delay and dissatisfaction in the aquino administration's ppp program: recommendations for future...

Upload: stratbase-adr-institute

Post on 02-Mar-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    1/13

    MAR

    DELAY AND DISSATISFACTION

    IN THEAQUINO ADMINISTRATIONSPPP PROGRAM:

    RECOMMENDATIONSFOR FUTUREPARTNERSHIPS ININFRASTRUCTURE

    9.3VOLUME

    PAPEROCCASIONAL

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    2/13

    The Public Private Partnership (PPP) program, claimed as a

    pillar of this administrations economic and infrastructure

    development plan, is under greater pressure this 2016

    as President Aquino has only three months left in oce. The

    emphasis President Aquino placed on the importance of

    infrastructure development back in 2010 should have been

    a good measure of the administrations consistent

    support for the PPP program.

    However, delay in the progress of the PPP scheme has been

    evident since its launch in 2010. The minimal number of PPPprojects that have been awarded since Aquino assumed of-

    ce12 out of the 53 projects in the pipeline is

    dissatisfying. Moreover, the President must realize that the

    number of awarded PPP projects should not be the sole

    basis of measuring success; the completion and successful

    operation of the infrastructure should also be made the basis.

    Nonetheless, the Aquino administration can use the remaining

    time in oce to fast track the PPP scheme without

    sacricing transparency and legitimacy in the process.

    This paper aims to identify the reasons why the PPP program

    could have been a good avenue to improve our countrys

    infrastructure industry but has thus far failed to fully deliver.The rst part tackles the Philippines overall competitiveness

    and the importance of infrastructure in this regard,

    * The views and opinions expressed in this Paper are those of the author and do not necessa

    comparing Philippine performance vis--vis neighboring

    Southeast Asian countries. It then turns to the chokepoints in the

    PPP scheme: the insucient technical capacity within some

    government agencies, the under-empowered PPP center,

    an improperly implemented bidding process,

    and barriers to foreign capital investment.

    In concluding, the paper provides recommendations to be

    considered for the next administration. In the time remaining, the

    Aquino administration should focus on maintaining the

    transparency and legitimacy of the PPP process as it seeks tofast-track the awarding of projects. Doing so in this manner will

    help it leave a legacy of enduring public-private partnerships.

    DELAY AND DISSATISFACTION

    IN THEAQUINO ADMINISTRATIONS

    PPP PROGRAM:RECOMMENDATIONSFOR FUTURE PARTNERSHIPS

    IN INFRASTRUCTURE

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

    OCCASIONAL PAPER MARCH 2016

    02

    PPP PROGRAM

    could have been a good avenue to improve our country's infrastructure industry buthas thus far failed to fully deliver. The Aquino administration can use the

    remaining time in office to fast track the PPP scheme withoutsacrificing transparency and legitimacy in the process.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    3/13

    The Public-Private Partnership Program

    PPP was rst introduced in the Philippines in 1990,

    through the passage of Republic Act (RA) No. 6957,

    known as the Build, Operate and Transfer Law (BOT

    Law), signed by then President Corazon Aquino. The

    BOT Law authorizes private entities to construct, nance,

    operate and maintain a public infrastructure facility.

    Four years later, RA 6957 was amended by RA 7718 to

    provide nancial incentives and to minimize government

    regulations so that the private sector will be more

    encouraged to participate in the PPP program. RA 7718

    governs the procurement of infrastructure or development

    projects by the private sector. Under this law,

    infrastructure or development projects may be

    undertaken through any of the contractual arrangements

    provided* therein for which pertinent incentives will be

    given to stimulate private resources for the purpose of

    nancing the construction, operation and maintenance of

    infrastructure and development projects normally

    undertaken by the government.

    Recognizing the importance of infrastructure in building

    the foundations of a strong economy, past administra-

    tions consistently focused on improving infrastructure,

    certain that investments in this area would bring benets

    across sectors and create more opportunities for the

    fast-growing population. Conversely, poor infrastructure

    is widely accepted to be a signicant barrier to

    trade and discourages investment.

    Projects through PPP are expected to boost the countrys

    growth rate to 7-8%.1 This means intensied infrastruc-

    ture spending, increased private investment and

    eventually higher tourism receipts, which will only

    be possible by increasing investor condence in the

    countrys ability to nance and complete these PPP

    projects. The resurgence of the PPP program in

    this Aquino administration shows its commitment to

    accelerating public infrastructure development that

    would likely attract more foreign investment

    and boost tourism, thereby increasing

    job opportunities for Filipinos.

    In 2011, Stratbase Research Institute published

    its analysis on PPP through its Occasional Paper

    entitled The PPP Challenge. The paper sought to

    establish the importance of PPP to the countrys

    economic growth for the succeeding years and,

    further, provided recommendations on how PPP

    can be properly implemented by the Aquino

    administration so as to make it an eective

    tool in national development.

    Yet, the promise of growth via PPP has been

    weakened by the vulnerability of the scheme to

    politics. Had the Aquino administration maximized

    the full potential of the PPP scheme, the Philippines

    would have reaped the benets of a growing

    economy and a high rate of inclusive growth.

    The underlying question arises as to how the

    slow progress of the PPP program of the

    Philippines has aected its competitiveness.

    Big ticket projects that investors h

    watching out to fund under the PP

    been slow to materialize. To date,

    three projects in the PPP pipeline

    projects have been awarded:

    (1) Daang Hari-South Luzon E

    Road;

    (2) First phase of the PPP for

    ture Project;

    (3) Ninoy Aquino International

    way;

    (4) Second phase of the PPP

    structure Project;

    (5) Modernization of the Philip

    Center;

    (6) Automatic Fare Collection

    (7) Mactan-Cebu Internationa

    (8) LRT Line 1 South Extensio

    (9) Integrated Transport Syste

    Terminal Project;

    (10) Cavite-Laguna Expressw

    (11) Integrated Transport Sys

    Terminal Project; and

    (12) Bulacan Bulk Water Supp

    Out of these twelve projects, only

    Hari-South Luzon Expressway Lin

    called the Muntinlupa Cavite Expr

    (MCX), is operational.2

    *Section 1 of R.A. 7718 enumerated/dened the following contractual arrangements: 1. Build-operate-and-transfer; 2. Buildand-operate; 4. Build-lease-and-transfer; 5. Build-transfer-and-operate; 6. Contract-add-and-operate; 7. Develop-operate-aoperate-and-transfer; 9. Rehabilitate-own-and-operate; and 10. Such other variations as may be approved by the President of

    OCCASIONAL PAPER MARCH 2016

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

    03

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    4/13

    Table 1. Global Competitiveness report(2015-2016)

    Source: the Global Competitiveness report 2015-2016

    As of February 2016, 10 PPP projects are up for

    bidding:

    (1) Operation and Maintenance of LRT Line 2;

    (2) Regional Prison Facilities;

    (3) Laguna Lakeshore Expressway Dike Project;

    (4) Davao Sasa Port Modernization Project;

    (5) PPP Airport Operations and Maintenance of

    the Bacolod (Silay) Airport & Iloilo Airport (bundle

    1);

    (6) PPP Airport Operations and Maintenance of

    the New Bohol (Panglao) Airport, Laguindingan

    Airport and Davao Airport (bundle 2);

    (7) Road Transport IT Infrastructure Project

    (Phase II);

    (8) North-South Railway Project (South Line);

    (9) Civil Registry System-Information Technology

    Project (Phase II); and

    (10) LRT Line 6 Project3

    Infrastructure Limits PhilippineCompetitiveness

    The World Economic Forum (WEF)s Global

    Competitiveness Report denes competitiveness

    as the set of institutions, policies, and factors that

    determine the level of productivity of a country. The

    level of productivity, in turn, sets the level of

    prosperity that can be reached by an economy. The

    productivity level also determines the rates of return

    obtained by investments in an economy, which in

    turn are the fundamental drivers of its growth rates.

    In other words, a more competitive economy is

    one that is likely to grow faster over time. 4

    Infrastructure is one of four pillars in the Global

    Competitiveness Reports index (GCI), alongside

    institutions, macroeconomic environment, and

    health and primary education. In elevating

    infrastructure as a pillar, the Global Competitiveness

    Report nds that [a] well-developed infrastructure

    system reduces the eect of distance between

    regions, integrating the national market and

    connecting it at low cost to markets in other

    countries and regions. In addition, the quality and

    extensiveness of infrastructure networks

    signicantly impact economic growth and reduce

    income inequalities and poverty in a variety of ways.

    A well-developed transport and communications

    infrastructure network is a prerequisite for the

    access of less-developed communities to core

    economic activities and services.5

    Overall, the Philippines has improved its

    competitiveness: rising ve notches on the Reports

    2015-2016 index to 47th of 140 countries. The

    countrys latest performance followed a 7-notch

    jump to 52nd in the 2014-2015 report and a

    6-notch jump to the 59th spot in 2013-2014. The

    Philippines has jumped 33 places in total under the

    Aquino administration, showing the largest gain

    among all other countries in the study since 2010.

    The Philippines got the highest ranking in terms of

    macroeconomic environment followed by market

    size and business sophistication (see Table 1).

    OCCASIONAL PAPER MARCH 2016

    04

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    5/13

    The same report shows, however, that the

    country lags behind in terms of infrastructure,

    labor market eciency and goods market

    eciency. The report lists the Philippines

    infrastructure score as the second most

    problematic factor for doing business in the

    Philippines, with the country ranking 91st ofthe 140 countries in the study. As the report

    illustrates, the countrys poor infrastructure

    holds back its total productivity, even given a

    permissive macroeconomic environment and

    other positive indicators. With infrastructure as

    the second pillar of competitiveness, serious

    actions must be taken in improving the quality

    of the countrys infrastructure. The specic

    diculties in the countrys infrastructure

    can be seen in Table 2.

    Compared to other Southeast Asian countries,

    Philippines is still lagging behind, stuck behind

    Singapore, Malaysia, Thailand and Indonesia

    at the bottom of the so-called ASEAN 5.

    Disappointingly, the country did not even show

    a close margin among the higher four; Indo -

    nesia, the next ranking neighbor placed ten

    notches away at 37 (see Table 3). With this in

    mind, the Philippines must identify

    best practices in these four countries to be

    able to know what it must follow for the

    betterment of the country.

    Singapore ranks to be one of the top

    competitive countries, not just in Asia, but in

    Table 2: Philippines Infrastructure Pillar Sub-index Ranking2015-2016

    Source: The Global Competitiveness Report 2015-2016

    OCCASIONAL PAPER MARCH 2016

    05

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    6/13

    the world ranking. It has an outstanding and stable

    performance across all pillars. It takes pride in its

    world-class infrastructure such as its roads, ports

    and air transport facilities. Malaysia remains to be

    highest among the developing Asian economies,

    and has been achieving high tourist arrivals.

    Thailand, which has been experiencing politica l

    crisis, performs well on macroeconomics pillars. Like

    the Philippines, there are barriers challenging market

    competition, most especially those that restrict

    foreign investment. Aside from these, Thailand faces

    challenges such as political instability, excessive red

    tape, pervasive corruption, security concerns and

    high uncertainty on property rights. Indonesia has

    prioritized infrastructure: Presidential Special Staer

    for Economic Aairs and Development Prof.

    Firmanzah, Ph.D. mentioned that infrastructure de-

    velopment in the last ve years is the Governments

    main priority to strengthen the countrys national

    competitiveness.6 The accelerating infrastructure

    development is supported by the Master Plan forAcceleration and Expansion of Indonesias Econo-

    mic Development (MP3EI), according to Firmanzah.

    With these assessments, the Philippines can learn a

    lesson or two from each of the countries mentioned.

    First, the country must focus its eorts on invest-

    ing on world-class infrastructures, in order to be at

    par with or at the least approach Singapores rank.

    Second, it should nd out how Thailand manages to

    obtain a high rank despite facing the same challeng-

    es similar to the Philippines, especially in the aspect

    of market competition. By doing so, the Philippines

    may be able to combat these barriers and excel

    in other pillars wherein Thailand stands out.

    It has been said that the Philippines lacks competitiveness in the

    global arena and has an unattractive investment climate. Investors

    have been repeatedly aected by the unpredictable policy environ-

    ment; government ineciency, and a poor regulatory quality and

    ineective control of corruption in the Phil ippines. Transparency, a

    level playing eld, and consistent govern

    factors that foreign investors are right to

    scheme. Returns on investment should b

    importantly, the investment should be se

    reprisals. Investors to PPP expect a well-

    Table 3: Global Competitiveness Index Ranking 2015-2016 of Southeast Asian Econo

    Source: The Global Competitiveness Report 2015-2016

    Table 4: Global Competitiveness Index Ranking 2015-2016 of Southeast Asian Economies for the In

    Source: The Global Competitiveness Report 2015-2016

    OCCASIONAL PAPER FEBRUARY 2016

    06

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    7/13

    tor Cosette Canilao of the PPP Center, the process

    of conceptualizing the PPP projects and reviewing

    the qualied companies who can participate in the

    bidding takes time. The concerned government

    agencies play the bigger role of conceptualizing and

    evaluating the projects. Although these government

    agencies are guided by a timeline, these are merely

    notional and can be adjusted. Thus, no direct

    accountability can be attributed to the PPP Center.

    For the implementing agencies, a major cause of

    delay is the prolonged period of consultation bet-

    ween the private sector and the concerned

    government agency. There is uneven technical cap-

    pacity within the implementing agencies, with many

    government ocials not equipped with technical

    training nor exposure to the nitty-gritty of infrastruc-

    ture projects. As such, consultants are often hired to

    provide an in-depth understanding of the complexi-

    ties involved and a full assessment of the projects.

    The Premium Bid (aka Concession Payment)

    controversy in the case of CALAX

    The controversial Cavite-Laguna expressway

    (CALAX), which aims to connect Bacoor and Kawit

    in Cavite and South Luzon Expressway areas, is a

    P35.4 billion project under the Build-Operate-and-

    Transfer structure. CALAX faced an issue on its bid-

    ding done in 2014. Among the bidders were Team

    Orion, the 50-50 joint venture of Ayala Corporation

    Critics of the Aquino governments PPP Policy are

    quick to point out that no capitalist will invest in

    big-ticket projects in a relatively small market like

    the Philippines without certain guarantees that will

    ensure the protection and protability of his

    investment. It is unlikely that investors will come in

    with fewer incentives. More investors will come only

    if given guarantees and protection such as guar-

    anteed investment return, access to loans backed

    by government guarantees, and in recent years,

    protection from risks arising from unfavorable

    court decisions that aect protability7

    PPP Programs Choke Points

    The majority of the delays occur during the feasibil-

    ity study and prequalication stages. The tendering

    stage would range anywhere between nine to twelve

    months: Invitation to Bid (21 days); Response (45

    days), Prequalication (60 days), Preparation of Bids

    (120-150 days), Evaluation & Award (30-60 days).

    Next comes contract negotiation and government

    approvals and this takes three months. Then there is

    nancial closing which takes anywhere from three to

    12 months.8The target deadlines keep on moving

    and moving for months, as seen in all projects.

    The PPP Center coordinates this process, working

    to ensure that timelines for proposals and

    studies are met. According to then Executive Direc-

    and Aboitiz Equity Ventu

    structure Development C

    ed conglomerate San M

    The nancial proposal o

    premium/concession pa

    the other hand, the conc

    was P20.105 billion. Op

    ceed with the bid due to

    In its defense, Optimal s

    is valid until 29 Novemb

    compliant with the bid re

    with the provisions of th

    the project as the highe

    Rebidding of CALAX wa

    NEDA Board chaired by

    ident explained that fore

    ence in premium bid of

    government projects. W

    Works and Highways as

    it underwent a revampe

    June 2015 after the gov

    from a previous bidding

    Board also approved a

    billion, the same amoun

    supposed winner of the

    no longer participated in

    Aside from Team Orions

    ment towards the gover

    OCCASIONAL PAPER MARCH 2016

    07

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    8/13

    investors have likewise expressed their sentiments

    towards the governments blunders. Speaking on

    behalf of local and foreign investors, Peter Angelo B.

    Perfecto, Executive Director of the Makati

    Business Club (MBC) previously pointed out that

    the groups level of condence will erode if the

    government approves a rebidding of the CALAX

    project. Notwithstanding Aquinos approval of therebidding, Perfecto remains rm in his statement but

    pointed out that there remains still a level of

    condence that the government will roll out

    more PPPs without such similar issues9

    In the end, rebidding happened between San

    Miguel Corporations Optimal Infrastructure

    Development, Inc. and Metro Pacic Investments

    Corporations MPCALA Holdings (MPIC). MPIC

    won with the highest bid of P27.3 billion.

    The Presidents decision to order the re-bidding

    of said CALAX project instigated the public to reviewprevious bids for certain PPP awarded projects like

    the Mactan-Cebu International Airport

    Passenger Terminal Building and Automatic Fare

    Collection System. Contracts were awarded to

    bidders who submitted the highest present value of

    proposed payments to government pursuant

    to Section 4.2 (H) of the Revised Implementing

    Rules and Regulations of BOT law, in lieu of the

    lowest bid and most favorable terms for the

    project, as set out in R.A. 7718.

    In a statement issued by the PPP Center, Deputy

    Executive Director, Ms. Sherry Ann N. Austria, shed

    light on the nature of premium payments. The

    PPP Center would like to point out that premium

    payments for the CALAX Project, just like in any

    other PPP contracts previously awarded, will not

    be passed on to the public through increased user

    charges as these charges are pre-determined prior

    to the bidding process and will be subject to the

    review and approval by the concerned regulatoryagency (e.g., Toll Regulatory Board). These premium

    payments will go straight to the National Treasury

    which can then be used to fund other equally

    important projects of the national government.10

    Further, it was noted that R.A. 7718 allows as

    bid parameter the highest present value of

    proposed payments to the government.

    R.A. 7718 does not unequivocally provide as a bid

    parameter the highest present value of proposed

    payments to the government. Verily, Section 5 of

    R.A. 7718 only provides that in case of build-

    operate-and-transfer arrangement, the contractshall be awarded to the bidder who, having satised

    the minimum nancial, technical, organizational and

    legal standards has submitted the lowest bid and

    most favorable terms for the project, based on the

    present value of its proposed tolls, fees, rentals and

    charges over a xed term. On the other hand, in the

    case of build-and-transfer or build-lease-and-trans-

    fer arrangement, the contract shall be awarded to

    the lowest complying bidder based on the present

    value of its proposed schedule of amortization

    payments for the facility to be constructed accord-

    ing to the prescribed minimum design and

    performance standards, plans and specications.

    Reference must be made

    Revised BOT Law Implem

    tions, which sets out the

    evaluation of nancial co

    i. Lowest proposed tol

    the start of project ope

    parametric tari adjustprescribed in the bid d

    ii. Lowest present valu

    to be provided for the

    by the contract;

    iii. Highest present valu

    to Government, such a

    lease/rental payments,

    payments, and/or varia

    percentage shares of r

    period covered by the

    iv. Any other appropriaas may be approved b

    Except for item iii, the for

    port from R.A. 7718, wh

    that the contract should

    complying bidder. On the

    of highest present value

    government was not con

    If at all, the premium/s (to

    ders, which represents th

    proposed payments to g

    vance payments or prep

    OCCASIONAL PAPER MARCH 2016

    08

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    9/13

    Only Filipinos or corpothat are A

    60% owned by Fare allowed to own lanPhilippines, but foreign

    allowed to leafor 50 to 7

    or its share of revenue, to the detriment of the

    future users of said infrastructure.

    As Henry Schumacher, Executive Vice President of the

    European Chamber of Commerce of the Philippines

    (ECCP), stated, It is also important to understand that

    the higher the bidding goes, it only favors government

    coers; Juan de la Cruz will later on have to pay more

    for the utilization of CALAX.11 Business logic dictates

    that proponents will seek to recover their investment for

    the said project/s, which necessarily translates

    to higher costs to the public. This arrangement

    defeats the purpose of a PPP.

    This view was supported by Senator Ralph Recto in

    his statement on August 10, 2014,12 thus: If a public

    infrastructure or basic service is the one being

    auctioned o, logic dictates that the best lowest bid

    should win it as it would translate to lower fees to be

    paid by the public who will use it. The higher the bid,the higher the fees that the public will eventually

    shoulder. It has a domino eect and the last tile will fall

    on the people. Further, he stated that the govern-

    ments main consideration in awarding contracts should

    be what the public will pay at the minimum, which will

    not be achieved if the government will get an advance

    payment or a prepaid tax, by way of premium,

    for a structure that has yet to be built.

    In view of the foregoing, the Senate passed

    Resolution No. 810 on August 6, 2014, which

    resolution was introduced by Senator Recto, directing

    the appropriate Senate Committee to conduct an inquiry, inaid of legislation, on the bidding process of PPP projects with

    the end in view of ensuring that the Filipino will benet quality

    public services at the least possible costs.

    The 60/40 Rule Applied to Infrastructure Investments

    Easing restrictions on foreign investments will give the

    countrys PPP program a shot in the arm. Republic Act No.

    7042 or Foreign Investments Act of 1991, the law that governs

    the participation of foreign entities in economic and

    commercial activities in the Philippines, states that

    foreigners may hold interests in corand other entities in the Philippines

    engaged in an activity that is reserv

    citizens or entities that are wholly ow

    citizens. The maximum amount of f

    allowed in a company depends on

    company is engaged in, which is un

    investors. Only Filipinos or corporat

    owned by Filipinos are allowed to o

    but foreigners are allowed to lease

    depending on the lands classicati

    whether local or foreign, can only le

    alienable public lands. There is no l

    OCCASIONAL PAPER MARCH 2016

    09

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    10/13

    Image Credit: corporatelivewire.com

    lands. The diculty lies when foreign investors try to tap the domestic market and work their way through

    complicated bureaucratic procedures, local government corruption, only to nd out that they are notqualied to do business in the Philippines due to the foreign equity restriction. However, foreign

    investors could still participate in the public bidding by partnering with a

    Philippine national or domestic corporation, provided that. 13

    at least sixty percent (60%) of the capital stock outstanding and entitled to vote is owned and held by

    citizens of the Philippines; or a trustee of funds for pension or other employee retirement or separation

    benets, where the trustee is a Philippine national and at least sixty (60%) of the fund will accrue to the

    benet of the Philippine nationals: Provided, That where a corporation and its non-Filipino stockholders

    own stocks in a Securities and Exchange Commission (SEC) registered enterprise, at least sixty percent

    (60%) of the capital stocks outstanding and entitled to vote of both corporations must be owned and

    held by citizens of the Philippines and at least sixty percent (60%) of the members of the Board of

    Directors of both corporations must be citizens of the Philippines, in order that the

    corporations shall be considered a Philippine national

    Notwithstanding the foregoing options, Philippines is still not an attractive place for foreign investments,

    whose capital is especially important for infrastructure investment. Big investments in infrastructure

    developments are brought in by foreign investors, yet their ownership cannot go beyond 40% of the

    equity and their participation in the management therefor is likewise subject to the same limitation. A

    minority shareholder is often at risk of losing. Thus, without removal of the foreign equity limitations,

    at least in the area of infrastrusture development, the condence level of foreign investors

    in the country will not improve, which is to the Philippines detriment.

    OCCASIONAL PAPER MARCH 2016

    10

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    11/13

    Recommendations and Conclusion

    1. President Aquino can hasten the awarding of

    more PPP projects, focus on monitoring already

    existing PPP projects, or do both. Improved

    transportation and infrastructure are needed to fully

    harness the countrys economic potential. These

    projects are also benecial in terms ofgenerating additional employment, investments and

    more foreign arrivals. The failure of the

    governments agship program thrust to take

    o has been a source of frustration since

    its launch in November 2010.

    2. For the progress of the program to accelerate, the

    government should be rm on the observance of its

    processes and timelines. Stakeholders such

    as the bidders, among others, should also do its

    part in strictly observing the process. There should

    be a strong mechanism for collaboration and

    consultation between the public and privatesectors in order to facilitate project development

    with minimum legal impediments.

    3. The success of a countrys PPP program

    depends on the continuity of a government policy,

    a perception of minimal political and economic risk

    that is instilled in the minds of the investors and

    stable macroeconomic management. As reality

    checks were made since its ambitious launch, the

    PPP Center is still optimistic that at least 80% of the

    PPP projects in the pipeline will be awarded before the term of President Aquino e

    4. The proposed amendments to the BOT Law, which is one of the priority bills of

    would have institutionalized the supposed reforms initiated by his administration a

    ensure that said reforms would be continued by the next administration.

    In particular, House Bill No. 6331, the House of Representatives version of the pro

    to the BOT Law, features provisions attuned to international standards, where priv

    truly encouraged and the partnership valued. Among the notable clauses of HB 63

    a) Issuance of Administrative Franchise, License or Permit. HB 6331 provides f

    grant of administrative franchise, local or national permits, or any other requirem

    implementation of the PPP project once the contract is duly executed;

    b) Projects of National Signicance. Upon classication by the President of ene

    transit, water, sewerage, and such other projects, HB 6331 proposes that said

    imbued with national signicance shall be exempt from the real property taxes

    Government Code, and from all local taxes and fees. The project shall also be

    issued the necessary business permits, including renewals of such permits; an

    c) Recovery of Investment. HB 6331 likewise mandates that PPP contracts inc

    the recovery of the proponents investment by collecting of tolls, fees, rentals o

    commercial development, or receiving viability gap funding (VGF), that is nanc

    government to make user fees aordable, or direct payment from government,

    The above cited provisions reect modern governance where there is acknowledg

    through a robust partnership with the private sector, the government can

    better deliver the services our country and our people need.*

    * House Bill No. 6331, An Act Institutionalizing and Strengthening Public-Private Partnerships, and Appropriating Fuas part of Committee Report No. 947, submitted by the Committee on Public Works and Highways, the Committeetions, and the Committee on Ways and Means on December 14, 2015, Sections 13, 20, 28 (c).

    OCCASIONAL PAPER MARCH 2016

    11

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    12/13

    Endnotes:

    1 Global Source Partners. (2011). A Bet on PPP. Retrieved fromhttp://www.globalsourcepartners.com

    2 PPP Center. (2016). Pipeline of Projects. Retrieved from http://ppp.gov.ph/?page_id=26075

    3 PPP Center. (2016). Pipeline of Projects. Retrieved from http://ppp.gov.ph/?page_id=26075

    4 World Economic Forum. (September 2014). The Global Com-petitiveness Report 2014-2015

    5 World Economic Forum. (September 2014). The Global Com-petitiveness Report 2014-2015

    6 Sekretariat Kabinet Republika Indonesia. (September 21,2014). Increase in Indonesias Global Competitiveness Index ReectsImprovements in Its Economic Performance. Retrieved from http://setkab.go.id/en/increase-in-indonesias-global-competitiveness-in -dex-reects-improvements-in-its-economic-performance/

    7 IBON. (November 11, 2010). PPP: More public debt, less govtresponsibility. Retrieved from http://ibon.org/2010/11/ppp-more-pub-lic-debt-less-govt-responsibility/

    8 Chanco, B. (Feb. 28, 2011). Philippine Star. Stale bureaucraticthinking delays PPP Retrieved from http://www.philstar.com/busi-ness/661176/stale-bureaucratic-thinking-delays-ppp

    9

    Business Mirror. (February 17, 2015). Calax should be soleexception. Retrieved from http://www.businessmirror.com.ph/calax-should-be-sole-exception/

    10 PPP Center. (Septembto Calax commentary. Retrienews=ppp-centers-reaction-to

    11 Amojelar, Darwin. (NoveCommerce of the PhilippinesCavite-Laguna Expressway prcom/articles-page.php?categ

    12 Senate of the Philippinebids could lead to higher usersenate.gov.ph/press_release/2

    13 Republic Act No. 7042 F

    5. The best lowest bid should always win as it would

    translate to lower fees to be paid by the public

    who will use it. The higher the bid, the higher the

    fees that the public will eventually shoulder.

    Inevitably, it will be the public who will suer from

    such arrangement. The governments main

    consideration in awarding contracts should be whatthe public will pay at the minimum, which will not be

    achieved if the government will get an advance

    payment, by way of premium, for a structure that

    has yet to be built. Not only is the public required

    to pay a fee for a basic service that a government

    should have rendered for free, but the public will be

    required to pay a higher fee in order to recompense

    the bidder for its premium payment to the govern-

    ment. Government should see that PPP is not

    crafted for the purpose of raising revenues

    but rather to be able to provide public services that

    the government cannot aord.

    6. Finally, more than being just a mere coordina-

    ting agency, the PPP Center should be given more

    leeway to act independently on proposals, whether

    for solicited or unsolicited projects. The PPP Center

    should be able to independently address the whole

    process of the PPP scheme. For that purpose,

    the PPP Center becomes a one-stop shop for

    infrastructure developments which would include

    the conceptualization, evaluation and approval ofprojects. This concept would eliminate or at the very

    least, minimize the bureaucracy problem.

    PPP projects should be a reection of the

    Philippines on how modernized and integrated our

    facilities will be, a link for an innovative and

    competitive environment for the future. Certainly, the

    PPP scheme has yet to reach its fullest potential.

    OCCASIONAL PAPER MARCH 2016

    12

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

    9 3

  • 7/26/2019 Delay and Dissatisfaction in the Aquino Administration's PPP Program: Recommendations for Future Partnerships in Infrastructure

    13/13

    C 2016ADRiNSTITUTEfor Strategic and International Studies. All rights reserved.

    is an independent international and strategic researchorganization with the principal goal of addressing theissues affecting the Philippines and East Asia

    Stratbases Albert Del Rosario Institute

    9F 6780 Ayala Avenue, Makati CityPhilippines 1200

    V 8921751F 8921754

    www.stratbase.com.ph

    ABOUT

    Victor Andres Dindo C. Manhitis the CEO and Managing Director of the Stratbase Group andPresident of the ADR Institute. He specializes in Strategic PublicManagement, Legislative Research and Governance Reforms. Hisresearch interest and eld of specialization had led him to pursueactive involvement in legislation, bureaucratic workand civil society advocacy.

    Maria Claudette L. Guevarais the Chief of Staff of theStratbase Group and is a Research Analyst at the ADR Institute.

    9.3VOLUME