demystifying the changes to tjc and cms...
TRANSCRIPT
Demystifying the Changes to TJC and CMS Standards11am-12pmFriday, January 6, 2017
Stephen L. Grimes, FACCE FHIMSS FAIMBEPrincipal ConsultantStrategic Healthcare Technology Associates, [email protected]
Demystifying the Changes to TJC and CMS Standards
Equipment class (i.e., High‐risk, non‐high‐risk, OEM, AEM)
Assuming existence of policies as outlined below
High‐risk (e.g., critical) equipment
Must have a 100% completion rate
Activities& frequencies per OEM recommendation(i.e., non‐AEM)
Must have a 100% completion rate
Activities & frequencies for non‐high‐riskequipment per AEMpolicy
Are to be completed at 100%
Available equipmentPolicy to conduct scheduled maintenance on equipment available (i.e., not “in‐use” or “missing” i.e., not found) during its maintenance window (i.e., scheduled date +/‐ grace period)
This equipment “must have a 100% completion rate” for scheduled maintenance
Equipment that is unavailable is not included in 100% completion rate calculation … but there must be an organization policy for effectively dealing with unavailable equipment and there must be evidence that policy is adhered to
This equipment “must have a 100% completion rate” for scheduled maintenance
Equipment that is unavailable is not included in 100% completion rate calculation … but there must be an organization policy for effectively dealing with unavailable equipment and there must be evidence that policy is adhered to
The policies addressing non‐high‐risk AEM equipment are “to be completed at 100%”
The organization may have a policy for conducting scheduled maintenance on a minimum percentage of non‐high‐risk AEM equipment (e.g., 90%) but must complete ALL scheduled maintenance activities on that equipment when maintenance is conducted on an item.
Demystifying the Changes to TJC and CMS Standards
Equipment class (i.e., High‐risk, non‐high‐risk, OEM, AEM)
Assuming existence of policies as outlined below
High‐risk (e.g., critical) equipment
Must have a 100% completion rate
Activities & frequencies per OEM recommendation (i.e., non‐AEM)
Must have a 100% completion rate
Activities & frequencies for non‐high‐risk equipment per AEM policy
Are to be completed at 100%
Equipment in‐usePolicy to flag equipment (in CMMS) that did not receive scheduled maintenance during its maintenance window because equipment was in‐use during that period.
An effective policy would require scheduled maintenance be conducted as soon as equipment becomes available and may include
• placing a prominent Inspection Due Before Next Use tag on in‐use equipment
• asking operator to notify HTM after removing from patient• notifying owners and organization leadership of all equipment not
receiving scheduled maintenance on time because it was in use• educating owners/users on the policy and process for informing HTM
when equipment becomes available
Equipment in this category that was not maintained on schedule because it was unavailable (in‐use) during the maintenance window is NOT included in the 100% completion rate calculation
Equipment in this category that was not maintained on schedule because it was unavailable (in‐use) during the maintenance window is NOT included in the 100% completion rate calculation
Equipment in this category that was not maintained on schedule because it was unavailable (in‐use) during the maintenance window is NOT a factor in “completed at 100%” calculation
Demystifying the Changes to TJC and CMS Standards
Equipment class (i.e., High‐risk, non‐high‐risk, OEM, AEM)
Assuming existence of policies as outlined below
High‐risk (e.g., critical) equipment
Must have a 100% completion rate
Activities & frequencies per OEM recommendation (i.e., non‐AEM)
Must have a 100% completion rate
Activities & frequencies for non‐high‐riskequipment per AEMpolicy
Are to be completed at 100%
Equipment missing‐in‐action (MIA)Policy to flag in CMMS equipment that did not receive scheduled maintenance during its maintenance window because equipment could not be located (i.e., was MIA) during that period.
An effective policy requires documented attempts to locate missing equipment and may include:• requesting aid in writing of owner/operators• requiring HTM staff performing sweeps • declaring equipment permanently gone (including notification of
owners & leadership of its status) and deactivating missing equipment in inventory after a reasonable period.
• Informing leadership regarding missing systems
Equipment in this category that was not maintained on schedule because it was unavailable (could not be located) during the maintenance window is NOT included in the 100% completion rate calculation
Equipment in this category that was not maintained on schedule because it was unavailable (could not be located) during the maintenance window is NOT included in the 100% completion rate calculation
Equipment in this category that was not maintained on schedule because it was unavailable (could not be located) during the maintenance window is NOT a factor in “completed at 100%” calculation
Demystifying the Changes to TJC and CMS Standards
Implement an Alternate Equipment Maintenance (AEM) Program!!Start with OEM recommendations for scheduled maintenance activities and frequenciesDevelop AEM strategies and move any eligible equipment to AEM and adjust scheduled maintenance activities and frequencies from OEM recommendationsThe strategies of an AEM program must not reduce safety of equipment and must be based on accepted standards of practice, such as ANSI/AAMI EQ56To verify that safety will not be reduced by AEM conduct risk assessments
Reference CMS Letter S&C: 14‐07‐Hospital (December 20, 2013)including Revised State Operations Manual (SOM) Hospital Appendix A
Demystifying the Changes to TJC and CMS Standards
Conducting Risk AssessmentRemember definition of Risk!
Risk = Function (Severity, Probability)
‐ and when we’re talking about maintenance issues ‐
Risk of scheduled maintenance‐related failure = Function (Severity of failure , Probability of scheduled maintenance‐related failure)
Demystifying the Changes to TJC and CMS Standards
Determining risks requires we establish progressive scales for both Severity and Probability Note: # of levels are arbitrary … should be what works for you and your organization
Example of Severity Levels
Note that in this model, any equipment given a score of 4 (Catastrophic) or 3 (Critical) would be considered “Critical” by CMS and “High Risk” by the Joint Commission
Level # Level Description Criteria1 Negligible No or negligible adverse effect (e.g., little or no health or safety effect)
2 Marginal Reversible adverse effect (e.g., minor health or safety effect)
3 Critical Permanent adverse effect (e.g., serious health or safety effect)
4 Catastrophic Loss of life
Demystifying the Changes to TJC and CMS Standards
Determining risks requires we establish progressive scales for both Severity and Probability Note: # of levels are arbitrary … should be what works for you and your organization
Example of Probability Levels of scheduled maintenance‐related failure
Example of Probability Levels
Level # Level Description Criteria
Examples: 1 ÷ MeanTimeBetweenMaintenanceRelatedFailure(years) = Annual Rate %
Mean Time Betweenmedical devices 10 yr life
expectancy on avgAnnual Rate
Percent of total sample
1 Improbable very unlikely to occur > 20 years < 5% per year
2 Remote unlikely but possible to occur > 10 and <20 years > 5% and < 10% per year
3 Occasional likely to occur > 5 and < 10 years > 10% and < 20% per year
4 Probable very likely to occur <5 years > 20% per year
Demystifying the Changes to TJC and CMS Standards
Any eligible device identified as LOW risk based on incident/service histories … can be placed in an Alternate Equipment Maintenance(AEM) Program as long as risks to patients or staff do not increase
Demystifying the Changes to TJC and CMS Standards
Any eligible device identified as LOW risk based on incident/service histories … can be placed in an Alternate Equipment Maintenance (AEM) Program reducing scheduled maintenance activities and/or frequencies as long you can demonstrate as risks to patients or staff do not increase
Assess maintenance related Risk
Consider whether risk indicates there should be a change in scheduled maintenance activities and/or frequencies
Monitor maintenancefailures
Feedback (regular review)
Demystifying the Changes to TJC and CMS Standards
Medical Device Risk Assessment
Review Form for AEM
Policy for Medical Equipment Risk Analysis ‐ Determining Suitability for an Alternate Equipment Maintenance
(AEM) Program
Flow Process for implementing and maintaining an AEM
ANSI/AAMI EQ56:2013 Recommended practice for a medical equipment management program
ANSI/AAMI EQ89: 2015 Guidance for the use of medical equipment maintenance strategies and procedures
AAMI Reliability‐Centered‐Maintenance (RCM) Workgroupfocused risk assessment and maintenance strategies
Contacts:• Alan Lipschultz [email protected]• Malcolm Ridgway [email protected]• Steve Grimes [email protected]
Demystifying the Changes to TJC and CMS Standards
12 © AAMI