug-2019

-

FoBs(3 nos) –West Kochi

215

Combined Feasibility Report submitted Thuruthy Project. Project scope being finalised in consultation with stakeholders

27-Sept-2019

30 days post confirmation of the scope of work

15 days post approval of DPR

90 days post tender

Implementation of Smart LED Lighting in ABD

1250 3209 Project Re-tendered.

12-Feb-18

17-Feb-18

24-Feb-18 Re tendered- 26-12-18

30-June-2019

Page 86: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 86 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Under evaluation

Intelligent Street Poles 30158 Tender issued. 8-Feb-18

15-Nov-2018/ 08-Feb-2019

07-Mar-2019 15-July-2019

Solar Panels in Govt. Buildings

1758 570 Project under implementation.

2-Feb-18 7-Feb-18 24-Sep-18 - -

Supply, Operation and Maintenance of Portable Compactor for Secondary Storage & Transportation of Solid Waste

600

440

Tender cancelled. Project to be re-tendered

14-Feb-18

20-Mar-18

04-Apr-18 Project to be retendered by 30th July, 2019

30-Sept-19

-

Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area

100 DPR Submitted

26-Feb-18

28-Feb-18

30 days post approval of KMC

60 Days post tender

Approval awaited from KMC

Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area

320

Tender cancelled. Project to be re-tendered

20-Mar-18

20-Mar-18

04-Apr-18 Project to be retendered by 30th July, 2019

30-Sept-19

-

Distribution of Household Bins & Street Litter Bins for improvement of waste segregation in ABD

74 67 LoA issued on 8th May, 2019

7-Feb-18

28-Feb-18

04-Apr-18 08-May-19

-

Page 87: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 87 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Public toilets in West Kochi & Ernakulam Market

10 180 Tender issued 27-Sept-18 -

13-Feb-2019 -

08-March-2019 15-June-2019

-

Development of open spaces and playgrounds

30 250 Feasibility report Submitted

26-Mar-2019

30-May-2019

20-June-2019

11-June-19 30-July-19

30-Sept-2019

Marine Drive Walkway Phase I

90 710 DPR Submitted

03-Nov-18

11-Nov-18 04-Feb-19 27-Mar-2019

08-Mar-2019 15-June-2019

Mangalavanam Eco-restoration project

100 100

Conceptualization Stage. Various discussions held. Confirmation awaited from stakeholder on scope of work

30 days post approval on concept shared

20 days post approval of Feasibility Report

20 days post approval of DPR

60 days post tender

Confirmation awaited from stakeholder on scope of work

Restoration of Mullassery canal - including linking of standardized area drains

100 100 Feasibility Stage

02-Mar-2019/ Rev- 30-July-2019

30-Sept-2019 30 –Oct-2019 30-Dec-2019

Feasibility report to be revised post confirmation on additional canal stretch and surveys by CSML

Restoration of Market canal - Walkways and Market square around the canal pond, Solar

500 500 Feasibility Stage

02-Mar-2019/ Rev- 30-July-2019

30-Sept-2019 30 –Oct-2019 30-Dec-2019

Feasibility report to be revised post confirmation on additional canal

Page 88: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 88 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

paneled roofs, LED Lighting, Light posts

stretch and surveys by CSML

Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features

2000 2000 Feasibility Stage

02-Mar-2019/ Rev- 30-July-2019

30-Sept-2019 30 –Oct-2019 30-Dec-2019

Feasibility report to be revised post confirmation on additional canal stretch and surveys by CSML

Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road

1500 1500 Feasibility Stage

02-Mar-2019/ Rev- 30-July-2019

30-Sept-2019 30 –Oct-2019 30-Dec-2019

Feasibility report to be revised post confirmation on additional canal stretch and surveys by CSML

Bicycle Sharing 1148 1000 Work under implementation

- 2-Mar-18 06-Mar-2018 15-Nov-18

-

Walkway from Ekm Jetty to Metro station

900 900 Under Implementation

30-Mar-17

Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

60 60

Concept Stage. Scope being finalised with KMC

30 days post confirmation of scope of work

30 days post approval of feasibility report

15 days post approval of DPR

60 days post tender Scope is being

finalised with Stakeholders

Page 89: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 89 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Standard Wifi Enabled Bus Stands with Commercial space development

300 300

Concept Stage. Scope being finalised with KMC

30 days post confirmation of scope of work

30 days post approval of feasibility report

15 days post approval of DPR

60 days post tender

Scope is being finalised with Stake Holders

Integrated redevelopment of Slum housing

14140 4685 Scope to be finalised by KMC

30 days post approval of Concept report

90 days post approval of feasibility report

20 days post approval of DPR

60 days post tender

Scope to be finalised by KMC

Construction of First tower at Thuruthy

7424

2100

Transfer of fund by CSML. No scope for PMC

Construction of Second tower at Thuruthy

3500 Scope being finalised with KMC

30 days post approval of Concept report

90 days post approval of feasibility report

20 days post approval of DPR

60 days post tender

Scope to be finalised by KMC

Construction & upgradation of Infrastructure in Thuruthy, Construction of Bridges

515 Feasibility report submitted

27-Sept-2019

30-May-2019

15-June-2019

15-June-2019

15-July-2019

30-Sept-2019

Location approval awaited

Broadway Street 11000 1000 Feasibility Report Submitted.

15-Oct-18 -

15-June-2019

30-July-2019

15-July-2019

14-Aug-2019

14-Oct-2019

R&R assistance required from KMC to complete DPR

Ernakulam Market Redevelopment+Escalator FOBs+Elevated Walkways and Travelator

10000 Feasibility Report Submitted,

19-Sep-18

30-April-2019

15-June-2019

22-June -2019

15-July-2019

16-Sept-2019

R&R assistance required from KMC to complete DPR

Standard Hawker zones in Fort Kochi +

500 560 Concept Stage 30-May-2019 15-July-2019

15-July-2019

30-July-2019

30-July-2019

30-Nov-2019

Scope of the work is being finalised

Page 90: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 90 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Standardize structures for "Petti Kada"

Cancer Extension Block, General Hospital.

3000 2600

LoA Issued to INKEL on nomination basis

10-Jul-18

Contract given on nomination basis

Out Patient & Admin block, Fort Kochi taluk Hospital

1000 467 Tender issued 28-Feb-18

17-Mar-18 Rev- 30-Oct-18

07-Mar-2019 15-June-2019

Out Patient & Admin block, Women & Child Hospital, Mattancherry

457 Tender issued 28-Feb-18 27-Jul-18 Rev- 13-Nov-18

07-Mar-2019 15-June-2019

E-health solutions for selected hospitals

371 LoA issued 15-Sep-18 20-Dec-18/ 07-Feb-19

-

27-Feb-2019

Contract to be awarded on nomination basis

Upgradation of Anganwadis

450 300 DPR under progress

06-Apr-2019

30-Mar-2019

30-May-2019

30-Apr-2019

30-June-2019

30-Aug-2019

Higher secondary block, Central Calvathy GHSS, Fort Kochi

100 467 Tender issued Submitted on 28-Feb-18 -

15-07-2018/ 03-12-2018 -

07-Mar-2019 30-Sept-2019

Project to be re- tender

Smart Classroom for 100 classrooms PAN city

490 Tender cancelled

5-Feb-18

9-Feb-18

24-Feb-18 - -

Intelligent Crime Surveillance system

30 1456 DPR Submitted

21-Jan-2019 -

21-Mar-2019 -

30-May-2019

30-July-2019

16-Sept-2019

Upgradation of Community Centre at Mattancherry with indoor sports facilities

100 100 Clarification on scope needed from KMC.

30 days post confirmation of scope of work

30 days post approval of Feasibility report

20 days post approval of DPR

60 days post tender

KMC proposed to drop the project. Formal confirmation needed

Page 91: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 91 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Implementation of identified Tourism related projects in Fort Kochi & Mattancherry

3000 3000 Master plan for Tourism Projects

Open Air theatre at Fort Kochi

110 Tender issued 20-Aug-18 Rev- 10-Oct-18/ Rev- 06-Feb-2019

02-Feb-2019

07-Mar-2019 30-Jun-2019

Museums of Freedom Struggle Jail

120 Feasibility Report submitted

20-Dec-2018

30-May-2019

30-May-2019

01-June-2019

30-June-2019

30-Aug-2019

RFP under preparation

Museums of spices 150 Feasibility Report submitted

20-Dec-2018

15-June-2019

15-June-2019

01-June-2019

15-July-2019

30-July-2019

Building confirmation awaited

Development of Ethnic Food Hub

(PPP) Feasibility Report submitted

20-Dec-2018 20-Feb-2019

Development of Dutch palace node parking area and palace street entry

110 Tender issued 20-Dec-2018

20-Feb-2019

7-Mar-2019 30-June-2019

Fort Kochi Beach Front improvements - Vasco Square

158 Tender issued

20-Dec-2018

28-Feb-2019

07-Mar-2019 30-Sept-2019

Project to be re- tender

Fort Kochi Beach Front improvements - Phase II

500

Feasibility report Submitted

28-Feb-2019

01-June-2019

30 June-2019

30-Aug-2019

Mattancherry Walkway 1100

Feasibility report Submitted

20-Dec-2018

15-June-2019

15-July-2019

15-July-2019

14-Aug-2019

14-Oct-2019

Approval awaited. Stakeholder consultations to be conducted

Page 92: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 92 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Name of Project - REVISED SCP Projectivisation

Original Project Cost as per SCP (Rs. in Lakh)

Clubbed / Segregated/ Estimated Cost (Rs. in Lakh)

Stage of project

Submission/Timeline Feasibility Report

Submission/Timeline DPR

Submission/Timeline Tender Proposed

Contract Award timeline

Remarks As per April 2019

Proposed Revised Timeline

As per April 2019

Proposed Revised - Timeline

As per April 2019

Proposed Revised Timeline

Cultural Corridor - PT Usha Road

100 Feasibility Stage

30-May-2019

30-June-2019

15-June-2019

15-July-2019

15-July-2019

14-Aug-2019

30-Oct-2019

Scope is being finalised

Spatial Mapping of assets and SCADA systems for Information gathering with monitoring centres

1500 50 DPR Submitted

- 21-Dec-2018

- To be tender by KMC

Integrated Command, Control and Communication Centre (IC4)

10000 6450 LoA issued 15-May-18

20-May-18

26-Apr-18

28-Feb-2019

23- May-2018 28-Feb 2019

Page 93: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 93 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Project planning

Page 94: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 94 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 95: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 95 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 96: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 96 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 97: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 97 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 98: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 98 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 99: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 99 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 100: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 100 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 101: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 101 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 102: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 102 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

3 WAY FORWARD

3.1 KEY CONCERNS

• KMC to start with confirmation of land for rehabilitation and agreements with

vendors Ernakulam market area

• Confirmation from KMC regarding Broadway market project

• No progress made by KMC regarding housing project. Smart city has limited time

for implementation hence same needs to be expedited by KMC.

3.2 ISSUES AND CONCERNS

3.3 ASSISTANCE REQUIRED

Finalisation of project scope. As we will be entering another year of SCM we need to

expedite project scope with stakeholders at the earliest.

List of projects requiring CSML assistance in finalizing the scope and conducting

stakeholder meetings

•Projects & scope not yet identified

•PMC to carry out multiple meetings to identify & finalise scope of projects

Identification of Project

•Once broad scope is identified stakeholders are informed

•Delayed response

•Continuous chasing required

•Change in project scope many times

•Multiple stakeholders within same organisation

Stakeholder management

•List of beneficiaries

•List of hawkers

•List of slums

•Timely Site clearances

KMC approvals & data

•Process for taking permisisons requere purchase of forms, stamp papers foraffidavit. CSML to purchse these forms as other stakeholders have nottendered thep rojects thus, unable show such costs

•Key agencies yet to appoint nodal person

•Nodal person to assist in provision of data, scope and approvals

•CSML to include nodal officers from key staekholder (owner of the project fromthe signing of the contract so that hand over at time of completion is easy andknown to owner.

Tendered projects & to be awarded

Page 103: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 103 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Table 3-1: Projects requiring stakeholder assistance

Project name Approx. Broad cost INR CR.

Assistance required

PROJECTS UNDER PROGRESS (FEASIBLITY REPORT / DPRS UNDER PREAPRATION) Smart water solutions - smart metering and smart valves for all connections in ABD

1.00 CSML to share letter with KWA requesting meeting to finalise scope.

Restoration of Mullassery Canal - including linking of standardized area drains

1.00 Confirmation on stretch of Canal to be taken up under Smart City scope. Surveys for additional stretch to be carried by SPV. Restoration of Market Canal - walkways and

market square around the canal pond, solar paneled roofs, led lighting, light posts

5.00

Restoration of Kalvathy Canal and area drain improvement - open spaces, street furniture and landscaping features

20.00

Restoration of Rameswaram-Kalvathy canal - upto cochin college – walkways and linking the canal bank road

15.00

Broadway street upgradation 10.00 CSML conducting various meetings. Ernakulam market redevelopment 100.00 CSML conducting various meetings. KMC to

lead with R&R Standard hawker zones in Fort Kochi + standardize structures for "petti kada"

5.60 Feasibility report to be submitted by 30 June 2019. Based on FR submitted combined stakeholder meeting to be conducted

MLCP at KTDC 7.00 Letter and meetings with stakeholders to finalise locations for tendering

Museum of freedom struggle 1.20 Letter to KMC & Stakeholders regarding scope of project formulated by CSML

Museum of spices history 1.50 Letter to KMC requesting for confirmation on space.

Mattancherry walkway 11.00 Combined stakeholder meeting Cultural corridor - Pt Usha road 0.50 Letter to KMC regarding scope of project

formulated by CSML Fort Kochi beach front improvements - part B walkway & beach

5.00 Combined stakeholder meeting & letter to stakeholders

Construction & upgradation Thuruthy, Kalvathy & Konchery colony - construction of bridges

5.15 Letter to KMC for confirmation on scope and location of Bridges.

Development of open spaces 2.50 Letter to KMC for confirmation and approval of open spaces and parks selected and proposals

Anganwadis 3.00 Letter to KMC & ICDS Combined stakeholder meeting for confirmation and approval of selected Anganwadis and proposals

PROJECTS REQUIRING STAKEHOLDER MEETINGS & CONFIRMATION ON SCOPE FOR FURTHER ACTION (PREPARATION OF REPORTS UNDER SCM)

Standard wifi enabled bus stands with commercial space development

3.00 Combined stakeholder meeting & letter to stakeholders

Construction of Second Tower at Thuruthy 35.00 Letter to KMC. Project preparation will require time. Minimum 3 months for DPR & tender preparation. Hence to enable tendering confirmation regarding project scope to be shared at the earliest.

Integrated redevelopment of slum housing 47.00 Letter to KMC Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM

Page 104: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 104 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

duration confirmation on scope to be shared by KMC at the earliest. R&R will require additional time. With limited SCM duration. Confirmation on scope needs to be expedited.

Spatial mapping of assets 0.35 (ABD) Letter to KMC. DPR shared, scope shared. KMC to tender the project at the earliest. CSML to follow. As of now no meeting required.

Smart & improved battery-operated tricycles for primary waste collection at West Kochi & Ernakulam in ABD area

1.00 Letter to KMC on further action required

Improvements to sewer collection system for mainland

35.00 Letter to KWA & KMC Project preparation will require time. Minimum 3-4 months for DPR & tender preparation depending on project scope. Hence to enable tendering and implementation within SCM duration confirmation on scope to be shared by KMC at the earliest. With limited SCM duration. Confirmation on scope needs to be expedited.

Kacheripady commercial complex 5.00 Letter to KMC. Option 1: Existing building to be upgraded for commercial development Option 2: demolition of existing building and new commercial structure. Option can be assessed based on KMC’s requirement.

Mangalavanam eco-restoration project 1.00 Combined stakeholder meeting & letter to stakeholders

Extend ‘Smart wi-fi bus shelters’ with led bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

0.60 Combined stakeholder meeting & letter to stakeholders

Mattancherry spice market redevelopment

Combined stakeholder meeting & letter to stakeholders

Upgradation of community centre at Mattancherry with indoor sports facilities

1.00 Combined stakeholder meeting & letter to stakeholders regarding further action required on this project.

CSML to provide way forward on projects to be taken up based on funds available.

3.4 WAY FORWARD FOR FEW PROJECTS

Following convergence & SCM projects are proposed to be dropped from Central MIS

maintained by MoHUA.

Table 3-2: Projects proposed to be dropped from CENTRAL MIS

Project name SCP cost INR CR.

Suggestion

24 X 7 WATER SUPPLY - PAN CITY 621 Based on input received from MoHUA during Video conference held for 100 Smart Cities, it is proposed that as implementation duration for 24x7 water supply project will not be in sync with Smart City implementation duration hence

Page 105: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 105 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

the project may be dropped and formal approval may be taken from all associated stakeholders.

Water supply projects in ABD proposed to be implemented by KWA under 24x7 water supply project

Approx. 90 Cr.

Water supply projects in ABD proposed to be implemented by KWA under 24x7 water supply project

Upgradation of community centre at Mattancherry with indoor sports facilities

1 As per KMC there is no community centre at Mattancherry requiring upgradation. Hence the project may be dropped. KMC to share final confirmation.

3.5 OVERALL STAKEHOLDER ROLES & RESPONSIBILITIES

S. No. Stakeholder Responsibility

1. Kochi Municipal Corporation

(KMC)

► Council approval including review and suggestion on

proposal

► Provision of rehabilitation land

► Conduct public consultations

► Relocation & rehabilitation (R&R) of existing vendors

► Carry out O&M post construction

► Event management

► Appointment of Nodal Officer for the Project

2. Cochin Port Trust ► Approval for the navigational area, as it should not interfere

with inland water routes etc.

► Approval for the projects within the jurisdiction of Cochin Port

Trust

3. District Collector ► Suggestions and approval of related projects

4. Police Department ► Suggestions and approval of related projects

5. Kerala Water Authority ► Integrating the proposed water metering & Sewerage system

with KWA SCADA software

6. Kerala State Electricity Board ► Approval of projects as applicable

► Approval and support in integrating the KSEB control room

(APIs) with IC4 project

► Inspection during implementation of net meters

7. RTO – Transport Department ► Sanctioning of permit and intermediate inspections

8. District Tourism Promotion

Council

► Promotion of tourism projects and open spaces projects

9. State Water Transport

Department

► Permission to go ahead with the pedestrian link between

Ernakulam Jetty and Subhash Park

10. Revenue Department ► Suggestions and approval of related projects within the

jurisdiction of Department

11. KMRL - Water Metro ► To incorporate continuous walkway through proposed boat

jetties

12. Kerala Irrigation Department ► Approval for utilizing canal surface for pumping stations

► Approval for discharging treated water into canal

13. Cochin Heritage Zone

Conservation Society

► Suggestion and approvals as required

14. Fire & Rescue Department ► Sanctioning of permit and intermediate inspections

Page 106: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 106 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

S. No. Stakeholder Responsibility

15. Public, Residential Welfare

Associations, NGOs, Social

workers

► Public Participation in events organized.

16. Food Safety and Standards

Authority of India (FSSAI)

► Sanctioning of permit and intermediate inspections

17. District Child Welfare Society ► Permission to go ahead with construction activity in Indira

Priyadarshini Children's Park

18. Vendor Associations ► Assistance with relocation & rehabilitation

Page 107: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 107 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 108: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 108 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

4 SMART CITY PROJECTS IN MEDIA COVERAGE

Following table provides an overview of projects and locations in ABD covered in media.

Sl

No

Date News Paper Headlines Link Screenshot

1 07.05.2019 The Hindu Consortium

selected to set up

IC4 under Smart

Mission

https://www.thehindu.com/new

s/cities/Kochi/consortium-

selected-to-set-up-ic4-under-

smart-

mission/article27052521.ece

2 14.05.2019 Indian

Express

Rajiv Awas

Yojana: Their

dream for a house

in limbo

http://www.newindianexpress.c

om/cities/kochi/2019/may/12/raj

iv-awas-yojana-their-dream-for-

a-house-in-limbo-1975975.html

Page 109: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 109 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl

No

Date News Paper Headlines Link Screenshot

2 22.05.2019 Times of

India

Kochi kids flock to hi-tech anganwadis

https://timesofindia.indiatimes.c

om/city/kochi/kids-flock-to-hi-

tech-

anganwadis/articleshow/69435

937.cms

3 27.05.019 Times of

India

Litterbugs to come under surveillance

https://timesofindia.indiatimes.c

om/city/kochi/litterbugs-to-

come-under-

surveillance/articleshow/69510

141.cms

Page 110: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 110 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl

No

Date News Paper Headlines Link Screenshot

4 29.05.2019 Times of

India

Corporation to demolish unauthorised building extensions at broadway

https://timesofindia.indiatimes.c

om/city/kochi/corp-to-demolish-

unauthorized-bldg-extensions-

at-

broadway/articleshow/6954980

0.cms

5 30.05.2019 Malayal

Manorama

Broadway Operation

https://localnews.manoramaonli

ne.com/ernakulam/local-

news/2019/05/29/ernakulam-

broadway.html

Page 111: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 111 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl

No

Date News Paper Headlines Link Screenshot

7 31.05.2019 Times of

India

Shopowners at Broadway continue to violate rules

https://timesofindia.indiatimes.c

om/city/kochi/shopowners-at-

broadway-continue-to-violate-

rules/articleshow/69589006.cm

s

Page 112: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 112 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

ANNEXURES

ANNEXURE 1: STAKEHOLDER MEMOS

Date 04.05.2019

Office Visited Greater Cochin Development Authority (GCDA), Kochi

Need / Reason

for Site visit

• To discuss the Marine Drive walkway project proposed by CSML and to ensure its effective implementation.

Location • The Greater Cochin Development Authority (GCDA), Ernakulam, Kochi

Stakeholders

met

• Mr. V. Saleem, Chairman, GCDA

• Mr. Rajesh, Senior Town Planner, GCDA (point of contact with GCDA)

• Representatives from various GCDA departments

Important

discussion

points

• CSML presented the Marine Drive Walkway proposal to the GCDA team. Proposals

identified two stretches – High Court Junction to Tata Canal (Stretch 1) and High Court

Junction to KSRTC/ Boat Jetty area (Stretch 2). Stretch 1: involves landscape proposals,

planters/seating around new trees, new coping stone and relaying of old coping stone

as surface finish for existing retaining wall, relaying and levelling of around 50% surface

area using the concrete pavers. Stretch 2: provision of new lighting, relaying of existing

tiles with concrete pavers, streetscaping, landscape and lighting.

• Discussions centred around the extent of intervention, clarifications on execution

timeline, maintenance, management of existing advertising contracts, electrical costs

and revenue issues.

• Mr Rajesh, Senior Town Planner of GCDA, was appointed as the point of contact for

further interactions with GCDA on the project. Co-ordination with various GCDA teams

will be done through Mr Rajesh.

Action Points • CSML to forward an official letter to GCDA (within a week), along with a project brief and

detailed drawings explaining the exact scope of intervention, and clarifications on

maintenance of infrastructure, advertisement areas, potential revenue and issues post

CSML’s maintenance period.

• Further to study and clarifications of the above project brief, GCDA will give their formal

reply.

List of Attendees

from CSML/ PMC

1. Clipson Mathew, Deputy General Manager, Cochin Smart Mission Ltd. 2. Anitha, Environmental Engineer, Cochin Smart Mission Ltd. 3. Abhishek Xavier, Urban Designer, IPE Global, Kochi Smart City PMC 4. Ramanujam S, Associate Architect, IPE Global, Kochi Smart City PMC

Memo No: Ernakulam Market

DIVISION

/LOCATION Ernakulam Market Stall Owner’s Association(EMSOA), Basin Road

DATE AND

TIME 06.05.2018, 12:00 AM

ATTENDEES

1 Shri. APM Mohammed

Hanish IAS

MD, CSML

2 Mr. George EMSOA, President

3 Mr. Shageer Mohd KMCC, General secretary

4 Ms. Raji R GM, CSML

5 Mr. Ajayakumar Team Leader, PMC- CSML

Page 113: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 113 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

6 Other officials from CSML & PMC, and Market associations

AGENDA Understand the functioning of market and conclude on a suitable proposal for Market

redevelopment

SUMMARY All the suggestions by Market association members shall be incorporated and the final

proposal shall be discussed in the next meeting in same venue on 13th May 2019 @ 3 pm.

Brief of Site visit:

• A Site visit was conducted by the Ernakulam Market stall owners Association (EMSOA) president along with other members of association to explain the current functioning of the market to MD of CSML and other officers of CSML and PMC.

• The visit started from Market road moving around the Ernakulam market, inside the existing market, the market square, auction area, banana stalls and other roadside vendors along basin road.

• Representatives of the Ernakulam Market explained all the activities and movement pattern to MD and other staff in detail at all the locations.

• Upon completing the site visit, MD, CSML took an overview of the locations of all the critical areas and the activities involved and decided to review the CSML proposal in detail in EMSOA office in Basin road.

Brief of Meeting:

• MD, CSML requested all the representatives of EMSOA to confirm and agree to the proposal of market redevelopment and assured that the proposal would only be having ground floor and 2 upper floors along with a basement.

• EMSOA expressed their support for the proposal and also confirmed that some stalls shall be shifted to the 1st floor in the new proposal which would include, Fish, meat, poultry and some other goods.

• EMSOA insisted that the ground floor plinth height be reduced in order to facilitate easy loading of goods by labour workers. CSML explained the use of push/pull carts and trolleys to be used within the market complex to assist the movement of goods.

• EMSOA were supportive with the provisions of internal truck loading bays within the proposed complex but expressed a concern that it would affect and reduce the internal shop area.

• It was suggested by EMSOA president and agreed by MD, CSML that the proposal will try to adjust the maximum number of stalls on the ground floor.

• It was decided that the level drop adjacent to canal and behind the hawkers sitting on basin road shall be raised up to road level and increase the road width in basin road. Also, it was suggested the hawkers would be allowed to sit only on the canal side of basin road with a fence between the road and hawking area to restrict encroachment.

• The stalls seated on the market square shall be incorporated in the square itself and mostly be shifted to upper floor on market square which is acting a bridge between market square and complex.

• The proposed development comprises of the following components a. Market complex (B+G+2), b. Market square with MLCP, compactor, goods lift and truck parking, c. Skywalk from Marine drive to Market, d. Canal rejuvenation, and B e. Vehicular Bridge connecting kuttapayi road to Basin road across canal.

Among these, Skywalk, Canal, and road bridge are to be taken up separately under other modules in smart city.

• The EMSOA president suggested to modify the proposals as per their requirements and discussions but give a detailed plan with all shops and areas mentioned.

• It was decided by MD, CSML and agreed by all market association members that the Sizes of shops allotted to each shop keeper shall be standardized into 3 types of modules, viz., small, medium and large units. The detailed shop sizes shall be formulated by CSML and shared in next meeting.

• The next meeting is scheduled for 13th May 2019 at 3 pm with the Market association members to discuss the final proposal and finalize the design. After which the proposal shall be shown to Mayor, Collector and GCDA chairman to get the approval and consent to use GCDA ground as temporary rehabilitation land during the construction of the complex.

• Once the proposal if confirmed by all the concerned stakeholders, the proposal shall be discussed in an open forum with all stall owners of the market.

Site visit images:

Page 114: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 114 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

PROJECT & VENDOR: VENUE:

Taj Gateway,

Ernakulam

Integrated Command Control and Communication Centre:

Fluentgrid limited in consortium with BEL

SUBJECT: Kick off Meeting for Integrated Command Control and Communication Centre : Fluentgrid limited

in consortium with BEL

PRESENT

CSML / PMC KMRL KSEB/KWA/ CONTRACTOR

1. Shri APM .Mohammed

Hanish MD,CSML

1. Sagar M,

SIGNAL &

TELECOMMUN

ICATION

CONSULTANT

1 Usha Mol P A,

Assistant Engineer,

KWA

1 Mr Vinod

Srivastava, SVP

Sales, Fluentgrid

2. Mr.Clipson Mathew

,DGM CSML

2 Anoop Mohan

KMRL

2 Mohammed Kasim,

EE, KSEB

2. Mr Vikas Narahari,

VP Account

Management,

Fluentgrid

3. Mrs.Binnya Joseph, IT

Manager CSML

3 Mr. Sunil D, GM

, OP& ST,

KMRL

3 R Rajash, EE, KSEB 3. Mr Ravi T, VP,

Delivery,Fluentgrid

4. Mr.Ajay Kumar

TL,PMC

4 James M , Chief

Engineer, KSEB

4

.

Mr. Sudheer

Nagireddy, Senior

Manager, Sales,

Fluentgrid

5. Surabhi Kureel

PM,PMC

Dennis Rajan,

Asst.EE, KSEB

5 Mr Hari Krishna B.,

Solution Architect,

Fluentgrid

Page 115: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 115 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

6. Mr.Koreth V Mathew,

IT Consultant PMC

6 Mrs. Sanjya Vyda,

Project Manager,

Fluentgrid

7. Riby Mathew,

Urban Planner, CSML

7 Mr. Praveen K,

GIS manager,

Fluentgrid

8. Anitha Mohan,

Environmental

Engg.Dept, CSML

8 Mr. Siva Rao,

Sr.Engagement

Manager,

Fluentgrid

9. Benty VA, CFO,CSML

10. Rajath R, IT Associate,

CSML

11. Soubhagya

Procurement Expert ,

PMC

12. Arun Savi

Sr.Manager, PMC

13. Karunakaran MN

Energy Expert, PMC

14. K K Paily

Road Engineer,PMC

15. Renuka K

Construction Manager,

PMC

16. Shafeena

Research

Associate,PMC

17. Manish

MIS Expert, PMC

18. Balamurugan

Solution Architect,

PMC

SL

N

O.

POINTS DISCUSSED

ACTI

ON

BY

TARGET

DATE

1. Agenda:

Kick off meeting for IC4 project was organized on 6 May 2019.

Same was attended by the implementing agency, KMRL, KSEB, KWA and PMC.

At the outset of the meeting Fluentgrid team introduced the project and welcomed

everyone present.

2. Key points of internal discussions:

a) Fluentgrid Team welcomes MD, CSML and all the officials from CSML & PMC

and other stakeholders who were attended in the kickoff meeting.

b) Mr. Vikas Narahari, V.P sales & Client Engagement started the presentation by

given an overview about various Smart City Projects done by Fluentgrid and also

introduce the team members who are working for Kochi IC4 Project.

Page 116: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 116 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

c) Mrs. Sanjya Vyda, P.M explained about the implementation schedule and action

plan for Kochi IC4 Project

d) Mr. Vikas Narahari, give the detailed presentation about the project objectives,

also he informed that they are going to use BSNL as the network partner. He

encourage the cloud based DC & DR for IC4 and informed that they are going to

use Amazon Cloud for cloud scalability.

e) Mr. Ravi explained the overall solution architecture of the project, Integration

architecture. Also explained how smart elements are going to integrate with IC4

application. Also he explained about the network architecture and data security

at all levels like API manager, Basic authentication, IP blacklist & IP whitelist,

Logging, Time restricted access etc.

f) Mr. Vikas explained about the high level project plan with time limits for setting

up the command control room with common cloud based DC & DR also he

explained about the list of deliverables like inception report, Detailed project plan,

orientation workshop and feasibility report for IC4 physical site.

g) The Fluentgrid team will be develop a Mobile app for the citizen services as

additional scope of work

Stakeholders Interaction

3. The KSEB officials interacted with Fluentgrid team as well as PMC team for

integration of their SCADA system. The Fluentgrid team explained that the SCADA,

Smart grid, Bill Payment system and Grievance Management can be integrated by

providing the API of their smart solution.

4. Mrs. Usha Mol, Asst. Engineer , KWA interacted with Fluentgrid team as well as PMC

team regarding water SCADA, The Fluentgrid team explained that the water SCADA

system is possible by implementing IoT devices to the entire water network structure,

and based on the inputs coming from the IoT devices the water consumption analytics

can be calculated.

Memo No: Ernakulam Market

DIVISION

/LOCATION

Ernakulam Market Stall Owner’s Association (EMSOA), Basin Road

DATE AND

TIME

13.05.2019, 03:00 PM

ATTENDEES

1 Shri. APM Mohammed

Hanish IAS

MD, CSML

2 Mr. George EMSOA, President

3 Mr. Shageer Mohd KMCC, General secretary

4 Ms. Raji R GM, CSML

5 Mr. Ajayakumar Team Leader, PMC- CSML

6 Other officials from CSML & PMC, and Market associations

AGENDA Finalize the proposal for Market redevelopment

SUMMARY Market association shall discuss the proposal with all member and giving final decision on

the layout while CSML shall share the revised layout based on the discussion.

Page 117: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 117 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Brief of Meeting:

• MD, CSML clarified that currently there is funding available for the complete development of the market to its full potential under smart city projects, but funds for this project may not be available for its redevelopment in future under any scheme.

• MD, CSML specified that the upper 2 floors above the 2 floor of existing Ernakulam market would be beneficial to the shopkeepers and there would be a need to provide office spaces, banks, storage, and facilities like e-commerce would be a common factor for the business development of the market.

• MD mentioned that the skywalk would benefit more pedestrian access into the market and enhance the business potential of the market.

• EMSOA expressed their support for the proposal and also confirmed that some stalls shall be shifted to the 1st floor in the new proposal which would include, Fish, meat, poultry and some other goods.

• CSML proposed a layout incorporating all the stalls in market within 2 floors (ground and first) having standard modules of 50, 100, 150, & 200 square feet area.

• Market association insisted on having all the stalls on the ground floor itself, to which CSML clarified that if al the stalls are required on ground floor, then the shop area of shop shall be further reduced and standardized with most of getting 100 square feet area.

• MD, CSML, suggested that all shop owners can be provided space on ground floor with smaller shop area, and any individual who has more area presently, shall be provided the additional area on the 1st floor which can be used for storage of goods or other functions.

• Market association suggested the existing shops on roadside would need to be provided on the roadside itself, and they can be provided with a mezzanine level within the shops.

• MD, CSML added that CSML shall provide 2 options of the layout with either smaller shops on ground with additional on upper floors or standard shop areas divided across 2 floors.

• Regarding rehabilitation land, MD suggested that the proposal shall be discussed with the councillor, Collector, and Mayor and finalize on the transit land.

• MD suggested the market association to discuss the project with GCDA chairman, about the transit land for during the construction period, but Marine drive cannot be guaranteed as an option. Meanwhile CSML shall also present the proposal to GCDA chairman and finalize land options.

• The revised proposal with shop areas shall be provided by CSML to market association.

• President of the market association requested time to discuss the project with all members and conclude on the final proposal, but requested MD, CSML to convene a meeting with all the shopkeepers to get a fruitful result.

Implementation of Intelligent Street Pole at Kochi under PPP on DBOOT model under Smart City Mission,

Kochi

Minutes of Meeting with Mayor and Council Members

DIVISION /LOCATION Mayor ‘s Chamber ,Ernakulum

DATE AND TIME 16-05-2019,11.30 am

Personnel met Mrs. Soumini Jain, Mayor along with council members and Secretary KMC.

AGENDA Implementation of Intelligent Street Pole at Kochi Under PPP on DBOOT model

SUMMARY Mayor shows interest in the concept of Smart Pole project however, mention various

challenges in executing the project discusses action plan

1. Project Background: The project was formulated on Public Private Partnership (PPP) mode and based on in-

principle approval from Worshipful Mayor, EOI was floated. The pre-bid meeting of the EOI with various operators

and was chaired by KMC, Standing Committee Chairman of Works – Mr. Harris. There was interest from five

different concessionaires and is presently in RFP stage. To proceed further with project implementation stage,

support from KMC and its members are a necessity. In this regard, a meeting was conducted under the

chairmanship of Worshipful Mayor and other council members to discuss about the support required from KMC.

2. PMC CSML briefly explained the scope and benefits of the Smart pole project as follows.

3. Scope of the Project.

a. Optimized Telecom Network for 4G and above using Intelligent Street Poles- Inter se distance of 400M.

Page 118: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 118 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

b. 400 Kms of Optical fibre interconnecting the pole will provide a fail proof super-fast data backbone for the

City.

c. Integrated Wi-Fi network with a minimum speed of 10 Mbps.

d. Smart Billboards for mass communication. Smart billboard will also earn advertisement revenue.

e. PA system for announcements and recorded messages pan city to be controlled from the Command and

control centre.

f. Pollution sensors will indicate the condition of the environment and broadcast environmental parameters.

g. SOS application (panic button) for citizen to communicate with command and control Room.

4. Revenue Benefits from the Project: There are two modes of revenue stream from this project as mentioned

below.

a. A fixed premium of Rs.12000 per pole per year for 9m – 12m poles with 10% escalation (minimum 600

poles).

b. A fixed premium of Rs.50000 per pole per year for 25m-30m poles with 10% escalation every year.

c. A fixed annual gross revenue share of 3%.

5. Infrastructure and other Benefits to the City

a. 10 Core OFC for use for the government ( minimum 400 KM)

b. One 40mm HDPE PLB Telecom Duct for laying OFC( min-400 Km)

c. Billboard – 10 minutes per hour for government messages.

d. PA system covering Pan City centrally operated from command and control Room.

e. SOS button for citizens to contact command control centre

f. 30 minutes of free Wi-Fi per day.

g. Free Wi-Fi for browsing Govt websites.

6. Support Required from KMC :KMC Support for the project is paramount for the success of the Project

a. KMC should not give any further license for any installation of any new Telecom tower.

b. Single Window Clearance.

c. ROW for laying the Optical Fibre Cable (OFC) has to be granted by IT Dept., GoK.

d. Waiver of permit fee and Road Restoration fee.

e. Relaxation of KMBR rule with respect to setback limits for poles.

f. Support for providing Electric Power connection to the Smart pole.

7. Points raised by Mayor and Council Members and suggested solutions are discussed below

Points from Mayor and Council Members Solutions and suggestions discussed

1 Removal of existing towers

Mayor enquired about what will happen to the

existing towers (2G/3G).

It was mentioned that together with the old telecom

poles and new smart poles the beauty of the city

will be affected.

So CSML has to take initiatives to remove the old

poles.

• The smart poles will ensure best telecom

coverage in the city with minimum number of

telecom towers. The smart pole being hi-tech

and uniformly designed will add to the beauty of

the city.

• With advent of 4G and higher technology

existing towers shall become redundant. All

operators will get a readymade, state of the art

pan city telecom infrastructure with smart pole

project.

• There will be no need to rely on primitive

technology. Operators are likely to shift onto

smart pole network voluntarily.

• The existing towers can be decommissioned and

removed in a phased manner by not renewing

the license.

2 Mayor wanted a meeting of the telecom operators

providing 2G/3G to ensure coordination in the

transition to smart pole and removal of old telecom

poles

• The meeting of the telecom operators may be

convened by KMC or CSML

Page 119: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 119 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

3 Mayor mentioned that they have already gave

permission to Reliance Services to lay poles

across the entire Ernakulam city two months back

and they are likely to start their work inside the city

• It was requested not to allow any other operator

to construct new towers in KMC area as the

same shall be provided by the concessionaire.

• This is paramount for the success of the project.

• No exclusivity is required for OFC.

4 During the implementation of Smart pole project

road excavation to be minimized and damage

whatsoever should be repaired

• Concessionaire will use HDD technology for

laying the Fiber especially for crossing the roads.

• Only in exceptional conditions, surface will be cut

open (permission will be sought)

• After laying the Fiber, Concessionaire shall be

responsible for road restoration of the cuts if any

made in the road.

5 Revenue Share : Mayor was not clear about the

revenue share arrangement with KMC

• CSML shall inform the details about the revenue

share in consultation with MD CSML.

6 Wavier of road restoration charges: Mayor stated

that the concessionaire will have to pay the road

restoration charges even when the work is done by

Concessionaire.

It may be difficult to get the exemption through

council approval from KMC as it is one of the major

revenue source.

• CSML shall try to get the exemption from

Government of Kerala

7 Advertisement:

As it is PAN city, and only the concessionaire will

be benefited from the advertisements. Also, the

revenue from advertisement to be with KMC

• No exclusivity for advertisement is provided. So,

other agencies can also place advertisement

boards in the KMC area.

• The revenue from the advertisement board will

with concessionaire and shall share with KMC as

fixed revenue share

Attendees from Kochi Municipal Corporation

S. No.

Name Designation and Organization

1 Smt. Soumini Jain Worshipful Mayor, KMC

2 Sri. P M Harris Standing Committee Chairperson, Works

3 Smt. Shiny Mathew Standing Committee Chairperson, Town Planning

4 Sri. K V P Krishnakumar Standing Committee Chairperson, Tax Appeal

5 Sri. C B Sabu Standing Committee Chairperson, Welfare

6 Sri. David Parambithara Councillor, Ward 61

7 Sri. R. Rahesh Kumar Additional Secretary, KMC

8 Sri. Titus Executive Engineer, KMC

Attendees from CSML and PMC

S. No.

Name Designation and Organization

1 Mrs. Binnya Joseph IT Manager, CSML

2 Mr. Rajath Assistant Manager, CSML

3 Mr. Korath Mathew E-Governance and IT Expert, IPE Global, Kochi Smart City PMC

4 Mr. Arun Savi Senior Manager, IPE Global, Kochi Smart City PMC

5 Mrs. Renuka Construction Manager, IPE Global, Kochi Smart City PMC

6 Mr. Balamurugan Solution Expert, IPE Global, Kochi Smart City PMC

7 Mr. Manish MIS Expert, IPE Global, Kochi Smart City PMC

8 Mrs. Shefeena KS Research Associate, IPE Global, Kochi Smart City PMC

Page 120: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 120 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

REF NO.:

PROJECT & VENDOR: VENUE: KRML Conference room 8th Floor, Revenue Tower

Intelligent Traffic Management Systems (ITMS): Kerala State Electronics Development Corporation Limited (KELTRON)

SUBJECT: Kick off Meeting for Intelligent Traffic Management Systems (ITMS): Kerala State Electronics Development Corporation Limited (KELTRON)

PRESENT

CSML / PMC KMRL KSEB/GIDA/Police CONTRACTOR

19. Shri APM .Mohammed Hanish MD,CSML

4. Mr.Abdul Kalam DGM KMRL

1 KR Rajeev,Town Planner ,GIDA

1 Binsun N.T Asst Manager,Keltron

20. Mr.Clipson Mathew ,DGM CSML

2 Anoop Mohan KMRL

2 Nazeer M.A ACP,Traffic West

5. Gopakumar S.P Head,Keltron Communication Division

21. Mrs.Binnya Joseph, IT Manager CSML

3 Gokulnath .k ,KMRL

3 Vinod C.S ACP,Traffic East

6. Vijeesh .V Sr.Engineer Keltron,Traffic

22. Mr.Ajay Kumar TL,PMC

4 Sivan N.K MVI-RTO-EKM

4. Srijith C.S Sr.Engineer Keltron,Traffic

23. Surabhi Kureel PM,PMC

Bijumon SP MVI-RTO-EKM

5 Lal.P Sr.Engineer Keltron,Traffic

24. Mr.Koreth V Mathew, IT Consultant PMC

6 Hameed A.A Sr.Engineer Keltron,Traffic

25. M.Imtiyaz Ahamed Transport Planner,PMC

SL NO.

POINTS DISCUSSED ACTION

BY TARGET

DATE

5. Agenda: Kick off meeting for ITMS project was organized on 18 May 2019. Same was attended by the implementing agency, KMRL, Traffic Police, GIDA, PMC and the Contractor. At the outset of the meeting CSML introduced the project and welcomed everyone present.

6. Key points of internal discussions: KELTRON

Page 121: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 121 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

➢ KELTRON during the meeting submitted PBG, contract document, solution document. KELTRON added that the solution document is to be revised based on site visits to be conducted. CSML mentioned that a revised solution document is to be submitted by KELTRON with 5 modified locations, locations which require dismantling of street furniture and detail of the project team, Staff schedule and detailed implementation schedule.

➢ Proposed joint site visit along with members from PWD, Police, KMC, GIDA, GCDA etc.

➢ Based on the site visit, there are lot of street furniture’s to be dismantled and removed – CSML replied that, stakeholders will be identified, and request will be made for the same. CSML requested to have the stakeholders and list required to be added in the revised solution document

➢ Request for space for storing of equipment – CSML responded that the SPV does not have any asset hence the material to be stored in space available with KELTRON.

➢ CSML also pointed out that till commissioning supply material is to be taken care of by the vendor. KELTRON agreed to the same

➢ Keltron stated that, Aroor manufacturing plant can be utilised for storing the equipment. KELTRON to share facility detail

➢ To manage delay, the implementation schedule is modified as 6+1 months ➢ For connectivity, MPLS VPN through OFC and as per proposal, the network

partner is BSNL ➢ The structural details of poles are provided with solution document.

7. CSML requested KELTRON to share recurring expense for ITMS project post completion of O&M period for submission to Traffic Police

KELTRON 30 May 2019

8. CSML requested the vendor to submit the following at the earliest to enable smooth implementation initiation of the project. ➢ Organization set up & CVs (Along with detailed contact information) ➢ Communication Matrix ➢ Date for initiating the project ➢ Implementation schedule ➢ Meeting schedule to be finalized and adhered upon. Meeting must be

conducted Fortnightly/Monthly basis. ➢ Another important aspect stressed upon was Health & Safety during

implementation for all aspects.

9. Material testing will be carried out by KELTRON as a routine exercise for all the components and the test certificates for the same will be submitted by KELTRON to PMC.

10. KELTRON requested for date for joint site visit. CSML suggest KELTRON to prepare detailed agenda for site visits including grouping of sites stakeholder wise Later during joint stakeholder discussion, 27th & 28th of May 2019 were proposed by stakeholders for joint site visit.

11. KELTRON was informed regarding other parallel project ongoing under Smart City and need for integration if any

- Sewerage in ward 1,2,3,4 &5 in West Kochi - Intelligent Traffic Management System Pan city (Kochi Municipal

Corporation area) - Smart poles pan city - Smart LED lighting

Coordination and planning for these projects is key to successful delivery of all projects.

12. Action points for KELTRON is provided in table 1

13. Key contacts for communication with CSML & PMC hared in annexure 1

14. Communication channel for the project shared in annexure 2 Contractor to share updated overall communication flow.

15. Letter to be submitted stating reasons for delay in submission of PBG with reference letters from Bank

From 1200 hours joint stakeholder meeting started

16. Traffic police confirmed that location now proposed are confirmed.

17. CSML requested traffic police to handover Control Centre location KELTRON to share detailed plan by when the same will be required

18. Meeting ended with Thanks to the Chair and all present.

Page 122: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 122 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Memo No: Department Name: KMC

VENUE KMC

DATE AND TIME 20.05.2019, 12:00 AM

NAME OF PERSON MET Ms. Sabitha, Section Clerk, Tourism Department (as directed by Ms. Kamalamma, Tourism Deputy Director)

AGENDA Regarding initiatives of Tourism Department at Fort Kochi Beach Area

Brief: The projects around Fort Kochi area, currently under timeline of Tourism department are:

1. Museum of Cultural Mosaic, Mattancherry 2. Development of Kochi Tourist Destination – Regarding the construction of sea wall at Fort Kochi

South beach where walkway and beachside got impacted during sea attack. The project worth 1.78 Cr is submitted to working group committee through Irrigation Department

3. Protection of Chinese Fishing Nets 4. Nehru park and Food Court, Fort Kochi 5. Information Centre, Fort Kochi etc.

Redevelopment of Sea Wall Project Project Name: Reformation of sunken seawall for a length of 65M from the boundary of INS Dhronacharya towards Fort Kochi including the restoration of side wall of walkway with Geo textile tubes between CP stone 1066 and 1068 (200m) at Fort Kochi Location Map:

Detailed Drawing:

List of Participants:

Page 123: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 123 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

1. Anu. K. Soman

Memo No:

DIVISION /LOCATION Greater Cochin Development Authority Office

DATE AND TIME 21-05-2019, 03:00 PM

Personnel met Jeby Jomy (Superintending Engineer) Rajesh T.N. (Town Planner) GCDA Team

AGENDA • To discuss on the submitted Marine Drive Walkway- Project Brief

SUMMARY The project details were briefed and project will be taken up for approval from GCDA Executive Council

Brief of meeting: Major Discussion Points:

• Project components and Maintenance measures were explained by the PMC.

• Electric charges for 104 street lights and 20 bollards were discussed, which is approximately Rupees 1.5 lakh/ annum.

• GCDA shall confirm whether railings are required along the walkway. However, it was confirmed that existing railings were installed to provide limited access to boating facility and not for safety of the visitors.

• GCDA confirmed that provision or renovation of existing or new kiosks would require provision of new license numbers from KMC

• CSML/PMC shall confirm whether provision of new license numbers is possible from KMC.

• GCDA further confirmed that the walkway shall not be covered.

• GCDA confirmed that Ar. Kuldeep Singh who has prepared the Master Plan for Marine Drive, in principle opposed the concept of MLCP in the area as it would not be environment friendly.

• Since, the proposal mainly includes streetscaping measures. GCDA shall further confirm whether an actual confirmation is required from Ar. Kuldeep Singh for the proposed development.

• CSML/PMC mentioned the tendering dates for the Marine Drive Walkway project.

• GCDA informed to prepare a construction schedule in consultation with the bidder so that the convenience of visitors and vendors can be maintained.

• GCDA shall confirm with the existing advertisement vendor about the advertisement arrangements and revert back.

Action Points:

• GCDA and CSML/PMC shall confirm the respective required details

• GCDA shall further take up the project for approval from the Executive Council.

List of Attendees from Cochin Smart Mission Limited (CSML) Team:

S. No. Name Designation and Organization

1 Clipson Mathew DGM, CSML

2 Abhishek Xavier Urban Designer, IPE Global, CSML PMC

3 Anitha Mohandas Environmental Engineer, CSML

4 Davesh Sharma Analyst, IPE Global, CSML PMC

Memo No:

DIVISION /LOCATION Greater Cochin Development Authority Office

DATE AND TIME 21-05-2019, 05:00 PM

Personnel met GCDA Chairman

AGENDA • To discuss on the submitted Marine Drive Walkway- Project Brief

SUMMARY Marine drive walkway progress was updated and further confirmation shall be provided by

GCDA.

Brief of meeting: Major Discussion Points:

• Progress on the Marine Drive walkway was discussed.

• The Chairman expressed interest to organize the existing haphazard boat mooring facility along the walkway as another project.

• The PMC presented the Marina proposal in brief and the Chairman expressed interest to take up the project.

Page 124: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 124 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

• The Ernakulam market project and issues to be faced during rehabilitation were also discussed. Action Points:

• GCDA shall provide confirmation and further actions for the above mentioned project.

List of Attendees from Cochin Smart Mission Limited (CSML) Team:

S. No. Name Designation and Organization

1 Jeby Jomy Superintending Engineer, GCDA

2 Clipson Mathew DGM, CSML

3 Abhishek Xavier Urban Designer, IPE Global, CSML PMC

4 Anitha Mohandas Environmental Engineer, CSML

5 Davesh Sharma Analyst, IPE Global, CSML PMC

Page 125: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 125 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 126: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 126 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 127: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 127 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Memo No:

DIVISION /LOCATION

Revenue divisional office, Fort Kochi

Date & Time 28.05.2019, 03:00 pm

Personnel met Mr. Snehil IAS, Sub-collector, Fort Kochi

Agenda Approval of the Proposed Freedom struggle Museum and other projects in Fort Kochi

Brief of meeting: Freedom Struggle Museum:

• The sub-collector was keen to get the projects implemented in fort Kochi and inquired about the status of tendered projects of Vasco square development.

• Sub-collector (SC) approved the proposal for Freedom struggle museum, and but informed that he had a proposal to build a single storey senior citizen counseling room building as an extension of RDO in the additional vacant land of 8 cents which CSML is proposing to develop along with the Museum project.

• PMC clarified that constructing a building in that land would require approval from Archaeological survey of India as it is within 300 meters from ASI protected monument of St. Francis Church. Hence, CSML may not be in a position to propose construction of that building.

• But CSML agreed to revise the existing proposal such that a sufficient space allotted for a small building to be constructed in future by RDO.

• SC confirmed that he shall issue a letter from revenue department confirming the proposal and usage of additional land for the Museum project.

Other projects:

• With regards to parks and open spaces project, Sub collector reviewed the proposal and mentioned that he has some suggestions of outdoor gym furniture which can be added in the proposal.

• Regarding Beach upgradation proposal, PMC requested SC to coordinate or inform if the Irrigation department would be interested to take up the construction of sea wall all along the fort Kochi water edge under smart city funding.

• SC agreed to coordinate with irrigation department and inform about the possibility of construction of sea wall.

• PMC clarified, that CSML can proceed with the beach upgradation project only if the seawall construction taken by another agency.

List of Attendees from Kochi Smart City Team

S. No. Name Designation and Organization

1 Anand Nair Associate Architect, IPE Global, Kochi smart city PMC

2 Jishnu Pillai Asst. Construction Manager, IPE Global, Kochi smart city PMC

PROJECT & VENDOR: VENUE: KRML Conference room 8th Floor, Revenue Tower

Rejuvenation of Canals In Kochi

SUBJECT: Stakeholder consultation on the Rejuvenation of Canals in Kochi – ABD Area

PRESENT

CSML / PMC KMRL IRRIGATION DEPT/ KWA/KMC/AMRUT/

JNNURM

NIUA

26. Riby R Mathew 7. Mr.Abdul Kalam AGM KMRL

1 Radhakrishnan.K; Ex.E, Irrigation Division, Ekm

1. Priyanka Mehra Research Associate

27. Mr.Ajay Kumar TL,PMC

2 Ajith.A.Nair, AGM, KMRL

2 Santhosh A.K Urban Planner, AMRUT

2. Dr.Debjani Ghosh Associate Professor

28. Surabhi Kureel PM,PMC

3 Abdullakutty.K.K Chief Project Consultant Water Transport

3 Joachan Joseph Executive Engineer, JNNURM

3. Asif Raza Research Associate

29. Dr.N.Balasubramanian, Infrastructure Specialist, PMC

4 Girija; Sr. Consultant - Civil

4 Vibin Kumar, Overseer, KWA (Sewerage)

Page 128: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 128 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

30. Renuka.K, Construction Manager, PMC

5 Shibu A.J, AE, KWA Sewerage

31. Pradyumna Mackchand, Canal Expert, PMC

32. Anitha Mohandas; Environmental Engineer

SL NO. POINTS DISCUSSED ACTION

BY

TARGET

DATE

1. Agenda:

Stakeholder consultation to discuss Canal Rejuvenation finding based on

feasibility report prepared by PMC. At the outset of the meeting CSML

introduced the project and welcomed everyone present.

2. Key points of internal discussions:

➢ Current situation of the canals under ABD area was discussed and the presentation of the feasibility report submitted was explained by Pradyumna Machhkhand, Canal Expert, PMC. Current situation, navigability and other constraints like social and environmental issues regarding the rejuvenation of the canal were elaborated.

➢ Regarding the Ernakulam Market Redevelopment Abhishek Xavier- PMC, explained the plan for constructing the Multi storied building for the Market shops. Navigability of the market canal was also discussed

➢ Regarding the Kalvathy Rameswarm Canals – the bridges formed over the canal was a topic of discussion. It was pointed out that many constructions including houses and shops were found to be constructed at the edges of the canal side wall especially the Mullasserry canal and the Kalvathy canal.

➢ Alternative methods of the rejuvenation and controlling of the storm water, sewerage and other wastes flowing to the canals was also a topic of discussion. Suggested alternative methods were (1) New trunk Sewer System with a proposal of STP. The site of STP may be proposed at the GCA parting area near the mouth of the canal. (2) New Trunk Sewer System to be integrated with the existing sewer network.

➢ Had carried out the hydrological study for all the three canals within the ABD catchment area and recommended for raising the side wall in the Feasibility Report. Also suggested the sheet piles construction at the boundaries of the existing walls of the canals for avoiding the damages of the side walls. The construction cost (excluding the urban designs, sewerage and other miscellaneous cost) for this construction is also mentioned in the feasibility report.

➢ Concluded the presentation with a note of improvement and additions to the feasibility report.

PMC

3. CSML requested the stakeholders for the suggestions and queries if any on

the report presentation.

4. Mr. Abdul Kalam, KMRL and Mr. Ajith, Mr.Abdullakutty K.K Water Metro

suggested the below points

1. Mention the width of the canals in the Feasibility report. 2. A holistic development with a combined system (STP and New trunk

system has to be combined and considered) 3. Water metro, suggested for pile and slab construction for the walls for

the canals. CSML & KMRL suggested to evaluate value for money engineering solutions.

4. How the construction of walls along the canal will be done should be detailed in the DPR.

5. Also informed Rameswaram canal renovation is put in consideration of the tourism project. And advised CSML to take forward with the Kalvathy and Mullassery Canal.

6. Social issues to be taken care with consulting the approving agencies 7. The catchment area must include the sewerage network area

considering with the storm water area and whole area of the canals for

KMRL

and Water

Metro

Page 129: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 129 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

the study purpose and proposal has to be submitted for the rejuvenation of the canals.

8. CSML mentioned that external agencies such as GIZ are keen to support CSML in funding for surveys. Detailed survey of canal including for that outside ABD covering entire canal stretch can be taken up by GIZ

9. Navigation of small tourist boats should also be proposed after the rejuvenation of the canals

10. The sewerage flowing to the canals has to be prevented and the alternatives has to be considered and discussed.

11. The Market Canal is already under the water metro project. For this 36 houses needed to be rehabilitated. It has to be confirmed whether design and implementation of Market Canal is to be taken up under Smart City or Water Metro.

12. Enhance the existing sewer system not required as the 50% of the pumping is only in use.

5. Suggestion from KMC AMRUT team

1. Catchment area to be taken into consideration including the drainage systems attached to the canal. Sewerage network area should also be considered along with the storm water area.

2. Reconstruction and protection of walls and residential areas near the canal has to be considered

3. How the sewerage coming to the canal can be stopped to be planned

6. KWA Sewerage: Asked what action or support has to be taken from their

side. If so, it may be discussed with the ExE. Hours of pumping at present

is 16 Hours not continuous.

KWA enquired whether planting or gardening is planned on the sides of the

canal for the recycling of canal water.

7. Irrigation Department

Present width has to be increased as the present width is not the actual

width for navigation.

Encroached areas has to be taken over.

What measures are taken to safeguard the canal and what operational

mechanism is referred after the redevelopment of the project?

CSML informed that land acquisition and associated tasks such as

encroachment removal is not under purview of Smart City. As per Smart city

guidelines same is to be taken up by ULBs

Name of organisation met: Engineering wing VENUE: Banquet Hall, 2nd floor, Govt. Guest House

AGENDA : Introduction and discussion of SCM and project status

ORGANISATION

1. Engineering wing

2. CSML

3. GIZ

4. PMC for Smart City

S. NO. POINTS DISCUSSED Clarification sought /

Suggestion from Eng. wing Clarification/Request by CSML/PMC

1. The agenda of the meeting was to appraise the engineering staff of the KMC about projects undertaken by

CSML and implement the projects with guidance & active assistance from Engineering wing.

Projects for discussion:

The projects from various sectors:

1. Urban Mobility and Road Projects

2. Open Spaces and Tourism Projects

3. Canal Projects

Page 130: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 130 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

4. Market projects

5. Housing projects

6. LED streetlight and electrical infrastructure, Solar projects

7. ICT – IC4, ITMS, e-health

8. Telecom - Smart Poles

9. Other projects

2. Urban Mobility and Road

Projects:

Projects discussed:

a) Smart and other

roads

b) Public bike sharing

system

c) Parking

management

1. Carriage way of Hospital

road seems to be reduced.

2. No two-wheeler parking

provision.

3. ROW seems to be

reduced

4. Subway as alternative

option for pedestrian

crossing.

1. Primary concept is to develop roads for

all types of road users and not just Cars.

Hence pedestrian friendly streets to be

developed.

2. Need to regularise & restrict vehicular

traffic rather than excessive expansion of

carriage way. Authorities may carry

separate parking study to understand why

this unauthorised parking on footpath is

taking place. Footpath is meant for

pedestrians.

3. Effective re-organisation of under-

utilised existing streets (most of the roads

with wider widths is taken up by

haphazard on-street parking). The space

is being reorganised considering various

criteria; one being Non-motorised user’s

needs.

4. Subway option not considered due to

factors like:

- perception an unsafe environment

- High ground water table level

- Not friendly to pedestrian and vulnerable

road user.

3. GIZ Presentation on Street

design:

The key objective is to design

safer and equitable streets for

all.

Re-organization of under-

utilized streets and promotion

of NMT & Public Transport.

Proposed principles for

improved streets:

a) Safer speed

b) Re-configure space

c) Accommodate

diverse users

d) Context based

solutions

e) Ensure universal

accessibility

f) Small solutions with

larger impacts

Proposed principles for

improved junctions:

g) Design compact

intersections

h) Simplify geometry

Page 131: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 131 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

i) Analyze networks

Use of Street Calming

Elements and Tactical

Urbanism ideas to build safer

streets. Physical and

physiological calming

measures to control vehicle

speed.

4. Open Spaces and Tourism:

Projects discussed:

a) Improveme

nts to

Marine

Drive

walkway

b) Vasco Square at Fort

Kochi

c) Open Air Theatre at Fort

Kochi

d) Parks improvement

e) Fort Kochi Beach

upgradation

f) Museums

g) Public walkway at

Mattancherry

5. Canal Projects:

Restoration of four canals:

a) Market canal

b) Mullassery canal

c) Calvathy –

Rameshwaram canal

Restoration involves:

a) Cleaning and

maintaining water quality

b) Side wall development

c) Urban design aspects

along the canal stretch

1. Officials informed

that in West Kochi, Calvathy-

Rameshwaram Canal work

on desilting & side wall

protection was taken up as

part of AMRUT

2. Restoration of

Calvathy-Rameshwaram &

Mullassery canal within ABD

alone will not suffice.

3. Integrate the work to

be undertaken with AMRUT

funds for Calvathy-

Rameshwaram canal

1. CSML requested for detail on Canal

work carried out under AMRUT, in

order to avoid any overlapping of

work.

2. CSML informed that taking up of entire

stretch of Canal is under consideration

and will be further discussed with

other stakeholders

3. Public awareness required for proper

restoration of canals and requested for

assistance of Engineering wing

6. Market projects:

The projects mentioned were:

a) Ernakulam market

development

b) Broadway street

upgradation

CSML requested Engineering wing to

assist KMC to initiate the following at the

earliest:

1. Formation of joint committee

2. Complete list of registered vendors to

be issued by KMC.

3. Land (1.5 Acre) to rehabilitate vendors

during construction phase to be identified

and finalisation of land for rehabilitation.

4. Legal agreement on rehabilitation of

vendors to be issued by KMC to vendors.

5. Detail of hawkers/ street vendors

6. Agreement with site owner

7. Site clearance

8. Agreement with PAPs by KMC

9. Relocation of existing vendors

Page 132: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 132 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

10. Way forward on Un-registered

vendors

All the above activities to be completed by

KMC latest by September 2019 to enable

tendering by October 2019.

7. Housing projects:

Projects discussed:

a) Bridges construction

b) Thuruthy colony – 1st

Tower

c) Integrated development

of Slum housing

d) Beneficiary Led housing

schemes

1. Any Vacant space for new

construction/ relocation or

slums that can be

redeveloped to be

considered and discussed

further for redevelopment of

slums component.

2. CSML can initiate

proposal for construction of

2nd tower for Thuruthy and

independent slum

redevelopment of specific

slums, once KMC provides

consent and necessary

details to proceed with the

work.

1. Vacant space besides Tower-1 of RAY scheme along with Mehboob Park, if acquired, CSML can propose and implement the construction of Tower-2 to relocate households. 2. Prioritisation / identification of the most vulnerable slums/ cluster to be specified by KMC so that CSML can prepare proposal accordingly. Engineering wing to assist KMC in finalising the same

3. CSML received request for development of slums from ward 5 which is a feasible proposal, but confirmed list of slums from all wards are requested from KMC to initiate the process formally

4. Analysing the credibility of land ownership document is a challenge.

5. Data base on slum housing project to be shared by concerned authority or new data base has to be developed with KMC. Engineering wing to assist..

6. Once the scope of all housing projects to be taken up under Smart City for implementation is finalised by KMC all project proposals & designs will be as per KMBR. Fire safety will be taken care off.

8. Other projects:

a. Healthcare:

Projects discussed :

a) Fort Kochi Hospital

b) Mattancherry

Hospital

b. Education:

Projects discussed :

a) Calvathy School

1. L.P Block of

Calvathy School requires

upgradation.

1. Assistance required for the fast

track demolition work of digital library and

toilet block of Calvathy School.

2. Calvathy School, L.P Block

upgradation can be done in development

phase – 2 considering temporary

relocation of current classrooms to the

new High school block built in phase -1.

CSML requested Engineering wing to

assist KMC to start the process of

demolition of existing building proposed to

be renovated

9. Sewerage & Solid waste &

sanitation:

Projects discussed:

a) Vacuum based

sewerage system for

West Kochi

b) Household waste bin

c) Public toilets

1. Engineering wing to assist KMC to

issue the beneficiary list and carry out

Household bin distribution

2. Engineering wing to assist KMC to

provide bin storage location

Page 133: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 133 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

10. ITMS:

Traffic enforcement and

management through VA

signals, Pelican Signals,

variable message boards, red

light violation.

Traffic management centre

above North police station

1. Permission for cutting roads under

KMC authority to be granted. Engineering

wing to assist KMC in sharing the same.

11. LED streetlight and

electrical infrastructure:

Projects discussed:

a) Smart LED street

light

b) Solar project

1. Implementation of

LED lights in – Pan City area

on PPP mode ( Energy

Saving Model) - Engineering

wing opined that while

replacing existing light

fixtures with LED light

fixtures and controllers, Poles

may also be replaced and

maintain lux level

requirements of each roads.

2. LED light and pole

design to be considered as a

whole for efficient design.

3. Leak in Fort Kochi

Govt. building found after

solar panel installation and

needs to be rectified.

1. In PPP mode, usually, LED fixtures

along with controllers and minor wiring is

done and O&M of LED fixtures for a fixed

tenure say 7 years be done in Energy

saving mode and all the cost are met from

the energy saving and duration is

dependent on the cost benefit analysis.

2. Cost of replacing poles and brackets

etc will be additional cost in the PPP

(energy saving mode). And the number of

poles required will be more than the

present quantity as the lighting design

may reduce the spacing between poles.

3. Currently, CSML is doing the LED

project in Capex mode (in ABD) and in the

project, the new LED fixtures, control

panels and poles are provided in smart

roads. In access roads, LED lights along

with GI poles suitable to carry Arial Bunch

cables are provided. The pole spacing and

size of the poles are based on lighting

design.

4. Technical assistance regarding new

proposal with new pole design can be

provided for pan city area for LED lighting

along roads

5. In the electrical infra project,

undergrounding of 11 KV and 415 volt

lines are done in ABD area along with

installation of Compact Substations,

Feeder pillars and smart Meters.

6. CSML has installed about 1000 KWp

grid connected solar roof top system in

government and Corporation buildings

(total 27 nos) in Kochi Municipal area.

Water leak reported by KMC in Fort Kochi

government hospital building will be

inspected and accordingly. BHEL will be

instructed to rectify the leak due to solar

panel installation at the earliest.

Page 134: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 134 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

12. Other important projects

discussed:

1. Integrated command

control and

communication centre

2. Smart poles

3. Cancer block for General

Hospital

1. KMC enquired regarding

location of Smart poles

1. CSML explained that two type of poles

shall be used based on their height. Smart

poles shall be placed along the roads but

taller poles shall be placed elsewhere

depending upon the availability of space.

2. Locations will be finalised jointly with

CSML & KMC and Engineering wing.

3. CSML requested Engineering wing to

assist KMC to share information on

existing number of mobile towers within

KMC limit.

4. City gas project status to be updated

in order to avoid cutting after road

development.

13. The Team Leader clarified the issues raised by the members of Engineering wing and others. The General

manager concluded the meeting thanking the members attending the meeting and with the decision to

further conduct, sector wise detailed discussion with concerned officials.

Page 135: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 135 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 136: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 136 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 137: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 137 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 138: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 138 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Page 139: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 139 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

ANNEXURE 3: LIST OF PROJECTS UNDER IMPLEMENTATION BY SPV

S No

Category

Module No.

Module Source of Fund

Project Name Project / SCP cost

Status

1. ABD 10 Urban Mobility SCM Walkway from Ekm Jetty to Metro station

4.70 Work order issued/Project Under Implementation

2. ABD 6 Energy

Efficiency SCM Solar panels in Govt. buildings 5.70

Work order issued/Project Under Implementation

3. ABD 10 Urban Mobility PPP Public Bicycle Sharing (PBS) 10.00 Work order issued/Project Under Implementation

4. ABD 4 Main Roads SCM Intelligent Traffic Management Systems (ITMS)

26.90 Work order issued/Project Under Implementation

5. ABD 13 Health SCM E-health solution for General Hospital

3.71 Work order issued/Project Under Implementation

6. ABD 13 Health SCM Cancer Extension Block, General Hospital

26.00 Work order issued/Project Under Implementation

7. ABD 18 Others SCM Integrated Command, Control and Communication Centre (IC4)

64.50 Work order issued/Project Under Implementation

8. ABD 3 NMT Roads SCM Development of Other Roads in Ernakulam

43.60 Work order issued/Project Under Implementation

9. ABD 4 Main Roads SCM Development of Smart Roads in Ernakulam

61.53 Work order issued/Project Under Implementation

10. ABD 4 Main Roads SCM Development of Smart Roads in West Kochi

30.31 Work order issued/Project Under Implementation

11. ABD 7 Solid Waste

and Sanitation SCM

Household and Street Bins for Segregation of Organic and Inorganic wastes

0.67 Work order issued/Project Under Implementation

12. ABD 6 Energy

Efficiency SCM

Implementation of Smart LED lighting

32.09 Tender Issued

13. ABD 7 Solid Waste

and Sanitation SCM

Smart & Improved Secondary Storage & Transportation of Solid Waste using Portable Compactor Technology

4.40 To be re-tendered

14. ABD 7 Solid Waste

and Sanitation SCM

Smart & Improved Mechanised Street Sweeping at West Kochi & Ernakulum in ABD area

3.20 To be re-tendered

15. ABD 3 NMT Roads SCM Development of Other Roads in West Kochi

60.20 To be re-tendered

16. ABD 5 Energy Supply SCM Development of Electrical Infrastructure in ABD

63.40 Tender Issued

17. ABD 17 Identity and

Culture SCM

Upgradation of Dutch Palace Entry Area

1.10 Tender Issued

18. ABD 17 Identity and

Culture SCM

Beach Front Upgradation at Vasco Square in Fort Kochi - Part A

1.71 Tender Issued

19. ABD 17 Identity and

Culture SCM

Open Air Theatre (OAT) at Fort Kochi

1.10 Tender Issued

20. ABD 13 Health SCM New Block at Fort Kochi Taluk Hospital

4.65 Tender Issued

21. ABD 13 Health SCM New Block of Mattancherry Women & Children Hospital

4.57 Tender Issued

Page 140: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 140 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

22. ABD 6 Energy

Efficiency PPP Intelligent Street Pole 301.58 Tender Issued

23. ABD 2 UGSS SCM

Construction of Vacuum Sewer Network with House Connections and Sewer Treatment Plant

154.50 Tender Issued

24. ABD 7 Solid Waste

and Sanitation SCM Public Toilets in ABD area 1.80 Tender Issued

25. ABD 8 Park and Open

Space SCM

Improvements to Marine Drive walkway - Phase I

7.10 Tender Issued

26. ABD 14 Education SCM Higher Secondary Block, Central Calvathy GHSS, Fort Kochi

4.67 Tender Issued

27. ABD 3 NMT Roads SCM Development of Multi Level Car Parking at Kacheripady

6.15 To be re-tendered

28. ABD 4 Main Roads SCM Road Signages for ABD area 2.40 DPR Prepared

29. ABD 17 Identity and

Culture PPP

Development of Ethnic Food Hub

1.00 DPR Prepared

30. ABD 15 Safety and

Security SCM

Safety & security - Intelligent Crime Surveillance System

14.56 DPR Prepared

31. ABD 8 Park and Open

Space SCM Development of open spaces 2.50 DPR Prepared

32. ABD 17 Identity and

Culture SCM

Museum of Freedom Struggle 1.20 DPR Prepared

33. ABD 9 Canal

Restoration SCM

Restoration of Mullassery canal - including linking of standardized area drains

1.00 DPR Under Preparation

34. ABD 9 Canal

Restoration SCM

Restoration of Market canal - Walkways and Market square around the canal pond, Solar paneled roofs, LED Lighting, Light posts

5.00 DPR Under Preparation

35. ABD 9 Canal

Restoration SCM

Restoration of Kalvathy canal and area drain improvement - Open spaces, Street furniture and landscaping features

20.00 DPR Under Preparation

36. ABD 9 Canal

Restoration SCM

Restoration of Rameswaram-Kalvathy canal - Upto Cochin college – Walkways and Linking the Canal Bank Road

15.00 DPR Under Preparation

37. ABD 12 Economy and Employment

SCM Broadway Street Upgradation 10.00 DPR Under Preparation

38. ABD 12 Economy and Employment

SCM Ernakulam Market Redevelopment

100.00 DPR Under Preparation

39. ABD 12 Economy and Employment

SCM Standard Hawker zones in Fort Kochi + Standardize structures for "Petti Kada"

5.60 DPR Under Preparation

40. ABD 3 NMT Roads SCM Smart Parking Solutions in ABD area

1.90 DPR Under Preparation

41. ABD 4 Main Roads SCM FOBs - West Kochi (3 Nos) 2.15 DPR Under Preparation

42. ABD 17 Identity and

Culture SCM

Cultural Corridor - PT Usha Road

0.50 DPR Under Preparation

43. ABD 17 Identity and

Culture SCM

Fort Kochi Beach Front improvements - Part B Walkway & Beach

5.00 DPR Under Preparation

44. ABD 11 Housing SCM

Construction & upgradation Thuruthy, Kalvathy & Konchery colony - Construction of Bridges

5.15 DPR Under Preparation

45. ABD 14 Education SCM Anganwadis 3.00 DPR Under Preparation

Page 141: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 141 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

46. ABD 11 Housing SCM Construction of Second tower at Thuruthy

35.00 Project scope to be confirmed by stakeholders

47. ABD 12 Housing SCM Construction of First tower at Thuruthy

21.00 Fund Transfer by SPV

48. ABD 11 Housing SCM Integrated redevelopment of Slum housing

46.85 Project scope to be confirmed by stakeholders

49. ABD 11 Housing SCM Beneficiary led housing 13.00 Fund Transfer by SPV

50. ABD 18 Others SCM Spatial Mapping of assets 0.00 DPR Prepared

51. ABD 7 Solid Waste

and Sanitation SCM

Smart & Improved Battery-Operated Tricycles for Primary Waste Collection at West Kochi & Ernakulam in ABD Area

1.00 DPR Prepared

52. ABD 1 Water Supply SCM Smart Water solutions - Smart Metering and smart valves for all connections in ABD

1.00 Project scope to be confirmed by stakeholders

53. ABD 3 NMT Roads SCM MLCP at KTDC 7.00 Project scope to be confirmed by stakeholders

54. ABD 3 NMT Roads SCM MLCP at GCDA 10.00 Project scope to be confirmed by stakeholders

55. ABD 2 UGSS SCM Improvements to Sewer collection system for Mainland

34.50 Project scope to be confirmed by stakeholders

56. ABD 3 NMT Roads SCM Kacheripady commercial complex

5.00 Project scope to be confirmed by stakeholders

57. ABD 6 Energy

Efficiency SCM

Solar panels in canals and backwaters

0.50 Project scope to be confirmed by stakeholders

58. ABD 10 Urban Mobility SCM Standard Wifi Enabled Bus Stands With Commercial space development

3.00 Project scope to be confirmed by stakeholders

59. ABD 17 Identity and

Culture SCM Museum of Spices history 1.50

Project scope to be confirmed by stakeholders

60. ABD 17 Identity and

Culture SCM Mattancherry Walkway 11.00

Project scope to be confirmed by stakeholders

61. ABD 8 Park and Open

Space SCM

Mangalavanam Eco-restoration project

1.00 Project scope to be confirmed by stakeholders

62. ABD 10 Urban Mobility SCM

Extend ‘Smart Wi-Fi bus shelters’ with LED bulbs, FM radio, USB drive slots, magazine/newspaper kiosks, mobile charger units

0.60 Project scope to be confirmed by stakeholders

63. ABD 16 Other Social Infrastructure

SCM Upgradation of Community Centre at Mattancherry with indoor sports facilities

1.00 Project scope to be confirmed by stakeholders

Page 142: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 142 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

ANNEXURE 5: PROJECT PROGRESS

1. Detail physical progress of solar panels in govt. Buildings

Sl No

Name of Building

Capacity In KWp

Roof Type

KSEB Feasibility

Solar Panel Installation

Inverter Installation

AC cabling

DC Cabling

Installation AC DB/ DC DB

Lightning Arrestor Installation.

Earthing

Net Meter Registration

Net Meter installation

Solar Meter installation

Drawing submission to EI

Drawing approval from EI

Access to Solar system is available or not.

Final approval from EI

Supply and installation of energy meters

Testing of Solar system by KSEB

Status

Remark

1

Fire station Gandhi Nagar

40 RCC Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done

Done Obtained

Yes 85%

EI inspection done. Precommissioning test to be carried out

2

General Hospital, Ernakulam

70 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done

Done Obtained

80%

EI inspection Pending. Will provide temporary ladder for inspection

3 Town Hall, Ernakulam

80 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done 70%

EI inspection Pending. Can be done without ladder

Page 143: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 143 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Name of Building

Capacity In KWp

Roof Type

KSEB Feasibility

Solar Panel Installation

Inverter Installation

AC cabling

DC Cabling

Installation AC DB/ DC DB

Lightning Arrestor Installation.

Earthing

Net Meter Registration

Net Meter installation

Solar Meter installation

Drawing submission to EI

Drawing approval from EI

Access to Solar system is available or not.

Final approval from EI

Supply and installation of energy meters

Testing of Solar system by KSEB

Status

Remark

4

Central Section Office, KSEB. Semitheri Mukku.

20 RCC Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Completed

Done Done Yes 65%

5

Government Ayurveda Hospital, Kacheripady.

15 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done 70%

6

Government Hospital, Fort Kochi.

30 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done 70%

7

Government Higher Secondary School, Panampilly Nagar

25 Roofing Sheet

Obtained

Completed

Pending

Pending

Pending

Pending

Pending

Pending

Done Done 40%

8

Government Girls HSS, Ernakulam South

30 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done Yes 70%

Page 144: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 144 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Name of Building

Capacity In KWp

Roof Type

KSEB Feasibility

Solar Panel Installation

Inverter Installation

AC cabling

DC Cabling

Installation AC DB/ DC DB

Lightning Arrestor Installation.

Earthing

Net Meter Registration

Net Meter installation

Solar Meter installation

Drawing submission to EI

Drawing approval from EI

Access to Solar system is available or not.

Final approval from EI

Supply and installation of energy meters

Testing of Solar system by KSEB

Status

Remark

9 Old Age Home, Thevara

20 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Completed

Done Done 65%

10 Town Hall, Palluruthy

20 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Completed

Done Done 65%

11 Vennala High School

40 Roofing Sheet

Obtained

Completed

Completed

Pending

Pending

Completed

Pending

Pending

Done Done 45%

12

PWD Rest House, Park Avenue Road.

60 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Completed

Done Done Yes 65%

13

Elamakkara Govt Higher Secondary School (Punnackal)

40 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Pending

45%

14

Government Hospital, Karuvalipady.

40 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Completed

Done Done 65%

15

Government High School, Edakochi.

45 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Completed

Done Done 65%

Page 145: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 145 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Name of Building

Capacity In KWp

Roof Type

KSEB Feasibility

Solar Panel Installation

Inverter Installation

AC cabling

DC Cabling

Installation AC DB/ DC DB

Lightning Arrestor Installation.

Earthing

Net Meter Registration

Net Meter installation

Solar Meter installation

Drawing submission to EI

Drawing approval from EI

Access to Solar system is available or not.

Final approval from EI

Supply and installation of energy meters

Testing of Solar system by KSEB

Status

Remark

16

Government High School, Edapally.

35 Roofing Sheet

Obtained

Completed

Completed

Completed

Pending

Completed

Pending

Completed

Done Done 60%

Govt Girls High School, Ernakulam

Roofing Sheet

Obtained

Dropped due to structural stability problem

17

Court Complex Ernakulam

40 RCC Obtained

Completed

Completed

Completed

Completed

Completed

Completed

Completed

Done Done Obtained

80%

18

Paramara Building, Ernakulam North

60 Roofing Sheet

Permission otained from KSEB

5%

Approval for converting 1 Ph to 3Ph received from KSEB

19 Advocate General Office

20 Roofing Sheet

Obtained

5%

Page 146: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 146 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Name of Building

Capacity In KWp

Roof Type

KSEB Feasibility

Solar Panel Installation

Inverter Installation

AC cabling

DC Cabling

Installation AC DB/ DC DB

Lightning Arrestor Installation.

Earthing

Net Meter Registration

Net Meter installation

Solar Meter installation

Drawing submission to EI

Drawing approval from EI

Access to Solar system is available or not.

Final approval from EI

Supply and installation of energy meters

Testing of Solar system by KSEB

Status

Remark

20 Building in Perumbotta ground.

30 Roofing Sheet

Permission otained from KSEB

5%

Approval for converting 1 Ph to 3Ph received from KSEB

21

New Excise Office, Ernakulam

40 RCC

Permission otained from KSEB

5%

Permanent connection to be obtained from KSEB

22

Kunnumpuram High School, Edapally

40 Roofing Sheet

Obtained

Mobilised

5%

23

Corporation Office, Ernakulam

20 Roofing Sheet

Obtained

Mobilised

Completed

Completed

20%

24

Maharajas College Britto Building

20 Roofing Sheet

Obtained

Completed

Completed

Completed

Completed

Completed

Pending

Pending

40%

25 Maharajas College

50 Roofing Sheet

Submitted

Page 147: csml.co.incsml.co.in/wp-content/uploads/2019/08/Kochi-PMC-Monthly-Progres… · Monthly Progress Report Page | 2 Project Management Consultant (PMC) to Implement Area Based Development

Monthly Progress Report

Page | 147 Project Management Consultant (PMC) to Implement Area Based Development - Smart City Kochi

Sl No

Name of Building

Capacity In KWp

Roof Type

KSEB Feasibility

Solar Panel Installation

Inverter Installation

AC cabling

DC Cabling

Installation AC DB/ DC DB

Lightning Arrestor Installation.

Earthing

Net Meter Registration

Net Meter installation

Solar Meter installation

Drawing submission to EI

Drawing approval from EI

Access to Solar system is available or not.

Final approval from EI

Supply and installation of energy meters

Testing of Solar system by KSEB

Status

Remark

Boys Hostel

26 Palluruthy Hospital.

70 Roofing Sheet

Obtained

Mobilised

5%

Total (KW)

1000

Total Completed (KW)

670

Physical Progress

48%