dealing with loss and expense in construction

Upload: riyas

Post on 06-Jul-2018

222 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/16/2019 Dealing With Loss and Expense in Construction

    1/33

     

    Dealing with Loss and Expense

    in Construction

    Tony Ward FRICS, FCIOB , MCIArb  

  • 8/16/2019 Dealing With Loss and Expense in Construction

    2/33

    Web Class Objectives

    By the end of the Web Class you will:

    Understand the Principles of Loss & Expense

    Be aware of Contract Provisions

    Understand Contractor’s Notices

    Demonstrate awareness of Heads of Claim

    Learn Top Tips for Loss & Expense

    Have knowledge of calculating Head Office Overheads

    Understand Procedures for Demonstrating Loss & Expense

    2

  • 8/16/2019 Dealing With Loss and Expense in Construction

    3/33

    3

    About You?

    Using the chat facility, please

    indicate which side of the

    construction industry you are

    from. Client,

    contractoror ….? 

  • 8/16/2019 Dealing With Loss and Expense in Construction

    4/33

    Loss & Expense - What is it ?

    4

    2.

    1.

    1. Loss

    2. Expense

  • 8/16/2019 Dealing With Loss and Expense in Construction

    5/33

    5

    Loss & Expense - What do

    you think it is?

    Please answer in the chat facility

  • 8/16/2019 Dealing With Loss and Expense in Construction

    6/33

    Loss & Expense – Why is it paid ?

    6

    It is paid by the client in order to put the Contractor’s cash

    position back to where it would have been if the Breach of

    Contract did not arise

    It reimburses financial losses and expenses incurred bythe Contractor

    Breach of Contract is typically an Extension of Time

  • 8/16/2019 Dealing With Loss and Expense in Construction

    7/33

    Loss & Expense – How is it calculated?

    7

    fi nd  out for cert ain

  • 8/16/2019 Dealing With Loss and Expense in Construction

    8/33

    Loss & Expense Procedures

    8

    1

    • Contractor makes application for Loss & Expense as soon as it

    becomes apparent

    2

    • Architect instructs Quantity Surveyor to ascertain Loss & Expense

    • Quantity Surveyor typically seeks further information fromContractor

    3

    • Contractor provides further information

    • Quantity Surveyor ascertains Loss & Expense

  • 8/16/2019 Dealing With Loss and Expense in Construction

    9/33

    Top Tip – A Good Contractor’s

    Notice

    9

    The Relevant

    Matter

    The Cause

    and Effect

    Supporting

    information(if available)

    Reference to

    documentsand records

  • 8/16/2019 Dealing With Loss and Expense in Construction

    10/33

    Top Tip – Contract Provisions

    10

  • 8/16/2019 Dealing With Loss and Expense in Construction

    11/33

    Loss & Expense – Contract

    Provisions

    11

  • 8/16/2019 Dealing With Loss and Expense in Construction

    12/33

    Loss & Expense – Top Tip !

    12

    When can loss and expense be ascertained?

    http://www.google.co.uk/url?sa=i&rct=j&q=&esrc=s&frm=1&source=images&cd=&cad=rja&docid=aDwpdtRyKEi8cM&tbnid=jb66z8sujM1xkM:&ved=0CAUQjRw&url=http://webclipart.about.com/od/Calendar_Clip_Art/ss/2013-Calendars_4.htm&ei=ZVS4Udj-BoGn0AXwhoHoDA&bvm=bv.47810305,d.d2k&psig=AFQjCNFnmArXkNXUx7sDcBCfwSY_Z_Zj7g&ust=1371121118955635

  • 8/16/2019 Dealing With Loss and Expense in Construction

    13/33

    Loss & Expense – Heads of

    Claim

    13

    Typically Heads of Claim include :-

    Site Preliminaries Prolongation

    Site Preliminaries “Thickening” 

    Head Office Overheads

    Increased Costs

    • Disruption Costs

    Finance ChargesSubcontractor Claims

  • 8/16/2019 Dealing With Loss and Expense in Construction

    14/33

    Loss & Expense -

    Preliminaries

    14

    Preliminaries are :-

    People and facilities required to carry out the works.

    Site Manager

    Site Huts

    Tower Crane

    Temporary Electrics

    Welfare Facilities

    Power and Water for the Works

    Site Telephones etc

  • 8/16/2019 Dealing With Loss and Expense in Construction

    15/33

    Loss & ExpenseSite Preliminaries Prolongation

    15

    •  Relates to the extended period of time that Prelims arekept on site for the delay period 

    For example :-

    • Delay of 6 weeks =

    • Site Manager x 6 weeks

    • Site Huts x 6 weeks

    • Welfare Labourer x 6 weeks

    • Etc, etc etc…… 

  • 8/16/2019 Dealing With Loss and Expense in Construction

    16/33

    Loss & Expense

    Site Preliminaries – “Thickening” 

    16

    This relates to extra over Prelims required on site as a result of abreach of contract by the Client

    For example :-

     Architect issues 100 variations for finishes in 2 week periodMajor changes

    Therefore additional Site Manager brought in to manage that

    process and those changes

    This additional Site Manager is termed as “PrelimsThickening” 

  • 8/16/2019 Dealing With Loss and Expense in Construction

    17/33

    Loss & Expense – Top Tip

    17

    Cause & Effect Schedules are ideal for demonstrating Loss & Expense

  • 8/16/2019 Dealing With Loss and Expense in Construction

    18/33

    Loss & Expense

    Head Office Overheads

    18

  • 8/16/2019 Dealing With Loss and Expense in Construction

    19/33

    Loss & ExpenseHead Office Overheads – Actual Recovery

    19

    For this you need :-

  • 8/16/2019 Dealing With Loss and Expense in Construction

    20/33

    Loss & Expense

    Head Office Overheads

    20

    Formula Approach

    Emden

    Hudson

    Eichleay

    On a scale of 1 (novice) to 10

    (expert), how familiar are youwith these approaches?

    Please type in the chat facility

  • 8/16/2019 Dealing With Loss and Expense in Construction

    21/33

    Loss & Expense

    Head Office Overheads

    21

    Emden Formula

    h x c x pd

    100 cp

    h = Head office percentage

    c = Contract Sum

    cp = Contract Period

    pd = Period of Delay

  • 8/16/2019 Dealing With Loss and Expense in Construction

    22/33

    Loss & Expense

    Head Office Overheads

    22

    Hudson Formula

    HO/Profit% x Contract Sum x Period of Delay ( weeks )

    Contract Period ( weeks )

  • 8/16/2019 Dealing With Loss and Expense in Construction

    23/33

    Loss & Expense

    Head Office Overheads

    23

    Eichleay Formula

    Rarely used in UK , it comes from an American legal case

    involving the Eichleay Corporation

  • 8/16/2019 Dealing With Loss and Expense in Construction

    24/33

    Loss & Expense

    Head Office Overheads

    24

    In order to succeed, a Contractor has to prove

    there was other work available which, but for thedelay, he would have secured that work.

    Top Tip

    Contractor can do this by producing invitations to

    tender and letters declining the tenders, as there

    was not enough resources available.

  • 8/16/2019 Dealing With Loss and Expense in Construction

    25/33

    Loss & Expense – Increased Costs

    25

    The Contractor may be entitled to increased costs

    due to delays if :-

    He would have purchased an item in 2010 for £10 and

    then due to delays he purchased it in 2011 for £11.

    Thus an increased cost of £1.

    This is increased costs due to inflation

    Invoices and Price lists can be used to demonstrate this

  • 8/16/2019 Dealing With Loss and Expense in Construction

    26/33

    Loss & Expense – Disruption

    Costs

    26

    • Out of sequence working• Return visits

    • Trade congestion

    • Disruption very difficult to prove

    • Keep good records and allocation sheets

    • Take photographs

    • Mark up drawings showing dates of work done

    • Typically recorded on daywork

  • 8/16/2019 Dealing With Loss and Expense in Construction

    27/33

    Loss & Expense – Finance

    Charges

    27

    Delays typically cause Contractor to :-

    Have cash flow disrupted

    Get paid later for his works

    Receive retention money later

    Prove cause and effect and how long Contractor is stood out of

    money

    Bank charges,

    loss of bank interest etc.

  • 8/16/2019 Dealing With Loss and Expense in Construction

    28/33

    28

    How can the subcontractor

    prove cause and effect?

    Please answer in the chat facility

  • 8/16/2019 Dealing With Loss and Expense in Construction

    29/33

    Loss & Expense – Subcontractor Claims

    29

    Ensure subcontractor proves cause and effect

    Seek copies of time sheets, wages slips, etc.

    When submitting Subcontract Claim to PQS, consider anyattendances Contractor has provided …such as hoisting,

    task lighting, etc…. 

    Contractor only entitled to actual loss and expense

    incurred

  • 8/16/2019 Dealing With Loss and Expense in Construction

    30/33

    Loss & Expense - Records

    30

    L & E

  • 8/16/2019 Dealing With Loss and Expense in Construction

    31/33

    Loss & Expense -

    Demonstration

    31

    Costs EventsNarrative

  • 8/16/2019 Dealing With Loss and Expense in Construction

    32/33

    Summary

    32

    Today we have discussed and experienced :-

    Defining Loss & Expense

    Contract Provisions & Relevant Matters

    Cause & Effect & Schedules

    Notices & their content

    • Heads of Claim and formulae

    Loss & Expense RecordsMethods of demonstrating Loss & Expense

    A Q i ?

  • 8/16/2019 Dealing With Loss and Expense in Construction

    33/33

    33

    Any Questions ?

    Thanks for attending , if you have to

    disconnect before the end of the Q&A please

    take a minute to complete the survey

    by clicking on the link

    located in the chat facilities