decommissioning of hifar documents...• medical radioisotopes • silicon irradiation •...

21
Decommissioning of HIFAR Daniel Pond HIFAR Manager May 2012

Upload: others

Post on 06-Oct-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Decommissioning of HIFAR

Daniel Pond

HIFAR Manager

May 2012

Page 2: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• 10 MW Materials Test

Reactor utilising 25 fuel

elements cooled and

moderated by heavy water

(D2O)

• Medical radioisotopes

• Silicon Irradiation

• Industrial radioisotopes

• Irradiated materials

research

• Neutron beams

• NAA

HIFAR

Page 3: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• 10MW operation from 1960 to

2007

• Original estimated life of 15

years based on anticipated

corrosion rate of the aluminium

tank (RAT)

• Reactor building steel shell is

21m tall and 21m diameter

HIFAR

Page 4: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• Biological shield is decagonal,

6.7m across flats and 5.9m high

• Total block mass 817 t

• RAT surrounded by 30 tonnes of

graphite

• 6 Control Arms

(Cadmium/Europium)

• 2 Safety Rods (Cadmium)

• Peak thermal neutron flux of

1.4e14 n cm-2 s-1

• Total energy created 130,000 MW-

days

HIFAR

Page 5: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• Neutron scattering

facilities

HIFAR

Page 6: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

HIFAR Decommissioning

• Phase A – Closure • Part 1 – Shutdown, remove fuel, water, rigs

• Part 2 – Preliminary dismantling

• Part 3 – Refurbishing

• Phase B – Care & Maintenance

• Phase C – Decommissioning • Part 1 – Preparation for dismantling

• Part 2 – Dismantling

• Phase D – Return to Green/Brown Field

Page 7: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Current Staffing (12)

• HIFAR Manager Daniel Pond

• HIFAR Site Supervisor John Wernej

• Project Officer (Mechanical) Hugo Rivera

• Project Officer (Electrical) Bernie Felkins

• Information Management Consultant Richard Healy

• Information Management Assistants Andrew Healy & Thomas Young

• Supervisor Active Handling Brad Ryan

• Electrical Fitter/Maintenance Planner Don Leitch

• Mechanical Fitter/Maintenance Planner Bill Gamblin

• HIFAR Technical Expert Pertti Sirkka

• HIFAR Waste Process Engineer Brett Taylor (starting May 2012)

Page 8: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

HIFAR Organisation Chart

GM, Nuclear Operations

Manager, Waste

Operations

(Facility License Nominee)

Manager, HIFAR

(HIFAR Facility Officer)

(HIFAR Licensing Officer)

Leader, Compliance

Management

HIFAR Maintenance

Group

Project OfficersSite Supervisor, HIFAR

(HIFAR Area Supervisor)

HIFAR Supervisor Active

Handling

Page 9: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Related Staffing

MPDO

Planning,

implementation,

supervision

Waste Operations

Decontamination &

Waste Management

SERA

OH&S advice &

Health Physics

Systems Safety and

Reliability

Safety Assessments &

Licensing

Engineering & Capital

Programs

Drafting, SAPO, Records

Management

Facilities Management

Maintenance, Inspections

Supervision

Reactor Operations

Maintenance & dismantling

Shielding and activity

calculations

Public Affairs

Legal & Regulations

Page 10: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• No shift staffing – facility is staffed Mon-Fri during routine business hours only

• Operations / General Administration

• Active Handler & Site Supervisor perform daily check (safety & operability)

• Routine maintenance and defect repairs

• Health physics surveys fortnightly (or before/after work)

• Remote check of environment prior to entry to HIFAR

• Regular monitoring of environmental parameters

• Projects – Refurbishment & Dismantling

• Preparation of project documentation

• Implementation of projects

Day to Day Activities

Page 11: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

HIFAR Decommissioning –

Approximate Timetable • Phase A – Closure - Jan 2007 to June 2012

• FRJ-2 DLA translation – Jan 2012

• Phase B – 2012 to 2016

• Characterisation – Jul 2012 – Jun 2014

• DLA preparation & EIS – Jul 2013 – Dec 2014

• ARPANSA & public review – Jan 2015 – Jun 2016

• ARPANSA Licence approval – Jun 2016

• Phase C – Decommissioning – 2016 to 2018

• Phase D – Green/Brown field – 2019

• NRWMF Construction – 2020

Page 12: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• Part 1 – Shutdown & removal of fuel, rigs, targets, absorbers

and water. Minimisation of nuclear material, fire loading and

safety hazards without making modification to plant.

• Part 2 – Preliminary dismantling of selected redundant plant.

Reduce footprint, minimise hazards (electrical, confined

space, fire loading, contaminants/radiation).

• Part 3 – Installation and commissioning of refurbished plant.

Reduce maintenance & operational costs, increase safety.

Phase A

Page 13: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

• Jan 07 Shutdown

• Feb 07 Fuel elements transferred to No.1 Storage Block

• Mar 07 Core fully unloaded to No.1 Storage Block

• Apr 07 Fuel shearing and removal of all fuel from HIFAR

• May 07 Heavy water drained from reactor (10.4t)

• May 07 Initial Possess or Control Licence application

• Jun 07 24hr shift staffing ceased

• Nov 07 Last control arm removed

• Jun 08 Remaining cobalt 60 targets removed

Milestones Since Shutdown

Page 14: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Milestones Since Shutdown

• Sep 08 Possess and Control Licence granted

• Apr 09 3D laser scan of HIFAR

• Mar 09 Spent fuel shipped overseas

• Mar 11 HIFAR cranes disabled (except Polar crane)

• Mar 11 Last Registered Radiation Source Removed from HIFAR

• Sep 11 Transfer of maintenance from Mainpac to SAP

• Sep 11 Evaporative drying of No.1 Storage Block Fuel Element

Tank is now completed

• Dec 11 Recruitment of new (old) maintenance group

Page 15: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

On going Operational Work

• Gradual Tritium reduction from 01 & 02 circuits via Active Extract stack release. Each week a 120 minute purge through the Active Extract System is performed

• Records Rationalisation

• Registration of hard and soft copy records

• Classification of records (more than security classification)

• Optical Character Recognition Scanning of records

• Disposal of duplicate records

• Maintenance work

• Projects

• Refurbishment

• Dismantling

• Upgrade of HIFAR Records Repositories

• Revision of HIFAR QMS

• Revision of HIFAR Plans and Arrangements

• HIFAR Decommissioning Scoping Project

Page 16: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Active Stack Tritium Discharge Stack: 15A Nuclide: TRITIUM Weekly

The 4-weekly notification level for B15A/TRITIUM is 2.00E+03 GBq

Max: 4.81E+01 GBq 4Week Rolling: 7.17E+01 GBq

Stack: B15A Nuclide: Tritium Unit: GBq

3/0

5/2

01

1

10

/05

/20

11

24

/05

/20

11

7/0

6/2

01

1

21

/06

/20

11

5/0

7/2

01

1

19

/07

/20

11

2/0

8/2

01

1

16

/08

/20

11

30

/08

/20

11

13

/09

/20

11

27

/09

/20

11

11

/10

/20

11

25

/10

/20

11

8/1

1/2

01

1

22

/11

/20

11

6/1

2/2

01

1

20

/12

/20

11

3/0

1/2

01

2

17

/01

/20

12

31

/01

/20

12

14

/02

/20

12

28

/02

/20

12

13

/03

/20

12

27

/03

/20

12

10

/04

/20

12

24

/04

/20

12

GB

q

50

48

46

44

42

40

38

36

34

32

30

28

26

24

22

20

18

16

14

12

10

8

6

4

2

0

Page 17: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Future Activities

• Dismantling Projects

• Closeout of Refurbishment Projects

• HIFAR Characterisation

• Class C Decommissioning Cost Estimate

• Mobilisation of Core Decommissioning Team

• Mobilisation of Decommissioning Team

• Decommissioning Licence Application

• Purchase of Decommissioning Plant & Equipment

• Purchase of Waste Packages

• Recruitment and Training of Decommissioning Personnel

• Decommissioning

Page 18: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Safety Incidents since

Shutdown • HIFAR staff member becoming trapped in the B42

Personnel Air Lock

• Contractor driving a forklift over concrete and steel

trench covers resulting in broken and buckled

trench covers

• Unsecured roof sheet metal being blown away by

wind gusts

Page 19: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR

Timeframe

• Characterisation - 2 years

• Decommissioning planning - 2 years

• Environmental approval process Up to 1 year

• Licence application: prepare and approve - 1 year

• Technical staff recruitment and training - 1 year

• Equipment and plant procurement - 1.5 years

• Dismantling of reactor - 1 year

• Site clean-up and decom report - 0.5 years

• Decommissioning Period - 6.5 years

Page 20: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR
Page 21: Decommissioning of HIFAR Documents...• Medical radioisotopes • Silicon Irradiation • Industrial radioisotopes • Irradiated materials research • Neutron beams • NAA HIFAR