daily progress report shikarpur grid 28-02-2014

Upload: yaser-majeed

Post on 03-Jun-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 Daily Progress Report Shikarpur Grid 28-02-2014

    1/3

    To,

    Toda y Thi s Month To Date Today This Month To Da te Today This Month To Date Today This Month To Date Toda y This Month To Date Today This Month To Da te Today This Month To Date

    Pile Work 2 56 9 20 40 40Excavation 7 7

    Beam 6 6

    Pile Cap/Pad 3 3

    Pedestals

    Backfilling

    S.SS. Errection

    Equip. Erection

    Toda y Thi s Month To Date Today This Month To Da te Today This Month To Date Today This Month To Date Toda y This Month To Date Today This Month To Da te Today This Month To Date

    Pile Work 56Excavation 7 7

    Pile Cap/Beam 5 5

    PedestalsBackfilling

    Switch YardPath Culverts (21

    Nos.)

    Contractor: NEIE

    Auto Transformer (7 Nos.)Line Gantry (5 Nos.)

    (20+10.75+9.25m)

    ATB Gantry (5 Nos.)

    (20+10.75+9.25m)

    Disconnecto r ( 24 Se ts) C ircu it Br ea ke r ( 9 S et s)

    High Level Gantry (10 Nos.)

    (30.75+9.25m)

    ActivitiesC.V.T (22 Nos)

    Activities

    Switch YardPath (1208 m)Current Trasnsformer (27 Nos)

    NEIE

    Al-Husain Traders & ContractorsDated: 28/02/2014

    DESIGN, MANUFACTURE, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF PLANT FOR UPGRADATION OF THE

    EXISTING 220 KV SHIKARPUR SUBSTATION TO 500 KV LEVEL.

    Daily Progress Report

    Fire Wall (7 Nos.)

    500 kV Switch Yard

    1 2 3 4 5 6 7

    8 9 10 11 12 13 14

    Post Insulator (72 Nos)Low Level Gantry (10 Nos.)

    (20m)Surge Arrestor (18 Nos.)

    S.SS. Errection

    Equip. Erection

    Toda y Thi s Month To Date Today This Month To Da te Today This Month To Date Today This Month To Date

    Excavation

    Lean Concrete

    Steel Work

    Form Work

    Conrete Work

    Bitumen Coating

    Backfilling

    3- Surface Preparation for Firewall-6 Bes is in Progress4- Surface preparation for lean concrete is in progress.

    TYPE-iv (510m)

    Today Activities Perfomed:1- Bitumen Coating and Back Filling of Fire wall(pile cap) And Auto Transformer (walls) are in Progress.2- Placement of M.s Rails and Levelling is in Progress

    15

    TYPE-ii(450m)Activities TYPE-iii(620m)

    Trenches (m)

    TYPE-i(140m)

  • 8/12/2019 Daily Progress Report Shikarpur Grid 28-02-2014

    2/3

    To,

    NEIE DESIGN, MANUFACTURE, SUPPLY, INSTALLATION, TESTING & COMMISSIONING OF PLANT FOR UPGRADATION OF THE EXISTING 220 KV SHIKARPUR SUBSTATION TO 500

    KV LEVEL.

    Al-Husain Traders & Contractors

    Daily Progress Report

    Activities Surge Arrestor (12 Nos.)

    High Level (4 Nos.)

    (13+5.5+4m)

    High Level (8 Nos.)

    (18.5+4m)

    Low Level (12 Nos.)

    (13+4m) C.V.T Line (12 Nos.)

    Dated: 28/02/2014

    Contractor: NEIE

    220 kV Switch Yard

    Post Insulator (26 Nos.)

    1 2 5 6 7

    Current Transformer (18 Nos.)

    3 4

    TodayThis

    MonthT o Da te T oda y

    This

    MonthT o D at e T od ay

    This

    MonthTo Date

    This

    MonthT o Da te T oda y

    This

    MonthTo Date Today

    This

    MonthTo Date Today

    This

    MonthTo Date

    Pile Work 32 48 16 6 6 6 6 4 4

    Excavation

    Pile Cap/Beam

    Pedestals

    Backfilling

    S.SS. Errection

    Today

    Equip. Erection

    TodayThis

    MonthT o Da te T oda y

    This

    MonthT o D at e T od ay

    This

    MonthT o Date Ac tivity To day

    This

    MonthT o Da te T oda y

    This

    MonthTo Date Activity Today This Month To Date

    Pile Work 12 12 3 3 3 Sub Base 146.7 146.7 76.65 88.65

    Brick

    Work/Stone

    Masonry

    Activities

    128 9 10 11

    Disconnector (16 sets) Transformer Way(111 m) Fencing (335m)

    13

    Cir cui t Br eaker (6 Sets) Path Way (257 m) Bi tumen Road (250 m)

    Excavation Base 146.7 146.7 Copping

    Pile Cap/Beam Carpet Fence Work

    Pedestals

    Backfilling

    S.SS. Errection

    Equip. Erection

    17

    1514 16

    TodayThis

    MonthT o Da te T oda y

    This

    MonthT o D at e T od ay

    This

    MonthTo Date Today

    This

    MonthTo Date Today

    This

    MonthTo Date Today

    This

    MonthTo Date

    Excavation 100% 100% Excavation 100% 100%

    Lean Concrete 100% 100% Lean Concrete 92.7 92.7

    Steel Work 100% 100% Steel Work

    Transformer Moving Area (118.7 M)

    Trenches (m)Path Way Culverts (7 Nos)

    Activities

    Transformer Way Culvert

    (01 No.) TYPE-iii (260 m) ActivitiesTYPE-i (126 m) TYPE-iv (257 m)

    Form Work 100% 100% Form Work

    Conrete Work 100% 100% Conrete Work

    Bitumen Coating 100% 100%

    Backfilling

    Today Activities Perfomed:

    2- Back Filling of Bitumen Road shoulders is completed

    1- Laying of base material of Bitumen Road is completed

    7- Steel Cutting and Bending of 11kV Feeder Trench is in Progress

    5- Compaction of Bitumen Road dis in Progress

    6- Lean Concrete of 11kV Feeder Trench is completed

    4- Pile Work of 220Kv Equipment Piles is in Progress

    3- Surface Preparation of Moving Area is in Progress.

  • 8/12/2019 Daily Progress Report Shikarpur Grid 28-02-2014

    3/3

    NEIE DESIGN MANUFACTURE SUPPLY INSTALLATION TESTING & COMMISSIONING OF PLANT FOR UPGRADATION OF THE EXISTING 220

    To,

    Dated:28/02/2014

    Daily Progress Report

    Control House Building

    KV SHIKARPUR SUBSTATION TO 500 KV LEVEL

    Contractor: NEIE

    AL-HUSSAIN TRADERS

    Sr. No. Status

    1 Completed

    2 Completed

    Excavation Work for Foundation Beams And Pile Caps

    Descripition of Activities

    Pile Work

    3 In Progress

    4 In Progress

    5 In Progress

    6 In Progress

    Steel Work of Pile Caps, Foundation Beams, Columns Up to Plinth Level

    Concrete Work of Pile Caps and Foundation Beams

    Form Work of Pile Caps and Foundation Beams

    Form Work of Columns upto Plinth Level

    7

    8

    Today Activities Performed

    3- Form Work of Columns upto Plinth Level is in Progress

    1- Steel Work of Foundation Beams Axis (5-8) is in progress

    2- Form Work of Foundation Beams Axis (5-8) is in progress.

    7- Bitumen Coating on Foundation Beams is in Progress

    -

    ee

    x

    ng o a

    r ase oun a on s n rogress

    5- Concrete Work of Pile Caps and Foundation Beams Axis (1~5- A~D) is completed

    6- Opening & Shifting of Form work is in progress.

    8- Bar Bending Schedule of Stair Case Submitted on 09-02-2014

    9- Bar Bending Schedule of Columns ( Plinth Level upto 1st Floor ) Submitted on 09-02-2014

    10- Bar Bending Schedule of 1st Floor Beams Submitted on 21-02-2014