cwd customer service turnaround project - phase 1

29
1 CITY OF CLEVELAND CWD Customer Service Turnaround Project - Phase 1 Project Briefing for Cleveland City Council, Public Utilities Committee November 16, 2011

Upload: others

Post on 01-Jun-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CWD Customer Service Turnaround Project - Phase 1

1

CITY OF CLEVELAND CWD Customer Service Turnaround Project - Phase 1

Project Briefing for

Cleveland City Council, Public Utilities Committee

November 16, 2011

Page 2: CWD Customer Service Turnaround Project - Phase 1

2

Agenda

• Turnaround Project

o Goals

o Actions and Accomplishments

o Overall Evaluation

o Phase 2

• DPU/CWD Reorganization

Page 3: CWD Customer Service Turnaround Project - Phase 1

3

Project Goals

• Accurate meter readings • Accurate bills • Quickly answering customer calls and first call resolution • Collecting money owed to CWD for water usage • More responsive to the needs of our jurisdictional partners

Key Issues

• Incomplete and ineffective operating procedures/processes

• Non-optimal organization structure and staffing, skills, training

• Lack of daily/weekly/monthly metrics for each business area

• Large backlogs (pended bills, field orders, etc) • Competing projects, prioritization of resources

Page 4: CWD Customer Service Turnaround Project - Phase 1

4

Actions and Accomplishments

Stabilization of core customer service areas • More accurate meter readings – fewer estimated bills • More accurate bills – fewer pended bills • Improved call center operations • Increased collections; turn-offs of delinquent

accounts • Substantial reductions in backlogs • Coordinated/prioritized competing projects

Comprehensive analysis of root causes • Issues are pervasive - no “silver bullets” • Fixed 73 technical/systems/data issues • Improved 54 operating procedures/processes • Comprehensive approach yielded 145 priority

improvements for Phase 2

Page 5: CWD Customer Service Turnaround Project - Phase 1

5

Accurate Meter Readings

• Fixed ubiquitous handheld “double-beep” warning

• Improved accuracy of meter readings by at least 8% (positive impact on over 33,000 quarterly bills)

• Integrated vacant property information into CC&B

• Identified accounts associated with vacant lots (4,800) and unoccupied properties (2,500) - stop uncollectable billings

• Completed/eliminated field activities which prevented more current work from being scheduled

• Eliminated nearly 10,000 unresolved field activities

• Identified true non-progressing meters

• Eliminated field investigation work for 23,000 locations not requiring meter change/repair

Page 6: CWD Customer Service Turnaround Project - Phase 1

6

Accurate Bills

• Began billing active meters that had not been billed • 2,574 accounts will now be consistently billed

• Resolved missing service agreements for accounts with multiple services • 2,089 accounts will now be billed for all services (water,

waste water, local charges) • Reduced backlog of suppressed bills

• August 12 - 1,923; November 4 - 194 • Increased billing based on actual reads

• Prevented valid low meter reads from failing the very low check, resulting in estimated bills

• Improved remediation of non-progressive meters • Reduced number of estimated bills by 10,000

• Corrected accounts that had received inaccurate final read adjustments • 353 account adjustments being corrected by backlog team

Page 7: CWD Customer Service Turnaround Project - Phase 1

7

Quickly Answer Customer Calls

• Implemented new call center metrics which are in-line with industry standards • Answer 80% of calls in 30 seconds or less • Abandoned call rate less than 5%

• Consolidate all call centers under one manager • Improved oversight of similar job functions

• Developed call scripts for frequently occurring call types • Ensures consistent information from customer service

representatives • Cross-trained CSR’s to handle calls in all queues

(Customer Service, Pay and Collections) • Improves wait times and reduces call transfers

• Created dedicated work group to support complex billing issues

Page 8: CWD Customer Service Turnaround Project - Phase 1

8

Page 9: CWD Customer Service Turnaround Project - Phase 1

9

Collect Money Owed to CWD

• Restarted active collections efforts on August 1, 2011:

• Eliminated non-collections activities from Collections

• Developed prioritized Collections Plan

• High $ accounts first

• Implemented outbound collections contacts

• Redeveloped customer contacts

• 1st notice, final notice, tenant notifications, door hangers

• Training/coaching to improve staff performance

• Stopped sending active accounts to collections agency

Page 10: CWD Customer Service Turnaround Project - Phase 1

10

Collect Money Owed to CWD, con’t

• Implemented corrections to past due totals on final notices

• Notices now show outstanding balances for all service agreements

• Removed credit score as a criterion for disconnections

• Equitable treatment of all customers

• Correct credit review date so that accounts are eligible for shut-off once delinquency criteria are met

• System flaw postponed the credit review date for some accounts until 2040 or later

Page 11: CWD Customer Service Turnaround Project - Phase 1

11

Page 12: CWD Customer Service Turnaround Project - Phase 1

12

• From September 2009 through July 2011, Water A/R averaged $1M per month increase

• 9/09 : $19.0M – 7/11: $43.1M

• Since August 1, 2011, A/R more than 180 days delinquent is declining

Page 13: CWD Customer Service Turnaround Project - Phase 1

13

Coordinate/Prioritize Competing Projects

• July 16, 2011 CWD fixed rate charge

• IT contractors and employee resource coordination

• AMR/Turnaround Project integration

• Ensure AMR project ‘fit’ with customers and CWD customer service operations

• January 1, 2012 rate changes

• CWD, NEORSD, Euclid, Strongsville, North Olmstead, Fairview Park, Bedford Heights, Newburgh Heights

Page 14: CWD Customer Service Turnaround Project - Phase 1

14

Responsive to Jurisdictional Partners

• Developed process for coordinating service requests from other jurisdictions

• Single point of contact

• 90 days notice for simple rate change

• 180 days notice for structural changes

• Developed implementation strategy for January 1, 2012 rate increases

• CWD, NEORSD, Euclid, Strongsville, North Olmstead, Fairview Park, Bedford Heights, Newburgh Heights

• NEORSD customer service coordination

• Euclid and Bedford Heights waste water collections

Page 15: CWD Customer Service Turnaround Project - Phase 1

15

Use of Operational Metrics

Page 16: CWD Customer Service Turnaround Project - Phase 1

16

B&V evaluation at beginning of Phase 1

Page 17: CWD Customer Service Turnaround Project - Phase 1

17

B&V evaluation at end of Phase 1

Page 18: CWD Customer Service Turnaround Project - Phase 1

18

Phase 2 – Building on Improvement

Phase 1

• “Stop the Bleeding”

• Root cause analysis

• Focus on highest value fixes

Phase 2

• Entrench normal operations

• Finish core system fixes

• Complete mandatory projects

• Implement prioritized enhancements by June 30, 2012

Page 19: CWD Customer Service Turnaround Project - Phase 1

19

Phase 2 Focus

• Complete system fixes by March 31, 2012 • Complete data integrity fixes, e.g. Datamatic interface • Resolve all backlog causes, e.g. invalid “to-do’s” and field

activities • Complete other CWD priorities by June 30, 2012

• Adoption of Phase 1 process improvements • Weekly metrics-driven performance management • Complete backlog resolution • Automate active collections • Integrate CC&B (billing system) with Ellipse (work

management system) • Complete all mandatory projects

• Oracle database upgrade • CC&B version upgrade • 9 new rate structure changes and increases • AMR – interface completion, business impact/process

changes, training, testing, deployment

Page 20: CWD Customer Service Turnaround Project - Phase 1

20

City of Cleveland Department of Public Utilities Reorganization Plan

Presented to Cleveland City Council, Public Utilities Committee

November 16, 2011

Page 21: CWD Customer Service Turnaround Project - Phase 1

21

Motivation for Reorganization

• Strengthen business focus on customer service • Business areas operating in “silos”

• Redundant operations within divisions

• Improve customer service and utilities operations support functions – HR, IT, Finance, Communications • Inefficient and redundant operations across

divisions

• Complete DPU-wide organizational reviews undertaken over the past two years

Page 22: CWD Customer Service Turnaround Project - Phase 1

22

Why Reorganize?

• Improve efficiency • Provide better cost effective customer service

• Deliver excellent customer service

• Make customer service DPU’s top priority • Responsive to our customers and regional partners

• Facilitate accountability

• Reduce layers of bureaucracy with oversight of customer service function

• Simplify organizational structure to: identify problems; elevate problems for solution; solve problems; and hold managers accountable when solutions are not achieved in a timely fashion

Page 23: CWD Customer Service Turnaround Project - Phase 1

23

Why Reorganize?

• Position DPU and CWD for future changes • Technological, Operational and Financial

• Make DPU a “provider of choice” to allow for service area expansion to further reduce average costs

• Focus CWD on its core activity – delivering high quality water • Maintain water quality

• Make DPU/CWD a model for other utilities

Page 24: CWD Customer Service Turnaround Project - Phase 1

24

How is the new structure different?

• Elevate customer service as a DPU priority – reports to Director through the Assistant Director of Public Utilities

• Eliminate two layers of bureaucracy over CS

• Consolidate all CS business areas under A.D.

• Meter Services, Billing Services, Customer Care and Collections

• Implement CS metrics for all divisions with monitoring by A.D.

• Consolidate functional/support services at DPU level in four areas:

• Chief Information Officer, Chief Financial Officer, Chief of Public Affairs and HR Manager

Page 25: CWD Customer Service Turnaround Project - Phase 1

25

How will things be better?

• DPU/CWD well positioned to maintain and build upon improvements of Turnaround Project

• Better customer services means: • Accurate meter readings • Accurate bills • Quickly answering customer calls and first-call resolution • Collecting money owed to CWD for water usage

• DPU and CWD better positioned for future growth/challenges

• Provider of “choice” • Shift to fixed cost recovery model • Equalization of rates

• Continue to provide high quality water

Page 26: CWD Customer Service Turnaround Project - Phase 1

26

CommissionerCWD

Asst. CommissionerPlant Operations

Asst. CommissionerIT

Asst. CommissionerEngineering

DPU Security

Asst. CommissionerD&M

Risk Manager

Asst. CommissionerCAS

Strategic Business Program Manager

Asst. CommissionerBudget and Finance

Communications Manger

Asst. CommissionerHuman Resources

Dep. CommissionerOrg. Performance

Dep. CommissionerCustomer Focus

Benefits and Payroll

Talent Acquisition &Workforce Planning

Performance Management

Employee/Labor Relations

Performance Development and

Support

PU Building Maintenance

Project Director

Central Warehouse

Finance/Procurement

Capital Finance Projects

Billing/Meter Reading Admin. Manager

Customer Service/Collections Admin.

Manager

CAS Admin. Project Director

Budget/Procurement Projector Director

IT Administration

GIS

IT Manager

Safety Programs Manager

Sustainability Programs Manager

Environmental Programs Manager

Asst. SBP Manager

Project Director

Special Events

Graphic Design

Media Communications

Public Outreach/Legislative Affairs

CWD “As Is” Organizational Chart

Chief of Dist. Administration

Chief of Dist.Pipe Repair

Chief of Dist.Meters

Asst. AdminBudget and

Procurement

Building Maintenance

General Maintenance Manager

Communication Center

Process Management

Capital Projects/Facilities

Management

Advance Planning and Hydraulics

Administration

Dist. Inspector

Dist. Engineer, Permits and Sales

Backflow Admin. Manager

Asst. Administrator

Baldwin

Crown

Morgan

Nottingham

Parma Control

Water Quality

Maintenance

Consulting Engineer

Legend

Reporting Structure

Changed by DPU Consolidation

Reporting Structure

Changed by CWD Reorganization

Page 27: CWD Customer Service Turnaround Project - Phase 1

27

DirectorDPU

CommssionerCWD

CommissionerWPC

Chief Information

Officer

CommissionerCPP

Chief Financial

Officer

Chief of Public

Affairs

HR Manager

Customer Care Manager

Collections Manager

Billing Services Manager

Commercial Care/High Level

Complaints Unit

Meter Services/AMR Manager

Water Review Board

Web

IT Security

Telecommunications

Standards

Infrastructure

Application Support

Rates

Controller

Risk Management

Budget

Legislation

Community Outreach/Special

Events

Strategic Planning

Communication

Coordination with City Priority

DPU “To Be” Organizational Structure

Asst. DirectorCustomer Service

Labor

Recruitment

Training

Personnel

Compensation

Intergovernmental Affairs

Procurement

Security/DPU Police

Page 28: CWD Customer Service Turnaround Project - Phase 1

28

Asst. DirectorCustomer Service

Collections Manager

Billing Services Manager

Customer Care Manager

Call Center Manager

Call Center Supervisors

CSR II

CSR I

CSR III

Out Bound CollectionsSupervisor

Field Operations Supervisor

Skip TraceSupervisor

Front Desk Supervisor

Dispatch (COR)

Outbound Calls (COR)

Datamatic (COR)

CSR

1st Shift Supervisor

2nd Shift Supervisor

CFR

CFR

CSR

CSR

Mail Staff

Telephone Operators

AMR Analyst

Meter Operations

Meter Reading (Phases out w/AMR)

Meter Readers

Data Analysts

Field Technicians

Investigations

Meter Repairmen

Meter Services Manager

AMR Contract Management (Phases

out w/ AMR)

Call Center Monitors

Correspondence

Commercial Care/High Level

Complaints Unit

CAS “To Be” Organizational Chart

DirectorDPU

(Consolidated from Permits and Sales, Meter Reading, Call Center, CAS

& Collections)

Page 29: CWD Customer Service Turnaround Project - Phase 1

29

CommissionerCWD

ManagerPlant Operations

ManagerD&M

Risk/Impact Assessment

Dep. CommissionerOperations

Dep. CommissionerEngineering

Safety Programs Manager

Environmental Programs Manager

CWD “To Be” Organizational Chart

Chief of Dist. Administration

Chief of Dist.Pipe Repair

Process Management

Asst. AdminBudget and

Procurement

Building Maintenance

General Maintenance Manager

Communication Center

Capital Projects/Facilities

Management

Advance Planning and Hydraulics

Dist. Inspector

Dist. Engineer, Permits and Sales

Backflow Admin. Manager

Asst. Administrator

Baldwin

Crown

Morgan

Nottingham

Parma Control

Water Quality

Maintenance

Consulting Engineer