CWU KCOM Contract Update 14th November 2011
• Welcome and Introductions – including new faces• Contract Performance & BTMSL Scorecard• Organisation Update• Resourcing Challenges• Performance Management• Engagement
Agenda
Contract Performance
Current Month Summary
KCOMLiability £30,000.00
SL's Failed this month 1
Potential Liabilities to date £451,000
Last 3 Month Total SLA Fails 6
Last 3 month Score 2
Same 3 Month SLA Fails Last year 4
Same 3 Month Score Last year 1
Sep-11
Key Threshold Target Stretch
Score Q1 Q2 Q3 Q4 Yr Forecast
KCOM 4 2 3
SLA Performance YTD SLG Liabilities YTD
Q1 Q2 Q3 Q412 15 18 21
£15,000.00 £60,000.00
£97,000.00 £96,000.00£153,000.00 £30,000.00£451,000.00
ScorecardWeight Threshold Target Stretch
% 50% 100% 200% Q2 target Q2 actual
Full Year Forecast
Position (or actual if quarterly banked)
FY ForecastOverall
(excluding BTO Shared )
Overall(including BTO
Shared )
1) Deliver MSL Gross Managed Costs (£m)
Measure: Measured at 31/3/12 from the BTO reported financial result with adjustments agreed by BT Group finance - reported in Millions (includes leaver costs)
20.0% Target + 7.5%Budget £56.4m Target - 10% £28.5m £29.76m Threshold 10.0%
2) Profititability - Contract Revenues
Measure: Contract Revenues
10.0% Target - 7.5%Budget
£265.8mTarget + 10%
£117.673m (TRF1)
£118.985m Below Threshold 0.0%
3) Profitability - MSL EBITDA
Measure: MSL EBITDA
10.0% Target - 7.5%Budget £8.82m
Target + 10% £5.517m £4.666m Stretch 20.0%
4) Service Delivery Measure: Contractual Measure met SLA 25.0%
26 previously 93.65%
24 previously
95.14%
18 previously
98.12%
24 Previous
92.2%
33 Previous
92.2%Threshold 12.5%
5) Transformation - MSL Operating Model
Measure: Transformation milestones met 10.0%
90% Milestones met
95% milestones
met
100% milestones
met95%
Between Threshold &
Target
Between Threshold &
Target7.5%
6) Transformation - Cost Transformation Projects
Measure: Cost transformation projects
10.0%90% Milestones
met95%
milestones met
100% milestones
met
95%Below
ThresholdThreshold 5.0%
7) Customer Satisfaction
Measure: Overall MSL CSAT Score
5.0% 76.7% 78.2% 79.7% 78.2% 80.03% Target/ Stretch 7.5%
8) Delivery of improvements in MSL (Unit) People Engagement and Performance Management Practices with significant focus on
Measure:6a) People Enagement improvement measure (% improvement in EEI)
6b) Delivery of team benefits from 'Transforming
10%a) 10/11 outturn
b) 95% Achievement
a) 10/11 outturn plus
0.1b) 100%
Achievement
a) 10/11 outturn plus
0.2b) 105%
Achievement
10/11 outturn plus 0.1
Below Threshold
Threshold & Target
7.5%
70% 70%
Q2 Results FY Forecast
Measure Measure Definition
Organisation Update
Responsible for:-
•NMC•Datafill & Provisioning•Carrier Diagnostics•KCOM Broadband, IP & Datacomms Support & FE
Responsible for:-
•I-Services• BB Carrier Ops Transformation• Switch Support & FE• IP Datacomms• Transmission Support• OSS Support Services• I & M Engineering• Power Engineering
Project Update• All interface testing between KCOM and BT now signed off. This provides the
capability to move KCOM tasks on WM.• Work Manager tools configured for MSL working.• Training plan on schedule with all ASC and MDF engineers now trained.• Control teams trained.• ASC team are now working off WM.• MDF team now in pilot, with full rollout expected over the next 2 weeks.• Cable and Jointing teams start training on 29th November with pilot and rollout to
follow• KCOM I&M team to begin take up once Building a Better Business organisation
design work is complete.
Resourcing Challenges – Work Manager
Microsoft Office Excel Worksheet
– BAFO not received from preferred supplier– Final pricing against certain elements still in negotiation– Agreement on pricing anticipated w/e 25/11– Expected transfer date Feb 2012– Garage Team kept informed of slow progress
Issue – TUPE Consultation
Resourcing Challenges – Garage ITT
PERFORMANCE MANAGEMENTQ3 PLANS
Our Culture Now
• Oppositional and Perfectionistic
Our ideal culture
•Less Aggressive•Less passive•Increased focus on developing and encouraging people• Increased expectation of self improvment
PERFORMANCE MANAGEMENTQ3 PLANS
Over the next few months our focus will be on:-
What Why
Objectives Refresh To review all personal objectives to ensure they remain relevant and aligned to the overall business objectivesImprove role clarity for our people
Review of job standards To reinforce BT Approach to Performance Management it is critical that all our people understand what they need to personally do to help BT MSL deliver what our customers want.
Job standards give managers and individuals an objective structure to for performance reviews.
People need to understand how their role contributes to the overall strategy. This helps to deliver that strategy as everyone is aligned in their efforts.
PERFORMANCE MANAGEMENTQ3 PLANS
Over the next few months our focus will be on:-
What Why
2 Way Deal Exercise 1) To check understanding of the two way deal, 2) To identify how well we are doing at implementing the
two way deal 3) To identify what we can do to better implement the two
way deal 4) To involve our people in the development of a high
performance culture
Mock Levelling As a follow on from 2-way performance deal activity - to overcome a number of common misconceptions regarding levelling and performance management
ENGAGEMENTFocus over the last quarter has been on:-
• Increasing visibility of senior leaders
• Improving communications about Building a Better Business
• Introducing regular channels of communication within the KCOM contract team
• Round Table events completed with Leadership Team & BT Wholesale CDD – ongoing commitment
• Trying get underneath issues of work life balance, and what makes people proud to work at BT
ENGAGEMENT – Q2 CARE Agile Results
KCOM External Operations & Network Planning
Network Management
EEI 3.62 (3.23) EEI 3.32 (NA)
PCI 3.75 (3.50) PCI 3.56 (NA)
B &H 10% (21%) B &H 8% (NA)
Any Questions?