design and construction of a reinforced soil embankment · pdf filedesign and construction of...

90
Design and construction of a reinforced soil embankment on soft soil Russell Jones, Golder Associates Gareth Swift, University of Salford

Upload: vothien

Post on 06-Mar-2018

243 views

Category:

Documents


9 download

TRANSCRIPT

Page 1: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design and construction of a reinforced soil embankment on soft soil

Russell Jones, Golder Associates

Gareth Swift, University of Salford

Page 2: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

OverviewBackground

Site details

Design philosophy

Design issues

Construction issues

Conclusions

Page 3: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

BackgroundIntroduction

Site is located south of Basildon in Essex

Bounded by:

• Wat Tyler country park on western boundary

• Pitsea Marshes (SSSI) along the northern boundary

• East Haven Creek along southern boundary (Thames beyond)

Page 4: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Background

Pitsea landfill site located south of Basildon in Essex, and covers an area of approx.284ha (>50ha currently operational)

Introduction

Page 5: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

BackgroundIntroduction

Paper and presentation deals with design and construction issuesrelating to a large leachate lagoon to be constructed on soft, compressible soils

Design carried out in June 2002

Construction between July 2002 and January 2003

Lagoon filled to capacity March 2008

Final Certificate issued by the Panel Engineer July 2008

Page 6: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

BackgroundClient brief:

Minimum leachate capacity of 150,000m3

Maximum cost of build £1.3mill

Maximum bund height 8mAOD (planning constraint)

……needs to be buildable!

Page 7: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

BackgroundAdditional design constraints:

Ensure stability

Minimise soil imports

Maximise lagoon area (hence, minimise bund height)

Minimise excavation in to existing soils

Page 8: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

BackgroundAdditionally…

Satisfy requirements of Reservoir Act 1975

the Act applies to Large Raised Reservoirs, defined as:

‘being designed to hold or capable of holding more than 25,000m3 of water as such above the natural level of any part of the land adjoining the reservoir (including the bed of any stream)’

Page 9: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

OverviewBackground

Site details

Design philosophy

Design issues

Construction issues

Conclusions

Page 10: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Site DetailsGround conditions

The area is relatively even but groundwater levels close to, or at, the ground surface

Waste dating from the 1950’s underlies the site in a layer between 1m and 7m thick

Waste comprises ash, clinker, glass, cans in hydraulic continuity with the surrounding landfill

This overlies a generally soft stratum of alluvial clays and sands (mv 0.2 – 0.8m2/kN).

Page 11: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Site DetailsGround conditions

A similar, but earlier, lagoon encountered significant difficulties during construction associated with the high groundwater levels and the trafficability of the waste and the soft alluvial material.

Page 12: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Site DetailsGround conditions

Page 13: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

OverviewBackground

Site details

Design philosophy

Design issues

Construction issues

Conclusions

Page 14: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyOriginal design philosophy

Reducing the existing ground level of approximately 3 m AOD to a minimum formation level of 1.0 m AOD

Pumping and dewatering required (estimated quantity 20,000 to 75,000m3)

Forming embankment slopes of 1v:4h utilising the excavated waste

Using a single ethylene inter-polymer alloy geomembrane liner on both the base and embankment slopes

Liner manufactured to a specific prefabricated size and shape tosuit the design

Page 15: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyOriginal design philosophy

Page 16: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyOriginal design philosophy

Page 17: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyOriginal design philosophy

Ground conditions are poor at best:

• Groundwater/leachate levels at or near to the ground surface; and

• Material to be excavated to produce a formation level comprised 1950’s waste of questionable engineering integrity

Dewatering logistically difficult due to up-gradient landfill (with leachate)

Single geomembrane liner not the most effective barrier

Tenderers’ comments

Page 18: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyProposed design

No excavation

• Reinforced basal platform 20 m wide by 700 mm thick constructed at the existing ground level

Steeper face angles

• Reinforced soil perimeter embankment, 5.5 m high

• External side slopes 1v:2h

• Internal side slopes 1v:1v

Page 19: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyOriginal design philosophy

Page 20: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyProposed design

Page 21: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyProposed design

Page 22: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyProposed design

Base area of approximately 32,000 m2 lined with a composite lining system

• 2 mm thick Linear Low Density Polyethylene (LLDPE) sheet

• Geosynthetic clay liner (GCL)

Underdrainage geocomposite drainage layer to limit hydraulic pressures from the leachate and gas

Lining of the perimeter embankment with

• 2 mm thick LLDPE geomembrane

• Geocomposite drainage layer connected to a piped drainage system

Page 23: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design PhilosophyProposed design

Page 24: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

OverviewBackground

Site details

Design philosophy

Design issues

Construction issues

Conclusions

Page 25: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesProposed design

Since material was limited to on-site sources, the quality would be variable

Side slopes would be steep in order to achieve capacity

• Geosynthetic reinforcement, geotextile rather than geogrid to aid dissipation of pore pressures

• Primary geotextile reinforcement

• Secondary geogrid reinforcement

Granular material used for foundation layer

Cohesive material used for most of embankment but granular material used for upper section

Page 26: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesProposed design

Page 27: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesProposed design

Page 28: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesReinforcement details

4Fornit 20/20

3Stabilenka 100/50Class 6I, 6J, 7B, 7C or 7D material

Embankment

1Tensar 120RECrushed concrete finesBasal layer 2

1Tensar 160RE75 mm crushed concrete (min 50 kN 10 % fines)

Basal layer 1

No. of Layers

ReinforcementMaterialLayer

Page 29: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesSettlement

Final top of embankment = 7.5m AOD

Constructed to = 8m AOD due to anticipated settlement

Page 30: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design Issues

mv = 0.2m2/MNk = 1 x 10-8m/s

0.2 to 0.8

25019Alluvium

Beneath northern embankment

0.325016Old waste

Beneath main slope

0.525016Old waste

-0.130018Foundation layer

-0.124020Embankment fill

Additional information

ruφ′(deg)

c′(kPa)

γb

(kN/m3)Material

Material parameters

Page 31: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesValue Engineering

Time constraints

Design optimisation during construction

Supported by field trials where possible

ECC form of contract

Page 32: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesValue Engineering

NEC/Engineering and Construction Contract

Six Main Options

• Option A - Priced with Activity Schedule

• Option B - Priced with BQ

• Option C - Target with Activity Schedule

• Option D - Target with BQ

• Option E - Cost Reimbursement

• Option F - Management Contract

Page 33: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesContract

NEC/Engineering and Construction Contract

Six Main Options

• Option A - Priced with Activity Schedule

• Option B - Priced with BQ

• Option C - Target with Activity Schedule

• Option D - Target with BQ

• Option E - Cost Reimbursement

• Option F - Management Contract

Page 34: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesStability

A key factor in the design of the perimeter embankments is theirstability

• Internal – Inside face and outside face

• External – Global failure and siding

Major issue is the development of pore water pressure in the sub-grade due to embankment construction

• Slope/w and Seep/w used to examine the effects of pore water pressure on stability

• Results indicate that the rate of build up and dissipation was critical to stability

Page 35: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesStability

Piezometers used on site to monitor pore water pressures

Construction of toe berms would improve short term stability

• Factor of safety >1.3 if ru <0.7

• Toe berms allow increase in ru to 0.8

Page 36: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesStability

Page 37: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesStability

700mm thick reinforced foundation layer:•300mm drainage layer •400mm stability layer

Page 38: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesStability

Typical output:

1.509

Top Layer of Fornit 20/20

3 Layers of Stablenka

Top Layer of 120RELower Layer of 160RE

10 kPa

Page 39: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesGroundwater

Geotextile reinforcement allows dissipation of pore pressures inembankment fill

Geocomposite allows dissipation of pore pressures beneath the lagoon

75mm crushed concrete layer allows dissipation of pore pressures beneath the embankment

Page 40: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Design IssuesEnvironmental considerations

Leachate containment

• 2mm LLDPE geomembrane

• GCL

• UV protection geotextile

Underdrainage

• Complete system required to remove gases beneath lining system

• 12mm geocomposite

Page 41: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

OverviewBackground

Site details

Design philosophy

Design issues

Construction issues

Conclusions

Page 42: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Groundwater monitoring

Settlement monitoring

Page 43: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Poor ground conditions

Page 44: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Generally, a flatlying area in a floodplain

Page 45: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Page 46: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Relatively flat formation level (3.0mAOD) required:

• Removal of bushes/trees

• Re-profiling of hummocky areas

• Elevated ground in NE was excavated

• Low area in south backfilled

Existing leachate trench backfilled

Dewatering, where required

Installation of piezometers

Construction of cut-off trench

Page 47: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Page 48: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal layer

• Separator geotextile on existing ground

• 9 mm Drainage geocomposite

• 300 mm thick drainage layer

• Separator geotextile on drainage layer

• 400 mm thick stability layer including two layers of geogridreinforcement

Page 49: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Foundation layer, first layer of geogrid

Page 50: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Foundation layer, second layer of geogrid

Page 51: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Foundation layer

Page 52: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Reinforced embankment

• Compacted general fill material (Class 6I, 6J, 7B, 7C or 7D)

• Geotextile primary reinforcement

• Geogrid secondary reinforcement

Page 53: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Lining system

• Drainage geocomposite

• Geomembrane

• Perforated pipe

• Soil retention geocomposite

Page 54: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Page 55: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Installation of perforated pipe at toe of inside slope

Page 56: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment starting to be constructed

Page 57: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works continuing

Page 58: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works continuing, inside face

Page 59: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works continuing, outside face

Page 60: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, becoming difficult with cohesive fill

Page 61: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Trafficability concerns…

Page 62: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, revised fill

Page 63: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, revised fill, impact on geotextile reinforcement

Page 64: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, revised fill, impact on geogrid reinforcement

Page 65: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, working in the winter

Page 66: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, geocomposite and geomembrane deployment

Page 67: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, uv protection geotextile and tyre wave wall

Page 68: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Embankment works, soil retention geocomposite

Page 69: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal works, prior to geocomposite deployment

Page 70: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal works, deployment of geocomposite, GCL and geomembrane

Page 71: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal works, deployment of geocomposite

Page 72: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal works, deployed GCL

Page 73: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal works, deployment of geomembrane

Page 74: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Basal works, hydraulic bund

Page 75: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Perimeter leachate trench

Page 76: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Tested to capacity for Reservoir Act sign off, 2008

Page 77: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesConstruction works

Completed lagoon, 2008

Page 78: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesGroundwater monitoring

piezometers installed at a number of locations to monitor PWP

Page 79: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesGroundwater monitoring

leachate level in lagoon

Page 80: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesGroundwater monitoring

ru typically between 0.2 and 0.3

Page 81: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesSettlement monitoring

Temporary vertical and horizontal stations at toe of embankment

Permanent stations at top of embankment

Page 82: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesSettlement monitoring

Page 83: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesSettlement monitoring

3

4

5

6

7

8

9

1-Jan-03 1-Apr-03 1-Jul-03 1-Oct-03 1-Jan-04 1-Apr-04 1-Jul-04 1-Oct-04 1-Jan-05

Lev

el (m

aO

D)

Leachate level in lagoon

Approximate elevation of top of bund –between 7.6m and 8.0mAOD

Elevation of foundation layer

Page 84: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction IssuesCQA

Quality assurance and conformance testing of all materials:

• Separator geotextiles

• Reinforcing elements

• Lining elements

• All soils

In accordance with the approved CQA Plan

Page 85: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Construction Issues

Page 86: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

OverviewBackground

Site details

Design philosophy

Design issues

Construction issues

Conclusions

Page 87: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

ConclusionsReview of the design issues relating to the construction of a leachate storage lagoon has been presented

Geotechnical and geoenvironmental applications of geosynthetics have been used to ensure the short and long term stability of the perimeter embankment of the lagoon and to maximize containment capacity

Design revised during construction as part of a Value Engineering approach

Lagoon now tested by filling to capacity

Page 88: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Conclusions

Soil retentionGeocomposite

Secondary component of composite linerGeosynthetic Clay Liner

Primary component of composite linerGeomembrane

DrainageGeopipes

ReinforcementGeogrid

DrainageGeocomposite

UV protectionGeotextile

Reinforcement and DrainageGeotextile

FunctionGeosynthetic Material

A range of geosynthetics was used in the project

This project could not have been constructed without the use of these materials

Page 89: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

AcknowledgementsVeolia Environmental Services (formerly Cleanaway)

Steve Smith (now Golder Associates)

John Bowers

Nick Sinclair

Panel Engineers

Michael Kennard (retired)

George Hallowes (deceased)

Chris Hoskins

Page 90: Design and construction of a reinforced soil embankment · PDF fileDesign and construction of a reinforced soil embankment on soft soil ... slope Old waste 16 0 25 0 ... Design and

Conclusion slide

Thank you for your attention

[email protected] [email protected]