degree project presentation

Upload: jonathan-evangelista

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Degree Project Presentation

    1/59

    IEEE 14-Bus Transmission System Analysis

    Group Members

    Jonathan Evangelista

    Tyler Ross

    Romair Wong

    Francis Idehen

    ENGI 4969Degree Project

    Project Supervisor

    Dr. Xiaoping Liu

  • 7/28/2019 Degree Project Presentation

    2/59

    Presentation Subject Matter

    Introduction

    Topics of Analysis

    1. Loadflow and State Estimation

    2. Transient Stability Analysis

    3. Fault Analysis

    4. Economic Dispatch

    Conclusion

    Question Period

  • 7/28/2019 Degree Project Presentation

    3/59

    IEEE 14 Bus Test System

  • 7/28/2019 Degree Project Presentation

    4/59

    Load Flow and State Estimation

    Load Flow: Results

    Load Flow: Verification

    Load Flow: Design Issues & Resolutions State Estimation: Justification

    State Estimation: Results

    State Estimation: Future Work

  • 7/28/2019 Degree Project Presentation

    5/59

    Load Flow

  • 7/28/2019 Degree Project Presentation

    6/59

    Load Flow Results & Verification

    Our Load Flow Results

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.383 -16.9783

    Bus 2 1.0192 -10.3343 -47.8 3.9

    Bus 3 1.0205 -8.7835 -7.6 -1.6

    Bus 4 1.07 -14.2012 -11.2 -31.6245

    Bus 5 1.0691 -13.3736 0 0

    Bus 6 1.09 -13.3736 0 12.9585

    Bus 7 1.0584 -14.9473 -29.5 -16.6

    Bus 8 1.053 -15.1015 -9 -5.8

    Bus 9 1.058 -14.7844 -3.5 -1.8

    Bus 10 1.0554 -15.056 -6.1 -1.6

    Bus 11 1.0507 -15.1409 -13.5 -5.8

    Bus 121.0371 -16.0293 -14.9 -5

    Bus 13 1.045 -4.9808 18.3 29.4137

    Bus 14 1.01 -12.7161 -94.2 5.1746

    Total System Losses 13.383 -35.356

    Verification Results: Capacitor Bank Susceptance =0.095

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.4232 -16.5455

    Bus 2 1.0177 -10.313 -47.6246 4.0096

    Bus 3 1.0195 -8.7774 -7.8563 -1.6539

    Bus 4 1.07 -14.221 -11.291 -30.2953

    Bus 5 1.0615 -13.36 -0.0061 -12.4472

    Bus 6 1.09 -13.3596 0.0046 17.6355

    Bus 7 1.0559 -14.939 -29.5205 -12.6304

    Bus 8 1.051 -15.0973 -8.9783 -5.7809

    Bus 9 1.0569 -14.791 -3.5074 -1.8015

    Bus 10 1.0552 -15.0576 -5.9094 -1.7403

    Bus 11 1.0504 -15.1563 -13.5668 -5.6964

    Bus 121.0355 -16.034 -14.9027 -5.0034

    Bus 13 1.045 -4.9826 18.3336 30.8398

    Bus 14 1.01 -12.7251 -94.2055 6.0603

    Total System Losses 13.3928 -35.0496

  • 7/28/2019 Degree Project Presentation

    7/59

    Load Flow Results & Verification

    Difference Between Results

    |Voltage| Percentage Voltage Angle Percentage

    Bus 1 0 0.00% 0 0.00%

    Bus 2 0.0015 -0.15% -0.0213 -0.21%

    Bus 3 0.001 -0.10% -0.0061 -0.07%

    Bus 4 0 0.00% 0.0198 0.14%

    Bus 5 0.0076 -0.72% -0.0136 -0.10%

    Bus 6 0 0.00% -0.014 -0.10%

    Bus 7 0.00247 -0.23% -0.0083 -0.06%

    Bus 8 0.002 -0.19% -0.0042 -0.03%

    Bus 9 0.00109 -0.10% 0.0066 0.04%

    Bus 10 0.0002 -0.02% 0.0016 0.01%

    Bus 11 0.0003 -0.03% 0.0154 0.10%

    Bus 12 0.00157 -0.15% 0.0047 0.03%

    Bus 13 0 0.00% 0.0018 0.04%

    Bus 14 0 0.00% 0.009 0.07%

  • 7/28/2019 Degree Project Presentation

    8/59

    Load Flow Design Issues & Resolutions

    Our Load Flow Results: Capacitor Bank Susceptance=0.19

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.3815 -17.5155

    Bus 2 1.0209 -10.367 -47.8 3.9

    Bus 3 1.0216 -8.7916 -7.6 -1.6

    Bus 4 1.07 -14.1069 -11.2 -36.202

    Bus 5 1.0749 -13.4342 9.49E-14 -2.19E-13

    Bus 6 1.09 -13.4342 -4.16E-14 9.3694

    Bus 7 1.0699 -15.008 -29.5 -16.6

    Bus 8 1.0625 -15.1374 -9 -5.8

    Bus 9 1.0628 -14.7629 -3.5 -1.8

    Bus 10 1.0562 -14.9641 -6.1 -1.6

    Bus 11 1.0524 -15.0704 -13.5 -5.8

    Bus 12 1.0444 -16.0215 -14.9 -5

    Bus 13 1.045 -4.9801 18.3 27.6958

    Bus 14 1.01 -12.71 -94.2 4.1137

    Total System Losses 13.3815 -46.8386

    Verification Results: Capacitor Bank Susceptance = 0.19

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.4232 -16.5455

    Bus 2 1.0177 -10.313 -47.6246 4.0096

    Bus 3 1.0195 -8.7774 -7.8563 -1.6539

    Bus 4 1.07 -14.221 -11.291 -30.2953

    Bus 5 1.0615 -13.36 -0.0061 -12.4472

    Bus 6 1.09 -13.3596 0.0046 17.6355

    Bus 7 1.0559 -14.939 -29.5205 -23.2228

    Bus 8 1.051 -15.0973 -8.9783 -5.7809

    Bus 9 1.0569 -14.791 -3.5074 -1.8015

    Bus 10 1.0552 -15.0576 -5.9094 -1.7403

    Bus 11 1.0504 -15.1563 -13.5668 -5.6964

    Bus 12 1.0355 -16.034 -14.9027 -5.0034

    Bus 13 1.045 -4.9826 18.3336 30.8398

    Bus 14 1.01 -12.7251 -94.2055 6.0603

    Total System Losses 13.3928 -45.642

  • 7/28/2019 Degree Project Presentation

    9/59

    Load Flow Design Issues & Resolutions

    Our Load Flow Results: Inductor Bank = 0.25

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.383 -16.9783

    Bus 2 1.0192 -10.3343 -47.8 3.9

    Bus 3 1.0205 -8.7835 -7.6 -1.6

    Bus 4 1.07 -14.2012 -11.2 -3.002

    Bus 5 1.0691 -13.3736 -5.30E-14 5.98E-13

    Bus 6 1.09 -13.3736 -2.19E-14 12.9585

    Bus 7 1.0584 -14.9473 -29.5 -16.6

    Bus 8 1.053 -15.1015 -9 -5.8

    Bus 9 1.058 -14.7844 -3.5 -1.8

    Bus 10 1.0554 -15.056 -6.1 -1.6

    Bus 11 1.0507 -15.1409 -13.5 -5.8

    Bus 12 1.0371 -16.0293 -14.9 -5

    Bus 13 1.045 -4.9808 18.3 29.4137

    Bus 14 1.01 -12.7161 -94.2 5.1746

    Total System Losses 13.383 -6.7335

  • 7/28/2019 Degree Project Presentation

    10/59

    State Estimation

  • 7/28/2019 Degree Project Presentation

    11/59

    State Estimation Justification

    State Estimation Results with only Ammeters

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.4307 -17.0215

    Bus 2 1.0191 -10.3413 -47.2628 3.5936

    Bus 3 1.0205 -8.7859 -5.2704 -1.0163

    Bus 4 1.07 -14.4591 -14.0875 -30.8252

    Bus 5 1.0692 -13.4532 -0.5992 0.419

    Bus 6 1.09 -13.4532 2.06E-13 12.8902

    Bus 7 1.0583 -15.0312 -29.3543 -17.4161

    Bus 8 1.0532 -15.1995 -8.4753 -5.5637

    Bus 9 1.0578 -14.9584 -3.5714 -2.0719

    Bus 10 1.0553 -15.3063 -6.0599 -1.5662

    Bus 11 1.0506 -15.3832 -13.8465 -5.9414

    Bus 12 1.0372 -16.1718 -14.7264 -4.902

    Bus 13 1.045 -4.9819 18.3457 29.4057

    Bus 14 1.01 -12.7178 -94.144 5.191

    Total System Losses 13.3787 -34.8248

    Our Load Flow Results

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 232.383 -16.9783

    Bus 2 1.0192 -10.3343 -47.8 3.9

    Bus 3 1.0205 -8.7835 -7.6 -1.6

    Bus 4 1.07 -14.2012 -11.2 -31.6245

    Bus 5 1.0691 -13.3736 0 0

    Bus 6 1.09 -13.3736 0 12.9585

    Bus 7 1.0584 -14.9473 -29.5 -16.6

    Bus 8 1.053 -15.1015 -9 -5.8

    Bus 9 1.058 -14.7844 -3.5 -1.8

    Bus 10 1.0554 -15.056 -6.1 -1.6

    Bus 11 1.0507 -15.1409 -13.5 -5.8

    Bus 12 1.0371 -16.0293 -14.9 -5

    Bus 13 1.045 -4.9808 18.3 29.4137

    Bus 14 1.01 -12.7161 -94.2 5.1746

    Total System Losses 13.383 -35.356

  • 7/28/2019 Degree Project Presentation

    12/59

    State Estimation Results

    State Estimation Results

    |Voltage| Voltage Angle Total MW Total MVAR

    Bus 1 1.06 0 231.5597 -16.9621

    Bus 2 1.0188 -10.1864 -45.7472 1.0942

    Bus 3 1.0205 -8.6489 -5.4136 -1.4732

    Bus 4 1.07 -14.0739 -12.4318 -30.8687

    Bus 5 1.0697 -13.2223 -0.1336 2.0601

    Bus 6 1.09 -13.2223 -2.08E-15 12.5355

    Bus 7 1.0579 -14.7869 -29.921 -18.9127

    Bus 8 1.0535 -14.932 -9.2096 -4.11

    Bus 9 1.0576 -14.5067 -1.5761 -3.2759

    Bus 10 1.0554 -14.9276 -6.0775 -1.5762Bus 11 1.0507 -15.0114 -13.6507 -5.9201

    Bus 12 1.0374 -15.8773 -14.6957 -4.7037

    Bus 13 1.045 -4.9902 14.2583 30.5225

    Bus 14 1.01 -12.6292 -93.8491 5.2924

    Total System Losses 13.1121 -36.2979

    Measurement Tag Error(%)

    21 23.4392

    51 10.7101

    18 10.5085

    80 19.4064

    40 14.7082

    42 4.2677

  • 7/28/2019 Degree Project Presentation

    13/59

    State Estimation ResultsIdentifying Good Data over Ten Iterations

    Branch Information Error Percentage on Fixed Specified Measurement

    Branch Tag # Branch Power Load Flow Powers 20%:P1-13 20%:P2-3 20%:Q13-2

    1 P1-3 75.5528 60% 60% 80% 100% 100% 90%

    2 Q1-3 3.4136 90% 90% 100% 100% 100% 100%

    3 P1-13 156.8302 0% 0% 70% 100% 80% 100%

    4 Q1-13 -20.392 90% 80% 90% 100% 100% 100%

    5 P2-3 -61.3705 70% 90% 0% 0% 100% 90%

    6 Q2-3 17.2562 80% 100% 40% 80% 100% 100%

    7 P2-5 28.246 90% 100% 100% 100% 100% 100%

    8 Q2-5 -24.1087 90% 100% 100% 100% 100% 100%

    9 P2-7 16.0969 100% 100% 100% 100% 100% 100%

    10 Q2-7 -6.7685 100% 100% 100% 100% 100% 100%

    11 P2-13 -54.4895 80% 90% 100% 100% 100% 100%

    12 Q2-13 3.8999 100% 100% 100% 100% 100% 100%

    13 P2-14 23.7171 100% 100% 90% 90% 90% 90%

    14 Q2-14 -3.9695 100% 100% 100% 100% 100% 100%

    15 P3-1 -72.7896 60% 70% 100% 100% 100% 90%

    16 Q3-1 2.6675 100% 90% 100% 100% 100% 100%

    17 P3-2 61.8928 70% 90% 20% 40% 100% 90%

    18 Q3-2 -15.6085 80% 100% 30% 50% 100% 80%

  • 7/28/2019 Degree Project Presentation

    14/59

    State Estimation Future Work

    Creating a Database

    Adjust for redundancy lower than one

    Incorporate Phasor Measurement Units intothe algorithm

  • 7/28/2019 Degree Project Presentation

    15/59

    Transient Stability Analysis

    What is Transient Stability?

    Multimachine System

    Classical Stability Model 5 Assumptions associated with a Classical

    Stability Study

    Test Bench (9-Bus System) IEEE 14-Bus Test System

  • 7/28/2019 Degree Project Presentation

    16/59

    What is Transient Stability?

    Transient disturbances

    Mechanical analogy

    This image is from Transient Stability of Large Scale Power Systems

    by Vijay Vittal of Iowa State University.

  • 7/28/2019 Degree Project Presentation

    17/59

    Multimachine System

    Equal area Criterion vs. Swing Equation

    Single Machine System

    Multi Machine System(9-Bus Test Bench Model)

  • 7/28/2019 Degree Project Presentation

    18/59

    Classical Stability Model

    Classical Representation of a

    Multimachine System

    Assumptions associated with this model:

    1. Constant mechanical power input

    during swing

    2. Negligible damping power

    3. Constant transient reactance in series

    with constant transient internal

    voltage

    4. Internal generator voltage angle

    coincides with mechanical rotorangle

    5. Constant load admittances

  • 7/28/2019 Degree Project Presentation

    19/59

    Calculations

    2 + cos +

    =1

    The Swing Equation:

    Internal Generator Voltages:

    +

    +

    Constant Load Admittances:

  • 7/28/2019 Degree Project Presentation

    20/59

    9 Bus System - Test Bench

    The 9 Bus transmission system which was used as a test bench was taken from Power

    System Control and Stability 2ndEdition by Anderson and Fouad:

  • 7/28/2019 Degree Project Presentation

    21/59

    9 Bus System - Test Bench

  • 7/28/2019 Degree Project Presentation

    22/59

    9 Bus System - Test Bench

  • 7/28/2019 Degree Project Presentation

    23/59

    9 Bus System - Test Bench

  • 7/28/2019 Degree Project Presentation

    24/59

    Fault Analysis

  • 7/28/2019 Degree Project Presentation

    25/59

    FAULT ANALYSIS

    Background

    Objective

    Methodology

    Sample Calculations

    GUI Flow Chart

    Graphical User Interface

    Extension of the project

    Future Expansion

    Problems Encounter

  • 7/28/2019 Degree Project Presentation

    26/59

    Fault Analysis (cont.)

    Background

    Causes of Faults

    1. Insulation failure

    2. Flashover

    3. Physical Damage

    4. Human error

  • 7/28/2019 Degree Project Presentation

    27/59

    Fault Analysis (cont.)

    Types of fault

    1. Symmetrical (Balanced)

    2. Unsymmetrical (Unbalanced)

  • 7/28/2019 Degree Project Presentation

    28/59

    Module Objective

    Build a dynamic software package to assist users

    to perform fault analysis

  • 7/28/2019 Degree Project Presentation

    29/59

    Extension to the Project

    Modification of an existing Z bus Case 1: Adding Zb from a new bus P to reference node

    Case 2: Adding Zb from a new bus P to an existing bus k

    Case 3: Adding Zb from Existing bus k to the reference node

    Case 4: adding Zb between two existing buses (j) and (k)

    Kron Reductions

    M h d l Fl Ch

  • 7/28/2019 Degree Project Presentation

    30/59

    Methodology Flow Chart

  • 7/28/2019 Degree Project Presentation

    31/59

    Method of Calculation and Procedure

    To illustrate, impedance matrix was used

    Consider a bus Power system shown below

  • 7/28/2019 Degree Project Presentation

    32/59

    Method of Calculation(cont.)

  • 7/28/2019 Degree Project Presentation

    33/59

    Method of Calculation(cont.)

    Y11Y21y31y41

    y12y22y32y42

    y13y23y33y43

    y14y24y34y44

    V1VFV3V4 = 0I F0

    0

    If

    V1VFV3V4

    Z11Z1y31Z41

    Z1ZZ3Z4

    Z13Z3Z33Z43

    Z14Z4Z34Z44

    0If

    00

    V Y1

    buI ZbuI

    1 1If 1 3 3If

    3

    4 4I

    f

    4

    V1V2V3

    V4

    = VfVfVf

    Vf

    + V1V2V3V4 = Vf

    Vf

    Vf

    Vf

    + 12

    22 VfVf3222 Vf

    42

    22

    Vf

    =

    1 12

    22 VfVf1 3222 Vf1

    42

    22

    Vf

    Impedance MatrixAdmittance Matrix

    Current

    Post Fault VoltagesDuring Fault Voltage

  • 7/28/2019 Degree Project Presentation

    34/59

    Method of Calculation(cont.)

  • 7/28/2019 Degree Project Presentation

    35/59

    GUI Flow Chart

  • 7/28/2019 Degree Project Presentation

    36/59

    MATLAB GUI Menu

  • 7/28/2019 Degree Project Presentation

    37/59

    MATLAB GUI Menu

    Figure 1: shows the Impedance matrix

    Figure 3: shows the post

    fault voltages

    Figure 2: shows the current matrix after the fault

  • 7/28/2019 Degree Project Presentation

    38/59

    Some Problems Encounter

    Making the program dynamic

    Expansion of the 4 cases

  • 7/28/2019 Degree Project Presentation

    39/59

    Summary

    Future Expansion

    And also implementation of a unsymmetrical fault, which could be the

    continuation of this project to enhance the fault states of the network. This

    causes a single line, line to line and double line fault to occur. A pop menu is

    also created within the Graphical User Interface for this application Addition of different zones around the network grid to aid in simulation of the

    location of the faulted in order to gather information in the selection of

    switchgears and relays.

  • 7/28/2019 Degree Project Presentation

    40/59

    Optimal Economic

    Dispatch

  • 7/28/2019 Degree Project Presentation

    41/59

    Points to be covered

    What is Optimal Economic dispatch?

    Design Phases

    Calculations Findings

    Summary

  • 7/28/2019 Degree Project Presentation

    42/59

    The Goal of Optimal

    Economic dispatch

  • 7/28/2019 Degree Project Presentation

    43/59

    Design Phases

    Phase 1: Devise Algorithm suitable for

    calculation of the Loss or B-Coefficients

    of the system.

    Phase 2: Obtain Optimal Economic

    Dispatch.

  • 7/28/2019 Degree Project Presentation

    44/59

    Transmission Loss

  • 7/28/2019 Degree Project Presentation

    45/59

    Obtaining an

    Expression for Transmission loss

    for the System

    Overall

    transmission lossexpression for the

    system

  • 7/28/2019 Degree Project Presentation

    46/59

    Flowchart for

    Obtaining LossCoefficients

  • 7/28/2019 Degree Project Presentation

    47/59

    Optimal Economic Dispatch

  • 7/28/2019 Degree Project Presentation

    48/59

    Classic Economic Dispatch

    The goal of economic dispatch is to determine

    the generation dispatch that minimizes the

    instantaneous operating cost.

    Such ThatMinimize

  • 7/28/2019 Degree Project Presentation

    49/59

    CalculationsIncremental Transmission LossIncremental Production Cost

    Overall Expression

    Taking into Account all Generators

    Condition for

    Optimum Dispatch

  • 7/28/2019 Degree Project Presentation

    50/59

    Economic

    Dispatch

    Flowchart

  • 7/28/2019 Degree Project Presentation

    51/59

    Graphical User Interface

  • 7/28/2019 Degree Project Presentation

    52/59

    B-Coefficients and Power Loss

  • 7/28/2019 Degree Project Presentation

    53/59

    Optimal Economic Dispatch

    T t b h d i i /

  • 7/28/2019 Degree Project Presentation

    54/59

    Test bench used in comparisons/

    verification

  • 7/28/2019 Degree Project Presentation

    55/59

    Discuss Results/Problems

    These results Verified with Test-bench. Graphs show after each iteration, the system starts from a max

    value then gradually begins to decrease closer to an optimaloperating point.

    The values and cost functions used in 14-bus economic dispatch

    were from another 14-bus system (Port Land State University). 15.21MW total system loss - compared to the 13.386MW on

    original 14-bus data sheet.

    14 bus incremental losses, cost and overall economic dispatch leftquestionable.

    At 15

    th

    iteration during the calculations of incremental loss, cost andoverall economic dispatch, error message stating matrix singularor badly scaled occurred.

  • 7/28/2019 Degree Project Presentation

    56/59

    Future Improvements

    dynamic retrieval of voltage and powers from

    the Load Flow module of the program.

    Include generator limits

    Include transmission limits were omitted from

    the analysis system. Simply, we considered the

    system without these restrictions.

    contingency in place should stability and fault

    issues severely impede its ability to function.

  • 7/28/2019 Degree Project Presentation

    57/59

    Conclusion

  • 7/28/2019 Degree Project Presentation

    58/59

    Demonstration

  • 7/28/2019 Degree Project Presentation

    59/59

    IEEE 14 Bus Test System

    Pre-Post

    Bus No. V Voltage Angle Real Power Reactive Power1 0 0 -0.1299 -0.05772 0.0009 0.032 0 03 0.0002 -0.0203 0 04 0 -0.3685 0 2.05025 0.0022 0.2409 8.9359E-14 3.68549E-136 0 0.2409 1.2837E-14 -1.3547 0.0041 0.354 0 08 0.0035 0.2269 0 09 0.002 -0.068 0 0

    10 -0.0017 -0.5135 0 011 -0.0045 -0.619 0 012 0.015 1.0763 0 013 0 0.0095 0 -0.722814 0 0.032 0 -0.5035