davao city expressway projecteia.emb.gov.ph/wp-content/uploads/2019/09/final-project...highway),...
TRANSCRIPT
1
DAVAO CITY EXPRESSWAY PROJECT
PROJECT DESCRIPTION
Davao City Expressway Project
1.1 PROJECT LOCATION AND AREA
Background
The Build! Build! Build! Program is the administration’s comprehensive infrastructure
development program launched in April 2017 under the ten-point Socio-Economic Agenda
that outlines the reforms of the government with the goal of economic growth, job creation,
and improvement in the lives of the Filipinos. Among the reforms is to accelerate annual
infrastructure spending with public-private partnership playing a key role. The program
identified 70 infrastructure flagship projects and one of those is Davao Expressway Project.
Location
According to the proposed plan of the Philippine Side, the proposed Davao City Expressway
Project is divided into three phases. Phase 1 is located within Davao City and extends along
the Davao River, which is an elevated viaduct and generally in the north-south direction. Phase
2 is located in the north of Davao City and close to the edge of the city and extends along the
existing Carlos P. Garcia National Highway Phase 2 also is an elevated viaduct and in the
east-west direction. Phase 3 is located in the western mountainous area of Davao City. Due
to the low alignment indicator and long detour of the mountain section of the existing AH26
(Carlos P. Garcia National Highway), the plan of elevating the alignment along the existing
road cannot be adopted. Phase 3 is entirely newly built and mainly in the form of subgrade
and tunnel.
According to the structure of road network of Davao City and the regional location of the
Project, Phase 1 is located within Davao City. The traffic flow is mainly intermediate-range and
long-range traffic flow in Davao City. The main function of Phase 1 is to connect with several
existing major traffic arteries in Davao City, quickly relieve the traffic flow of existing traffic
arteries, improve the traffic capacity of road network of Davao City, and relieve the traffic
pressure in Davao City
2
DAVAO CITY EXPRESSWAY PROJECT
Figure 1: Map Davao City Expressway Project
Phase 2 and Phase 3 mainly extend along the existing AH26 (Carlos P. Garcia National
Highway), which is the national main road connecting Tagum – Panabo-Davao-Lungsod Bg
Digos – Lungsod Ng General Santos. AH26 is currently mainly responsible for transit traffic.
Davao City Bypass Road is located in the north of AH26 and is a planned transit passage in
the north of Davao City. At present, the design of construction drawing of Davao City Bypass
Road has been completed. The Project is about to be implemented. Upon completion of the
Project, it will attract most of the transit vehicles, while the existing AH26 is mainly responsible
for traffic flow around Davao City. The Project is equivalent to the expressway of AH26 Davao
section. After the completion of the Project, the traffic flow will mainly be the traffic flow around
Davao City
Impact Area
The direct impact areas (DIA) which will cover the ROW of the project will have an approximate
total length of 6.7 kilometers. In terms of the socio-economic impacts, the DIA are the host
barangays as project beneficiaries for employment, livelihood, relocation, taxes, and other
benefits from the decongestion of the roads. Presented above are the Barangays directly
affected by the Project alignment - Phase 1 consists of Barangays Ma-a, 8-A, 5-A, 2-A, 40-
D and 76-A (Bucana); Phase 2 are Dumoy, Bago Galera, Matina Pangi, Catalunan
Grande, Catalunan Pequeno and Talomo Proper; Phase 3 Buhangin Proper, Cabantian,
Comunal, Sasa and Panacan .
3
DAVAO CITY EXPRESSWAY PROJECT
1.1 PROJECT RATIONALE
Davao City is the Premier Socio-economic, Investment, Tourism Center in Mindanao, East
ASEAN Growth Area (EAGA) and the Asia-Pacific Region propelled by enlightened leaders
and empowered citizenry and committed to sustainable social growth and development, and
economic growth without compromising the environment under the guidance of Divine
Providence.
Today, the City of Davao looks forward to accelerating further its economic development. The
lure of business opportunities with the fast-rising population, along with its agricultural and
industrial potentialities, has continuously brought ever increasing number of adventurous and
equally ambitious investors as well as men and women of every profession, art and trade.
Together with the Lumads of Davao City – the Ubo Manobo, Ata Manobo, Bagobo-Tagabawa,
Bagobo-K'lata, Matigsalog and Kalagan and the other tribes from other part of Mindanao -
Maguindanao, Tausug, Maranao and Sama, the Tagalogs, Pampangos, Ilocanos and
Visayans have found grounds in the city wherein to start or renew their base in life. They have
all molded to become Davaoweños and Davao City has earned the honor and is justifiably
proud to be called “the Melting Pot of the Philippines”.
Davao City operates on a flexible market-oriented economy where the private investments are
encouraged by the government to address the current needs of the population. The resilience
of the government continually opens doors of opportunities to investors from micro to large-
scale enterprises.
Records show that Davao City has a steadily growing economy due to various factors that
contribute to the influx of investments such as the provision of infrastructure support and
utilities, investment incentives, land area commensurate to the needs of investors, and human
resource to serve the employment requirements of establishments and sound peace and order
situation.
Revenue sources of Davao City are from establishments and activities ranging from micro to
large-scale enterprises covering agriculture, commerce and trade, industry and tourism.
These major sectors of the economy operate by pouring investments that continue to grow
annually in number and capitalization.
Having an annual growth rate of 15.98 percent from 2006 to 2010 in terms of capitalization of
micro, small, medium and large-scale establishments or a total of P 182 billion in 2010 from P
109.0 billion in 2006, revenues also proved to increase annually. Commerce and trade posted
an annual growth rate of 3.81 percent in revenues for the same period while industries
registered 6.12 percent.
Business Bureau recorded the number of establishments in 2006 at 24,638 which rose to
29,542 in 2010. The annual growth rate was computed at 4.70 percent which covers all
categories in terms of capitalization.
The implication of the continual pouring in of investments to the economy of the City highlights
the healthy business environment where revenues are sure to come in.
4
DAVAO CITY EXPRESSWAY PROJECT
1.3 PROJECT ALTERNATIVES
Selection of Specifications for Proposed Project
Phase 1 and Phase 2 of the Project are located within Davao City, and Phase 3 is located in
the suburbs of Davao City. The main service object of the Project is vehicles in Davao City
and surrounding towns, so the Project should be defined as an urban road.
The main specification adopted for highway bridge projects in Philippines is Design
Guidelines, Criteria and Specifications for Public Works and Highways (DGCS). There is no
clear distinction between highways and urban roads in the specification. Moreover, the
technical indicators of horizontal alignment and vertical alignment stipulated in Philippine
specifications are generally lower than those stipulated in Chinese specifications. Therefore,
it is suggested that the technical indicators of horizontal alignment and vertical alignment of
the Project should be subject to Chinese specifications, and Philippine specifications should
be adopted in case of conflict with Philippine specifications.
Most of the Project is located within Davao City. Phase 1 passes through the urban area, with
dense buildings. For Phase 2, an elevated viaduct is built along the existing road with limited
width and adjacent to buildings on both sides. By comparing the Philippine specifications with
the Chinese specifications, the cross-section indicators adopted in the Philippine
specifications are generally lower than that stipulated in the Chinese specifications. If the
Chinese specifications are adopted, it will result in larger quantities of demolition. Considering
actual situations in Philippines, the demolition is more difficult. Therefore, it is suggested that
the cross-section indicators should be subject to the Philippine specifications on the premise
of ensuring traffic safety, and the indicators unspecified in the Philippine specifications should
be subject to the Chinese specifications.
Determination of Grade of Proposed Highway
According to the proposed plan of the Philippine Side, the proposed Davao City Expressway
Project is divided into three phases. Phase 1 is located within Davao City and extends along
the Davao River, which is an elevated viaduct and generally in the north-south direction. Phase
2 is located in the north of Davao City and close to the edge of the city and extends along the
existing Carlos P. Garcia National Highway). Phase 2 also is an elevated viaduct and in the
east-west direction. Phase 3 is located in the western mountainous area of Davao City. Due
to the low alignment indicator and long detour of the mountain section of the existing AH26
(Carlos P. Garcia National Highway)), the plan of elevating the alignment along the existing
road cannot be adopted. Phase 3 is entirely newly built and mainly in the form of subgrade
and tunnel.
In recent years, with the development of economy of Davao City, the traffic flow has gradually
increased, the existing traffic network is under greater pressure, the traffic capacity of the
roads has decreased, and the traffic congestion is more serious, which have seriously
restricted the further development of economy and society of Davao City. The construction
5
DAVAO CITY EXPRESSWAY PROJECT
of the Project is of great significance to the development of economy and society of
Davao City, Philippines. The implementation of the Project can effectively alleviate the
increasingly serious traffic congestion in Davao City and has important strategic
significance for promoting the further development of economy and society of Davao
City.
According to the structure of road network of Davao City and the regional location of the
Project, Phase 1 is located within Davao City. The traffic flow is mainly intermediate-range and
long-range traffic flow in Davao City. The main function of Phase 1 is to connect with several
existing major traffic arteries in Davao City, quickly relieve the traffic flow of existing traffic
arteries, improve the traffic capacity of road network of Davao City, and relieve the traffic
pressure in Davao City. Therefore, it is suggested that Phase 1 should be constructed
according to the standards of urban expressway.
Phase 2 and Phase 3 mainly extend along the existing AH26 (Carlos P. Garcia National
Highway), which is the national main road connecting Tagum – Panabo – Davao – Lungsod
Ng Digos - Lungsod Ng General Santos. AH26 is currently mainly responsible for transit traffic.
Davao City Bypass Road is located in the north of AH26 and is a planned transit passage in
the north of Davao City. At present, the design of construction drawing of Davao City Bypass
Road has been completed. The Project is about to be implemented. Upon completion of the
Project, it will attract most of the transit vehicles, while the existing AH26 is mainly responsible
for traffic flow around Davao City. The Project is equivalent to the expressway of AH26 Davao
section. After the completion of the Project, the traffic flow will mainly be the traffic flow around
Davao City. Therefore, it is suggested that Phase 2 and Phase 3 should be constructed
according to the standards of urban expressway.
Determination of Number of Lanes of Proposed Highway
The service level of basic road sections in 2046 calculated according to the two-way four-lane
plan is shown in Table 1.
Table 1: Calculation Results of Service Level for Road Section of the Project
Road Section I
Traffic
volume in
2046
Number of
lanes
V/C
value
Classification
of service
level
Starting point: Davao-Cotabato
Road 34104
Two-way
four-lane 0.41 Level B
Davao-Cotabato Road - Ma-a
Bridge 44507
Two-way
four-lane 0.53 Level C
Ending point: Ma-a Bridge 51964 Two-way
four-lane 0.62 Level C
6
DAVAO CITY EXPRESSWAY PROJECT
Mean of the road section 45057 Two-way
four-lane 0.54 Level C
Road Section II
Traffic
volume in
2046
Number of
lanes
V/C
value
Classification
of service
level
Starting point: Cargo Terminal
Access Road 70973
Two-way
four-lane 0.85 Level D
Cargo Terminal Access Road-
Buhangin-Lapanday Road 76750
Two-way
four-lane 0.92 Level E
Ending point: Buhangin-
Lapanday Road 55051
Two-way
four-lane 0.66 Level C
Mean of the road section 68830 Two-way
four-lane 0.82 Level D
Road Section III
Traffic
volume in
2046
Number of
lanes
V/C
value
Classification
of service
level
Starting point: Catalunan
Grande Road 41020
Two-way
four-lane 0.49 Level B
Catalunan Grande Road-
Davao-Bukidnon Road 36308
Two-way
four-lane 0.43 Level B
Ending point: Davao-Bukidnon
Road 37585
Two-way
four-lane 0.45 Level B
Mean of the road section 39050 Two-way
four-lane 0.47 Level B
According to calculation results of the service level (2046) of basic road section, We draw the
following conclusions: the predicated service level of road section in 2046 by adopting two-
way four-lane plan is Level C/D as a whole, indicating that the technical standards of two-way
four-lane in the Project is more reasonable
Determination of Carriageway Width
To sum up, according to Philippine specification, considering the passage of large vehicles,
the ideal lane width should be 3.65 m. According to provisions of Chinese specifications, the
carriageway width of large vehicle, truck or mixed lane and car lane are 3.75 m and 3.5 m
respectively for urban expressways with design speeds of 80 km/h and 60 km/h. Considering
that the Project is located within Davao City, in order to reduce the quantities of demolition, it
is suggested that the carriageway width of the Project should be 3.65 m stipulated in
Philippine specification.
7
DAVAO CITY EXPRESSWAY PROJECT
Determination of Width of Hard Shoulder
1.) Table 2 of the Philippine specification - Design Guidelines, Criteria and Standards
Volume 4, Highway Design (2015) stipulates that when the average daily traffic volume
is greater than 2,000, the ideal hard shoulder width should be 3.0 m.
Table 2: Design Standards for Highways at All Levels in Philippine Specification
2.) For the width of hard shoulder, Section 3.7.3 of the Philippine specification - Design
Guidelines, Criteria and Standards Volume 4, Highway Design (2015) stipulates that
the minimum width of hard shoulder for highways at all levels is 1.0 m, but it is
better to be wider. If the shoulder is occupied by vehicles pulling animals, vehicles
carrying animals or pedestrians, a larger width should be considered. When the
average daily traffic volume is more than 1,250 vehicles, the minimum width of hard
shoulder should be 1.5 m.
Determination of Width Earth Shoulder
The Philippine specification stipulates that the newly paved pavement must have at least 3-
foot-wide earth shoulder or aggregate shoulder. However, considering that most sections of
the Project are located within Davao City and elevated viaducts are constructed along the
existing roads, it is suggested that 0.50 m wide concrete guardrail should be provided on the
outer side of the elevated road section of the Project and 1.00 m wide earth shoulder should
be provided on the subgrade section with less restrictions on ROW acquisition and demolition
in the outer suburbs to reduce the scale of ROW acquisition and demolition.
Road Design
The Project is located in Davao City and its suburbs in Philippines. The buildings on both sides
of the road in the urban section are dense, and the quantities of demolition are large. The
elevated viaduct is the main part of the urban section, which reduces the quantities of
demolition. The towns in the suburb section have just developed and there are a large number
of residential areas and factory buildings under construction. The vegetation coverage
8
DAVAO CITY EXPRESSWAY PROJECT
in the suburb section is high and the ecological environment is good. The overall
design idea of the Project is to strive to build the Project into an environmental and
ecological road, a human-oriented landscape road integrating nature and humanity,
and an economic and reasonable, safe operation and resource-saving benefit road.
Selection of plans for Davao Tunnel - ending point section (Alignment B and Alignment B1)
According to different ending point connection positions, Alignment B Plan and Alignment B1
Plan are proposed for the ending point section to compare and select the ending point plans.
1. Discussions on Alignment Plans
Alignment B Plan: After passing through the mountain in the form of 260 m long tunnel, the
alignment will extend to the west and cross Matina River. The alignment will cross Catalunan
Grande Road near Catalunan Grande and then extend to the southwest. The alignment will
cross Davao – Bukidnon National Highway on the south side of Catalunan Pequeno and then
continue to extend to the southwest. The ending point of the alignment will be near Dumoy. A
T-shaped junction interchange will be constructed to connect with Davao – Cotabato National
Highway. The alignment will be 10.436 km long.
Alignment B1 Plan: After passing through the mountain in the form of 260 m long tunnel, the
alignment will extend to the southwest. The alignment will cross Matina River and Matina
Pangi Road near Matina Pangi and then continue to extend to the southwest. The ending point
of the alignment will be near Bangkal and connected to Davao – Cotabato National Highway.
At the same time, a single trumpet interchange will be constructed to connect to MacArthur
Highway. The alignment will be 5.066 km long.
9
DAVAO CITY EXPRESSWAY PROJECT
Figure 2: Comparison and Selection of Alignment B Plan and Alignment B1 Plan
2. Comparison and selection of Alignment Plans
The main control factors affecting alignment layout in the section include Carlos P. Garcia
National Highway, Davao – Cotabato National Highway, MacArthur Highway, Davao –
Bukidnon National Highway, Matina River, Extension of Diversion Road, The Resort, etc.
Table 4: Comparison and Selection of Plans for Davao Tunnel - Ending Point Section
(Alignment B and Alignment B1)
Items Alignment B Alignment B1
Characteristics
Pass Catalunan Pequeno
Village
Connect to the diversion
road of Davao City near
Dumoy
Pass Matina Pangi Village
Connect to the diversion
road of Davao City in
Bangkal
Project
scale
Alignment
length
(km)
10.436 5.066
Subgrade
length
(km)
5.856 1.531
10
DAVAO CITY EXPRESSWAY PROJECT
Elevated
viaduct
length
(km)
4.580 3.535
Technical
comparison
Connection
with the City
Pass the outer suburbs of
Davao City
The ending point is far from
Downtown Davao
Pass the suburbs of
Davao City
The ending point is close
to Downtown Davao
Connection
with road
network
Consistent with the planned
alignment of Extension of
Diversion Road
Comply with the
requirements of the overall
road network planning of
Davao City
Inconsistent with the
planned alignment of
Extension of Diversion
Road
An interchange with 5 road
crossings will be
constructed in Bangkal,
and the connection of the
Project will aggravate
traffic congestion there
Construction
difficulty
Construction conditions for
interchange in Dumoy are
relatively simple
Overall project construction
is less difficult
Construction conditions for
interchange in Bangkal are
complicated
It is difficult to keep the
traffic during the
construction of
interchange and has great
social impact
Traffic
volume
attraction
Radiate the surrounding
towns in the outer suburbs
of Davao City and effectively
attract traffic from the
surrounding towns
Save time for towns along
Davao-Bukidnon National
Highway to Davao City
Help the development of the
surrounding areas of Davao
City and effectively expand
the future development
space of Davao City
The same spaces
(corridor) as the diversion
road of Davao City, with a
small radiation range
Poor attraction to
surrounding traffic
Economic comparison
Direct
engineering
cost
New elevated viaducts and
subgrades are large in
scale, with slightly higher
construction cost
New elevated viaducts
and subgrades are small
in scale, with low
construction cost
RMB 1136.63 million RMB 707.22 million
Compensation
for demolition
The alignment covers a
large area
The demolition of houses is
relatively scattered
The alignment covers a
small area
The demolition of houses
for interchange in Bangkal
11
DAVAO CITY EXPRESSWAY PROJECT
is concentrated and the
coordination of demolition
is difficult
Comparison conclusion Recommended Alternative plan
PROJECT COMPONENT
The following will be the components of the proposed project:
Interchanges
No. Interchange
name
Crossing
chainage
Spacing
(km)
Interchange
Type
Intersection
Mode
Name and grade
of crossed road Remarks
1
Davao –
Cotabato Road
Interchange
AK1+560 Diamond interchange
Overpass
on main
alignment
Davao – Cotabato
Road.
Urban main road
2 Gold Steet
Interchange AK4+100 2.54
Diamond interchange
Overpass
on main
alignment
Gold Street
Urban Secondary
Main Road
3
Panacan
Crossing
Interchange
BK0+000 - Type T
interchange
Overpass
below main
alignment
Davao-Agusan
National Highway
National Main
Road
4 Davao Airport
Interchange BK2+500 2.5
Diamond interchange
Overpass
on main
alignment
Airport Linking
Road
5 Mandug Road
Interchange BK6+900 4.400
Diamond interchange
Overpass
on main
alignment
Mandug Road
Local Road
6 Ma-a
Interchange BK9+555 2.655
Type T interchange
Overpass
below main
alignment
Davao
Expressway
Urban Main Road
7
Catalunan
Grande
Interchange
BK15+879 6.324 Diamond interchange
Overpass
below main
alignment
Catalunan Grande
Road
Local roads
8
Davao-Bukidnon
Road
Interchange
BK18+150 2.271
Partial
cloverleaf interchange
Overpass
on main
alignment
Davao-Bukidnon
National Highway
National Main
Road
12
DAVAO CITY EXPRESSWAY PROJECT
9 Dumoy
Interchange
BK22+436.
395 4.286
Type T
interchange
Overpass
on main
alignment
Davao-Cotabato
National Highway
National Main
Road
Figure 3: Davao – Cotabato Road Interchange Scheme
Figure 4: Panacan Crossing Interchange Scheme
13
DAVAO CITY EXPRESSWAY PROJECT
Figure 5: Davao Airport Interchange Scheme
Figure 6: Mandug Road Interchange Scheme
14
DAVAO CITY EXPRESSWAY PROJECT
Figure 7: Ma-a Interchange Scheme
Figure 8: Catalunan Grande Interchange Scheme
15
DAVAO CITY EXPRESSWAY PROJECT
Figure 9: Davao – Bukidnon Road Interchange Scheme
Figure 10: Dumoy Interchange Scheme
Structures
a) Viaducts
Construction scheme of PSCG-I beam elevated viaduct
In the Project, other than the bridge crossing Davao River which involves offshore
construction, other elevated viaducts are all land-based bridges. The superstructure shall be
16
DAVAO CITY EXPRESSWAY PROJECT
constructed as PSCG-I beam, and the substructure shall be constructed as the single-column
large cantilever capping beam pier, the large-spacing double-column or multicolumn large
capping beam pier, and the conventional whole-frame double-column pier.
b) Bridge
Bridge design scheme
For pre-stressed concrete continuous box girder bridge crossing Davao River with the
(45+80+45) m span, the design scheme is as follows.
1. Superstructure
The straight web and inclined web can be used for cast-in-place box girder section, both of
which are convenient for construction and mature and reliable in technology. The width of the
main girder in the Project is 19.1 m. Compared with the box girder with straight web, the
inclined web structure can reduce the width of the bottom plate of the box girder so as to
reduce the self-weight of the structure and make the stress on the structure more reasonable.
At the same time, due to the low height of the elevated viaduct and the reduction of the width
of the bottom plate, the width of the pier is effectively reduced, making the upper and lower
parts of the bridge look more harmonious and beautiful. In addition, the box girder with
inclined web matches with the curved pier shaft, thus increasing the overall landscape
effect of the bridge. Therefore, it is recommended to use inclined web for box girder section.
To sum up, the variable-section pre-stressed concrete box girder with inclined web is used for
superstructure, with single-box double-chamber structure, 2.0% symmetrical herringbone
transverse slope on the top surface and horizontal bottom plate. The main beam is 4.5 m high
at the center of the pier, and 2.5 m high at the middle of the midspan. The beam height varies
according to parabola of 1.8 times. The top width of the box girder is 19.1 m. The construction
method of hanging basket cantilever casting segmental box girder is adopted.
17
DAVAO CITY EXPRESSWAY PROJECT
Figure 11: Standard Section of Upper Box Girder (Root)
Figure 12: Standard Section of Upper Box Girder (Midspan)
2. Substructure
The size of the bottom of the lower pier shaft is initially proposed to be 4 m×3 m
(transverse×vertical), with a solid rectangular fillet section and the top expanded to 8 m
transversely. The bearing platform is rectangular with a plane size of 12.0×7.5 m and a
thickness of 3.0 m. 6 bored cast-in-place piles with diameter of 1.8 m are set under each
bearing platform, which are designed according to the friction pile.
18
DAVAO CITY EXPRESSWAY PROJECT
Figure 13: Typical Cross Section of Bridge Crossing Davao River
Bridge design scheme for standard section
The PSCG-I beam+cast-in-place bridge deck structure is adopted for the superstructure of the
main alignment standard section bridge, with standard span of 30 m and 5 spans in one
continuous unit. The single-column large cantilever capping beam pier is used at the
substructure, and the foundation is bored cast-in-place pile group foundation.
19
DAVAO CITY EXPRESSWAY PROJECT
Figure 14: Bridge Type Scheme for Main Alignment Standard Section (Single Column Large
Cantilever Capping Beam)
Figure 15: Bridge Type Scheme for Main Alignment Standard Section (Large-spacing
Double-column Large Capping Beam)
20
DAVAO CITY EXPRESSWAY PROJECT
Figure 16: Bridge Type Scheme for Main Alignment Standard Section (Conventional
Whole-frame Double-column Pier)
c) Drainage
Drainage design principles
1. The drainage design shall be comprehensively considered according to the highway grade
of the Project, the terrain, geology, hydrology, meteorology and other conditions along the
route as well as the setting of bridges and culverts, and the connection between various
drainage facilities and drainage structures shall be noted so as to form a complete drainage
system for the whole alignment.
2. Comprehensive planning, reasonable layout, less farmland occupation, coordination with
local irrigation and drainage systems, emphasis on environmental protection, and prevention
of soil erosion and water pollution shall be made.
Subgrade drainage design
The subgrade drainage system is proposed to use the design of side ditch, intercepting ditch,
drainage ditch, drop chute and chute, side ditch culvert, municipal drainage, etc. The
probability flow of drainage facilities is calculated by using the maximum rainstorm intensity of
confluence duration within the return period of 15 years.
1. Side ditch
For general filling sections, soil grass planting ditches are adopted without scouring. For
sections with large surface runoff and poor soil permeability, precast concrete block side
ditches are adopted; for sections with slow slopes, sheetflood+shallow dish-shaped side
21
DAVAO CITY EXPRESSWAY PROJECT
ditches+blind ditches with crushed stones are adopted.
Side ditches are set in excavated sections, filling sections with embankment height less than
the depth of side ditches, filling sections in farmland areas, and at the foot of slope on the back
side of the embankment in the mountain section, and longitudinal platform interception ditches
are also set on the slope platform of excavated sections.
The side ditch on the back side of the embankment on the hillside shall not only collect water
from the subgrade slope, but also intercept water from the hillside slope. At this time, the side
ditch shall be at least 2.0 meters away from the embankment slope toe, and a slope protection
road with a inclined slope of 3% to the ditch shall be built between the embankment slope toe
and the side ditch to allow water from the subgrade slope to flow into the side ditch for
discharge.
The excavation side ditch is a rectangular side ditch with a cover plate, with a depth of 0.70 m
of the ditch and a width of 0.6 m at the bottom of the ditch in general sections, with the inner
and outer side slopes standing upright. For sections with gentle slopes, shallow dish-shaped
side ditches+blind ditches with crushed stones are adopted.
2. Drainage ditch
Drainage ditches shall be set near side ditches, intercepting ditches, side slopes and subgrade
to drain accumulated water outside bridges and culverts or subgrade.
The alignment of drainage ditch must be smooth, and straight line shall be used as much as
possible; however arc line may be adopted in turning position, and its diameter shall not be
less than 10 m; if designed drainage ditch is not enough long, it can be lengthened according
to actual demand, but shall not be more than 500 m.
3. Drop chute and chute
If the slope surface is steep or the longitudinal slope of the side ditch is more than 60%, the
design shall be provided with drop chute and chute when the water flow in the intercepting
ditch is introduced into the drainage ditch and the water flow in the drainage ditch is introduced
into the natural ditch or bridge and culvert structure.
4. Culvert
Culvert design in the Project is based on the principle of setting culvert at every ditch. When
there are formed local roads, farming roads and pedestrian roads, culverts are set to also
serve as passages. The culvert shall be of reinforced concrete box culvert type according to
its service nature, design flood discharge, subgrade fill height, geological conditions and
earthquake, etc. Considering the convenience of dredging, the net diameter of culvert is
generally not less than 2.0 m.
22
DAVAO CITY EXPRESSWAY PROJECT
5. Municipal drainage
Corresponding rainwater collection systems shall be set along the alignment and connected
with the surrounding municipal pipe network.
Pavement drainage design
The pavement drainage system mainly consists of shoulder drainage facilities and drainage
facilities in the medial strip.
Since the super-high side marginal strip forming the full-section one-way road arch is provided
with a longitudinal slit type water collecting tank, the water on the super-high side road surface
is collected by the longitudinal water collecting tank, and is discharged from the subgrade
range by the water collecting wells and the horizontal buried drainage pipes which are
arranged at intervals. As the water quantity is generally large, a slope drainage tank is
arranged at the outlet of the horizontal drainage pipe of the embankment to prevent the slope
from being scoured.
Bridge drainage design
Longitudinal drainage pipes are arranged under sidewalks on both sides of the existing roads
in Davao City. Most of the drainage pipes are reinforced concrete round pipes with a diameter
of 1 m. Water inlets and inspection wells are arranged at a longitudinal interval of 15-20 m. At
present, DPWH in Davao City is carrying out the investigation and planning of the drainage
pipe network in Davao City to connect the drainage pipe network of the existing roads in the
city. The overall drainage direction of the city is from the mountainous area in the northwest
to Davao Gulf in the southeast.
Rainwater collection systems are set for elevated viaducts along the whole alignment of the
Project, and the collected rainwater is discharged into the municipal drainage pipe network
along the pier.
Figure 17: Centralized Rainwater Collection System for Bridge
23
DAVAO CITY EXPRESSWAY PROJECT
d) Underpass/Tunnel
Tunnel construction scheme
In the Project, it is planned to construct 1 tunnel with length of 260m, which is a multi-arch
tunnel. The tunnel construction other than civil works includes tunnel decoration, operating
equipment installation and commissioning, as well as construction of management office. The
construction sequence is described as follows: tunneling — lining — tunnel portal —
decoration — tunnel pavement — installation of mechanical and electrical facilities.
The temporary tunnel construction site can be arranged nearby the subgrade area outside the
tunnel, and within the gentle slope zone. The material room should be arranged as far as
possible in the vicinity of the access. The air compressor room should be located nearby the
tunnel portal to reduce windage loss. The living quarters and office area shall be arranged in
overall consideration of convenience for both production and living. The firework material and
oil room should be located in the sheltered and safe mountain area. The detonators and
explosives shall be stored respectively, with distance from the alignment of more than 300 m.
The tunnel construction shall be organized and implemented according to the New Austrian
Tunneling Method. The main process is mechanized operation; trackless transportation mode
is adopted for slag discharging in the tunnel; a formwork trolley is used for secondary lining
pouring. During the construction, the principle of "weak blasting, short excavation, strong
support and early closure" shall be adhered to.
Utility Requirements
Utility requirements during construction include fuel, power supply, water supply, and
construction access. The details of the requirements during construction and operation are
described below.
Power requirement
During Construction
Power supply during construction will either be tapped from the nearest electricity source or
the use of generator sets.
During Operation
Power supply during operation will be sourced from Davao Light and Power Company. The
estimated power requirement during this phase is 169,520 KWh per year.
Water Supply
During Construction
24
DAVAO CITY EXPRESSWAY PROJECT
Water for the construction of the project will be taken care of by the contractor. In the absence
of a water provider, water will be sourced from ground water after obtaining necessary permit
from NWRB.
During Operation
Water supply during operation will be sourced from Davao City Water District. Water usage
is limited to domestic use only. It is estimated that the water requirement during this phase is
220 m3 per month.
Construction Access
The project site is located in high-density urban areas; thus, the access to the site will through
public roads.
Fuel requirement
During Construction
Fuel requirement during construction will be based on the use of heavy equipment, transport
and other service vehicles.
During Operation
It is estimated that the fuel requirement during this phase is 500 liters of diesel for the use of
back-up generators during power interruptions and service vehicles.
Pollution Control Devices
Noise suppressors and buffers will be installed to minimize noise brought about by earthwork
activities and heavy equipment, especially in areas close to noise-sensitive areas such as
schools and churches. Drainage structures such as ditches, culverts, and pipe drains will be
installed to divert surface water run-off to protect the slopes from erosion.
Air Pollution Control Devices
A regular sprinkling of water on highly populated areas or exposed road surfaces will be
implemented to mitigate increase in suspended particulates. A canvass cover / tarpaulin for
trucks will also be placed to mitigate the increase in air emissions during construction. Speed
limits for delivery trucks will also be implemented.
Wastewater
Turbidity of the waterways may increase during heavy rains due to the construction debris.
This may be avoided by installing proper spoils management at the construction site. The toxic
materials (e.g. used oils, paints) will not be disposed in the drainage system at the site.
25
DAVAO CITY EXPRESSWAY PROJECT
Proper disposal of these materials will be ensured.
Solid Waste Management System
The goal is to minimize the amount of waste in the project by optimizing the use of raw
materials. Techniques or processes in reusing scrap materials will be introduced. For the solid
waste, sufficient number and size of dumpsters will be provided to contain these solid wastes
that will be generated by the project. The storage areas for the solid wastes shall also be
located at least 15m from drainages and shall not be placed in flood-prone areas. Also, littering
on the ground will also be prohibited.
Temporary Facilities
Toilet facilities will be constructed and regularly maintained by the project proponent.
Existing Utilities within ROW
The utilities found within the ROW of all phases include road signs, roadway lighting,
traffic lights, electrical posts, pavement, islands, concrete line ditches, fiber optic
cables, and CCTVs. These will be relocated and replaced as needed.
DESCRIPTION OF PROJECT PHASES
Pre-Construction Phase
Activities involved during the pre-construction phase of the project include:
1. Pre-Feasibility and Feasibility Studies;
2. Preparation of Environmental Impact Statement and Acquisition of Environmental
Compliance Certificate (ECC) for the Project;
3. Securing Various Permits and Clearances (i.e. Special Tree Cutting Permit, Project
Endorsements, LGU Clearances, etc.);
4. Conduct of Detailed Engineering Design (DED);
5. Implementation of Right-of-Way (ROW) / Land Acquisition and Implementation of the
Resettlement Action Plan (RAP) by DPWH;
6. Pre-qualification, Tendering, and Awarding of Contract for the Construction of the
Project;
7. Sourcing of construction materials; and
8. Construction of Temporary Facilities
The project is expected to last from 2019 to 2026 which covers pre-construction to construction
phase.
26
DAVAO CITY EXPRESSWAY PROJECT
Construction Phase
Civil work contract package
According to the construction experience of China, similar elevated viaduct projects in cities
shall be generally divided into phases at an internal of 6 km to 8 km. The Project is totally
29.21 km long. The whole alignment is divided into three phases, with a "T"-shaped
distribution. Considering the project cost, project scale, cost balance and continuity of
construction area, it is recommended that the civil work contract package of the Project shall
be divided into three phases, namely, the Phase 1 from Coastal Road to Ma-a, Phase 2 from
Panacan to Ma-a, and Phase 3 from Ma-a to Dumoy.
Construction execution plan
Temporary works
Construction access works
The Project is located in the urban area and the suburbs of Davao city. It is characterized by
dense road network along the alignment, good road condition and convenient transportation.
The main roads along the Project include Davao - Agusan National Highway, Carlos P. Garcia
National Highway, Davao - Cotabato National Highway, Quezon Boulevard, MacArthur
Highway, Quimpo Boulevard, Davao - Bukidnon National Highway, J. P. Laurel Avenue,
Damaso Quimones Road, R.Castillo Street, Ma-a Road, Davao City Bypass Road and Davao
City Coastal Road.
The Project features large bridge/tunnel ratio and good construction access condition.
However, some local road features abrupt turn and steep slope, which is only suitable for
material transportation. Special consideration has been given to the construction access
works during the feasibility study stage of the Project. The general principle is to ensure the
smooth connection between the construction access layout and the proposed expressway
construction as well as the construction precast yard, mixing yard, material yard, borrow area
and spoil yard, and ensure the requirements of construction machinery mobilization and
material transportation in construction stage. As far as possible, temporary construction
access shall be integrated with local rural roads to make them permanent works for the benefit
of local people.
The construction access is constructed in combination with the local road network construction
in the surrounding towns of Davao city and rural road construction. Attention shall be paid to
the connection and coordination of construction access in the phases. The main access is
constructed as a 9m-wide subgrade. The branch access road is 4.5 m wide. The pavement is
filled with gravels. For the use of existing urban and rural roads, after completion of
construction, the roads shall be restored according to the existing urban and rural road
standards. The vertical construction access shall be arranged in principle within the red line
area of the subgrade area. The vertical construction access at culvert and structure shall be
27
DAVAO CITY EXPRESSWAY PROJECT
constructed by sections to avoid land use beyond the red line.
To ensure construction machinery mobilization and material transportation in construction
stage, it is planned to construct a new construction access with total length of 43.11 km. by
relying on the existing roads, totally 47.4km construction access, 21 piece/1,810 m temporary
bridge for construction, and 69 piece/1,588 m construction culvert are renovated.
Other temporary works
Special consideration has been given to the arrangement of temporary works during the
feasibility study stage of the Project. A total of 5 temporary construction sites are set up along
the whole alignment. The specific arrangement conditions are shown in the table below. Land
use and temporary facilities such as electricity and telecommunications shall be arranged as
soon as possible. If necessary, coordination shall be provided for the local government to
ensure the overall coordination with the Project and the smooth implementation of the whole
Project.
Construction Scheme of Bridge across Davao River
1. Construction trestle
2. Pile foundation construction
3. Construction of bearing platform
4. Pier shaft construction
5. Superstructure construction
6. Construction scheme of PSCG-I beam elevated viaduct
7. Pile foundation construction
8. Construction of bearing platform
9. Construction of pier shaft and capping beam
10. Construction of PSCG-I beam
11. Tunnel construction
Operational Phase
Construction of Superstructure and Road Pavement
Once the embankment and viaduct foundations are built, the superstructure will then be
constructed. Road will be paved, and facilities guardrails will be made. This activity also
includes placement of traffic signage, painting of road, and installation of light posts and other
ancillary facilities.
Operation and Maintenance Phase
Once construction phase is finished, the project will be opened for public use. Activities during
the O&M phase of the project include:
28
DAVAO CITY EXPRESSWAY PROJECT
1. Regular monitoring, maintenance, and repair of the project;
2. Regular conduct of tree and mangrove planting activities;
3. Observance and implementation of road safety practices; and
4. Continuously improve road facilities, if necessary.
Abandonment Phase
Abandonment or decommissioning in this project can be only referred to the pulling out of
temporary facilities used during the construction of the project once construction of the project
is done. During the decommission of the contractor, it will be assured that all the construction
areas will be cleared. All construction spoil materials will be hauled out from the site.
Recyclable construction spoils will be sold to interested buyers, residuals will be dumped to
sanitary landfill, and spoils containing hazardous materials, including contaminated soils, will
be hauled by a DENR-registered Treat-Store-Dispose (TSD) Facility.
Most of the proposed location for the siting of temporary facilities are planned to be developed
as residential or commercial areas. Therefore, once the temporary facilities are dismantled
and taken out from the site, it is already ready for development for its intended use.
Manpower Requirements
More than 2,000 skilled and unskilled workers will be required during the construction of the
project, while 4-5 personnel will be employed during its operation phase.
Table 5: Manpower Requirement of the Project
Project Phase
Manpower Requirement
Skilled Non-Skilled
Construction Phase 500 1,500
Operation Phase 10 40
During construction phase of the project, most of the jobs available are construction workers
such as mason, laborers, steel men, electricians, plumbers, welders, heavy equipment
operators, among others. Therefore, most of workers during the construction phase of the
project will require men. Office staffs and site engineers, however, can be represented by
women.
The operation of the project, on the other hand, will be manned by supervisor and road
maintenance staffs. These jobs can be represented by both men and women. As much as
possible, all non-skilled workers will be sourced locally. Skilled workers which are available
locally will be prioritized. The Contractor, with the help of LGU, will be required to post job
vacancies that are needed for the project at public bulletin boards. Job fairs will be also
conducted to enhance local manpower sourcing.
.
29
DAVAO CITY EXPRESSWAY PROJECT
Project Cost
The project has an approximate cost of Php69B billion.
Summary of base cost
The total cost estimate of the recommended scheme of the Project (Alignment A + Alignment
B) is taken as RMB 8,919,246,700 or PHP 69034.97 million, excluding the cost of ROW
acquisition and demolition. The detailed cost is summarized in the table below.
Table 6: Total Cost Estimate of the Project
Basis / source of cost composition Preliminary estimate
(RMB 10,000)
Preliminary estimate
(PHP 1 million) Project cost
composition Basic sources
A. Direct cost ¥595107.18 ₱46061.30
Materials ¥386839.27 ₱29941.36
Labor ¥106290.68 ₱8226.90
Equipment ¥101977.24 ₱7893.04
B. Indirect cost ¥83315.01 ₱6448.58
Mobilization/dem
obilization
expenses
1% of A ¥5951.07 ₱460.61
Indirect
expenses,
unexpected
expenses and
miscellaneous
expenses
8% of A ¥47608.57 ₱3684.90
Profit 5% OF A ¥29755.36 ₱2303.06
C. Added-value
tax 12% of (A+B) ¥81410.66 ₱6301.19
D. Total civil
works costs A+B+C ¥759832.85 ₱58811.06
E. Budget
reserve 5% OF D ¥37991.64 ₱2940.55
F. Engineering
service cost NEDA ¥34688.38 ₱2685.82
Construction
drawing design 2% (D+E) ¥15956.48988 ₱1235.03
Construction
supervision 2% (D+E) ¥15956.48988 ₱1235.03
30
DAVAO CITY EXPRESSWAY PROJECT
Basis / source of cost composition Preliminary estimate
(RMB 10,000)
Preliminary estimate
(PHP 1 million) Project cost
composition Basic sources
Relevant
thematic costs
Preliminary
estimate ¥2775.40 ₱214.82
G. Management
cost 2%(D+E) ¥15956.49 ₱1235.03
H. ROW
acquisition cost
Based on the
required industry
and market value
/ R.A.10752
¥0.00 ₱0.00
I. Loan interest
in construction
period
Preliminary
estimate ¥43455.30 ₱3363.44
J. Total project
cost D+E+F+G+H+I ¥891,924.67 ₱69034.97
Note: 1. The exchange rate of USD 1 = RMB 6.88 = PHP 53.27 shall prevail;
2. The ROW acquisition cost will be supplemented and completed later.
PROJECT SCHEDULE
Study of the implementation priority of Davao expressway section
The Project is divided into three phases, with a "T"-shaped distribution. Phase 2 from Coastal
Highway to Ma-a is an elevated viaduct along the whole alignment, including 2 recommended
diamond interchanges and 5 bridges crossing Davao River, with large bridge span and
complex construction process. Phase 2 from Panacan to Ma-a is also an elevated viaduct
along the whole alignment, including hub interchanges and 2 recommended diamond
interchanges. In Phase 3 from Ma-a to Dumoy, it is planned to set up a 260m-long tunnel,
including 1 hub interchange, 1 deformable cloverleaf interchange and 1 simple diamond
interchange.
According to comprehensive analysis, the bridges crossing Davao River and interchanges in
the three phases of the Project are characterized by complex construction conditions, high
technical difficulty and construction difficulty, long control period and high construction
difficulty. Therefore, the simultaneous construction is recommended. In the process of
implementation, the dominant resources shall be concentrated for the construction of the
following structures, such as the pier pile foundation, the bearing platform and the pier shaft
crossing the Davao River and the existing road, and then the superstructure and the bridge
deck system should be carried out. During the construction of the above bridges, the
construction of the connecting bridge on both sides shall be conducted simultaneously, and
the construction along the whole alignment shall be finally completed.
Commented [a1]:
31
DAVAO CITY EXPRESSWAY PROJECT
Implementation schedule
The implementation schedule is temporarily arranged as follows:
1. The prospective financial lending institutions is expected to carry out a
project evaluation in November 2019;
2. The loan agreement is expected to be signed in June 2020;
3. The selection of detailed engineering design consultancy units will be made
from June 2020 to August 2020;
4. The detailed engineering design will be performed from August 2020 to July
2021;
5. The right of way acquisition will be performed from August 2020 to July 2021;
6. The selection of contractors will be made from July 2021 to December 2021;
7. The Project will start in January 2022 and opened to traffic in December
2026, with a duration of 60 months.
Project Size
The proposed project has 29.2 km in length, 4-lane urban main road, 23.1 meters
width (roadbed),34 viaducts, tunnel of 260m and 9 interchanges (3 T-Hub, 1 partial
cloverleaf and 5 diamond interchanges.