DCS CHECK-OUT AND OPERATOR TRAINING WITH HYSYS D YNAMICS José Naranjo, Edgar Goitia (Técnicas Reunidas, Chile) José María Nougués, Rodolfo Tona, Josep Daví, JoséMaría Ferrer (inprocess)

Upload: trinhhanh

Post on 29-Jul-2018

250 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

DCS CHECK-OUT AND OPERATOR TRAINING WITH HYSYS DYNAMICS

José Naranjo, Edgar Goitia (Técnicas Reunidas, Chile)

José María Nougués, Rodolfo Tona, Josep Daví, JoséMaría Ferrer (inprocess)

Page 2: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

AGENDA

• Introduction

– Dynamic Simulation

– Operator Training Systems

– DCS Check-Out

• Case of Study

– Modelling of an E&P facility

– DCS Integration and checkout

– Training scenarios

• Key findings & Conclusions

2

Page 3: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

INTRODUCTION

3

© 2006, Sverck et al., A Real Time Approach to Process Control, 2nd Ed.

Page 4: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

WHY DYNAMIC SIMULATION?

4

Dynamic Model

1. Equipment sizing and process layout verification:

• Compression systems

• Pipeline networks

2.- Flare Load calculation and PSV sizing

• Design/revamp flare networks

3.- Emergency System verification and HAZOP studies support

• HIPPS studies

• Cause & Effect matrixes

4.- Design control layout

• Scenarios analysis

• Perturbation rejection

• Control loops selection

5.- Prototyping MPC

• Obtain MPC models

• Study non-linearities

• Test/Tune MPC controller

6.- Develop virtual sensors

• Online Analyzers backup

• Fault diagnostic

• Look-ahead sensors

7.- DCS checkout

• DCS FAT with virtual plant

• Operating procedure test

8.- Operator Training System(OTS)

• Operator Training

• Emergency scenarios

• Knowledge base system

Consolidated

Exploring

Page 5: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

AOs, DOs AIs, DIs

Real Plant

Control System

Hardware

Operator Console

REAL WORLD

Dynamic HYSYS Model

AIs, DIs AOs, DOs

Control System

Software Emulation

Operator Console

OPERATOR TRAINING SYSTEM

OPC

DOWNLOAD DATABASE

DOWNLOAD GRAPHICS

Instructor Station

WHAT IS AN OPERATOR TRAINING SYSTEM?

5

Page 6: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

Plant Controls Operator Console

Stimulated

Emulated

Simulated

HYSYS Model

DCS Console

Graphic Interface

HYSYS Environment

Real Plant DCS Hardware

HYSYS Controls

Software emulation

6

Page 7: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

BENEFITS FROM OTS PROJECTS

7

Page 8: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

WHAT IS A STANDARD DCS FAT?

Factory Acceptance Test (FAT) involves of:

1. Hardware, such as controllers, I/O modules, power supplies, terminations, etc.

2. Logic, forcing analog and discrete inputs, then watching the logic to be sure it responds as expected.

3. Operator displays and alarms, which are tested in conjunction with the forced logic and signals step above.

8

Page 9: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

MOTIVATION FOR BETTER TESTING

• Increasing complexity of DCS Tightens the requirements for functional testing before commissioning.

• Client/Suppliers try to minimize involved risks: This includes software testing, as well as early detecting specification errors.

• At the real installation: The available time does not suffice to achieve the required depth of testing.

Testing environments with a simulated installation are a worthwhile alternative.

9

Page 10: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

WHY USING SIMULATION IN DCS FAT?

Control system checkout allows the Simulator to be used to:

1. Pre-tune control loops

2. Test motor start/stop logic

3. Validate permissive logic for start-up/shutdown sequences

4. Evaluate controls stability/interactions against perturbations

5. Check graphics displays and operability with procedures

6. Re-setting for certain alarms limits

7. Test ESD systems and logic sequences

8. Evaluate procedures for abnormal operation

10

Page 11: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

DCS FAT WITH ONLY EMULATED DCS&SIS

Control design and configuration is independent of the hardware, DeltaV Simulate allows all configuration to run in virtual control with identical functionality Virtual Control with

DeltaV Simulate Pro

Discrete I/Os are stimulated by engineer, Analog I/Os use tie-backs 11

Page 12: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

DCS FAT WITH FULL VIRTUAL PLANT Virtual Control with DeltaV Simulate Pro

The I/Os (discrete & analog) are fully simulated by a process dynamic simulator of the entire plant

12

Page 13: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

STANDARD FAT VS. VIRTUAL PLANT FAT? STANDARD DCS FAT DCS FAT with VIRTUAL PLANT

Hardware Actual DCS/SIS modules Standard PCs or laptops

Software Actual DCS /SIS software DeltaV Simulate Pro, HYSYS Dynamics

Location At DCS vendor Facilities At any location (Customer, EPC, etc)

Timing When DCS hardware and I/Os modules are available

As soon as DCS logic and configuration is available

Testing proceeding Limited to the I/O signal introduced by hand

Same as during commissioning & start-up with real plant

Procedures testing Limited verification All procedures and start-up/shutdown sequences

Loop testing No possible Full, as in real plant

Alarm verification Only non-time dependent Full, as in real plant

SIS verification Limited, no plant interaction Full, as in real plant

13

Page 14: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

PROJECT ANTICIPATION

Certain tasks don´t need to wait for the physical good to exist, they can start as soon as the dynamic simulation is available

14

1-4 weeks earlier

Page 15: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

START-UP WITH OTS

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

With OTS

Typical Start-up

Plant starts weeks earlier

Faster ramp-up

Less incidents

Safer Operation

15 Weeks

Page 16: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

SCOPE OF THE DYNAMIC MODEL

16

Page 17: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

DYNAMIC MODEL

17 Model Management Section

Page 18: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

18

Simulation Scope Train I • Equipments: 68 • Isolation valves: 55 • Control valves: 38 • Relief valves: 55 • PID loops: 56 • I/O Count: 800

OTS ARCHITECTURE Operator

Emerson’s Delta V PCS & SIS

Aspen HYSYS Dynamics

Instructor

Action on Controllers (SP or OP) and Selectors

Information published on the PCS

Information from the model (strip charts)

Activation of Training scenarios

Control Action Information from sensors

Page 19: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

OTS HARDWARE ARCHITECTURE

19

Page 20: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

OTS ACTUAL SETUP

20

Page 21: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

DCS DATABASE

• Types of modules:

– Control Modules. Associated to controllers and indicators inside the control logic of the plant areas under model scope

– SIS Modules. Associated to the plant safety logic. Only the ones that affect the modelled areas.

– Modules grouped by working areas

21

Page 22: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

DCS DATABASE CHECKOUT

List of problems detected:

– Problems with the screens

– Problems with Controllers tuning

– Problems with alarms in controllers and indicators

• Wrong limits trip spurious alarms together with signal noise that could trip ESD.

– Configuration of modules

• Control modules configurations generated wrong signals affecting other modules that generate range deviations and could trip ESD.

22

Page 23: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

KEY FINDINGS OF THE DCS CHECKOUT

• The OTS was configured with the post-FAT database and several items were revised:

– 30% PID control action change, direct/reverse

– Re-tuning of all Kp and Ti of all loops

– Slug-catcher level control, control logic modified

– Logic control verification of external DCS packages (Compressors)

– Interlock in blowdown valves after identify issues in manual operation

– Timing of SIS valves were verified

– Redefine alarms limits (more than 50%)

– Minor bugs of DCS operator screens

23

Page 24: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

TRAINING SCENARIOS DESCRIPTION

24

# Scenario description

1 Trip of Sales Gas Compressor

2 Shutdown of Sales Gas Compressors due to a High Pressure Alarm in the export line

3 Fire in separator V-002-A/B, ESD activation and depressuring valve opening (according to Cause and Effect Matrix)

4 Sudden stop of EPF

5 Hot oil loss in stablizer reboiler

6 Trip of recycle gas compressor

7 Trip of one propane compressor

8 Plant adaptation to 50% throughput by only manipulating the load to the sales compressor, without affecting the operation of EPF

Page 25: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

OTS IN PLACE AND IN OPERATION

• OTS currently in operation in the plant, being used by plant operators/engineers for operating procedures

• Operators were trained on safe and optimized procedures for all scenarios

• Incidents and equipment damages are being minimized

• Second phase of the project is currently being carried out in order to expand the scope of the first model with new Train II

25

Page 26: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

OTS BENEFITS 1. Identify unit or process operating

constraints at design phase

2. Identify errors in the automation system before commissioning and operation

3. Verify/Improve operating procedures

4. Train operators on safe and optimized procedures for all scenarios

1. Begin startup sooner

2. Complete startup in less time

3. Improved steady operating rate and product quality

4. Minimize incidents and equipment damages 26

Page 27: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

RECAP

– Uses of Dynamic Simulation

– What are Operator Training Systems

– Additional value: DCS Check-Out

– Case Study: E&P facility

– Detected DCS problems

– OTS Benefits

27

Page 28: DCS Check-Out and Operator Training with HYSYS …€¦ · AGENDA •Introduction –Dynamic Simulation –Operator Training Systems –DCS Check-Out •Case of Study –Modelling

QUESTIONS, CONTACT

Contact: JoseMaria Ferrer

Inprocess Technology & Consulting Group, S.L.

Phone: +34 933 308 205

Cell: +34 607 570 685

[email protected]

28

Q&A