d istributed g eneration successful implementation of grid-connected rooftop pv programmes 27...
TRANSCRIPT
DISTRIBUTED GENERATION
SUCCESSFUL IMPLEMENTATION OF GRID-CONNECTED ROOFTOP PV PROGRAMMES
27 November 2013
ICORE 2013
Outline
Introduction
Critical Aspects for Successful Implementation
Programme Structure for G’nagar rooftop o Govt. Roleso Transaction Structureo Financial Structure
Outlook of Rooftop Policy of Gujarat
Key Learning of 5 MW Gandhinagar PV Rooftop2Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Success of Grid Connected Rooftop PV Programme
3
Technical Configuration
Implementation
Long-Term Operation
Commercial Viability
Eventual Scalability
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Typical PV System Architecture
4
Photovoltaic Modules(Approx. 1 – 100 kWP)
Grid-tied inverter Meter 2: Solar Electricity
Generation
Meter 1: Conventional Electricity Consumption
Transformer Grid
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Advantages of PV System Architecture
5
Relatively simple to install, operate and maintain. Most popular and globally accepted configuration. Disadvantage: No availability when grid is down.
Meter 1: Conventional Electricity Consumption
Transformer Grid
Photovoltaic Modules(Approx. 1 – 100 kWP)
Grid-tied inverter Meter 2: Solar Electricity
Generation
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Model II Net Metering
6
Relatively simple to install, operate and maintain. Net Electricity consumed will be charged. Issue of Non availability of grid is addressed
Meter 1: Bi-directional Meter
Transformer Grid
Photovoltaic Modules(Approx. 1 – 100 kWP)
Grid-tied inverter
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Gandhinagar Photovoltaic Rooftop Programme
The Gandhinagar Photovoltaic Rooftop Programme (the “Programme”) marks the first distributed power generation programme in India in its true sense.
True Public Private Partnership, brings together…
7
o Government o Developers o Regulatorso Home owners o Utility o R&D
“Kilowatt-programme at a megawatt-scale”
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Aim of Programme
Gandhinagar Photovoltaic Rooftop Programme aims for…o net 5 megawatt of photovoltaic installations…o in distributed kilowatt-sized photovoltaic systems…o through a PPP mode…o to promote clean energy and energy security...o as a part of the Gandhinagar Solar City Initiative.
Greater outcome of this pilot Programme:o Establish a practice/ philosophy of distributed solar and other
energy generation.o Bring a level of comfort to all stakeholders for further scale-up.o Encourage public participation.
8Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Project
Implementation
Agreement
(PIA)
Transaction Structure among Stakeholders
9
GoG/ EPD(Project Proponent)
GEDA(Nodal Agency)
GERMI(Project Str., Bid Process)
Azure Sun Energy(Capacity: 2.5 MW)
SPV by SunEdison (Capacity: 2.5 MW)
Torrent Power Ltd.(Off-taker)
2.5
MW
GPCL(Implementing Agency)
IFC & Consultants (Transaction Str. Advisor)
GERC(For Regulatory Approval)
GoG(For Govt. Approval)
PPA, based on GERC solar tariff
Ap
pro
vals
FundingG.R.
Screening & Selection
2 MW Govt. Rooftops
2 MW Govt. Rooftops
0.5 MW Private Rooftops
0.5 MW Private Rooftops
2.5
MW Gre
en
Ince
nti
ve
Selection through RFP
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Project Implementation Agreementfor ‘Viability’ tariff funding
Financial Transaction Model
10
Torrent Power Ltd.(Off-taker)
2 xProject Developer (Capacity: 2.5 MW ea.)
GPCL(Implementing Agency)
Private Rooftops: 1 MW
Govt. Rooftops: 4 MW- R&B- Education- Legal- Forest & Environment- Industries & Mines- Agriculture- Health & Family Welfare- Vigilance- Collectorate- Revenue- (Can be replaced by
Commercial Rooftops/ Terraces)
Power Purchase Agreementbased on GERC solar tariff ofRs. 12.44 /kWh (w/o AD: Rs. 11.14 /kWh)P
P A
P I A
‘Green Incentive’ Agreement
Generation-based, minimumRs. 3 per kWh
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Implementation Process at G’nagar
11Distributed Generation- ICORE 2013; 27 Nov. 2013
Developer Submits the Plant Drawing
Developer Starts Installation
A= Day 0
PV Capacity allotted to the Developers
1.GERMI approves Drawing2. Once approved by GERMI CEI also approves it
B=A+3 days
Regular Inspections are done at the site
Completes PV DC Installation
1.GERMI Inspects and give Installation Certificate2. CEI simultaneously inspects and give Certificate
C= B + 20 days( for 70 kw PV
system)
D= C + Within 2 Days
Implementation Process at G’nagar
Distributed Generation- ICORE 2013; 27 Nov. 2013 12
Ask GERMI/CEI for Commissioning Test
GERMI & CEI Performs Commissioning Test
GERMI & CEI Provides Commissioning
Certificate
Submits it to DisCom and PV Plant becomes Live
Start Paying Tariff to Developer
Within 2 Days
Submits Certificates to DisCom
DisCom installs meter and connects the Plant to the
Grid.Within 2 Days
Consolidated Status as on 07 Nov, 2013
Sr. Status Azure SunEdison TOTAL
1 Commissioned 2,200.00 kW 1599.77 kW 3,799.77 kW
2 Installed 000.00 kW 237.00 kW 237.87 kW
TOTAL 2,200.00 kW 1,830.77 kW 4,030 kW
13
Installations on Private Residential Premises
Total Energy Generated Till 23 July 2013 : 4,37,000 Green Units
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Installations under 5 MW Gandhinagar Programme
14
60.48 kW @ Lokayukta,Sector 10
80.61 kW @ Govt. Arts College, Sector 15
80.61 kW @ Govt. Arts College,Sector 20
264.04 kW @ Jivraj Mehta Bhavan Nos. 1, 2 and 4, Sector 10-b
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
PV Installation on J.M. Bhavan
15Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
PV Installation on J.M. Bhavan (2)
16Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Green Incentive: Aid to Roof-owners
‘Green Incentive’ is the minimum generation-based incentive for participating Roof-owners specified by GoG.
Advantages:o Encourage awareness and participation among roof-owners.o Will be correlated to home-owner’s electricity bill.o Should not be compared to ‘constant’ (or ‘dead’) lease rental.
17
Plot Size(Sq. m.)
Built-up Area(60%)
Typical Solar Area
(30%)
Typical PV Capacity
(kW)
Monthly Generation
(kWh)
Green Incentive (Rs.)
@ Rs. 2/ kWh
@ Rs. 3/ kWh
@ Rs. 4/ kWh
50 30 9 1 135 270 405 54070 42 12.6 1.5 202.5 405 607.5 81081 48.6 14.58 2 270 540 810 108090 54 16.2 3 405 810 1215 1620
135 81 24.3 4 540 1080 1620 2160200 120 36 6 810 1620 2430 3240250 150 45 7 945 1890 2835 3780330 198 59.4 8 1080 2160 3240 4320
Distributed Generation- ICORE 2013; 27 Nov. 2013
Distributed Generation- ICORE 2013; 27 Nov. 2013
Future Outlook
New Cities – 5-10 MW each:o Bhavnagaro Mehsanao Rajkoto Surato Vadodara
Incorporation of Rooftop Photovoltaics at Policy and Regulatory Level.
Explore different implementation models:o Feed-in or net metering?o Third party/ Developer driven or private ownership?
18
The Gandhinagar Solar Rooftop Programme
is selected as on of the TOP 10 DEALS OF ASIA-PACIFIC
by Infrastructure Journal.
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Learning of Critical Aspects
How appealing is the Green Incentive?o What is the value of my roof?
How appealing is the Third-Party Model?o Am I willing to sign a 25-year lease agreement?o Why can’t I get the full benefit of my PV system?
Interdependency of Contracts and Financial Closure:o Lease Agreement PIA PPA.
Implementation:o Coordination between Statutory Bodies, Regulator, Chief Electrical
Inspector, DisCom, Building Owners/ Govt. Departments, Developer, Financer, Project Management, Social.
19Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Evolution & Implementation of Rooftop Solar PV Installations for Gujarat
Model I: Capital cost borne by the Governmento Advantage:
• Ease of implementation, and widely implemented.o Disadvantage:
• Ownership issues, and hence, maintenance suffers.o Example: Most rooftop solar installations by various governments throughout
India (including GEDA).
Model II: Public Private Partnership o Example: 5 MW Gandhinagar Rooftop Solar Programme.o Advantage:
• Generation-based incentive ensures long-term utilization.• Government interaction with limited number of credible Developers.• Standard quality and optimization of PV installations.• No upfront cost to Government/ Utility.
o Disadvantage: • Property owners unwilling to sign long-term lease agreements.• Incentives from solar generation not enough compared to real-estate lease.
20Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Model III: Individual Ownership (Proposed in Current Rooftop Solar Policy)
Advantage: o Equal opportunity to smaller rooftop owners.o Ownership of individual is well-defined.o Investors reap the direct benefit of electricity and
also become energy aware/ efficient.o Investment yields definite returns.o Potential for widespread public deployment.o Successful model globally.
Challenge: o Investment expected from someone who does not
understand technology.o Capital subsidies required to incentivize participation
(under net-metering scheme).o Direct dealing of DisComs directly with Customers.
21Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Policy Implementation: Preparatory Phase
DisComs: Obvious focal agencyo Specify standards of interconnection and Net-Meter.o Set up internal process viz. accepting applications for interconnection, PV system commissioning,
regulatory compliance, billing.
State Nodal Agency: GEDAo Empanelment of Channel Partners/ Installers.o Avail necessary funds from State Dept., Central Ministries.o Act as a single-window for disbursing subsidies.o Publicize and monitor overall progress.
Channel Partners/ Installerso Link between System Owners and DisCom/ GEDA for administrative procedures.o Comply with relevant guidelines of safety, standard, performance outlined by DisCom, GEDA, MNRE,
GERC, CEA, etc.
Eligible Entities/ System Ownerso Only employ Channel Partners/ Installers empanelled by GEDA.o Apply for interconnection of rooftop PV system.o Comply with any other approvals/ clearances required from time to time.o Shall be final beneficiaries of subsidies.o Shall own and be responsible for operation of PV systems.
22Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Policy Implementation: Preparatory Phase
23
GEDA Empanels Channel Partners/ Installers.
DisComs set up standards for Net-Metering.
GEDA Educates Channel Partners with compliance
requirements.
GEDA publically promotes Rooftop Solar
Policy/Programme
DisComs set up internal processes for:
1. Accepting and scrutinizing customer applications, and
2. Commissioning PV systems.
Channel Partners commence their own marketing.
Rooftop Solar Policy is Launched.
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
Policy Implementation:Implementation Phase
24
Eligible Entity contacts Channel Partner.
Channel Partners undertak-es feasibility of installation.
Eligible Entity, via Channel Partner, applies to GEDA
for subsidy.
GEDA approves:1. Subsidy subject to fund
availability, and2. PV System capacity
subject to DisCom’s and CEI’s clearance.
DisCom:1.Verifies installation, and2. Installs Net-Meter to
commission the system.
Channel Partner installs rooftop PV system.
Eligible Entity, via Channel Partner, applies to DisCom
for interconnection.
DisCom bills System Owner based on net consumption.
System Owner owns and operates the PV system.
CEI’s Approves:1.Capacity of installations
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
A Unit of Energy SAVED= 2 Units of Energy GENERATED
DISTRIBUTED GENERATION
SUCCESSFUL IMPLEMENTATION OF GRID-CONNECTED ROOFTOP PV PROGRAMMES
27 November 2013
ICORE 2013
Backup Slides…
27Distributed Generation- ICORE 2013; 27 Nov. 2013
Distributed Generation- ICORE 2013; 27 Nov. 2013
Successful Developers
L1: Azure Sun Energy Pvt. Ltd. (“Azure”)
L2: Ananth Solar Power Maharashtra Pvt. Ltd. (“SunEdison”)o A subsidiary of SunEdison Energy India Pvt. Ltd.
28
Azure SunEdisonQuoted Tariff: Rs. 11.21 /kWh Rs. 11.793 /kWhGERC Relevant Tariff: Rs. 11.14 /kWh Rs. 12.44 /kWh
Torrent pays: Rs. 11.21 /kWh Rs. 11.793 /kWhGoG-PIA (GPCL) Pays: Rs. 0.07 /kWh ---
Distributed Generation- ICORE 2013; 27 Nov. 2013 [email protected]
DISTRIBUTED GENERATION
SUCCESSFUL IMPLEMENTATION OF GRID-CONNECTED ROOFTOP PV PROGRAMMES
27 November 2013
ICORE 2013