Reduce Your Progress Status Cycle Time and Improve Data Quality at the Same Time Using PM CompassRuthanne Schulte, PMP, DeltekJack Newton, DeltekGC-445
2 ©2012 Deltek, Inc. All Rights Reserved
Demonstrate how simple it is to enter progress, the validations, and questions answered by PM Compass
Demonstrate approve progress and see schedule update
Schedule progress and Cost progress
Schedule progress cycle
Assignment mapping grid — who enters and who approves
Schedule the automatic creation of progress items
Pending Progress report
Agenda
3 ©2012 Deltek, Inc. All Rights Reserved
Lots of Manual Steps
Rekeying of information
Lost time chasing down updates
Typical Status Update Process
7 ©2012 Deltek, Inc. All Rights Reserved
Only what needs to be progressed by me is displayed
All activity information is accessible
Entering Progress
8 ©2012 Deltek, Inc. All Rights Reserved
Highlights entries of concern
Easy to see which rows have been edited
Entering Progress
10 ©2012 Deltek, Inc. All Rights Reserved
Click on the ‘delta’ column to see what changed
See What Changed
12 ©2012 Deltek, Inc. All Rights Reserved
Approver can see all the submitted status updates. Visual cues highlight potential trouble areas.
Quickly check what has changed and approve or reject as needed.
Approval
13 ©2012 Deltek, Inc. All Rights Reserved
Question: I only see two activities that were progressed. Is Jack finished entering progress, or did he not finish?
Using this report, I can see that Jack, Will and Sam still have activities that have not been submitted.
Is That All of the Progress?
14 ©2012 Deltek, Inc. All Rights Reserved
Click on the ‘delta’ column to see what changed
See what changed
17 ©2012 Deltek, Inc. All Rights Reserved
Progress History Report shows how progress changed over time
Progress History
18 ©2012 Deltek, Inc. All Rights Reserved
Schedule Progress for when a schedule is attached
Cost Progress for smaller, LoE projects
Two Types of Progress
22 ©2012 Deltek, Inc. All Rights Reserved
Starting at the smallest data element (activity) and working to the top, the first populated user is ‘nagged’ by workflow
Any user in a parent field has access to enter progress.
Benefit: The person responsible for the activity enters the progress, and anyone defined at a higher level, such as the CAM, can also enter progress.
Climbing the Assignment Mapping
23 ©2012 Deltek, Inc. All Rights Reserved
Schedule the creation of progress items
How Items are Created
24 ©2012 Deltek, Inc. All Rights Reserved
Progress Items are created when the activity is: in progress Forecasted to start in the current period Forecasted to start in the next period
This reduces the number of items to choose from.
You can Search for an activity to be progressed
What Items are Created?
25 ©2012 Deltek, Inc. All Rights Reserved
Only activities for which you have rights to progress
Options: My Pending Progress Current Period Only
Search
04/18/202327 ©2012 Deltek, Inc. All Rights Reserved
This alert sends notification
The alert is a combined email so each user gets one email notifying of all progress items
Adding a dashboard alert would give an alert for each activity
Notification
28 ©2012 Deltek, Inc. All Rights Reserved
S
The Approval
Clicking Submit advances the workflow to the next step
29 ©2012 Deltek, Inc. All Rights Reserved
The combine email flag sends one email to the approver notifying they have progress
The Approval Notification
30 ©2012 Deltek, Inc. All Rights Reserved
The rejection notification occurs immediately
Rejection Notification
31 ©2012 Deltek, Inc. All Rights Reserved
Do NOT delete progress items or you will lose the history in the progress history report
If you are testing the process and you want to start over, a KB article #58278 describes the process
Deleting Progress