cycling & pedestrian network priority infrastructure for capital works | draft december 2009

Upload: north-canberra-community-council-inc

Post on 30-May-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    1/86

    Cycling & Pedestrian NetworkPriority Infrastructure for Capital Works DRAFT|

    December 2009

    Prepared for TAMS(Territory and Municipal Services)

    Represented by Roads ACT

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    2/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 2

    Sydney

    Level 3, Cardno Building

    910 Pacific Highway

    Gordon NSW 2072

    Tel: (02) 9496 7700

    Fax: (02) 9499 3902

    Brisbane

    Green Square

    Level 11, North Tower

    515 St Paul's Terrace

    Locked Bag 4006

    Fortitude Valley QLD 4006

    Tel: (07) 3310 2401

    Fax: (07) 3369 9722

    Wollongong

    278 Keira Street

    Wollongong NSW 2500

    Tel: 1300 369 093

    Gold Coast

    Level 2, Emerald Lakes Town Centre

    1/3321 Central Place

    Carrara QLD 4211

    PO Box 391 Nerang QLD 4211

    Tel: (07) 5502 1585

    Fax: (07) 5502 1586

    DOCUMENT CONTROL

    Version DateAuthor Reviewer

    Name Initials Name Initials

    DraftDecember

    2009

    Andrew McGill

    Sam Laybutt

    Jerryn Zwart

    Russell Yell

    Jerryn Zwart

    " 2009 Cardno All Rights Reserved. Copyright in the whole and every part of this document belongs to Cardno

    and may not be used, sold, transferred, copied or reproduced in whole or in part in any manner or form or in or on

    any media to any person without the prior written consent of Cardno.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    3/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 3

    TABLE OF CONTENTS

    1 Introduction 11.1 Background 11.2 Scope 21.3 Consultation 3

    2 Town Centre Networks 52.1 Civic 52.2 Belconnen 72.3 Woden 82.4 Gungahlin 92.5 Tuggeranong 10

    3 Trunk Network 123.1 Overall Plan 133.2 Employment Centre Infrastructure 13

    3.2.1 Canberra Airport/Business Park 133.2.2 Hume 143.2.3 Barton/Parkes 143.2.4 Fyshwick 153.2.5 Mitchell 153.2.6 Molonglo 15

    3.3 Review of Standards (DS13) 164 Accessible Streets 18

    4.1

    Civic 20

    4.2 Belconnen 214.3 Woden 224.4 Gungahlin 224.5 Tuggeranong 234.6 Fyshwick 23

    5 Seven Year Works Program 255.1 Methodology 25

    5.1.1 Background 255.1.2 Multi-criteria Analysis 255.1.3 Criteria Weighting 30

    5.2 Priorities 315.3 Works Program 31

    6 Recommendations 336.1 Other Issues 33

    List of Tables

    3.1 Recommended Changes to DS13

    5.1 Multi Criteria Analysis Criteria

    5.2 MCA Scoring System

    5.3 Criteria Weighting

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    4/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 4

    List of Figures

    2.1 Civic Town Centre Pedestrian and Cycling Accessibility Issues

    2.2 Civic Proposed Pedestrian and Cycle Facilities

    2.3 Belconnen Town Centre Pedestrian and Cycle Accessibility Issues

    2.4 Belconnen Proposed Pedestrian and Cycle Facilities

    2.5 Woden Town Centre Pedestrian and Cycle Access Issues

    2.6 Woden Proposed Pedestrian and Cycle Facilities

    2.7 Gungahlin Town Centre Pedestrian and Cycle Accessibility Issues

    2.8 Gungahlin Proposed Pedestrian and Cycle Facilities

    2.9 Tuggeranong Pedestrian and Cycle Accessibility Issues

    2.10 Tuggeranong Proposed Pedestrian and Cycle Facilities

    3.1 Existing and Proposed Trunk Network

    3.2 Canberra Airport Employment zone Cycle Network Connections

    3.3 Canberra Airport and Business Park Existing and Proposed Pedestrian and Cycle Facilities

    3.4 Hume Employment Zone Cycle Network Connections

    3.5 Hume Existing and Proposed Pedestrian and Cycle Facilities

    3.6 Barton/Parkes Town Centre Pedestrian and Cycle Accessibility Issues

    3.7 Barton/Parkes Existing and Proposed Pedestrian and Cycle Facilities

    3.8 Fyshwick Employment Zone Cycle Network Connections

    3.9 Fyshwick Existing and Proposed Pedestrian and Cycle Facilities

    3.10 Mitchell Employment Zone Cycle Network Connections

    3.11 Mitchell Existing and Proposed Pedestrian and Cycle Facilities

    3.12 Molonglo Existing and Proposed Pedestrian and Cycle Facilities5.1 Top 50 Priority Routes

    List of Photographs

    1 Current Facilities in Civic

    2 Shared Space and Copenhagen Bike Lane Example

    3 Existing Facilities in Belconnen

    4 Existing Facilities in Woden

    5 Existing Facilities in Gungahlin

    6 Existing Facilities in Tuggeranong

    7 The Range of Facilities in Canberra

    Appendices

    Appendix A Stakeholder Consultation ResultsAppendix B Works ProgramAppendix C Public Consultation Results

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    5/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 1

    1 INTRODUCTIONAs part of the response to the ACT Governments development and release of the ACT Sustainable Transport

    Plan in 2004, Roads ACT, working with the ACT Planning Authority (ACTPLA) and the key ACT cycling advocacy

    group Pedal Power, undertook a master plan to examine and plan the next 10 years of pedestrian and cyclist

    infrastructure provision. It was anticipated that this plan would undergo biennial updates to account for

    completion of some projects and identification of others. This report forms the outcome of the 2009 review of the

    10 Year pedestrian and cycle infrastructure plan. This review will also coordinate with the current preparation of

    the Sustainable Transport Action Plan 2010-2016, which will incorporate a walking and cycling strategy.

    Underpinning this study is the 2004 Sustainable Transport Plan for the ACT, which aims to have a 14% mode

    share for walking and cycling in the ACT by 2026.

    The aim of this study is to update the infrastructure plan with new projects, particularly within Canberras town

    centres and employment zones. The network plans were then utilised to produce a seven years works program,

    which will be determined based on a prioritisation process applied to each project.

    The following sections of the report outline the process undertaken in the development of the works program,

    including the review of the 2007 Commuter Cycling Network Priorities for Capital Works report, the

    identification of new links and gaps in the network and the assessment and ranking of the proposed projects.

    1.1 BackgroundThe following reports provided a background to the project team in developing the projects and reviewing the 10

    year plan:

    Sustainable Transport Plan for the ACT (TAMS, 2004); Commuter Cycling Network Priorities for Capital Works (CBRE, July 2007); Integrated Transport Framework (ACT Government, 2008); TAMS Design Standard 13 Pedestrian and Cyclist Facilities (TAMS, 2007); Ten Year Master plan for Trunk Cycling and Walking Path Infrastructure 2004-2014 Final Report (McCann

    Property and Planning/R.D. Gossip Pty Ltd, 2004);

    Civic Accessibility Study Volume 3 Access Guidelines (Eric Martin and Associates, 2004); Gungahlin Bicycle Network Plan (ACTPLA, 2008); Gungahlin Town Centre Study (ACTPLA, 2009 ); Road Safety Improvements for Gungahlin (ACT Government Media Release, 2009); Design Concept Report for Belconnen Town Centre Public Transport Improvements and Transit Oriented

    Development (ACTPLA, 2008);

    Canberra Central Movement Study (Intelligent Space Partnership Ltd, 2006); ACT Strategic Public Transport Network Plan and Service Design (McCormack Rankin Cagney, 2009).

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    6/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 2

    1.2 ScopeThe following tasks were undertaken as part of the review and development of the works program:

    a review of the 2007 Commuter Cycling Network Priorities for Capital Works report; a review and documentation of the detailed requirements for pedestrian and cycle networks in the five

    town centres:

    Civic; Woden; Belconnen; Gungahlin; Tuggeranong;

    the development of an accessible pedestrian network for visually and mobility impaired persons in the fivetown centres;

    a review and documentation of the detailed requirements for cycle networks to the major employmentnodes:

    Fyshwick; Hume; Mitchell; Barton/Parkes; Canberra Airport (Brindabella and Majura Park business precincts);

    a stakeholder and public consultation process to present the results of the analysis and to receivefeedback and input;

    updating the standard drawing DS13-13 from Standard Design 13 to incorporate the outcomes of thestudy process and provision for new standard drawings as appropriate to document the master plans

    intent for each of the major town centres and employment areas;

    reporting of the process and outcomes (this report).

    The 2007 Commuter Cycling Network Priorities for Capital Works report formed a key component of the review

    process. Since the report was completed, 16 of the top ranked 21 projects identified in the report as priority

    works have been constructed or have had funding secured for investigation or construction. The following

    projects, together with their ranking, are among those which are progressing to construction or have been

    constructed:

    1 Bowen Drive Crossing; 2 Launceston Street; 3 Northbourne Terrace North of Mouat; 4 Cotter Road 1; 5 Jerrabomberra Wetlands; 6 Kingston Foreshore Link; 8 Airport Shared Path; 9 Cotter Road 2; 10 State Circle; 11 David Street Crossing; 13 Causeway Connection;

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    7/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 3

    14 De Burgh Street Crossing; 15 Cotter Road 3; 17 Ginninderra Drive 2; 18 Mouat Street; 21 Ginninderra Drive 1.

    In addition, other lower ranked projects have been completed, including:

    Fairbairn Avenue on road, ANZAC Parade to Northcott Drive; Launcestion Street on road at Woden; Lanyon Drive on road from Monaro Highway to Shepherd Street; Morshead Drive on road from Dairy Road to Monaro Highway; Pialligo Avenue on road form Monaro Highway to Airport.

    The focus of the 2007 Commuter Cycling Network Priorities for Capital Works report was on the trunk network

    connections, forming the overall network. Projects within town centres formed a minor component of the overall

    network. As part of the 2009 review, the priority is to develop town centre networks, ensuring that accessible

    networks for both pedestrians and all types of cyclists within the town centres are created as well as

    connections to the trunk network sections surrounding the town centres. The trunk network connections will also

    be updated to include the developing employment zones and new development areas. A further focus for the

    study is to consider other projects which would further the recreational network needs of the people of Canberra.

    1.3 ConsultationAn important component for this project and the review and development of the network was the input andfeedback from the community and key stakeholders. Key elements of the consultation undertaken for this project

    involved:

    Initial meetings with the Bicycle Advisory Group (BAG), comprising representatives from Government,NRMA, Motor Cyclist Riders Association, Pedestrian Forum and Pedal Power;

    Issues Workshops were held at the Civic Griffin Centre and the Gungahlin Community Centre withmembers of the community councils, BAG and other stakeholders, including members of ACTPLA and

    TAMS;

    One on one meetings were also held with key stakeholders including Pedal Power, Geoff Farrar, a CivilScope and Pedal Power member, Rod Baxter and James Cox from ACTPLA;

    An invitation to the Community Councils to discuss issues was made. 4 Councils (North Canberra,Tuggeranong, Gungahlin and Belconnen Community Councils) accepted the invitation where meetings

    were held to brief the councils on the process being undertaken and provide the opportunity to provide

    feedback and input into the network plans;

    A community consultation process was undertaken between 13 November and 4 December 2009. Theconsultation process was advertised in the Canberra Times, as well as online and on community

    noticeboards. The process included the provision of the proposed draft network plans for each town

    centre on the TAMS website, as well as three public display locations at:

    Tuggeranong Hyperdome; Westfield Woden; Westfield Belconnen.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    8/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 4

    These displays were staffed for a couple of hours each day on 9 and 10 November and feedback formswere available from the website and at the public displays for public comment. From the consultation

    process, a total of 66 feedback forms were received by the project team.

    Appendix A contains a summary of the stakeholder consultation outcomes, while the public consultationfeedback received are summarised at Appendix C.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    9/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 5

    2 TOWN CENTRE NETWORKSIn order to assess the required infrastructure requirements for pedestrian and cyclist facilities in each of the town

    centres, a site visit was undertaken. During these visits key issues were identified. These issues included such

    aspects as:

    footpath quality; connectivity; crossings convenience and safety aspects; personal safety; accessibility considerations; land use and desire line observations.

    In addition, existing facilities were identified, including public transport facilities, attractors and generators,bicycle parking and shaded areas. It is important to note that the site visits were not a full safety and

    accessibility audit of the existing facilities. Consideration was also given during the on-site assessment of the

    needs of various user types, including considering the quality of the facilities from the point of view of those with

    mobility impairments.

    The site visits assisted with the development of future networks. In addition, for each town centre, a detailed

    review of existing and future land uses, public transport connections, users, other planning studies, and

    consideration of ability of the transport corridors to include walking and cycling facilities underpinned the

    assessment and planning of the future networks. As previously discussed these proposed networks were also

    submitted for consideration and consultation by the internal stakeholders and the general public.

    Resulting from the above process was the development of strong, accessible and legible internal pedestrian and

    cycle networks, linking key attractors and generators throughout each of the town centres and connections to the

    surrounds. The following sections document the key outcomes for each town centre.

    2.1 CivicThe network plan responded to issues identified through the site visits and desire line analysis for Civic. Figure

    2.1 summarises the issues identified. The key observations included:

    generally good quality footpaths throughout the centre, however some areas lack tactile paving oncrossings;

    a lack of connectivity in all directions through the centre of Civic, within London Circuit specifically; well spaced bicycle parking facilities in use, particularly in the eastern precinct; no footpaths along Vernon Circle; significant areas utilised for at-grade car parking facilities, resulting in potential personal safety issues in

    some locations, given lack of activity and surveillance. It is noted that there are plans for many of these

    areas to be redeveloped;

    generally comprehensive existing cycling and pedestrian facilities on most streets within the core; a need to develop facilities to assist and foresee the intensification of activity in the centre of Civic.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    10/86

    6

    6

    5

    2 3

    47

    1

    1

    3

    6

    5

    4

    7

    Poor sight distance to Commonwealth Bridge

    potential for car-cyclist conflict

    Pedestrians have long wait times around

    Northbourne Avenue and London Circuit

    Shared zone at the top of the mall is unsigned and

    has unnecessary linemarkings

    Sections of Bunda Street have the potential for

    shared space form, given the high pedestrian

    volumes, active frontages, low traffic volumes and

    slow speed environment for further investigation

    Vernon Circle lacks easy pedestrian throughmovement opportunities and involves mixing with

    high speed vehicle traffic

    Car parking areas make t hrough movement difficult

    and unattractive

    Alinga Street bus interchange lacks wayfinding

    signage from nearby destinations

    2

    Legend

    Existing

    Bus interchange

    Areas with good shade cover

    Areas with high pedestrian volumes observed

    Bike parking observed

    Study area boundary

    Issues

    Uneven footpath

    Footpath does not meet observed demand

    Footpath with clutter

    No footpath

    Frequent driveway intrusion on footpath

    Potential personal safety issues

    No disabled access

    Tactile paving incorrect or non existent

    Poor crossing

    Poor connection/crossing (incl. through car park)

    Poor lighting

    *Note: This plan includes a preliminary assessment of

    walking and cycling related issues. A full audit of all

    facilities has not been undertaken.

    05 | 11 |2009

    C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 2.1_Civic PAI.ck.cdr

    Figure 2.1 | Job Number: CES01143

    Civic Town Centre - Pedestrian & Cycling Accessibility Issues

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    11/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 6

    Photograph 1 Current Facilities in Civic

    Some key recommendations emerged from the investigations, including:

    an area of shared space (i.e. equal priority to all users) for investigation along Bunda Street, to enable abetter utilisation of the space by pedestrians and cyclists, as the relative volumes of various user modes

    appeared to support this concept. This investigation should consider service vehicle requirements and

    volumes for all transport modes;

    an area for investigation with the potential for the provision of protected bicycle lanes (also known as

    Copenhagen bicycle lanes) along Marcus Clarke Street, Alinga Street and Parkes Way.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    12/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 7

    Photograph 2 Shared Space and Copenhagen Bike Lane Example

    Figure 2.2 contains the proposed walking and cycling facilities recommended as a result of the investigations and

    analysis undertaken. These also reflect results of the public consultation on these draft plans. These facilities

    were assessed and prioritised for inclusion in the works program.

    2.2 BelconnenA number of issues were identified for Belconnen. Figure 2.3 summarises the issues identified. The key

    observations were:

    poor connections from the Westfield Shopping Centre west to the industrial area between Lathlain Street

    and Josephson Street; uneven footpaths on many roads and footpaths which are not wide enough to accommodate their

    relatively high pedestrian volumes, including Benjamin Way;

    cycling facilities in existence along the major roads surrounding the town centre, providing goodcommuter and longer distance trip connections;

    gaps between the external connections as well as the connections within the town centre itself; consideration required of the forthcoming changes to pedestrian and cycle movement due to the Cohen

    Street extension;

    areas of poor connections from surrounding residential communities, through service/light industryprecinct to town centre, particularly to the west and south;

    possible need to consider a 40km/h speed limit for Lathlain Street while the area remains a major publictransport node;

    improvements required to east-west connections to support the recent changes to the public transportsystems which have resulted in the Belconnen bus interchange demolished and interim facilities installed,

    on Lathlain Street and Cameron Avenue;

    Benjamin Way has the potential to develop as a major pedestrian and cycle connection through the towncentre, with significant median space available for improved facilities.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    13/86

    West

    Basin

    Central

    Basin

    West

    Lake

    Lond

    onCct

    Corande

    rrkSt

    Ainslie

    Av

    Anz

    acPde

    ParkesWay

    CommonwealthA

    v

    Edinburg

    hAv

    Akuna

    St

    Nort

    hb

    ourne

    Av

    ConstitutionAv

    Limestone

    Av

    Girrahw

    eenSt

    MassonSt

    BallumbirSt

    CooyongSt

    lcCno

    nre

    V

    ParkesWay

    Mort

    St

    Forbes

    St

    Doonkuna

    St

    CurrongSt

    FlynnD

    r

    ParkesPl

    WendoureeDr

    KingEdwardTceAlexandrinaDr

    LawsonC

    r

    Clunies

    RossSt

    Daley

    Rd

    North

    Rd

    McCau

    gh

    eyS

    t

    Mar

    cusClar

    keSt

    Allar

    aSt

    UniversityAv

    AlingaSt

    CityWalk

    RuddSt

    BundaSt

    Lonsdale

    StWatson

    St

    Torrens

    StDon

    aldsonS

    t

    BoldrewoodSt

    BarryDr

    Macle

    ayS

    t

    Henty

    St

    Torrens

    St

    BRADDON

    CIVICTOWN CENTRE

    REID

    PARKES

    ACTON

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 2.2_Civic.cdr

    Figure 2.2 | Job Number: CES01143

    Civic - Proposed Pedestrian and Cycle Facilities

    LEGEND

    Existing off-road pedestrian and cycle facility

    Proposed off-road pedestrian and cycle facility

    Existing on-road cycle facility

    Proposed on-road cycle facility

    Proposed shared space

    Recreational areas

    Waterways

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    14/86

    3

    2

    1

    4

    1

    2

    3

    Lack of active frontages in some places sight line

    axis is disrupted by Chandler Street underpass and

    unnecessary detour on slope towards waterfront

    Benjamin Way is too wide and car oriented. It

    requires active frontages and more pedestrian

    crossing facilities

    The bus stops on Lathlain Street have inadequate

    shelter for the patron demand. Temporary measures

    for shelter should be considered

    Site of future bus interchange

    Legend

    Existing

    Bus interchange

    Areas with good shade cover

    Areas with high pedestrian volumes observed

    Bike parking observed

    Study area boundary

    Issues

    Uneven footpath

    Footpath does not meet observed demand

    Footpath with clutter

    No footpath

    Frequent driveway intrusion on footpath

    Potential personal safety issues

    No disabled access

    Tactile paving incorrect or non existent

    Poor crossing

    Poor connection/crossing (incl. through car park)

    Poor lighting

    *Note: This plan includes a preliminary assessment of

    walking and cycling related issues. A full audit of all

    facilities has not been undertaken.

    4

    05 | 11 |2009

    C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 2.3_Belconnen PAI.ck.cdr

    Figure 2.3 | Job Number: CES01143

    Belconnen Town Centre - Pedestrian & Cycle Accessibility Issues

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    15/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 8

    Photograph 3 Existing Facilities in Belconnen

    Some key recommendations emerged from the investigations, including:

    increased connections to be provided from the surrounding residential areas, particularly to the south andwest;

    improved east-west connections to be provided, between and within the industry and retail precincts; Benjamin Way as a potential major pedestrian and cycle connection through the town centre, with

    significant median space available for improved facilities.

    Figure 2.4 contains the proposed facilities to emerge from the investigations. These facilities were assessed and

    prioritised for potential inclusion in the works program.

    2.3 WodenA number of issues were identified for Woden. Figure 2.5 summarises the issues identified. The key

    observations identified were:

    many walking and cycling connections exist to/from the surrounding areas; improvements required on the internal connections to improve accessibility within the town centre itself

    as well as higher quality, more frequent connections from surrounding residential areas to town centre;

    walking and cycling links needed to service the industry precinct to the south and Canberra Hospital to theeast;

    some uneven footpaths and footpaths with widths that do not meet existing demands were identified,particularly along major roads, including Hindmarsh Drive as well as throughout the industry precinct to

    the south;

    intimidating road crossings for pedestrians along Hindmarsh Drive; identified gaps in footpath provision along desire lines. This includes areas with ongoing construction

    where alternatives where not provided;

    some potential personal safety issues were present, including in the vicinity of Callam Street where thereis a lack of surveillance and activity;

    poor connections from nearby residential areas to the east and west, particularly to the east, whereresidential areas are separated from the town centre by undeveloped land parcels.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    16/86

    Ginninderra

    Dr

    Emu Bank

    Aik

    monD

    r

    SouthernCrossDr

    LuxtonS

    t

    Cou

    lter

    Dr

    Joy

    ntonS

    mithDr

    College St

    BelconnenWay

    EasternValley

    Way

    Cou

    lterDr

    RedfernSt

    BenjaminWa

    y

    Lake Ginninderra

    BELCONNENTOWN CENTRE

    MACQUARIE

    PAGE

    BELCONNEN

    FLOREY

    COOK

    ARANDA

    William

    SlimD

    r

    Nettle

    fold

    St

    ChanSt

    CohenSt

    Bind

    ubiSt

    BenjaminWay

    Ch an d ler St

    Beisse

    lSt

    CatchpoleSt

    BindelSt

    BandjalongCr

    JohnClela

    ndCr

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 2.4_Belconnen.cdr

    Figure 2.4 | Job Number: CES01143

    Belconnen - Proposed Pedestrian and Cycle Facilities

    LEGEND

    Existing off-road pedestrian and cycle facility

    Proposed off-road pedestrian and cycle facility

    Existing on-road cycle facility

    Proposed on-road cycle facility

    Proposed shared space

    Recreational areas

    Waterways

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    17/8605 | 11 |2009

    C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 2.5_Woden PAI.ck.cdr

    Figure 2.5 | Job Number: CES01143

    Woden Town Centre - Pedestrian Access Issues& Cycle

    1

    3

    2

    5

    4

    7

    6

    1

    2

    3

    5

    Lack of permeability through town centre precinct.

    Limited signage and poor visual cues for those

    unfamiliar with the area

    Inaccurate signage within Westfield regarding

    location of bus interchange and no signage into

    Westfield from bus interchange

    Woden Town Park has poor amenity and displays

    evidence of vandalism and poor maintenance as

    well as poor casual surveillance due to lack of

    surrounding land uses

    Hindmarsh Drive provides a major barrier between

    the retail and business precinct and the southern

    commercial/light industry precinct, with eight

    traffic lanes, few crossing points and long delays

    for pedestrians wishing to cross

    The residential area east of the town centre lacks

    connections to the town centre

    Callam Street pedestrian path is closed on the

    eastern verge for construction, however there is

    evidence of significant pedestrian demand

    The bus interchange has poor amenity and layout

    4

    Legend

    Existing

    Bus interchange

    Areas with good shade cover

    Areas with high pedestrian volumes observed

    Bike parking observed

    Study area boundary

    Issues

    Uneven footpath

    Footpath does not meet observed demand

    Footpath with clutter

    No footpath

    Frequent driveway intrusion on footpath

    Potential personal safety issues

    No disabled access

    Tactile paving incorrect or non existent

    Poor crossing

    Poor connection/crossing (incl. through car park)

    Poor lighting

    *Note: This plan includes a preliminary assessment of

    walking and cycling related issues. A full audit of all

    facilities has not been undertaken.

    6

    7

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    18/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 9

    Photograph 4 Existing Facilities in Woden

    Some key recommendations emerged from the investigations, including:

    increased connections from the surrounding residential areas to the town centre to be provided,particularly from the east;

    improved connections to nearby destinations to be provided, such as the Canberra Hospital; improved connections through the southern industry precinct required.

    Figure 2.6 contains the proposed facilities to emerge from the investigations. These facilities were assessed and

    prioritised for potential inclusion in the works program.

    2.4 GungahlinA number of issues were identified for Gungahlin. Figure 2.7 summarises the issues identified. The key

    observations identified were:

    the area is a developing community with many existing walking and cycling facilities; the existing facilities need to be linked cohesively to allow for greater mobility; connections to the residential areas surrounding the town centre are also required; some potential personal safety issues were present in some areas due to many sites not currently being

    developed. In particular some areas lack casual surveillance, including along Ernest Cavanagh Street and

    Gribble Street. However these are all proposed to be developed and as such these issues should be

    resolved in time;

    bicycle parking exists along Hibberson Street, in prominent and visible locations; variation in level of activity in retail frontages, requiring careful consideration when determining possible

    pedestrian/cyclist treatments;

    some poor crossing facilities exist between the town centres and the surrounding residential areas to thenorth;

    the central open space plaza is currently underutilised space which would benefit from an intensificationof activity.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    19/86

    Melro

    seDr

    YambaDr

    LauncestonSt

    Hindmarsh Dr

    Egglesto

    nCr

    Yarra

    Gle n

    CarruthersSt

    Athllo

    nDr

    WODENTOWN CENTRE

    PHILLIP

    CHIFLEY

    OMALLEY

    GARRAN

    HUGHES

    LYONS

    Cal l a

    mSt

    Melro

    seDv

    W

    isdom

    St

    GilmoreCr

    RobsonSt

    K

    entS

    t

    Bradle

    ySt

    TownshendSt

    Parram

    attaSt

    AinsworthSt

    Beasley

    St

    TuggeranongP

    ky

    Alan

    St

    Daven

    portSt

    Groom St

    Irvin

    gSt

    Easty

    St

    ChappellSt

    PlunkettSt

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 2.6_Woden.cdr

    Figure 2.6 | Job Number: CES01143

    Woden - Proposed Pedestrian and Cycle Facilities

    LEGEND

    Existing off-road pedestrian and cycle facility

    Proposed off-road pedestrian and cycle facility

    Existing on-road cycle facility

    Proposed on-road cycle facility

    Proposed shared space

    Recreational areas

    Waterways

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    20/86

    4

    3

    3

    41

    1

    4

    4

    4

    4

    4

    5

    2

    4

    Underused space

    Shared zone opportunity for investigation

    Bus stops located outside developed area

    Lack of activity results in reduced personal safety.

    Once these areas develop some of these issues

    may be resolved

    Disabled spaces well placed near bus interchange

    * Note overall lack of signage

    lighting good in developed areas

    1

    2

    3

    4

    5

    Legend

    Existing

    Bus interchange

    Areas with good shade cover

    Areas with high pedestrian volumes observed

    Bike parking observed

    Study area boundary

    Issues

    Uneven footpath

    Footpath does not meet observed demand

    Footpath with clutter

    No footpath

    Frequent driveway intrusion on footpath

    Potential personal safety issues

    No disabled access

    Tactile paving incorrect or non existent

    Poor crossing

    Poor connection/crossing (incl. through car park)

    Poor lighting

    *Note: This plan includes a preliminary assessment of

    walking and cycling related issues. A full audit of all

    facilities has not been undertaken.

    05 | 11 |2009

    C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 2.7_Gungahlin PAI.ck.cdr

    Figure 2.7 | Job Number: CES01143

    Gungahlin Town Centre - Pedestrian & Cycle Accessibility Issues

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    21/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 10

    Photograph 5 Existing Facilities in Gungahlin

    Some key recommendations emerged from the investigations, including:

    an area along Hibberson Street was identified which could undergo investigation for conversion into ashared space form (i.e. equal priority to all users);

    increased connections for the surrounding residential areas required, particularly to the north-west andsouth;

    new connections to fill gaps within the town centre area should be provided.

    Figure 2.8 contains the proposed facilities to emerge from the investigations. These facilities were assessed and

    prioritised for potential inclusion in the works program.

    2.5 TuggeranongA number of issues were identified for Tuggeranong. Figure 2.9 summarises the issues identified. The key issues

    identified were:

    Tuggeranong is a newer town centre with extensive pedestrian and cyclist facilities; there are some missing links in the footpath network that were not provided during development of the

    town centre and where demand is evident;

    some streets are difficult to cross due to a combination of road reserve width and limited pedestriancrossing facilities;

    connectivity between the bus interchange and the northern area of the town centre is poor; cycle lanes along Anketell Street could create a cycling spine through the town centre; and connections from the town centre to surrounding suburbs are limited due to barriers such as the lake, and

    major roads such Soward Way and Athllon Drive (south) routes.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    22/86

    Yerrabi Pond

    MirrabeiDr

    GundarooDr

    Horse

    Park

    Dr

    Gund

    arooR

    d

    FrancisF

    ordeBvd

    FlemingtonRd

    AnthonyRolfeAv

    HibbersonSt

    TheValleyAv

    KateC

    raceS

    t

    GungahlinDr

    Kosciuszk

    oAv

    Gundar

    ooDr

    DelmaWay

    MapletonAv

    Oodge

    rooAv

    Nudu

    rrDr

    AMAROO

    FORDE

    GUNGAHLIN

    PALMERSTON

    HARRISON

    SwainSt

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 2.8_Gungahlin.cdr

    Figure 2.8 | Job Number: CES01143

    Gungahlin - Proposed Pedestrian and Cycle Facilities

    LEGEND

    Existing off-road pedestrian and cycle facility

    Proposed off-road pedestrian and cycle facility

    Existing on-road cycle facility

    Proposed on-road cycle facility

    Proposed shared space

    Recreational areas

    Waterways

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    23/86

    Legend

    Existing

    Bus interchange

    Areas with good shade cover

    Areas with high pedestrian volumes observed

    Bike parking observed

    Study area boundary

    Issues

    Uneven footpath

    Footpath does not meet observed demand

    Footpath with clutter

    No footpath

    Frequent driveway intrusion on footpath

    Potential personal safety issues

    No disabled access

    Tactile paving incorrect or non existent

    Poor crossing

    Poor connection/crossing (incl. through car park)

    Poor lighting

    *Note: This plan includes a preliminary assessment of

    walking and cycling related issues. A full audit of all

    facilities has not been undertaken.

    1

    1 Pram ramps point into centre of road

    05 | 11 |2009

    C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 2.9_Tuggeranong PAI.ck.cdr

    Figure 2.9 | Job Number: CES01143

    Tuggeranong Town Centre - Pedestrian & Cycle Accessibility Issues

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    24/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 11

    Photograph 6 Existing Facilities in Tuggeranong

    Some key recommendations emerged from the investigations, including:

    missing footpaths should be provided, particularly in the southern part of the town centre; a cycle spine along Anketell Street would bring cyclists to within a block of their destination; difficult road crossings should be improved by the provision of pedestrian crossing facilities to allow safe

    crossing manoeuvres;

    pedestrian and cyclist approach routes from Erindale Drive and Isabella Drive should be improved.

    Figure 2.10 contains the proposed facilities to emerge from the investigations. These facilities were assessed

    and prioritised for potential inclusion in the works program.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    25/86

    Athllon

    Dr

    OXLEY

    MONASH

    TUGGERANONG

    WANNIASSA

    ISABELLA PLAINS

    BONYTHON

    Lake Tuggeranong

    Isabella Pond

    SowardWay

    Erindal

    eDv

    TavernerSt

    IsabellaDv

    Drak

    efo

    rdD

    v

    Athllon

    Dr

    OHall

    oranC

    ct

    AnketellSt

    WheelerCr

    TharwaDr

    John

    sonDr

    Keverstone

    Cct

    Cowishaw

    St

    Bartl

    etPl

    JoselandSt

    ScollaySt

    ReedSt

    Sth

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 2.10_Tuggeranong.cdr

    Figure 2.10 | Job Number: CES01143

    Tuggeranong - Proposed Pedestrian and Cycle Facilities

    LEGEND

    Existing off-road pedestrian and cycle facility

    Proposed off-road pedestrian and cycle facility

    Existing on-road cycle facility

    Proposed on-road cycle facility

    Proposed shared space

    Recreational areas

    Waterways

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    26/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 12

    3 TRUNK NETWORKThis development of the trunk network was divided into three key aspects:

    review of the 2007 Trunk Network and identification of missing commuter links; addition of major recreational links; development of proposed links into individual projects.

    These tasks were addressed via a desktop reviews of the 2007 Commuter Cycling Network Priorities for Capital

    Works report, aerial photographs and site visits to assist in defining the missing links and scoping individual

    projects. The review focused on providing additional cross-regional links (e.g. Belconnen to Mitchell, Long Gully

    Road/Mugga Lane), links with the Queanbeyan cycle network (e.g. Lanyon Drive, Pialligo Avenue) and serving

    suburbs which were not connected to the trunk network. The developing public transport interchanges at Erindale

    and Kippax were also identified as nodes in need of improved connectivity. The review identified additional linkswere required in some areas, particularly in parts of Tuggeranong, Weston Creek and western Belconnen. It is

    noted that the review did not include a full safety and accessibility audit of all facilities in the network.

    In addition to the commuter network, recreational links were given greater consideration through the provision of

    off-road facilities as an alternative to the on-road facilities preferred by commuters. Routes that facilitated loop

    rides, such as Majura Road, Cotter Road and Long Gully Road were also included.

    Discussions with Pedal Power and other stakeholders indicated that whilst many corridors were substantially

    complete, there were still significant barriers to cycling such as multi-lane roundabouts, short missing lengths of

    cycle lane or difficult road crossings that discouraged cyclists. Site visits and aerial photographs were used toidentify pinch points or missing links and these have been incorporated into adjacent projects or included as

    standalone projects. It is noted that the review did not include a full safety and accessibility audit of all facilities

    in the network, and hence all issues may not be identified.

    An examination of pedestrian and cyclist access to the following employment centres was also undertaken via a

    review of aerial photographs and site visits:

    Mitchell; Canberra Airport (including the adjacent business parks); Fyshwick; and Hume.

    The improvements proposed for these employment centres were generally located on approach routes to the

    centre. The employment centre of Barton/Parkes were also reviewed for the connections to/from the trunk

    network as well as the internal connections to key destinations in the area. Barton/Parkes underwent a review

    similar to that undertaken in the town centres due to its unique characteristics and significance.

    The following details the trunk network projects identified for Canberra as a whole, as well as those specific

    facilities which are proposed for each of the Employment Zones.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    27/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 13

    3.1 Overall PlanThe ACT government has constructed a vast proportion of the pedestrian and cycle trunk network, consisting of

    both on and off-road facilities. This has included proactive schemes, such as providing cycle lanes as part of re-

    sealing programmes and providing both on and off-road facilities as part of major capital works. As a result,

    Canberra has a significant network of pedestrian and cycling facilities. There are however, improvements which

    could be made to reduce significant barriers to cycling or walking along these corridors which reduce potential

    usage of the facilities. The major focus of the review was to identify these missing links, as well as expand the

    coverage of the trunk network.

    Some key corridors which were identified as having missing links include:

    Lake Burley Griffin Loop; Athllon Drive;

    City to Belconnen; and Woden to Fyshwick.

    Some key additions to expand the coverage of the Trunk Network include:

    Long Gully Road/Mugga Lane; Tharwa Drive; Pialligo Avenue; and Majura Road.

    All the proposed trunk network facilities are contained on Figure 3.1.

    3.2 Employment Centre InfrastructureThe following are the proposed projects intended to provide greater accessibility to/from the key employment

    zones within Canberra. They have been included as part of the Trunk Network.

    3.2.1 Canberra Airport/Business ParkCanberra Airport and the adjacent business parks have suffered from being poorly linked to the rest of Canberra.

    The analysis of issues is contained in Figure 3.2. The recent completion of the City to Airport shared path to

    Fairbairn Avenue has improved the situation, however there are still a number of desirable improvements,including:

    Majura Road cycle lanes; Fairbairn Avenue cycle lanes; Morshead Drive cycle lanes from Russell to Airport; Pialligo Avenue cycle lanes; and a more direct link across the Molonglo River to Fyshwick and Narrabundah.

    The proposed facility improvements are contained in Figure 3.3.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    28/86

    Athlon

    Dr

    DrakefordDv

    JohnsonDv

    Isabe

    llaDr

    MonaroH

    wy

    MuggaLa

    Tu g

    g eranong Pky CotterRd

    AdelaideA

    v

    Hindmar

    shDr

    CanberraAv

    PialligoAv

    MorsheadDr

    CommonwealthAv

    Nor thbou

    r neAv

    BelconnenWy

    Gung

    ahlin

    Dr

    G u n g a

    h l i

    n D

    r

    M a

    j u r a

    R d

    FederalHw

    y

    ParkesWy

    WilliamHovellDr

    GinninderraDr

    King

    sfordSm

    ithDr

    BartonHwy

    Gund

    arooD

    r

    HorsePark

    Dr

    GUNGAHLIN

    FORDE

    BONNER

    AMAROO

    NGUNNAWAL

    NICHOLLS

    PALMERSTON

    FRANKLIN

    KENNYMITCHELL

    WATSON

    DOWNER

    AINSLIE

    HACKETT

    BRADDONCANBERRA

    TURNER

    OCONNOR

    LYNEHAM

    KALEEN

    GIRALANG

    LAWSON

    CM KELLAR

    EVATT

    FRASER

    FLYNN

    CHARNWOOD

    DUNLOP

    MACGREGOR

    LATHAM

    HOLT

    HIGGINSSCULLIN

    PAGE

    HAWKERWEETANGERA

    COOKARANDA

    BRUCE

    ACTON

    PARKESRUSSELL

    CAMPBELL

    MAJURA

    PIALLIGOFYSHWICKINGSTON

    CAPITAL HILL

    FORREST

    GRIFFITH

    DEAKIN

    YARRALUMLA

    CURTIN

    DUFFY

    RIVETT

    STIRLING

    CHAPMANFISHER

    CHIFLEY

    LYONS

    PEARCE

    TORRENS

    MAWSON

    OMALLEY

    ISAACS

    FARRER

    SYMONSTON

    QUEANBEYAN

    HUME

    MACARTHURFADDEN

    WANNIASSA

    OXLEY

    MONASH

    GOWRIE

    CHISHOLM

    RICHARDSONISABELLAPLAINS

    BONYTHON

    CALWELL

    THEODORE

    LakeBurleyGriffin

    LakeTuggeranong

    LakeGinninderra

    GungahlinPond

    YerrabiPond

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.1_Trunk Network.cdr

    Figure 3.1 | Job Number: CES01143

    Existing and Proposed Trunk Network

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    29/86

    10 | 11 |2009C:\CK Shared Artwork Folder\BRISBANE\CES01143_Figures\CE001143_Fig 3.2_Canberra Airport EZ CNC.ck.cdr

    Figure 3.2 | Job Number: CES01143

    Canberra Airport Employment Zone - Cycle Network Connections

    Missing link to business preceint

    Missing link to Queanbeyan

    Missing link

    Missing link to airport

    1

    2

    3

    4

    Legend

    Existing paths

    Proposed paths

    Existing lanes

    Proposed lanes

    Identified missing links

    Study area boundary

    to Gungahlin

    to Queanbeyan

    *Note: This plan includes a preliminary

    assessment of walking and cycling related

    issues. A full audit of all facilities has not been

    undertaken.

    3

    1

    2

    4

    3

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    30/86

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.3_Canberra.cdr

    Figure 3.3 | Job Number: CES01143

    Canberra Airport and Business Park - Existing and Proposed Pedestrian and Cycle Facilities

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    31/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 14

    3.2.2 HumeHume is a relatively isolated employment centre, located several kilometres from the nearest residential areas.

    Its proximity to Queanbeyan and Jerrabomberra was an important consideration, as is the potential future

    development of Tralee. The results of the investigations are contained in Figure 3.4. Consideration has beengiven to desirable links between Hume and Tralee, however none have been included in the prioritisation process

    due to the uncertainty surrounding this development. It is anticipated that these links would be funded as part of

    the development should it go ahead.

    Key improvements on approach routes to Hume include:

    cycle lanes along Monaro Highway from Fyshwick to Tharwa Drive; cycle lanes along Isabella Drive from Tuggeranong to Hume; cycle lanes along Lanyon Drive to be provided as part of duplication works; and cycle lanes/wide shoulders along Long Gully Road and Mugga Lane to link with southern Woden and

    northern Tuggeranong.

    The proposed facility improvements are contained on Figure 3.5.

    3.2.3 Barton/ParkesBarton and Parkes are the locations for many of the centres of national significance in Canberra. These include,

    but are not limited to:

    National Gallery of Australia;

    Old Parliament House; High Court of Australia; National Portrait Gallery; National Library of Australia; National Science Centre (Questicon).

    As such the area is a key attractor for tourists and large volumes of people. Given this, the need for high quality

    pedestrian networks is important, particularly to cater for large volumes. Figure 3.6 contains the outcomes of

    observations of the precinct. Some of the proposed projects to overcome issues identified in this area include:

    footpaths along the outer verge of Federation Mall; proposed off road shared path along King Edward Terrace; improved footpath facilities along National Circuit; on-road facility along Kings Avenue.

    Figure 3.7 contains the proposed infrastructure improvements.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    32/86

    Potential future link to Tralee

    Major entrance point

    Missing link (Mugga Lane/Long

    Gulley Road to Woden)

    Potential future link as

    Hume/Tralee develops

    1

    2

    3

    4

    Legend

    Existing paths

    Proposed paths

    Existing lanes

    Proposed lanes

    Identified missing links

    Study area boundary

    *Note: This plan includes a preliminaryassessment of walking and cycling relatedissues. A full audit of all facilities has not beenundertaken.

    4

    3

    2

    2

    2

    1

    1

    1

    1

    to Queanbeyan

    10 | 11 |2009C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 3.4_Hume EZ CNC.ck.cdr

    Figure 3.4 | Job Number: CES01143

    Hume Emploment Zone - Cycle Network Connections

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    33/86

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.5_Hume.cdr

    Figure 3.5 | Job Number: CES01143

    Hume - Existing and Proposed Pedestrian and Cycle Facilities

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    34/86

    2

    4

    1

    5

    3

    1

    2

    3

    5

    The varying traffic volumes and speeds on King

    Edward Terrace and Parkes Place are an

    opportunity for walking and cycling facilities to

    improve. There are high speeds and traffic volumes

    on Commonwealth Avenue and Kings Avenue, also

    warranting consideration for pedestrian/cyclist

    facilities improvements

    No kerb ramps

    Pedestrians have long delays at Kings Avenue to

    cross and are required to cross only half the

    intersection at a time

    Some routes along Federation Mall lack footpaths,

    though there are obvious desire lines

    The High Court precinct has poor permeability

    *Note: poor wayfinding signage generally

    4

    Legend

    Existing

    Bus interchange

    Areas with good shade cover

    Areas with high pedestrian volumes observed

    Bike parking observed

    Study area boundary

    Issues

    Uneven footpath

    Footpath does not meet observed demand

    Footpath with clutter

    No footpath

    Frequent driveway intrusion on footpath

    Potential personal safety issues

    No disabled access

    Tactile paving incorrect or non existent

    Poor crossing

    Poor connection/crossing (incl. through car park)

    Poor lighting

    *Note: This plan includes a preliminary assessment of

    walking and cycling related issues. A full audit of all

    facilities has not been undertaken.

    10 | 11 |2009

    C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 3.6_Barton_Parkes PAI.ck.cdr

    Figure 3.6 | Job Number: CES01143

    Barton/Parkes Town Centre - Pedestrian & Cycle Accessibility Issues

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    35/86

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.7_BartonParkes.cdr

    Figure 3.7 | Job Number: CES01143

    Barton Parkes - Existing and Proposed Pedestrian and Cycle Facilities

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    36/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 15

    3.2.4 FyshwickFyshwick is a centre that can be quite difficult to negotiate for both pedestrians and cyclists due to significant

    numbers of vehicles illegally parked on verges and footpaths. Figure 3.8 contains the outcomes of the

    observations. The main spine routes, Newcastle and Ipswich Streets, do not have any cycle facilities and the

    multi-lane roundabouts on Newcastle Street can be difficult to negotiate for both pedestrians and cyclists.

    Important approach routes to Fyshwick identified include Monaro Highway (north and south), Canberra Avenue

    and Hindmarsh Drive. Completion of the Lake Burley Griffin loop through Kingston Foreshore would provide an

    off-road link to the centre. The rail corridor and the alignment of the Newcastle Street extension were both

    identified as potential routes for direct off-road links with Kingston.

    Key improvements for Fyshwick employment centre include:

    cycle lanes along Newcastle Street;

    an off-road path along the western side of Ipswich Street; cycle lanes on Hindmarsh Drive and Canberra Avenue; and an off-road link from Narrabundah via Wormald Street and an existing underpass beneath Monaro

    Highway; and

    off-road links to Kingston via the rail corridor and Newcastle Street extension.

    Figure 3.9 contains the proposed facilities for Fyshwick.

    3.2.5 MitchellThis employment zone is focussed on light industry. Surrounding the area are existing and proposed residential

    precincts. Figure 3.10 contains the outcomes of the observations in this area. There are existing on-road

    facilities along key roads which run adjacent to the employment zone, Gungahlin Drive, Flemington Road and

    Sandford Road, therefore the proposed links are intended to connect these facilities.

    Some of the proposed connections included:

    Hoskins Street; Vicars Street.

    These proposed facilities are contained on Figure 3.11.

    3.2.6 MolongloThe Molonglo area is a new development area. As part of this process ACTPLA has planned some preliminary

    pedestrian and cyclist routes through the area. New routes were proposed as part of this study. This included

    additional links parallel to the primary road links and connections to the key destinations, such as local

    educational and community facilities. These are shown on Figure 3.12.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    37/86

    10 | 11 |2009C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CE001143_Fig 3.8_Fyshwick EZ CNC.ck.cdr

    Figure 3.8 | Job Number: CE001143

    Fyshwick Employment Zone - Cycle Network Connections

    1

    2

    3

    4

    to Airportto Chapel Hill

    Shared path should continue

    along greenspace not Service

    Road

    Missing links across rail line

    Poor permeability

    Missing link to airport and

    business parks

    1

    2

    3

    4

    Legend

    Existing paths

    Proposed paths

    Existing lanes

    Proposed lanes

    Identified missing links

    Poor crossing

    Study boundary area

    *Note: This plan includes a preliminary

    assessment of walking and cycling related

    issues. A full audit of all facilities has not been

    undertaken.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    38/86

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.9_Fyshwick.cdr

    Figure 3.9 | Job Number: CES01143

    Fyshwick - Existing and Proposed Pedestrian and Cycle Facilities

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    39/86

    10 | 11 |2009C:\CK Shared Artwork Folder\BRISBANE\CE001143_Figures\CES01143_Fig 3.9_Mitchell EZ CNC.ck.cdr

    Figure 3.10 | Job Number: CES01143

    Mitchell Employment Zone - Cycle Network Connections

    3

    1

    2

    1

    to Gungahlin

    to Civic

    North-south missing internal

    connection

    East-west missing internal

    connection

    Northern precinct missing internal

    connection

    1

    2

    3

    Legend

    Existing paths

    Proposed paths

    Existing lanes

    Proposed lanes

    Identified missing links

    Study area boundary

    *Note: This plan includes a preliminary

    assessment of walking and cycling related

    issues. A full audit of all facilities has not been

    undertaken.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    40/86

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.11_Mitchell.cdr

    Figure 3.11 | Job Number: CES01143

    Mitchell - Existing and Proposed Pedestrian and Cycle Facilities

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    41/86

    17 | 12 | 2009C:\CK Shared Artwork Folder\SYDNEY\CES01143_Figures\Maps for Report\CES01143_Fig 3.12_Molonglo.cdr

    Figure 3.12 | Job Number: CES01143

    Molonglo - Existing and Proposed Pedestrian and Cycle Facilities

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    42/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 16

    3.3 Review of Standards (DS13)The following table summarises the recommendations for changes to Design Standards for Urban Infrastructure

    Pedestrian and Cycle Facilities (DS13 ) based on the analysis undertaken in this 2009 review, consultation

    undertaken and proposed network plans documented in this report.

    Table 3.1 Recommended Changes to DS13

    Section Recommended Change

    13.1.1 General Second paragraph discusses the AUSTROADS documents Part 13 and Part 14. These

    documents have recently been revised and such reference needs to be updated here and

    throughout the document.

    13.1.4 ACT policies This section needs to be updated to reference new Sustainable Transport Plan and Walk and

    Cycle Strategy references to be updated here and throughout the document.

    13.2.2 Industry standards Update AUSTROADs references as discussed above.

    13.2.3 Policy and

    Guidelines

    Update with new sustainable transport plan and walk and cycle strategy documents.

    TAMS to consider adding guidelines in relation to implementing shared spaces and protected

    bike lanes (Copenhagen style cycle lanes). Suggestions include:

    Liveable Copenhagen: The Design of a Bicycle City

    http://www.sightline.org/research/sprawl/res_pubs/Livable_Copenhagen_reduced.pdf

    Street Design Manual (New York City DOT)

    http://www.nyc.gov/html/dot/html/about/streetdesignmanual.shtml

    It is also noted that in terms of Bicycle parking provision, AUSTROADS Guidelines are outdated

    in terms of supply for different land uses. It is recommended that the Green Building Council

    of Australia rates for bicycle parking in their Green Star rating tools be considered as best

    practice and reference to these guidelines be included in this section.

    http://www.gbca.org.au/green-star/rating-tools/

    13.6.3.1 Table 13-1 Off

    Road Path types

    The Column width should be described as minimum width. Another column should be added

    to include desirable widths to encourage wider paths which should cater for potential future

    demands and future proofing. Recommendations for changes to minimum widths are:

    - Minor path minimum width should be 1.8m to be consistent with newAUSTROADS guidelines

    - Intermediate path minimum width should be 2.5m to be consistent with newAUSTROADS guidelines

    - Trunk path minimum width should be 3.0m- Trunk path minimum width should 3.5m

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    43/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 17

    13.6.4.1 On road cycling

    facilities

    The list of alternative types should be increased to include protected bike lanes and shared

    spaces.

    The last paragraph after Table 13.2 should also discuss the opportunity to consider shared

    spaces in town centres.

    13.6.4.1 Table 13.2 On

    Road Cycling Provisions

    for New Road

    Major Collector Streets addition of shared space treatments should be added to the on road

    cycling provision column.

    Arterials (both categories) and Parkway addition of protected bike lane treatments should be

    added to the on road cycling provision column.

    13.6.5.1 General A dot point should be added to also consider the concept of Road Dieting as another way to

    retrofit facilities on arterial roads. A road diet entails removing travel lanes from a roadway

    and utilizing the space for other uses and travel modes.

    A new section under 13.6.5 should also be added to describe when such treatment could be

    considered. Refer to the Road Diet handbook: Setting trends for Liveable Cities by Jennifer

    Rosales.

    http://egov.oregon.gov/ODOT/TD/TP_RES/docs/2008NWTC/2008_presentations/7A_3_rosale

    s.pdf

    13.6.10.2 Flexible

    pavements and 13.6.10.3

    Concrete Paths

    There are improved construction practices which result in concrete paths being a smoother

    ride due to the treatment of joins. Concrete paths have benefits in regards to reduced cracking

    and consequently reduced maintenance and an overall longer life, and hence could beconsidered for Trunk Paths and other paths. These construction practices should be

    investigated by TAMS and dependant on the outcomes Section 13.6.10.2 and 13.6.10.3 be

    amended accordingly.

    13.6.14.1 Accessible

    Pedestrian Networks

    The last paragraph should be updated to refer to the APNs recommended for town centres in

    this report.

    13.6.15 Provisions at

    structures

    The minimum clear widths should be updated to reflect the recommendations discussed above

    for Table 13-1.

    13.8 Glossary Definitions of Shared Spaces, Protected Bike Lanes and Road Dieting should be added

    13.9 Standard Drawings DS13-01 The recommendations in regards to changes to minimum widths need to be applied

    to this drawing (i.e. Table 13-1). Dependant on the outcomes of investigations into new

    concrete paths constructions, notes in regards to asphalt and concrete should be updated.

    DS13-11 To be updated with recommended trunk network in this report.

    A new standard design drawing should be developed for protected bike lanes.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    44/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 18

    4 ACCESSIBLE STREETSThe assessment and development of key routes through the town centres to cater for those with vision andmobility impairments was central to the priority plan review. All streets should be developed to consider all

    users, however in some situations this has not occurred. As a result, a recommendation for a key route through

    each town centre was identified for priority action.

    To identify these routes, site visits were undertaken of each town centre, examining key land uses and

    destinations to assess demand along various potential routes. In tandem with this was the assessment of the

    quality of the facilities present and the works which would be required.

    In addition, discussions were held with representatives of Guide Dogs NSW/ACT to collaboratively identify key

    routes which were frequently used by their members.

    Representatives from the Guide Dogs NSW/ACT noted the following important considerations for the placement

    of the accessible routes:

    Many people who are vision impaired or blind use public transport as their means to access town centres around

    ACT. Therefore, a key route through each town centre must have accessible routes to both the bus interchanges

    and the taxi ranks, from this point people will vary where they access in the town centre.

    People who are vision impaired or blind use a technique with their white long canes called Shorelining. This

    technique involves using two different tactile surfaces to follow a straight line. This might be a building line, a

    grassed edge footpath or an open space with two different surfaces, i.e. brick tiles and smooth concrete.Because of the use of this technique it is important to keep the edges of these surfaces clear of any obstacles,

    i.e. sandwich boards, signs, tables and chairs as they can become a hazard.

    To achieve a high quality, accessible route, standards identified in the Civic Accessibility Study Volume 3

    Access Guidelines (2004) were used for all centres.

    The guidelines were developed in order to ensure that Civic was accessible to all users. The guidelines

    established designs to meet the requirements of the Building Code of Australia, Australian Standards and the

    Disability Discrimination Act.

    The Guidelines set out specific notes related to various areas of interest for accessible travel, including:

    accessible pedestrian networks (including path clearance, grades and maintenance aspects); kerb ramps; Tactile Ground Surface Indicators (TGSIs or tactiles); lighting; controlled intersections; information signage.

    The key outcomes are summarised in the following.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    45/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 19

    Accessible Pedestrian Networks

    The guidelines state that:

    Special access provisions should not be necessary if the environment is built to adequately reflect the diversityand needs of the community. Good design should seamlessly provide access for all. Providing equal access

    should be a fundamental part of good design rather than, at a later stage providing solutions to problems. Access

    is required for all people including adults and children, the frail aged and young children as well as those with

    intellectual, physical, sensory or mobility disabilities.

    The guidelines outline the primary requirements for an accessible path. These are as follows:

    A clear path of travel is the basis of the accessible pedestrian network. It should be free of steps, lips and steep

    gradients and free of all barriers and hazards..

    The clear path of travel shall be adjacent to a tactile cue to enable people with a visual impairment to track offit. This can include a wall, shopfront or a kerb.

    The minimum width of an accessible pedestrian network and any path is to be 1800mm. In the high volume open

    areas without roads the path width should be a minimum of 2,500mm.

    It is desirable that the accessible pedestrian network is covered using a colonnade network or awning.

    Paving should be slip resistant, including when wet and should not have transitions greater than 5mm in height.

    The surface should be overall hard, flat and stable, with appropriate use of colours to assist accessibility.

    Gradients for ramps should be a maximum of 1 in 8 if less than 1,520mm long and a maximum of 1 in 14 with

    landings every 9m at 1 in 20 landings at 15m. Sloping walkways at 1 in 33 landings should be located every 25m,

    over 1 in 33 does not require landings. Cross fall should not exceed 1 in 40. Landings should be a minimum

    1,200mm long for the full width of the clear path of travel. Overhead obstacles must be at least 2.0m high,

    unless identified. Cycleways shall not intrude into the clear path of travel. Any location where they do cross any

    clear path of travel should be treated as a hazard and tactile should be deployed. They are also to be clearly

    signed.

    Kerb ramps

    These enable the safe and easy crossing of kerbs and direct users in the correct direction. They should belocated within the clear path of travel and direction of travel.

    Tactiles

    Tactiles are to be used to alert people to hazards as well as to direct people to important facilities.

    They are required on road crossings, vehicle crossings on an accessible pedestrian path, where there are

    overhead obstructions and ground level obstructions, intrusions into the clear path of travel and the top and

    bottom of stairs.

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    46/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 20

    Directional tactile are required at mid block crossings, t-intersections, to bus timetables, to major signage and

    across large open spaces where there are no other route of tactiles available.

    Lighting

    It is intended that lighting will provide adequate vision for safe use and access at all times and conditions, with

    levels set down in AS1158.3.1 or the ACT Crime Prevention and Urban Design Resource Manual.

    Controlled Intersections

    Traffic signals are recommended to assist pedestrian movement, and should have visible, tactile and audible

    cues. Traffic islands should be safe and accessible for people with wheelchairs, with a minimum length of

    1200mm and width of 1000mm. Cut through or ramped walkways are required, with push buttons within reach.

    Fixtures

    Fixtures are intended to be located within areas of public facilities but must not impinge on the accessible

    pedestrian network, with location preference being on the kerb side of the accessible pedestrian network.

    Information Signage

    The intention of this measure is to ensure that signs provide users with easy to understand and essential

    information. It is recommended that information signage to assist in travel and identification of amenities should

    include tactile maps and Braille.

    The considerations of the above standards assisted with identifying works required along each of the proposedaccessible routes.

    The outcome of these investigations was an accessible route being identified within each town centre and

    associated works required. Details of the proposed accessible routes are contained below.

    4.1 CivicThe priority route for Civic is between the Alinga Street bus interchange and the Canberra Centre. This route

    runs along Alinga Street, Garema Place and Scotts Crossing. This route would also encompass the Bunda Street

    taxi rank, which runs perpendicular to Garema Place. It would also encompass connections north to the GriffinCentre, either along Bunda street or internally through the Canberra Centre.

    Key issues were raised about many aspects of this priority route by the representatives of Guide Dogs NSW/ACT.

    With regard to the bus interchange at Alinga Street, the following observations were made:

    The Civic [bus] interchange has extremely poor access for a person who is vision impaired or blind. From the

    majority of the bus platforms a person must cross East Row, Mort street or Alinga street to access most facilities

    in the area. This area can be confusing and dangerous for people with low vision. Firstly, there is a combination

    of loud distracting noises, including the high flow of bus traffic sometimes drowning out the sounds from other

    service vehicles using this area, there is often construction noise from buildings in the area, there are no safe

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    47/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 21

    points to cross as there could be buses pulling up at any point along the road, and on the corners the pram ramps

    lead into the middle of the intersection rather than straight across the road. This is a definite area for concern

    and keeps some travellers from accessing buses to Civic. This area also houses Vision Australia which is a very

    highly used service for people with a vision impairment or who are blind, they must first be able to make their

    way through the interchange.

    There were also concerns about the accessibility of the route from the bus interchange to the Canberra Centre

    via Garema Place:

    This area can be very confusing also for vision impaired and blind. There are no straight lines to follow, ie

    shorelines, there are unexpected drop offs and stairs in open areas that are not marked effectively, there are also

    cars travelling through the area, and many unexpected obstacles ie sandwich boards along the footpaths.

    The connections north to the Griffin Centre currently has good connections, according to the Guide Dogs

    NSW/ACT representatives and is accessible and safe.

    The following works would be required along this route to improve its accessibility for those with mobility or

    visual impairments:

    provision of a dedicated pedestrian crossing facility (ideally signals) for visually impaired at East Row,Mort Street or Alinga Street;

    audit of all pedestrian crossing facilities along the proposed route to ensure it is safe and convenient forcrossing by visually impaired persons. This should include identification and replacement of pram ramps

    which do not meet the guidelines;

    detailed audit of priority route to identify safe movement from the interchange across to the CanberraCentre, to provide a clear path along the shoreline, tactile paving, signage and lighting to clearly

    demonstrate safe passage options;

    provision of improved tactile facilities, particularly around the Scotts Crossing section of the route; improved lighting of Scotts Crossing to improve the ease of use of the pedestrian crossing facility.

    4.2 BelconnenThe proposed priority route would be located from the Lathlain Street bus station to the Belconnen shopping

    centre. This would also continue to the eastern commercial buildings around Chandler Street. The Guide Dogs

    NSW/ACT representatives made the following observations on the issues facing those with mobility and visual

    impairment throughout this key route:

    Currently to do this route one must walk through the car park to access either the red bridge or the mall, this is

    not an ideal route and is highly used. Pedestrians must give way to vehicles in the carpark and this can become

    particularly confusing for Vision Impaired or blind that are accessing this route. There is also a lot of surrounding

    noise from the buses and traffic on Lathlain Street interfering with the safe crossings at the car park.

    The key infrastructure required for the improvement of this route would include:

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    48/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 22

    audit of all pedestrian crossing facilities along the proposed route to ensure they are safe and convenientfor crossing by visually impaired persons. This should include identification and replacement of pram

    ramps which do not meet the guidelines and identification for tactile paving at key conflict points such as

    driveways. The audit may also identify need for further pedestrian crossing facilities;

    detailed audit of priority route to provide a clear path along the shoreline, tactile paving and lighting toclearly demonstrate safe passage options;

    associated lighting, wayfinding signage, to assist movement beyond the shopping centre to the lake.

    Benjamin Way was also cited as a potential key route, with the area outside the Churches Centre cited as an

    area with poor access conditions. These should be the next priority for works.

    4.3 WodenThe proposed priority route would be located between the Woden bus interchange and the shopping centre. This

    area would connect not only the public transport and the primary retail destination, but would also serve other

    key services, including banks and the post office. As stated by the Guide Dogs NSW/ACT representative:

    The Woden interchange is currently quite accessible for blind and vision impaired, however the stairs that lead

    from the interchange have quite poor access including no marking on the edge of each step and poor lighting.

    The key works which would therefore be necessary to achieve a more accessible route for those with mobility

    and visual impairment would include:

    audit of all pedestrian crossing facilities along the proposed route to ensure they are safe and convenientfor crossing by visually impaired persons. This should include identification and replacement of pram

    ramps which do not meet the guidelines and identification for tactile paving at key conflict points such as

    driveways. The audit may also identify need for further pedestrian crossing facilities;

    detailed audit of priority route to provide a clear path along the shoreline, tactile paving and lighting toclearly demonstrate safe passage options;

    improved lighting along Bradley Street, linking the bus interchange to the shopping centre; introduce appropriate Markings on the steps leading up to the courtyard areas (in accordance with Civic

    Accessibility Study Volume 3 Access Guidelines (2004));

    investigate opportunity to provide alternative treatments to stairs, including ramps for disability access; CPTED treatments to increase the safety perceptions of users of this route.

    4.4 GungahlinThe proposed priority route is along Hibberson Street, between the bus services and the retail destinations.

    Currently Hibberson Street has a wide and clear pathway. Another proposed route would be in the vicinity of the

    library and community centre and this would be the second priority for treatment in this centre.

    The key works which would be required to achieve these routes would include:

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    49/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 23

    audit of all pedestrian crossing facilities along the proposed route to ensure they are safe and convenientfor crossing by visually impaired persons. This should include identification and replacement of pram

    ramps which do not meet the guidelines and identification for tactile paving at key conflict points such as

    driveways. The audit may also identify need for further pedestrian crossing facilities. It is noted that the

    majority of this route is already up to standard;

    detailed audit of priority route to provide a clear path along the shoreline, tactile paving and lighting toclearly demonstrate safe passage options. It is noted that the majority of this route is already up to

    standard;

    improved kerb ramps in the vicinity of the library and community centre.

    4.5 TuggeranongThe proposed priority route identified is from the Tuggeranong bus interchange and taxi rank to the Hyperdome

    and beyond to the public service buildings on Anthllon Drive. The route could also be extended from the taxi rank

    to the library and Community Centre along Anketell Street and connecting through to Cowlishaw Street. The

    issues raised by Guide Dogs NSW/ACT were:

    Most of the crossings in this area are ground level, giving vision impaired and blind no warning of where exactly

    the road starts and the footpath/gutter finishes, this can become a great hazard.

    This area already possess wide footpaths. Therefore the key infrastructure requirements for this priority route

    are as follows:

    provision of appropriate lighting and wayfinding signage throughout the route;

    audit of the route to identify and provide tactile tiles along the route, which should include identificationof pedestrian crossing hazards;

    detailed audit of priority route to provide a clear path along the shoreline, tactile paving and lighting toclearly demonstrate safe passage options. It is noted that the majority of this route is already up to

    standard.

    4.6 FyshwickFyshwick has also been added to the assessment of accessible streets, despite not being a town centre, due to

    particular concerns raised by Guide Dogs NSW/ACT. Guide Dogs NSW/ACT note the following issues:

    The area and route of concern is from the Canberra South Motor Park to the closet bus stop which is at the

    Canberra Eye Hospital. Currently there is no footpath that leads to this bus stop and the visually impaired client

    must trek either through nature reserve or along Canberra Av, where there is also no footpath and traffic running

    at 80kms/hour. We are unaware of many of clients accessing Fyshwick at all due to safety concerns for

    pedestrians. If they need to access the area they generally take a carer with them.

    The route identified is along Canberra Avenue, between Wormald Street and the Monaro Highway. The specific

    works which would be required for this route would include:

    provision of footpath along the extent of the route; lighting and wayfinding signage as required;

  • 8/14/2019 Cycling & Pedestrian Network Priority Infrastructure for Capital Works | DRAFT December 2009

    50/86

    Cycling and Pedestrian Network

    Priority Network for Capital Works

    1143 draft report 181209 24

    tactile paving; audit of all pedestrian crossing facilities along the proposed route to ensure they are safe and convenient

    for crossing by visually impaired persons. This should include identification and replacement of pram

    ramps which do not meet the guidelines and identification for tactile paving at key conflict points such as

    driveways. The audit may also identify need for further pedestrian crossing facilities;

    detailed audit of priority route to provide a clear path along the shoreline, tactile paving and lighting toclearly demonstrate safe passage options.

  • 8/14/2019 Cycling & Pedestrian Ne