der interconnection requirement whitepaper · 2018. 4. 6. · lm3 lm1 ride-through lc6 lc5 lc3 lc4...
TRANSCRIPT
© 2015 Electric Power Research Institute, Inc. All rights reserved.
Jens C. BoemerLeading research on the grid integration
of renewable and distributed energy resources
NERC ERSTF, AtlantaMarch 11th, 2015
DER Interconnection Requirement Whitepaper
Recommended Settings for Voltage and Frequency Ride-Through of
Distributed Energy Resources
2© 2015 Electric Power Research Institute, Inc. All rights reserved.
Background
Bulk and distribution system needs
EPRI‘s Recommended Minimum Requirements & Settings
Conclusions
Discussion– NERC coordination with
revision of IEEE Standard 1547 ???
Content
3© 2015 Electric Power Research Institute, Inc. All rights reserved.
Background
Interconnection Standards and Grid Codes are one out of 3 key EPRI research areas in the context of the Integrated Grid
Why does EPRI engage in this topic?
Benefit/Cost Framework
Inter-connection Technical
Guidelines
Grid Planning & Operations
Collaboration with All StakeholdersIncluding Regulatory/Policy Needed
4© 2015 Electric Power Research Institute, Inc. All rights reserved.
Background
IVGTF Report (Task 1-7), Dec. 2013– Gives a solid rationale for ride-through requirements for all
DER, regardless of size or technology– In the short-term, NERC should engage in current efforts to
revise DER interconnection standards Recommends explicit low and high voltage & frequency
ride-through requirements Gives “examples” for VRT and FRT curves / tables
– In the longer-term, NERC should establish a coordination mechanism with IEEE Standard 1547 … ???
NERC PRC-024-2, Jan. 2015– Standard for Generator Frequency and Voltage Protective
Relay Settings– Limited to NERC jurisdiction, i.e., Bulk Electric System I4,
Dispersed power producing resources: > 75 MVA (gross nameplate rating) PCC at a voltage of 100 kV or above
– Not an explicit ride-through standard! Units may trip due to internal protection functions, e.g.,
out-of-step, loss-of-field, instab. in pwr. conv. ctrl. equipm.
What are the related NERC activities / publications?
5© 2015 Electric Power Research Institute, Inc. All rights reserved.
BackgroundWhat is the status of the revision of the IEEE Standard 1547?
2005
2011
FERC SGIP (Small Generator Interconnection Procedure)
IEEE 1547-20032003
2000 California Rule 21
Updated California Rule 21(consistent with IEEE 1547-2003)
IEEE 1547a-20142014
2015
2016
Updated California Rule 21 & HECO’s FVRT Requirements
(go far beyond IEEE 1547a-2014)
2018IEEE 1547rev-20xx
Revisions in IEEE 1547a-2014: Allows DER1 to support voltage
via real/reactive power Permits frequency/watt functions Optional widening of trip limits and
clearance times Dynamic trip limits now allowed
Refine in IEEE 1547rev-20xx: Ride-through Voltage Support Communication/Control Anti-islanding detection
1 distributed energy resources
6© 2015 Electric Power Research Institute, Inc. All rights reserved.
Bulk and Distribution System Needs
Transmission Distribution
… are quite different but can only be approached in an integrated way.
Voltage/Reactive Power Power quality: voltage limits/power factor
Frequency Stability
Health & Safety: protection coordination/anti-islanding
7© 2015 Electric Power Research Institute, Inc. All rights reserved.
Bulk and Distribution System Needs
Transmission Distribution
… are quite different but can only be approached in an integrated way.
Future Technical Guidelines Must Equally Address Bulk and Distribution System Needs
Voltage/Reactive Power Power quality: voltage limits/power factor
Health & Safety: protection coordination/anti-islanding
Frequency Stability
8© 2015 Electric Power Research Institute, Inc. All rights reserved.
EPRI‘s Recommended Minimum Requirements & Settings
Three types of zones Zone 1: Must Trip Zone 2: Ride-Through or Trip is
Allowed Zone 3: Ride-Through
Various operating zones/modes “Passive” ride-through “Active” ride-through
– “as you were”– “smart”
Event Duration
Appl
icab
le V
alue
(p.u
.)
1.0 p.u.
Must Trip
LC1
LM5LM4
LM2LM3
LM1
Ride-Through LC6LC5
LC3 LC4
LC2
HM5HM4
HM3HM2
HM1
HC3HC4
HC2HC1
Must Trip
Ride-Through or Trip is Allowed
Ride-Through or Trip is Allowed
Appl
icab
le V
alue
(p.u
.)
1.0 p.u.
LC1
LC6LC5
LC3 LC4
LC2
HC3HC4
HC1 HC2
Event Duration
Zone A Mode
Zone B Mode
Zone C Mode
Ride-Through
Ride-Through or Trip is Allowed
What is the high-level concept behind these recommendations?
9© 2015 Electric Power Research Institute, Inc. All rights reserved.
EPRI‘s Recommended Minimum Requirements & Settings
Recommendations should be technology-neutral
Guiding principles for frequency ride-through were– DER should not be tripped before under-frequency load
shedding (UFLS) is fully activated and before the frequency is restored following a major disturbance;
– DER should not be tripped during over-frequency events likely to occur during contingency situations;
– DER should comply with a minimum ride-through requirement
No droop characteristic (frequency-watt) as a minimum requirement, rather an advanced requirement
What are the recommendations for frequency ride-through?
10© 2015 Electric Power Research Institute, Inc. All rights reserved.
EPRI‘s Recommended Minimum Requirements & SettingsWhat are the recommendations for frequency ride-through?
56.0
56.5
57.0
57.5
58.0
58.5
59.0
59.5
60.0
60.5
61.0
61.5
62.0
62.5
63.0
0.01 0.1 1 10 100 1000
Freq
uenc
y (H
z)
Time (s)
Normal Operation
aHFRT - "as you were"
aLFRT - "as you were"
Tripped
Tripped
65.0 Hz 65.0 Hz
300 s
10 s0.16 s
10 s
60.5 Hz
61.5 Hz
50.0 Hz
59.5 Hz
0.16 s 10 s
50.0 Hz
58.5 Hz
300 s10 s
12 s
Legend
range of adustability
default value
operating region
11© 2015 Electric Power Research Institute, Inc. All rights reserved.
EPRI‘s Recommended Minimum Requirements & Settings
Recommendations should be technology-neutral
Guiding principles for voltage ride-through– Consider the geographic extension of a voltage dip at bulk system
level and the affected DER capacity;– Consider the voltage dip propagation from bulk system to
distribution level;– Minimum trip times and LVRT duration should consider bulk system
fault clearing times for both normally cleared faults (by primary protection) and stuck breaker faults cleared with delay (by remote backup);
– Keep the impact of LVRT requirements on the Area EPS as low as possible;
– Ensure a fast restoration of pre-fault real power output after disturbances.
What are the recommendations for voltage ride-through?
12© 2015 Electric Power Research Institute, Inc. All rights reserved.
EPRI‘s Recommended Minimum Requirements & SettingsWhat are the recommendations for voltage ride-through?
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
0.01 0.1 1 10 100 1000
Volta
ge (p
.u.)
Time (s)
aHVRT - "as you were"
Tripped1.30 p.u. 1.30 p.u.
13 s0 s 0.16 s
1 s
1.10 p.u.1.20 p.u.
0.20 p.u.
0.70 p.u.
0 s1 s
0.20 p.u.
0.45 p.u.
21 s2 s
Legend
range of adustability
default value
operating region
Normal Operation
pHVRT
aLVRT - "as you were"
pLVRT OR aLVRT - "as you were"
0.20 p.u.
11 s
Tripped
1 s0.50 p.u.
0.32 s
0.32 s
13© 2015 Electric Power Research Institute, Inc. All rights reserved.
Conclusions
NERC’s IVGTF Report (Task 1-7), Dec. 2013, has set the scene for voltage & frequency ride-through requirements;
CA Rule 21 and HECO’s F/VRT requirements are leading, but IEEE Standard 1547 is speeding up thanks to involvement of EPRI;
EPRI proposes minimum requirements & settings for voltage and frequency ride-through of DER and engages in discussions with relevant stakeholders;
These minimum requirements could define the baseline of F/VRT in IEEE 1547rev-20xx to address both bulk and distribution system needs;– Advanced requirements could be defined in “higher” performance classes;
How to further coordinate NERC input with the revision of the IEEE Standard 1547?
14© 2015 Electric Power Research Institute, Inc. All rights reserved.
Together…Shaping the Future of Electricity
Feel free to ask questions…
Jens C. Boemer, email [email protected] , phone +1.206.471.1180
15© 2015 Electric Power Research Institute, Inc. All rights reserved.
DiscussionHow to coordinate NERC input with the revision of the IEEE Standard 1547?
2015 2016
Common Definitions
High-level Ride-
Through Concept
Draft Ride-Through
Trip settings & ranges
Permissive Ride-Through: “passive” or “active” Ride-Through
Continuous Operation
Smart Ride-
ThroughPermissive Operation:
1. duration 2. applicable voltageReturn to Service
Momentary Cessation
“active” Ride-Through - “as you were”
“Energize”
Mandatory Operation
state transition
16© 2015 Electric Power Research Institute, Inc. All rights reserved.
Example for Advanced RequirementsFault induced delayed voltage recovery (FIDVR) in distribution systems with high A/C loads
1.0
0.8
0.9
1.1
1
2
34
5
6
2 Delayed recovery as stalled A/Cs disconnect
3 Overvoltage due to capacitors still on line
4 Capacitors switch off due to overvoltage
5 A/C loads come back
6 Undervoltage due to capacitors off line
1 Fault & fault clearance
5 to 30 sec.
Time [s]
Volta
ge [p
.u.]
w/o “smart” ride-through
with “smart” ride-through
FIDVR can be mitigated by “smart” LVRT
17© 2015 Electric Power Research Institute, Inc. All rights reserved.
P1547 III) General Requirements 2 – Ride-Through
Consensus reached within Sub-W.G. / proposal to Overall Working Group
Topic is still under discussion within Sub-W.G.
Alternative positions within Sub-W.G.
Traffic light indicate where the process stands
18© 2015 Electric Power Research Institute, Inc. All rights reserved.
P1547 III) General Requirements 2 – Ride-Through
Reference point for requirements– Point of Common Coupling (PCC), or– Point of DER Connection / Electrical Connection Point
Differentiation of requirements– Technology classes, e.g., directly-connected synchronous generators, inverter-coupled generation
– Performance classses, e.g., minimum requirements for bulk system reliability, advanced requirements for distribution system power quality
Fundamental open decisions
19© 2015 Electric Power Research Institute, Inc. All rights reserved.
P1547 III) General Requirements 2 – Ride-Through
Continuous Operation (“normal operation”) Trip (industry standard term)
– “Cease to Energize” (from IEEE Std. 1547-2003) Ride Through
– Operating RegionPermissive Operation (“passive” or “active” ride-through)Momentary Cessation (“passive ride-through”)Mandatory Operation (“active” ride-through)
– “Return to Service” “Energize” (term already reserved by Area EPS)
Manufacturer stated accuracy
Common terms to describe ride-through behavior
20© 2015 Electric Power Research Institute, Inc. All rights reserved.
P1547 III) General Requirements 2 – Ride-Through
For voltage ride-throughLatest proposal (Feb 26) – work in progress
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
0.01 0.1 1 10 100 1000
Volta
ge (p
.u.)
Time (s)
Momentary Cessation or Volt/Watt
Tripped1.30 p.u. 1.30 p.u.
13 s0 s 0.16 s
1 s
1.10 p.u.1.20 p.u.
0.00 p.u.
0.88 p.u.
0 s1 s
0.00 p.u.
0.45 p.u.
21 s2 s
Legend
range of adustability
default value
operating region
Continuous Operation
Mandatory Operation
Permissive Operation
Tripped
0.16 s
0.32 s
Measure 4• Frequency nadir as a function of unit trip size
at similar load (net load) conditions;• For example, low net load conditions are of
interest since synchronous inertia is lower and less generators with governors in service are available.
• Other system conditions may also be of interest
Measure 4
Inertial and Frequency Response Estimator tool (IFRET)
• Estimates inertial frequency response to disturbance in MW/0.1 Hz• Allows in real time to estimate Point A to Point C frequency deviation for a
generation trip• Uses real time information about committed conventional generation (H
and MVA), system load data, wind penetration (as % of load), available spinning reserves
• Uses linear equations (e.g. see previous slide) obtained from historical generation trip events at similar set of conditions.
• Can provide System Operator with better awareness of the potential frequency deviation due to loss of a unit.
• Can be used as a decision support tool. The System Operator can commit additional units to provide adequate Inertia support in normal operations based on IFRET result.
• During 2010, IFRET was running in the control room, since Nodal Market the tool has been used intermittently, needs update with recent frequency events.
Change in System Frequency and MW loss relationship for Data-Set II
Change in System Frequency and MW loss relationship for Data-Set I
ERSTFLoads and Resources Balance
Clyde Loutan, Senior Advisor – Renewable Energy Integration, CAISO
Jacksonville, Florida
March 11 & 12
RELIABILITY | ACCOUNTABILITY2
Loads and Resources Team
Subgroup Lead Company Email
Clyde Loutan CAISO [email protected]
Subgroup Members
Amir Najafzadeh NERC [email protected]
Brendan Kirby Kirby Consulting [email protected]
Dave Devereaux IESO [email protected]
Ed Scott Duke Energy [email protected]
Jay Ruberto First Energy [email protected]
Layne Brown WECC [email protected]
Michael McMullen MISO [email protected]
Michael Milligan NREL [email protected]
Noha Abdel-Karim NERC [email protected]
Pooja Shah NERC [email protected]
Ron Carlsen Southern Company [email protected]
Todd Lucas Southern company [email protected] Siegrist Brickfield, Burchette, Ritts & Stone, P.C. [email protected] Dariush Shirmohammadi California Wind Energy Association [email protected] Tuohy EPRI [email protected]
RELIABILITY | ACCOUNTABILITY3
CAISO: 1-Hour Upward Ramping Needs
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2011_1h 3,935 3,630 3,271 2,897 2,951 2,637 3,137 2,933 3,004 3,514 3,746 4,5062012_1hr 3,875 3,394 3,428 2,959 2,736 2,606 2,695 2,766 3,143 3,240 5,358 4,3522013_1hr 4,524 3,557 3,224 2,893 3,072 3,401 2,723 2,380 2,964 3,406 3,759 4,5672014_1hr 3,862 3,374 3,064 3,653 2,527 3,128 2,446 2,320 2,848 3,012 3,192 4,2352018_1hr 5,790 6,545 6,298 5,459 4,515 4,220 3,976 4,774 5,999 6,084 6,794 7,420
0
1,000
2,000
3,000
4,000
5,000
6,000
7,000
8,000
MW
Maximum 1-Hour Upward Ramps
RELIABILITY | ACCOUNTABILITY4
CAISO: 3-Hour Upward Ramping Needs
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2011_3hr 6,766 6,067 5,688 5,942 6,732 7,822 7,702 7,251 6,767 6,433 7,098 2012_3hr 7,173 7,028 5,774 6,278 5,543 6,367 7,410 6,591 6,422 6,062 7,2112013_3hr 7,171 6,736 5,881 6,096 8,745 6,426 6,024 6,591 6,609 7,355 8,3432014_3hr 6,170 5,755 5,363 6,394 6,177 6,559 5,879 7,862 5,952 5,844 6,4942018_3hr 15,048 14,100 11,332 11,022 10,769 10,390 12,143 14,174 12,509 15,190 17,179
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
16,000
18,000
20,000
MW
Maximum 3-Hour Upward Ramps
RELIABILITY | ACCOUNTABILITY5
CAISO: 1-Hour Downward Ramping Needs
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2011_1h -2,823 -2,939 -2,751 -2,758 -3,374 -3,771 -3,994 -3,920 -4,758 -3,267 -2,719 -3,2522012_1hr -3,118 -7,240 -2,940 -3,056 -3,458 -3,457 -4,049 -3,919 -4,220 -3,972 -4,547 -3,0432013_1hr -3,236 -2,663 -3,004 -3,194 -4,043 -3,820 -4,398 -4,140 -3,926 -3,026 -2,849 -3,0442014_1hr -2,506 -2,510 -2,601 -3,554 -4,170 -3,728 -3,826 -3,830 -4,248 -3,453 -2,426 -2,7952018_1hr -4,014 -4,078 -5,344 -4,593 -4,901 -4,672 -4,955 -5,316 -5,659 -4,997 -4,638 -4,590
-8,000
-7,000
-6,000
-5,000
-4,000
-3,000
-2,000
-1,000
0
MW
Maximum 1-Hour Downward Ramps
RELIABILITY | ACCOUNTABILITY6
CAISO: 3-Hour Downward Ramping Needs
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2011_3hr -7,091 -7,118 -6,711 -6,690 -8,276 -9,248 -10,362 -9,919 -11,684 -8,162 -6,900 -8,202 2012_3hr -7,083 -7,363 -6,900 -7,472 -8,472 -7,734 -9,804 -10,775 -10,195 -10,256 -6,865 -7,6802013_3hr -7,600 -6,794 -6,806 -7,769 -9,908 -10,357 -10,023 -10,438 -10,136 -6,765 -6,643 -7,2272014_3hr -6,258 -6,263 -6,350 -9,330 -10,538 -9,395 -9,813 -10,128 -10,981 -8,996 -6,346 -7,1132018_3hr -8,815 -9,106 -9,086 -9,418 -12,068 -10,684 -11,676 -12,871 -13,143 -10,223 -8,541 -9,572
-14,000
-12,000
-10,000
-8,000
-6,000
-4,000
-2,000
0
MW
Maximum 3-Hour Downward Ramps
RELIABILITY | ACCOUNTABILITY7
BC Hydro 1-Hour Ramps
RELIABILITY | ACCOUNTABILITY8
BC Hydro 3-Hour Ramps
RELIABILITY | ACCOUNTABILITY9
Duke Energy Florida (DEF)
RELIABILITY | ACCOUNTABILITY10
Duke Energy Carolinas (DEC)
RELIABILITY | ACCOUNTABILITY11
Duke Energy Progress (DEP)
RELIABILITY | ACCOUNTABILITY12
Measure 6Ramping Capability Measures
The historical and projected maximum one-hour up, one-hour down, three-hour up, and three-hour down net load ramps (actual load less production from VERs) using one minute data.
Year One-hour Up One-hour down Three-hour Up Three-hour Down
2011 6166 -6325 11714 -100962012 5560 -4376 10385 -96142013 4192 -4521 9034 -90722014 4423 -3868 9911 -92362015 4423 -3868 9911 -92362016 4423 -3868 9911 -92362017 4423 -3868 9911 -9236
YearWind
Capacity, MW PV, MW2011 0 02012 0 02013 202 462014 404 502015 404 11822016 654 11822017 654 1670
Southern Company
RELIABILITY | ACCOUNTABILITY13
Southern Company
RELIABILITY | ACCOUNTABILITY14
Southern Company
Todd Lucas
RELIABILITY | ACCOUNTABILITY15
PJM
RELIABILITY | ACCOUNTABILITY16
PJM
Ken Schuyler
RELIABILITY | ACCOUNTABILITY17