delay and dissatisfaction in the aquino administration's ppp program: recommendations for future...
TRANSCRIPT
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
1/13
MAR
DELAY AND DISSATISFACTION
IN THEAQUINO ADMINISTRATIONSPPP PROGRAM:
RECOMMENDATIONSFOR FUTUREPARTNERSHIPS ININFRASTRUCTURE
9.3VOLUME
PAPEROCCASIONAL
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
2/13
The Public Private Partnership (PPP) program, claimed as a
pillar of this administrations economic and infrastructure
development plan, is under greater pressure this 2016
as President Aquino has only three months left in oce. The
emphasis President Aquino placed on the importance of
infrastructure development back in 2010 should have been
a good measure of the administrations consistent
support for the PPP program.
However, delay in the progress of the PPP scheme has been
evident since its launch in 2010. The minimal number of PPPprojects that have been awarded since Aquino assumed of-
ce12 out of the 53 projects in the pipeline is
dissatisfying. Moreover, the President must realize that the
number of awarded PPP projects should not be the sole
basis of measuring success; the completion and successful
operation of the infrastructure should also be made the basis.
Nonetheless, the Aquino administration can use the remaining
time in oce to fast track the PPP scheme without
sacricing transparency and legitimacy in the process.
This paper aims to identify the reasons why the PPP program
could have been a good avenue to improve our countrys
infrastructure industry but has thus far failed to fully deliver.The rst part tackles the Philippines overall competitiveness
and the importance of infrastructure in this regard,
* The views and opinions expressed in this Paper are those of the author and do not necessa
comparing Philippine performance vis--vis neighboring
Southeast Asian countries. It then turns to the chokepoints in the
PPP scheme: the insucient technical capacity within some
government agencies, the under-empowered PPP center,
an improperly implemented bidding process,
and barriers to foreign capital investment.
In concluding, the paper provides recommendations to be
considered for the next administration. In the time remaining, the
Aquino administration should focus on maintaining the
transparency and legitimacy of the PPP process as it seeks tofast-track the awarding of projects. Doing so in this manner will
help it leave a legacy of enduring public-private partnerships.
DELAY AND DISSATISFACTION
IN THEAQUINO ADMINISTRATIONS
PPP PROGRAM:RECOMMENDATIONSFOR FUTURE PARTNERSHIPS
IN INFRASTRUCTURE
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
OCCASIONAL PAPER MARCH 2016
02
PPP PROGRAM
could have been a good avenue to improve our country's infrastructure industry buthas thus far failed to fully deliver. The Aquino administration can use the
remaining time in office to fast track the PPP scheme withoutsacrificing transparency and legitimacy in the process.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
3/13
The Public-Private Partnership Program
PPP was rst introduced in the Philippines in 1990,
through the passage of Republic Act (RA) No. 6957,
known as the Build, Operate and Transfer Law (BOT
Law), signed by then President Corazon Aquino. The
BOT Law authorizes private entities to construct, nance,
operate and maintain a public infrastructure facility.
Four years later, RA 6957 was amended by RA 7718 to
provide nancial incentives and to minimize government
regulations so that the private sector will be more
encouraged to participate in the PPP program. RA 7718
governs the procurement of infrastructure or development
projects by the private sector. Under this law,
infrastructure or development projects may be
undertaken through any of the contractual arrangements
provided* therein for which pertinent incentives will be
given to stimulate private resources for the purpose of
nancing the construction, operation and maintenance of
infrastructure and development projects normally
undertaken by the government.
Recognizing the importance of infrastructure in building
the foundations of a strong economy, past administra-
tions consistently focused on improving infrastructure,
certain that investments in this area would bring benets
across sectors and create more opportunities for the
fast-growing population. Conversely, poor infrastructure
is widely accepted to be a signicant barrier to
trade and discourages investment.
Projects through PPP are expected to boost the countrys
growth rate to 7-8%.1 This means intensied infrastruc-
ture spending, increased private investment and
eventually higher tourism receipts, which will only
be possible by increasing investor condence in the
countrys ability to nance and complete these PPP
projects. The resurgence of the PPP program in
this Aquino administration shows its commitment to
accelerating public infrastructure development that
would likely attract more foreign investment
and boost tourism, thereby increasing
job opportunities for Filipinos.
In 2011, Stratbase Research Institute published
its analysis on PPP through its Occasional Paper
entitled The PPP Challenge. The paper sought to
establish the importance of PPP to the countrys
economic growth for the succeeding years and,
further, provided recommendations on how PPP
can be properly implemented by the Aquino
administration so as to make it an eective
tool in national development.
Yet, the promise of growth via PPP has been
weakened by the vulnerability of the scheme to
politics. Had the Aquino administration maximized
the full potential of the PPP scheme, the Philippines
would have reaped the benets of a growing
economy and a high rate of inclusive growth.
The underlying question arises as to how the
slow progress of the PPP program of the
Philippines has aected its competitiveness.
Big ticket projects that investors h
watching out to fund under the PP
been slow to materialize. To date,
three projects in the PPP pipeline
projects have been awarded:
(1) Daang Hari-South Luzon E
Road;
(2) First phase of the PPP for
ture Project;
(3) Ninoy Aquino International
way;
(4) Second phase of the PPP
structure Project;
(5) Modernization of the Philip
Center;
(6) Automatic Fare Collection
(7) Mactan-Cebu Internationa
(8) LRT Line 1 South Extensio
(9) Integrated Transport Syste
Terminal Project;
(10) Cavite-Laguna Expressw
(11) Integrated Transport Sys
Terminal Project; and
(12) Bulacan Bulk Water Supp
Out of these twelve projects, only
Hari-South Luzon Expressway Lin
called the Muntinlupa Cavite Expr
(MCX), is operational.2
*Section 1 of R.A. 7718 enumerated/dened the following contractual arrangements: 1. Build-operate-and-transfer; 2. Buildand-operate; 4. Build-lease-and-transfer; 5. Build-transfer-and-operate; 6. Contract-add-and-operate; 7. Develop-operate-aoperate-and-transfer; 9. Rehabilitate-own-and-operate; and 10. Such other variations as may be approved by the President of
OCCASIONAL PAPER MARCH 2016
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
03
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
4/13
Table 1. Global Competitiveness report(2015-2016)
Source: the Global Competitiveness report 2015-2016
As of February 2016, 10 PPP projects are up for
bidding:
(1) Operation and Maintenance of LRT Line 2;
(2) Regional Prison Facilities;
(3) Laguna Lakeshore Expressway Dike Project;
(4) Davao Sasa Port Modernization Project;
(5) PPP Airport Operations and Maintenance of
the Bacolod (Silay) Airport & Iloilo Airport (bundle
1);
(6) PPP Airport Operations and Maintenance of
the New Bohol (Panglao) Airport, Laguindingan
Airport and Davao Airport (bundle 2);
(7) Road Transport IT Infrastructure Project
(Phase II);
(8) North-South Railway Project (South Line);
(9) Civil Registry System-Information Technology
Project (Phase II); and
(10) LRT Line 6 Project3
Infrastructure Limits PhilippineCompetitiveness
The World Economic Forum (WEF)s Global
Competitiveness Report denes competitiveness
as the set of institutions, policies, and factors that
determine the level of productivity of a country. The
level of productivity, in turn, sets the level of
prosperity that can be reached by an economy. The
productivity level also determines the rates of return
obtained by investments in an economy, which in
turn are the fundamental drivers of its growth rates.
In other words, a more competitive economy is
one that is likely to grow faster over time. 4
Infrastructure is one of four pillars in the Global
Competitiveness Reports index (GCI), alongside
institutions, macroeconomic environment, and
health and primary education. In elevating
infrastructure as a pillar, the Global Competitiveness
Report nds that [a] well-developed infrastructure
system reduces the eect of distance between
regions, integrating the national market and
connecting it at low cost to markets in other
countries and regions. In addition, the quality and
extensiveness of infrastructure networks
signicantly impact economic growth and reduce
income inequalities and poverty in a variety of ways.
A well-developed transport and communications
infrastructure network is a prerequisite for the
access of less-developed communities to core
economic activities and services.5
Overall, the Philippines has improved its
competitiveness: rising ve notches on the Reports
2015-2016 index to 47th of 140 countries. The
countrys latest performance followed a 7-notch
jump to 52nd in the 2014-2015 report and a
6-notch jump to the 59th spot in 2013-2014. The
Philippines has jumped 33 places in total under the
Aquino administration, showing the largest gain
among all other countries in the study since 2010.
The Philippines got the highest ranking in terms of
macroeconomic environment followed by market
size and business sophistication (see Table 1).
OCCASIONAL PAPER MARCH 2016
04
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
5/13
The same report shows, however, that the
country lags behind in terms of infrastructure,
labor market eciency and goods market
eciency. The report lists the Philippines
infrastructure score as the second most
problematic factor for doing business in the
Philippines, with the country ranking 91st ofthe 140 countries in the study. As the report
illustrates, the countrys poor infrastructure
holds back its total productivity, even given a
permissive macroeconomic environment and
other positive indicators. With infrastructure as
the second pillar of competitiveness, serious
actions must be taken in improving the quality
of the countrys infrastructure. The specic
diculties in the countrys infrastructure
can be seen in Table 2.
Compared to other Southeast Asian countries,
Philippines is still lagging behind, stuck behind
Singapore, Malaysia, Thailand and Indonesia
at the bottom of the so-called ASEAN 5.
Disappointingly, the country did not even show
a close margin among the higher four; Indo -
nesia, the next ranking neighbor placed ten
notches away at 37 (see Table 3). With this in
mind, the Philippines must identify
best practices in these four countries to be
able to know what it must follow for the
betterment of the country.
Singapore ranks to be one of the top
competitive countries, not just in Asia, but in
Table 2: Philippines Infrastructure Pillar Sub-index Ranking2015-2016
Source: The Global Competitiveness Report 2015-2016
OCCASIONAL PAPER MARCH 2016
05
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
6/13
the world ranking. It has an outstanding and stable
performance across all pillars. It takes pride in its
world-class infrastructure such as its roads, ports
and air transport facilities. Malaysia remains to be
highest among the developing Asian economies,
and has been achieving high tourist arrivals.
Thailand, which has been experiencing politica l
crisis, performs well on macroeconomics pillars. Like
the Philippines, there are barriers challenging market
competition, most especially those that restrict
foreign investment. Aside from these, Thailand faces
challenges such as political instability, excessive red
tape, pervasive corruption, security concerns and
high uncertainty on property rights. Indonesia has
prioritized infrastructure: Presidential Special Staer
for Economic Aairs and Development Prof.
Firmanzah, Ph.D. mentioned that infrastructure de-
velopment in the last ve years is the Governments
main priority to strengthen the countrys national
competitiveness.6 The accelerating infrastructure
development is supported by the Master Plan forAcceleration and Expansion of Indonesias Econo-
mic Development (MP3EI), according to Firmanzah.
With these assessments, the Philippines can learn a
lesson or two from each of the countries mentioned.
First, the country must focus its eorts on invest-
ing on world-class infrastructures, in order to be at
par with or at the least approach Singapores rank.
Second, it should nd out how Thailand manages to
obtain a high rank despite facing the same challeng-
es similar to the Philippines, especially in the aspect
of market competition. By doing so, the Philippines
may be able to combat these barriers and excel
in other pillars wherein Thailand stands out.
It has been said that the Philippines lacks competitiveness in the
global arena and has an unattractive investment climate. Investors
have been repeatedly aected by the unpredictable policy environ-
ment; government ineciency, and a poor regulatory quality and
ineective control of corruption in the Phil ippines. Transparency, a
level playing eld, and consistent govern
factors that foreign investors are right to
scheme. Returns on investment should b
importantly, the investment should be se
reprisals. Investors to PPP expect a well-
Table 3: Global Competitiveness Index Ranking 2015-2016 of Southeast Asian Econo
Source: The Global Competitiveness Report 2015-2016
Table 4: Global Competitiveness Index Ranking 2015-2016 of Southeast Asian Economies for the In
Source: The Global Competitiveness Report 2015-2016
OCCASIONAL PAPER FEBRUARY 2016
06
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
7/13
tor Cosette Canilao of the PPP Center, the process
of conceptualizing the PPP projects and reviewing
the qualied companies who can participate in the
bidding takes time. The concerned government
agencies play the bigger role of conceptualizing and
evaluating the projects. Although these government
agencies are guided by a timeline, these are merely
notional and can be adjusted. Thus, no direct
accountability can be attributed to the PPP Center.
For the implementing agencies, a major cause of
delay is the prolonged period of consultation bet-
ween the private sector and the concerned
government agency. There is uneven technical cap-
pacity within the implementing agencies, with many
government ocials not equipped with technical
training nor exposure to the nitty-gritty of infrastruc-
ture projects. As such, consultants are often hired to
provide an in-depth understanding of the complexi-
ties involved and a full assessment of the projects.
The Premium Bid (aka Concession Payment)
controversy in the case of CALAX
The controversial Cavite-Laguna expressway
(CALAX), which aims to connect Bacoor and Kawit
in Cavite and South Luzon Expressway areas, is a
P35.4 billion project under the Build-Operate-and-
Transfer structure. CALAX faced an issue on its bid-
ding done in 2014. Among the bidders were Team
Orion, the 50-50 joint venture of Ayala Corporation
Critics of the Aquino governments PPP Policy are
quick to point out that no capitalist will invest in
big-ticket projects in a relatively small market like
the Philippines without certain guarantees that will
ensure the protection and protability of his
investment. It is unlikely that investors will come in
with fewer incentives. More investors will come only
if given guarantees and protection such as guar-
anteed investment return, access to loans backed
by government guarantees, and in recent years,
protection from risks arising from unfavorable
court decisions that aect protability7
PPP Programs Choke Points
The majority of the delays occur during the feasibil-
ity study and prequalication stages. The tendering
stage would range anywhere between nine to twelve
months: Invitation to Bid (21 days); Response (45
days), Prequalication (60 days), Preparation of Bids
(120-150 days), Evaluation & Award (30-60 days).
Next comes contract negotiation and government
approvals and this takes three months. Then there is
nancial closing which takes anywhere from three to
12 months.8The target deadlines keep on moving
and moving for months, as seen in all projects.
The PPP Center coordinates this process, working
to ensure that timelines for proposals and
studies are met. According to then Executive Direc-
and Aboitiz Equity Ventu
structure Development C
ed conglomerate San M
The nancial proposal o
premium/concession pa
the other hand, the conc
was P20.105 billion. Op
ceed with the bid due to
In its defense, Optimal s
is valid until 29 Novemb
compliant with the bid re
with the provisions of th
the project as the highe
Rebidding of CALAX wa
NEDA Board chaired by
ident explained that fore
ence in premium bid of
government projects. W
Works and Highways as
it underwent a revampe
June 2015 after the gov
from a previous bidding
Board also approved a
billion, the same amoun
supposed winner of the
no longer participated in
Aside from Team Orions
ment towards the gover
OCCASIONAL PAPER MARCH 2016
07
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
8/13
investors have likewise expressed their sentiments
towards the governments blunders. Speaking on
behalf of local and foreign investors, Peter Angelo B.
Perfecto, Executive Director of the Makati
Business Club (MBC) previously pointed out that
the groups level of condence will erode if the
government approves a rebidding of the CALAX
project. Notwithstanding Aquinos approval of therebidding, Perfecto remains rm in his statement but
pointed out that there remains still a level of
condence that the government will roll out
more PPPs without such similar issues9
In the end, rebidding happened between San
Miguel Corporations Optimal Infrastructure
Development, Inc. and Metro Pacic Investments
Corporations MPCALA Holdings (MPIC). MPIC
won with the highest bid of P27.3 billion.
The Presidents decision to order the re-bidding
of said CALAX project instigated the public to reviewprevious bids for certain PPP awarded projects like
the Mactan-Cebu International Airport
Passenger Terminal Building and Automatic Fare
Collection System. Contracts were awarded to
bidders who submitted the highest present value of
proposed payments to government pursuant
to Section 4.2 (H) of the Revised Implementing
Rules and Regulations of BOT law, in lieu of the
lowest bid and most favorable terms for the
project, as set out in R.A. 7718.
In a statement issued by the PPP Center, Deputy
Executive Director, Ms. Sherry Ann N. Austria, shed
light on the nature of premium payments. The
PPP Center would like to point out that premium
payments for the CALAX Project, just like in any
other PPP contracts previously awarded, will not
be passed on to the public through increased user
charges as these charges are pre-determined prior
to the bidding process and will be subject to the
review and approval by the concerned regulatoryagency (e.g., Toll Regulatory Board). These premium
payments will go straight to the National Treasury
which can then be used to fund other equally
important projects of the national government.10
Further, it was noted that R.A. 7718 allows as
bid parameter the highest present value of
proposed payments to the government.
R.A. 7718 does not unequivocally provide as a bid
parameter the highest present value of proposed
payments to the government. Verily, Section 5 of
R.A. 7718 only provides that in case of build-
operate-and-transfer arrangement, the contractshall be awarded to the bidder who, having satised
the minimum nancial, technical, organizational and
legal standards has submitted the lowest bid and
most favorable terms for the project, based on the
present value of its proposed tolls, fees, rentals and
charges over a xed term. On the other hand, in the
case of build-and-transfer or build-lease-and-trans-
fer arrangement, the contract shall be awarded to
the lowest complying bidder based on the present
value of its proposed schedule of amortization
payments for the facility to be constructed accord-
ing to the prescribed minimum design and
performance standards, plans and specications.
Reference must be made
Revised BOT Law Implem
tions, which sets out the
evaluation of nancial co
i. Lowest proposed tol
the start of project ope
parametric tari adjustprescribed in the bid d
ii. Lowest present valu
to be provided for the
by the contract;
iii. Highest present valu
to Government, such a
lease/rental payments,
payments, and/or varia
percentage shares of r
period covered by the
iv. Any other appropriaas may be approved b
Except for item iii, the for
port from R.A. 7718, wh
that the contract should
complying bidder. On the
of highest present value
government was not con
If at all, the premium/s (to
ders, which represents th
proposed payments to g
vance payments or prep
OCCASIONAL PAPER MARCH 2016
08
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
9/13
Only Filipinos or corpothat are A
60% owned by Fare allowed to own lanPhilippines, but foreign
allowed to leafor 50 to 7
or its share of revenue, to the detriment of the
future users of said infrastructure.
As Henry Schumacher, Executive Vice President of the
European Chamber of Commerce of the Philippines
(ECCP), stated, It is also important to understand that
the higher the bidding goes, it only favors government
coers; Juan de la Cruz will later on have to pay more
for the utilization of CALAX.11 Business logic dictates
that proponents will seek to recover their investment for
the said project/s, which necessarily translates
to higher costs to the public. This arrangement
defeats the purpose of a PPP.
This view was supported by Senator Ralph Recto in
his statement on August 10, 2014,12 thus: If a public
infrastructure or basic service is the one being
auctioned o, logic dictates that the best lowest bid
should win it as it would translate to lower fees to be
paid by the public who will use it. The higher the bid,the higher the fees that the public will eventually
shoulder. It has a domino eect and the last tile will fall
on the people. Further, he stated that the govern-
ments main consideration in awarding contracts should
be what the public will pay at the minimum, which will
not be achieved if the government will get an advance
payment or a prepaid tax, by way of premium,
for a structure that has yet to be built.
In view of the foregoing, the Senate passed
Resolution No. 810 on August 6, 2014, which
resolution was introduced by Senator Recto, directing
the appropriate Senate Committee to conduct an inquiry, inaid of legislation, on the bidding process of PPP projects with
the end in view of ensuring that the Filipino will benet quality
public services at the least possible costs.
The 60/40 Rule Applied to Infrastructure Investments
Easing restrictions on foreign investments will give the
countrys PPP program a shot in the arm. Republic Act No.
7042 or Foreign Investments Act of 1991, the law that governs
the participation of foreign entities in economic and
commercial activities in the Philippines, states that
foreigners may hold interests in corand other entities in the Philippines
engaged in an activity that is reserv
citizens or entities that are wholly ow
citizens. The maximum amount of f
allowed in a company depends on
company is engaged in, which is un
investors. Only Filipinos or corporat
owned by Filipinos are allowed to o
but foreigners are allowed to lease
depending on the lands classicati
whether local or foreign, can only le
alienable public lands. There is no l
OCCASIONAL PAPER MARCH 2016
09
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
10/13
Image Credit: corporatelivewire.com
lands. The diculty lies when foreign investors try to tap the domestic market and work their way through
complicated bureaucratic procedures, local government corruption, only to nd out that they are notqualied to do business in the Philippines due to the foreign equity restriction. However, foreign
investors could still participate in the public bidding by partnering with a
Philippine national or domestic corporation, provided that. 13
at least sixty percent (60%) of the capital stock outstanding and entitled to vote is owned and held by
citizens of the Philippines; or a trustee of funds for pension or other employee retirement or separation
benets, where the trustee is a Philippine national and at least sixty (60%) of the fund will accrue to the
benet of the Philippine nationals: Provided, That where a corporation and its non-Filipino stockholders
own stocks in a Securities and Exchange Commission (SEC) registered enterprise, at least sixty percent
(60%) of the capital stocks outstanding and entitled to vote of both corporations must be owned and
held by citizens of the Philippines and at least sixty percent (60%) of the members of the Board of
Directors of both corporations must be citizens of the Philippines, in order that the
corporations shall be considered a Philippine national
Notwithstanding the foregoing options, Philippines is still not an attractive place for foreign investments,
whose capital is especially important for infrastructure investment. Big investments in infrastructure
developments are brought in by foreign investors, yet their ownership cannot go beyond 40% of the
equity and their participation in the management therefor is likewise subject to the same limitation. A
minority shareholder is often at risk of losing. Thus, without removal of the foreign equity limitations,
at least in the area of infrastrusture development, the condence level of foreign investors
in the country will not improve, which is to the Philippines detriment.
OCCASIONAL PAPER MARCH 2016
10
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
11/13
Recommendations and Conclusion
1. President Aquino can hasten the awarding of
more PPP projects, focus on monitoring already
existing PPP projects, or do both. Improved
transportation and infrastructure are needed to fully
harness the countrys economic potential. These
projects are also benecial in terms ofgenerating additional employment, investments and
more foreign arrivals. The failure of the
governments agship program thrust to take
o has been a source of frustration since
its launch in November 2010.
2. For the progress of the program to accelerate, the
government should be rm on the observance of its
processes and timelines. Stakeholders such
as the bidders, among others, should also do its
part in strictly observing the process. There should
be a strong mechanism for collaboration and
consultation between the public and privatesectors in order to facilitate project development
with minimum legal impediments.
3. The success of a countrys PPP program
depends on the continuity of a government policy,
a perception of minimal political and economic risk
that is instilled in the minds of the investors and
stable macroeconomic management. As reality
checks were made since its ambitious launch, the
PPP Center is still optimistic that at least 80% of the
PPP projects in the pipeline will be awarded before the term of President Aquino e
4. The proposed amendments to the BOT Law, which is one of the priority bills of
would have institutionalized the supposed reforms initiated by his administration a
ensure that said reforms would be continued by the next administration.
In particular, House Bill No. 6331, the House of Representatives version of the pro
to the BOT Law, features provisions attuned to international standards, where priv
truly encouraged and the partnership valued. Among the notable clauses of HB 63
a) Issuance of Administrative Franchise, License or Permit. HB 6331 provides f
grant of administrative franchise, local or national permits, or any other requirem
implementation of the PPP project once the contract is duly executed;
b) Projects of National Signicance. Upon classication by the President of ene
transit, water, sewerage, and such other projects, HB 6331 proposes that said
imbued with national signicance shall be exempt from the real property taxes
Government Code, and from all local taxes and fees. The project shall also be
issued the necessary business permits, including renewals of such permits; an
c) Recovery of Investment. HB 6331 likewise mandates that PPP contracts inc
the recovery of the proponents investment by collecting of tolls, fees, rentals o
commercial development, or receiving viability gap funding (VGF), that is nanc
government to make user fees aordable, or direct payment from government,
The above cited provisions reect modern governance where there is acknowledg
through a robust partnership with the private sector, the government can
better deliver the services our country and our people need.*
* House Bill No. 6331, An Act Institutionalizing and Strengthening Public-Private Partnerships, and Appropriating Fuas part of Committee Report No. 947, submitted by the Committee on Public Works and Highways, the Committeetions, and the Committee on Ways and Means on December 14, 2015, Sections 13, 20, 28 (c).
OCCASIONAL PAPER MARCH 2016
11
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
12/13
Endnotes:
1 Global Source Partners. (2011). A Bet on PPP. Retrieved fromhttp://www.globalsourcepartners.com
2 PPP Center. (2016). Pipeline of Projects. Retrieved from http://ppp.gov.ph/?page_id=26075
3 PPP Center. (2016). Pipeline of Projects. Retrieved from http://ppp.gov.ph/?page_id=26075
4 World Economic Forum. (September 2014). The Global Com-petitiveness Report 2014-2015
5 World Economic Forum. (September 2014). The Global Com-petitiveness Report 2014-2015
6 Sekretariat Kabinet Republika Indonesia. (September 21,2014). Increase in Indonesias Global Competitiveness Index ReectsImprovements in Its Economic Performance. Retrieved from http://setkab.go.id/en/increase-in-indonesias-global-competitiveness-in -dex-reects-improvements-in-its-economic-performance/
7 IBON. (November 11, 2010). PPP: More public debt, less govtresponsibility. Retrieved from http://ibon.org/2010/11/ppp-more-pub-lic-debt-less-govt-responsibility/
8 Chanco, B. (Feb. 28, 2011). Philippine Star. Stale bureaucraticthinking delays PPP Retrieved from http://www.philstar.com/busi-ness/661176/stale-bureaucratic-thinking-delays-ppp
9
Business Mirror. (February 17, 2015). Calax should be soleexception. Retrieved from http://www.businessmirror.com.ph/calax-should-be-sole-exception/
10 PPP Center. (Septembto Calax commentary. Retrienews=ppp-centers-reaction-to
11 Amojelar, Darwin. (NoveCommerce of the PhilippinesCavite-Laguna Expressway prcom/articles-page.php?categ
12 Senate of the Philippinebids could lead to higher usersenate.gov.ph/press_release/2
13 Republic Act No. 7042 F
5. The best lowest bid should always win as it would
translate to lower fees to be paid by the public
who will use it. The higher the bid, the higher the
fees that the public will eventually shoulder.
Inevitably, it will be the public who will suer from
such arrangement. The governments main
consideration in awarding contracts should be whatthe public will pay at the minimum, which will not be
achieved if the government will get an advance
payment, by way of premium, for a structure that
has yet to be built. Not only is the public required
to pay a fee for a basic service that a government
should have rendered for free, but the public will be
required to pay a higher fee in order to recompense
the bidder for its premium payment to the govern-
ment. Government should see that PPP is not
crafted for the purpose of raising revenues
but rather to be able to provide public services that
the government cannot aord.
6. Finally, more than being just a mere coordina-
ting agency, the PPP Center should be given more
leeway to act independently on proposals, whether
for solicited or unsolicited projects. The PPP Center
should be able to independently address the whole
process of the PPP scheme. For that purpose,
the PPP Center becomes a one-stop shop for
infrastructure developments which would include
the conceptualization, evaluation and approval ofprojects. This concept would eliminate or at the very
least, minimize the bureaucracy problem.
PPP projects should be a reection of the
Philippines on how modernized and integrated our
facilities will be, a link for an innovative and
competitive environment for the future. Certainly, the
PPP scheme has yet to reach its fullest potential.
OCCASIONAL PAPER MARCH 2016
12
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
9 3
-
7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure
13/13
C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.
is an independent international and strategic researchorganization with the principal goal of addressing theissues affecting the Philippines and East Asia
Stratbases Albert Del Rosario Institute
9F 6780 Ayala Avenue, Makati CityPhilippines 1200
V 8921751F 8921754
www.stratbase.com.ph
ABOUT
Victor Andres Dindo C. Manhitis the CEO and Managing Director of the Stratbase Group andPresident of the ADR Institute. He specializes in Strategic PublicManagement, Legislative Research and Governance Reforms. Hisresearch interest and eld of specialization had led him to pursueactive involvement in legislation, bureaucratic workand civil society advocacy.
Maria Claudette L. Guevarais the Chief of Staff of theStratbase Group and is a Research Analyst at the ADR Institute.
9.3VOLUME