cv bnm project finance newswire · few days before and after enron filed for bankruptcy whateffect...

32
Cv bnm News W ire December 2001 Fallout From Enron by Keith Martin, in Washington Chadbourne asked many thoughtful people in the project finance community in the few days before and after Enron filed for bankruptcy what effect they foresee from Enron’s struggles on the independent power industry.Here are the main points that came out of the survey. Tighter Debt Market Project developers expect to have to pay more to borrow money at least for the next six to 12 months. One senior banker summed up the situation as “delays, higher costs and more scrutiny.”The head of structured finance at a large energy company said, “We will all pay a direct price for Enron’s failure.” One investment banker predicted that energy companies will have to pay 10 to 35 basis points more to borrow money in the future as an Enron premium. Another investment banker trying to place a Rule 144A debt offering in early December called that “a modest assessment.”At least one debt private placement risked a delay in closing because the road trip had to be extended to call on more potential buyers for the debt issue. Lenders are reassessing how much leverage projects can support.Watching the seventh largest corporation in the United States in terms of sales collapse in the space of just a few weeks makes lenders worry that the worst-case / continued page 2 PROJECT FINANCE 1 Fallout From Enron 6 FERC Adopts New Test For Market Rates 9 IRS Clarifies Tax Treatment Of Electric Interties 11 Wind Projects Advance In California 14 Current Issues In Construction Contracts 16 Lender Held Liable For Construction Defects 18 Political Risk Coverage: What’s New? 22 Spotlight On Captive Insurance 25 Mega Gas Project Advances In Bolivia 26 Projects Lose Acid Rain Protection 30 Environmental Update IN THIS ISSUE IN OTHER NEWS YEAR-END DEALS may qualify for more generous tax depreciation. The IRS said in November that it will give most taxpayers the option of claiming a half year worth of depreciation for assets placed in service during the remainder of this year.The government hopes this will boost investment. Ordinarily, assets placed in service at any time during the year qual- ify for only a half year of tax depreciation. In the past, there was always a rush in late December to close transactions in order to enable com- panies to claim a half year of depreciation for assets that they owned for only a few days. Congress took steps to discour- / continued page 3

Upload: others

Post on 19-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Cv

    bnm

    NewsWireDecember 2001

    Fallout From Enronby Keith Martin, in Washington

    Chadbourne asked many thoughtful people in the project finance community in thefew days before and after Enron filed for bankruptcy what effect they foresee fromEnron’s struggles on the independent power industry. Here are the main points thatcame out of the survey.

    Tighter Debt MarketProject developers expect to have to pay more to borrow money at least for the nextsix to 12 months. One senior banker summed up the situation as “delays, higher costsand more scrutiny.” The head of structured finance at a large energy company said,“We will all pay a direct price for Enron’s failure.”

    One investment banker predicted that energy companies will have to pay 10 to 35basis points more to borrow money in the future as an Enron premium. Anotherinvestment banker trying to place a Rule 144A debt offering in early December calledthat “a modest assessment.” At least one debt private placement risked a delay inclosing because the road trip had to be extended to call on more potential buyers forthe debt issue.

    Lenders are reassessing how much leverage projects can support. Watching theseventh largest corporation in the United States in terms of sales collapse in thespace of just a few weeks makes lenders worry that the worst-case / continued page 2

    P ROJ E CT F I N A N C E

    1 Fallout From Enron

    6 FERC Adopts New Test ForMarket Rates

    9 IRS Clarifies Tax Treatment OfElectric Interties

    11 Wind Projects Advance InCalifornia

    14 Current Issues In ConstructionContracts

    16 Lender Held Liable ForConstruction Defects

    18 Political Risk Coverage:What’s New?

    22 Spotlight On CaptiveInsurance

    25 Mega Gas Project Advances InBolivia

    26 Projects Lose Acid RainProtection

    30 Environmental Update

    I N T H I S I S S U E

    IN O

    TH

    ER

    NE

    WS YEAR-END DEALS may qualify for more generous tax depreciation.

    The IRS said in November that it will give most taxpayers theoption of claiming a half year worth of depreciation for assets placedin service during the remainder of this year. The government hopes thiswill boost investment.

    Ordinarily, assets placed in service at any time during the year qual-ify for only a half year of tax depreciation. In the past, there was alwaysa rush in late December to close transactions in order to enable com-panies to claim a half year of depreciation for assets that they ownedfor only a few days. Congress took steps to discour-/ continued page 3

  • 2 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    scenario in their deals could be worse than they imaginedbefore. A consequence of making the downside case moresevere is it will not support as much leverage. This has aripple effect through the power business. It changes thecalculus for smaller developers who lack their own equityto put into deals. They may be unable to hold on to as largean ownership share in their projects as before. The higher

    cost of capital means some projects will be deferred.Turbine prices will continue to decline.

    Closer attention will be focused than before on who isthe offtaker for a project. The head of project finance lend-ing for a bank that has been in the lead on many recentmerchant plant financings in the US market said heexpects to face a lot tougher questions from his creditcommittee about the strength behind the offtake con-tracts, but that “in speaking to other bankers, it seems thatthey are already recognizing the difference between Enronand other power marketers who have physical assets toback their trades.”

    “This is probably not the moment to run a new namepast the guys in risk management,” said another seniorbanker. “Every marketer will be getting a new level ofscrutiny on existing exposure as will any new requests ifthe originator has the guts to ask.” This banker sees an“opportunity” for power marketers to provide more capi-tal — equity, mezzanine — to projects under develop-ment. He suggested that power marketers try to use thenext few months to firm up trading activities with morephysical assets.

    Another factor that may lead to longer lead time toclose deals is the market is not as confident as before

    about investment grade ratings. Just six weeks before thebankruptcy filings, Enron put out an earnings release pro-jecting strong pro forma profits. Two of the three big ratingagencies reaffirmed Enron’s rating of triple-B plus. Moody’sremained skeptical. It put the rating under review, but hint-ed that the danger was a downgrade of one notch. Ratingsare a timesaver for lenders, but only if they are credible.However, it is not clear that banks gain any better insightinto credit risk by spending more time on due diligencethemselves. They may have no realistic alternative other

    than to continue with theexisting system but charge ahigher risk premium.

    One banker predictedsome smaller banks thatmerely tag along in lendingsyndicates would withdrawfrom the market for a while.

    Financial officers at proj-ect developers echoed thebankers. The chief financial

    officer of a large independent power company said, “Theashes are still falling from the volcano, but clearly given allthe shocks to the industry this year, bank financing willbecome more difficult as those bankers who were alreadyworrying about the merchant business may use this asanother excuse to reduce commitments or exit the marketaltogether. Ditto for bond buyers who will likely take enor-mous losses on the Enron structured and supposedlysecured off-balance sheet financings.”

    How long will these effects last? A leading bankerwith many years of experience in the market said,“Liquidity in the marketplace will be affected, but I thinkthis is a short run issue, as these markets are very deep,broad and resilient.” At the end of the day, the more sig-nificant issue is the demand and supply for power —how long it will take the economy to pull out of reces-sion and whether there was already an oversupply ofmerchant plants headed for construction even before theEnron collapse.

    Uneven EffectsThe market adjusted surprisingly smoothly to the Enroncollapse for traders, but perhaps more unevenly for others.

    Enron had a very broad reach in the economy. The com-

    Enron Falloutcontinued from page 1

    The market adjusted surprisingly smoothly to the Enroncollapse for traders, but perhaps more unevenly forothers.

  • pany accounted for 14.7% of electricity trades, much of it onits own electronic trading floor, EnronOnline, according tothe last trade figures in early October. Enron owns 7.5% oftotal capacity on gas pipelines in the United States. About25% of its income came from overseas assets.

    One trader said after the bankruptcy filing, “The jury isstill out on the effects, but at this point, it doesn’t appearthat there will be as large a domino effect as may havebeen expected. We are watching two companies closely tosee if we need to restrict trading with them due to Enronexposure. All of the large trading firms seem to have expo-sures within the $100 million range, which is manageable.I’m not sure yet if we will see smaller firms go down as aresult. The banks seem to be the worst hit.”

    Perhaps consistently with this view, one banker com-plained, “How can Enron have been the number one traderand almost no one — with the sad exception of us banks —has any exposure to them?” Traders had three to fourweeks after the first signs of trouble to reduce their expo-sure. One banker spoke of a ripple effect among banks. Thebanks are “scrambling to review their exposure and tomake sure we are taking the necessary appropriate steps toprotect our positions.” An analysis by Lehman Brothers pub-lished soon after the merger talks with Dynegy collapsedpredicted that the ultimate recovery on senior unsecurednotes, bonds and debentures would be in the range of 25¢to 35¢ on the dollar. Lehman Brothers advised Dynegy onthe merger.

    The collapse left many project developers in a bind. Atleast 17 projects have contracts with the Enron affiliate,NEPCO, to build gas- or waste-fired power plants both inthe US and abroad for completion in 2002 or 2003. Projectsthat are already under construction are in a different posi-tion than ones that have not yet gotten financing. One sen-ior banker said, “Certainly we see NEPCO EPC contracts thatwe were going to take earlier stopping deals.” Another said,“The biggest issue I have seen thus far related to NEPCO,which is building several power plants for clients andwhose balance sheet, when revealed for the first time a fewweeks ago to one who insisted on seeing it after Enron’sproblems grew greater revealed — surprise — NOTHING!No real assets, no liabilities, just a shell company to takeorders. This may be a bit of overstatement, but not much.”

    One harried general counsel at a developer, when askedabout the effects of the Enron col- / continued page 4

    age this in 1986 by adopting a “mid-quarterconvention” that reduced the depreciationthat could be claimed on late-year asset pur-chases. Since 1986, companies that placemore than 40% of their total assets for theyear in service in the last quarter have beenlimited to only a month and a half worth ofdepreciation on assets they put into servicein the last quarter.

    In November, the IRS said in two noticesthat it is waiving this mid-quarter conven-tion for the rest of 2001. Companies some-times use odd tax years. The waiver appliesto any company for whom September 11 fallsin its third or fourth quarter.

    Any company wanting to take advantageof the waiver must write “ElectionPursuant to Notice 2001-70” across thetop of the Form 4562 it files with its 2001tax return. This is the form on whichdepreciation and amortization arereported.

    SOME CONVERTIBLE DEBT INSTRUMENTShave come under fire.

    Lee Sheppard, a writer read by many taxpolicymakers in Washington, urged theTreasury Department in November to preventborrowers from deducting more than thestated interest rate on loans that the lender canconvert into shares in the borrower.

    Many corporations have been issuingzero coupon or other debt with a statedinterest rate that is below the current mar-ket rate. The lender has a right to convertinto common shares of the borrower, there-by making up for the lower interest. Theloans are structured intentionally with con-tingent features that increase the statedinterest paid in certain events. This has theeffect of causing the instruments to be treat-ed as having been issued at a discount for UStax purposes. The result is the borrower candeduct not just the stated interest it actual-ly pays, but also deduct

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 3

    IN O

    TH

    ER

    NE

    WS

    / continued page 5

    Cv

    bnm

  • 4 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    lapse, responded: “Up to my eyes dealing with the problemsbeing created with lenders, EPC contracts, and other inter-ested parties.” He said he would say more when he couldfind “a few spare moments to collect my thoughts.”

    Flood of QuestionsThe collapse led to a flood of questions.

    Chadbourne quickly put up an internal distribution list

    on e-mail to keep project finance and bankruptcy lawyerswho were fielding questions about the situation betterinformed about what issues the firm was being asked toaddress. The list grew quickly to 50 people.

    Chadbourne lawyers reported fielding three main typesof questions from clients.

    One set of questions had to do with the options fordevelopers who are saddled with Enron contracts. This is anespecially difficult problem for developers whose projectsare not yet financed and may never be unless they canbreak free of the contracts. Unfortunately, once a companyhas filed for bankruptcy, the law does not let the other par-ty to the contract simply walk away from the contract for a“status default” — a clause that says the Enron contractorhas defaulted on the contract if it goes bankrupt. Thedeveloper’s only remedy in such a case would be to per-suade the bankruptcy court that there was a true substan-tial performance default. The bankruptcy judge is unlikelyto allow the contract to be cancelled at such an early stagein the proceedings, according to David LeMay, a bankruptcypartner in the New York office. However, LeMay said “one ofthe chinks in the armor that Enron created by filing for only

    [21] companies is they left themselves open to cancella-tions involving nonfiled entities.”

    Another set of questions revolved around projectswhere other companies have minority interests and inwhich Enron is either the majority or managing partner.Neil Golden, a project finance partner in the Washingtonoffice, advised looking first at the shareholders or partner-ship agreement. “Sometimes if a shareholder goes intobankruptcy, he loses the right to vote or other shareholdersmay have a right to buy him out.” (Provisions like those aresometimes invalidated by bankruptcy courts, LeMay noted.)

    Golden said there are twopotential problems created byEnron’s troubles. One is thebankruptcy filing may be adefault under the projectfinancing agreements or maytrigger an obligation on thepart of other partners to postguarantees. This may not be aproblem if the Enron partnerwas not included in the bank-ruptcy filing. There is also the

    issue whether the project company can be run efficiently ifEnron personnel lose their jobs or their attention is divert-ed or if decisions involving the project must be run by abankruptcy judge. Golden said that, in such situations, theother partners may have few real options.

    Questions also came from companies that want to buyEnron assets. Enron reported receiving three to four calls aday from interested purchasers in some of its assets. Atleast in the case of assets belonging to “filed entities,”David LeMay said, the debtor usually signs an agreementwith a “stalking horse bidder” to sell it the assets subject tooverbids and then takes the agreement to bankruptcycourt for approval. Bidding procedures are set by the courtand a breakup fee is approved for the stalking horse if itloses ultimately to another bidder. An auction is then heldand the winning bid is presented to the court for approval.

    An interesting question is whether many Enron assetsmay be harder than appears at first glance to sell. Onebanker cautioned, “They haven’t been doing much projectfinancing. They often put their guarantee on risks, and theytook cash from projects in return . . . . Now they will havedifficulty selling some of those assets.”

    Enron Falloutcontinued from page 3

    Clients inundated law firms with three types ofquestions.

  • Enron Europe Limited and six affiliates filed separatelyfor “administration” in London, the UK equivalent of chap-ter 11 bankruptcy. Denis Petkovic, a partner in the Londonoffice, said the filing “operates to stop secured and othercreditors from trying to liquidate or take other proceed-ings against the company.” Petkovic said the action willalso lead to scrutiny of past transactions and their possi-ble vulnerability to court orders, effectively cancellingsome contracts entered into up to two years before theonset of insolvency. This could happen if the administra-tor can prove that a contract was “at undervalue,” mean-ing the company received significantly less value from thecontract than it had given. Also, payments to affiliatesand other creditors will be scrutinized and will be at risk ifthey are “preferences,” meaning that the payor was influ-enced, when making the payment, to put the recipient ina better position than other creditors in the event ofinsolvent liquidation.

    Estimates are for the bankruptcy proceedings ultimate-ly to take six years. Enron has a sprawling corporate struc-ture. A large part of the complication will be sorting outthe priority of creditors of its 3,500 subsidiaries and amongany litigants who win suits against the company or man-agers whom the company may be required to indemnify.

    Regulatory BacklashMany people speculate that the Enron collapse might leadto a regulatory backlash. A lot will depend on how the storyultimately plays in the press.

    The New York Times said in an editorial, “There is a cer-tain irony that Enron, a champion of deregulation, nowbecomes a poster child for the need for strong regulationon Wall Street.” Both houses in the US Congress announcedhearings to look into the financial collapse. A banker said, “Iam a bit fearful that the politicians will read more into thisthan there really is, and try to do something.” The Senatehas put energy policy on the agenda for debate starting inJanuary. However, the Bush administration has no interestin rolling back deregulation, and an omnibus energy policybill that the opposition party introduced in early Decemberin the Senate made no move in that direction, either.

    The main effect is likely to be more subtle. Enron hadprobably the largest and most effective lobbying staff work-ing for open markets — not only at the federal level, but alsoin state capitals. It will take a while / continued page 6

    the discount as it accrues over time. Someborrowers also deduct the premium paid atconversion into shares as additional interest.

    The loans go by such names as LYONs.Sheppard suggested four ways the gov-

    ernment can deny interest deductions onthe instruments and urged the US Treasuryto act quickly before corporate America isawash in such instruments.

    According to Investment Dealer’s Digest,“$77.4 billion in new converts had pricedas of October 17, a record-smashing num-ber.” The number of convertible bondsissued in the first two weeks of Octoberwas $4.1 billion.

    SYNFUEL PLANT owners are breathing moreeasily after the IRS resumed ruling that theprojects qualify for section 29 tax credits.

    The US government offers a tax credit of$1.059 an mmBtu for producing “syntheticfuel from coal.” The agency stopped ruling inthe late summer 2000 that coal agglomera-tion facilities that add chemicals to coal par-ticles qualify for the credits. It reopened therulings window in theory in late April, but norulings were issued in practice while the IRStried to get plant owners to agree to low lim-its on output in exchange for future rulings.

    The IRS backed off this effort on October 9.Most projects were originally designed

    to glue together coal fines to form bri-quettes or pellets. However, a majority offacilities have dispensed with making pel-lets. The IRS takes the position that projectsthat omit this step must be able to showthat the omission did not result in a signifi-cant increase in output. The agency said onOctober 9 that it would resume ruling thatthe projects qualify for tax credits and essen-tially defer any argument with taxpayersabout whether output increased until audit.

    The IRS had a backlog of some 25 rulingrequests. By early December as theNewsWire was going to

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 5

    IN O

    TH

    ER

    NE

    WS

    / continued page 7

    Cv

    bnm

  • 6 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    before other companies can fill the gap.“Enron was the piedpiper of restructuring: its loudest, boldest and often mosteloquent champion,” said one veteran of Capitol Hill. Thehead of the Washington office of one of the largest US inde-pendent power companies said,“Enron’s legislative staff aresmart, aggressive and hard working . . . . I think we all reliedon their ability to cover a lot of members when contact hadto be made. The other independent power companies aregrowing their legislative capacities, but it will take a while tomake up the difference.”

    Final ThoughtOn Tuesday, December 4, perhaps to provide some sense ofperspective, the following e-mail arrived from someone inan office building across the street from Enron headquar-ters in Houston:

    I’ve been looking out of my 7th floor office window at avery dismal day. Dismal, not just due to the weather, butdismal also because since 10 a.m., I have been watching4,000 dedicated and loyal Enron employees stream outof the buildings with boxes, bags and briefcases in tow, insome cases maybe their life’s work.

    These are hardworking Houstonians, our neighbors, ourfellow bus riders, our children’s Sunday school teachers,piano teachers, coaches, etc. Today, they not only lost

    their jobs and some, if not all, of their retirement money,they don’t even know if they have medical insurance.Until the bankruptcy hearing at 4 p.m. today, there’s noword even on any severance pay.

    FERC Adopts New TestFor Market Ratesby Robert F. Shapiro, in Washington

    The Federal Energy Regulatory Commission issued twoorders at the end of November that mark a significantchange in its tests for approving market-based rates forpublic utilities.

    With a few exceptions, all public utilities in the lower 48states must have their wholesale power rates on file andaccepted at FERC. “Public utilities” include not only vertical-ly-integrated investor-owned utilities, but also power mar-keters and independent power producers. The exceptionsare municipal or other state or federal systems, utilities inERCOT in Texas and certain electric cooperatives.

    In recent years, FERC has been permitting these utili-ties to file to make wholesale sales under a market-basedrate tariff instead of a traditional cost-of-service tariff ifthey could demonstrate an absence of market power ingeneration and transmission. Under a market-based ratetariff, the seller can sell at any rate that it can negotiatewith any wholesale power purchaser, that is, whatever themarket will bear.

    In the November orders, FERC jettisoned a “hub andspoke” test that it has used until now for determiningwhether the applicant has too much market power to beallowed to sell at market rates. The commission introduced

    in its place an interim, supplymargin assessment or “SMA,”test. The commissionalso sought comments on aproposal to modify all existingmarket-based rate tariffs andto include in new tariffs arequirement that each utilityagree to give refunds if it exer-cises anticompetitive behavior.Finally, it imposed a refundcondition on all existing mar-

    ket-based rate tariffs beginning on January 28, 2002. This isclearly not your grandfather’s Republican administration.

    The scope of the decisions took the power industry bysurprise.

    Enron Falloutcontinued from page 5

    “I have been watching 4,000 dedicated and loyal Enronemployees stream out of the buildings.”

  • The declared rationale for these actions was the con-cern that the dysfunctional California power sector wassubject to potential market manipulation and that othermarkets could face similar problems. However, FERC itselfnever completed an investigation of market manipulationby power sellers in any other market in the country.Moreover, the new, interim market test was announced inthe context of a triennial rate review of the market-basedrates of three power marketers who, not coincidentally,happened to be affiliates of the three of the largest verti-cally-integrated public utility holding companies control-ling vast transmission assets.

    The FERC chairman made no effort to conceal the factthat the commission’s actions, which applied the newmarket test to the detriment of each of the three appli-cants, were designed to prod these entities to join largeregional transmission organizations, or “RTOs.”

    Interestingly, the commission did not invite interestedpersons to comment on its new market test, the SMA,which it announced in the order that conducted the trien-nial review of the three applicants. Rather, it issued a com-panion order that sought comments only on themodification of existing tariffs and the inclusion in all newtariffs of the requirement for refunds in the event thepower marketer engages in anticompetitive behavior.Parties who were not involved in the triennial rate reviewproceeding will probably file for late intervention in thatproceeding and submit requests for rehearing on the newmarket test.

    SMA – The New Market TestUnder the old hub-and-spoke analysis, the commissionusually approved market-based rate tariffs if the applicantcould show that it had less than a 20% share of installedand uncommitted generation in the relevant market, andeither owned no transmission or had an open-accesstransmission tariff — called an “OATT” — on file. Underthis new SMA test, the commission intends to determine“whether an applicant is pivotal in the market,” and theapplicant will be deemed pivotal, and thus denied market-based rate approval, “if its capacity exceeds the market’ssurplus of capacity above peak demand — that is, the mar-ket’s supply margin.” The commission will also considertransmission constraints in the relevant market.

    The SMA test appears to boil / continued page 8

    press, seven rulings had been issued, and theagency had worked through ruling requestsfiled by September 2000.

    The IRS will be on the lookout on auditfor projects that are not making pellets.Joseph Makurath, the IRS official who signssection 29 rulings, said the IRS will not both-er such projects on audit if the taxpayer vol-untarily limits his output to the “contractcapacity” of his facility. Contract capacitymeans 50 tons an hour for Startec plants, 70tons an hour for Covol plants, and 150 tons anhour for Earthco plants.

    Taxpayers who do not do this shouldexpect to be asked on audit to prove theplant did not significantly increase output byfailing to make pellets. Makurath said the IRSwill accept as proof the fact that annual out-put at the taxpayer’s plant did not exceedthe actual output at which the taxpayer’splant or a “comparable” facility operated fora full year while making pellets.

    Many tax counsel question whether theIRS has authority to enforce productionlimits. Meanwhile, most projects aredebating at what level to operate.

    MULTINATIONAL CORPORATIONS have beenmaking retroactive elections to increase for-eign tax credits. The IRS said in late Octoberthat it will fight most such elections.

    US multinational corporations must allo-cate the interest they pay each year on loanspartly to their foreign operations on the the-ory that money is fungible. Interest expenseis allocated between US and foreign opera-tions in the same ratio as assets are deployedat home and abroad. The more interest allo-cated abroad, the fewer foreign tax credits acompany will be allowed to claim in theUnited States.

    Historically, most US companies haveallocated between US and foreign assetsbased on the “tax bases” of their assets.However, in recent

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 7

    IN O

    TH

    ER

    NE

    WS

    / continued page 9

    Cv

    bnm

  • 8 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    down essentially to this — if the capacity that the appli-cant controls in the relevant market exceeds the reservemargin in that market, then the applicant cannot sell atmarket-based rates but must use a form of cost-basedrates. So, for example, if the reserve margin in a region is20% and the applicant’s capacity in that region exceeds20% of the total available capacity, the applicant will notpass the screen. However, the SMA screen will not apply toany applicant that makes its sales in a market that utilizesan independent system operator or an RTO with a FERC-approved market monitoring and mitigation plan. Thus,this new interim approach to market analysis is clearlyintended to serve as an incentive for big utilities to joinRTOs, since only big utilities with a large capacity portfolioare likely to violate the new test.

    The three utilities evaluated by FERC — affiliates ofAmerican Electric Power, Entergy and the SouthernCompany — were each found to have a capacity portfolio

    in the regions in which they have franchised service terri-tories — their “control areas” — that exceeded the region’sreserve margin by between one and one-half times andfour times. Accordingly, they each flunked the marketscreen.

    For the uncommitted capacity, each applicant wasrequired to use a “split the savings” approach — amethod traditionally used by investor-owned facilitieswhen making spot or economy energy sales to each oth-er. Under a “split the savings” approach, the rate is theaverage of the seller’s incremental operating costs andthe buyer’s decremental operating costs. For example, if

    the seller’s incremental cost is $30 a mWh and the buy-er’s decremental cost is $50 a mWh, the split-the sav-ings-rate is $40 a mWh.

    It remains to be seen whether this cost-basedapproach will cause heartburn for the investor-ownedutilities that fail to satisfy the new test. However, there islittle doubt that it will produce major ulcers for powermarketers, who have traditionally refused to disclosetheir fuel and other operating costs to anyone for com-petitive reasons.

    The commission went on to find that the uncommittedcapacity that each of the three applicants owned and soldoutside its control area satisfied the SMA screen and thusthe applicants can continue to sell such power at market-based rates.

    The three applicants have until early January to filerevised tariffs that include the new rate mitigation plan.Further, Mirant, which was formerly an affiliate of theSouthern Company but is now wholly independent, wasdirected to submit a standalone SMA analysis.

    One of the FERC commissioners wrote a dissent to thedecision in which she arguedthat the move to the SMAwas premature since it wasadopted without any indus-try input and the commissionhas already initiated a rule-making into the continuedviability of the “hub andspoke” market analysis. Shewas also disturbed that theSMA was created for use as a“stick” to encourage large,

    investor-owned utilities to join RTOs. Again, she wouldhave preferred to use a rulemaking approach to mandateparticipation in RTOs.

    Whether FERC’s requirement that a refund conditionfor anticompetitive actions be added to all market-basedrate tariffs will prove to be a significant, added risk forpower marketers will depend upon FERC’s willingness toinvestigate market irregularities and to place responsibili-ty on individual market participants. Thus far, FERC’s trackrecord has been primarily to try to stop the bleeding inCalifornia rather than to try to target specific marketmanipulators.

    Market Rates continued from page 7

    If an electricity seller controls more capacity than thelocal reserve margin, it will not be free to sell atmarket rates.

  • It should be noted that these orders do not affectexisting, long-term agreements in which the capacity iscommitted to specific offtakers.

    IRS Clarifies TaxTreatment Of ElectricIntertiesby Keith Martin, in Washington

    The Internal Revenue Service said on December 6 that utili-ties do not have to report interconnection payments fromindependent generators in most cases as taxable income.

    The decision is important because some utilities hadbeen insisting that independent generators pay not only thecost to connect their power plants to the grid, but also a “taxgrossup” that added in some cases millions of dollars to thecost.

    The IRS announcement came in the form of a “notice” onwhich all taxpayers can rely. The notice will be published inthe Internal Revenue Bulletin on December 24.

    The IRS said it has decided to extend its existing policy ofnot taxing interties at qualifying facility, or QF, projects tointerties at merchant plants. The problem had been thatmerchant plant interties failed certain tests that the IRS setup in 1988 for QF interties to escape tax. The IRS said it isrelaxing those tests.

    BackgroundPower plants must be connected to utility grids in order todeliver their electricity to market. It is market practice for theowner of the power plant to pay the cost not only of anyradial lines and substations needed to connect to the grid,but also the cost of any upgrades to the grid itself to accom-modate the extra power.

    The utility insists on owning those parts of the intertiethat come in contact with the grid.

    The generator usually either constructs the intertieand conveys title to the utility or reimburses the utilityfor the cost.

    Ordinarily, when one company pays money or transfersproperty to another, the recipient must / continued page 10

    years, many companies have moved to allo-cate based on the relative fair market valuesof assets, and many companies have electedto do this retroactively in amended taxreturns covering several years in the past.

    The IRS said in a “coordinated issuespaper” in late October that it plans to chal-lenge companies on these retroactive elec-tions. The agency said it would only allow achange in allocation method to be made upto the due date for the original tax return forthe year in question.

    Courts sometimes allow retroactive elec-tions in other circumstances, but the IRSsuggested that, if necessary, it would fightthis issue in court.

    CALIFORNIA decided to assess power plantsfor property tax purposes at the state level,but delayed implementing the decision untilJanuary 2003.

    The delay gives the legislature time todecide how to allocate property taxes col-lected by the state among counties andcities. The municipalities want the revenueto go back to the same counties or cities thatwould have collected it had assessmentremained at the local level.

    The move to state assessment shouldmean higher property tax bills for manypower plant owners. Local assessors arebarred by Proposition 13 from claiming morethan a 2% a year increase in property valuesunless the property is sold. This limit doesnot apply at the state level. Some powerplants that are qualifying facilities under thePublic Utility Regulatory Policies Act andpower plants with nameplate capacities ofless than 50 megawatts are exempted fromthe change and will continue to be assessedlocally.

    Some developers wonder what the shiftwill mean for special deals negotiated withlocal officials when power plants wereunder development.

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 9

    IN O

    TH

    ER

    NE

    WS

    / continued page 11

    Cv

    bnm

  • 10 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    report the value as taxable income.Interties paid for by generators have historically never

    been reported by utilities as taxable income. However, in1986, Congress changed the law to say that property sup-plied to a utility by a “customer or potential customer” mustbe reported.

    QF IntertiesAt the urging of the independent power industry, the IRSissued a notice in 1988 to make clear that QF interties donot have to be reported by utilities, but there were condi-tions. First, the QF had to have a power purchase agree-ment with a term of at least 10 years to sell electricityeither to the interconnecting utility or to another utility towhich the electricity would be wheeled. Second, the utilitycould not put the intertie into rate base. QFs argued thatutilities had no income in the sense of an accession towealth because the utility lacked unfettered use of theproperty, at least during the period of the power contractwith the QF, and the utility could not earn a profit from itsuse because the intertie was not put in rate base. Theserules are in Notice 88-129.

    The 1988 notice said that if the utility retains title to theintertie after the power contract with the qualifying facilityends, then it would have income to report at that time. Theutility would have income equal to the then-fair market val-ue of the intertie less any “basis” the utility has in the intertieon account of having paid the QF something for it. In 1990,the IRS said in a second notice that it would determine thevalue at contract termination based on “all facts and circum-stances, including the age and condition of the property and

    whether the property is needed to serve the utility’s cus-tomers.”Thus, if the utility has no further use for the intertie,the intertie would have no value. The agency also said it willordinarily accept whatever value the local public utility com-mission attaches to the intertie for purposes of setting com-pensatory payments.

    Equipment that is required solely for the utility to sellpower to the QF did not qualify for tax-free treatment.

    “Dual-use interties” were subject to special rules. A dual-use intertie is one that is usedboth to carry power to the gridand supply it back to the gen-erator. An example is where anintertie is equipped to carrybackup power to a powerplant for purposes of startup.The utility must show that itexpects that no more than 5%of the total power flowing inboth directions over a dual-useintertie will be power flowing

    back to the generator during the first 10 years after the inter-tie is put into service. If in fact this proves untrue, then it canlead to a “disqualification event” where the utility wouldhave to report the portion of the intertie used to supply pow-er to the QF as income.

    In the early 1990’s, the IRS issued a large number of pri-vate letter rulings extending the policy in Notice 88-129 tonon-QF interties, gas pipelines and interconnectionsbetween utility grids. However, some IRS officials began toquestion by the late 1990’s whether the policy ought toapply to merchant plant interties. At issue was whethermerchant plants are “customers” of the utilities with whomthey interconnect and, if so, whether this meant that thechange in the tax code in 1986 that utilities had to reportcontributions from “customers or potential customers” asincome meant they must report the value of merchantplant interties.

    Notice 2001-82The new notice makes clear that most merchant plant inter-ties do not have to be reported as income. Merchant plantinterties will be treated the same as QF interties. Some of thetests in the 1988 notice are being changed to fit the new factpatterns found in the merchant power industry.

    Electric Interties continued from page 9

    The IRS made clear that most merchant plant interties donot have to be reported as income.

  • The new notice creates essentially a “safe harbor.”Interties that fall within the safe harbor will not have to bereported as income. Parties to transactions that are outsidethe safe harbor must apply for private letter rulings.

    The tests for tax-free treatment remain the same as in the1988 notice for QF interties, with the following changes. First,the generator does not have to be a QF. Second, it does not needa contract to sell electricity to a utility; a long-term interconnec-tion agreement will suffice.The IRS said that an interconnectionagreement that has no fixed term but is tied to the period thegenerator will remain in commercial operation is consideredlong term.Third, ownership of the electricity must pass fromthe generator “to the purchaser prior to its transmission on theutility’s transmission grid.”The IRS said this requirement is sat-isfied if title to the electricity passes from the generator to thepurchaser at the busbar for the power plant.The industry urgedTreasury before the new notice was issued to allow transfers atother points along the intertie before the power goes on to thegrid.The final notice allows such downstream transfers. It alsomakes clear that the transfer can be to a power marketer whois affiliated with the generator.

    The generator must recover his interconnection pay-ments for tax purposes over 20 years using the straight-linemethod. The IRS insisted on this as a tradeoff for concludingthat interties are not income to utilities.

    The notice is prospective. It applies to interconnectionpayments made pursuant to interconnection agreementssigned after December 24, 2001. Projects that already signedinterconnection agreements will have to apply for privaterulings. The IRS said it will waive its usual policy of not rulingin cases where the issue already appears on the utility’s taxreturn in order to deal with past cases.

    Wind ProjectsAdvance In Californiaby William A. Monsen, David Howarth, and Heather Vierbicherwith MRW & Associates, Inc. in Oakland, California

    As California emerges from the power crisis of the past year,windpower is uniquely positioned to benefit from a newfocus on power supply, although some barriers to more wide-spread development remain. / continued page 12

    LOUISIANA will have to defend in court itsview that owners of new merchant powerplants built in the state qualify for a 10-yeartax holiday from parish and local propertytaxes.

    A state legislator — Rep. Kip Holden (D.)— filed suit challenging an announcementby the state Board of Commerce andIndustry last August that merchant powerplants qualify potentially for the tax holiday.The tax holiday applies to all improvementsthat are part of a “manufacturing” process.

    Holden won a similar suit against wasteincinerators in 1998.

    He has temporarily withdrawn the suit,at least as it applies to merchant plants, untilafter the state formally approves the firstapplication from a merchant plant developerfor the tax holiday. Until then, the suit is pre-mature. He is pursuing the suit in the mean-time against the state on the issue whethersalt and other chemical processing plants“manufacture” a product.

    Eleven companies have asked the court tointervene on the side of the state taxauthorities.

    WIND DEVELOPERS got good news fromthe IRS.

    The US government offers a tax credit of1.7 cents a kilowatt hour for generating elec-tricity from wind. The tax credits must bereduced to the extent the project benefitsfrom government grants, tax-exempt financ-ing or other tax credits.

    The wind industry has been workinghard at the state level to persuade legisla-tures to enact their own tax credits toencourage windpower development.

    The IRS had been of the view that thesestate credits reduce the federal credit. It is notclear the IRS is right when the state credit is tiedto the amount of output at the power plantrather than its cost. Cost-based credits clearlyreduce the federal credit.

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 11

    IN O

    TH

    ER

    NE

    WS

    / continued page 13

    Cv

    bnm

  • 12 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    One significant barrier that is common to all power proj-ects in California is the issue of securing a power purchaseagreement with a creditworthy entity. Because California’sfinancially-crippled investor-owned utilities are unable toprovide the necessary level of credit support, the state hasstepped into this role. The Department of Water Resources or“DWR” is responsible for procurement, and a new ConsumerPower and Conservation Financing Authority has beenformed to ensure supply adequacy.

    Windpower has proven competitive in recent state solici-tations for long-term power supply. The state sees an oppor-tunity to reduce price volatility by including in its supplyportfolio renewable energy sources like windpower that havelittle or no fuel price risk. Somewhat offsetting the fuel pricerisk mitigation benefits of windpower is the supply uncer-tainty associated with intermittent renewable resources.Because of the uncertainty associated with the timing of

    deliveries from wind projects, wind developers typically enterinto non-firm, as-available power sales agreements. This hasbeen the case with recent DWR contracts for wind genera-tion.

    Even though wind developers can get as-available powersales agreements that have fixed commodity energy pricesand no firm power delivery obligations, the owners of theseprojects may still face price uncertainty. Under current mar-ket rules, generators incur imbalance energy charges whentheir deliveries deviate from scheduled levels. Since windgenerators have highly intermittent supply, they can be sub-jected to significant risks of imbalance energy charges.However, these issues are now being addressed through a

    collaborative process between the windpower industry andthe California Independent System Operator or “ISO.”

    DWR: The Only Game In TownDWR has stepped into the role of procuring power for theinvestor-owned utilities in California. Among the more than40 projects with which DWR has executed contracts arethree windpower projects with a total capacity of 174.6megawatts.

    A PG&E National Energy Group project, with 66.6megawatts of installed capacity, began operating in earlyOctober. The project’s contract is for a term of 10 years andhas a fixed price payment of $58.50 per mWh.

    Two Whitewater Energy Corp. projects are scheduled tobegin operation by the end of 2001. These projects have con-tracts for 12 years at a fixed price of $60 per mWh. In eachcase, DWR takes energy as delivered, with no firm capacityrequirements. The sellers retain any state or federal subsi-dies, including the production tax credit, as well as rights toany “green credits” associated with renewable generation

    that may be sold in a second-ary market. Interestingly, thesecontracts specifically addressthe issue of imbalance energycharges, with DWR takingresponsibility for paying suchcharges.

    California PowerAuthority: Major Ownerof Wind Projects?The Consumer Power and

    Conservation Financing Authority was created last summerunder Senate Bill 6X, which passed in direct response toCalifornia’s supply adequacy problems of the past year. Thepower authority is charged with ensuring reasonably priced,long-term availability of reliable supply of electricity and nat-ural gas, promoting environmentally friendly supply anddemand solutions, and achieving adequate capacity reservesby 2006. The legislation allows the authority to issue up to $5billion in revenue bonds to finance projects to be owned andoperated by the authority itself. S. David Freeman, formerhead of the Tennessee Valley Authority, Sacramento UtilityDistrict, and Los Angeles Department of Water & Power, wasselected as the power authority chairman. Freeman has a

    California Wind Projectscontinued from page 11

    California will eventually take ownership of windprojects from which it buys power.

  • long history of promoting and implementing conservationand renewable energy.

    The power authority announced a goal of acquiring 1,000megawatts of renewable energy projects to be part of a total3,000 megawatt resource portfolio by next summer. Towardthis end, the power authority has already signed letters ofintent with developers for more than 2,200 megawatts ofrenewable generation projects. More than 1,700 megawattsare windpower facilities, with all but 300 megawatts to belocated in southern California.

    The power authority intends to own and operate all non-windpower projects in its supply portfolio; however, forwindpower projects, the authority will instead enter into 10-year fixed-price power purchase agreements with the projectdevelopers. At the end of the contract period, the powerauthority would take ownership of the facilities for a negoti-ated price. The reason for this arrangement is to preserve thefederal production tax credit for private owners. The credits,which run for 10 years after a project is first placed in service,are of no value to public agencies. The power authorityexpects to sell the power from its projects to DWR.

    Although no contracts have been executed to date, thepower authority has agreed in the letters of intent to pricesfor power ranging from $40 to $50 per mWh. These pricesare competitive with other sources and are well below pricesseen in the market during the past year.

    Notwithstanding the agreement on prices, it is unclearwhen, or even whether, actual contracts between the projectdevelopers and the power authority will be signed. Since theDWR is supposed to be the purchaser of power from thepower authority’s plants, the creditworthiness of DWR mustbe assured. DWR has yet to issue revenue bonds to back itspast and future power purchases. Until the bonds are issued,the power authority’s contracts with DWR will probably haveto remain on hold.

    Imbalance Energy ChargesUnlike the credit problems, progress has been made in theeffort to address another barrier to the project financing ofwindpower projects in California. The intermittent nature ofwindpower has made it difficult to participate in ISO marketsbecause of the difficulty in hour-ahead and real-time sched-uling. To the extent that actual deliveries deviate from thescheduled amount, generators scheduling through the ISOare responsible for imbalance energy / continued page 14

    At last count, five states — Arizona,Hawaii, Montana, North Carolina andOregon — allow a tax credit that is a per-centage of the cost of a wind project.Minnesota has a tax credit that is tied to out-put. Tax credit proposals are pending inNorth Dakota and Pennsylvania.

    In late October, the IRS released a privateruling in which it said that the owner of awind project did not have to reduce his fed-eral tax credit on account of receiving“renewable energy credits” — or RECs —from the state where the project is located.The state requires local utilities to accumu-late a certain number of RECs each year.Generators of electricity using renewabletechnologies are awarded credits by thestate and then sell them to utilities. Thecredits are based on output.

    Investors in windpower projects should becareful to check for state credits as part oftheir due diligence.

    HUNGARY will overhaul its income tax sys-tem and make tax cuts in 2002, the financeminister said in October. The governmentalso plans to overhaul value added taxeswith the aim of reducing the top rates andincreasing the lowest rates to make themmore compatible with rates in the EuropeanUnion. The VAT changes are expected to takeeffect in 2003.

    DESIGNATING A SALES CONTRACT AS AHEDGE does not change the timing of whenthe seller must report income under the con-tract.

    A mineral producer contracted to sellminerals over several years, but the patternof sales varied. The seller could decide not tomake sales for an extended period. It desig-nated the contract as a hedge. The IRS saidincome did not have to be reported untilactual sales occurred under the contract. Thefact that the seller

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 13

    IN O

    TH

    ER

    NE

    WS

    / continued page 15

    Cv

    bnm

  • 14 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    charges. The financial impacts of these charges, and theuncertainty introduced by this issue, have made it difficultfor California wind projects to secure project financing.

    The operational and cost issues associated with integrat-

    ing intermittent renewable resources into the ISO grid havebeen addressed by a consensus proposal developed by an ISOintermittent resources working group. This group held week-ly meetings over the summer in an effort to develop a struc-ture through which intermittent resources could participatein ISO markets and, therefore, increase their ability to obtainfinancing while minimizing costs and impacts on ISO opera-tions

    The consensus proposal establishes a framework forimproving real-time windpower forecasting to reduce sched-ule deviations and a monthly settlement period for nettingout schedule deviations for participating wind projects. Theforecasting project will be conducted by independentexperts and be administered by the ISO, with funding from awind generator payment of $0.10 per mWh. Forecasts will bedeveloped for day-ahead and hour-ahead scheduling, andthe hour-ahead schedule will be updated by a near real-timeforecast. The forecasted amounts will be deemed delivered,so intermittent resources will not be charged for replace-ment reserves and imbalance energy. These costs will insteadbe assigned to scheduling coordinators with imbalancedload. A forecasting working group will be established tomonitor the forecasting effort and determine the impact ofwindpower on the ISO system.

    The ISO board of governors approved the consensus pro-posal at its September 20 meeting. The consensus proposalrequires certain operational and tariff modifications thatmust be approved prior to implementation. These steps are

    underway and will be considered by the ISO board in thenear future, probably as part of a broader package of tariffamendments.

    Hurdles RemainWhile progress is being made on resolving issues regardingthe integration of intermittent wind resources into the

    operation of the ISO grid inCalifornia, larger hurdles facewind project developers. ThePower Authority could con-tract for about 1,700megawatts of new windcapacity. However, the powerauthority must establish off-take agreements with one ormore creditworthy entities

    prior to acquiring these assets. The DWR is, at the moment,the main creditworthy wholesale power buyer in the state.However, DWR will not be able to enter into additionalpower purchase agreements until it has solved its bondfinancing issues.

    Current Issues InConstructionContractsby Paul Weber, in London

    A longstanding tenet of project finance dogma is that a proj-ect must be constructed pursuant to a lump-sum, turnkeyengineering, procurement and construction or “EPC” contractwhere the risks of delayed completion and failure of theplant to meet performance standards rest squarely on theEPC contractor’s shoulders.

    Market developments, cost considerations and thechanging perspectives of developers have caused somecracks in the doctrinal wall.

    Turbine WrapsMany project developers placed large orders for gas tur-bines with Siemens Westinghouse Power Corporation,

    California Wind Projects continued from page 13

    The intermittent nature of windpower makesparticipation in power pools difficult.

  • General Electric and other turbine suppliers in anticipationof using these turbines in projects under development. Fora long time, turbine slots were in short supply; the situa-tion has now turned around to a point where 100 turbinesor turbine slots are reportedly for sale. Developers typicallyenter into purchase orders for turbines prior to negotiatingan EPC contract.

    If the developer anticipates financing a project on a lim-ited recourse basis, when it negotiates an EPC contract ittypically asks the contractor to assume the turbine pur-chase order and provide a turnkey “wrap” of the turbinesupplier’s obligations in the same manner as if the contrac-tor had negotiated and entered into the turbine purchaseorder itself.

    This approach has opened the door to contractor claimsthat the turbine purchase orders are insufficient in certainrespects to allow a full wrap and may lead to negotiationsabout exceptions to the turnkey wrap. The most significantexceptions a contractor may seek relate to the amount andtiming of, and triggers for, liquidated damages payments. Forexample, if the liquidated damages payable under the tur-bine purchase order for late performance or for failure tomeet guarantees of electrical capacity and heat rate are lessthan those otherwise payable for such events under the EPCcontract, then the contractor may seek to limit its liabilityunder the EPC contract for such amounts to the amountspayable under the purchase order where the turbine supplieris responsible for the delay or performance shortfall.

    However, the determination of which party is responsiblefor a delay or performance shortfall is not necessarily a sim-ple exercise. Project construction involves numerous subcon-tractors and suppliers performing thousands of tasks. Asolution is to allocate responsibility for the delay or perform-ance shortfall between the contractor and turbine supplierand to adjust the liquidated damages accordingly. This is acomplex task and is likely to result in delays in finally deter-mining the amounts due. This issue can be partiallyaddressed by providing that the contractor must, at a mini-mum, pay liquidated damages in the amounts providedunder the turbine purchase order.

    Other mismatches between the obligations of the tur-bine supplier and the EPC contractor may lead to othercontract adjustments. For example, where guaranteedequipment delivery times under the turbine purchaseorder do not support the contractor’s / continued page 16

    labeled the contract a “hedge” for tax pur-poses does not change the timing of whenincome had to be reported, the IRS told oneof its agents in a “field service advice.” TheIRS memo is FSA 200146046.

    AN “OWNERSHIP FSC” transaction is underaudit.

    The IRS released a “field service advice” inlate November in which it told the agenthandling the audit to disallow the tax bene-fits claimed by the lessor.

    An ownership FSC is a form of cross-bor-der lease where an aircraft or other equip-ment is leased by a US lessor to a foreign les-see. The transaction is structured to takeadvantage of US foreign sales corporationrules that allow the US lessor to avoid havingto report up to 30% of the rents as income. Inthe meantime, the lessor also has tax depre-ciation and interest deductions to claimfrom the transaction.

    Roy Meilman, a leasing expert atChadbourne, said “there are the usual dele-tions and the facts are a bit garbled, but itseems fair to say that the transaction struc-ture under audit was substantially moreelaborate than in a standard OFSC transac-tion.” For one thing, the transaction involveddefeasance arrangements, which are atypi-cal in a FSC lease. The IRS focused on a rightthe lessee had to buy the airplane at the endof the lease for a fixed price. It concludedthat the transaction had been structured tomake exercise of the purchase option a fore-gone conclusion by the lessee so that the les-see should be viewed as owning the equip-ment for tax purposes from inception. TheIRS position is explained in FSA 200145002.

    LOAN GUARANTEE FEES from a US sub-sidiary to its foreign parent are subject to USwithholding taxes.

    A US company borrowed money. Its for-eign parent guaranteed

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 15

    IN O

    TH

    ER

    NE

    WS

    / continued page 17

    Cv

    bnm

  • 16 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    milestone schedule, the EPC contract may provide for achange order if the turbines are not timely delivered.Broader force majeure provisions in the turbine purchaseorder may find their way (as to the turbine supplier only)into the EPC contract.

    These sorts of exceptions to the turnkey wrap of an EPCcontract should not render the contract unfinanceable.Rather, the lenders will analyze the EPC contract in light ofthe additional risks the exceptions pose and will look to thedeveloper to cover those risks. For example, if the EPC con-tract contemplates scenarios under which liquidated dam-ages may be payable at the rate provided for in the turbinepurchase order, lenders will analyze whether liquidateddamages payable at the lower rate adequately cover thecosts to the project of delays or performance shortfalls. Ifthey do not, then the lenders will likely require that thesponsor provide a contingent equity commitment to coverpotential shortfalls.

    Construction Management AgreementsSome developers have been taking a very different approach.They are not looking for the contractor to wrap the turbinecontract and in certain instances are not looking for the con-tractor to provide liquidated damages or minimum perform-ance guarantees. These developers, including those that arethe offspring of electric utilities, may have substantial histo-ries of constructing power plants other than on a turnkeybasis and managing the construction process. They areaccustomed to putting their balance sheets behind the con-struction effort. The payoff is a substantial reduction in theEPC contract price; contractors charge significant sums forfull turnkey wraps. Another payoff may be a shorter period of

    time to get a contract in place and construction underway.The clear downside to this approach is that these con-

    tracts are not financeable without sponsor support. One wayto provide this is through a sponsor construction guaranteeor a contingent equity funding commitment in favor of thelenders. Another approach which may avoid balance sheetrecognition of the contingent liabilities of a guarantee orequity funding commitment is for the sponsor to enter into a

    construction managementagreement. This agreement isdrafted to fill the gaps in theEPC contract — to provide forthe payment of liquidateddamages or for minimum per-formance guarantees wherethe EPC contract is lacking.

    The construction manage-ment agreement is entered

    into by the sponsor with the developer— not the lenders —and it makes no mention of project debt. Hence, it is not afinancial guarantee or equity funding commitment. This mayhave the effect of permitting the sponsor to exclude theseobligations from its financial obligations for purposes ofdetermining whether certain of its financial covenants aremet under its corporate financing agreements. The construc-tion management agreement is collaterally assigned to thelenders. The bargain struck by developers taking thisapproach is clear: substantial savings on construction costscome at the price of substantial recourse.

    The lump-sum turnkey EPC contract is far from dead andis still the preferred approach of developers for managingconstruction risks. However, where the circumstances requireor where the savings of taking other approaches are com-pelling, developers have shown a willingness to look at otherapproaches to managing construction risks.

    Lender Held Liable ForConstruction Defectsby Thomas J. Hall and Douglas M. Fried, in New York

    Lenders want to be repaid. Taking prudent steps to protectthe value of collateral enhances this prospect. In construc-

    Construction Contractscontinued from page 15

    Most developers expect the construction contractor to“wrap” the turbine contract.

  • tion financing, lenders have a legitimate interest in assuringthat loan proceeds are put to good use and that the con-struction work is properly performed in a timely manner.

    However, where is the line between a lender takingresponsible and prudent steps to protect its capital and secu-rity, and the lender exercising management over the con-struction so as to expose itself to liability for constructiondefects?

    A recent jury verdict in the New Jersey Superior Court canbe instructive for all types of construction lending.

    The AllegationsIn 1999, the Ocean County Club Condominium Associationbrought suit against the developer of its Atlantic Cityhighrise condominium complex alleging, among otherthings, defective construction work including leaks, deteri-orating balconies and building code violations. The devel-oper, in turn, brought suit against its construction lender,Bank of America National Trust and Savings Association,alleging that the bank was responsible for any such con-struction defects.

    The developer’s complaint charged that the bank, as acondition to its financing, required the developer to retainPavarini Construction Company, Inc. as the general con-tractor. The developer charged further that the bank knew,or in the exercise of reasonable diligence should haveknown, that Pavarini was not competent to construct orpromptly complete the project. The project needed a con-tractor with experience in highrise, ocean-front construc-tion. The developer claimed that the bank required thatPavarini be hired to further that bank’s own business rela-tionship with Pavarini. The developer also claimed that thebank misrepresented the ability and qualifications ofPavarini and induced the developer to accept Pavarini asthe contractor.

    The VerdictFollowing a three-month trial, the jury found the bankliable in late September, concluding that the bank had devi-ated from accepted standards of banking practice andimproperly exercised effective control over the construc-tion. The jury returned a punitive damage verdict againstthe bank in the amount of $6.6 million. In a proceduralquirk, a separate jury will now determine the amount ofcompensatory damages, if any, to be / continued page 18

    repayment of the loan. The subsidiary paidthe parent ongoing guarantee fees.

    The United States normally collects a30% withholding tax on payments by UScompanies to persons who are offshore. Therate is sometimes reduced by treaty.Withholding taxes ordinarily apply only topayments that are considered to have a “USsource.”

    The subsidiary argued in this case thatthe payments are foreign source becausethey are for services by the parent, and theservices are performed abroad. The IRS saidthat the payments are more in the nature ofinterest, which is sourced to where the payorresides — in this case, in the United States.

    The taxpayer then argued that the with-holding tax should be at less than a 30% ratebecause a tax treaty between the US and thecountry that is home to the parent companyprovides for a lower withholding rate on“interest.”The IRS said the provision does notapply because guarantee fees are not literal-ly “interest.”

    The IRS released a “field service advice” inNovember on the case. The number is FSA200147033.

    ENVIRONMENTAL CLEANUP costs had to becapitalized, a federal appeals court said inOctober.

    United Dairy Farmers, Inc. purchased twostores in Ohio. Both properties had contami-nated soil caused by leaking undergroundstorage tanks. UDF spent money to clean upthe soil and replace the leaking tanks. Thecourt said the spending had to be capitalizedrather than deducted. UDF could have paidmore for the property and had the sellerclean it up, in which case its costs wouldclearly have gone into its tax basis in theproperty.

    The court said a company can onlydeduct cleanup costs if it did the pollutingitself and the cleanup is

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 17

    IN O

    TH

    ER

    NE

    WS

    / continued page 19

    Cv

    bnm

  • 18 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    awarded to the developer. These verdicts are subject topost-trial motions and appeal.

    The Lesson LearnedThere are various ways by which a construction lender canprotect its collateral while minimizing its potential liabilityexposure. The key is to leave decisionmaking with the bor-rower while establishing certain parameters to protect thelender. For example, instead of requiring the developer touse a particular contractor, the lender could have retainedapproval rights over the developer’s choice of contractor.Alternatively, the lender could have withheld commitmentto the financing until such time as the borrower selected areputable contractor acceptable to the lender, or the lenderand borrower might have agreed to a list of acceptablecontractors from which the contractor could choose.Variations on these approaches exist. With any of theseapproaches, appropriate disclaimers in the loan documentswould be helpful as well as a contractual obligation thatthe borrower thoroughly investigate the qualifications ofthe contractor it chooses. These concepts could also bemade applicable to the selection of major subcontractorsand other professionals.

    What may have doomed the bank in this case is thecharge that the bank directed the use of a particular contrac-

    tor out of its own self interest. The developer alleged — andapparently the jury believed — that the bank imposed thecontractor, not to assure that the construction would be sat-isfactorily performed, but to advance its own relationshipwith the contractor. In the jury’s mind, this may have beenwhere the line was crossed.

    Political RiskCoverage: What’sNew?by Julie A Martin, with Marsh McLennon, and Kenneth W. Hansen,in Washington

    The October Newswire carried an article reviewing the coretraditional political risk insurance coverages available fromthe private and public agency insurers, namely coverageagainst expropriation, political violence and currencyinconvertibility. It concluded with a promise to discuss inthe next Newswire the cutting edge innovations and otherdevelopments in the political risk insurance arena, includ-ing developments post-September 11.

    The parameters of the traditional coverages have beensubstantially settled for the past half century. Recent yearshave seen growing pressure to update conventional cover-ages, by expanding or enhancing the scope of coverage toencompass more contemporary risks — notably breach ofcontract by governments and currency devaluation risk.

    Breach of ContractExpropriation cover has traditionally compensatedinvestors for a government’s taking of a project withoutadequate compensation. With the nineties and the fall of

    the Berlin Wall came privati-zations in myriad forms.These included all shades ofpublic-private partnershipsand private projects based onpublic undertakings, such assovereign guarantees of theperformance of state-ownedentities that act as offtakersand fuel suppliers. The gov-ernment became if not overt-

    ly, at least for all practical purposes, a partner in thedevelopment and success of these projects.

    Traditional expropriation cover protected privateinvestors from the government seizing their property, butsuch coverage was never intended to protect one partnerfrom bad acts of another partner — including the govern-

    Lender Liability continued from page 17

    Lenders should not select the construction contractor.

  • ment. Indeed, coverage often explicitly excludes from thedefinition of expropriation the failure of a government toprovide goods, services or cash promised to a project or itsinvestors. Breach of contract by the government may beexplicitly carved out from the scope of coverage or simplybe unlikely to fall within the boundaries of the more con-ventional definitions of expropriation.

    Yet a government’s breaches of obligations upon whichthe project’s economics are founded are clearly a politicalrisk and a critical risk to mitigate if the public-private part-nerships that have come to dominate infrastructure devel-opment in emerging markets during the past decade are tobe successfully developed and financed.

    The traditional mitigation for the risk of breach of con-tract is a lawsuit. Perform or pay damages. As imperfect aremedy as that may be for commercial counterparties, it isscant comfort when dealing with sovereigns — who aresubstantively omnipotent and, if they choose, immune tosuit. Consequently, subject to the relatively minimal con-straints of international law, they may be quite free to treatand mistreat their business partners as the mood, or thecurrent administration, sees fit and to do so free from anyconcern of being held accountable in court.

    Thus arose demand for “enhanced expropriation cover-age” to cover the risk that sovereign partners will walkaway from their promises.

    The market demand has been met, at least part way, byboth commercial and agency insurers offering variations of“disputes cover.”

    Under such cover, if a government breaches a contractthat has an arbitration provision, the project company or, asappropriate, the project sponsors must invoke that clause.If the government loses the arbitration, including by failureto participate, but fails to pay the arbitral award, then theinsurer pays that award. A common theme of these cover-ages is that the insurer depends upon an arbitral panelrather than its own staff or the insured to determinewhether a breach has occurred.

    Demand for coverage that avoids the requirement ofpursuing arbitration in advance of a claim payment fromthe insurer has been substantial. Though a number ofinsurers have agreed to provide such coverage in connec-tion with direct payment obligations of a government orone of its ministries under export sales or other contracts,it generally remains a step beyond the / continued page 20

    merely to restore the property to its formercondition rather than prepare it for a differ-ent use.

    The case is United Dairy Farmers, Inc. v.United States. The decision is by the 6thcircuit court of appeals. The court cited asimilar holding in a case last year in the4th circuit involving Dominion Resources

    LEASE REFINANCING COSTS must be amor-tized over the remaining lease term.

    In most big-ticket lease financings ofequipment, the lessee has a right to causethe lessor to refinance the debt if interestrates fall. Rents are then recalculated to passthrough the benefit of the lower financingcosts. The lessee pays the cost of the refi-nancing as “supplemental rent.”

    The owner of a power plant got into adispute with the IRS about such a provisionrecently on audit. The parties amended theparticipation agreement for an existingpower plant lease to give the lessee the rightto ask for a refinancing. The lessee then exer-cised this right. At the same time, the partiesagreed to extend the term of the lease. Thelessee deducted the cost of the refinancingas additional rent. The IRS said it had to beamortized over the remaining term of theextended lease.

    The lessee argued that spending toreduce future costs can be deducted imme-diately. The IRS said the spending in this caseserved two purposes — not only to reducerents but also to extend the lease. The IRSexplained its position in a “technical advicememorandum” in November. The number isTAM 200145003.

    MINOR MEMOS: The IRS has asked for com-ments on “disguised” sales of partnershipinterests. The issue is when should the IRStreat partners whose interests are diluteddownward after the admission of a newpartner as having sold

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 19

    IN O

    TH

    ER

    NE

    WS

    / continued page 21

    Cv

    bnm

  • 20 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    cutting edge for infrastructure projects. Still, some projectdevelopers are currently pressing both commercial andagency insurers to provide such cover in connection withgovernment undertakings in support of infrastructure proj-ects. This is an area where further evolution is likely.

    Currency Devaluation CoverThe Asian economic crisis, triggered in 1997, highlighteddisappointment in the marketplace with the inability toinsure against the risk that a currency would not becometechnically inconvertible but would suffer a wholesale col-lapse in its market value. Although forward contracts andother currency hedges exist, in emerging market currenciessuch instruments are scarce and for, at best, very shortterms. Project term lenders would very much appreciate a

    hedge against the risk of project debt defaults as a conse-quence of a general collapse in the value of the host coun-try currency.

    Until recently, this was generally deemed an insolubleproblem. This past May, however, the AES Tiete projects inBrazil closed a $300 million project bond issue supportedby a devaluation guaranty from OPIC. (See related article inthe June 2001 NewsWire.) The industry has been holding itsbreath a bit since then to see whether this would prove aunique event or the first in a series.

    The second volley sounded in late November. SovereignRisk Insurance Ltd., a leading commercial political riskinsurer, issued a press release indicating that it was pre-pared to issue devaluation insurance for lenders to appro-priate projects. Where this will all lead is an open question,

    but it is likely that, while the number of transactions maybe constrained by short supply of available coverage, a newproduct line may be taking form in the political risk mar-ketplace.

    Capital Markets CoverOne relatively recent development in the political risk mar-ket relates not to the scope of coverages but to the benefi-ciaries. Originally, political risk insurance was very muchassociated with equity investment. In the 1990s, there wasgreat growth in demand by institutional lenders for suchcoverage to support their foreign project loans. Morerecently, such coverage has been sought for bond offeringsand has been provided both by agency and private politicalrisk insurers.

    Beginning in July 1999 with the Overseas PrivateInvestment Corporation’s currency inconvertibility coverageof bonds issued by Ford Otosan in Turkey, many of the other

    providers have also nowissued coverage on such capi-tal markets transactions.More than a dozen bondissues have now been suc-cessfully supported withpolitical risk insurance.

    The coverage can enablean investment grade projectin a non-investment gradecountry to “pierce the sover-eign ceiling” and achieve an

    investment grade rating. The benefits are greater access tothe US capital markets and improved pricing.

    Terrorism Cover Post-September 11Political violence coverage, whether from formal warfareor informal terrorism or insurrection, has been solidlywithin the core coverages available from political riskinsurers for the past half century. And it continues to beavailable today. Yet the headlines have correctly reported acollapse in the availability of, and escalation of the pricingfor, such coverage.

    Not surprisingly, the most dramatic developments havebeen in the arena of property (damage) and casualty (liabil-ity) insurers. Though not generally considered part of therelatively narrow fraternity of political risk insurers, proper-

    Political Risk Insurancecontinued from page 19

    More than a dozen bond issues have now beensuccessfully supported with political risk insurance.

  • ty and casualty insurers have conventionally covered warand terrorism coverage as part of their basic coverage,mostly via the lack of specific exclusions, and at little to noincremental premium. The supply of such insurance for air-craft, marine vessels, and industrial and commercial facili-ties has been dramatically cut back. Reinsurance treatiesthat expire December 31 of this year pose the prospect forspecific terrorism exclusions or very specific sublimits aswell as price increases still to come. A number of legislativeproposals that are intended to stem the unwinding ofcapacity for such insurance in the United States are nowpending in Congress.

    The situation for casualty liability insurance is more direin emerging markets where, for the moment, some insurersare hesitating to offer coverage for any kind of casualty lia-bility. The likelihood is that markets will soon develop newmechanisms to fill the vacuum and provide casualty cover-age generally, but terrorism cover as an element of suchcover is no longer automatic, much less free, and its avail-ability post-January 1, 2002, when existing reinsurance plat-forms expire and remain to be renegotiated, is very muchan open question in certain emerging markets.

    As for property insurance, many companies with billionsof dollars in assets are facing the prospect of no terrorismcoverage at all or, at best, coverage with limits of $5 millionin total. While some terrorism coverage is being placed inthe London market and, with the announcement of a newfacility this week, by AIG in the property markets, limits inboth facilities remain small and the coverage is expensive.

    In late November, representatives of the major multilat-eral development banks plus a number of US trade promo-tion and development agencies gathered in Washington todiscuss how they might, individually or jointly, act to assureavailability of adequate coverage to support infrastructureprojects in emerging markets. What products or initiativesmay emerge from these agency efforts remains to be seen.But organizations that in the best of times require time tonavigate initiatives through a maze of policies, politics andlegislative hurdles are not likely to head off entirely avail-ability or cost problems whose severity will probably esca-late effective New Year’s Day.

    Notwithstanding the arsenal of political risk mitigantsavailable in the private and public agency marketplaces, itis clear that the correspondence between risks and miti-gants is far from perfect. While / continued page 22

    DECEMBER 2001 PROJECT FINANCE NEWSWIRE 21

    IN O

    TH

    ER

    NE

    WS

    Cv

    bnm

    part of their interests to the new partner.That could trigger a gain. It would only hap-pen in cases where cash the new partner putinto the partnership was effectively distrib-uted to the existing partners. Comments aredue by March 31 . . . . The head of the largeand mid-size business division at the IRS saidthe agency is concerned about cases wherecorporate partners walk away from partner-ships with large deficits in their capitalaccounts and the partnership fails to file itslast tax return . . . . Pamela Olson, the numbertwo tax policy official in the US Treasury, saidon October 19 that the government is con-sidering waiving penalties for companieswho voluntarily disclose their participationin certain aggressive tax schemes that theIRS has targeted on audit. The governmentwill want copies of any marketing materialsand the name of the broker who sold themthe transaction. It will then go after the bro-ker for his customer lists.

    — contributed by Keith Martin, HelénaKlumpp and Samuel R. Kwon in Washington.

  • 22 PROJECT FINANCE NEWSWIRE DECEMBER 2001

    demand for the products readily available in the market isprobably stronger today than at any time in recent memo-ry, it is also clear that important risks spill over the bound-aries of the scope of the traditional products. Those riskstake careful identification and negotiation — or will quietlygo unmitigated and, with some probability, arise to hauntthe project and its investors. Commerce, like nature, abhorsa vacuum, so it is much more likely that risk mitigants willbe found. Who -– that is, which companies, which agencies

    of which countries, and which multilateral organizations —will step in, with what products and at what price remainsto be seen.

    Spotlight On CaptiveInsuranceby Heléna Klumpp, in Washington

    More and more companies appear to be setting up captiveinsurance subsidiaries. In 2000, the number of captivesincreased worldwide by 31.6% over the prior year, climbingto more than 3,400. Insurance industry specialist A.M. Bestpredicts that the 2001 figures will show continued stronggrowth in the number of captives.

    Captives became popular as companies sought waysaround the skyrocketing insurance premiums that resultedfrom a tightening of the insurance market in the mid-1980’s. Although at first glance self insurance appears to bethe best way to cut costs, amounts set aside in a self-insur-

    ance reserve are not deductible for tax purposes (as com-pared to traditional insurance premiums, which are). Thecaptive market boomed as companies figured out arrange-ments that allowed them to enjoy the best of both worlds:lower insurance costs plus deductibility of premiums.

    CaptivesIn the simplest, or “single parent,” captive structure, a par-ent company establishes a wholly-owned subsidiary toinsure or reinsure the parent company or other companiesin the parent company’s group. The subsidiary, known as a“captive insurance company” or simply a “captive,” is incor-

    porated in a US state or for-eign country that has acaptive insurance statute.Nearly a third of the world’scaptive insurance companiesare located in Bermuda. Thenext most popular locationsare the Cayman Islands,Vermont, Guernsey,Luxembourg, Barbados, theBritish Virgin Islands, Ireland,

    the Isle of Man and Hawaii. Washington, DC established acaptive insurance regime in 2000.

    Offshore jurisdictions are popular for several reasons,most notably for the fact that some maintain less stringentregulatory requirements for insurers and reinsurers. Forexample, many US states strictly regulate the type ofinvestments an insurance company can make. Many off-shore captive jurisdictions have no such restrictions. Also,when they first came onto the insurance scene, captivesthat were established in tax havens like Bermuda or theCayman Islands were able to avoid income taxes on theirunderwriting and investment profits. The US tax laws havesince evened this playing field, requiring current taxation inthe US of the income of most offshore captive insurancecompanies that are owned by US parents. (There are someexceptions to this rule for offshore captives of US parentsthat insure risks located in the captive’s home country or inany other country but the US. Those exceptions are set toexpire at the end of this year, but may be extended byCongress.) Some state premium taxes may still be avoidedby incorporating a captive in an offshore jurisdiction.

    The captive can be used to insure against the same

    Political Risk Insurance continued from page 21

    Many companies with billions of dollars in assets arefacing the prospect of no terrorism coverage at all or, atbest, coverage with limits of $5 million in total.

  • DECEMBER 2001 PROJECT FINANCE NEWSWIRE 23

    types of risks for which a corporation would use a third-par-ty insurer or self-insurance program: property and casualty,general and product liability, workers’ compensation, etc.

    In a different twist on the same basic idea, the cap-tive may reinsure primary liability coverage written forother members of its group by a third-party insurer. Mostcaptive insurance companies are reinsurers. This is truefor a number of reasons, especially the fact that a thirdparty who deals with the insured party — for example, alender — may be more comfortable if a recognizableinsurance name is the company’s primary insurer. Also,inmany jurisdictions the reporting and capitalizationrequirements are less onerous for reinsurers than for pri-mary insurers.

    Other variations on the basic captive structure includeseveral different types of “group captives,” in which a singlecaptive is owned by a number of unrelated corporate par-ents. The parents are typically similar in size or in the sameindustry or both.

    BenefitsInsuring through a captive may be attractive for a numberof reasons.

    First, a captive may be able to charge lower premiumsbased on a company’s loss experience. A third-party insurerbases the premiums it charges on industry loss averages. Acompany whose loss experience is lower than the normmay thus pay a rate that takes into account the higheraverage. When a company in that position insures througha captive, its loss experience will be viewed in isolation andthe premiums will be priced lower accordingly. In otherwords, the insured’s premiums will be based on its particu-lar level of risk instead of an insurance carrier’s generalview of the market for that type of coverage. Thus, a com-pany whose loss experience is lower than average may ben-efit from using a captive.

    In addition, a captive insurer — particularly a reinsurer— will save on overhead costs associated with commissions,marketing, claims handling and regulatory compliance.These costs can be high for an insurance company and mayrepresent close to half of an insured’s premium. By contrast,the overhead of a captive is insignificant. This is especiallytrue in the case of an offshore captive, which is less likely tobe burdened with extensive regulatory requirements.However, in many cases, marketing, commission and other

    acquisition costs will be low or nonexistent for a captive.Another benefit is that the captive can earn investment

    income on its premiums and thus potentially reap financialgains for the corporate group that would otherwise be lostto a third-party insurer. This investment income is typicallysubject to income tax in the US, either directly (where thecaptive is a US entity) or indirectly through anti-deferralrules that apply to certain offshore entities (where the cap-tive is a foreign entity).

    A captive may be able to provide coverage that isunavailable or prohibitively expensive if purchased fromthird-party insurers. The insurance market is cyclical. Lowpremiums one year may lead to high premiums the follow-ing year to make up for the insurance companies’ losses. Acaptive’s risks are more isolated than a traditional insur-ance company and thus it is less subject to the market’svolati