design and construction of a reinforced soil embankment · pdf filedesign and construction of...
TRANSCRIPT
Design and construction of a reinforced soil embankment on soft soil
Russell Jones, Golder Associates
Gareth Swift, University of Salford
OverviewBackground
Site details
Design philosophy
Design issues
Construction issues
Conclusions
BackgroundIntroduction
Site is located south of Basildon in Essex
Bounded by:
• Wat Tyler country park on western boundary
• Pitsea Marshes (SSSI) along the northern boundary
• East Haven Creek along southern boundary (Thames beyond)
Background
Pitsea landfill site located south of Basildon in Essex, and covers an area of approx.284ha (>50ha currently operational)
Introduction
BackgroundIntroduction
Paper and presentation deals with design and construction issuesrelating to a large leachate lagoon to be constructed on soft, compressible soils
Design carried out in June 2002
Construction between July 2002 and January 2003
Lagoon filled to capacity March 2008
Final Certificate issued by the Panel Engineer July 2008
BackgroundClient brief:
Minimum leachate capacity of 150,000m3
Maximum cost of build £1.3mill
Maximum bund height 8mAOD (planning constraint)
……needs to be buildable!
BackgroundAdditional design constraints:
Ensure stability
Minimise soil imports
Maximise lagoon area (hence, minimise bund height)
Minimise excavation in to existing soils
BackgroundAdditionally…
Satisfy requirements of Reservoir Act 1975
the Act applies to Large Raised Reservoirs, defined as:
‘being designed to hold or capable of holding more than 25,000m3 of water as such above the natural level of any part of the land adjoining the reservoir (including the bed of any stream)’
OverviewBackground
Site details
Design philosophy
Design issues
Construction issues
Conclusions
Site DetailsGround conditions
The area is relatively even but groundwater levels close to, or at, the ground surface
Waste dating from the 1950’s underlies the site in a layer between 1m and 7m thick
Waste comprises ash, clinker, glass, cans in hydraulic continuity with the surrounding landfill
This overlies a generally soft stratum of alluvial clays and sands (mv 0.2 – 0.8m2/kN).
Site DetailsGround conditions
A similar, but earlier, lagoon encountered significant difficulties during construction associated with the high groundwater levels and the trafficability of the waste and the soft alluvial material.
Site DetailsGround conditions
OverviewBackground
Site details
Design philosophy
Design issues
Construction issues
Conclusions
Design PhilosophyOriginal design philosophy
Reducing the existing ground level of approximately 3 m AOD to a minimum formation level of 1.0 m AOD
Pumping and dewatering required (estimated quantity 20,000 to 75,000m3)
Forming embankment slopes of 1v:4h utilising the excavated waste
Using a single ethylene inter-polymer alloy geomembrane liner on both the base and embankment slopes
Liner manufactured to a specific prefabricated size and shape tosuit the design
Design PhilosophyOriginal design philosophy
Design PhilosophyOriginal design philosophy
Design PhilosophyOriginal design philosophy
Ground conditions are poor at best:
• Groundwater/leachate levels at or near to the ground surface; and
• Material to be excavated to produce a formation level comprised 1950’s waste of questionable engineering integrity
Dewatering logistically difficult due to up-gradient landfill (with leachate)
Single geomembrane liner not the most effective barrier
Tenderers’ comments
Design PhilosophyProposed design
No excavation
• Reinforced basal platform 20 m wide by 700 mm thick constructed at the existing ground level
Steeper face angles
• Reinforced soil perimeter embankment, 5.5 m high
• External side slopes 1v:2h
• Internal side slopes 1v:1v
Design PhilosophyOriginal design philosophy
Design PhilosophyProposed design
Design PhilosophyProposed design
Design PhilosophyProposed design
Base area of approximately 32,000 m2 lined with a composite lining system
• 2 mm thick Linear Low Density Polyethylene (LLDPE) sheet
• Geosynthetic clay liner (GCL)
Underdrainage geocomposite drainage layer to limit hydraulic pressures from the leachate and gas
Lining of the perimeter embankment with
• 2 mm thick LLDPE geomembrane
• Geocomposite drainage layer connected to a piped drainage system
Design PhilosophyProposed design
OverviewBackground
Site details
Design philosophy
Design issues
Construction issues
Conclusions
Design IssuesProposed design
Since material was limited to on-site sources, the quality would be variable
Side slopes would be steep in order to achieve capacity
• Geosynthetic reinforcement, geotextile rather than geogrid to aid dissipation of pore pressures
• Primary geotextile reinforcement
• Secondary geogrid reinforcement
Granular material used for foundation layer
Cohesive material used for most of embankment but granular material used for upper section
Design IssuesProposed design
Design IssuesProposed design
Design IssuesReinforcement details
4Fornit 20/20
3Stabilenka 100/50Class 6I, 6J, 7B, 7C or 7D material
Embankment
1Tensar 120RECrushed concrete finesBasal layer 2
1Tensar 160RE75 mm crushed concrete (min 50 kN 10 % fines)
Basal layer 1
No. of Layers
ReinforcementMaterialLayer
Design IssuesSettlement
Final top of embankment = 7.5m AOD
Constructed to = 8m AOD due to anticipated settlement
Design Issues
mv = 0.2m2/MNk = 1 x 10-8m/s
0.2 to 0.8
25019Alluvium
Beneath northern embankment
0.325016Old waste
Beneath main slope
0.525016Old waste
-0.130018Foundation layer
-0.124020Embankment fill
Additional information
ruφ′(deg)
c′(kPa)
γb
(kN/m3)Material
Material parameters
Design IssuesValue Engineering
Time constraints
Design optimisation during construction
Supported by field trials where possible
ECC form of contract
Design IssuesValue Engineering
NEC/Engineering and Construction Contract
Six Main Options
• Option A - Priced with Activity Schedule
• Option B - Priced with BQ
• Option C - Target with Activity Schedule
• Option D - Target with BQ
• Option E - Cost Reimbursement
• Option F - Management Contract
Design IssuesContract
NEC/Engineering and Construction Contract
Six Main Options
• Option A - Priced with Activity Schedule
• Option B - Priced with BQ
• Option C - Target with Activity Schedule
• Option D - Target with BQ
• Option E - Cost Reimbursement
• Option F - Management Contract
Design IssuesStability
A key factor in the design of the perimeter embankments is theirstability
• Internal – Inside face and outside face
• External – Global failure and siding
Major issue is the development of pore water pressure in the sub-grade due to embankment construction
• Slope/w and Seep/w used to examine the effects of pore water pressure on stability
• Results indicate that the rate of build up and dissipation was critical to stability
Design IssuesStability
Piezometers used on site to monitor pore water pressures
Construction of toe berms would improve short term stability
• Factor of safety >1.3 if ru <0.7
• Toe berms allow increase in ru to 0.8
Design IssuesStability
Design IssuesStability
700mm thick reinforced foundation layer:•300mm drainage layer •400mm stability layer
Design IssuesStability
Typical output:
1.509
Top Layer of Fornit 20/20
3 Layers of Stablenka
Top Layer of 120RELower Layer of 160RE
10 kPa
Design IssuesGroundwater
Geotextile reinforcement allows dissipation of pore pressures inembankment fill
Geocomposite allows dissipation of pore pressures beneath the lagoon
75mm crushed concrete layer allows dissipation of pore pressures beneath the embankment
Design IssuesEnvironmental considerations
Leachate containment
• 2mm LLDPE geomembrane
• GCL
• UV protection geotextile
Underdrainage
• Complete system required to remove gases beneath lining system
• 12mm geocomposite
OverviewBackground
Site details
Design philosophy
Design issues
Construction issues
Conclusions
Construction IssuesConstruction works
Groundwater monitoring
Settlement monitoring
Construction IssuesConstruction works
Poor ground conditions
Construction IssuesConstruction works
Generally, a flatlying area in a floodplain
Construction IssuesConstruction works
Construction IssuesConstruction works
Relatively flat formation level (3.0mAOD) required:
• Removal of bushes/trees
• Re-profiling of hummocky areas
• Elevated ground in NE was excavated
• Low area in south backfilled
Existing leachate trench backfilled
Dewatering, where required
Installation of piezometers
Construction of cut-off trench
Construction IssuesConstruction works
Construction IssuesConstruction works
Basal layer
• Separator geotextile on existing ground
• 9 mm Drainage geocomposite
• 300 mm thick drainage layer
• Separator geotextile on drainage layer
• 400 mm thick stability layer including two layers of geogridreinforcement
Construction IssuesConstruction works
Foundation layer, first layer of geogrid
Construction IssuesConstruction works
Foundation layer, second layer of geogrid
Construction IssuesConstruction works
Foundation layer
Construction IssuesConstruction works
Reinforced embankment
• Compacted general fill material (Class 6I, 6J, 7B, 7C or 7D)
• Geotextile primary reinforcement
• Geogrid secondary reinforcement
Construction IssuesConstruction works
Lining system
• Drainage geocomposite
• Geomembrane
• Perforated pipe
• Soil retention geocomposite
Construction IssuesConstruction works
Construction IssuesConstruction works
Installation of perforated pipe at toe of inside slope
Construction IssuesConstruction works
Embankment starting to be constructed
Construction IssuesConstruction works
Embankment works continuing
Construction IssuesConstruction works
Embankment works continuing, inside face
Construction IssuesConstruction works
Embankment works continuing, outside face
Construction IssuesConstruction works
Embankment works, becoming difficult with cohesive fill
Construction IssuesConstruction works
Trafficability concerns…
Construction IssuesConstruction works
Embankment works, revised fill
Construction IssuesConstruction works
Embankment works, revised fill, impact on geotextile reinforcement
Construction IssuesConstruction works
Embankment works, revised fill, impact on geogrid reinforcement
Construction IssuesConstruction works
Embankment works, working in the winter
Construction IssuesConstruction works
Embankment works, geocomposite and geomembrane deployment
Construction IssuesConstruction works
Embankment works, uv protection geotextile and tyre wave wall
Construction IssuesConstruction works
Embankment works, soil retention geocomposite
Construction IssuesConstruction works
Basal works, prior to geocomposite deployment
Construction IssuesConstruction works
Basal works, deployment of geocomposite, GCL and geomembrane
Construction IssuesConstruction works
Basal works, deployment of geocomposite
Construction IssuesConstruction works
Basal works, deployed GCL
Construction IssuesConstruction works
Basal works, deployment of geomembrane
Construction IssuesConstruction works
Basal works, hydraulic bund
Construction IssuesConstruction works
Perimeter leachate trench
Construction IssuesConstruction works
Tested to capacity for Reservoir Act sign off, 2008
Construction IssuesConstruction works
Completed lagoon, 2008
Construction IssuesGroundwater monitoring
piezometers installed at a number of locations to monitor PWP
Construction IssuesGroundwater monitoring
leachate level in lagoon
Construction IssuesGroundwater monitoring
ru typically between 0.2 and 0.3
Construction IssuesSettlement monitoring
Temporary vertical and horizontal stations at toe of embankment
Permanent stations at top of embankment
Construction IssuesSettlement monitoring
Construction IssuesSettlement monitoring
3
4
5
6
7
8
9
1-Jan-03 1-Apr-03 1-Jul-03 1-Oct-03 1-Jan-04 1-Apr-04 1-Jul-04 1-Oct-04 1-Jan-05
Lev
el (m
aO
D)
Leachate level in lagoon
Approximate elevation of top of bund –between 7.6m and 8.0mAOD
Elevation of foundation layer
Construction IssuesCQA
Quality assurance and conformance testing of all materials:
• Separator geotextiles
• Reinforcing elements
• Lining elements
• All soils
In accordance with the approved CQA Plan
Construction Issues
OverviewBackground
Site details
Design philosophy
Design issues
Construction issues
Conclusions
ConclusionsReview of the design issues relating to the construction of a leachate storage lagoon has been presented
Geotechnical and geoenvironmental applications of geosynthetics have been used to ensure the short and long term stability of the perimeter embankment of the lagoon and to maximize containment capacity
Design revised during construction as part of a Value Engineering approach
Lagoon now tested by filling to capacity
Conclusions
Soil retentionGeocomposite
Secondary component of composite linerGeosynthetic Clay Liner
Primary component of composite linerGeomembrane
DrainageGeopipes
ReinforcementGeogrid
DrainageGeocomposite
UV protectionGeotextile
Reinforcement and DrainageGeotextile
FunctionGeosynthetic Material
A range of geosynthetics was used in the project
This project could not have been constructed without the use of these materials
AcknowledgementsVeolia Environmental Services (formerly Cleanaway)
Steve Smith (now Golder Associates)
John Bowers
Nick Sinclair
Panel Engineers
Michael Kennard (retired)
George Hallowes (deceased)
Chris Hoskins