data center pue- guide
DESCRIPTION
A Guide to measuring and optimizing PUE in your Data CenterTRANSCRIPT
All Rights Reserved Data Connections Inc. 2010
Data Center PUE
Where to Start,What to do first!
Data Connections Inc
All Rights Reserved Data Connections Inc. 2010
About PUEPower Usage Effectiveness (PUE)
Power Usage Effectiveness (PUE) is a standard developed by The Green Grid™ consortium to provide a clear answer to the primary issue surrounding energy efficiency within the data center which is how much power is devoted to driving the actual computing/IT components (servers, for example) versus the ancillary support elements such as cooling and lighting. The components of the PUE calculation look at the relationship between "Total Facility Power" (TFP) and "IT Equipment Power" (IEP). TFP is measured at the utility meter for the data center space and includes all of the components required to support the IT load.
At Data Connections, we can help you 1.Baseline your PUE, 2. Make incremental changes to optimize your data center and improve your
PUE.
All Rights Reserved Data Connections Inc. 2010
PUE Project Flow
STEP 1:Instrumentation for Baseline PUE
Step 2 Optimize: Low hanging fruit
Instrumentation output
Step 3 Optimize: Moderately Invasive
Optimization
Step 4 Optimize: Invasive Optimization
Step 5 Optimize: Disruptive Optimization
PUE by mouse click
All Rights Reserved Data Connections Inc. 2010
Minimum Instrumentation required for valid Baseline PUE
IT Load•This is usually the output of the PDU’s
Cooling Load•For CRAC’s this is the power to those CRAC’s and their condensers.•For CRAH’s this is the fan power plus the Chilled Water Energy used by the CRAH’s (involves BTU meters and kW/ton from the CHW plant)•For non‐traditional cooling we have to evaluate on a case by case basis
Load Losses•Loss across PDU’s (need input and output of PDU)•Loss across UPS’s (need input and output of UPS)•Loss across building transformer(s) (need input and output at xfmr)•Depending on the complexity of the DC, a & b can sometimes be combined so that all you need is PDU output and UPS input
Lighting load•This can be metered or calculated
Every data center is different, but this is the core of PUE.
All Rights Reserved Data Connections Inc. 2010
STEP 1:Instrumentation for Baseline PUE
Installed Instrumentation can be Integrated:
•BMI Integration•Other systems or dry contact points
All Rights Reserved Data Connections Inc. 2010
Our Preferred form of instrumentation is a Wireless Mesh Network
System SoftwareStack
Applications
1
802.15.4NetworkStack
2
Optional Path
Optimal Path
Wireless sensors are easy to install an usually do not require downtime.
If installing on PDU’s or other power devices, downtime of one side of the circuit is required.
All Rights Reserved Data Connections Inc. 2010
Sensor Network Components
All Rights Reserved Data Connections Inc. 2010
One Gateway Node serves multiple sensors
• SynapSense Wireless Network (SWN) to Ethernetconnection
• IP addressable
• Secure– Rijndael 128‐bit encryption, password protection, IP address filtering,
blocking features, hardened OS and stack
• External 5VDC Power Adapter, 110‐240VAC (50~60Hz) with battery backup
• Deployed in N+1 topology on top of rack
All Rights Reserved Data Connections Inc. 2010
ThermaNode™: Temperature/Humidity
Internal Sensed Data• Dew Point & Temperature
• Cold Aisle – Rack Top
External Sensed Data
• Up to 6 thermistors– Cold Aisle
• Middle
• Bottom
– Hot Aisle• Top
• Middle
• Bottom
– Under Raised Floor• Reference Temperature
8 Sense Points/ThermaNode
All Rights Reserved Data Connections Inc. 2010
PressureNode: Differential Air Pressure• Collects Air Pressure data and transmits to SWN
• 4 Energizer AA Lithium‐Iron
• Typically 1 per 500 sq ft
¼” hose with diffuser
All Rights Reserved Data Connections Inc. 2010
Instrumentation complete and Baseline PUE is captured
All Rights Reserved Data Connections Inc. 2010
Step 2: Begin Optimization starting with Low Hanging Fruit
Down time unlikely
• Blanking Panels
• Floor leaks
• Automated Floor Tiles
• CRAC Return Optimization
• Hot Air Removal and redirection
• Watch your PUE # drop!!
Simple, reversible, mobile
All Rights Reserved Data Connections Inc. 2010
Low Hanging Fruit‐ Easy installs, quick PUE results
Down time unlikely
• Blanking Panels‐ you know what these are!
• Floor leaks‐Fill Floor leaks and cut‐outs with Foam or Brush• Automated Floor Tiles
– Bring more cold air to hot spots
• CRAC Return Optimization– Send hot air to short cycling CRAC
• Hot Air Removal and redirection– Capture heat from hot areas and send to Starving CRAC
All Rights Reserved Data Connections Inc. 2010
Step 3 for greater resultsModerately Invasive Optimization
Down time possible
• Additional Instrumentation– Increase the amount of instrumentation at server inlet, Under floor pressure, CRAC/Systems monitoring,
• Under Floor blocking and redirection of Conditioned Air
• Networked Power Floor Tiles
Immediate results, reversible
All Rights Reserved Data Connections Inc. 2010
Step 3Moderately Invasive Optimization
Down time possible• Additional Instrumentation
– Increase the amount of instrumentation at server inlet, Under floor pressure, CRAC/Systems monitoring,
• Under Floor blocking and redirection of Conditioned Air • Networked Floor Tiles and Heat Removal
All Rights Reserved Data Connections Inc. 2010
Step 4 Invasive OptimizationDown time probable
• Optimize Cabinets for Heat Removal
• Adaptive Control of Conditioned Air Systems
• Aisle Containment
All Rights Reserved Data Connections Inc. 2010
Step 4:Invasive OptimizationDown time probable
• Optimize Cabinets for Heat Removal
All Rights Reserved Data Connections Inc. 2010
Step 4:Invasive OptimizationDown time probable
Adaptive Control of Conditioned Air Systems-•Regulate Fan Speed•Water Temp•Pressure
With Control
After ContainmentBaseline
All Rights Reserved Data Connections Inc. 2010
Cold Aisle Containment –Panels or Curtains
Step 4:Invasive OptimizationDown time probable
All Rights Reserved Data Connections Inc. 2010
Step 5 :Disruptive OptimizationPlan for Down time
• Clean up cabinet cabling
• Clean‐up of under floor cabling
• Change Cabinet placement
• Re‐design of layout
• Alternative Cooling!
All Rights Reserved Data Connections Inc. 2010
Step 5: Disruptive OptimizationPlan for Down time
• Clean up cabinet cabling
• Clean‐up of under floor cabling
• Change Cabinet placement
• Re‐design of layout
• Alternative Cooling!– Server Emersion Cooling
– CPUs operate reliably at 75° C, and hard drives are reliable at 45° C. Our coolant at 40°C will keep the hard drives below 45° C, and the CPUs below 62° C, a full 13° C cooler than normal. Coolant at 40° C requires little energy to keep at that temperature, unlike the typical method of using chilled water cooled to 10° C to then cool air.
All Rights Reserved Data Connections Inc. 2010
Contact Data Connections Inc
Thank you for viewing the PUE Guide!
For more information or to schedule an onsite visit:
Email : [email protected]
Or call: 704-893-2301