demand-side flexibility for reliable ancillary services

93
Demand-Side Flexibility for Reliable Ancillary Services in a Smart Grid: Eliminating Risk to Consumers and the Grid ANALYTIC RESEARCH FOUNDATIONS FOR THE NEXT-GENERATION ELECTRIC GRID Irvine, California, Feb. 11–12, 2015 Sean P. Meyn Florida Institute for Sustainable Energy Department of Electrical and Computer Engineering — University of Florida Thanks to my colleagues, Prabir Barooah and Ana Buˇ si´ c and to our sponsors NSF, AFOSR, DOE / TCIPG

Upload: sean-meyn

Post on 16-Jul-2015

359 views

Category:

Engineering


0 download

TRANSCRIPT

Page 1: Demand-Side Flexibility for Reliable Ancillary Services

Demand-Side Flexibility for ReliableAncillary Services in a Smart Grid:

Eliminating Risk to Consumers and the Grid

ANALYTIC RESEARCH FOUNDATIONSFOR THE NEXT-GENERATION ELECTRIC GRID

Irvine, California, Feb. 11–12, 2015

Sean P. Meyn

Florida Institute for Sustainable Energy

Department of Electrical and Computer Engineering — University of Florida

Thanks to my colleagues, Prabir Barooah and Ana Busicand to our sponsors NSF, AFOSR, DOE / TCIPG

Page 2: Demand-Side Flexibility for Reliable Ancillary Services

Eliminating Risk to Consumers and the GridOutline

1 Challenges of Renewable Energy Integration

2 FERC Pilots the Grid

3 Demand Dispatch

4 Buildings as Batteries

5 Intelligent Pools in Florida

6 Conclusions

Page 3: Demand-Side Flexibility for Reliable Ancillary Services

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Challenges

Page 4: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the Challenges

1 Large sunk cost (decreasing!)

2 Engineering uncertainty

3 Policy uncertainty

4 Volatility

Start at the bottom...

1 / 25

Page 5: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the Challenges

1 Large sunk cost (decreasing!)

2 Engineering uncertainty

3 Policy uncertainty

4 Volatility

Start at the bottom...

1 / 25

Page 6: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the Challenges

1 Large sunk cost (decreasing!)

2 Engineering uncertainty

3 Policy uncertainty

4 Volatility

Start at the bottom...

1 / 25

Page 7: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the Challenges

1 Large sunk cost (decreasing!)

2 Engineering uncertainty

3 Policy uncertainty

4 Volatility

Start at the bottom...

1 / 25

Page 8: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the ChallengesWhat’s so scary about volatility?

4 Volatility

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

2 / 25

Page 9: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the ChallengesWhat’s so scary about volatility?

4 Volatility =⇒ greater regulation needs

0

2

4

6

8

2

4

6

8

0

October 20-25 October 27 - November 1

Hydro

Gen

erat

ion

and

Laod

GW

GW Thermal

Wind

Load

Generation

Disturbance from Nature

0

2

4

6

8

2

4

6

8

0

0.8

-0.8

1

-1

0

0.8

-0.8

1

-1

0

Sun Mon Tue

October 20-25 October 27 - November 1

Hydro

Wed Thur FriSun Mon Tue Wed Thur Fri

Gen

erat

ion

and

Laod

GW

GW

GW

Reg

ulat

ion

GW

ThermalWind

Load

Generation

Regulation

Error Signal in Feedback Loop

3 / 25

Page 10: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Some of the ChallengesWhat’s so scary about volatility?

4 Volatility =⇒ greater regulation needs

0

2

4

6

8

2

4

6

8

0

October 20-25 October 27 - November 1

Hydro

Gen

erat

ion

and

Laod

GW

GW Thermal

Wind

Load

Generation

Disturbance from Nature

0

2

4

6

8

2

4

6

8

0

0.8

-0.8

1

-1

0

0.8

-0.8

1

-1

0

Sun Mon Tue

October 20-25 October 27 - November 1

Hydro

Wed Thur FriSun Mon Tue Wed Thur Fri

Gen

erat

ion

and

Laod

GW

GW

GW

Reg

ulat

ion

GW

ThermalWind

Load

Generation

Regulation

Error Signal in Feedback Loop

3 / 25

Page 11: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Comparison: Flight controlHow do we fly a plane through a storm?

Brains

Brawn

Brains

Brawn

What Good Are These?

4 / 25

Page 12: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Comparison: Flight controlHow do we fly a plane through a storm?

Brains

Brawn

Brains

Brawn

What Good Are These?

4 / 25

Page 13: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

Comparison: Flight controlHow do we operate the grid in a storm?

Balancing Authority Ancillary Services Grid

Measurements: Voltage Frequency Phase

Σ

Brains

Brawn

What Good Are These?

5 / 25

Page 14: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 15: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 16: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 17: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 18: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 19: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 20: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 21: Demand-Side Flexibility for Reliable Ancillary Services

Challenges of Renewable Energy Integration

How do we operate the grid in a storm?Disturbance decomposition

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 GW (t) = Wind generation in BPA, Jan 2015

Scary ramps

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary ramps

GW (t) +Gr(t) ≡ 4GW

Sca

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4 G

Goal:

W (t) = Wind generation in BPA, Jan 2015

Scary

Scary Scary

Scary

Scary GW (t) +Gr(t) ≡ 4GW

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Goal: GW (t) +Gr(t) ≡ 4GW

obtained from generation?

Gr(t)

Gr(t)

Scary

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

6 / 25

Page 22: Demand-Side Flexibility for Reliable Ancillary Services

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

G1

G2

G

Traditional generation

FERC Order 745

FERC Order 7553

Gr = G1 +G2 +G3

FERC Pilots the Grid

Page 23: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745: Demand & Generation smooth the Grid

7 / 25

Page 24: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

Origin of FERC 745 – Incentives for Demand Response

FERC 745 is Born!

134 FERC ¶61,187UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION18 CFR Part 35

[Docket No. RM10-17-000; Order No. 745]

Demand Response Compensation in Organized Wholesale Energy Markets(Issued March 15, 2011)

The Commission concludes that paying LMP can address the identifiedbarriers to potential demand response providers.

The outcome?

8 / 25

Page 25: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

Origin of FERC 745 – Incentives for Demand Response

FERC 745 is Born!

134 FERC ¶61,187UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION18 CFR Part 35

[Docket No. RM10-17-000; Order No. 745]

Demand Response Compensation in Organized Wholesale Energy Markets(Issued March 15, 2011)

The Commission concludes that paying LMP can address the identifiedbarriers to potential demand response providers.

The outcome?

8 / 25

Page 26: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

Origin of FERC 745 – Incentives for Demand Response

FERC 745 is Born!

134 FERC ¶61,187UNITED STATES OF AMERICA

FEDERAL ENERGY REGULATORY COMMISSION18 CFR Part 35

[Docket No. RM10-17-000; Order No. 745]

Demand Response Compensation in Organized Wholesale Energy Markets(Issued March 15, 2011)

The Commission concludes that paying LMP can address the identifiedbarriers to potential demand response providers.

The outcome?

8 / 25

Page 27: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 28: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 29: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 30: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 31: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 32: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 33: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC 745 Is Dead!

Conjecture: It had to die.

FERC 745 Nirvana:

Peaks shaved!

Contingencies resolved in seconds!!

Prices smoothed to Marginal Cost!

Contour Map: Real Time Market - Locational Marginal Pricing Help?

$10/MWh

Nirvana @ ERCOT

The problem: In this market, there is no opportunity without crisis

The paradox: In this nirvana,there is no business case for demand response

9 / 25

Page 34: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC Order 755Pay-for-Performance

Time

Regulation Required @ MISO

0

200

400

600

-400

-200

Requires ISO/RTOs to pay regulation resourcesbased on actual amount of regulation service provided

(speed and accuracy).

10 / 25

Page 35: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC Order 755Pay-for-Performance

Time

Regulation Required @ MISO

0

200

400

600

-400

-200

Requires ISO/RTOs to pay regulation resourcesbased on actual amount of regulation service provided

(speed and accuracy).

10 / 25

Page 36: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC Order 755Pay-for-Performance

Time

Regulation Required @ MISO

0

200

400

600

-400

-200

Two part settlement:

1 Uniform price for frequency regulation capacity

2 Performance payment for the provision of frequency regulationservice, reflecting a resource’s accuracy of performance

Performance? Now interpreted as mileage:

Payment ∝∫ T

0

∣∣ ddtG(t)| dt (or discrete-time equivalent)

Not perfect, but it is creating incentives

Question: What is the cost/value of regulation?

11 / 25

Page 37: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC Order 755Pay-for-Performance

Time

Regulation Required @ MISO

0

200

400

600

-400

-200

Two part settlement:

1 Uniform price for frequency regulation capacity

2 Performance payment for the provision of frequency regulationservice, reflecting a resource’s accuracy of performance

Performance?

Now interpreted as mileage:

Payment ∝∫ T

0

∣∣ ddtG(t)| dt (or discrete-time equivalent)

Not perfect, but it is creating incentives

Question: What is the cost/value of regulation?

11 / 25

Page 38: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC Order 755Pay-for-Performance

Time

Regulation Required @ MISO

0

200

400

600

-400

-200

Two part settlement:

1 Uniform price for frequency regulation capacity

2 Performance payment for the provision of frequency regulationservice, reflecting a resource’s accuracy of performance

Performance? Now interpreted as mileage:

Payment ∝∫ T

0

∣∣ ddtG(t)| dt (or discrete-time equivalent)

Not perfect, but it is creating incentives

Question: What is the cost/value of regulation?

11 / 25

Page 39: Demand-Side Flexibility for Reliable Ancillary Services

FERC Pilots the Grid

FERC Order 755Pay-for-Performance

Time

Regulation Required @ MISO

0

200

400

600

-400

-200

Two part settlement:

1 Uniform price for frequency regulation capacity

2 Performance payment for the provision of frequency regulationservice, reflecting a resource’s accuracy of performance

Performance? Now interpreted as mileage:

Payment ∝∫ T

0

∣∣ ddtG(t)| dt (or discrete-time equivalent)

Not perfect, but it is creating incentives

Question: What is the cost/value of regulation?

11 / 25

Page 40: Demand-Side Flexibility for Reliable Ancillary Services

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

Gr = G1 +G2 +G3

G1

G2

G3 Where do we �nd these ailerons?

Demand Dispatch

Page 41: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS?

Reliable?

Cost effective?

Is the incentive to the consumer reliable?

Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 42: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS? (Ancillary Service)Does the deviation in power consumption accurately track the desireddeviation target?

Reliable?

Cost effective?

Is the incentive to the consumer reliable?

Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 43: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS? (Ancillary Service)

-15

-10

-5

0

5

10

15

20

25

30

35

6:00 7:00 8:00 9:00 6:00 7:00 8:00 9:00

Reg

ulat

ion

(MW

)

Gen 'A' Actual Regulation

Gen 'A' Requested Regulation

-20

-15

-10

-5

0

5

10

15

20

:

Reg

ulat

ion

(MW

)

Gen 'B' Actual Regulation

Gen 'B' Requested Regulation

Fig. 10. Coal-�red generators do not follow regulation signals precisely.... Some do better than others

Regulation service from generators is not perfectFrequency Regulation Basics and Trends — Brendan J. Kirby, December 2004

Reliable?Cost effective?Is the incentive to the consumer reliable?Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 44: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS?

Reliable?Will AS be available each day?It may vary with time, but capacity must be predictable.

Cost effective?

Is the incentive to the consumer reliable?

Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 45: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS?

Reliable?

Cost effective?This includes installation cost, communication cost, maintenance,and environmental.

Is the incentive to the consumer reliable?

Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 46: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS?

Reliable?

Cost effective?

Is the incentive to the consumer reliable?If a consumer receives a $50 payment for one month, and only $1 thenext, will there be an explanation that is clear to the consumer?

Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 47: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS?

Reliable?

Cost effective?

Is the incentive to the consumer reliable?

Customer QoS constraints satisfied?The pool must be clean, fresh fish stays cold, building climate issubject to strict bounds, farm irrigation is subject to strict constraints,data centers require sufficient power to perform their tasks.

Perhaps demand dispatch can do all of this?

12 / 25

Page 48: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

We want: Responsive RegulationDemand Dispatch the Answer?

A partial list of the needs of the grid operator, and the consumer:

High quality AS?

Reliable?

Cost effective?

Is the incentive to the consumer reliable?

Customer QoS constraints satisfied?

Perhaps demand dispatch can do all of this?

12 / 25

Page 49: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

Control ArchitectureFrequency Decomposition for Demand Dispatch

Power GridControl FlywheelsBatteries

CoalGas Turbine

BP

BP

BP C

BP

BP

Voltage Frequency Phase

HCΣ

Actuator feedback loop

A

LOAD

Today: PJM decomposes regulation signal based on bandwidth,R = RegA + · · · + RegD

Proposal: Each class of DR (and other) resources will have its ownbandwidth of service, based on QoS constraints and costs.

13 / 25

Page 50: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

Control ArchitectureFrequency Decomposition for Demand Dispatch

Power GridControl FlywheelsBatteries

CoalGas Turbine

BP

BP

BP C

BP

BP

Voltage Frequency Phase

HCΣ

Actuator feedback loop

A

LOAD

Today: PJM decomposes regulation signal based on bandwidth,R = RegA + · · · + RegD

Proposal: Each class of DR (and other) resources will have its ownbandwidth of service, based on QoS constraints and costs.

13 / 25

Page 51: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

Control ArchitectureFrequency Decomposition for Demand Dispatch

Jan 01 Jan 02 Jan 03 Jan 04 Jan 05 Jan 06

GW

0

1

2

3

4

Gr(t)

G1

G2

G

Traditional generation

DD: Chillers & Pool Pumps

DD: HVAC Fans3

Gr = G1 +G2 +G3

14 / 25

Page 52: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

Control ArchitectureFrequency Decomposition for Demand Dispatch

Balancing Reserves from Bonneville Power Authority:

−800−600

-1000

−400−200

0200400600800

BPA Reg signal(one week)

MW

= HVAC + Pool Pumps

15 / 25

Page 53: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

Control ArchitectureFrequency Decomposition for Demand Dispatch

Balancing Reserves from Bonneville Power Authority:

−800−600

-1000

−400−200

0200400600800

BPA Reg signal(one week)

MW

0

−800−600

-1000

−400−200

200400600800

MW

−800−600

-1000

−400−200

0200400600800

= +

= HVAC + Pool Pumps

15 / 25

Page 54: Demand-Side Flexibility for Reliable Ancillary Services

Demand Dispatch

Control ArchitectureFrequency Decomposition for Demand Dispatch

Balancing Reserves from Bonneville Power Authority:

−800−600

-1000

−400−200

0200400600800

BPA Reg signal(one week)

MW

0

−800−600

-1000

−400−200

200400600800

MW

−800−600

-1000

−400−200

0200400600800

= +

= HVAC + Pool Pumps

15 / 25

Page 55: Demand-Side Flexibility for Reliable Ancillary Services

0

−800−600

-1000

−400−200

200400600800

MW

=

Buildings as Batteries

Page 56: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesHVAC flexibility to provide additional ancillary service

◦ Buildings consume 70% of electricity in the USHVAC contributes to 40% of the consumption.

◦ Buildings have large thermal capacity

◦ Modern buildings have fast-responding equipment:VFDs (variable frequency drive)

16 / 25

Page 57: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesHVAC flexibility to provide additional ancillary service

◦ Buildings consume 70% of electricity in the USHVAC contributes to 40% of the consumption.

◦ Buildings have large thermal capacity

◦ Modern buildings have fast-responding equipment:VFDs (variable frequency drive)

16 / 25

Page 58: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesHVAC flexibility to provide additional ancillary service

◦ Buildings consume 70% of electricity in the USHVAC contributes to 40% of the consumption.

◦ Buildings have large thermal capacity

◦ Modern buildings have fast-responding equipment:VFDs (variable frequency drive)

16 / 25

Page 59: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesHVAC flexibility to provide additional ancillary service

◦ Buildings consume 70% of electricity in the USHVAC contributes to 40% of the consumption.

◦ Buildings have large thermal capacity

◦ Modern buildings have fast-responding equipment:VFDs (variable frequency drive)

16 / 25

Page 60: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesTracking RegD at Pugh Hall — ignore the measurement noise

In one sentence:

Ramp up and down power consumption, just 10%, totrack regulation signal.Result:

PJM RegD Measured

Power

(kW

)

0

1

-1

0 10 20 30 40Time (minute)

17 / 25

Page 61: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesTracking RegD at Pugh Hall — ignore the measurement noise

In one sentence: Ramp up and down power consumption, just 10%, totrack regulation signal.

Result:

PJM RegD Measured

Power

(kW

)

0

1

-1

0 10 20 30 40Time (minute)

17 / 25

Page 62: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesTracking RegD at Pugh Hall — ignore the measurement noise

In one sentence: Ramp up and down power consumption, just 10%, totrack regulation signal.Result:

PJM RegD Measured

Power

(kW

)

0

1

-1

0 10 20 30 40Time (minute)

17 / 25

Page 63: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesTracking RegD at Pugh Hall — ignore the measurement noise

In one sentence: Ramp up and down power consumption, just 10%, totrack regulation signal.Result:

PJM RegD Measured

Power

(kW

)

0

1

-1

0 10 20 30 40Time (minute)

17 / 25

Page 64: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Pugh Hall @ UFHow much?

−4

−2

0

2

4

−10

0

10

0 500 1000 1500 2000 2500 3000 3500−0.2

0

0.2

Time (s)

Fan Power Deviation (kW )Regulation Signal (kW )

Input (%)

Temperature Deviation (◦C)

. One AHU fan with 25 kW motor:> 3 kW of regulation reserve

. Pugh Hall (40k sq ft, 3 AHUs):> 10 kW

Indoor air quality is not affected

. 100 buildings:> 1 MW

That’s just using the fans!

18 / 25

Page 65: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Pugh Hall @ UFHow much?

−4

−2

0

2

4

−10

0

10

0 500 1000 1500 2000 2500 3000 3500−0.2

0

0.2

Time (s)

Fan Power Deviation (kW )Regulation Signal (kW )

Input (%)

Temperature Deviation (◦C)

. One AHU fan with 25 kW motor:> 3 kW of regulation reserve

. Pugh Hall (40k sq ft, 3 AHUs):> 10 kW

Indoor air quality is not affected

. 100 buildings:> 1 MW

That’s just using the fans!

18 / 25

Page 66: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Pugh Hall @ UFHow much?

−4

−2

0

2

4

−10

0

10

0 500 1000 1500 2000 2500 3000 3500−0.2

0

0.2

Time (s)

Fan Power Deviation (kW )Regulation Signal (kW )

Input (%)

Temperature Deviation (◦C)

. One AHU fan with 25 kW motor:> 3 kW of regulation reserve

. Pugh Hall (40k sq ft, 3 AHUs):> 10 kW

Indoor air quality is not affected

. 100 buildings:> 1 MW

That’s just using the fans!

18 / 25

Page 67: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity?

Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 68: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 69: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 70: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 71: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 72: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 73: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 74: Demand-Side Flexibility for Reliable Ancillary Services

Buildings as Batteries

Buildings as BatteriesWhat do you think?

Questions:

Capacity? Tens of Gigawatts from commercial buildings in the US

Can we obtain a resource as effective as today’s spinning reserves?

Yes!! Buildings are well-suited to balancing reserves,and other high-frequency regulation resources

much better than any generator

How to compute baselines?

Who cares? The utility or aggregator is responsible for the equipment –the consumer cannot ‘play games’ in a real time market!

What open issues do you see?

19 / 25

Page 75: Demand-Side Flexibility for Reliable Ancillary Services

−600−400−200

0200400600

Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7

MW

Intelligent Pools in Florida

Page 76: Demand-Side Flexibility for Reliable Ancillary Services

−600−400−200

0200400600

Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7

MW

Intelligent Pools in Florida

Page 77: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Example: One Million Pools in FloridaHow Pools Can Help Regulate The Grid

1,5KW 400V

Needs of a single pool

. Filtration system circulates and cleans: Average pool pump uses1.3kW and runs 6-12 hours per day, 7 days per week

. Pool owners are oblivious, until they see frogs and algae

. Pool owners do not trust anyone: Privacy is a big concern

Randomized control strategy is needed.

20 / 25

Page 78: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Example: One Million Pools in FloridaHow Pools Can Help Regulate The Grid

1,5KW 400V

Needs of a single pool

. Filtration system circulates and cleans: Average pool pump uses1.3kW and runs 6-12 hours per day, 7 days per week

. Pool owners are oblivious, until they see frogs and algae

. Pool owners do not trust anyone: Privacy is a big concern

Randomized control strategy is needed.

20 / 25

Page 79: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Example: One Million Pools in FloridaHow Pools Can Help Regulate The Grid

1,5KW 400V

Needs of a single pool

. Filtration system circulates and cleans: Average pool pump uses1.3kW and runs 6-12 hours per day, 7 days per week

. Pool owners are oblivious, until they see frogs and algae

. Pool owners do not trust anyone: Privacy is a big concern

Randomized control strategy is needed.

20 / 25

Page 80: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Example: One Million Pools in FloridaHow Pools Can Help Regulate The Grid

1,5KW 400V

Needs of a single pool

. Filtration system circulates and cleans: Average pool pump uses1.3kW and runs 6-12 hours per day, 7 days per week

. Pool owners are oblivious, until they see frogs and algae

. Pool owners do not trust anyone: Privacy is a big concern

Randomized control strategy is needed.

20 / 25

Page 81: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Pools in Florida Supply G2 – BPA regulation signal∗Stochastic simulation using N = 105 pools

Reference Output deviation (MW)

−300

−200

−100

0

100

200

300

0 20 40 60 80 100 120 140 160t/hour

0 20 40 60 80 100 120 140 160

∗transmission.bpa.gov/Business/Operations/Wind/reserves.aspx

21 / 25

Page 82: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Pools in Florida Supply G2 – BPA regulation signal∗Stochastic simulation using N = 105 pools

Reference Output deviation (MW)

−300

−200

−100

0

100

200

300

0 20 40 60 80 100 120 140 160t/hour

0 20 40 60 80 100 120 140 160

Each pool pump turns on/off with probability depending on1) its internal state, and 2) the BPA reg signal

21 / 25

Page 83: Demand-Side Flexibility for Reliable Ancillary Services

Intelligent Pools in Florida

Pools in Florida Supply G2 – BPA regulation signal∗Stochastic simulation using N = 105 pools

Reference Output deviation (MW)

−300

−200

−100

0

100

200

300

0 20 40 60 80 100 120 140 160t/hour

0 20 40 60 80 100 120 140 160

Mean-field model: Input-output system stable? Passive?

21 / 25

Page 84: Demand-Side Flexibility for Reliable Ancillary Services

Power GridControl Water PumpBatteries

CoalGas Turbine

BP

BP

BP C

BP

BP

Voltage Frequency Phase

HCΣ

Actuator feedback loop

A

LOAD

Conclusions

Page 85: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

ConclusionsAnswers ... and Questions

1 Volatility

This appears to be manageable! Demand Dispatch can be designedto work cooperatively with generation and other resources.

Open questions on many spatial and temporal scales. Most loadscould provide synthetic inertia and governor response1. Is this wise?

2 Engineering uncertaintyThis is real We don’t know why the grid is so reliable today.Need for better understanding of grid2/distribution/social dynamics.

3 Policy uncertaintyScary!

Need for Research in Engineering and Economics1Scweppe et. al. 19802Thorpe et. al. 2004

22 / 25

Page 86: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

ConclusionsAnswers ... and Questions

1 VolatilityThis appears to be manageable! Demand Dispatch can be designedto work cooperatively with generation and other resources.

Open questions on many spatial and temporal scales. Most loadscould provide synthetic inertia and governor response1. Is this wise?

2 Engineering uncertaintyThis is real We don’t know why the grid is so reliable today.Need for better understanding of grid2/distribution/social dynamics.

3 Policy uncertaintyScary!

Need for Research in Engineering and Economics

1Scweppe et. al. 1980

2Thorpe et. al. 2004

22 / 25

Page 87: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

ConclusionsAnswers ... and Questions

1 VolatilityThis appears to be manageable! Demand Dispatch can be designedto work cooperatively with generation and other resources.

Open questions on many spatial and temporal scales. Most loadscould provide synthetic inertia and governor response1. Is this wise?

2 Engineering uncertaintyThis is real We don’t know why the grid is so reliable today.

Need for better understanding of grid2/distribution/social dynamics.

3 Policy uncertaintyScary!

Need for Research in Engineering and Economics

1Scweppe et. al. 1980

2Thorpe et. al. 2004

22 / 25

Page 88: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

ConclusionsAnswers ... and Questions

1 VolatilityThis appears to be manageable! Demand Dispatch can be designedto work cooperatively with generation and other resources.

Open questions on many spatial and temporal scales. Most loadscould provide synthetic inertia and governor response1. Is this wise?

2 Engineering uncertaintyThis is real We don’t know why the grid is so reliable today.Need for better understanding of grid2/distribution/social dynamics.

3 Policy uncertaintyScary!

Need for Research in Engineering and Economics

1Scweppe et. al. 19802Thorpe et. al. 2004

22 / 25

Page 89: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

ConclusionsAnswers ... and Questions

1 VolatilityThis appears to be manageable! Demand Dispatch can be designedto work cooperatively with generation and other resources.

Open questions on many spatial and temporal scales. Most loadscould provide synthetic inertia and governor response1. Is this wise?

2 Engineering uncertaintyThis is real We don’t know why the grid is so reliable today.Need for better understanding of grid2/distribution/social dynamics.

3 Policy uncertaintyScary!

Need for Research in Engineering and Economics

1Scweppe et. al. 19802Thorpe et. al. 2004

22 / 25

Page 90: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

ConclusionsAnswers ... and Questions

1 VolatilityThis appears to be manageable! Demand Dispatch can be designedto work cooperatively with generation and other resources.

Open questions on many spatial and temporal scales. Most loadscould provide synthetic inertia and governor response1. Is this wise?

2 Engineering uncertaintyThis is real We don’t know why the grid is so reliable today.Need for better understanding of grid2/distribution/social dynamics.

3 Policy uncertaintyScary!

Need for Research in Engineering and Economics1Scweppe et. al. 19802Thorpe et. al. 2004

22 / 25

Page 91: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

Conclusions

Thank You!

23 / 25

Page 92: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

Control TechniquesFOR

Complex Networks

Sean Meyn

Pre-publication version for on-line viewing. Monograph available for purchase at your favorite retailer More information available at http://www.cambridge.org/us/catalogue/catalogue.asp?isbn=9780521884419

Markov Chainsand

Stochastic Stability

S. P. Meyn and R. L. Tweedie

August 2008 Pre-publication version for on-line viewing. Monograph to appear Februrary 2009

π(f)<

∆V (x) ≤ −f(x) + bIC(x)

‖Pn(x, · )− π‖f → 0

sup

CEx [S

τC(f)]<

References

24 / 25

Page 93: Demand-Side Flexibility for Reliable Ancillary Services

Conclusions

Selected ReferencesMore at www.meyn.ece.ufl.edu

A. Brooks, E. Lu, D. Reicher, C. Spirakis, and B. Weihl. Demand dispatch. IEEE Powerand Energy Magazine, 8(3):20–29, May 2010.

H. Hao, T. Middelkoop, P. Barooah, and S. Meyn. How demand response from commercialbuildings will provide the regulation needs of the grid. In 50th Allerton Conference onCommunication, Control, and Computing, pages 1908–1913, 2012.

H. Hao, Y. Lin, A. Kowli, P. Barooah, and S. Meyn. Ancillary service to the grid throughcontrol of fans in commercial building HVAC systems. IEEE Trans. on Smart Grid,5(4):2066–2074, July 2014.

S. Meyn, P. Barooah, A. Busic, Y. Chen, and J. Ehren. Ancillary service to the grid usingintelligent deferrable loads. ArXiv e-prints: arXiv:1402.4600 and to appear, IEEE Trans. onAuto. Control, 2014.

D. Callaway and I. Hiskens, Achieving controllability of electric loads. Proceedings of theIEEE, vol. 99, no. 1, pp. 184–199, 2011.

M. Parashar, J. Thorp, and C. Seyler. Continuum modeling of electromechanical dynamicsin large-scale power systems. IEEE Trans. on Circuits and Systems I, 51(9):1848–1858,2004.

25 / 25