db contract documents part 3 project requirements … · region 8 bundled bridges (contract 3) pin...

80
REGION 8 BUNDLED BRIDGES (CONTRACT 3) PIN 8BOW.0H, Contract D900025 DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS Final March 6, 2015

Upload: others

Post on 24-Mar-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

REGION 8 BUNDLED BRIDGES(CONTRACT 3)

PIN 8BOW.0H, Contract D900025

DB CONTRACT DOCUMENTS

PART 3PROJECT REQUIREMENTS

Final March 6, 2015

Page 2: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

This Page is intentionally left blank

Page 3: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges – Contract 3 i Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Table of Contents

SECTION 1 GENERAL ........................................................................................................11.1 PURPOSE .................................................................................................................................. 11.2 SCOPE ...................................................................................................................................... 11.3 SCOPE OF WORK – MAJOR ITEMS ................................................................................................ 21.4 COORDINATION WITH OTHER PROJECTS ....................................................................................... 31.5 THIRD PARTY AGREEMENTS (NON-UTILITY) .................................................................................. 31.6 DESIGN CODES AND MANUALS..................................................................................................... 31.7 REQUIREMENTS ......................................................................................................................... 71.8 DELIVERABLES ........................................................................................................................... 81.9 INDICATIVE PLANS ...................................................................................................................... 81.10 DIRECTIVE PLANS ....................................................................................................................... 81.11 CADD ...................................................................................................................................... 81.12 SCHEDULE OF PROJECT COMPLETION .......................................................................................... 81.13 WORK PAYMENT SCHEDULES ...................................................................................................... 81.14 INTERIM COMPLETION MILESTONES ........................................................................................... 12

SECTION 2 PROJECT MANAGEMENT ............................................................................132.1 DESIGN-BUILDER’S ROLE .......................................................................................................... 132.2 DESIGN-BUILDER’S KEY PERSONNEL .......................................................................................... 132.3 MANAGEMENT PLANS AND SCHEDULES ....................................................................................... 15

2.3.1 Management Plans and Schedule Requirements .......................................................... 152.3.2 Workforce Participation Plan ......................................................................................... 152.3.3 Safety Plan ................................................................................................................... 152.3.4 Quality Control Plan ...................................................................................................... 152.3.5 Overall Design-Build Team Organizational Plan ............................................................ 162.3.6 Design Management Plan ............................................................................................. 162.3.7 Construction Management Plan .................................................................................... 16

2.4 BASELINE PROGRESS SCHEDULE ............................................................................................... 162.5 MEETINGS ............................................................................................................................... 172.6 COMPUTER AND NETWORKING REQUIREMENTS ........................................................................... 172.7 DEPARTMENT’S CONSULTATION AND WRITTEN COMMENTS ........................................................... 182.8 PROJECT WISE ........................................................................................................................ 18

SECTION 3 ENVIRONMENTAL COMPLIANCE ................................................................203.1 SCOPE .................................................................................................................................... 203.2 ENVIRONMENTAL APPROVALS ........................................................................................... 203.3 REQUIREMENTS ....................................................................................................................... 22

3.3.1 General ........................................................................................................................ 223.3.2 Environmental Plans ..................................................................................................... 253.3.3 Soil Erosion and Water Pollution Control ....................................................................... 253.3.4 Asbestos-Containing Materials ..................................................................................... 253.3.5 Inaccessible/Assumed ACMs ........................................................................................ 273.3.6 Environmental Plan Deliverables .................................................................................. 27

3.4 THREATENED AND ENDANGERED SPECIES COORDINATION .......................................... 27

SECTION 4 GENERAL PROJECT SCOPE OF WORK .....................................................294.1 SCOPE .................................................................................................................................... 294.2 STANDARDS ............................................................................................................................. 294.3 REQUIREMENTS ....................................................................................................................... 29

4.3.1 Field Office ................................................................................................................... 29

Page 4: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges – Contract 3 ii Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

4.3.2 Construction Vehicles on Bridge ................................................................................... 304.3.3 Salvage ........................................................................................................................ 304.3.4 Surplus Quantity ........................................................................................................... 304.3.5 Sidewalk Plowing Coordination During Winter Shutdown .............................................. 30

SECTION 5 SURVEYING AND GIS ...................................................................................315.1 SCOPE .................................................................................................................................... 315.2 STANDARDS ............................................................................................................................. 315.3 REQUIREMENTS ....................................................................................................................... 31

5.3.1 Project Survey Control .................................................................................................. 315.3.2 Department-supplied Data ............................................................................................ 315.3.3 Survey Reports, Records and Maps.............................................................................. 315.3.4 Permanent Survey Markers .......................................................................................... 32

5.4 SURVEYING AND GIS DELIVERABLES .......................................................................................... 32

SECTION 6 RIGHT-OF-WAY .............................................................................................336.1 SCOPE .................................................................................................................................... 336.2 REQUIREMENTS ....................................................................................................................... 33

6.2.1 Right-of-Way Fencing ................................................................................................... 336.2.2 Property Interests Identified by the Design-Builder for its Convenience ......................... 33

SECTION 7 PUBLIC INVOLVEMENT ................................................................................347.1 SCOPE .................................................................................................................................. 347.2 STANDARDS ......................................................................................................................... 347.3 REQUIREMENTS .................................................................................................................. 34

7.3.1 Public Notification Plan, Stakeholder Coordination Meetings and General OutreachActivities 347.3.2 Public Notification Plans: .............................................................................................. 347.3.3 Stakeholder Coordination Meetings: ............................................................................. 357.3.4 General Outreach Activities: ......................................................................................... 357.3.5 Media Relations ............................................................................................................ 37

SECTION 8 UTILITIES .......................................................................................................388.1 SCOPE .................................................................................................................................... 388.2 STANDARDS ............................................................................................................................. 388.3 GENERAL REQUIREMENTS ......................................................................................................... 38

8.3.1 Utility Relocation Agreements ....................................................................................... 398.3.2 Other Utility Conflicts .................................................................................................... 39

SECTION 9 GEOTECHNICS ..............................................................................................409.1 SCOPE .................................................................................................................................... 409.2 STANDARDS ............................................................................................................................. 409.3 DESIGN REQUIREMENTS ........................................................................................................... 40

9.3.1 Geotechnical Work Plan ............................................................................................... 409.3.2 Geotechnical Investigations .......................................................................................... 419.3.3 Minimum Number of Borings......................................................................................... 419.3.4 Subsurface Investigation Records ................................................................................. 419.3.5 Software Requirements ................................................................................................ 419.3.6 Geotechnical Data Report ............................................................................................. 419.3.7 Retaining Walls ............................................................................................................ 429.3.8 Geotechnical Instrumentation & Construction Monitoring .............................................. 429.3.9 Slope Stability............................................................................................................... 429.3.10 Rock Slope Stability ...................................................................................................... 439.3.11 Temporary Works ......................................................................................................... 43

9.4 CONSTRUCTION REQUIREMENTS ................................................................................................ 439.4.1 Dewatering and Groundwater Control ........................................................................... 43

Page 5: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges – Contract 3 iii Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

9.4.2 Deep Foundations ........................................................................................................ 439.4.3 Soil and Rock Excavations and Embankments.............................................................. 439.4.4 Condition Surveys ........................................................................................................ 44

9.5 DELIVERABLES ......................................................................................................................... 44

SECTION 10 STRUCTURES ...............................................................................................4610.1 SCOPE .................................................................................................................................... 4610.2 STANDARDS ............................................................................................................................. 4610.3 DESIGN REQUIREMENTS ......................................................................................................... 46

10.3.1 Components ................................................................................................................. 4710.3.2 Aesthetic Requirements ................................................................................................ 51

10.4 DEMOLITION REQUIREMENTS ............................................................................................ 5110.4.1 Scope ........................................................................................................................... 5110.4.2 Standards ..................................................................................................................... 52

10.5 CONSTRUCTION REQUIREMENTS ...................................................................................... 5210.6 DELIVERABLES ......................................................................................................................... 52

SECTION 11 LANDSCAPE ARCHITECTURE .....................................................................5311.1 SCOPE .................................................................................................................................... 5311.2 STANDARDS ............................................................................................................................. 5311.3 GENERAL LANDSCAPE DEVELOPMENT ........................................................................................ 53

11.3.1 Existing Vegetation ....................................................................................................... 5311.3.2 Tree Replacement Factors ........................................................................................... 5311.3.3 Replacement Locations ................................................................................................ 5411.3.4 Proposed Planting ........................................................................................................ 5411.3.5 Location Specific Landscape Development Concerns ................................................... 54

SECTION 12 SIGNAGE, PAVEMENT MARKING AND SIGNALS.......................................5512.1 SCOPE .................................................................................................................................... 5512.2 STANDARDS ............................................................................................................................. 5512.3 REQUIREMENTS ....................................................................................................................... 55

12.3.1 Design Requirements ................................................................................................... 5512.3.2 Construction Requirements .......................................................................................... 56

12.4 DELIVERABLES ......................................................................................................................... 56

SECTION 13 LIGHTING .......................................................................................................5713.1 SPECIFIC LIGHTING REQUIREMENTS FOR BIN 1040550 ................................................... 57

13.1.1 Scope ........................................................................................................................... 57

SECTION 14 INTELLIGENT TRANSPORTATION SYSTEMS (ITS) ....................................5814.1 SCOPE .................................................................................................................................... 58

SECTION 15 WORK ZONE TRAFFIC CONTROL AND ACCESS .......................................5915.1 SCOPE .................................................................................................................................... 5915.2 STANDARDS ............................................................................................................................. 5915.3 REQUIREMENTS ....................................................................................................................... 59

15.3.1 General Requirements .................................................................................................. 5915.3.2 Work Zone Traffic Control Plan ..................................................................................... 6015.3.3 General Restrictions ..................................................................................................... 6115.3.4 Access to Commercial Properties and Driveways ......................................................... 6215.3.5 Closure Restrictions ..................................................................................................... 6315.3.6 Minimum Lane Widths during Construction ................................................................... 6315.3.7 Portable Variable Message Signs ................................................................................. 6315.3.8 Temporary and Interim Pavement Markings .................................................................. 6315.3.9 Coordination with Regional Traffic Management Center ................................................ 6415.3.10 Emergency Response and Transportation Management Plans ..................................... 64

Page 6: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges – Contract 3 iv Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 16 PAVEMENT DESIGN AND CONSTRUCTION ...............................................6516.1 SCOPE .................................................................................................................................... 6516.2 STANDARDS ............................................................................................................................. 6516.3 REQUIREMENTS ....................................................................................................................... 65

16.3.1 Full Depth Reconstruction ............................................................................................. 6516.3.2 Milled and Resurfaced Roadways ................................................................................. 6616.3.3 Utility Trench Restoration.............................................................................................. 66

SECTION 17 DRAINAGE AND STORMWATER .................................................................6717.1 SCOPE .................................................................................................................................... 6717.2 STANDARDS ............................................................................................................................. 6717.3 REQUIREMENTS ....................................................................................................................... 67

17.3.1 General ........................................................................................................................ 6717.3.2 Drainage Report ........................................................................................................... 6717.3.3 Connections to Existing Systems .................................................................................. 6817.3.4 Spill Management ......................................................................................................... 68

17.4 DELIVERABLES ......................................................................................................................... 68

SECTION 18 HIGHWAY DESIGN ........................................................................................6918.1 SCOPE .................................................................................................................................... 6918.2 STANDARDS ............................................................................................................................. 6918.3 REQUIREMENTS ....................................................................................................................... 69

18.3.1 General ........................................................................................................................ 6918.3.2 Design Requirements ................................................................................................... 6918.3.3 Barrier Systems and Impact Attenuators ....................................................................... 7018.3.4 Clear zone .................................................................................................................... 71

18.4 DESIGN EXCEPTIONS AND NON-STANDARD FEATURES ................................................................. 71

SECTION 19 STANDARDS .................................................................................................7219.1 GENERAL REQUIREMENTS ......................................................................................................... 7219.2 SPECIFIC REQUIREMENTS ......................................................................................................... 72

SECTION 20 SECURITY ......................................................................................................73

Page 7: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

This Page is intentionally left blank

Page 8: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 1 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 1 GENERAL

1.1 PURPOSE

This Part 3 establishes the basic Requirements of the Project. The Contract Documents,NYSDOT standard drawings, manuals and specifications, and the referenced Design Codesand Manuals shall be followed for the preparation of design and construction documents andthe execution of the Work. Any proposed deviation from the Contract requirements or NYSDOTstandards shall be submitted to the Department’s Design Quality Assurance Engineer forreview, and shall require the submission of a Non-conformance Report.

All designs shall be prepared in U.S. Customary units. The Design-Builder shall be responsiblefor converting any mapping, plans, etc. into U.S. Customary units as necessary for thecompletion of the Project.

The Design shall be in conformance with the latest edition of the New York State Department ofTransportation, Standard Specifications, with addenda, issued by the Office of Engineering,current as of the date of Proposal submission, except as noted in these Contract Documents.

The Design-Builder shall prepare Project Specifications for the Project, for Work Items notcovered by the NYSDOT Standard Specifications or applicable Special Specifications, and shallprepare Design Plans for the Project in accordance with NYSDOT standards for general contentand format, and in accordance with the Contract.

Deviations may be proposed within the framework of these Design Requirements to meet therequirements of a particular situation. However, any deviation, discrepancy, or unusual solutionrequires review by the Department’s Design Quality Assurance Engineer before it can beincluded in the design. It is the responsibility of the Design-Builder to identify, explain, andjustify any deviation from the established criteria to the Department’s Design Quality AssuranceEngineer.

The Design-Builder shall prepare and submit a Non-conformance Report (in accordance withthe provisions of DB §105-16) for any Work performed that does not conform to the Contractrequirements and for any deviations from NYSDOT standards.

1.2 SCOPE

The Design-Builder shall be responsible for complying with all terms of the Contract Documents.The Design-Builder shall review and understand all terms and conditions of the ContractDocuments prior to the commencement of the Project and shall be responsible for determiningthe full Scope of the Project by undertaking a thorough examination of the Contract Documents,the Reference Documents and the Project Site.

Page 9: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 2 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

1.3 SCOPE OF WORK – MAJOR ITEMS

The scope of work for the Project includes but is not limited to the following items:

A) Superstructure replacement and abutment and pier rehabilitation for the following bridge:

BIN County Municipality Carried Crossed

1040550 Orange Village of Washingtonville Route 208 Moodna Creek

Work at the structure in the above table shall include but not be limited to the following:

a) Removal of the existing superstructure;

b) Modifications to the substructures as necessary to accommodate the newsuperstructure;

c) Construction of new superstructure and approach slabs;

d) Approach roadway reconstruction necessary to connect existing roadway to new bridgeincluding curbs and sidewalks;

e) Development of a WZTC plan;

f) Remediation and disposal of possible asbestos containing materials;

g) Utility work and involvement.

B) Full Replacement of the following bridges:

BIN County Municipality Carried Crossed

5500969 WestchesterVillage/

Town of Mount Kisco andTown of Bedford

Saw Mill River Parkway(Route 987D) Kisco Avenue

5500870 Westchester Village of Pleasantville Saw Mill River Parkway(Route 987D Saw Mill River

5500890 Westchester Village of Pleasantville Saw Mill River Parkway(Route 987D Saw Mill River

5521680 Westchester City of New Rochelle EHPA DPW Road Hutchinson River

Work at each of the structures in the above table shall include but not be limited to the following:

a) Removal of the existing substructures and superstructures;

b) Replacement of the existing bridges; including new foundations, substructures,superstructures and approach slabs;

c) Approach roadway reconstruction necessary to connect existing roadways to the new

bridges;

d) Construction of speed change lanes (BIN 5500969);

e) Design and construction of a noise barrier (BIN 5500969);

f) Reconstruction of median (BIN 5500969);

Page 10: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 3 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

g) Development of a WZTC plan for each site;

h) Remediation and disposal of asbestos containing materials;

i) Remediation and disposal of lead based paint (BIN 5500969);

j) Removal of silt bar (BIN 5521680);

k) Utility work and involvement.

C) Bridge rehabilitation (pipe lining) for the following bridge:

BIN County Municipality Carried Crossed

1005080 Westchester Town of Cortlandt Route 9 Dickey Brook

Work at the structure in the above table shall include but not be limited to the following:

a) Lining of existing pipes;

b) Removal of vegetation and installation of rip-rap on the upstream and downstream endsof the pipes.

1.4 COORDINATION WITH OTHER PROJECTS

The table below lists the projects currently scheduled to occur within or adjacent to the Contractlimits prior to the Project Completion Date.

Sponsor Project Location

NYSDOT8811.97 Maintenance

by Contract BridgeRegion Wide

BINs 5502091 and 5502092 Route 987G(Taconic State Parkway) over Route 987D SawMill River Parkway and Ramps

WestchesterCounty

Department ofPublic Works and

Transportation

13-510

Pleasantville Road paving project (traversingboth Briarcliff Manor and Pleasantville) is fromSouth State Road to Bedford Roard and fromNorth State Road to the Ossining Line. Thebridge (BIN 3348030) carrying PleasantvilleRoad over the Pocantico River will also berehabilitated.

1.5 THIRD PARTY AGREEMENTS (NON-UTILITY)

No Third Party Agreements have been developed in connection with this Project.

For information regarding Preliminary DB Utility Work Agreements, Refer to Section 8 of thisPart 3.

1.6 DESIGN CODES AND MANUALS

In addition to this Part 3, Project Requirements, the Design-Builder must comply with allapplicable engineering codes and standards, including those of the various Federal, State, andlocal jurisdictions.

Page 11: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 4 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

If codes, standards and/or manuals are specified herein for the design of an element of theProject, then the edition(s) in effect on the Proposal due date shall be applicable to the Project.Responsibility for design remains with the Design-Builder in accordance with the terms andconditions of the Contract. If a code, manual or standard is subsequently modified by theissuer, the Design-Builder shall notify the Department of such modification(s) and request theDepartment’s decision regarding application of the modification(s).

All work shall conform to the following documents. In the event of a conflict between the codesand reference documents listed below, the more stringent requirements, as determined by theDepartment, shall apply.

For Work not specifically covered by the individual sections of the Project Requirements, theDesign-Builder shall, at a minimum, apply the Standards normally applied by NYSDOT for suchWork, to the extent they do not conflict with express requirements in the Contract Documents.The Design-Builder shall be solely responsible for ensuring that it identifies and applies allcorrect Standards.

AASHTO:

A Guide for Accommodating Utilities within Highway Right-of-Way

A Policy on Design Standards - Interstate System

A Policy on Geometric Design of Highways and Streets

Construction Handbook for Bridge Temporary Works

Guide Design Specifications for Bridge Temporary Works

Guide for the Design of Pavement Structures (with Supplement)

Guide Specification for Bridge Railings (1989)

Guide Specifications for LRFD Seismic Bridge Design

LFRD Bridge Construction Specifications

LFRD Bridge Design Specifications

Manual for Assessing Safety Hardware (MASH)

Manual for Bridge Evaluation

Manual on Subsurface Investigations

Mechanistic-Empirical Pavement Design Guide (MEPDG)

Roadside Design Guide

Standard Specifications for Highway Bridges

Standard Specifications for Structural Supports for Highway Signs,LuminairesLuminaries and Traffic Signals

Guide Specifications for Structural Design of Sound Barriers, 1992 Interim

AISC: Steel Construction Manual

ANSI

Page 12: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 5 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

ANSI/AASHTO/AWS D1.5-95 Bridge Welding Code

ANSI/IES Approved Recommended Practice for Roadway Lighting, RP-8-00

Asphalt Institute: Drainage of Asphalt Pavement Structures

ASTM: E2213-03 Standard Specification for Telecommunications and Information Exchange

Between Roadside and Vehicle Systems

E2259-03 Standard Guide for Archiving and Retrieving ITS-Generated Data

E2468-05 Standard Practice for Metadata to Support Archived Data ManagementSystems

E2655-08 Standard Guide for Reporting Uncertainty of Test Results and Use of theTerm Measurement Uncertainty in ASTM Test Methods

Federal Geographic Data Committee: GIS Standards

FHWA: FHWA NHI-00-043 Mechanically Stabilized Earth Walls and Reinforced Soil Slopes

Design and Construction Guidelines

FHWA Ground Improvement Methods

FHWA NHI-05-123 Soil Slope and Embankment Designs

FHWA NHI-11-032 GEC No. 3 LRFD Seismic Analysis and Design of TransportationGeotechnical Features and Structural Foundations

FHWA HI-99-007 Rock Slopes Reference Manual

HEC 18 Evaluating Scour at Bridges

HEC 23 Bridge Scour and Stream Instability Countermeasures

Manual of Uniform Traffic Control Devices (MUTCD)

Pavement Publications

Standard Highway Signs and Markings (SHSM) Book

Steel Bridge Design Handbook

Technical Advisory T6640.8A, 10/30/87 (environmental analyses)

Traffic Monitoring Guide

Guidance Noise Barriers – Design and Construction

NFPA: NFPA 70 – National Electrical Code (NEC)

502: Standard for Road Tunnels, Bridges, and Other Limited Access Highways

Page 13: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 6 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

NYSDEC: Standards and Specifications for Erosion and Sediment Control (SESC)

Stormwater Management Design Manual (SMDM)

NYSDOT: Annual Report titled "Axle Factor Update"

Approved Materials List

Bridge Detail (BD) Sheets US Customary (NYSDOT BD Sheets)

Bridge Inspection Manual

Bridge Inventory Manual

Bridge Manual

Bridge Safety Assurance Seismic Vulnerability Manual

Comprehensive Pavement Design Manual

Consultant Instructions (CIs)

Design Consultant Manual

Engineering Bulletins (EBs)

Engineering Instructions and Directives (EIs and EDs)

Environmental Procedures Manual (EPM) / The Environmental Manual (TEM)

GCP-17, Procedure for the Control of Granular Materials

Geotechnical Design Manual, including all appendices

Highway Design Manual (HDM)

Land Surveying Standards and Procedures Manual

LRFD Blue Pages / LRFD Bridge Design Specifications

Manual for Uniform Record Keeping

Materials Bureau - Applicable Sampling and Testing Manuals, Inspection Manuals, andMaterials Methods

New York State Supplement to the Manual on Uniform Traffic Control Devices

Overhead Sign Structure Design Manual

Policy and Standards for the Design of Entrances to State Highways

Policy on Highway Lighting

Prestressed Concrete Construction Manual (PCCM)

Project Development Manual

Reference Marker Manual

Rules and Regulations Governing the Accommodation of Utilities within the StateHighway Right of Way

Page 14: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 7 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Special Specifications as indicated in the Contract Documents

Standard Specifications for Construction and Materials

Steel Construction Manual (SCM)

Structures Design Advisories

Structures Technical Advisories

U.S. Customary Standard Sheets

Work Zone Traffic Control Manual

The above is a partial listing of applicable NYSDOT Engineering Manuals and Guidelines. TheDesign-Builder shall perform the Work in conformance with all NYSDOT Engineering Manualsand Guidelines in effect on the Proposal due date.

OSHA:

PART 1926 - Safety And Health Regulations For Construction

SPC: Society of Protective Coatings Standards

USDOJ: ADA Accessibility Guidelines for Buildings and Facilities

USDOT: ADA Standards for Transportation Facilities

1.7 REQUIREMENTS

The “Requirements” subsection of the individual sections of Part 3 – Project Requirementsestablishes the Department’s expectations with respect to specific Project elements. Theseinclude administrative, managerial and technical considerations as deemed appropriate to thesubject, and encompass performance specifications, design criteria, and directive instructionsas the Department deems best suited to the subject. The Design-Builder shall develop itsDefinitive Design, Design Plans and Project Specifications in conformance with this Part 3 –Project Requirements.

The Design-Builder shall be responsible for meeting all requirements and terms contained inthis Part 3 – Project Requirements unless explicitly stated otherwise.

The specific requirements in this Part 3 – Project Requirements may be more stringent and shallgovern over the criteria given in the Standards. Where a specific requirement in this Part 3 –Project Requirements is more stringent than the criteria specified in a Standard, said specificrequirement shall become the basis for determining compliance. Non-standard features needingjustification and FHWA and/or NYSDOT approval are defined as those not meeting the criteriacited in the Standards listed in this Part 3 – Project Requirements.

Page 15: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 8 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

1.8 DELIVERABLES

The subsection entitled “Deliverables” in each section of this Part 3 – Project Requirementsestablishes the Department’s expectations. These shall supplement the review plan andconsultation and written comment cycles cited in DB §111-8 through DB §111-14. The Design-Builder may submit deliverables for the Department’s consideration or consultation and writtencomment in addition to those requested. The Design-Builder shall include such additionalsubmittals in its review plan and revise the review plan as necessary to incorporate sufficientadvance notice to the Department.

Unless otherwise indicated in a specific section of this Part 3 – Project Requirements, alldeliverables shall be submitted in both electronic format and hardcopy format. Acceptableelectronic formats include Bentley Microstation .dgn format and Bentley InRoads.alg and dtmformat, Microsoft Word®, Microsoft Excel®, ArcMAP, or searchable portable document format(PDF) files, with no copy or password protection on the file content, unless otherwise indicatedin a specific section of this Part 3 - Project Requirements or a Standard cited in a specificsection of this Part 3 - Project Requirements.

1.9 INDICATIVE PLANS

The Indicative Plans, if provided to the Design-Builder in Part 6 – RFP Plans, convey an overallpotential solution to the Project’s needs. The Indicative Plans are not mandatory, with theexception of elements specifically mentioned elsewhere in this Part 3.

1.10 DIRECTIVE PLANS

The Directive Plans, if provided to the Design-Builder in Part 6 – RFP Plans, depict requiredelements and components of the Project within specifically defined parameters. The Design-Builder has no latitude to adjust components or details shown on Directive Plans, unlessspecifically noted or through an approved Alternative Technical Concept (ATC).

1.11 CADD

CADD formatting for Design and As-Built Plans shall conform to the Department’s CADDDrafting Standards and CADD Design Standards in effect on the Proposal due date.

1.12 SCHEDULE OF PROJECT COMPLETION

All work on the design and on the construction shall be completed in accordance with Part 1, DBAgreement, Article 2, Contract Time, but in no case shall the Project Completion Date be laterthan August 18October 30, 2017.

1.13 WORK PAYMENT SCHEDULES

Progress Payments will be made as each Work Item is completed to the satisfaction of theDepartment’s Construction Quality Assurance Engineer. Progress payments shall be subject tothe requirements of DB §109-2. Payments for Design, Construction Inspection and Laboratoryactivities will be made in conformance with DB § 109-2.2.

Page 16: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 9 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

WORK PAYMENT SCHEDULE – BIN 1040550

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM PRICE(To be completed

by D-B)1

Work Zone Traffic Control – Off-Site Detour InOperation 5%

Demolition and Removal of Existing Superstructure 20%Demolition and Removal of Existing Approach Slabs 5%Rehabilitation of Abutments and Pier 15%Fabrication and Installation of Bearings 5%Construction of Bridge Superstructure and ApproachSlabs 25%

Installation of Gas Main Casing on Bridge 105%Installation of Permanent Sanitary Force Main Sewer 510%Reconstruction of the Bridge Approaches IncludingCurbs and Sidewalks 10%

Fabrication and Installation of Bridge Rail andApproach Guide Rail 10%

Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

WORK PAYMENT SCHEDULE – BIN 5500969

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM PRICE(To be completed

by D-B)1

Construction of Noise Barrier 10%Work Zone Traffic Control – 5% for Each Stage(Assume 3 Stages) 15%

Stage I Demolition and Removal of Existing BridgeElements 15%

Stage II Demolition and Removal of Existing BridgeElements 15%

Stage I Construction of Foundations 5%Stage II Construction of Foundations 5%Stage I Construction of Abutments and Wing Walls 10%Stage II Construction of Abutments and Wing Walls 10%

Page 17: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 10 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Stage I Construction of Bridge Superstructure andApproach Slabs 10%

Stage II Construction of Bridge Superstructure andApproach Slabs 5%

Stage III Construction of Bridge Superstructure andApproach Slabs 5%

Construction of Drainage System 2.5%Reconstruction of Median 2.5%Rock Excavation is Completed 2.5%Construction of Speed Change Lanes 2.5%Milling and Inlay Paving and Sidewalk Replacement onKisco Avenue 2.5%

Fabrication and Installation of Signage and PavementMarkings 2.5%

Fabrication and Installation of Bridge Rail andApproach Guide Railing and Highway Guide Railing 2.5%

Completion of Miscellaneous Items 2.5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

WORK PAYMENT SCHEDULE – BIN 5500870

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM PRICE(To be completed

by D-B)1

Work Zone Traffic Control 25%Demolition and Removal of Existing Bridge Elements 35%Installation of Foundations 5%Construction of Abutments and Wing Walls 5%Fabricate and Install Bearings 5%Installation of Replacement Structure 25%Reconstruction of the Highway Bridge Approaches 5%Fabrication and Installation of Bridge Barrier andApproach Guide Railing 5%

Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

Page 18: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 11 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

WORK PAYMENT SCHEDULE – BIN 5500890

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM PRICE(To be completed

by D-B)1

Relocation of Sanitary Sewer and Installation of SewerStub 5%

Work Zone Traffic Control 25%Demolition and Removal of Existing Bridge Elements 35%Installation of Foundations 5%Construction of Abutments and Wing Walls 5%Fabricate and Install Bearings 5%Installation of Replacement Structure 25%Reconstruction of the Highway Bridge Approaches 5%Fabrication and Installation of Bridge Barrier andApproach Guide Railing 5%

Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

WORK PAYMENT SCHEDULE – BIN 5521680

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM PRICE(To be completed

by D-B)1

Removal of Existing Corrugated Pipes Stage I 15%Removal of Existing Corrugated Pipes Stage II 15%Installation of Replacement Structure Stage I 35%Installation of Replacement Structure Stage II 35%Installation of Approach Slabs Stage I 2.5%Installation of Approach Slabs Stage II 2.5%Reconstruction of the highway bridge approaches 5%Fabrication and Installation of Bridge Rail andApproach Guide Railing 5%

Complete Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

Page 19: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 12 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

WORK PAYMENT SCHEDULE – BIN 1005080

WORK ITEM

MAXIMUMPERCENT OFLUMP SUM

PRICE

PERCENT OFLUMP SUM PRICE(To be completed

by D-B)1

Installation of Pipe Liner 50%Removal of Vegetation and installation of Stone Fillingon Slope

30%

Removal of Silt/Sand Bar 30%Completion of Miscellaneous Items 5%Punch list work, Site Cleanup and Restoration 2% (fixed) 2%Final Acceptance (Per DB §109-12.1) 1% (fixed) 1%Final Agreement (Per DB §109-12.2) 2% (fixed) 2%

Notes: (1) See Work Payment Schedule included in ITP, Appendix E.

(2) Subsequent to Selection of Best Value, the Design-Builder may submit to theDepartment a more detailed Work Payment Schedule which breaks individual workitems into multiple stages, for the Department’s review and acceptance. However,the sum of the percentages proposed for each stage shall equal the percentage forthat work item submitted by the Design-Builder included on Form WPS, and in nocase shall the payment for any individual stage be more than 50% nor less than 10%of the total percentage bid for that work item.

1.14 INTERIM COMPLETION MILESTONES

This Project’s Interim Completion Milestones, if applicable, are defined as shown in Part 5 –Special Provisions of the RFP.

The Interim Completion Milestone Dates may not be changed without written approval by theDepartment’s Project Manager.

Page 20: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 13 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 2 PROJECT MANAGEMENT

2.1 DESIGN-BUILDER’S ROLE

The Design-Builder shall have responsibility for controlling and managing the Work, includingthe responsibility for quality management as defined in the Contract Documents, Part 2 - DB §§111, 112 and 113. This section identifies the Design-Builder’s Key personnel and summarizesthe Management Plans to be produced by the Design-Builder in accordance with the ContractDocuments.

2.2 DESIGN-BUILDER’S KEY PERSONNEL

The positions listed below shall be the Design-Builder’s key personnel for the Project. KeyPersonnel are preferred to have experience on projects of a similar size, type of work, andcomplexity as this Project, and should meet the qualifications described below. Proposed staffwith qualifications less than those described below will receive a reduced score compared tostaff that meet or exceed the described qualifications. Any requirements described as “shallhave...” or “shall be…”are determined to be minimum response requirements. The Design-Builder shall provide personnel that meet these minimum requirements.

The Design-Builder’s Project Manager shall be the Design-Builder’s representative and singlepoint of contact with the Department.

The Department’s Project Manager may designate other Key Personnel positions as needed atany time during the Contract.

A) Project Manager: Shall have a minimum of 10 years, but preferably 15 years ofdemonstrated experience in construction and construction management of majortransportation and infrastructure projects. Projects should be of similar size and type ofwork as this Project, including projects with compressed timelines, and communityinformation requirements. Such experience in construction and management-of-construction should include at least one bridge infrastructure construction project havinga construction value in excess of $15,000,000. The Project Manager, who should haveDesign-Build experience and have extensive project management experience, can holdonly this one Key Personnel position. The Project Manager should dedicate no less than50% of their work time to this Project. It is preferred, but not required, that this individualbe licensed and currently registered as a Professional Engineer in the State of NewYork.

B) Design Manager: Shall be licensed and currently registered as a Professional Engineerin the State of New York, shall be an owner or employee of the Designer and shall havea minimum of 15 years demonstrated experience in managing design for infrastructureprojects of similar scope as this Project. The Design Manager, should preferably haveDesign-Build experience, and should have specific experience on projects of similar sizeand type. The Design Manager can hold only this one Key Personnel position. TheDesign Manager should dedicate no less than 75% of their work time to this Project.

C) Construction Manager: Should preferably be licensed and currently registered as aProfessional Engineer in the State of New York and should have a minimum of 15 yearsof demonstrated construction experience in civil works projects with experience inmanaging the site work of superstructure and bridge replacement and highway

Page 21: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 14 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

construction and reconstruction projects. Experience should include work of the natureanticipated in the Project, and should preferably include Design-Build contracts. TheConstruction Manager should dedicate no less than 50% of their work time to thisProject.

D) Quality Manager: Should have demonstrated experience in bridge design and majorinfrastructure construction with at least 10 years experience in quality assurance andquality control activities, including preparation and implementation of Quality Plans andprocedures for design and construction. The Quality Manager can hold only this KeyPersonnel position. The Quality Manager should dedicate no less than 40% of their worktime to this Project. The Quality Manager shall have experience of quality systemsbased on ISO 9001, and preferably have experience with the quality systems of theDepartment.

E) Resident Engineer: Should be licensed and currently registered as a ProfessionalEngineer in the State of New York and should have demonstrated at least 10 yearsexperience in bridge and highway construction inspection, including at least 5 years as aResident Engineer. The Resident Engineer should have performed Resident Engineerduties on a project within the last 3 years.

F) Lead Structural Engineer: Shall be licensed and currently registered as a ProfessionalEngineer in the State of New York and shall have demonstrated at least 10 yearsexperience in structural analysis and design.

G) Lead Civil Engineer: Shall be licensed and currently registered as a ProfessionalEngineer in the State of New York and shall have at least 10 years experience in civilroadway design, including congestion management and the preparation of Work ZoneTraffic Control Plans.

H) Lead Geotechnical Engineer: Shall be licensed and currently registered as aProfessional Engineer in the State of New York and shall have a minimum of 10, butpreferably 15 years of experience which should include the following: planning andoverseeing subsurface exploration programs for highway structures/facilities; thedevelopment of design soil/rock profiles, for the purpose of geotechnical analysis,design, and construction; design of structure foundations and earth support structures;analysis and design for static and dynamic (seismic) loading under current LRFD;analysis and design of mitigation measures for embankment settlement and stability;analysis and design of both temporary and permanent earth support structures; andinterpreting geotechnical instrumentation programs.

I) Project Superintendent: Should have at least 5, but preferably 10 years ofdemonstrated experience overseeing work on bridge and highway construction projects.Experience should include directing and coordinating the activities of a contractor’sworkforce and all subcontractors, ensuring work progressed according to schedule,within budget and that material and equipment were delivered to the site on time. TheProject Superintendent should have experience as Project Superintendent on a bridgeproject valued at $15,000,000 or more.

J) Lead Public Involvement Specialist: Shall have a minimum of 10 years experienceworking in the field of transportation planning/public involvement. Individual shall have

Page 22: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 15 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

demonstrated experience in the development and successful implementation of publicnotification plans and associated tasks such as, but not limited to: organizing, preparingfor, and facilitating stakeholder meetings and public meetings; development of publicinformational materials for public meetings and project websites; drafting of Project pressreleases; and so on.

2.3 MANAGEMENT PLANS AND SCHEDULES

2.3.1 Management Plans and Schedule Requirements

The Design-Builder shall submit to the Department’s Project Manager, for review and commentor approval (as applicable), all the Management Plans listed in Table 2-1. Following receipt ofthe Department’s acceptance or approval of the individual Management Plans, as described inthe Contract Documents, the Management Plans shall be resubmitted to the Department’sProject Manager as the Design-Builder’s consolidated Project Management Plan for the Project.

Table 2-1 – Project Management Plans

Plan Title Contract DocumentReference

Initial Plan to beSubmitted withthe Proposal?

SubmittalDeadline

Workforce Participation Plan DB § 102-9.4B No 45 Days after NTP

Safety Plan * DB § 107-7.5 No 30 Days after NTP

Quality Control Plan * DB § 113 Yes 25 Days after NTPOverall Design-Build TeamOrganization Plan

Project RequirementSection 2.3.5 Yes 25 Days after NTP

Design Management Plan Project RequirementSection 2.3.6 Yes 30 Days after NTP

Construction Management Plan Project RequirementsSection 2.3.7 Yes 45 Days after NTP

* Requires Department approval

2.3.2 Workforce Participation Plan

The Design-Builder shall develop a Workforce Participation Plan to meet the requirements ofDB §102-9.4B and submit it to the Department’s Project Manager for review and comment.

2.3.3 Safety Plan

The Design-Builder shall develop a Safety Plan to meet the requirements of Part 2, DB §107-7.5and submit it to the Department’s Project Manager for written approval in accordance with DB§107-7.8. No construction Work shall progress and no payment shall be made to the Design-Builder until the Safety Plan is approved by the Department.

2.3.4 Quality Control Plan

The Design-Builder shall use the Initial Quality Control Plan submitted with the TechnicalProposal, modify and develop it, as necessary, to include the content required by Part 2, andsubmit it to the Department’s Project Manager for written approval in accordance with Part 2 DB§113. The Quality Control Plan shall be revised and resubmitted to the Department’s Project

Page 23: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 16 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Manager within 14 calendar days of receipt of the Department’s written comments andresubmitted as required until Approved by the Department’s Project Manager. No offsitefabrication Work or Construction Work shall commence before the Quality Control Plan hasbeen approved by the Department’s Project Manager. No payment will be made to the Design-Builder until the Quality Control Plan has been approved by the Department.

2.3.5 Overall Design-Build Team Organizational Plan

The Design-Builder shall update the Initial Overall Design-Build Team Organization Plandescribing the design and construction organizational arrangements it intends to implement.The organizational arrangements described should clearly identify responsibilities and reportinglines of staff, particularly relating to Key Personnel.

The Design-Builder shall include an organization chart (on an 11" x 17" sheet of paper),illustrating the Proposer’s Key Personnel and their prospective roles and responsibilities, as wellas other principal participants and any known Subcontractors having a material role in theProject’s design Work, design check Work, construction Work and construction inspection Work.

The Design-Builder shall describe the interrelationships and interfaces between each disciplinewithin the Proposer’s organization (e.g., design, design check, shop drawing preparation andreview, construction, and quality management).

The Overall Design-Build Team Organization Plan shall also describe the interrelationships andinterfaces between the Design-Builder’s organization, the Department and other governmentalagencies, utility owners, stakeholders, businesses, the public and other contractors working inthe vicinity and impacted by the construction of the Project. This description shall also, at aminimum, address the following activities:

A) Reviews of plans and permits;

B) Progress, workshop, partnering and utility coordination meetings; and

C) Construction, engineering and inspection activities.

2.3.6 Design Management Plan

The Design-Builder shall update the Initial Design Management Plan submitted with its Proposaland submit it to the Department’s Project Manager for Review and Comment.

2.3.7 Construction Management Plan

The Design-Builder shall update the Initial Construction Management Plan submitted with itsProposal and submit it to the Department’s Project Manager for Review and Comment.

2.4 BASELINE PROGRESS SCHEDULE

The Design-Builder shall expand and Preliminary Utility Work Agreements update the InitialBaseline Progress Schedule submitted with the Technical Proposal and modify and develop it,as necessary, in accordance with DB §108-1 and Part 5, Special Provision SP-3.

Design shall be considered complete when all Design related documents have been completedand accepted by the Department including: all calculations, specifications, records of design

Page 24: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 17 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

quality control reviews and procedures; descriptions of and justification for any non-standardfeatures created or retained as a result of the design; resolution of any non-conformancereports; and submission of “As Built” drawings.

Construction shall be considered complete when: the entire Scope of Work has beencompleted; any damage to the area caused by the Design-Builder’s performance of the Workhas been repaired to the satisfaction of the Department; all construction quality controldocuments, test and inspection reports and forms have been completed; As-Built drawings havebeen completed; and the work site(s) have been cleaned of any debris.

2.5 MEETINGS

The Design-Builder shall convene or participate in meetings as indicated in Part 2 DB §105-17.

It is the Department’s policy to use the principles of partnering to guide the management ofDesign-Build contracts and the Design-Build program within the parameters covered by thelaws, regulations, and other policies that govern the work. The Design-Builder shall convene orparticipate in meetings designed to foster the principles of partnering in accordance with Part 2DB §103-2.

The Design-Builder shall record the minutes for each meeting.

2.6 COMPUTER AND NETWORKING REQUIREMENTS

The Department will issue Citrix connection accounts to the Design-Builder and its ConstructionInspection Professional Engineering Firm CIPE firm.

Upon request, the Department will also supply the Design Builder with a CSMIN networkconnection at the CIPE Field Office with the following Computer and Networking equipmentthrough a third party vendor:

1 Wireless connection with Router 3 fully configured laptops w/ accessories (for RE, OE, and Chief Inspector) 1 Multi Function Printer

The Design-Builder shall provide ALL additional Computer and Networking equipment to theCIPE as necessary. The Design-Builder will need to provide separate high-speedcommunication into the CIPE office for all non-CSMIN users. A separate printer will be neededfor the non-CSMIN users, as their laptops/computers will not be networked to the CSMIN MFP.It is recommended that the Design-Builder test the network connection success prior to fullyequipping its staff and the CIPE firm, to ensure both hardware and software compatibility.

The following computer related specifications reflect the current technology utilized by theDepartment when making Citrix Connections and are provided for informational purposes only:

• 2/HM65 Chipset, and Intel HD Graphics 3000 (or equivalent);• 2nd Generation Intel Core i5 2620M Processor, 2.70GHz (Turbo up to 3.40GHz),

1333MHz, 4MB L3 Cache;• Mobile Intel HM65 Chipset;• 14” diagonal LED-backlit HD anti-glare (1366x768);

Page 25: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 18 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

• Intel HD Graphics 3000;• 4 GB 1333 MHz DDR3 SDRAM – Dual Channel Active;• 250 GB 7200 RPM 2.5 inch hard drive – or 120 GB Intel SSD;• DVD R/W SuperMulti DL Drive;• Full Keyboard;• Broadcom 4313 GN 802.11 g/b/n 1x1 WiFi Adapter;• 65W Hardware Kit;• 6 cell Li-ion Battery; and• Integrated Gigabit Ethernet

Computers shall have Citrix Receiver installed, which can be accessed at:

http://receiver.citrix.com/

2.7 DEPARTMENT’S CONSULTATION AND WRITTEN COMMENTS

The Department’s review, oversight, audit, and inspection activities are referred to as“consultation and written comment” (see Part 2, DB §105-16). The Department’s consultationand written comment will be provided to the Design-Builder in writing. The Design-Builder shallbe responsible for addressing the Department’s comments and shall indicate in writing whetherit concurs with the comments. If the Design-Builder does not concur with the Department’scomments, then the Department and Design-Builder will work together to resolve the issuebefore proceeding.

If agreement cannot be reached, the issue must be resolved as provided in the ContractDocuments for dispute resolution in accordance with Part 2 DB §109-10.

2.8 PROJECT WISE

ProjectWise shall be used to organize, manage and archive electronic Project designdocuments for NYSDOT. These documents typically include but are not limited to:

All design reports including drafts and final;

All studies and supporting reports;

Permits;

Survey and ROW mapping;

Photos taken prior to and during design;

CADD and 2D/3D models files including current NYSDOT-supported Microstation andInRoads file formats;

Engineering calculations to support designs;

All electronic plan sheets;

Engineer of Record’s estimate based on Payment Breakdown Structure; and

Public Information.

All files posted to ProjectWise shall be in accordance with the file naming convention andsubmission procedures as defined in Appendix 14 of the NYSDOT Project Development

Page 26: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 19 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Manual. In addition the Payment Breakdown Structure (PBS) shall be used in the file namingconvention, specifically the work item number in the PBS.

The Design-Builder may obtain a ProjectWise account by contacting the Department’s ProjectManager and providing the required account information per Appendix 14 of the ProjectDevelopment Manual.

The Design-Builder shall ensure that all electronic design documents are stored in ProjectWise.Updates of engineering documents shall be provided on a monthly basis.

Page 27: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 20 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 3 ENVIRONMENTAL COMPLIANCE

3.1 SCOPE

Except as otherwise detailed herein, the Design-Builder shall be responsible for preparing itsdesign, obtaining environmental approvals, carrying out construction activities, performingQuality Control, and undertaking other activities as needed to ensure compliance with theProject’s Environmental Requirements and all applicable environmental laws and regulations.

This Project Requirement identifies certain required actions to be performed by the Design-Builder to ensure that the Environmental Requirements are complied with throughout theduration of the Project.

3.2 ENVIRONMENTAL APPROVALS

The Department has determined that this Project is a NEPA Class II Categorical Exclusion.Class II actions that do not individually or cumulatively have a significant environmental effectare excluded from the requirement to prepare an Environmental Impact Statement (EIS) or anEnvironmental Assessment (EA).

Because the work has an effect on two (2) National Register Eligible structures (BINs 5500870and 5500890), the Department has determined that this Project is a SEQR Non-Type II Actionin accordance with 17 NYCRR Part 15 - Procedures for Implementation of State EnvironmentalQuality Review Act. SEQR Non-Type II projects include actions for which the environmentalimpacts are not clearly established and require an Environmental Assessment (EA). The ProjectScoping Report/Final Design Report acts as the Project’s Environmental Assessment underSEQRA.

The Design-Builder is responsible for obtaining all environmental permits and approvals neededfor the Project. Approvals previously secured for the Project are included in Part 7 –Engineering Data.

The following environmental approvals have been obtained by the Department:

BIN 1005080

o A Federal Aid Notification, including a Federal Consistency Assessment Form,was submitted to New York State Department of State (NYSDOS) on April 1,2014 and general concurrence was received on May 27, 2014.

o In a letter received by the Department on April 3, 2014, New York StateDepartment of Environmental Conservation (NYSDEC) concurred with theDepartment’s assessment that the proposed work is not likely to result in a “take”of will not require an Incidental Take Permit for NY-listed species, pursuant tomitigation measures detailed in Part 3 Section 3.4 - Threatened And EndangeredSpecies Coordination.

o In a letter received by the Department on May 19, 2014, the United States Fishand Wildlife Service (USFWS) concurred with the Department’s determinationsas detailed in Part 3 Section 3.4 - Threatened And Endangered SpeciesCoordination, pursuant to the commitments therein.

Page 28: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 21 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

BIN5500870

o A Determination of No Significant Effect (DONSE) was filed in accordance with17 NYCRR 15.10.

o In a letter received by the Department on April 3, 2014, the NYSDEC concurredwith the Department’s assessment that the proposed will not require anIncidental Take Permit for work is not likely to result in a “take” of NY-listedspecies.

o In a letter received by the Department on May 19, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

o Per New York State Historic Preservation Act Section 14.09 the Departmentprepared a No Adverse Effect Finding Document and sent it to SHPO.SHPO concurred with the determination in a letter dated May 28, 2014.

BIN 5500890

o A Determination of No Significant Effect (DONSE) was filed in accordance with17 NYCRR 15.10.

o In a letter received by the Department on April 3, 2014, the NYSDEC concurredwith the Department’s assessment that the proposed work will not require anIncidental Take Permit for is not likely to result in a “take” of NY-listed species.

o In a letter received by the Department on May 19, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

o Per New York State Historic Preservation Act Section 14.09, the Departmentprepared a No Adverse Effect Finding Document and sent it to SHPO;SHPO concurred with the determination in an email dated March 28, 2014.

BIN 5500969

o NYSDOT concluded that there will be no historic properties affected by theproject. NYSDOT requested concurrence from the SHPO on March 28, 2014.SHPO concurred with the determination in a letter dated May 28, 2014.

o In a letter dated December 8, 2014 USFWS concurred with the Department’sdeterminations as detailed in Part 3 Section 3.4 - Threatened And EndangeredSpecies Coordination, pursuant to the commitments therein.

BIN 1040550

o In a letter dated August 18, 2014, the NYSDEC concurred with the Department’sassessment that the proposed work will not require an Incidental Take Permit foris not likely to result in a “take” of NY-listed species, pursuant to mitigation

Page 29: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 22 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

measures detailed in Part 3 Section 3.4 - Threatened And Endangered SpeciesCoordination.

o In a letter received by the Department on May 21, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

BIN 5521680

o In a letter received by the Department on April 3, 2014, the NYSDEC concurredwith the Department’s assessment that the proposed work will not require anIncidental Take Permit for is not likely to result in a “take” of NY-listed species.

o In a letter received by the Department on May 19, 2014, USFWS concurred withthe Department’s determinations as detailed in Part 3 Section 3.4 - ThreatenedAnd Endangered Species Coordination, pursuant to the commitments therein.

The Department has not secured any environmental permits associated with this project. It isthe Design-Builder’s responsibility to secure all environmental permits associated with andrequired for construction of this project.

If during detailed design the Design-Builder introduces design elements, variations, ormethodologies that may result in environmental effects beyond those already identified duringpreliminary engineeringdesign, then the Design-Builder shall re-evaluate environmental impactsfor this Project. This requirement also applies to proposed variations which may affectresources covered under Section 106, Section 4(f), Executive Order 11990 (wetlands), andother applicable federal and state environmental regulations. The environmental screeninglimits used during preliminary engineering design are provided as Reference Documentsin Part7 – Engineering Documents. The Design-Builder is responsible to obtain all environmentalpermits and approvals needed for the Project.

3.3 REQUIREMENTS

3.3.1 General

A) The Design-Builder shall procure all Environmental Approvals as needed for all Design-Builder-located areas, including staging, borrow and disposal sites, and any other areasused by the Design-Builder, for its convenience, in the execution of the Project;

B) The Design-Builder shall be responsible for preparing all permit application materials andfor obtaining all Environmental Approvals necessary for the Project and not alreadyobtained by the Department, including those that are precipitated by the Design-Builder’s design or actions that deviate from the requirements of any acquiredpermit(s) (if any). For any such environmental permits/approvals. For any suchpermits/approvals required to be obtained by the Design-Builder that must formally beissued in the Department's name, the completed application shall be sent to theDepartment for signature and transmission to the permitting agencies. The Design-Builder shall assume five (5) business days to be taken by the Department for thisaction and for each time correspondence passes between the Design-Builder and aregulatory agency. Department’s name, other than the SPDES NOI, the Design-Builder

Page 30: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 23 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

shall allot 5 business days for the Department to review and comment on the completenessand adequacy of application materials. It shall then be at the Design-Builder’s discretion toaddress any Department comments or elect to risk moving forward with the applicationmaterials as submitted. The Department will cooperate with the Design-Builder asreasonably requested by the Design-Builder, including execution and delivery ofappropriate applications. The Department will not be responsible for any delay or additionalcosts associated with the Design-Builder’s environmental permit/approval applications.

C) The Design-Builder shall be solely responsible for compliance with and violations of anyEnvironmental Requirements; and

D) The Design-Builder is responsible for any fines, non-compliance, violations, or damagesincurred by reason of failure of the Design-Builder to comply with Environmental Approvals.Resulting fines or damages shall be deducted from monies owed the Design-Builder.

E) NYSDEC Article 15 – Streams

For any locations involving work in or within 50 feet of a stream, compliance with theNYSDEC-NYSDOT Memorandum of Understanding (MOU) regarding EnvironmentalConservation Law Articles 15 and 24 is required. The MOU is provided as a ReferenceDocument.

In-water work must occur between the allowable work periods listed in Table 3-1 NYSDECArticle 15 Stream Classifications and Allowable Work Periods, unless waived in writing byNYSDEC.

Table 3-1 – NYSDEC Article 15 Stream Classifications and Allowable Work Periods

BIN Road Stream/featurecrossed Classification Allowable Work

Period

5500870 Route 987D SAW MILL RIVER B, B(T) May 1 - Sept 30

1005080 Route 9 DICKEY BROOK C, C None NoRestriction

5500969 Route 987D KISCO AVE. N/A None NoRestriction

1040550 Route 208 MOODNA CREEK C, C None NoRestriction

5500890 Route 987D SAW MILL RIVER B, B(T) May 1 - Sept 30

5521680Route

97EHPADPW Road

HUTCHINSON RIVER C, C None NoRestriction

F) New York City Water Supply Watershed

BIN 5500969: This bridge is located within the boundaries of the New York City (NYC)Water Supply Watershed – East of Hudson. Coordination, including final design plans and

Page 31: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 24 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SWPPP review, with the NYC Department of Environmental Protection East of HudsonStormwater Program is required in accordance with NYS Executive Order 51 (EO 51) andthe Memorandum of Understanding (MOU) between NYSDOT and NYCDEP. EO 51 andthe MOU are provided as Reference Documents. The Design-Builder shall allow 30 days forreview by NYCDEP.

G) Section 106 of the National Historic Preservation Act and Section 14.09 of the NYS HistoricPreservation Act

BIN 5500870: A historic property eligible for inclusion in the National Register of HistoricPlaces, the bridge carrying Bedford Road over Saw Mill River Parkway (BIN 5500860), islocated within the Project’s area of potential effect. The Department has committed to theState Historic Preservation Officer (SHPO) that there would be no physical changes to themasonry arches and parapets, or distinctive arcaded brick corbels of BIN 5500860.

BIN 5500890: A historic property eligible for inclusion in the National Register of HistoricPlaces, the bridge carrying Pleasantville Road and Route 117 over the Saw Mill Parkwayand Saw Mill River (BIN 3037170), is located within the Project’s area of potential effect.The Department committed to the SHPO that there would be no impacts to the contributingelements of historic BIN 3037170 on the façade of the bridge elevation. Specifically, thereshall be no physical changes to the masonry arches and parapets, or distinctive arcadedbrick corbels of BIN 3037170.

H) Regulated Floodways and Floodplains

BINs 1040550, 5500870, 5500890, 5521680, and 1005080: These BINs are located withinthe limits of 100 year floodplains and/or regulatory floodways. NYSDOT has committed tohaving no encroachment on the floodways.

I) Stormwater Outfall Mapping

BINs 5500969, 5500870, 5500890, 5521680, and 1005080 are within a mapped MunicipalSeparate Storm Sewer System (MS4). Therefore, new and relocated stormwater outfallsare required to be mapped per Engineering Instruction (EI) 07-033, Stormwater OutfallMapping Inventory Guidance for NYSDOT Regional Data Exchange. Information is to bedirected to the NYSDOT Project Manager.

J) BINS 5500870 and 5500890 Tree Removal Restriction

Part 3 Section 3.5 indicates that the environmental screening area for the two above bridgesincludes an estimated tree removal of 110 and 140 trees respectively. However, treeremoval at these two bridges shall be minimized and will not be permitted west of the SawMill River.

K) Noise Abatement Measures

BIN 5500969: The Department has committed to noise abatement measures in the form of anoise barrier located along the north side of the Saw Mill River Parkway and west of thebridge to provide noise reduction for the residents of Pinecrest Manor.

See Section 10 for Noise Barrier structural requirements.

Page 32: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 25 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

L) Lead Based Paint

BIN 5500969: Lead-based paint, a hazardous material, is present on this bridge. TheDesign-Builder shall comply with the hazardous materials and lead safety and healthrequirements specified in DB §107.

3.3.2 Environmental Plans

The Design-Builder shall be responsible for preparing the following documents in conformitywith all Environmental Requirements. The Design-Builder shall submit the followingEnvironmental Documents:

A) Stormwater Pollution Discharge Elimination System (SPDES) Permit application; see SoilErosion and Water Pollution Control;

B) Stormwater Pollution Prevention Plan (SWPPP; see Section 17 – Drainage andStormwater).

3.3.3 Soil Erosion and Water Pollution Control

The Design-Builder shall prepare and maintain on file a SWPPP complying with the New YorkState SPDES General Permit for Stormwater Discharges from Construction Activities (GP-0-10-001 or current version). The SWPPP is to include but is not limited to construction entrance(s),construction phasing, drawings showing size and location of permanent (e.g., swales, checkdams, etc.) and temporary (e.g., silt fence, temporary seed, mulch, etc.) erosion controls, anddetails. The SWPPP shall include plans and details for water quality volume, runoff reductionvolume, stream channel protection, overbank flood, and extreme flood controls, as appropriate.The Design-Builder shall apply for coverage under the SPDES General Permit for StormwaterDischarges from Construction Activities after preparing a compliant Erosion Control Plan andSWPPP as noted. The Design-Builder shall prepare the final SWPPP and a conforming Noticeof Intent (NOI), sign/complete the Contractor/Subcontractor SPDES Permit Certification form(CONR 5), and submit the NOI to NYSDEC for approval. Discharges covered under the SPDESgeneral permit shall not commence until the date authorized on the SPDES AcknowledgementLetter from NYSDEC. The SWPPP can be subject to review and comment by the Departmentand/or NYSDEC upon request of the Design-Builder.

For BINs 1040550, 5500870, 5500890, 5521680, and 1005080, soil disturbance in excess ofone (1) acre will require a SWPPP. For BIN 5500969, since it is in the New York CityWatershed east of the Hudson River, soil disturbance in excess of 5,000 square feet will requirea SWPPP. If a SWPPP is required for both BIN 5500870 and BIN 5500890, one SWPPP shallbe prepared to cover both of these sites.

See also Section 17 – Drainage and Stormwater.

3.3.4 Asbestos-Containing Materials

An Asbestos Screening and Assessment of the impacted right-of-way and structures wasperformed by a NYS Department of Labor licensed firm using certified inspection staff.Asbestos-containing materials identified during this screening/assessment were sampled andpositively analyzed for asbestos content; suspect asbestos-containing materials are presumed

Page 33: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 26 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

positive. The complete Asbestos Assessment Reports are located in the Reference Documentssection of the Project Web Site.

BINs 1040550, 5500969, and 5500890: Confirmed or suspect asbestos containing material(s)(ACM) were identified.

BIN 5500890: subsequent to completion of the Asbestos Assessment Report, the Village ofPleasantville identified the presence of an 8” transite sanitary sewer pipe in the work area. Thispipe shall be considered an assumed ACM.

BINs 5500870, 5521680, and 1005080: No confirmed or suspect ACM was identified.

ACMs may be associated with various underground utilities located within the Project limits.Any ACMs associated with private utilities shall be the responsibility of the utility owner. AnyACMs associated with public utilities shall be the responsibility of the Design-Builder. TheDesign-Builder shall coordinate with the private utility owners for the remediation of any ACMswhich may be identified.

The Design-Builder shall be responsible for the abatement design, containment, removal anddisposal of all confirmed and assumed asbestos containing materials if such materials will bedisturbed during the performance of the Work, except as noted in Section 3.3.7 5 below. Theremoval and disposal of ACMs shall be performed in accordance with the applicable safety andhealth codes and all applicable State and Federal regulations. See also DB Section 112-5.5,Asbestos.

If during the course of work, any asbestos-containing materials not already documented in theasbestos screening report or project record plans are encountered, the Design-Builder shall beresponsible for performing all abatement, containment, removal and disposal activities andprovide project/air monitoring services as part of this Contract in accordance with 12 NYCRR56. Furthermore, should removal and disposal of asbestos-containing materials be required, itshall be performed in accordance with all applicable safety and health codes. This additionalwork shall be paid for under the Force Account pay item.

New York State Department of Labor (NYSDOL) asbestos licensure and applicable staffcertification(s) are required for Work where confirmed or presumed asbestos-containingmaterials are impacted. All necessary asbestos inspection, Project design and project/airmonitoring work shall be conducted in conformance with policy and guidance provided in theNYSDOT Environmental Procedures Manual (EPM)/The Environmental Manual (TEM).

At the completion of the asbestos abatement activities, the Design-Builder shall be responsiblefor providing two (2) hard copies and one (1) electronic copy of the complete set of abatementrecord documents, including chain-of-custody records, worker sign-in/sign-out sheets, proof ofworker certifications, and other such records required by law to be kept on record. The recordsfor each bridge shall be assembled as a single, logical report, with all information boundtogether. The information shall be directed to the NYSDOT Project Manager.

Page 34: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 27 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

3.3.5 Inaccessible/Assumed ACMs

ACMs may be associated with various underground utilities located within the Project limits.Any ACMs associated with these utilities shall be the responsibility of either the private utilityowner or the Department (for municipally-owned utilities). The Design-Builder shall coordinatewith the private utility owners for the remediation of any ACMs which may be identified.

3.3.6 Environmental Plan Deliverables

At a minimum, the deliverables shall include the items listed in Table 3-2 – EnvironmentalCompliance Deliverables. for the Department’s review.

Each of the deliverables listed in Table 3-2 – Environmental Compliance Deliverables, shall beprovided to the Department 30 days prior to the relevant on site activity, including start ofconstruction.

Table 3-2 – Environmental Compliance Deliverables

DeliverableNumber of Copies Reference

SectionDeliverable

DateHardcopy Electronic

Stormwater Pollution Discharge EliminationSystem (SPDES) Notice of Intent andStormwater Pollution Prevention Plan(SWPPP)

3 1 3.3.2 60 days¹

¹ Prior to start of construction.

² Prior to relevant on-site activity.

3.4 THREATENED AND ENDANGERED SPECIES COORDINATION

A Biological Assessment (BA) was prepared for BIN 5500969, and a Biological Evaluation (BE)was prepared for BINs 1040550, 5500870, 5500890, 5521680, and 1005080, to addresspotential impacts on federal and state protected threatened, endangered, or proposed species.The BA is included in Part 7 – Engineering Data. The BEs are available upon request. For allsix locations, a may affect, not likely to adversely affect determination was concluded for Indianabat and northern long-eared bat. Tree removals (direct count or acreage) are estimated asfollows:

BIN 1040550 - 48 trees;

BIN 5500969 - 3.3 acres identified in the BA;

BIN 5500870 – 110 trees;

BIN 5500890 – 140 trees;

BIN 5521680 – 9 trees;

BIN 1005080 – 20 trees.

Actual tree removals may be less.

Page 35: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 28 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Tree removals in excess of those stated above may require the Department to coordinate withthe lead Federal Agencies and US Fish and Wildlife Service. The Design-Builder shall preparethe necessary documentation for the Department’s use in gaining the needed approvals.

For BIN 5500969, a may affect, not likely to adversely affect determination was also concludedfor the bog turtle.

In order to maintain USFWS and/or NYSDEC threatened and endangered species concurrence,the Design-Builder shall comply with the following mitigation measures:

All locations: Removal of any trees greater than 3 inches in diameter at breast heightshall occur between October 31 and March 31.

BIN 5500969: The Design-Builder is responsible for fulfilling all constructioncommitments to USFWS that are contained in the BA for this bridge. Constructioncommitments include, but are not limited to, the following:

Work between 6 8 pm and 8 am is prohibited. The tree removal areas shall bedelineated with silt fence and/or orange fencing. A double row of silt fence shall beinstalled outside the Wetland D/K-31 boundary to exclude any potential bog turtles thatmay wander into the work zone and minimize both soil disturbance and potentialsedimentation. The silt fence installation shall occur between October 31 and March 31.Placement of heavy equipment needed for tree removal from Wetland D/K-31 shall berestricted to the roadway and/or road embankment whenever possible. If work isneeded in this wetland, timber mats shall be used to support heavy equipment to reducesoil disturbance and compaction. If the placement of timber mats occurs between Apriland October (outside the bog turtle hibernation window), a bog turtle specialist with astate permit will monitor for turtles and remove the turtles from the work area, if any arefound.

BINs 5500870 and 5500890: The tree removal at these two bridges shall be minimizedand is not permitted west of the Saw Mill River. Therefore it is anticipated that the actualtree removal quantities will be considerably less than the estimated 110 and 140 trees.

BIN 5521680: It is anticipated that the Department will cut the trees before March 31,2015. The Design-Builder shall satisfy themselves that the tree cutting has occurred.Removal of the cut trees shall be the responsibility of the Design-Builder.

BIN 1005080: In order to avoid impact to wintering bald eagles, no blasting (if required)shall occur from December 1st to March 31st. Perch deterrents shall be placed on anycranes or other tall equipment.

Page 36: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 29 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 4 GENERAL PROJECT SCOPE OF WORK

4.1 SCOPE

The Design-Builder shall perform all Work necessary to prepare the Project site for construction,maintain the site in suitable condition during all stages of construction and provide cleanup andrestoration of the construction site and all disturbed areas.

4.2 STANDARDS

The Design-Builder shall perform the Work in accordance with the applicable Standards, DesignCodes and Manuals cited in Section 1.6, unless otherwise stipulated in this ProjectRequirement, or otherwise applicable to the Project.

4.3 REQUIREMENTS

The Design-Builder shall prepare site work plans showing the extent of site works; disposal andstorage locations; facility removal details; and approximate volumes; and shall provide foruninterrupted Department maintenance and operations. All regulated waste shall be handledaccording to Section 3 – Environmental Compliance.

The site work may include but not be limited to: clearing and grubbing; removal of debris fromthe waterway at the bridge location; excavation and embankment; removal of pavement andpavement markings, road barriers, soil, drainage facilities, fencing, signs, and miscellaneousstructures; subgrade preparation and stabilization; dust control; removal of abandoned above-ground and shallow piping and wiring, valves, meters, and other waste materials; and aggregatesurfacing.

Unless specified otherwise in the Contract Documents, the Design-Builder shall remove allobstructions down to a minimum of 2 feet below the existing or proposed surrounding groundelevation or to the elevation necessary to properly construct the Work, whichever is lower.

The Design-Builder shall grade and restore all disturbed areas to match the existing surroundingground elevation unless otherwise specified elsewhere in the Contract Documents. TheDesign-Builder shall cut pavement or sidewalk to full depth with straight lines at removalterminations.

The Design-Builder shall over-excavate as necessary to remove unsuitable material from underthe footprint of pavements and structures and backfill with properly compacted suitable material.Topsoil may be stripped, stockpiled, and reused within the Project Limits.

The Design-Builder may only reuse materials on the Project that meet the requirements forgrading and backfill materials. Disposal of obsolete, unsuitable, and surplus material is notallowed within the Right-of-Way and shall be removed. All material to be removed shall becomethe property of the Design-Builder and shall be disposed of off-site.

4.3.1 Field Office

The Design-Builder shall provide, furnish and maintain a Field Office for use by the Departmentin accordance with the NYSDOT Standard Specifications. The Field Office shall be a Type 1Office as described in the NYSDOT Standard Specifications. The Field Office shall be located at

Page 37: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 30 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

the same address as the Construction Manager, or within a quarter one (1) mile from theDepartment’s Construction Quality Assurance Engineerof the onsite inspection office.

4.3.2 Construction Vehicles on Bridge

The Design-Builder is prohibited from running equipment that does not operate on rubber tires(milling machines, rollers, etc) across newly constructed bridge decks unless proper precautions(mats, etc) are provided to prevent damage to the deck. The methods used to move equipmentacross bridge decks shall be subject to approval by the Construction Inspection ProfessionalEngineering Firm with comments from the CQAE.

4.3.3 Salvage

All materials removed from the Project site shall become the property of the Design-Builder.

4.3.4 Surplus Quantity

Section not used.

4.3.5 Sidewalk Plowing Coordination During Winter Shutdown

Prior to the end of the construction season, the Design-Builder shall provide the State a list ofnew sidewalks that are open to the public that will need to be plowed by the municipality duringthe winter months. Before winter shutdown, the Design-Builder shall ensure that all sidewalksare free and clear of obstructions, barricades, fixed objects, etc. that would interfere with thesnow plowing effort.

Page 38: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 31 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 5 SURVEYING AND GIS

5.1 SCOPE

The Design-Builder shall perform all surveying tasks necessary to undertake and complete theProject including but not limited to: acquisition of terrain data (topography); mapping ofroadways and appurtenances, features, bridges, and utilities as needed; locating boundaries;waterway surveys; contract control plan; construction and stakeout surveys; As-Built surveys;surveys that arise from other Project Requirements; asset inventory; and all other surveyingservices as necessary.

5.2 STANDARDS

The Design-Builder shall perform the surveying activities in accordance with the applicableStandards, Design Codes and Manuals cited in Section 1.6, unless otherwise stipulated in thisProject Requirement or otherwise applicable to the Project.

5.3 REQUIREMENTS

5.3.1 Project Survey Control

Survey control, if available, will be provided with the Reference Documents. The Design-Buildermay supplement that information or conduct complete new survey as necessary to perform allthe necessary surveys required to complete the Project, as the Design-Builder deemsappropriate.

5.3.2 Department-supplied Data

The Department will provide the Design-Builder with the following Survey-Related Data asReference Documents:

ROW / Highway Boundary Geometry; Survey / Photogrammetric Base Mapping Planimetrics; Survey / Photogrammetric Digital Terrain Model;

Acquisition Maps;

The Design-Builder shall be responsible for verifying any data used for the Project.

5.3.3 Survey Reports, Records and Maps

The Design-Builder shall submit to the Construction Inspection Professional Engineering Firm,all information listed under the ‘Documentation’ sub-section of each chapter of the NYSDOTLand Surveying Standards and Procedures Manual that is applicable to its survey work. TheDesign-Builder shall index and submit all calculations, notes, computer files, raw data, Projectreports, meeting notes, correspondence, digital images, maps, corner records, records ofsurvey, aerial photogrammetric products, centerline alignment maps, and other maps andrelated items.

The Design-Builder shall be responsible for ensuring that information submitted is compatiblewith the applicable NYSDOT CADD standards, software and operating systems and formats.

Page 39: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 32 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

All survey reports and maps, including bathymetric survey plans, shall be signed-and-sealed bya licensed New York State professional land surveyor.

5.3.4 Permanent Survey Markers

Section not used.

5.4 SURVEYING AND GIS DELIVERABLES

At a minimum, the Design-Builder shall submit the items listed in Table 5-1 - Survey and GISDeliverables to the Department.

Electronic measurement raw data shall be provided in electronic format only.

Where applicable, electronic copies of deliverables listed in Table 5-1 - Survey and GISDeliverables shall be supplied as per the specifications given in Chapter 20 of NYSDOT HDM.All relevant Bentley MicroStation® files (including .DGN files) and Bentley InRoads® files(including DTM, ALG files) shall be compatible with the MicroStation XM and InRoads XMsoftware versions.

Table 5-1 - Survey and GIS Deliverables

DeliverableNumber of Copies Delivery Schedule

(for final submission)Reference

SectionHardcopy Electronic

All surveyReports, Recordsand Maps

1 1 Not more than 30 daysafter Final Acceptance

5.3.3

GIS-format data - 1 (txt) Not more than 60 daysafter Final Acceptance 5.4

As-Built surveys 1 (signed and sealed) 1 Not more than 60 daysafter Final acceptance -

Page 40: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 33 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 6 RIGHT-OF-WAY

6.1 SCOPE

The Right-of-Way (ROW) for the Project has been acquired by the Department and the Right ofWay Acquisition Maps are included in Part 7. The Design-Builder shall perform all thepermanent Project Work within the limits shown on those Right of Way maps.

Right of ownership of all ROW and the improvements made thereon by the Design-Builder shallremain at all times with the Department. The Design-Builder’s right to entry and use of theROW arises solely from permission granted by the Department under the Contract.

6.2 REQUIREMENTS

6.2.1 Right-of-Way Fencing

Any ROW fencing that has been damaged due to construction of the Project or removed by theDesign-Builder shall be replaced by the Design-Builder with new ROW fencing meeting currentNYSDOT standards.

6.2.2 Property Interests Identified by the Design-Builder for its Convenience

The Design-Builder shall be responsible for all costs associated therewith for any temporaryland or other property required for the Design-Builder’s convenience outside the ROW Limits,such as for staging, lay-down, access, office space, temporary works, or other purposes. TheDesign-Builder shall assume responsibility for satisfying all Federal and State regulations,identifying, analyzing, and documenting the environmental impacts associated with theadditional space and securing all necessary consent, including that of the Department, prior toinitiating use of the space, in accordance with DB §107-22.

Page 41: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 34 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 7 PUBLIC INVOLVEMENT

7.1 SCOPE

The goal of the public involvement activities is to inform the public and agency participants byproviding timely information throughout the design and construction process. The Design-Builder shall be responsible for supporting and cooperating with the Department with all publicinvolvement activities.

7.2 STANDARDS

The Design-Builder, in close coordination with the Department, shall perform the PublicInvolvement/Notification activities in accordance with the NYSDOT Project DevelopmentManual: Appendix 2, Public Involvement Manual.

7.3 REQUIREMENTS

7.3.1 Public Notification Plan, Stakeholder Coordination Meetings and GeneralOutreach Activities

The Design-Builder shall have the primary responsibility for assisting the Department indeveloping and implementing of the Public Notification Plan (PNP); assisting in identifyingProject stakeholders at each bridge location; assisting in the logistics for holding coordinationstakeholder meetings; and assisting in providing on-going outreach activities for the Project. Allstakeholder coordination meetings and outreach efforts shall be coordinated with theDepartment’s Project Manager (PM). The Department’s PM shall be the lead at all publicnotification and/or stakeholder meetings and therefore shall be in attendance at all publicstakeholder coordination meetings and public meetings. All public communication activitiesmust be reviewed and approved by the Department’s PM. The documentation of all stakeholdercoordination meetings and public meetings shall be the responsibility of the Design-Builder.

7.3.2 Public Notification Plans:

The Design-Builder shall assist in developing a Project Notification Plan (PNP) for each bridgelocation which shall involve the inclusion of all the requirements listed in this Section 7. ThePNP shall include a chronological list of public involvements tasks, description of tasks,responsible parties, and tentative dates for the execution of each task. The PNP will serve as aliving document and updated regularly by the Department with assistance from the Design-Builder.

The Design-Builder shall submit an initial draft PNP for each required bridge location for reviewby the Department’s PM. The initial draft(s) shall be submitted for the intended bridge location(s)to be under construction in 2015 not more than 30 calendar days following the Noticeto Proceed (NTP). The remaining draft PNPs for bridges to be under construction in 2016 and2017 shall be delivered to the Department’s PM no later than the end of 2015 for work in 2016and the end of 2016 for work in 2017 and shall be delivered in the order of the bridge locationsin the Design-Builder’s construction schedule. All draft PNPs should be developed usingthe timeframes provided below, unless the date of the NTP and implementation of any WorkZone Traffic Controls including off-site detours and/or the start of significant constructionactivities in 2015 does not allow. In that case, the Design-Builder should prepare a draft PNPfor that bridge location that best meets the timeframes listed below. However no work shallprogress at any bridge location without said final PNP and the conditions established below.

Page 42: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 35 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

7.3.3 Stakeholder Coordination Meetings:

TMC, Municipal Officials & Emergency Services Coordination Meetings: TheDesign-Builder shall be responsible for scheduling, in close coordination with theDepartment’s PM, these meetings and preparing meeting materials for municipal officialsand emergency services coordination meetings for each bridge location at least eightweeks prior to implementing Work Zone Traffic Controls including off-site detours and/orthe start of significant construction activities. The results of these meetings need to becoordinated, as specified by the Department’s PM, by the Design-Builder with theDepartment’s Regional Transportation Management Center (TMC). More than onecoordination meeting, per bridge site, may be required.

Public Information Meetings: A public information meeting is required for BIN1040550 Route 208 at Moodna Creek; BIN 5500969 SMRP/Kisco Ave.; BIN 5500870SMRP/SMR; and BIN 5500890 SMRP/SMR. The Design-Builder shall be responsiblefor scheduling the public information, in close coordination with the Department’s PM,and preparing presentation materials to inform the general public about the bridgeprojects and associated construction activities and the intended construction schedules.The public information meetings shall be held three weeks prior to implementing workzone traffic controls including off-site detours and/or the start of significant constructionactivities.. The Design-Builder will be responsible for securing an appropriate meetinglocation, scheduling a date, and inviting the public, including key Project stakeholders.

The public information meetings may include PowerPoint presentations, informaldiscussion about the planned work, and upcoming construction activities, Work ZoneTraffic Control, traffic detours, anticipated construction impacts, and Project schedule.Design-Builder is responsible for preparing all meeting handouts, PowerPointpresentations, and displays.

The Design-Builder and the Department PM, Regional PIO and RPIC shall meet at thePoughkeepsie State Office Building at least one week in advance of any publicinformation meetings to review draft agenda, discuss meeting materials needs, andreview logistics. All public meeting materials must be reviewed and approved by theDepartment’s PM prior to the public informational meeting. Public meeting materialsshould be submitted to the Department’s PM at least two days prior to meeting at thePoughkeepsie State Office Building.

In addition to the public meeting requirements outlined above, for BIN 5500969SMRP/Kisco Ave., the Design-Builder will be responsible for scheduling and providing asecond public information/community meeting for the residents of the Pine Crest Manorduring the same week as the general public meeting. Meeting materials shall beprovided in English and Spanish for this second meeting.

7.3.4 General Outreach Activities:

Notification Letters to Elected Officials, Municipal Officials, School Districts andTransit Operators: The Design-Builder will be responsible for preparing Projectnotification letters on DOT letterhead and DOT envelopes (supplied by DOT) for eachbridge location, for signature by the Regional Director, and distribution by the Design-Builder to the following key stakeholders, but not limited to: state and federal electedofficials, municipalities, school districts and transit operators. Design-Builder should

Page 43: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 36 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

work with the Department’s PM to generate a list of key Project stakeholders. Projectnotification letters should be mailed four weeks prior to implementing Work Zone Trafficcontrols including off-site detours and/or the start of significant construction activities.Draft notification letters should be submitted to the Department’s PM for review andsignature by Regional Director at least one week prior to scheduled letter mailing.

General Public Notification & NYRideShare: The Department will has identifyied athegeographical area of potential Project construction impact using zip codes for eachbridge location, with the exception of BIN 1005080 Route 9/Dickey Brook and BIN5521680 EHPA DPW Rd./Hutchinson River. The list of zip codes identified for eachbridge is available as a Reference Document. The Department estimates approximately230,000 business and households are present within the zip code areas identified. Theresidents and businesses within the geographical areas identified shall be notified viaUS Mail postcard of the Project including the following information: anticipatedconstruction start, brief Project description, NYSDOT’s 24-hour project phone number,NYSDOT’s Project email address, and the anticipated completion date. Draft postcardand associated zip codes (graphically shown in a map pdf format) should be submittedto Department’s PM one week prior to mailing date., based. Postcards should be mailedby Design-Builder three weeks prior to implementing Work Zone Traffic Controlsincluding off-site detours and/or the start of significant construction activities, based.The intent of this mailing is to inform potential travelers in the immediate Project vicinityand potential commuters using the route on a daily basis of planned Project activities sothat they may choose to take an alternate route or allow for additional travel time.

For BIN 1005080 Route 9/Dickey Brook and BIN 5521680 EHPA DPW Rd./HutchinsonRiver project notification as outlined above needs to be directed only to adjacentproperty owners and nearby neighborhoods, identified by NYSDOT, potentially impactedby construction access and activities.

The Design-Builder shall provide the Department’s PM Project information, as describedabove, three weeks prior to start of significant construction activities for use anddistribution by the Department’s partner “NYRideShare” through the use of an emailblast. The intent of this email blast is to inform commuters and corporations of plannedProject activities which may impact travel times and commuter route decisions.

Website: The Design-Builder shall provide monthly Project updates, including anarrative, photos, and appropriate graphic for each bridge location. Website materialsmust be submitted to the Department’s PM for review and approval. Some of thisinformation may be prepared primarily for other outreach activities but may need to bereformatted by the Design-Builder for use on the DOT website. The Project informationshall be available for posting on the website 30 days prior to any work beginning at anybridge location.

24-Hour Project Phone Number: The Design-Builder shall provide for a toll-freeProject phone number. The Project phone line and email address will be monitored bythe Construction Quality Assurance Engineer (CQAE) or his designee.

Project Contact Database: All contacts provided by the Department and/or made bythe Design-Builder shall be logged into a database that is capable of tracking all contactsmade, per bridge location. The Design-Builder shall create the database using MicrosoftAccess. The database, at a minimum, shall list contact name, affiliation, address, phone

Page 44: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 37 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

number, and email. The database shall be populated by the Design-Builder withstakeholder information gathered by the Department and/or the Design-Builder. Thecontact information will be used for mass mailings, invites to public information meetings,and mailing project notifications as necessary. The Project contact database shallinclude, but not be limited to, residents, elected state and federal official(s), municipalofficials, business owners, emergency services, schools, transit operators,environmental groups, and so on.

7.3.5 Media Relations

Media Inquiries: All media inquiries, requests for interviews from local print or broadcast newsmedia, trade magazines or other media outlets must be referred to the Department’s PM fordirection. The Region’s PIO will coordinate and respond to all media requests. In emergencysituations, the Design-Builder shall immediately notify the Department’s PM of any situationsthat may involve the media. The Design-Builder shall alert all project personnel about thispolicy.

Press Releases: Upon request by the Department’s PM, the Design-Builder shall draft a pressrelease announcing public information meetings, the start of construction, and completion of theproject for use by the Regional PIO.

Travel Advisories: The Design-Builder shall provide the Department’s Construction QualityAssurance Engineer (CQAE) two week advance notice of: the commencement of constructionwork; any lane closures; road closures; or changes to traffic patterns. This will allow for timelynotice to the traveling public with the issuance of travel advisories by the Regional PIO. TheRegional PIO will develop the draft travel advisories for content and quality review by theDesign-Builder and the Department’s CQAE. The travel advisories will be finalized anddistributed to the press and appropriate state elected officials, and posted on the Projectwebsite by the Regional PIO.

Page 45: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 38 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 8 UTILITIES

8.1 SCOPE

The utility requirements set forth in Part 4 – Utility Requirements and DB §102-5 present theDesign-Builder’s responsibilities as they relate to existing and/or new utilities, the manner inwhich utilities shall be protected, relocated, upgraded, constructed or incorporated into theconstruction, and responsibilities for the Work.

8.2 STANDARDS

The Design-Builder shall perform all utility activities in accordance with the ContractRequirements, the applicable Standards, Codes and Manuals listed in Section 1.6 or otherwiseapplicable to the Project, and the standards required by the various utility companies affected bythe work.

8.3 GENERAL REQUIREMENTS

The Design-Builder shall examine the record plans of the work site, make a field survey of thework site and examine all other available documents to determine the type and location of allutilities that may be affected by the Design-Builder’s Work. Before any work begins the Design-Builder shall inform the Department’s Project Manager what utilities are present and how theymay be affected by the work.

The Design-Builder, in coordination with the Department’s Project Manager (or designee) andthe Regional Utility Engineer, shall meet with all the affected Utility owners or operators for thepurpose of discussing the effect on the utility facilities and to agree on a plan to maintain,protect, relocate, reinstall, or other action that may be necessary for the work to progress.

All utilities must be maintained, supported and protected during construction, unless otherwisedirected by the utility owner. Any damage to utilities due to the Design-Builder’s operationsshall be repaired at the Design-Builder’s expense.

Any utility conduit, conductor, splice box, pull box or other item that is part of a utility system orstreet light system that is embedded in a concrete deck, sidewalk or other concrete element thatis being removed and replaced as part of this Project shall be replaced and its locationcoordinated with the utility owner unless the utility owner indicates that replacement is notrequired. The design and construction of the replaced utility shall be in conformance with thecurrent standards of the Utility owner.

The Design-Builder shall make good any damage and consequential damages to those utilitiescaused by his operations. If the nature of the damage is such as to endanger the satisfactoryoperations of the utilities and the necessary repairs are not immediately made by the Design-Builder, the work may be done by the respective owning companies and the cost thereofcharged against the Design-Builder.

The Design-Builder shall provide notice to the Construction Quality Assurance Engineer (CQAE)at least two weeks before construction begins on any portion of the Project. The CQAE willnotify the Regional Utility Engineer of the pending construction and of any planned interruptionsto service. It should be noted that utility companies set their own notification time frames andrequirements. Preliminary time frames have been identified in Part 4 – Utility Requirements ofthese Contract Documents. The Design-Builder shall coordinate with respective Utility Owners.

Page 46: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 39 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

8.3.1 Utility Relocation Agreements

It is anticipated that the required Final Utility Work Agreements will be executed between theDepartment, the Design-Builder and the owners of impacted utilities once the Design-Builderhas determined the final locations of the impacted utilities. See Part 4 for details on utilityinventory, coordination and relocations.

The Design-Builder shall be responsible for the design and construction of these facilities asoutlined in Part 4 - Utilities.

8.3.2 Other Utility Conflicts

Please see Part 4 – Utility Requirements for additional utilities in the project vicinity that mayrequire relocation and modification.

Page 47: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 40 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 9 GEOTECHNICS

9.1 SCOPE

The Design-Builder shall be responsible for all Geotechnical Work necessary for the design andconstruction of all permanent and temporary structures, including assessing availableinformation, planning and implementing subsurface investigations, geotechnical analysis andreporting, geotechnical instrumentation and monitoring, and protection of existing infrastructure,structures and utilities in accordance with the requirements of the Contract Documents.

These requirements are considered as a minimum and do not include all possible conditionsthat may be encountered in the Design-Builder’s final design.

The Department has performed limited subsurface investigationsexplorations in the vicinity ofthe Projecteach bridge site. Information from these previous subsurfaceinvestigationsexplorations has been provided as Reference Documents. Presentation of thisinformation in no way implies that subsurface conditions are the same at other locations. ateach bridge site.

The Design-Builder shall be familiar with available geotechnical, geologic, seismic,hydrogeology, soils literature, and existing site conditions (both native and man-made), andshall interpret the existing geotechnical data pertaining to the Project Site. The Design-Buildershall form its own interpretation of the existing geotechnical data, and any additionalgeotechnical data the Design-Builder may obtain from its own investigations, and satisfy itself asto the nature and behavior of the ground and sub-soil, the form and nature of the Site, andnature of the Work that may affect its detailed design, construction method, and tools.

9.2 STANDARDS

The Design-Builder shall perform geotechnical activities in accordance with the ContractRequirements and the applicable Standards, Design Codes and Manuals cited in Section 1.6. orotherwise applicable to the Project.

9.3 DESIGN REQUIREMENTS

9.3.1 Geotechnical Work Plan

The Design-Builder shall prepare a geotechnical work plan, which shall include:

A) Design-Builder’s knowledge and understanding of the geotechnical, geologic, hydrogeologicand seismic settings of the Project Site and how the nature and behavior of the soil, rock,groundwater and subsurface conditions will affect the investigation, design and methods ofconstruction;

B) Identification of key constraints and a description of how the geotechnical activities designedand constructed meet these constraints; and

C) Types of subsurface investigations to be carried out for the Project, including locations anddepths of borings and other field testing with a narrative of the in-situ tests (if applicable) andlaboratory tests to be carried out.

Page 48: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 41 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

9.3.2 Geotechnical Investigations

The Design-Builder shall plan and conduct geotechnical investigations in accordance with theDepartment’s and AASHTO Standards for subsurface exploration programs, and as deemednecessary by the Design-Builder’s Lead Geotechnical Engineer to establish the geotechnicalconditions and to perform all geotechnical and foundation design and analysis.

The Design-Builder shall determine the State Plane coordinate location and ground surfaceelevation for each boring and field investigationexploration position, and shall show the actualcoordinates, and the datum version, the station and offset, and the elevation for each individualboring log or investigationexploration record in accordance with Department standards.Coordinates and Station and offsets for the borings shall be referenced to the Project stationing.Elevations shall be referenced to the Project datum and horizontal control system.

The proposer should note that ongoing movement of the existing substructures has been notedin past bridge inventory reports at BIN 5500969.

9.3.3 Minimum Number of Borings

The minimum number of borings required for various structures shall be as per the applicablestandards.

Information from existing borings provided by the Department as Reference Documents may becombined by the Design-Builder with the Design-Builder’s subsurface investigation to complywith the requirements of the applicable standards. It is the sole responsibility of the Design-Builder to determine if the existing borings referenced are suitable for use in the Project. It isthe sole responsibility of the Design-Builder to determine the extent to which further borings bythe Design-Builder are necessary for the Project.

9.3.4 Subsurface Investigation Records

For each subsurface exploration, the Design-Builder shall be responsible for keeping acontinuous and accurate log of the materials encountered and a complete record of theoperations. If Test Borings utilize a drilling mud process the Design-Builder shall only obtainwater level measurements at least four days after completion of the Test Boring. Records shallbe kept using the NYSDOT Subsurface Exploration Log Form (US Units)..

9.3.5 Software Requirements

The Design-Builder shall use Bentley gINT® or similar commercial software to develop andmaintain an electronic database of subsurface information including in-situ test and laboratorytest results, and to produce boringall final subsurface exploration logs or records.

9.3.6 Geotechnical Data Report

The Design-Builder shall be responsible for preparing a geotechnical data report, signed andsealed by the Lead Geotechnical Engineer. The geotechnical data report shall serve as afactual depiction of the subsurface conditions and at a minimum it shall include:

A) A detailed description of the investigation methods;

B) Complete records with summary tables of investigation;

Page 49: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 42 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

C) Complete records with summary tables of laboratory test results; and

D) An exploratory holeA subsurface exploration location plan, showing locations of anyexisting (pre-award) exploratory holessubsurface explorations for which data was used bythe Design-Builder plus locations of post-award exploratory holesubsurface explorationlocations undertaken by the Design-Builder.

The Design-Builder shall provide the Department with a copy of the final log for each subsurfaceinvestigation exploratory hole progressed.

9.3.7 Retaining Walls

The Design-Builder shall design and construct retaining walls, if required, in accordance withSection 10 of this Part 3 - Project Requirements. The Design-Builder shall provide retaining walldesigns to address internal, external, and global (overall) stability and settlements (total anddifferential) of the walls in accordance with the AASHTO LRFD Bridge Design Specifications. Allretaining walls shall be evaluated and designed for seismic stability internally and externally (i.e.sliding and overturning). With regard to overall seismic slope stability (global stability) involvinga retaining wall, with or without liquefaction, the Lead Geotechnical Engineer shall evaluate theimpacts of failure due to seismic loading, if failure is predicted to occur.

Gabion and crib walls (stretcher and header type) shall not be used. Earth retaining structureshall have a minimum service life of 75 years.

9.3.8 Geotechnical Instrumentation & Construction Monitoring

The Design-Builder shall develop, implement, and maintain a geotechnical instrumentationand/or construction monitoring plan to monitor vibrations, accelerations, vertical settlement, andlateral movement of temporary support structures and adjacent, ground, and surfaces, orexisting structures and infrastructure during construction, including ancillary structures andinfrastructure within the zone of influence of construction.

Wherever vibration-producing activities are located within 100 feet of a structure, building, orutility, the Design-Builder shall perform vibration monitoring in accordance with SpecialSpecification 634.99020017 to address the potential impacts to nearby receptors due toconstruction or demolition activities associated with this Project. The term “receptor” includesbuildings, utilities, newly constructed elements, and existing structures, for which constructionimpacts or Work above the recommended vibration limits may be detrimental.

The Design-Builder shall provide weekly construction instrumentation monitoring reports to theDepartment. Monitoring reports shall be interpretive in nature, and shall enumerate anycorrections applied to the data including, but not limited to any notification measures takenregarding data. The weekly reports shall include clear and explicit statements of reading(s)exceeding any pre-determined threshold values. The Design-Builder shall maintain theinstrumentation and monitor the measurements during and after construction up to FinalAcceptance.

9.3.9 Slope Stability

The Design-Builder shall be responsible for assessing the stability and impacts of any new soilor rock fill and cut slopes, and any new fill slopes (permanent and temporary) required for theProject, and for ensuring the long term stability of these slopes.

Page 50: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 43 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

9.3.10 Rock Slope Stability

The Design-Builder shall be responsible for designing new rock cuts and for developing rock fallcatchment areas (permanent and temporary) and ancillary stabilization measures along eithernew or existing slopes.Section not used.

9.3.11 Temporary Works

The Design-Builder shall be responsible for the design and construction of all temporary worksrequired for the Project.

9.4 CONSTRUCTION REQUIREMENTS

9.4.1 Dewatering and Groundwater Control

The Design-Builder shall be responsible for evaluating the potential need for dewatering andgroundwater control, and for implementing such measures as appropriate, and shall evaluatethe effects on existing facilities resulting from any dewatering and draw down.

9.4.2 Deep Foundations

The Design-Builder shall design and provide integrity and/or capacity testing of all drilled shaftsand test shafts. At a minimum,deep foundations, in accordance with Department standards. Ifapplicable, integrity testing requirements on drilled shafts and test shafts shall comprise of, as aminimum, crosshole sonic logging on all drilled shafts.

As part of the As-Built Plans, the Design-Builder shall provide installation records for all piles,micro-piles and/or shafts installed. For driven piles and micro-piles, the pile driving records shallinclude hammer stroke, fuel setting, final pile tip elevations, resistance achieved, pile lengthsused, and details of the cap, cap block and cushion system. For all drilled shafts with rocksockets or bearing on rock, the rock socket and the base of the drilled shaft shall beinspected.deep foundations installed, in accordance with Department standards.

The Design-Builder shall report the results of all foundation installation inspections and rocksocket observations.

9.4.3 Soil and Rock Excavations and Embankments

Excavations and embankments for roadwaysroadway foundations shall be constructed so thatpost construction settlement is expected to remain within two inches of the profile grade line atany point along the entire alignment. Also, prior to the project’s final acceptance, differentialsettlement along travel lane and shoulder surfaces shall not exceed one inch two inches over a100-footft length along the alignment or one inch in the traverse(longitudinal direction. Thislatter requirement excludes the 10-), or over a half inch along a ten foot length adjacent to in thetransverse direction or within ten feet of any approach slab or edge of a structure.

structure, where any post construction settlement shall be no more than one-half inch prior tothe project’s final acceptance.

Page 51: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 44 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

9.4.4 Condition Surveys

9.4.4.1 Pre-Construction Condition Survey

The Design-Builder shall conduct a pre-construction inspection and survey of the existingcondition of all structures and properties within 100200 feet of vibration or settlement causingconstruction activities for the purposes of generating photographic and video documentation ofexisting damage, leaks and cracks, in accordance with the requirements of NYSDOT SpecialSpecification 634.99010017. The pre-construction condition survey shall form the basis againstwhich all new cracks, existing progressive cracks, or damage will be measured.

In its preparation for the pre-construction survey, the Design-Builder shall ensure that the pre-construction condition survey encompasses at a minimum all properties and structures withinareas that are identified by the Design-Builder to be potentially proneexposed to: (i) groundvibration levels, expressed as resultant peak particle velocity, in excess of 2.0 inches persecond; and (ii) predicted ground settlements of greater than ¼ inch.

The Design-Builder shall submit torecord the NYSDOT the records and photographic and videodocumentationresults of theany pre-construction condition survey, which shall be signed andstamped by a Professional Engineer registered in the State of New York.

9.4.4.2 Post-Construction Condition Survey

The Design-Builder shall conduct a post-construction condition survey of the properties coveredby the pre-construction conditions survey. The post-construction condition survey shall beperformed by the Design-Builder within 20 days of Project Completion, and it shall compare thepost-construction conditions with the conditions recorded in the pre-construction conditionsurvey. The location and scope of the post-construction condition survey shall match those ofthe pre-construction condition survey. The complete documentation of the post-constructionsurvey, describing the comparison with the preconstruction conditions and signed by aProfessional Engineer registered in the State of New York, shall be submitted to theDepartment.

9.5 DELIVERABLES

At a minimum, the deliverables shall include the items listed in Table 9-1, for the Department’sreview.

Table 9-1 – Geotechnical Deliverables

DeliverableNumber of Copies

Delivery Schedule ReferenceSectionHardcopy Electronic

Geotechnical Work Plan 1 1 20 days after NTP 9.3.1

Geotechnical Data Report 1 1

20 days after completionof subsurfaceinvestigation, includingtesting

9.3.76

Page 52: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 45 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

DeliverableNumber of Copies

Delivery Schedule ReferenceSectionHardcopy Electronic

Geotechnical Instrumentation& Construction MonitoringPlan

3 130 Days prior to the startof any constructionactivities

9.3.8

Pre-Construction ConditionSurvey Report 3 1

Not less than 30 daysprior to start ofconstruction

9.4.34.1

Post-Construction ConditionSurvey 3 1 Not less than 30 days

before Final Acceptance 9.4.34.2

Page 53: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 46 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 10 STRUCTURES

10.1 SCOPE

The Design-Builder shall be responsible for all work necessary to complete the design andconstruction of all permanent and temporary structures required to complete the Project,including, but not limited to, the permanent bridges, superstructures, retaining walls, barriersand miscellaneous structures. The design and construction of all structural systems andcomponents shall provide functionality, durability, ease of maintenance and inspection andsafety.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The review and approval process shall be in conformance withthe Design-Builder’s Quality Control Plan.

10.2 STANDARDS

The Design-Builder shall perform structural design and construction activities in accordance withthe Contract Requirements and the applicable Standards, Design Codes, and Manuals cited inSection 1.6, unless otherwise stipulated in this Project Requirement or otherwise applicable tothe Project.

10.3 DESIGN REQUIREMENTS

The Design-Builder shall design replacement bridge structure(s), including but not limited to thefollowing: primary and secondary structural elements, reinforced concrete deck, deck joints,pedestrian sidewalks, utility placement, curb(s), abutment structures, abutment foundations,wingwalls, bridge railings, bearings and drainage systems.

The Design-Builder may propose various types of superstructure systems and/or foundationsand substructures to replace the existing bridges subject to the limitations outlined below.

The new structures shall be designed as follows:

A) BIN 1040550 - If the proposed hydraulic opening is less than the existing hydraulicopening, the Design-Builder shall provide a hydraulic analysis that shows the newsuperstructure has a minimum freeboard of two (2) feet for the 50 year flood event.

The design shall also provide for a utility support system for a natural gas pipe andcasing and a sanitary sewer force main and casing to be installed on the bridge.

B) BIN 5500969 - The design of BIN 5500969 shall include a minimum clear span of 123.5feet (from face of abutment to face of abutment) to accommodate the future roadwaysection for Kisco Avenue, with the center of the span opening over the existingcenterline of Kisco Avenue.

C) BIN 5500870 - The minimum clear opening perpendicular to the flow shall be 20 feet - 0inches. The vertical clearance under BIN 5500860 which carries Bedford Road over thisstructure shall not be reduced. A minimum upstream low chord elevation of 257.21 feetand a minimum downstream low chord elevation of 257.02 feet shall be provided. Thebottom low chord elevation for the replacement bridge shall not be lower than the

Page 54: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 47 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

existing bottom low chord elevation and the vertical clearance under BIN 5500860 whichcarries Bedford Road over this structure shall not be reduced.

D) BIN 5500890 - The minimum clear opening perpendicular to the flow shall be 20 feet - 0inches. The vertical clearance under BIN 3037170 which carries Pleasantville Road overthis structure shall not be reduced. A minimum upstream low chord elevation of 261.35feet and a minimum downstream low chord elevation of 260.46 feet shall be provided.The bottom low chord elevation for the replacement bridge shall not be lower than theexisting bottom low chord elevation and the vertical clearance under BIN 3037170 whichcarries Pleasantville Road over this structure shall not be reduced

E) BIN 5521680 - The minimum clear opening perpendicular to the flow shall be 28 feet – 0inches. A minimum freeboard of 0.25 feet for the 50 year flood shall be provided.However, the Design-Builder shall make every effort to maximize the available freeboardfor the 50-year flood event. The DB shall remove the stream bed silt bar and vegetationlocated approximately 80 feet upstream of the bridge. The silt bar shall be removed toexpose the top of the concrete channel.

F) BIN 1005080 – No road work is required. The minimum clear opening of each pipe shallbe 8 feet 6 inches. Prior to lining, the pipes shall be inspected and any holes shall berepaired. The lining material shall provide a maximum Manning roughness coefficient (n)of 0.012. The service life for the liner shall be 70 years. The DB shall remove the streambed silt bar located just upstream of the bridge. The silt bar shall be removed to anelevation of approximately 6.3 feet or to an elevation that matches the surroundingnatural stream bed elevation.

10.3.1 Components

A) Barriers, Railings and Pedestrian Fencing: Temporary traffic barriers shall meet the testingrequirements of TL 2 and permanent traffic barriers shall meet the testing requirements ofTL 4, except that no timber railing will be accepted.

Barriers, railings and/or fencing that will be designed and constructed to contain users andmaterials, shall be detailed and constructed to prevent people from climbing, and providefor maximum safety and security.

Refer to Section 10.3.2 for aesthetic requirements related to bridge parapet walls andfencing, if any.

B) Decks: Precast panel and/or cast in place decks are preferred. Two-course decks withasphalt overlays as defined in the NYSDOT Bridge Manual are not permitted. Unfilledsteel grating decks and orthotropic steel decks are not permitted. Bridge decks shall bemade fully composite with the underlying primary member system. All decks shall beprotectively sealed. All decks and top slabs on the Saw Mill River Parkway shall havestainless steel bar reinforcement in the top and bottom of the deck and top slabs.

C) Deck Joints: No deck joints shall be permitted.

D) Superstructure: The superstructure may be constructed of concrete or structural steel.Structural steel, if used, shall be galvanized or metalized for all BINs in this project with the

Page 55: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 48 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

possible exception of BIN 5500969. Should weathering steel be used at this location thefollowing conditions apply:

Uncoated weathering steel bridges shall be detailed to include an additional 1 / 16 inchof thickness per exposed face beyond what is required by design for the small amountof corrosion expected over the life of the bridge. The additional thickness shall not beincluded in calculations for design strength, but must be included in the dead load andcamber calculations. Guidance in the Bridge Manual Section 8 regardingrecommended plate thickness increments shall still be followed.

Each end of uncoated weathering steel beams embedded in an integral or semi-integral abutment shall be protectively coated for the length of the beam embedmentinto the abutment plus an additional 12 in.

Uncoated weathering steel used with curbless bridge decks that do not have concretebarriers shall require the web and entire bottom flange of the exterior fascia girder tobe protectively coated. If structural steel is used for bridges in this contract, thefollowing requirements shall be adhered to:

BIN 1005080 – Not Applicable.

BIN 1040550 – All structural steel shall be galvanized orand metalized.

BIN 5500969 – All structural steel shall have a protective coating applied. Structuralsteel can be weathering steel without an additional preventative coating.

BIN 5500870 - All structural steel shall be galvanized orand metalized.

BIN 5500890 - All structural steel shall be galvanized orand metalized.

BIN 5521680 - All structural steel shall be galvanized orand metalized.

Timber superstructure systems are not permitted. Composite beams, such as fiberreinforced polymer beams, are not permitted. Fracture-critical members are not permitted.

Refer to Section 10.3.2 for color requirements related to painted steel superstructureelements, if any.

E) Prefabricated superstructure components and precast bridge deck panels: If prefabricatedsuperstructure components and/or precast bridge deck panels are used, field cast jointsbetween prefabricated components and panels shall be made with ultra-high-performanceconcrete (UHPC). The proposed special specification for UHPC joints shall be similar toNYSDOT Special Specification 557.21020016 and in compliance with guidance given inFHWA publication No.: FHWA-HRT-14-084, Design and Construction of Field Cast UHPCConnections. This publication can be found at the following link:http://www.fhwa.dot.gov/publications/research/infrastructure/structures/14084/14084.pdf ,regarding field cast joints between precast concrete units (including but not limited toSpecial Specification 557.21020016).

If pre-stressed concrete adjacent boxes or slab units are used, stainless steelreinforcement is required.

F) Bearings: Design and location of bearings shall provide for maintenance, accessibility andfuture replacement. Jacking points with sufficient capacity (full dead load and live load) toallow the superstructure to be lifted for future bearing replacement under live load shall beprovided. The plans shall include the location of the jacking points and the jacking loads.

Page 56: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 49 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

G) Substructures:

Abutments: The tops of all bridge seats and the backwall tops and face below expansionjoints shall be coated with penetrating type protective sealers. Stainless Steelreinforcement shall be utilized at all exposed surfaces of bridge seats and backwalls belowexpansion joints. Reinforcing bars that extend from the superstructure into the backwallbelow expansion joints shall not be plain steel.

Pier Caps (if necessary): The tops of all piers below expansion joints shall be coated withpenetrating type protective sealers. Stainless Steel reinforcement shall be utilized at allexposed surfaces of pier caps below expansion joints. Reinforcing bars that extend intothe pier cap below expansion joints shall not be plain steel.

H) Earth Retaining Structures: The Design-Builder shall determine the location(s) and typesof earth retaining structures. Wall type selection and design by the Design-Builder shallmeet all applicable Project Requirements. All earth retaining structures shall be designedfor seismic and hydraulic events. Wingwalls shall be considered as part of the abutmentfor a distance, measured along the wingwall from the centerline of bearings, equal to themaximum height of the abutment wall (as measured from top of grade at the base of theabutment to the bottom of lowest girder). Gabion and crib walls are not permitted.

I) Foundations: The Design-Builder shall calculate settlements for the different foundingconditions along the bridge. Settlements likely to occur during construction shall becalculated separately from long term settlements.

J) Drainage: Drainage requirements are outlined in Section 17 of these ProjectRequirements.

K) Noise Barrier at BIN 5500969:

The noise barrier shall begin 75 feet west of the centerline of Kisco Avenue andapproximately 28 feet north of the existing southbound Saw Mill River Parkway edge ofpavement. From the point of beginning, the noise barrier shall be installed in a westerlydirection of approximately 395 feet parallel to the Saw Mill River Parkway. At this point thenoise barrier will begin a horizontal taper length of 300 feet along the parkway to an offsetpoint 60 feet from edge of existing pavement. The barrier will continue westerly at the 60foot offset until a total of 720 linear feet of barrier is constructed. The height of the noisepanel shall be 10 feet minimum above finished grade measured at the Saw Mill RiverParkway side of the barrier at the noise barrier location. The noise wall barrier is expectedto be located at the top of the grading slope (cut section) or outside the deflection distanceof the guide rail (fill section).

The noise barrier wall shall be precast concrete panels, posts and caps. The Design-Builder shall stain both sides of the concrete panel to produce a natural stone lookindigenous to the site. The panel shall be stained in accordance with Department’sSpecial Specification for Item 555.01940007, Staining Concrete Surfaces. The intent ofthe staining is to color the concrete units such that the wall will resemble a natural stonewall. The final coloration shall appear natural and shall accurately simulate theappearance of real stone, including multiple colors, shades and flecking. It shall alsoinclude colors that result from aging, such as staining from oxidation, rusting and/ororganic staining from soil and/or vegetation. The staining contractor shall have a minimum

Page 57: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 50 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

of 5 years of experience at staining form lined concrete patterns, and shall have a varietyof artistic stain application techniques. The wall shall also be sealed with a penetratingtype protective sealer conforming to Department’s Standard Specifications Section 717-03. The contractor can use the sealer to help achieve a more natural look to the stainedconcrete.

A stained and sealed sample wall panel (5 feet by 5 feet), cap and post shall be providedby the Design-Builder for approval by the Department’s Project Manager.

Both Sides of Panel -o Pattern: Customrock Formliner Pattern #1214 – Minnesota Ashlar or approved

equal.o Joint depth 2”o Color – Stain natural stone indigenous to Project site

Post and Cap -o Pattern: Noneo Color: None

Panel Cap -o Panel Cap should be one continuous piece or a multiple of 3 for the length of the

panel.o Pattern: Noneo Color: None

The noise barrier shall be installed prior to the start of any other construction work at thissite beginning, with the exception of tree removal. However, once trees are removed, theDesign-Builder has 30 days to begin the construction of the noise barrier.

L) BIN Plate Sign: The Design-Builder shall furnish and install a new BIN plate meeting therequirements set forth in this section.

The material requirements for the BIN plate are:

Panel with reflective background: The aluminum panel shall conform to therequirements of the NYSDOT Standard Specifications. The background material shallbe green reflective sheeting conforming to the requirements of the NYSDOT StandardSpecifications for Class A Sheeting. The size of the panels shall be 1/8" thick by 3" by12". A thin rubber or plastic gasket or sheeting matching the plate size shall be placedbehind the plate prior to installation;

Numbers: The numbers shall be reflective sheeting conforming to the requirements ofthe NYSDOT Standard Specifications for Class A Sheeting, except that the adhesiveshall be pressure-sensitive such that the numbers can be applied to the background inthe field. The numbers shall be 2" high and silver-white in color conforming to FHWAseries C dimensions.

Prior to placing the numbers on the panel, the reflective background shall be clean and freeof dirt and oil which may adversely affect proper adhesion. The numbers shall be placed onthe reflective background, perpendicular to the longitudinal axis of the panel and verticallycentered. The reflective background and numbers shall be coated and/or edge sealed inaccordance with the recommendations of the sheeting manufacturer.

Page 58: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 51 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

The BIN plate shall be attached to the beginning abutment, right side of the bridge usingexpansion anchors. The plate shall be placed high on the abutment, near the fascia of thebridge so that it cannot be painted over via a spray paint can or easily removed or damaged.

10.3.2 Aesthetic Requirements

The Design-Builder shall provide plans showing all aesthetic enhancements to be incorporatedinto the design; including but not limited to textures, patterns, and colors; to the Design QualityAssurance Engineer for review and comment. The required color for painted steelsuperstructure elements, if any, shall be Federal Standard 595, Color FS 20059.

10.3.1.110.3.2.1 Specific Aesthetic Requirements for BIN 5500969

Aesthetic treatment of the new bridge abutment and wingwalls shall be customized texturedsurfaces. The the pattern of proposed finish should be Form Liner No. 304 manufactured byGreenstreak Group, Inc., or approved equal.a trapezoidal or fractured rib design texturedconcrete finish that is appropriate to the context of the surrounding area.

10.4 DEMOLITION REQUIREMENTS

10.4.1 Scope

BIN 1040550 – Superstructure demolition and abutment and pier modification only.

BIN 1005080 – No demolition is required.

The following requirements shall apply to BINs 5500969, 5500870, 5500890, 5521680.

The Design-Builder shall demolish and remove the existing bridge superstructures, piers,abutments, foundations, retaining walls, and pavement within the Project Limits in a safe andenvironmentally acceptable manner.

The demolition of the existing bridges shall include all existing superstructure elements and allsubstructure elements to two feet below final grade elevation or in accordance withenvironmental permitting. Where new foundations are placed at the locations of existingfoundations the existing foundations shall be removed to the extent needed to construct the newfoundations.

The Design-Builder shall test for the presence of Hazardous Materials in all structures to bedisturbed to ensure the handling, removal and disposal is done in accordance with all applicablelaws and standards. Refer to Section 3 of this Part for information regarding hazardousmaterial.

The abatement of all Hazardous Materials shall be completed to the greatest extent possibleprior to any demolition taking place unless a legal variation from related laws, rules andregulations can be obtained. If the Hazardous Material has been identified through theHazardous or Asbestos Screening document and/or the record plans, the Design-Builder isresponsible for all costs. Should Hazardous Material or Asbestos be found and informationrelated to its presence not previously available to the Design-Builder, all costs associated withabatement, containment, removal, and disposal shall be covered under the Fixed Force Accountitem.

Page 59: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 52 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

The Design-Builder shall perform all Work with care so that any materials that are to remain inplace, or that are to remain the property of the Department shall not be damaged. If the Design-Builder damages any materials that are to remain in place or which are to become or to remainthe property of the Department, the damaged materials shall be repaired or replaced in amanner satisfactory to the Department at no cost to the Department.

The Design-Builder shall ensure that no aspects of the Works have a detrimental effect onpublic safety or the environment.

Upon mobilization at a bridge structure, Tthe Design-Builder shall assume responsibility forsafety and maintenance of all existing structures within the bridge’s Project Limits, identified forremoval, in accordance with DB §105-12. Maintenance of existing structures identified forremoval shall be performed in accordance with the applicable Standards, Design Codes andManuals cited in Section 1.6, unless otherwise stipulated in this Project Requirement. All costsof maintenance Work of existing structures identified for removal will be paid for under the ForceAccount pay item. Any work proposed under this Contract regarding maintenance Work shall beaccepted by the Department’s PM prior to beginning (designing or construction) work.

Utility connections shall be discontinued and capped in accordance with the requirements of theutilities companies or the Department prior to demolition works.

10.4.2 Standards

The Design-Builder shall perform the demolition activities in accordance with the ContractRequirements and the applicable Standards, Codes and Manuals listed in Section 1.6 unlessotherwise stipulated in this Project Requirement, or otherwise applicable to the Project.

10.5 CONSTRUCTION REQUIREMENTS

The Design-Builder shall develop erection procedures for the bridges that include completedetailed erection sequence drawings; erection stresses in permanent and temporary members;bent and falsework reactions determined for each construction stage.

10.6 DELIVERABLES

At a minimum, the deliverables shall include the items listed in Table 10-1 for the Department’sreview.

Table 10-1

Deliverable Number of Copies Delivery Schedule ReferenceSectionHardcopy Electronic

Bridge Load Ratings 2 1 At Final Design Review ---

Page 60: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 53 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 11 LANDSCAPE ARCHITECTURE

11.1 SCOPE

The Design-Builder shall perform the landscape architectural activities as described in thisSection 11.

11.2 STANDARDS

The Design-Builder shall perform site work in accordance with the Contract Requirements andthe applicable Standards, Design Codes and Manuals cited in Section 1.6, unless otherwisestipulated in this Project Requirement.

11.3 GENERAL LANDSCAPE DEVELOPMENT

11.3.1 Existing Vegetation

Existing vegetation removal and disturbance shall be minimized to the cut/fill limits and anyremovals beyond those areas shall be replaced in kind with native species appropriate forUSDA NY Plant Hardiness Planting Zone for that bridge location:

BIN 1040550 - Zone 6a

BIN 5500969 - Zone 6b

BIN 5500870 - Zone 7a

BIN 5500890 - Zone 7a

BIN 5521680 - Zone 7a

BIN 1005080 - Zone 6b

The Design-Builder shall obtain acceptance from the Department’s CQAE prior to the removalof any tree with a diameter breast height (DBH) of 6 inches or greater.

Vegetation outside the limits of disturbance shall be protected with temporary plastic barrierfence. The temporary plastic barrier fence shall be installed at or as close as feasible to the dripline of the trees to be protected.

Disturbed areas shall receive topsoil and turf establishment. The type of topsoil and turfestablishment, either roadside or lawn, will vary based on location.

11.3.2 Tree Replacement Factors

A) Every live, native deciduous tree greater than six inches diameter at breast height (“DBH”)which is removed must be replaced with a total quantity of deciduous trees a minimum of 2inch caliper (size measured 6 inches above the base of the tree) equal to the total DBHsize of the tree removed. For example, 10 inch DBH tree removed should be replacedwith (5) two inch caliper trees; however the replacement quantity will go down if largercaliper trees are used.

Page 61: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 54 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

B) Every live, native coniferous tree removed must be replaced with a total quantity ofconiferous trees equal to the height and width of the tree removed. For example, a 20 fthigh x 10 ft wide coniferous tree should be replaced by two (2) 10 ft high x 5 ft wideconiferous trees.

C) Each replacement tree should be the same genus and species of the tree removed, unlessthe tree being removed was identified by the Design-Builder as an invasive plant species.

D) The minimum replacement sizes shall be as follows: 2-inch caliper for major deciduoustrees, 1.5-inch caliper for minor deciduous trees, 6-foot height for coniferous trees, 3-footheight for deciduous shrubs, and 2-foot height for evergreen shrubs.

11.3.3 Replacement Locations

Replacement planting may be located in the available right-of-way near the original locations ofthe trees that were removed.

Replacement planting may also be done near the right-of-way line or on private property.Planting on private property may only be done if private property owners provide writtenpermission to the Design-Builder and agree to take over the long term care and maintenance ofthe plant material, and the appropriate release is obtained by the Design-Builder and inconsultation with the adjoining property owner in accordance with NYSDOT EI 11-010.

The removal of any major deciduous trees over 6 inches in diameter at breast height shall bedocumented and the species noted in the existing tree inventory prepared by the Design-Builder. Note that all trees, living and dead, shall be included in the existing tree inventory andcalculations for tree replacement.

11.3.4 Proposed Planting

The Design-Builder shall not use invasive plant species for any of the proposed planting asrequired by the New York State 2012 Invasive Species Prevention Act, or a monoculture ofplant species, to reduce the potential for disease or invasive insect species to eradicate theproposed planting. Planting shall be located in a manner that does not interfere with the safeuse of travel ways. Planting should be designed in a manner that provides a mix of plantmaterial species to create seasonal interest for the traveling public.

Post planting care and replacement plantings shall be as per the requirements of SpecialSpecification 611.190X0024, Post Planting Care with Replacement.

11.3.5 Location Specific Landscape Development Concerns

BIN 5500969: A vegetated buffer will need to be established between the Saw Mill RiverParkway and the noise barrier, and between the noise barrier and the Pinecrest Manorapartment complex. If any view shed is opened up between the Saw Mill River Parkway andthe surrounding residential or commercial areas then a vegetated buffer would need to beestablished between the parkway and these areas. Landscaping shall be used to soften theappearance of the bridge abutments and wing walls.

.

Page 62: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 55 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 12 SIGNAGE, PAVEMENT MARKING AND SIGNALS

12.1 SCOPE

The Design-Builder shall provide all permanent fixed signing and permanent pavementmarkings required for the Project.

The Design-Builder shall be responsible for identifying, designing, detailing, fabricating,delivering and installing all signing, including reference markers, and pavement markingmaterials and shall install all components necessary for a complete and functional systemwhich, in addition to meeting the design and construction criteria specified above, meets thefollowing requirements:

A) Provides for the orderly and predictable movement of all traffic;

B) Provides such regulation, guidance, warnings and advisories as are needed to ensuresafe and informed operation;

C) Is fully and seamlessly integrated into the existing signing elements beyond the Projectlimits; and

D) Is integrated into the existing intelligent transportation system (ITS) components, ifapplicable.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The review and approval process shall be in conformance withthe Design-Builder’s Quality Control Plan.

12.2 STANDARDS

The Design-Builder shall perform the signage and pavement marking activities in accordancewith Contract Requirements and the applicable Standards, Design Codes and Manuals cited inSection 1.6, unless otherwise stipulated in this Project Requirement or otherwise applicable tothe Project.

12.3 REQUIREMENTS

12.3.1 Design Requirements

The Design-Builder shall develop a signing and pavement marking plan for the Project thatshall:

A) Provide for all components as called for in this Section 12;

B) Encompass the replacement of all existing signs within the Project limits;

C) Provide signing and pavement markings for bicycle and pedestrian facilities within theProject Limits;

D) Locate signs in accordance with the MUTCD and the NYS supplement;

Page 63: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 56 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

E) Provide signs with high reflectivity with Type IX sheeting such as to not warrant signlighting;

12.3.2 Construction Requirements

12.3.2.1 Signs

The Design-Builder shall not reuse any existing NYSDOT sign materials as part of thepermanent signing installation and shall be responsible for the disposal of all signing materialsand structures that are removed from the Project. Standard signs owned by municipalities otherthan NYSDOT, and non-standard signs owned by private entities but placed within NYSDOTright-of-way, with the acceptance of the Department, shall be removed, stored and reinstalled asrequired.

The Design-Builder shall be responsible for the provision of all signs, posts, frames and otherstructural components required for the installation and support of the sign panels.

Specific Requirements for BIN 5500969:The Project limits for Kisco Avenue is Holiday Inn Drive to Croton Lake Road.

An intersection warning sign mounted on a solar powered flashing beacon shall beinstalled in both directions on Kisco Avenue to alert motorist of the northbound Saw MillRiver Parkway ramp/Kisco Avenue intersection. The solar powered flashing beacon andsign shall be installed in accordance with the Department’s Specifications for Items645.5201, 645.85 and 680.82220210. Pavement Markings

All linear roadway and special markings shall be installed in accordance with the Department’sSpecifications for Item 685.11 through Item 685.14.

12.3.2.2 Traffic Signals

Section not used.

12.4 DELIVERABLES

Section not used.

Page 64: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 57 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 13 LIGHTING

13.1 SPECIFIC LIGHTING REQUIREMENTS FOR BIN 1040550

13.1.1 Scope

The Design-Builder shall relocate the existing lighting bracket arms and luminaries to the newrelocated utility poles. The luminary shall overhang the travel lane by 2 feet. If the existingbracket-arm length does not provide 2 feet of overhang, a New longer bracket arm may berequired shall be providedto adequately illuminate the roadway. The replacement bracket-armtype shall match the existing bracket-arm type. This work shall include all the requiredhardware etc. as necessary for a complete and functioning street light. The Design-Builder shallmake all arrangements with the local utility company to complete the service connections.

Page 65: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 58 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 14 INTELLIGENT TRANSPORTATION SYSTEMS (ITS)

14.1 SCOPE

For BIN 5500969: the Design-Builder shall perform all work necessary to relocate the existingwireless acoustic detector site (FDA-SMP-N-25.63-NB/SB), located on the northbound Saw MillRiver Parkway at MM 25.63 north of Exit 37 Kisco Avenue. This work shall include but not belimited to: remote and onsite functional testing by notifying, seven days prior to dismantling, andin presence of HVTMC representative prior to relocating acoustic sensor site. All cabinet items(not rigidly fixed parts), solar panel and detector head shall be dismantled in presence ofHVTMC representative according to the procedure given below. All items shall be stored in asecure location. If the sensor is found to be non-functional at the time of the testing, all issuesshall be documented and signed by both parties. The pole and acoustic detector equipmentshall be installed 25 feet offset from its present location with a new foundation having newanchor bolts. The footing and anchor bolts shall be replaced in kind. The relocated pole andcabinet shall have earthing with resistance less than 5 ohms and sealing at all cable entry ducts.The contractor shall replace all batteries with new deep cycle GEL type 100 AH 12V batteries.After the detector has been relocated and properly calibrated a stand-alone test shall beperformed according to procedure included in the Reference Documents (old test result are alsoincluded). Solar panel mounting direction and angle and clearing and grubbing shall be done asper HVTMC. Remote access and full functioning testing shall be done after the stand alonetest. If the detector fails to function as it was, the Design-Builder shall be responsible for makingthe detector functional.

Acoustic Detector Dismantling Procedure:

1) Turn off the power of all active devices. Remove modem power plug from modem andCT card.

2) Remove battery connection from solar controller – positive terminal first (put insulationtape on terminal lug) then negative terminal.

3) Remove solar connection from solar controller – positive terminal first (put insulationtape on terminal lug) then negative terminal.

4) Remove CT to modem and acoustic head interface connector.

5) Separate battery parallel connection – positive first then negative.

6) Remove batteries from the cabinet.

7) Remove cable connection from acoustic head terminal block then dismantle head.

8) Remove solar panel terminal connection – positive first then negative. Dismantle bracketwith solar panel.

9) Dismantle the cabinet.

The acoustic detector installation shall be performed in the opposite manner of the dismantlingprocedure.

For BIN 5500969, the Design-Builder shall also provide two (2) inch PVC coated galvanizedsteel conduits. One conduit shall be located on each side of the bridge (northbound andsouthbound) for future ITS. The conduits shall be capped underground off the structure in apullbox.

Page 66: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 59 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 15 WORK ZONE TRAFFIC CONTROL AND ACCESS

15.1 SCOPE

The Design-Builder shall be responsible for the planning and provision of Work Zone TrafficControl (WZTC), required to perform the Project Work until Project Completion. This ProjectRequirement applies to any roads, ramps, cross roads, local streets, maintenance roads,driveways, and active paths within and/or affected by the Project.

The Design-Builder shall provide WZTC for the safe and efficient movement of people, goods,and services through the Project area(s) while maintaining access and minimizing negativeimpacts to residents, commuters, businesses, and NYSDOT maintenance operations.

Note that, as used in this section, “Work Zone Traffic Control plan” or “WZTC plan” is theequivalent of “Maintenance and Protection of Traffic plan” or “MPT plan” as described inChapter 16 of the Highway Design Manual (HDM).

15.2 STANDARDS

The Design-Builder shall perform the work zone traffic control activities in accordance with theContract Requirements and the applicable Standards, Design Codes and Manuals listed inSection 1.6, unless otherwise stipulated in this Project Requirements, or otherwise applicable tothe Project.

15.3 REQUIREMENTS

In general, bridges (site locations) with off-site detours should utilize the shortest route on State-owned highways (except as noted below) that involve no bridges with load postings, R-postedrestrictions, or vertical clearance restrictions, or that are or will be under construction during thedetour. The detours shall be fully signed.

15.3.1 General Requirements

A) BIN 1040550 - Route 208 may be closed and an off-site detour utilized. Work at this siteshall only be between June 30 and August 11. An off-site detour utilizing Hudson Streetshall be used during the closure period. Nighttime construction is permitted during theclosure period. Staged bridge construction is not permitted. If traffic is maintained on-site,a minimum of two lanes of traffic (one in each direction) shall be maintained at all timesexcept between the hours of 9:30 am and 3:30 pm or where alternating one way traffic ispermissible.

B) BIN 5521680 - Lane closures on the Hutchinson River Parkway are not permitted.Construction work between 8 pm and 8 am is not permitted. One lane of the driveway shallremain open at all times. The Work at this site can only be performed between April 1st

and November 15th.

C) BIN 1005080 - Construction work between 8 pm and 8 am is not permitted. Lane andshoulder closures on Route 9 are not permitted at any time.

D) BIN 5500870 and BIN 5500890 - The number of lanes to be maintained at all times shallbe as specified in Table of Key Corridor Lane Chart included in Part 7 – Engineering Data,unless otherwise noted as follows:

Page 67: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 60 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

a. Bridge Replacement: The northbound and southbound Saw Mill River Parkway maybe reduced to one lane in each direction in advance of the work site for both bridges.Southbound traffic may be detoured to the northbound Saw Mill River Parkwayseparated by a temporary concrete barrier. If the Design-Builder elects to implementsuch a detour, the existing traffic signal at Grant Street shall be turned off andvehicular and pedestrian access to/from Grant Street shall be prohibited for theduration of the detour. Access to/from the Saw Mill Parkway southbound at ManvilleRoad shall also be prohibited for the duration of the detour. The maximum allowedduration for this detour shall be 14 calendar days. The detour may be implementedno earlier than July 6, and traffic shall be restored to the southbound Saw Mill RiverParkway no later than August 26 of the same year. Nighttime construction may beused during this time. An off-site detour is not permitted. Full time tow truck serviceshall be provided during this period.

b. Sanitary Sewer Work: Work within the northbound lanes of the Saw Mill RiverParkway, related to the sanitary sewer work described in Part 4 – UtilityRequirements, may be performed by utilizing off-peak single lane closures and/ornighttime full closures utilizing an off-site detour. However, no more than two (2)nighttime full closures of the northbound Saw Mill River Parkway will be permitted. Inaddition, no work within the northbound Saw Mill River Parkway may occur until alltraffic has been permanently restored to BINs 5500870 and 5500890.

Work on Pleasantville Road and Manville Road may only occur during off-peakhours. During these times, the Design-Builder may implement single-lane, two-waytraffic utilizing flagger controlalternating one-way traffic.

E) BIN 5500969 – The number of lanes to be maintained at all times shall be as specified inTable of Key Corridor Lane Chart included in Part 7 – Engineering Data, unless otherwisenoted as follows. Construction work between 8 pm and 8 am is not permitted. An off-sitedetour for the Saw Mill River Parkway is not permitted. Short term dDaily ramp closuresbetween 9 am and 3 pm are permitted for the speed change lane tie in work. Themaximum number of daily ramp closures shall be 20. Kisco Avenue shall remain open atall times except during the demolition and erection of the bridge. Kisco Avenue may beclosed between the Parkway ramps and traffic may be detoured. The detour shall bepermitted between the hours of 9 am and 8 pm. The maximum number of closures shallbe 10. Pedestrian access shall be maintained through the closed work area.

15.3.2 Work Zone Traffic Control Plan

The Design-Builder shall prepare and submit a WZTC Plan for managing traffic operations andcontrolling access until Project Completion. A WZTC Plan must be submitted in advance of anywork that restricts the roadway cross section and includes durations and traffic pattern changesthat will exceed 10 hours in any 24-hour period.

The WZTC Plan shall be submitted to the Department’s Design Quality Assurance Engineer aminimum of two weeks prior to initiation of any Work requiring a lane closure or theimplementation of any change in traffic patterns.

The WZTC Plan shall include:

A) Contingency plans for reasonable unforeseen interruptions;

Page 68: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 61 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

B) Duration of each WZTC stage, including duration of lane closure(s), if any;

The Design-Builder shall notify local officials, and affected police jurisdictions to facilitate safeand effective enforcement. The WZTC Plan shall recognize the need for approval of the use oflocal public roads.

The Design-Builder shall produce a clear design of each stage, with associated traffic clearlydelineated, in chronological order. Each significant change in traffic patterns shall be presentedas a separate stage.

The Design-Builder shall be responsible for updating the WZTC Plan as necessary throughoutthe Contract, so that at all times the current traffic control on site is representative of the designdrawings that have been accepted by NYSDOT.

15.3.3 General Restrictions

The Design-Builder shall be aware that no work shall be performed and no temporary laneclosures and/or shoulder closures shall be permitted on the following State recognized holidays:

A) New Years Day;

B) Memorial Day;

C) Independence Day;

D) Labor Day;

E) Thanksgiving Day;

F) Christmas Day;

If a holiday is observed on a Monday or Tuesday, the above restrictions will be in effect from 12noon Friday before the holiday until 10 a.m. on the day after the holiday.

If a holiday is observed on a Wednesday, the above restrictions will be in effect from 12 noonTuesday before the holiday until 10 a.m. on the Thursday following the holiday.

If a holiday is observed on a Thursday or Friday, the above restrictions will be in effect from 12noon the day before the holiday until 10 a.m. on the Monday following the holiday.

All proposed lane and/or shoulder closures of the Saw Mill River Parkway pertaining to BINs5500969, 5500870, and 5500890 must be approved by the Hudson Valley TransportationManagement Center’s Surface Transportation Controller (STC) prior to implementation. TheDesign-Builder can expect no more than 5 disapprovals of lane closure proposal requests, thatmeet the key corridor provision or as noted within this contract, for the duration of this Project.

STC shall be informed of all other proposed lane and/or shoulder closures on key and non-keycorridors prior to implementation. The key corridors for this Project are Saw Mill River Parkwayand Hutchinson River Parkway.

The Hudson Valley Transportation Management Center’s Road Work Form shall be used torequest STC approval of lane and/or shoulder closures of the Saw Mill River Parkway pertaining

Page 69: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 62 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

to BINs 5500969, 5500870, and 5500890, and to notify the STC of any other lane and/orshoulder closures on key and non-key corridors. The Road Work Form will be made available tothe Design-Builder by the Department’s Project Manageris included as a Reference Document.

The Design-Builder is responsible for preparing the Road Work Form and forwarding it to theSTCDepartment’s PM. The Road Work Form must be submitted to the STC at [email protected] Department’s PM a minimum of seven (7) calendar days in advance ofscheduled closures. The STC Department’s PM will respond within four (4) calendar days afterreceipt of the Road Work Form. The Design-Builder shall include the Department on allcorrespondence with STC.

15.3.4 Access to Commercial Properties and Driveways

The Design-Builder shall provide uninterrupted access to all commercial properties anddriveways within the Project Limits at all times.

15.3.4.1 Specific Access Requirements for BIN 5521680:

The bridge and driveway is also used by the City of New Rochelle Fire Department to foremergency access, by the Westchester County Department of Environmental Facilities foraccess to their Trunk Sewer, their reservoir #2 and by Crown Castle Communications to accesstheir cell tower facility. The Design-Builder shall contact and coordinate with both all parties priorto the start of work. Contact information provided below.

City of New Rochelle Fire DepartmentContact: Captain Barry Nechis, MPA EMT-POEM/EMS Coordinator90 Beaufort PlaceNew Rochelle, NY 10801

T: (914) 654-4343F: (914) 632-2907C: (914) 760-4213Email: [email protected]

Westchester County Department of Environmental FacitilitesContact: Marian Pompa, Jr., P.E.Associate Engineer270 North AvenueNew Rochelle, NY 10801

T: (914) 813-5419F: (914) 813-5460Email: [email protected]

Crown CastleContact: Tammy NosekProject/Construction Manager- NYS Contracts (Contractor)3 Corporate Park Drive, Suite 101

Page 70: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 63 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Clifton Park, NY 12065

T: (518) 373-3542Email: [email protected]

15.3.5 Closure Restrictions

If short-term, stationary, short-duration, or mobile lane closures are used, the followingrestrictions apply:

For BINS 5500969, 5500870 and 5500890 refer to the Table of Key Corridor Lane Chartincluded in Part 7 – Engineering Data.

On non-key corridors and non-State highways the same number of travel lanes (includingturning lanes) as exist prior to this work shall be maintained in each direction during the hours of7:00 a.m. to 9:30 a.m. and 3:30 p.m. to 6:00 p.m. - Monday to Friday, inclusive. At BIN5500969, an exception to this restriction is permitted on Kisco Avenue (9 am and 8 pm) duringthe bridge demolition and erection work – Monday to Friday inclusive. Shoulders on any bridgeshall not be closed during these time periods.

15.3.6 Minimum Lane Widths during Construction

The Design-Builder shall maintain a minimum travel lane width of 1110 feet during constructionexcept for BINs 55008705500969 and 5500890 where a an 1011 foot minimum travel lanewidth is acceptablerequired.

15.3.7 Portable Variable Message Signs

The Design-Builder shall provide, as a minimum, 10 Portable Variable Message Signs, but moreshould the Design-Builders design dictate, for the duration of this Contract. The PortableVariable Message Signs shall be deployed as necessary for the various WZTC schemesdeveloped in coordination and concurrence/acceptance by the Department’s Project Manager.

The portable variable message signs provided shall meet the requirements of NYSDOT ItemNo. 619. 110405 (Portable Variable Message Boards with Cellular Option NTCIP Compliant).

The development of messages for the Variable Message Sign(s) shall be the responsibility ofthe Department’s CQAE and operations staff at the NYSDOT’s Transportation ManagementCenter.

The Design-Builder shall contact the Department’s CQAE at least two weeks prior to placementof any Variable Message Sign regarding their location and receive concurrence of the location.

15.3.8 Temporary and Interim Pavement Markings

The Design-Builder shall provide temporary and interim pavement markings during allconstruction phases conforming to the requirements of the NYSDOT Standard Specifications.

Page 71: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 64 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

15.3.9 Coordination with Regional Traffic Management Center

The Design-Builder is advised that the NYSDOT’s Traffic Management Center will providesupport for the Project’s WZTC activities. Therefore, coordination among the Department’sConstruction Quality Assurance Engineer, Design-Builder, and NYSDOT’s Traffic ManagementCenter, will be required for all WZTC activities, including the use of Variable Message Signs(VMS)) in the Project area.

15.3.10 Emergency Response and Transportation Management Plans

The Design-Builder shall notify the Department’s CQAE immediately following any impacts tomotorists due to construction activities and/or unforeseen circumstances. The CQAE will beresponsible for disseminating the information to the appropriate personnel/entities forappropriate response to mitigate impacts to motorists.

The Design-Builder shall prepare an Emergency Response Plan to be implemented in the eventthe roadway is shut down for unforeseen or unplanned circumstances. The Plan shall beimplemented when the anticipated duration of closure exceeds twenty (20) minutes. The Planshall be submitted to the Department’s Project Manager for review and comment a minimum oftwo weeks prior to the beginning of Work. Work on this Project shall not begin until the Design-Builder receives written notification from the Department’s Project Manager that the EmergencyResponse Plan has been reviewed by the Department and all Department comments have beenresolved.

The Emergency Response Plan shall include a notification and communication plan thatdescribes how the Design-Builder will promptly inform the appropriate personnel/entities of anunforeseen or unplanned circumstance. No later than 30 calendar days following NTP, theDepartment’s Project Manager will provide the Design-Builder with a list of personnel andentities that need to be contacted in this section of the Emergency Response Plan.

The Design-Builder shall also provide the Department’s Project Manager a TransportationManagement Plan (TMP) per FHWA’s Final Rule on Work Zone Safety and Mobility, 23 CFR630 Subpart J.

Page 72: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 65 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 16 PAVEMENT DESIGN AND CONSTRUCTION

16.1 SCOPE

The Design-Builder shall perform all Work necessary to provide all pavement required for theProject. This includes design, furnishing of materials, fabrication and construction of alltemporary and permanent pavement for roadways within the Project Limits.

The Design-Builder shall be responsible for the review and approval of all submittals needed forthe scope of work. The review and approval process shall be in conformance with the Design-Builder’s Quality Control Plan.

16.2 STANDARDS

The Design-Builder shall perform the pavement activities in accordance with the ContractRequirements and the applicable Standards, Design Codes and Manuals listed in Section 1.6,unless otherwise stipulated in this Project Requirement, or otherwise applicable to the Project.

16.3 REQUIREMENTS

All pavement materials and construction methods shall be in accordance with the requirementsof the NYSDOT Standard Specifications and the NYSDOT materials and pavement installationmethods.

Limestone and/or dolomite, regardless of the acid insoluble residue content, shall not beallowed for Type 1 or F1 friction aggregate requirements.

16.3.1 Full Depth Reconstruction

The Design-Builder shall develop and construct pavement section(s) for full depthreconstruction, including subbase, of the Project roadways in conformance with theComprehensive Pavement Design Manual, using the ESAL-based pavement design method.

The pavement design and HMA mix design for all Parkways and state highways shall be basedon a minimum Estimate Traffic Level of 30 Million ESALs.

No partial-width full depth reconstruction will be permitted; any roadway requiring full depthreconstruction shall be reconstructed for its full width except as noted below.

BINs 5500870 and 5500890 - the width of the full depth pavement reconstruction for thesouthbound Saw Mill River Parkway shall be 20 feet measured from 2 feet left from the center ofthe median barrier.

BIN 5500969 - the reconstruction of the roadway median will not require the full depth pavementreconstruction of the remaining roadway width.

If any roadway is permanently widened for the purpose of providing additional travel and/orturning lanes, new full depth pavement need only be developed and constructed for the widenedsection, provided that no other portion of the pavement within the widened section requires fulldepth reconstruction for any other purpose. However, the existing pavement within the widenedsection shall be milled and resurfaced from curb to curb or edge of pavement to edge ofpavement to provide a uniform pavement as specified in Section 16.3.2.

Page 73: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 66 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

16.3.2 Milled and Resurfaced Roadways

The Design-Builder shall mill and resurface pavement areas as necessary to provide for asmooth transition between the existing and fully reconstructed pavement surfaces inaccordance with the applicable Standard Sheets. The Design-Builder shall mill a minimum of50 feet beyond the limits of any full depth reconstructed pavement sections, unless as notedbelow.

Within the horizontal limits of any widened pavement section, the existing pavement shall bemilled and resurfaced in conjunction with the top course placement for the widened section inorder to provide a uniform pavement within the widened section of roadway.

Other Sspecific requirements are as follows:

A) BIN 1040550

2.0 inch mill and inlay Route 209 208 between Depot Street and Route 94

B) BIN 5500969

2.0 inch mill and inlay the Saw Mill River Parkway within the speed change lanes.

2.0 inch mill and inlay Kisco Avenue between the Saw Mill River Parkwaysouthbound ramps and Holiday Inn Drive.

C) BIN 5500870 and BIN 5500890

2.0 inch mill and inlay the northbound Saw Mill River Parkway between GrantStreet and 500 feet south of BIN 5500870.

16.3.3 Utility Trench Restoration

Outside areas of full depth reconstruction, pavements in trench restoration areas shall matchthe adjacent pavement section.

16.3.3.1 Specific Utility Trench Restoration Requirements for BIN 5500890

Pleasantville Road is owned and maintained by Westchester County. Their requirement fortrench restoration of their newly paved roads is a 2 inch mill and inlay 50 feet in each directionof the trench for the full width of the roadway. For roads that have not been newly paved, the 2inch mill and inlay limit shall be 25 feet in each direction for the full width of the roadway.

Page 74: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 67 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 17 DRAINAGE AND STORMWATER

17.1 SCOPE

The Design-Builder shall design and construct a drainage system as needed for the estimatedstorm runoff that provides functionality, durability, ease of maintenance, maintenance access,safety, and pleasant aesthetics.

The Design-Builder shall be responsible for the review and approval of all shop drawingsneeded for the scope of work. The review and approval process shall be in conformance withthe Design-Builder’s Quality Control Plan.

Where drainage patterns will or must be changed from existing patterns, the Design-Buildershall be responsible for securing all necessary permits prior to construction of any drainagefacilities.

Prior to Project Completion, the Design-Builder shall be responsible for cleaning all new andexisting drainage facilities within the Project Limits.

17.2 STANDARDS

The Design-Builder shall perform the drainage and stormwater activities, including highway,bridge and site systems, in accordance with the Contract Requirements and the applicableStandards, Design Codes and Manuals listed in Section 1.6, unless otherwise stipulated in thisProject Requirement or otherwise applicable to the Project.

Stormwater shall be conveyed from point to point through the use of a single pipe. Smallerpipes in parallel shall not be permitted without justification from the Design-Builder andacceptance from the Department.

17.3 REQUIREMENTS

17.3.1 General

The Design-Builder shall perform a hydraulic analysis to determine if bridge drainage andconveyance is required.

The Design-Builder shall design and construct the drainage and stormwater systems to meetthe following requirements:

A) Provide a 75-year minimum service life on all drainage and stormwater managementfacilities for NYSDOT stormwater within the Limits of Construction; and

B) Modify the existing drainage and stormwater management elements for the Project toaccommodate the proposed construction.

17.3.2 Drainage Report

The Design-Builder shall provide a Drainage Report to the Department and any other entitieswhose facilities will be impacted by the Project in accordance with HDM Chapter 8. TheDesign-Builder shall be responsible for coordination in advance with any third party to determinethe necessary document submission required by the third party. At least two weeks prior to

Page 75: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 68 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

providing documents to any third party, the Design-Builder shall submit a draft Drainage Reportto the Department’s Design Quality Assurance Engineer for consultation and written comment.

The Drainage Report shall document the design criteria used, final design basis, and allsupporting calculations and computer model output.

17.3.3 Connections to Existing Systems

The Design-Builder shall develop Design Plans and Project Specifications for any connectionsto existing storm systems. The Design-Builder shall be responsible for calculations performedto ensure there is sufficient capacity to accommodate any increase in flow due to changes indrainage catchment area and/or to land use. This paragraph shall not be construed to relievethe Design-Builder of the obligation to treat runoff water that requires treatment.

17.3.4 Spill Management

Spill prevention and response measures shall be described in the SWPPP.

17.4 DELIVERABLES

At a minimum, the deliverables in Table 17-1 shall be provided to the Department forconsultation and written comment.

Table 17-1 Deliverables

DeliverableNumber of Copies

Delivery Schedule ReferenceSectionHardcopy Electronic

Drainage Report 1 1Two weeks prior toproviding documentsto third party

17.3.1

Page 76: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 69 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 18 HIGHWAY DESIGN

18.1 SCOPE

The Design-Builder shall be responsible for the design, construction and reconstruction of thepermanent roadway(s) to be constructed within the Project Limits, and any other roadsdamaged by construction operations, or necessary for permanent operations, all in accordancewith the design requirements stated herein. Highway design, construction and reconstructionshall be understood to include the design, furnishing, and construction of all roadappurtenances, protections, and safety devices not specifically cited in other ProjectRequirements.

In addition, the Design-Builder shall be responsible for the removal of non-standard systemsthat currently exist within the project limits whether they are affected by the proposed work ornot and replaced with systems meeting current Department Standards, unless specifieddifferently in the Project Requirements Sections 1-17 and 19-20.

18.2 STANDARDS

The Design-Builder shall perform the Work in accordance with the Contract Documents and theApplicable Standards, Design Codes and Manuals listed in Section 1.6, unless otherwisestipulated in this Project Requirement or otherwise applicable to the Project.

18.3 REQUIREMENTS

18.3.1 General

The Design-Builder shall be responsible for performing the detailed highway design andconstruction within the Project Limits in accordance with the Project Requirements set forthherein.

18.3.2 Design Requirements

A) Design requirements for the reconstruction of Route 208 (BIN 1040550) shall be asspecified below.

Design Speed: 35 mph;

Minimum Required Lane Widths and Number of Lanes: Two 12 foot lanes;

Minimum Shoulder Widths: 5 foot Southbound and 1 foot Northbound;

Curb and Sidewalk: 5 inch curb Southbound and Northbound and a 5 foot sidewalkSouthbound and a 4 foot sidewalk Northbound.

B) Design requirements for the reconstruction of Saw Mill River Parkway and construction ofSpeed Change Lanes (BIN 5500969) shall be as specified below.

Design Speed: 65mph;

Minimum Travel and Speed Change Lane Widths: 12 feet;

Minimum Right Shoulder Widths: 6 foot when adjacent to speed change lanes, and 8foot elsewhere;

Page 77: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 70 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

Minimum Left Shoulder Widths: 2 foot on highway and 4 foot on bridge;

Minimum Median Width: 6 foot on highway and 10 foot on bridge

Curb and Sidewalk: T 100 curb on right side and no sidewalk.

C) Design requirements for the reconstruction of Saw Mill River Parkway Ramps (BIN5500969) shall be as specified below.

Design Speed: 25mph for the loop ramp and 30mph for all others;

Lane Widths: 12 foot minimum and 18 foot maximum;

Minimum Shoulder Widths: 6 foot maximum;

Curb and Sidewalk: NA.

D) Design requirements for Kisco Avenue (BIN 5500969) shall be as specified below.

Refer to Section 10 for the future reconstruction widths.

Curb and Sidewalk: Replace the existing curb and sidewalk located on the west side ofKisco Avenue with a 9 inch wide Type VF 150 curb and a 5 feet wide sidewalk. Theapproximate length of the curb and sidewalk replacement is 360 feet. The limits are 150feet south of the existing south bridge fascia and 150 feet north of the existing northbridge fascia.

E) Design requirements for the reconstruction of Saw Mill River Parkway (BIN 5500870 andBIN 5500890) shall be as specified below.

Design Speed: 60 mph;

Minimum Required Lane Widths and Number of Lanes: Two 10 foot lanes;

Minimum Shoulder Widths: 1 foot on both the left and right side of roadway;

Curb and Sidewalk: NA.

F) Design requirements for the reconstruction of EHPA DPW Road (BIN 5521680) shall be asspecified below.

Design Speed: NA;

Minimum Required Lane Widths and Number of Lanes: Two 12 foot lanes;

Minimum Shoulder Widths: Two 6 foot on right side of inbound roadway and& 6 foot onright side of outbound roadway;

Curb and Sidewalk: NA.

18.3.3 Barrier Systems and Impact Attenuators

The Design-Builder shall remove and dispose of all existing barrier systems within the Projectlimits and/or which are directly impacted by the Project Work, and replace with new barriersystems to current NYSDOT Standards.

The limits of work for new roadside and new median barrier shall be the lesser of the following:

1) The point where barrier is no longer warranted; or

Page 78: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 71 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

2) A point where the proposed barrier can be transitioned to an existing barrier systemwhich conforms to current standards.

All existing barrier systems that are removed shall become property of the Design-Builder

18.3.4 Clear zone

The Design–Builder shall document clear zone on the final record plans.

18.4 DESIGN EXCEPTIONS AND NON-STANDARD FEATURES

It is the responsibility of the Design-Builder, in coordination with the Department, to obtainacceptance of any non-standard features included in the final design.

Page 79: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 72 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 19 STANDARDS

19.1 GENERAL REQUIREMENTS

The Design-Builder shall identify the specific version of each Standard it uses. It is the Design-Builder’s responsibility to obtain clarification of any apparent error, omission, ambiguity orconflict regarding any Standard in accordance with DB §102-2.

19.2 SPECIFIC REQUIREMENTS

The Design-Builder shall assume that all provisions of the Standards, including the figures andtables, are mandatory and guidelines contained therein shall be assumed to be requirements.All words such as “should,” “may,” “must,” “might,” “could,” and “can” shall mean “shall” unlessthe context requires otherwise, as determined in the sole discretion of the Department. It shallbe in the Department’s sole discretion to determine when the context does not require aprovision to be mandatory.

Except as expressly otherwise provided in the Contract Documents, any reference to NYSDOTunder a Standard shall mean the Department.

When a Standard refers to an action being necessary, needed, or recommended, the Design-Builder shall construe the action as required unless the context requires otherwise, asdetermined in the sole discretion of the Department.

Where reference is made in the Standards to items that are indicated in the plans or specialprovisions or required in the plans or special provisions, the plans or special provisions shallmean the Design-Builder’s Plans or the Special Provisions.

References in the Standards to approved products or materials shall mean approved by theDepartment.

All references in the Standards to the inspector, the field inspector, the project engineer, theengineer, the materials engineer, the district materials engineer, the survey crew, the projectsupervisor, the agency certified technician, the certified plant technician, and the representativeof the Office of Materials shall mean the Design-Builder, except as otherwise expressly providedin the Contract Documents or otherwise directed by the Department.

When a Standard refers to an approval of any correction or repair that deviates from theContract requirements, the Acceptance must be by the Department.

When a Standard refers to items that will be performed or provided by NYSDOT or by a divisionor employee of NYSDOT, the Design-Builder shall construe the requirements as applying to theDesign-Builder unless otherwise specified in the Contract Documents, or unless the contextrequires otherwise. It shall be in the Department’s sole discretion to determine when the contextrequires otherwise.

Page 80: DB CONTRACT DOCUMENTS PART 3 PROJECT REQUIREMENTS … · region 8 bundled bridges (contract 3) pin 8bow.0h, contract d900025 db contract documents part 3 project requirements final

New York State Department of Transportation

Region 8 Bundled Bridges 73 Part 3 - Project RequirementsPIN 8BOW.0H, Contract D900025 Final March 6, 2015

SECTION 20 SECURITY

Section not used.