damian vujchich, fluor, case study: modularisation for iron ore plant in western australia
DESCRIPTION
Damian Vujchich delivered the presentation at 2014 Bulk Materials Handling Conference. The 11th annual Bulk Materials Handling Conference is an expert led forum focusing on the engineering behind the latest expansions and upgrades of bulk materials facilities. This conference will evaluate the latest engineering feats that are creating record levels of throughput whilst minimising downtime. For more information about the event, please visit: http://www.informa.com.au/bulkmaterials14TRANSCRIPT
Geography
1 SEA TRANSPORT ROAD TRANSPORT
CHINA (Fabrication)
PORT FACILITIES, WESTERN AUSTRALIA
Project Site
4000 NAUTICAL
MILES
PORT FACILITIES, WESTERN AUSTRALIA
Steelwork Totals
2
STEELWORK TOTALS - 19 000 T of STEELWORK
15 000 T FABRICATED OFF SHORE (CHINA) {136 MODULES + ADDITIONAL LOOSE STEEL AND BREAK BULK ITEMS}
4 000 T FABRICATED IN AUSTRALIA
Steelwork Totals
3
STEELWORK TOTALS - 19 000 T of STEELWORK
15 000 T FABRICATED OFF SHORE (CHINA) {136 MODULES + ADDITIONAL LOOSE STEEL AND BREAK BULK ITEMS}
4 000 T FABRICATED IN AUSTRALIA
ADDITIONAL 1500 TONNES OF SHIPPING STEEL DUE TO OFF SHORE FABRICATION – ROUGHLY 10% ADDITIONAL STEEL
Movement of Modules – Off-shore Fabrication
4
FABRICATE MODULE IN YARD
DELIVER MODULE TO WHARF
LOAD ONTO SHIP SHIP TO SITE
UNLOAD ONTO ROAD TRANSPORT
TEMPORARY STORAGE AT PORT LAYDOWN
YARD
ROAD TRANSPORT TO SITE BY CONVOY
UNLOAD ONTO LAYDOWN AREA
INSTALL INTO FINAL POSITION
1 2 3 4
5
6 7
8
9
NUMBERED STAGES
Movement of Modules – Off-shore Fabrication
5
FABRICATE MODULE IN YARD
DELIVER MODULE TO WHARF
LOAD ONTO SHIP SHIP TO SITE
UNLOAD ONTO ROAD TRANSPORT
TEMPORARY STORAGE AT PORT LAYDOWN
YARD
ROAD TRANSPORT TO SITE BY CONVOY
UNLOAD ONTO LAYDOWN AREA
INSTALL INTO FINAL POSITION
1 2 3 4
5
6 7
8
9
FABRICATION CONTRACTOR
INTERNATIONAL SHIPPING
CONTRACTOR
ROAD TRANSPORT CONTRACTOR
SMP INSTALLATION CONTRACTOR
TRANSPORT MANAGEMENT CONTRACTOR
MARINE WARRANTY SURVEYOR
CONTRACTOR RESPONSIBILITIES
Movement of Modules – Off-shore Fabrication
6
FABRICATE MODULE IN YARD
DELIVER MODULE TO WHARF
LOAD ONTO SHIP SHIP TO SITE
UNLOAD ONTO ROAD TRANSPORT
TEMPORARY STORAGE AT PORT LAYDOWN
YARD
ROAD TRANSPORT TO SITE BY CONVOY
UNLOAD ONTO LAYDOWN AREA
INSTALL INTO FINAL POSITION
1 2 3 4
5
6 7
8
9
FABRICATION CONTRACTOR
INTERNATIONAL SHIPPING
CONTRACTOR
ROAD TRANSPORT CONTRACTOR
SMP INSTALLATION CONTRACTOR
TRANSPORT MANAGEMENT CONTRACTOR
MARINE WARRANTY SURVEYOR
Constructability & Transportation Requirements
7
♦ Each phase / stage will have restrictions on what type of module they can handle, lift, rotate, move, fit, approve, insure, transport and install.
♦ These size restrictions & transport loads need to be compiled into envelopes and guidelines for the design & construction team before detailed design taking place.
♦ This approach, which has been built up from experience on several projects, requires input and close collaboration between engineering, fabrication and construction teams for successful project delivery.
♦ Strong and clear guidelines minimises the potential for issues, delays and rework along the detailed engineering, fabrication, transportation & construction processes.
Fabrication Requirements
Fabricator’s capability ideally should include: ♦ Crane capabilities – lifting and rotation. ♦ All weather work areas – size can limit module work. ♦ Load out capabilities – are wharves wide & deep enough
for Heavy Lift Vessels? ♦ Paint shop and ventilated blasting yards – large enough to
handle long modules. ♦ Transportation of modules around yard via vehicles. ♦ Capabilities to perform pre-assembly, trial fitting and match
drilling of large inter connected modules.
8
Fabrication Requirements
Fabricator’s capability ideally should include: ♦ Weighing facilities for modules larger than 50T. Weight
reports must be provided to engineering and shipping contractor prior to load out.
♦ Internal teams to handle Quality Assurance including certification of materials, welding, welders, tolerance and trial assembly sequences.
♦ Capabilities for support and shadowing services by EPCM and client representatives for QA, planning, scheduling and engineering.
9
Fabrication Requirements
10
Crane Capacity
Covered Paint Sheds / Ventilated Blasting Sheds
All Weather Workshops
Outdoor Work Areas
Fabrication Requirements
11
Wharf Capacity – Length and Depth
Issues
Wharf Capacity – Access for Movement
of Modules
Fabrication Requirements
12
MODULE WEIGHING
THREE TESTS DONE TO GET
ACCURATE RESULTS
FABRICATOR TO PROVIDE WEIGHT
REPORT FOR EACH MODULE OVER 50T
PROJECT WIDE WEIGHT CONTROL IS IMPORTANT FOR BOTH HANDLING OF
MODULES AND TRACKING OF QUANTITIES FOR INVOICING
Fabrication Requirements
13
TRIAL ASSEMBLY AND MATCH
DRILLING OF A MODULED TAKE UP
TOWER
CRITICAL CONNECTION
AT SITE – WORKING AT
HEIGHTS
Fabrication Requirements
14
TRIAL ASSEMBLY MATCH DRILLING
ASSEMBLE MODULES TOGETHER TO CHECK FABRICATION – ANY ERRORS TO
BE CORRECTED PRIOR TO MODULE LEAVING FABRICATION YARD
MATCH DRILL CONNECTION TOGETHER TO ENSURE CORRECT
FIT UP AT SITE
Fabrication Requirements
15
END PRODUCT – MODULE INSTALLED AT SITE WITH CORRECT FIT UP USING
ONE LIFT ONLY – EFFICENT AND AVOIDS WORKING AT
HEIGHTS ISSUES.
Marine Warranty Surveyor
♦ The MWS acts on behalf on the underwriters providing third party reviews for high value transportation projects.
♦ MWS have requirements for lifting on and off the vessels and these must be followed.
♦ Design team must understand MWS requirements for transport & submit calculations prior for review. The MWS reviews transportation calculations as well as the structural design to assess suitability for transportation.
16
Marine Warranty Surveyor
17
Surveyor Present at Lifts > 50T – Providing Approval of Rigging prior to each Lift
Provides Sailaway Certificates of Insurance of Seafastening
Prior to Vessel Departures
Transport & Logistics Management
♦ Responsible for customs and employment of international shipping & road transport. This could be done by EPCM if experienced personal are within the project team or alternatively by a external contractor.
♦ Fabricators must be able to provide clean modules with wash down facilities wharf side (including EWP for access). Module must be clean to be accepted by local quarantine agencies. Transport management conducts inspections of wharf side cleaning and washing down of modules prior to loading onto vessel.
18
Transport & Logistics Management
♦ Consideration for wash down & access about modules responsibility of the engineering design team. Temporary handrail can provide safe access about modules and seal plates around difficult access areas can provide for an easy wash down process.
♦ Additional responsibility with co-ordination role with local road authorities for acceptable road transport procedures. These include but are not limited to:
19
o Bridge width and strength o Permitted turning circles
o Road widths and height limits o Clashes with power lines
Transport & Logistics Management
20
Transport Management Contractor Supervises and
approves Module wash down for AQUIS approval at Local Port.
International Shipping Requirements
♦ Responsible for the transport from off-shore wharves to local ports.
♦ Has restrictions with respect to lifting arrangements and to module sizes transported (ships have dimensional constraints).
♦ Must work with port’s local stevedores to rig and release module loadings.
♦ Responsible for sea fastening of modules to boat deck. ♦ Responsible for providing actual sea force accelerations
for review, inclusion in design and approval by the MWS.
21
International Shipping Requirements
22
STOWAGE PLANS Document Provided For Each Voyage. Must be approved by Engineering and
MWS. Outlines Lifting, Stowage & Seafastening Procedures.
METHOD STATEMENT DOCUMENT
Voyage’s Method Statement Outlines Actual Sea-Forces.
Restraint Provide on Boat Deck.
International Shipping Requirements
23
Module By Module Lifting Plans with each piece of
equipment detailed.
Overall Height critical for clearance over Ships Rails.
International Shipping Requirements
24
LIFTING - DUAL CRANE SEAFASTENING
240T
MODULE TRANSPORTER
MODULE
GRILLAGE
STOPPER (RESISTS SLIDING)
CLIPS (RESISTS SLIDING & UPLIFT
Road Transport Requirements
♦ Responsible for the transport of the modules from the local wharf to the construction site lay down yard.
♦ Has dimensional and tie down restrictions which govern grillage design with respect to placement of stiffeners.
♦ Provides road transport accelerations for review by Engineering. ♦ Details convoy movements for clearance by local authorities,
including the arrangement of police escorts, road blocks, temporary road houses, mechanics and road side pull overs.
25
Road Transport Requirements
26
EXAMPLE OF ARRANGEMENT OF ROAD TRANSPORT
4 FILE TRAILER PROVIDES WIDER BASE FOR BETTER SUPPORT AND STABILITY
8 AXLES 4 FILE TRAILER
TRESTLES
Road Transport Requirements
27
SAFELY DELIVERED TO SITE
4 FLOOR PIECES LIFTING LUGS
GRILLAGE
TRAILERS CAN BE LOWERED – MODULE STORED ON CONCRETE
BLOCKS – NO NEED FOR CRANAGE
Installation Requirements
♦ Design team to provide lay-down area for modules with sufficient bearing capacity for module storage.
♦ Installation contractors to be aware of special crane requirements and construction procedures for module construction.
♦ Must be prepared for free issued pre-module inspection & time requirements for bolting, unbolting, rotating and rigging of modules.
♦ Engineering to assist by providing safe access around lifting lugs for rigging teams.
28
Installation Requirements
29
Long Lead Item – 750T Crawler Crane – rented by EPCM for
use by SMP
Prior to the design team commencing work, a set of project guidelines needs to be formed to control the properties of the
modules.
30
Formation of Project Guidelines
♦ Module Envelope
31
IMPORTANT INFORMATION. MODULE DIMENSIONS PROVIDED TO ALL ENGINEERS AND DESIGNERS IN EASY TO REFERENCE FORMAT.
Formation of Project Guidelines
♦ Shipping Loads
32
Referenced from “Simplified Motion Criteria” – DNV – “Rules for Planning
& Executing Marine Operations”
IMPORTANT CRITERIA FOR STRUCTURAL DESIGN TEAM
Formation of Project Guidelines
♦ Road Transport Loads
33
DISTANCE BETWEEN TRAILER HARD POINTS IS CRITICAL FOR DESIGN TEAM
Overall Module Stability during Road Transport is the
responsibility of the Road Contractor.
IMPORTANT CRITERIA FOR STRUCTURAL DESIGN TEAM
Using these guidelines, the engineering team is able to arrange module split lines.
34
Designs were developed for all off-shore fabricated structures.
Resulted in four different “types” of
modules.
Type 1: Flat Pack Stacks (Floors & Trestles)
♦ Used for flat pack floors and trestles. ♦ Dimensions & connection locations needs to be similar ♦ Efficiency of transport is achieved as module does not have a
high percentage of transported air. ♦ SMP will be required to unbolt module to install each floor item. ♦ Requires detail consideration to how SMP will “lift & drop” into
place. Temporary support must be considered.
35
Type 1: Flat Pack Stacks (Floors & Trestles)
36
FLAT PACKED FLOORS TRESTLES TRANSPORT & GRILLAGE DRAWINGS PROVIDE
CONTRACTORS (AND OTHER MEMBERS OF EPCM TEAM) INFORMATION REGARDING MODULES
GRILLAGE
LIFTING POINT INFORMATION
Type 1: Flat Pack Stacks (Floors & Trestles)
37
SAFELY DELIVERED TO SITE
LIFTING LUGS
GRILLAGE
TRAILERS CAN BE LOWERED – MODULE STORED ON CONCRETE
BLOCKS – NO NEED FOR CRANAGE
LAYDOWN STORAGE INFORMATION
ROAD TRANSPORT CONFIGURATION
Type 1: Flat Pack Stacks (Floors & Trestles)
38
INSTALLATION OF TRESTLES
TEMPORARY STABILITY OF TRESTLES BY SMP
CONTRACTOR
TEMPORARY SUPPORTS ALLOW SMP TO LIFT & DROP MODULE – MINIMISES MEN WORKING AT HIGH NEAR
RIGGED LOADS
Type 2: Rotated Tower Structures
39
♦ Used for stair towers as well as Take Up Towers for conveyors. Can not be transported standing up as would be outside of the module envelopes.
♦ Requires two sets of four lifting lugs such that the module can be rotated in the fabrication yard and the site by SMP. Extra analysis required by structural engineers.
♦ Often requires horizontal braces to aid stability during transport. ♦ Lands directly onto concrete pedestals. ♦ Can be have internal stairs fully installed as to provide instant
access for construction.
Type 2: Rotated Tower Structures
40
LIFT 1: SUCCESSFUL LIFTING ONTO
VESSEL
GRILLAGE
LIFTING POINT INFORMATION
TRANSPORT & GRILLAGE DRAWINGS PROVIDE CONTRACTORS (AND
OTHER MEMBERS OF EPCM TEAM) INFORMATION REGARDING MODULES
ROTATION DETAILS PROVIDED TO CONTRACTORS BY ENGINEERING SHOWED LIFTING ASSUMPTIONS (EQUALISING SHEAVES) USED BY DESIGN TEAM FOR INSTALLATION.
Type 3: Large Modules with Mechanical Components
41
♦ Used for trusses, large screens, bins & hoppers. ♦ Shipped with handrail, grating, mechanical chute work and all
liners. Typical weight is between 150 T and 250 T. ♦ Modules can be installed onto of other modules and tolerances
can be provided to ease installation. ♦ Large Modules can be provided with 85T lifting lugs or
alternatively, lifting trunnions to minimise work at height on site.
Type 3: Large Modules with Mechanical Components
42
USE OF TRUNNIONS ALLOWS FOR RIGGING & RELEASING FROM GROUND LEVEL. THIS MINIMISES WORK AT HEIGHT
AND REDUCES RISK. HOWEVER THIS COMES AT A LARGE
FABRICATION COST.
LIFT ONTO SHIP
Type 3: Large Modules with Mechanical Components
43
UTILISATION OF LARGE CRANE FOR
MODULE INSTALLATION
MODULE INSTALLED INTO BUILDING WITH VENDOR SUPPLYIED
GATES ALREADY INSTALLED
Type 4: Large Modules with Vendor Items, Electrical Cabling and Piping – known as Smart Modules
44
♦ EPCM delivered to site commissioned, with gates installed as well as electrics and piping.
♦ Module could be dropped onto concrete pedestals and connected to services, minimising commissioning time on-site.
Type 4: Large Modules with Vendor Items, Electrical Cabling and Piping – known as Smart Modules
45
FABRICATION AT AMC
HENDERSON.
TRANSPORTED BY HEAVY LIFT VESSEL TO PORT HEDLAND.
INSTALLED & TRANSPORTED WITH
AUSTRALIAN VENDOR SUPPLYIED
COMPONENTS. POTENTIAL FOR
COMMISSIONING PRIOR TO ARRIVAL ON SITE.
VENDOR SUPPLIED
EQUIPMENT ALREADY INSTALLED
Summary – Part 1
46
♦ Complete logistics study prior to setting module split lines. ♦ Award all contracts early so that inputs can be made to the
design engineering effort. This results in less rework and more efficient grillage.
♦ Contractors to work with EPCM to establish criteria for transport forces, tie down methods and trailer configurations.
♦ Early information provides opportunity to build shipping grillage & temporary braces into the structures, minimising rework and resulting in cost savings for the client.
♦ The planning and creation of schedules needs to be realistic to the tasks performed with allowances for trial fitting and unforeseen transport delays.
Summary – Part 2
47
♦ Location of offshore fabrication is critical to successful project delivery and the providing of early information to the engineering design team. Issues include:
♦ Steel Material Grade ♦ Section Size & Availability ♦ Bolt and Weld Quality ♦ Paint Availability ♦ Providing this information to the design team early in the project
lifecycle avoids rework and delays for: ♦ Engineering ♦ Shop Detailing
♦ Fabrication ♦ On-site Construction
♦ Language Issues ♦ Cultural Issues ♦ Approach to Safety ♦ Efficient Transport Routes
Questions