Table of Contents
1. Key Project Structure & Involved Parties
2. Key Risks and Mitigation Guideline
3. Key Documentation & Timeline
Strictly Private & Confidential 1
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 3/18
Typical Project Finance StructureShareholders Agreement
Sponsors SponsorsOwner’s
EngineersSponsor’s
Legal Counsel
Lender’sLegal Counsel Sponsor Support
AgreementSupplierSupplier Warranty
Project CompanyLendersEPC
Contractor
O&M
EPC Contract
O&M Contract
Loan and FinancialPackage Agreement
/Trustees OperatorPower Purchase
Agreement
Insurance PolicyAssignment of Agreements
Off-Taker
IndependentEngineers
Insurer
Assignment of Proceeds
Strictly Private & Confidential 2
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 4/18
Table of Contents
1. Key Project Structure & Involved Parties
2. Key Risks and Mitigation Guideline
3. Key Documentation & Timeline
Strictly Private & Confidential 3
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 5/18
Key Perception of Risks and Mitigations
ssuesssues
Balance of Plant Panel/Inverter
ga onga on
Fixed price, turn key
u e neu e ne
Liquidated damage termsonstruct ononstruct on
Synchronization
Cost Controls andCompletion
Guarantee completion date
Select experienced contractor
Acceptable performance guarantee
Strong status of EPC
Technologyand
Technologyand
Reliability and Durability
Environmental Suitability
Technology and performancerecords reviews
Lab testing and Certificates
Proven technology with reasonabletrack records
Proper Manufacturing test&warranty
ro ec conom cs
Service/Maintenance program Reachable manufacturer/supplier
Location clear of surrounding futureIrradiation
andProduction
Irradiationand
Production
Suitability
Climate Impact
Geographic Limitation
Historical climate/season review
On site survey and verification
Yield Analysis
development, flooding, shadows,smog and smoke
Technical Advisor with formulatedyield analysis approach
Strictly Private & Confidential 4
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 6/18
Key Risks and Mitigations of Solar Farm Development (Con’t)
Continuity of the Power
ga onga on
Understand PPA characteristic
u e neu e ne
Legal counsel to review warranty, LD
ontractuaontractua
Terms and enforceabilityof contracts and warranty
(PPA to renew every 5 years)
Legal due diligence Legal counsel to review contract
enforceability under Thai Laws
EnvironmentalEnvironmental
Potential environment pollutionsassessments
Local community communication
Technical/Environmental Advisor toperform review and study
Local road show and education
Impact and effect tosurrounding environment
Local community
Social responsibility program
Job creationacceptance
Strictly Private & Confidential 5
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 7/18
Table of Contents
1. Key Project Structure & Involved Parties
2. Key Risks and Mitigation Guideline
3. Key Documentation & Timeline
Strictly Private & Confidential 6
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 8/18
Key Documentation
Financial DocumentsFinancial Documents
• Indicative Terms and Conditions
• Credit Facilities Agreement
• Shareholder Undertaking
• Power Purchase Agreement
• Interconnection Agreement
• EPC Agreement
• Warranties and Service
• BOP Contracts
• O&M Contracts
Project DocumentsProject Documents • Land Agreements
• Joint Venture or Shareholder Agreement
• Performance Bonds
• Supply Contracts
• Technology/Operating Licenses
• Planning and Environmental Consents (IEE)
Strictly Private & Confidential 7
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 9/18
Key Documentation
Security DocumentsSecurity Documents
• Mortgage of land• Mortgage of all plant equipment/machineries
• Assignment of project documents/bonds
• Insurance endorsement
Expert OpinionsExpert Opinions
•Technical Evaluation Report•Legal Opinion•Insurance Report
•Conduct due diligences 4-6 weeks
•Conclude Terms and Conditions 1-2 weeks• ra t ng & negot ate oan ocumentat on 4-8 wee s•Final bank’s board approval 4-6 weeks•Financial close
•Fulfill condition precedence prior to drawdown 4 weeks
(2-3 months)
Strictly Private & Confidential 8
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 10/18
Example of Key Project Enhanced Parties
SponsorsSolar Power Co. LtdE for E, Kyocera Corp.
Experienced Developerproper selection of location, selection of technology, matchingcomponents, cost-effective component
Off-taker PEAStrong Governmental Agency
Power purchase agreement under strategic and long termgovernmental support
Counsels/Consultants Clifford Chance (Legal)
Mott MacDonald (IE)
Understand issues of renewable – supplier warranty, contracttermination, performance warranty
Understand dynamic of technical development – assessments of
Advisor/Lender KBank (FA/Arranger)
, ,
Keen and familiar with renewable projects – understand keyspecific characteristic of renewable projects
Understand project requirements – able to advise and deliver
EPC/Equipment Suppliers Kyocera Corp.SMA
Strong R&D and track records – traceable and proven recordsProduction readiness – provide quality products within timeframeCommitment of services – ability to provide commitment/warranty
Strictly Private & Confidential 9
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 11/18
KBank’s CredentialsKBank’s Credentials
Strictly Private & Confidential 10
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 12/18
Focus on Client Solutions
Products &
Services
Origination &
Structuring
Syndication &
Distribution
Client-Focused
Solutions
• Commercial Papers/ Bill of
Exchange
• Debentures
• In-depth knowledge base from
our experienced industry
specialists adds value to the
• Well-established market
intelligence, in depth and
breadth, essential for
Our professionals’
common objective is
• Asset-Backed Securities
• Project Finance
• Syndicated Loans
• Structured Finance
transaction
• Initiative structuring team to
execute and deliver the well-
structured transaction
formulation of syndication
strategy
• Experienced sale team to
offer roducts and services
solution to clients, withexpertise, initiatives and
commitments.
• Property Fund
• FX/Derivative Products
• Structured Notes
• Credit Ratin Advisor Services
• Solution-driven origination &
structuring
to the right targets
• Highly efficient distribution
infrastructure i.e. subscription
and a ment s stem
• Financial Advisory Services
Strictly Private & Confidential 11
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 13/18
KBank’s 2009 Performance in DCM Recognized Domestically / Internationally
Best Foreign Currency Liquidity Providers in Thailand
Best Bond House
Best THB Interest Rates Contributors in Thailand Top Bookrunners of Thailand Syndicated Loans
Best Cash & Liquidity Management Bank Best Private Wealth Management House Best Project Financing Deal of the Year
Best Domestic Providers for Local Currency Products and Interest Rate Products Best Domestic Provider of FX Services in Thailand as voted by Financial Institutions Best Domestic Provider of FX Services in Thailand as voted by Corporates Best Domestic Provider for Innovative FX Products and Structured Ideas in Thailand as voted by Corporates
Best Bond House
Best Domestic Provider of FX Prime Broking Services in Thailand as voted by Corporates Best Domestic Provider of Single-Bank Electronic Trading Platform in Thailand as voted by Corporate
Best Trade Finance Bank
Project Finance Deal of the Year
THB 13 940 million and USD 187.5 million Pro ect Financin for Theun-Hinboun H dro ower Ex ansion Pro ect
Strictly Private & Confidential 12
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 14/18
…with outstanding track record of Power Project Advisory
“KBank is also honored to have been selected as Financial Advisor to the world’s largestsolar farm: NED developed by EGCO, CLP and Mitsubishi Corporation and the ASEAN’s
”Strictly Private & Confidential 13
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 15/18
Top Five Thailand Loans Mandated Arrangers – Bloomberg
solution to clients with a variety of optimum financing products.
• Our funding arrangement services will formulate the most suitable funding to client with ultimateobjective to maximise return to the sponsors or shareholders.
Deal Volume
January – December 2009
Count (USD Million)
1 KASIKORNBANK 10 626 27.3
2 Ban kok Bank 3 292 12.7
3 Siam Commercial Bank 2 201 8.7
4 Bank of Ayudhya 3 189 8.3
5 Tisco Bank 1 121 5.3
Strictly Private & Confidential 14
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 16/18
Deal Volume
January – December 2009Top Five Thailand Loans Book Runners
an ameCount (USD Million)
ares
1 KASIKORNBANK 6 527 33.2
2 Siam Commercial Bank 1 407 25.6
3 Bank of Ayudhya 1 120 7.6
4 Siam City Bank 1 102 6.5
. .
Rank NameDeal Volume
% Shares
January – December 2009
1 KASIKORNBANK 7 792.2 38.9
2 Siam Commercial Bank 2 274.2 13.5
3 Bangkok Bank 1 203.5 10.0
4 Bank of Ayudhya 1 120.9 5.9
5 DnB NOR BANK ASA 1 100.0 4.9Strictly Private & Confidential 15
8/6/2019 D2 Key Success to Achieve the Best Financing
http://slidepdf.com/reader/full/d2-key-success-to-achieve-the-best-financing 17/18
Feel free to contact:
นพเดช กรรณส ูต(Nopadej Karnasuta)
First Vice PresidentMulti-Corporate Business Department
KASIKORNBANK PCL.
Tel: 662-470-6004-5
E-mail: [email protected]