deck issues-construction perspective

31
1 The State of Practice for Highly Skewed Bridges The State of Practice for Highly Skewed Bridges Construction Perspective The State of Practice for Highly Skewed Bridges The State of Practice for Highly Skewed Bridges Deck Issues: Construction Perspective Deck Issues: Construction Perspective MAH MAH - - 193 193 - - 0028 0028

Upload: others

Post on 12-Sep-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Deck Issues-Construction Perspective

1

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Construction Perspective

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

MAHMAH--193193--00280028

Page 2: Deck Issues-Construction Perspective

2

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

MAHMAH--193193--0028:0028:

• Spans: 5 (963’)• Girders: 84” Hybrids @ 11’-8”• Skew = 0°

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

MAHMAH--193193--0028:0028:

• Frames: Slotted L4”x4”x½”– 3 piece and 4 piece– Expected Deflection during Pour = 10.67”

• Frame Spacing: 24’

Page 3: Deck Issues-Construction Perspective

3

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Overhang from 4’ to 4’-3”

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

MAHMAH--193193--0028:0028:

Page 4: Deck Issues-Construction Perspective

4

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Cross Frame

Cross Frame

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Cross Frames

Page 5: Deck Issues-Construction Perspective

5

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

MAHMAH--193193--0028:0028:

• Structure was milled ¾” to 1 ¼”

• Structure was given a 2”-3” microsilicaoverlay

• Extra tall overhang brackets were used to dissipate web loading on the adjacent sister structure.

Remedy:

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

FAIFAI--3333--14171417

Page 6: Deck Issues-Construction Perspective

6

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

FAIFAI--3333--1417:1417:

• Spans: 3 (184’)• Beams: 45” Type III Prestressed Concrete• Skew = 23°

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

FAIFAI--3333--1417:1417:

• Frames: Slotted MC 18x47.2– Expected Deflection during Pour = 15/16”

• Frame Spacing: 38’-10”

Page 7: Deck Issues-Construction Perspective

7

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Overhang = 4’-2 ½”

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Page 8: Deck Issues-Construction Perspective

8

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Page 9: Deck Issues-Construction Perspective

9

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

FAIFAI--3333--1417:1417:

• The beam rotation also caused the deck to be thin and the resteel cover to be less than specified.

Page 10: Deck Issues-Construction Perspective

10

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

FAIFAI--3333--1417:1417:

• Fascia bearings at piers were replaced and beveled shim plates were added to address translational rotation.

Corrections Performed:

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Topics:Topics:

• Typical Deck Forming

• Typical Overhang Forming

• Bridge Paving Machine

• Use of Screed Elevations

Page 11: Deck Issues-Construction Perspective

11

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Deck Forming:Deck Forming:

Generic Interior Cross Section

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Falsework Between the Beams

Strut

Hanger

Deck Forming:Deck Forming:

Page 12: Deck Issues-Construction Perspective

12

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Deck Forming:Deck Forming:

Hanger

Soffit

Haunch

Edge Forms

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Corrugated, galvanized metal• Assume 18 psf for additional concrete

StayStay--inin--place forms (SIP):place forms (SIP):

Page 13: Deck Issues-Construction Perspective

13

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

StayStay--inin--place forms (SIP):place forms (SIP):

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

StayStay--inin--place forms (SIP):place forms (SIP):

Clip angle

Page 14: Deck Issues-Construction Perspective

14

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

StayStay--inin--place forms (SIP):place forms (SIP):

HaunchStyrofoam

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Topics:Topics:

• Typical Deck Forming

• Typical Overhang Forming

• Bridge Paving Machine

• Use of Screed Elevations

Page 15: Deck Issues-Construction Perspective

15

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Spacing is typically 2’-3’

• Typically no haunch

• No SIP forms

• Vertical leg length is currently determined by capacity of bracket only.

Page 16: Deck Issues-Construction Perspective

16

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Inspection Rail

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Overhang brackets can cause localized buckling and rotation of deep girders

Page 17: Deck Issues-Construction Perspective

17

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Std. Max = 50”

Deep Max = 70”

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Topics:Topics:

• Typical Deck Forming

• Typical Overhang Forming

• Bridge Paving Machine

• Use of Screed Elevations

Page 18: Deck Issues-Construction Perspective

18

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Rotating Rollers

Augers

Rail

Vibrating Rollers

Page 19: Deck Issues-Construction Perspective

19

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well 3600Well 3600

Max. Paving Width = 96’Basic Machine = 5990 lbs.Additional = 53 lbs. / ft.

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Wheel Base = 3’

BidBid--Well 3600Well 36008’-7”

Page 20: Deck Issues-Construction Perspective

20

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well 4800Well 4800

Max. Paving Width = 120’Basic Machine = 7600 lbs.Additional = 75 lbs. / ft.

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Wheel Base = 4’

11’-7”BidBid--Well 4800Well 4800

Page 21: Deck Issues-Construction Perspective

21

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well 4800 w/ 66” Deep TrussWell 4800 w/ 66” Deep Truss

Max. Paving Width = 160’

Specialty Item – Do Not Use without Consulting OCA

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Contractor Typical Method of Placement

Deck Placement:Deck Placement:

Page 22: Deck Issues-Construction Perspective

22

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Design Assumes Loading Along the Skew

Deck Placement:Deck Placement:

- OR -

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• “Magical” Simultaneous Loading

Deck Placement:Deck Placement:

Page 23: Deck Issues-Construction Perspective

23

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Load and finish along skew (±5°) up to 50°.• Above 50°, finish at 50° and load at actual

skew (±5°), but limit leading edge of concrete to 20’ ahead of bridge paving machine.

Deck Placement Going Forward:Deck Placement Going Forward:

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Calculating BidCalculating Bid--Well Machine Length:Well Machine Length:

11’-6”1.56 x w5010’-6”1.41 x w459’-0”1.31 x w408’-0”1.22 x w357’-0”1.15 x w306’-6”1.10 x w255’-6”1.06 x w205’-0”1.04 x w15

┴Skew Width + Extra

Machine Length = Width + Extra Length┴

Page 24: Deck Issues-Construction Perspective

24

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well Limitations:Well Limitations:Connections

Page 25: Deck Issues-Construction Perspective

25

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well Limitations:Well Limitations:

Crown

Break

Break

Must be an even truss dimension

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well Limitations:Well Limitations:

Crown

Break

Break

Must be an even truss dimension

Page 26: Deck Issues-Construction Perspective

26

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well Limitations:Well Limitations:

Crown

Break

Break

Variable

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

BidBid--Well Limitations:Well Limitations:

1 2 543 6 VariesVariesVariesVariesVaries 7

Page 27: Deck Issues-Construction Perspective

27

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Deck Placement:Deck Placement:

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Deck Placement:Deck Placement:

Page 28: Deck Issues-Construction Perspective

28

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Topics:Topics:

• Typical Deck Forming

• Typical Overhang Forming

• Bridge Paving Machine

• Use of Screed Elevations

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Contractor receives a table of screed elevations at quarter points of each span.

• Deviations in the camber of the beams is normally corrected by varying the haunch height Haunch

Setting Grade:Setting Grade:

Page 29: Deck Issues-Construction Perspective

29

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• The haunch height is determined by subtracting the elevation of the top of the beams from the theoretical bottom of the deck

• The theoretical bottom of the deck is determined by subtracting the thickness of the deck from the given screed rail elevations

Screed Elevation

Deck Thickness

Top of Beam

Theoretical Bottom of Deck }

Setting Grade:Setting Grade:

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Example of a haunch height or “fill” table

Beam RearRow Elev. Abut 1/4 Pt 1/2 Pt 3/4 Pt Pier 1

ScreedDeck BotBeam TopHaunch Ht

A

966.64 966.48 966.32 966.16 966.00965.89 965.73 965.57 965.41 965.25965.22 965.07 964.93 964.75 964.58

0.66 0.64 0.66 0.670.67

Setting Grade:Setting Grade:

Page 30: Deck Issues-Construction Perspective

30

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Cups or Saddles

Rails

Setting Grade:Setting Grade:

• Grade must be set by instrument

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Check deck thickness and concrete cover over reinforcing steel **

• Make sure bridge paving rails are secure with no deflection

Dry Run

• Make sure bridge paving machine is functioning properly

Page 31: Deck Issues-Construction Perspective

31

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

• Contractor can only make adjustments for deflections due to the finishing machine weight (not the concrete dead load)

Dry Run

• Contractor assumes deflections due to concrete dead loads have been addressed in the screed elevations provided

The State of Practice for Highly Skewed BridgesThe State of Practice for Highly Skewed Bridges

Deck Issues: Construction PerspectiveDeck Issues: Construction Perspective

Email Questions to:

[email protected]

Questions ??Questions ??