«Current NPP Projects in Turkey & Risk
Management»
08.09.2016
Vienna
IAEA
IAEA, Technical Meeting on Risk Management in NPP Construction, 6-8 September 2016
Barış GÜNER Turkish Atomic Energy Authority Head of the Construction Group (Akkuyu NPP Licensing Project )
AKKUYU NPP Licensing Project:
Head of the Construction Group
Group membership: Deputy Chairman of
Site Group, member of Specific Design
Principles Group and Legislations Group
SİNOP NPP Licensing Project:
Member of Site Group
Participant Intro (TURKEY – TURKISH ATOMIC ENERGY AUTHORITY – DEPARTMENT of NUCLEAR SAFETY)
Barış GÜNER
- Civil Engineer
- Business Administration
(B.B.A.)
- MBA
- Earthquake Engineer
(M.Sc.)
(+)
Nuclear Safety Inspector
Publications:
B. Güner, “Six Sigma Methodology and Case Studies in Construction Industry”, Master Thesis (2010).
B. Güner, A. Menekşe, A. A. Özacar ve Z. Gülerce, “Determination of Earthquake Recurrence Parameters for North
Anatolian and East Anatolian Fault Zone”, 3. Turkey Conference on Earthquake Engineering and Seismology, İzmir",
(2015).
B. Güner, "Comparison of Seismic Hazard Assessment Applications for Nuclear Facilities in terms of Different
Countries Perspectives", Master Thesis (expected 2016).
B. Sayın, B. Uçak, B. Güner, B. İşcan, and A. Akgöz, “Comparison of Aircraft Impact Assessment Regulations &
Applications for Nuclear Power Plants in terms of Different Countries Perspectives and Structural Analysis”, XI.
National Nuclear Science and Technology Congress, Kuşadası (12-14 October 2016)
B. Güner, B. İşcan, B. Sayın, B. Uçak and A. Akgöz, “Evaluation of Lessons Learned from Fukushima Accident based
upon Structural Design and External Events”, XI. National Nuclear Science and Technology Congress (12-14 October
2016) 2
PART - I
Current NPP Project in Turkey
CONTENT
3
PART - II
Risk Management
• Aim & Focus Areas
• Identification of Project Specific Risks
• Project Specific Risk Management Examples
• Conclusion
PART-I
CURRENT NPP PROJECT
4
Current NPP Projects in Turkey
SİNOP
AKKUYU
5
VVER-1200 (AES-2006)
AKKUYU NPPs PROJECT
History of Project:
“Akkuyu Site” is the only licenced site for NPP’s (in 1976)
Up to 2009, four attempts but NPP was not built.
Current NPP Projects in Turkey
Current Status (after 2010)
Russian – Turkey Partnership in Akkuyu NPPs
(12 May 2010) Signing of Agreement between the Government of the Russian Federation and
the Government of the Republic of Turkey on cooperation in relation to the construction and
operation of a nuclear power plant at the Akkuyu site in the Republic of Turkey.
Project: Akkuyu NPP construction in Turkey (units 1, 2, 3, 4) 4 x 1200 MWe VVER (AES 2006
Design)
(TENTATIVE SCHUDULE FOR AKKUYU)
Activity
Submission
Date
Approval
Date
Approval of updated site license report (SITE) May, 2012 Dec, 2013
Approval of site parameters report (SITE PARAMETERS) Dec., 2014 Oct, 2016
Approval of limited work permit (LWP) Dec, 2016 June., 2017
Approval of Construction License application (CL) June., 2018
6
SİNOP NPPs PROJECT
History of Project:
1975 - Sinop Site is one of the sites evaluated by Turkish Electricity Authority (TEK)
for first NPP Project but Akkuyu Site selected.
1978 - Selection of second NPP site in 1978. Sinop Site was amongst the candidate
sites.
2004 - Turkish Atomic Energy Authority (TAEK) conducted a site selection study and it
determined as the most promising site for the installation of a Nuclear Technology
Center.
Current NPP Projects in Turkey
Current Status:
Japanese Consortium (Mitsubishi Heavy Industries, Itochu and GDF-Suez) – Turkish Partnership in
Sinop NPP
(22nd of August 2012) “Owner” status was granted to Electricity Generation Co. (EÜAŞ) (Turkish part –
State-owned enterprise) will be a shareholder in Project Company.
(3rd of May 2013) Turkey and Japanese Government signed an IGA* on to cooperate for the construction of
Sinop NPP and development of Nuclear Industry in Turkey. Negotiations are being carried out for finalization
of a HGA** to establish a Project Company for the implementation of the Sinop NPP Project with the
Japanese Consortium (Mitsubishi Heavy Industries, Itochu and GDF-Suez)
(5th of October 2013) EÜAŞ start site studies.
(September 2014) EÜAŞ currently conducting studies for the determination of the seismicity of the site on
land and sea. Up to now, TAEK had conducted 9 inspections during these studies.
Project & Design: Japanese Consortium proposes an NPP comprised of 4 units of ATMEA-1 (ASN and
IRSN completed an assessment of ATMEA-1 generic design in 2012)
(* Inter-Governmental Agreement ** Host Governmental Agreement) 7
PART-II
RISK MANAGEMENT
8
Aim & Focus Areas
9
Focus of the presentation (mainly regulatory perspective)
1. Turkey’s experiences related to risk management for nuclear new-build
construction project
2. Especially
- Risk Identification (Project Specific Possible Risks)
- Risk Management & Risk Response Planning
- Our Future Needs
Aim of the presentation
- to share our experiences between Member
States (regulatory point of view),
Albert Lester (2014), Project Management, Planning, and Control Managing Engineering, Construction, and
Manufacturing Projects to PMI, APM, and BSI Standards (Sixth Edition)
Generic risk categories
Types of risks in the construction industry (Al-Bahar, 1990) 10
Identification of Project Specific Risks
11
AKKUYU NPPs Specific Risk Identification
Political & Environmental Risks
a. Political risks
o “Aircraft crisis” between Turkey & Russian Federation
o Possible effects of politically unstable neighbouring countries (Iraq,
Syria etc.) in Middle East
b. Legal basis risks (legislation infrastructures related risks)
o Turkish legislations are not fully compatible with nuclear projects
(e.g. Olive Cultivation Law, Construction Inspection Law, Coastal
Law etc.)
o Nuclear Energy Law & Liability Law (new laws & not finalized)
o Complexity of “licensing basis list”
Identification of Project Specific Risks
12
AKKUYU NPPs Specific Risk Identification
Political & Environmental Risks
a. Political
o Turkey – Russian Federation “aircraft crises”
(November 2015)
(December 2015)
(August 2016)
Undesired Situation
Happy Ending
Turkey and Russia have
mutual interests.
There are deep-rooted
strong relations and
cooperation between two
country.
Identification of Project Specific Risks
AKKUYU NPPs Specific Risk Identification
Economic & Financial risks
a. Current & future economic situation in Russian Federation & Turkey
b. Construction Cost Overruns / Cost Estimation
OECD (2016), Inflation (CPI) (indicator). doi: 10.1787/eee82e6e-en (Accessed on 30 August 2016)
http://www.worldbank.org/eca/pubs/rer35_ENG.pdf
13
Identification of Project Specific Risks
AKKUYU NPPs Specific Risk Identification
Financial risks
a. Current & future economic situation in Russian Federation & Turkey
b. Construction Cost Overruns / Cost Estimation
14
Sola M. Talabi, «Improving Cost
and Schedule Performance on
Large Energy Infrastructure
Deployment Projects:
Establishment of Best Practices for
Risk Management and
Organizational Learning in Nuclear
Projects Post-Fukushima»
Identification of Project Specific Risks
AKKUYU NPPs Specific Risk Identification
Schedule Overruns / Construction Delays
15
Mycle Schneider,
Antony Froggatt,
«World Nuclear
Indutry Status
Report» July,
2016
Ch
ern
ob
yl,
1986
Fu
ku
sh
ima,2
011
TM
I,1979
Identification of Project Specific Risks
16
AKKUYU NPPs Specific Risk Identification
Regulatory body related
risks
a. Regulatory uncertainties
b. Lack of experiences,
c. Full independency of RB
Other Possible Risks
a. Technical Support / TSO
b. Design Issues & Design Changes
c. Supply Chain Variability
d. Site Specific possible risks
o External Natural Events related risks (Earthquake & Tsunami)
o External Human Induced Events (Aircraft Impact Assessment etc.
related risks)
Project Specific Risk Management Examples
SİNOP NPPs Risk Management Examples
17
CONCLUSIONS
18
We shouldn't be PESSIMISTIC /
OPTIMISTIC
We don’t have fully functional «systematic»/»formal» risk
management system
We probably need proper tools & software and human resource in
order to operate risk management system
We should be
REALISTIC
Unproven OR first of a kind
design
Proven Design /
Reference Plant
Our Possible Future Needs
There is no «learing curve» considering
CONSTRUCTION COST & SCHUDULE OVERRUNS
THANK YOU FOR YOUR KIND ATTENTION !
Barış GÜNER Head of the Construction and Fire Protection
Group (Akkuyu NPP Licensing Project)
Civil Engineer / Nuclear Safety Inspector
Phone: 0090 (312) 295 88 54
E-mail: [email protected]