danainfo ieeexplore.ieee.org+04651442

Upload: beni-akhirul-ramadhan

Post on 07-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 DanaInfo Ieeexplore.ieee.Org+04651442

    1/5

    A New Genetic Algorithm Method for Optimal

    Coordination of Overcurrent Relays in a Mixed

    Protection Scheme with Distance RelaysHossein.Askarian.Abyaneha

    [email protected]

    Somayeh.Sadat.Hashemi.Kamangara

    MSc. [email protected]

    Farzad.RazaviAssistant Professor

    [email protected]

    Reza.Mohammadi.Chabanlooa

    PhD. [email protected]

    AbstractSeveral optimal coordination of overcurrent relayshave been done in the past by using linear programming such assimplex, two-phase simplex and dual simplex and also intelligentoptimization techniques such as genetic algorithm (GA)techniques. In this paper, a powerful optimal coordinationmethod based on GA is introduced. The objective function (OF)is developed in a way that in addition to coordination ofovercurrent relays, the coordination of overcurrent and distancerelays is achieved. In other words, the novelty of the paper is themodification of the existing objective function of GA, by addinga new term to OF to fulfill the coordination of both overcurrentand distance relays. The method is applied to a power networksystem and from the obtained results it is revealed that the newmethod is efficient and accurate.

    Index TermsOvercurrent Relay, Distance Relay, OptimalCoordination, Genetic Algorithm.

    I. INTRODUCTIONOvercurrent (OC) and distance relays are commonly used

    for transmission and subtransmission protection systems [1].

    To consider comprehensive coordination, a distance relay

    with a distance one, an overcurrent relay with an overcurrentone and finally a distance relay with an overcurrent one when

    one of them is considered to be the main relay and the other isthe backup, must be coordinated.

    When both considered main and backup (M/B) relays aredistance types, the impedances of the three zones of relays are

    calculated considering all conditions of an interconnectednetwork such as connecting and disconnecting of generatorsand lines [2].

    For overcurrent relays the optimal coordination has been performed using linear programming techniques, includingsimplex [3], two-phase simplex [4] and dual simplex [5]

    methods. In reference [6] also, optimal solution is made by

    constraints only. The disadvantage of the above optimizationtechniques is that they are based on an initial guess and may be trapped in the local minimum values [7]. Intelligent

    optimization techniques such as genetic algorithm (GA) canadjust the setting of the relays without the mentioneddifficulties.

    aDepartment of Electrical Engineering, Amirkabir University of Technology,

    Tehran, Iran.b

    Department of Electrical Engineering, Tafresh University, Tafresh, Iran.

    In these methods the constraints are included in objectivefunction [7]. The optimal coordination in reference [8] has

    been done by a method based on GA and in reference [9] byan evolutionary algorithm. These methods have twoproblems. One of them is miscoordination and the other is not

    having the solution for relays with both discrete andcontinuous time setting multipliers (TSMs). In reference [7]the mentioned problems have been solved.

    In the cases that the distance relay is considered to be mainand the overcurrent one is the backup relay, it is necessary tofind the critical fault locations. The critical fault locations arethe positions when faults considers on those points, the

    discrimination time (t) between the backup and main relaysis minimum. The coordination is made based on theconstraints derived from the values of t for critical fault

    locations.In references [1] & [10] coordination of overcurrent,

    distance and circuit breaker failure (CBF) relays has beendone using linear programming techniques.

    In this paper a new optimal coordination method based onGA is introduced. The objective function (OF) is developed

    by adding a new term that is the constraint related to thecoordination of the distance and overcurrent relays when afault occurs at the critical locations.

    II. REVIEW OF RECENTLY DEVELOPED GA FOROPTIMAL OCRELAY COORDINATION

    GA like all other optimization methods needs initial values

    which are chosen randomly. TSMs of relays are the unknown

    quantities in the optimization problem. Therefore, the TSMs

    in respect to the number of relays are considered as the

    genomes of the chromosomes in GA. In other words, some

    TSMs sets, i.e. (TSM1, TSM2, TSM3, , TSMn), (TSM1,

    TSM2, TSM3, , TSMn), belonging to relay set (R1, R2,R3, , Rn) are initially randomly selected. The number of

    TSMs sets is referred as the population size. Then, after each

    iteration, the new TSMs sets belong to relays R1 to Rn are

    given to the algorithm. The process is terminated when the

    number of iterations becomes equal to the generation size [7].

    To evaluate the goodness of each chromosome, it is

    essential to define an OF. The purpose of optimization is to

    minimize the OF. The chromosomes are evaluated regarding

    the OF and the chromosomes which have more effectiveness

    will be used for producing new generation of chromosomes.

  • 8/6/2019 DanaInfo Ieeexplore.ieee.Org+04651442

    2/5

    Mutation in each iteration will cause the algorithm not to trap

    in local minimums.

    After a fixed number of generations, the process will be

    terminated. Increasing the number of generations will lead to

    the better solutions and on the other hand, will increase the

    run time. The required number of generation varies from

    system to system depending on the system complexity and

    the size of population [7].

    III. PROBLEM STATEMENTAs mentioned in section , relay coordination must be done

    for the cases below:

    1) Coordination of overcurrent relays with overcurrentones.

    2) Coordination of distance relays with distance ones.3) Coordination of distance relays with overcurrent ones.As mentioned in section II, the first one has been made in

    the frame of GA. In this paper, it is necessary to be done the

    optimal coordination in a way that all three cases above are

    satisfied. For the third case it is assumed that the distancerelay is the main relay and the overcurrent relay is the

    backup. This assumption is a routine protection scheme in

    power networks. In interconnected networks, an overcurrent

    relay can be the backup of some other distance relays.

    Therefore, TSMs of all overcurrent relays and the operating

    time the second zone of all distance relays must be

    determined for critical conditions. The critical condition is

    defined and shown in Fig. 1. An overcurrent relay is located

    at B and a distance one at M. The overcurrent relay is the

    backup of distance relay. When a fault occurs at F, the

    discrimination time between the operating time of overcurrent

    relay and that of the distance one is minimum. Therefore, theexpression below must be appointed at the critical fault

    location, F.

    ( ) CTItFt 2Zb > (1)

    Where ( )Ftb is the operating time of overcurrent relay atF, 2Zt is the operating time of the second zone of the distance

    relay and CTI is the coordination time interval.

    As mentioned above, coordination between overcurrent and

    distance relays must be made by adding a new constraint to

    OF in GA. The details of this method are described in section

    IV.

    IV.NEW METHODIn the new method, the OF is formulated as:

    ( )

    ( )2P

    1kkmbDISOCkmbDISOC3

    P

    1k

    2

    kmbkmb2

    N

    1i

    2i1

    2

    2

    22

    1

    1

    11

    tt

    tt

    tFO

    =

    =

    =

    +

    +

    = )(.

    (2)

    Where 321 ,, are the weighting factors, i is the number

    of overcurrent relays that changes from 1 to N, 1k is thenumber of main and backup overcurrent relays that changes

    from 1 to 1P , 2k is the number of mai distance and backup

    overcurrent relays changing from 1 to 2P , 1kmbt is the

    discrimination time between the main and backup overcurrent

    relays.2kmbDISOC

    t is the discrimination time between the

    main distance and backup overcurrent relays which isobtained from the equation below:

    CTIttt222 kmDISkbOCkmbDISOC= (3)

    Where 2kbOCt is the operating time of backup overcurrent

    relay for the fault at the end of the first zone of main distance

    relay(critical fault locations),2kmDIS

    t is the operating time of

    the second zone of main distance relay and CTI is the

    coordination time interval that is equal to 0.3(sec).Two first terms of (2) are the same as the OF in [7]. The

    third term is added to OF to fulfill the requirement ofovercurrent and distance relays. To describe the role of this

    new term, consider2kmbDISOC

    t to be positive, then the

    relative term is zero, however if2kmbDISOC

    t is negative the

    mentioned term will be2kmbDISOC

    3 t2 and obviously for

    positive values of 3 the new term will have great values.

    Then, based on a concept of the evaluation and selection parts

    of GA, those values that have more optimal OF values (lessvalue) in the chromosomes, are granted more opportunities toselect for the next iteration.

    The flowchart of new method is shown in Fig. 2. At first,after entering the network data, the impedances of the first,second and the third zones of distance relays are calculated.Then, the short circuit currents for the faults exactly close tothe circuit breaker (CB) of the main overcurrent relays andfor the faults at the end of the first zone of main distance

    Fig. 1. Critical fault location in coordination between overcurrent anddistance relays

  • 8/6/2019 DanaInfo Ieeexplore.ieee.Org+04651442

    3/5

    relays( critical fault locations) are calculated. After that, GA

    will start. The operating time of the second and third zones ofdistance relays are selected respectively 0.3(sec) and 0.6(sec)

    and1kmbi

    tt , and2kmbDISOC

    t are calculated using short

    circuit currents. The other steps of GA are described in

    section II and in [7].

    V. TEST CASEThe new method proposed in this paper, is applied to a

    power network shown in Fig. 3. This network consists of 6

    buses, 7 lines, 2 transformers and 2 generators. The

    information data of the network is given in Tables I, II and

    III. R (pu) and X (pu) are based on 100 MVA and 150 kV. It

    is assumed that all the lines are protected by both overcurrent

    and distance relays. All distance relays have moho

    characteristic.

    It should be noted that for finding the overcurrent relays

    operating times, a more common formula for approximatingthe relay characteristic is used [7, 11]:

    ( ) ( ) ( )

    +

    +

    +

    +=3

    3

    2

    210

    1M

    a

    1M

    a

    1M

    aa

    TSM

    t (4)

    Where M is the ratio of short circuit current ( scI ) to the

    pickup current ( bI ) of relay ( bsc IIM /= ), t is the relay

    operating time and ,...,,, 3210 aaaa are the scalar quantities

    and for overcurrent relays with normal inverse characteristicsthat are used in this paper, these quantities are [7]:

    0003199010a03644650a

    461290a579228a987721a

    4

    3

    2

    1

    0

    ..

    ...

    ===

    ==

    (5)

    It is also assumed that TSMs of the relays are discrete and

    TSMs vary from 0 to 1 in steps of 0.05.

    The control parameters of GA are listed in Table IV. To

    compose OF, the values of 321 ,, are mentioned asbelow:

    1001001 321 === ,, (6)

    TABLE ILINESINFORMATION OF SAMPLENETWORK

    Line R (pu) X (pu) V (kV)

    1 0.0018 0.0222 150

    2 0.0018 0.0222 150

    3 0.0018 0.02 150

    4 0.0022 0.02 150

    5 0.0022 0.02 150

    6 0.0018 0.02 150

    7 0.0022 0.0222 150

    TABLE IIGENERATORSINFORMATION OF SAMPLENETWORK

    GeneratorX (pu) V (kV)

    0.1 10

    21 kmbDISOCkmbittt ,,

    ( )

    ( )2

    P

    1k

    kmbDISOCkmbDISOC3

    P

    1k

    2

    kmbkmb2

    N

    1i

    2

    i1

    2

    2

    22

    1

    1

    11

    tt

    tt

    tOF

    =

    =

    =

    +

    += )(

    Evaluation

    Fig. 2. Flowchart of new method

    Fig. 3. Sample network

  • 8/6/2019 DanaInfo Ieeexplore.ieee.Org+04651442

    4/5

    TABLE IIITRANSFORMERSINFORMATION OF SAMPLENETWORK

    TransformerX (pu)

    0.02666

    By applying the GA with selected values, the output results

    for TSMs are obtained. These TSMs are given in Table V.

    The operating time of the second and third zones of distance

    relays are selected respectively 0.3(sec) and 0.6(sec).

    From the second column of Table V, it can be seen that the

    values of TSMs are small and they are in valid range, i.e.

    between 0.05 and 1.Discrimination time between M/B overcurrent relays and

    discrimination time between the main distance and backup

    overcurrent relays are given in Table VI. All1kmb

    t (sec) and

    2kmbDISOCt (sec) values are positive and most of them are

    small. That means, the relay settings are accurate, fit and havenot any miscoordination.

    TABLE IVCONTROL PARAMETERS OF GA

    GA Parameters Value

    Number of Generations 2500

    Size of population 100

    Initial Population Random

    Mutation 1

    TABLE VTSMS OF OVERCURRENT RELAYS

    Relay

    NumbersTSM

    1 0.1

    2 0.2

    3 0.15

    4 0.05

    5 0.05

    6 0.2

    7 0.1

    8 0.15

    9 0.05

    10 0.1

    11 0.15

    12 0.25

    13 0.05

    14 0.1

    TABLE VIDISCRIMINATION TIMES OF M/BRELAYS

    Main

    Relay

    Backup

    Relay(sec)

    1kmbt

    (sec)2kmbDISOC

    t14 1 0.6527 0.0000

    3 2 0.0024 0.2676

    4 3 0.1082 0.0016

    5 4 0.1000 0.0000

    6 5 0.0000 0.0000

    7 5 0.0000 0.0000

    1 6 0.0036 0.2122

    2 7 0.1702 0.1749

    8 7 0.2790 0.0024

    13 8 0.0030 0.0559

    8 9 0.0000 0.0000

    14 9 0.0000 0.0000

    9 10 0.0028 0.0000

    10 11 0.0039 0.0175

    11 12 0.0021 0.2044

    7 13 0.0000 0.0000

    6 14 0.2887 0.0000

    12 14 0.1561 0.2203

    2 1 0.1387 0.0000

    12 13 0.0110 0.0000

    VI. CONCLUSIONA new computer program for distance and overcurrent

    relay coordination based on GA has been developed. In theproposed method, the OF has been modified by adding a new

    term which presents the constraint for distance and

    overcurrent relay coordination. The computer program has

    been tested on a power system network. From the obtained

    results, it has been shown that the new method is successful

    and accurate.

    REFERENCES

    [1] L. G. Perez and A. J. Urdaneta, Optimal computation of distance relays

    second zone timing in a mixed protection scheme with directional relays,

    IEEE Trans. on Power Delivery, vol.16, no.3, pp.385-388, July 2001.

    [2] T. S. Sidhu , D. S. Baltazar, R. M. Palomino and M. S. Sachdev, Anew approach for calculating zone-2 setting of distance relays and its use in

    an adaptive protection system , IEEE Trans. on Power Delivery, vol. 19,

    no. 1, pp.70-77, January 2004.

    [3] A. J. Urdaneta, H. Resterpo, J. Sanchez and J. Fajardo, coordination of

    directional overcurrent relays timing using linear programming, IEEE

    Trans. on Power Delivery, vol. 11, no. 1, pp.122-129, January 1996.

    [4] B. Chattopadhyay, M. S. Sachdev, and T. S. Sidhu, An on-line relay

    coordination algorithm for adaptive protection using linear programming

    techniques, IEEE Trans. Power Delivery, vol. 11, no. 1, pp. 165173,

    January 1996.

    [5] H. Askarian. Abyaneh and R. Keyhani, Optimal co-ordination of

    overcurrent relays in power system by dual simplex method, in: Proc. 1995

    AUPEC Conf. , Perth, Australia, vol. 3, pp. 440445,1995.

  • 8/6/2019 DanaInfo Ieeexplore.ieee.Org+04651442

    5/5

    [6] H. Askarian. Abyaneh, M. Al-Dabbagh, H. K. Karegar, S. H. H Sadeghi

    and R. A. H. Khan, A new optimal approach for coordination of overcurrent

    relays in interconnected power systems, IEEE Trans. on Power Delivery,

    vol. 18, no. 2, April 2003.

    [7] F. Razavi, H. Askarian. Abyaneh, M. Al-Dabbagh, R. Mohammadi and

    H. Torkaman, A new comprehensive genetic algorithm method for

    overcurrent relays coordination,Electr .Power Syst. Res., May 2007.

    [8] C. W. So, K. K. Li, K. T. Lai, and K. Y. Fung, application of genetic

    algorithm for overcurrent relay coordination, in: Proc. 1997 IEE Conf.

    Developments in Power System Protection, pp. 6669, 1997.

    [9] C. W. So and K. K. Li, Time coordination method for power systemprotection by evolutionary algorithm,IEEE Trans. on Industry Applications,

    vol. 36, no. 5, pp. 1235-1240, September-October 2000.[10] L. G. Perez, A. J. Urdaneta, Optimal coordination of overcurrent

    relays considering definite time backup relays, IEEE Trans. on Power

    Delivery, vol.14, no.4, pp.1276-1284, October 1999.

    [11] H. K. Karegar, H. Askarian. Abyaneh, V. Ohis, M. Meshkin, Pre-processing of the optimal coordination of overcurrent relays, Electr .Power

    Syst.Res., June 2005.