date of presentation: 23 april 2013 the presidency department of performance monitoring and...
TRANSCRIPT
Date of presentation: 23 April 2013
The Presidency The Presidency Department of Performance Monitoring and EvaluationDepartment of Performance Monitoring and Evaluation
Briefing to the Standing Committee on Appropriations on the Strategic Plan and Annual Performance Plan for the 2013/14 financial year
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Background Background During 2010/2011, PME unit was part of the Presidency vote focusing on
government-wide M&E frameworks and putting in place performance and delivery agreements related to the 12 priority outcomes
2011/2012 was first year for DPME to have own budget, its focus widened to include monitoring of the implementation of the delivery agreements and the following additional initiatives:
Management Performance Assessments of national and provincial departments
National Evaluation Policy Framework, national and provincial evaluation plans, and evaluations
Front-line Service Delivery Monitoring Programme
The Presidential Hotline (transferred to DPME from The Presidency)
Citizen-based Monitoring
22
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Background continued..Background continued.. In April 2012, we submitted a revised Strategic Plan, which took into account
the following: Additional mandate of managing the Presidential Hotline Place more emphasis and focus on evaluations (Cabinet approved a National
Evaluation Policy Framework on 23 November 2011) Effect improvements to the plan based on comments from Internal Auditors
and the Auditor General on our previous plan (including refinements of our outputs, indicators and targets)
Reflect further clarification of our mandates
Guided by the revised Strategic Plan we developed the 2013/14 APP
There have been no further substantial changes to our mandates since April 2012, so we have not submitted a revised strategic plan in 2013
33
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Overview of DPMEOverview of DPME
44
• Focus on outcomes and impacts of government work in priority areas• Plans for the 12 priority outcomes (delivery agreements)• Monitoring progress against the plans• Evaluating to inform improvements to programmes, policies, plans
• Focus on monitoring of experience of citizens when obtaining services• Presidential hotline• Unannounced visits , request improvement plans• Citizen-based monitoring
• Focus on quality of management practices in individual departments • Moderated self assessment • Drive a process of continuous improvement of management practices• Lead to improved government performance and service delivery
M&E of national priorities
Management performance M&E
M&E of front-line service delivery
Custodianship for M&E across government
• Develop capacity of national and provincial departments and municipalities to carry out M&E themselves
• Develop a management culture of continuous improvement based on M&E
• Address problems with data quality and information management• National Evaluation System
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
1. Programme 1: Administration Provide strategic leadership and management as well as administrative
support (Departmental Management, HR, Financial Management and IT services)
2. Programme 2: Outcomes monitoring and evaluation (OME) Co-ordination and management of the outcomes orientated performance
monitoring and evaluation system3. Programme 3: M&E Systems Coordination and Support
Creation of policy platform for the GWM&E system, ME capacity building, provision of data support to the department and clients
4. Programme 4: Public Sector Oversight (PSO) Performance monitoring of individual institutions , FSD, Management of the
Hotline and CBM
55
Main programmes Main programmes
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation 6
Programme Priorities 2013/14
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Key priorities 2013/14: Programme 1Key priorities 2013/14: Programme 1
Output Target Intended outcome
Service delivery improvement programme (SDIP)
Integrate areas of weaknesses identified through MPAT and audit findings in the SDIP and monitor on quarterly basis
Clean audit report and improved service delivery
Government-wide M&E IT guideline and support
Develop guidelines and conduct capacity building on M&E IT support
Good quality M&E IT systems
77
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Key priorities 2013/14: Programme 2Key priorities 2013/14: Programme 2Output Target Intended outcome
Monitoring of the implementation of the delivery agreements for the 12 outcomes
Monitor the implementation of outcomes and produce quarterly reports and briefing notes for Cabinet
12 outcomes achieved
Evaluations of major programmes
Evaluate all major programmes identified in the evaluation plan
Better programmes which achieve better impacts
Review of government performance
Produce 20 year review 20 year review provides nation with balanced assessment of progress since 1994
MTSF Translation of NDP into the 2014-2019 MTSF and delivery agreements
MTSF completed by April 2014, providing the first five-year building block of the NDP
88
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Key priorities 2013/14: Programme 2 continued…..Key priorities 2013/14: Programme 2 continued…..Output Target Intended outcome
Local government performance monitoring tool and reports of pilot on 10 municipalities
Municipal Assessment Tool tested, refined and memo on municipal assessment tool submitted to Cabinet by end of October 2013
Improved delivery of service to the citizens at local level
10 assessments (inclusive of pilots) of municipalities completed and reports produced and submitted to the municipalities by the end of March 2014
Improved data quality for outcomes reporting
Convene data forum meetings with sector departments to improve data quality on a quarterly basis
Enhanced credibility and reliability of data used to compile quarterly progress reports
Capacity building for evaluations
300 government staff completing at least one course
Capable staff to do evaluations
99
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Key priorities 2013/14: Programme 3Key priorities 2013/14: Programme 3Output Target Intended outcome
Whole of government M&E capacity building
Conduct a survey of various elements of M&E systems in national and provincial departments and develop 2 new or revised guidelines
Improved M&E capacity and systems in national and provincial government departments
M&E forums meetings held on a quarterly basis to coordinate key stakeholders
Improved coordination of M&E practice
Development Indicators
Develop and publish Development Indictors by March 2014
Inform the public about trends in key areas of development
1010
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Key priorities 2013/14: Programme 4Key priorities 2013/14: Programme 4Output Target Intended
outcome
Management performance Assessment
Conduct annual MPAT assessments and have at least 60% of national departments and 80% of provincial departments MPAT scores signed off by their HoDs by the end of the third quarter
Improved management practice
FSDM 120 new sites monitored with site monitoring reports captured on the web-based portal for the programme, by 31 March 2014
Improved services to citizens
10 case studies produced and published on FSDM practices, by 31 March 2014
FSDM annual findings report submitted to Cabinet by end of the financial year
50% of service delivery sites which have been visited at least twice have an improvement in scores for a least two of the eight assessment areas by end of March 2014
1111
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Key priorities 2013/14: Programme 4 cont.…Key priorities 2013/14: Programme 4 cont.…Output Target Intended outcome
Citizen based monitoring
Citizen based monitoring piloted in 3 departments with six-monthly progress reports on the implementation signed off by the programme manager
Government account to the citizens on the quality of services provided them
Presidential Hotline performance improvement programme
Develop and implement Improvement plan implemented as per timeframes
Improved rate of resolution of citizens
1212
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation 13
Resources overview
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
MTEF Budget AllocationMTEF Budget Allocation
The Department requested an increased budget, particularly to increase its capacity to monitor municipalities
However, in the context of a rising budget deficit and the on-going global economic problems, Cabinet decided in 2012 that, with a few exceptions, departments’ baseline MTEF budgets would have to decrease by 1%, 2% and 3% respectively over the MTEF
In addition, Cabinet decided that there must be limits on increases in personnel budgets – this means that the department’s personnel budget has been capped over the MTEF and the department may not allocate more money to personnel beyond the MTEF baseline amounts for personnel
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
CompensationCompensation
At the end of the 2012/13 financial year the department had 197 funded posts of which 173 were filled (vacancy rate was 12% (24 posts) at the end of 2012/13). Reasons include: Normal staff turnover of 8% (14 people left the department) Time taken to complete compulsory pre-employment screening (2 to 3
months delay) Delay in DPSA directive on implementing PSCBC resolution 1 of 2012
related to salary levels 9/10 and 11/12 Posts created to capacitate HoD assessment unit not filled (3 posts) –
awaiting approval of policy by Minister for Public Service and Administration
1515
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Compensation continued ….Compensation continued ….
All but 2 of the 208 funded posts for 2013/14 have been advertised and are in various stages of being filled (the other 2 are funded from December 2013 and will be advertised in July 2013)
During the 2012 MTEC planning cycle we calculated that we would need to increase to 236 posts over the MTEF
However, given the reduction in baselines explained earlier, we have only been able to fund an increase in posts from 197 in 2012/13 to 214 over the MTEF
This will have impact on the following areas in particular: Number of municipal assessments carried out Number of evaluations conducted or supported
1616
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Goods and servicesGoods and services
Main expenditure items:Professional services (R22m for 2014/15)
Evaluations (R12m for independent evaluators. Skills required vary depending on evaluation topics – not possible to employ on a full-time basis. International good practice to have independent evaluators.)
M&E capacity building (R5m for conducting surveys, training providers) Internal Audit (R1.7m for co-sourced internal audit expertise which is not
efficient for a small department to recruit on a full-time basis)Computer services (R15.7m)
SITA - Hotline call centre (12m) ICT Services (SITA) and annual software licences (R3.5m)
Travel and subsistence (R10m)
1717
The Presidency: Department of Performance Monitoring and EvaluationThe Presidency: Department of Performance Monitoring and Evaluation
Expenditure on Capital AssetsExpenditure on Capital Assets
Department required significant capital expenditure in 2012/13 and 2013/14 to establish own ICT system
Reduced expenditure over the rest of the MTEF relates to maintenance of ICT system, replacement of equipment and improvements to PoA, MPAT, MAT and FSD systems
1818
THANK YOU!