FORM FHWA 17-348 (12/2007) U.S. DEPARTMENT OF TRANSPORTATION FEDERAL HIGHWAY ADMINISTRATION Western Federal Lands Highway Division 610 E. 5 th St. Vancouver, Washington 98661 FP-03 109.01 Date Stamp (a) Project Name: Project Number: (b) Item Number: Item Description: (c) Date work performed: Copy Stamp Daily Record Of Miscellaneous Items (f) Calculations*: (g) Supporting sketch and details*: Summary of Quantities (d) Location: (e) Measured quantity: *Attach additional sheets if necessary. Total Quantity: Unit of Measurement: (h) Name of person measuring work: FHWA Use Only (i) Interim Measurement Final Measurement Verified By: Construction Inspector I certify the above measurements and calculations are correct and the total quantity is subject to direct payment for the item identified. Approved Entered To Record Checked By: (j) Contractor Representative FHWA Representative Date: 40101 Superpave Hot Asphalt Concrete Pavement 35+840 to 34+338 (plus 3 loads for turnouts): 1187.47 t Lot 2 See the following attachments: (a) daily mass record WFLHD 422M (b) street delivery report, spread report WFLHD 434 (c) ticket check MS Excel spreadsheet see above stations 1187.47 t 1187.5 t Page 77 of 134

Upload: vanthuan

Post on 04-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

FORM FHWA 17-348 (12/2007) U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION Western Federal Lands Highway Division 610 E. 5th St. Vancouver, Washington 98661 FP-03 109.01

Date Stamp

(a) Project Name: Project Number:

(b) Item Number: Item Description:

(c) Date work performed:

Copy Stamp

Daily Record Of Miscellaneous Items (f) Calculations*:

(g) Supporting sketch and details*:

Summary of Quantities (d) Location: (e) Measured quantity:

*Attach additional sheets if necessary. Total Quantity: Unit of Measurement: (h) Name of person measuring work:

FHWA Use Only(i) Interim Measurement Final Measurement Verified By:

Construction Inspector

I certify the above measurements and calculations are correct and the total quantity is subject to direct payment for the item identified. Approved Entered To Record

Checked By:(j) Contractor Representative FHWA Representative Date:

40101Superpave Hot Asphalt Concrete Pavement

35+840 to 34+338 (plus 3 loads for turnouts): 1187.47 t

Lot 2

See the following attachments:(a) daily mass record WFLHD 422M(b) street delivery report, spread report WFLHD 434(c) ticket check MS Excel spreadsheet

see above stations 1187.47 t

1187.5

t

Page 77 of 134

Page 78 of 134

Page 79 of 134

Page 80 of 134

FORM FHWA 17-348 (12/2007) U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION Western Federal Lands Highway Division 610 E. 5th St. Vancouver, Washington 98661 FP-03 109.01

Date Stamp

(a) Project Name: Project Number:

(b) Item Number: Item Description:

(c) Date work performed:

Copy Stamp

Daily Record Of Miscellaneous Items (f) Calculations*:

(g) Supporting sketch and details*:

Summary of Quantities (d) Location: (e) Measured quantity:

*Attach additional sheets if necessary. Total Quantity: Unit of Measurement: (h) Name of person measuring work:

FHWA Use Only(i) Interim Measurement Final Measurement Verified By:

Construction Inspector

I certify the above measurements and calculations are correct and the total quantity is subject to direct payment for the item identified. Approved Entered To Record

Checked By:(j) Contractor Representative FHWA Representative Date:

40105Antistrip Additive

9/11 = 26.4 tons9/14 = 28.7 tons9/16 = 27.2 tons

= 82.3 tons total

8,700.97 tons of Superpave Pavement Placed, @ 5.5% AC mix design = 8,222.41 tons of rockAntistrip Additive added at 1% per weight of rock = 82.2 tons

Invoice totals verified by weight of total tons placed

See attachments

82.3

82.3

t

Page 81 of 134

Page 82 of 134

Page 83 of 134

Page 84 of 134

FORM FHWA 17-348 (12/2007) U.S. DEPARTMENT OF TRANSPORTATION

FEDERAL HIGHWAY ADMINISTRATION Western Federal Lands Highway Division 610 E. 5th St. Vancouver, Washington 98661 FP-03 109.01

Date Stamp

(a) Project Name: Project Number:

(b) Item Number: Item Description:

(c) Date work performed:

Copy Stamp

Daily Record Of Miscellaneous Items (f) Calculations*:

(g) Supporting sketch and details*:

Summary of Quantities (d) Location: (e) Measured quantity:

*Attach additional sheets if necessary. Total Quantity: Unit of Measurement: (h) Name of person measuring work:

FHWA Use Only(i) Interim Measurement Final Measurement Verified By:

Construction Inspector

I certify the above measurements and calculations are correct and the total quantity is subject to direct payment for the item identified. Approved Entered To Record

Checked By:(j) Contractor Representative FHWA Representative Date:

Be sure to check the contractors application rate

41201Tack Coat

Attached Ticket: 5.09 tons = 5.1 tons

Station 20+05 to Station 121+84 = 10,179 feet @ 12' wide = 122,148 SQ FT = 13572 SYTack applied at 0.09 gal/SY = 1221.48 gal @ 240 gal/ton = 5.0895 tons

Weigh ticket matches measured verified by measured calculations

See attachments