design and execution of jack-in piles in malaysia” at the 1-day
TRANSCRIPT
G&P Geotechnics Sdn Bhd
Ir. Chow Chee MengG&P Geotechnics Sdn Bhd (Malaysia)
31st August 2015
DESIGN AND EXECUTION OF JACK-IN PILES IN MALAYSIA
One Day Seminar on
JACK-IN FOUNDATION PILES –
GOOD PRACTICES AND ITS APPLICATIONS
Organized by Geotechnical Society of Singapore (GEOSS)
Bored Pile Contractors/Engineers working with Bored Pile
Contractors?
PLEASE RAISE YOUR HAND!!!
Jack-in Pile Contractors/Engineers working with Jack-in Pile
Contractors?
PLEASE RAISE YOUR HAND!!!
Engineering consultants / Government engineers?
PLEASE RAISE YOUR HAND!!!
SCENARIO A SCENARIO B
PROCEED WITH PRESENTATION!
Are we a victim of confirmation bias on selection of foundation system?
In psychology and cognitive science, confirmation bias (or confirmatory bias) is a tendency to search for or interpret information in a way that
confirms one's preconceptions, leading to statistical errors.
Good girl?
Good academic results?
Good wife material?
What is our immediate opinion?
We like this picture more!!!
G&P Geotechnics Sdn Bhd
INTRODUCTION
Jack-in pile has been adopted in Malaysia since early 1990s
Currently, 600mm diameter spun pile with working load up to 3000kN adopted for high-rise developments up to 45-storeys
G&P Geotechnics Sdn Bhd
HIGH CAPACITY JACK-IN PILE MACHINE
G&P Geotechnics Sdn Bhd
HIGH CAPACITY JACK-IN MACHINE
•Maximum jack-in force up to 7000kN
•Width of machine up to 13.5m
•Required clearance for piling works: 5.5m to 6.9m (centre jacking)
•Clearance can be reduced to 1.5m to 2.0m for side jacking but maximum jack-in force reduced to approx. 3500kN
G&P Geotechnics Sdn Bhd
G&P Geotechnics Sdn Bhd
G&P Geotechnics Sdn Bhd
G&P Geotechnics Sdn Bhd
Typical schematic of high capacity jack-in pile machine
G&P Geotechnics Sdn Bhd
SMALLER CAPACITY JACK-IN PILE MACHINE
G&P Geotechnics Sdn Bhd
Maximum Jack-in Force = 700kNSize = 4.8m x 3.6m
G&P Geotechnics Sdn Bhd
Maximum Jack-in Force = 1500kNSize = 6.6m x 5.0m
G&P Geotechnics Sdn Bhd
PROS & CONS
PROS:
Low noise and vibration
Faster construction rates (vs. bored piles)
Cleaner sites (vs. bored piles)
Relatively clean site compared to bored piles!
G&P Geotechnics Sdn Bhd
CONS
Strong and flat piling platform required
Larger working area required (vs. driven piles/bored piles)
Limited pile size (vs. bored piles)
Unable to go through intermittent hard layers/boulders (vs. bored piles)
PROS & CONS
G&P Geotechnics Sdn Bhd
Comparisons JACK-IN PILE DRIVEN PILE BORED
PILE Cyclic load during pile installation
Less cycles compared to driven pile
Number of cycles more especially
for long piles
N.A.
Termination criteria
Static (pseudo) load imposed onto
pile head
Dynamic load imposed onto pile
head
Based on SI information
Variables affecting efficiency of load transfer during pile installation
1. Hydraulic system of jacks
2. Calibration of pressure gauge
1. Efficiency of hammer, helmet, etc.
2. Hammer drop height
3. Cushion properties
4. Eccentricity of pile/hammer
N.A.
Verification of geotechnical capacity during installation
Relatively straightforward as loading rate is
slow
Indirect verification based
on dynamic analysis. Often
unreliable.
N.A.
Probability of pile damage during installation
Low High Depends on workmanship
G&P Geotechnics Sdn Bhd
GEOTECHNICAL CAPACITY OF PILES
G&P Geotechnics Sdn Bhd
GEOTECHNICAL CAPACITY OF PILES
Ultimate shaft resistance,fsu = Ksu x SPT-N (in kPa)
Ultimate base resistance,fbu = Kbu x SPT-N (in kPa)
Typically,Ksu = 2.5 to 3.0Kbu = 200 to 400 (clay to sand)
G&P Geotechnics Sdn Bhd
Design based on driven piles experience
Valid for jack-in pile design?
GEOTECHNICAL CAPACITY OF PILES
G&P Geotechnics Sdn Bhd
BEHAVIOUR OF JACK-IN PILES
G&P Geotechnics Sdn Bhd
BEHAVIOUR OF JACK-IN PILES
Rankine Lecture by Prof. Mark Randolph (2003):
•Bored piles – zero residual pressures
•End-bearing can only be mobilised at relatively large displacement
G&P Geotechnics Sdn Bhd
Driven and jacked in piles - significant residual pressures are locked in at the pile base during installation
Higher end-bearing can be mobilised at working load
BEHAVIOUR OF JACK-IN PILES
G&P Geotechnics Sdn Bhd
White & Lehane (2004):
Greater number of cycles during pile installation
larger reduction in shaft friction
BEHAVIOUR OF JACK-IN PILES
G&P Geotechnics Sdn Bhd
Reduction in shaft
resistance!!!
White & Lehane, 2004
G&P Geotechnics Sdn Bhd
Deeks, White & Bolton (2005):
The measured jacking force during installation indicates plunging capacity of the pile
BEHAVIOUR OF JACK-IN PILES
G&P Geotechnics Sdn Bhd
Jacked piles have a high base stiffness
Stiffness of jacked piles> 2 times stiffness of driven piles> 10 times stiffness of bored piles
BEHAVIOUR OF JACK-IN PILES
G&P Geotechnics Sdn Bhd
CASE HISTORIES
G&P Geotechnics Sdn Bhd
• Starting of Jack-In Pile system using large size pile in Malaysia (Year 1999)
• Installed through municipal dumping site with mine tailings overlying Karstic Kuala Lumpur Limestone bedrock.
• Adopted 450mm Spun Pile with Working Load of 1500kN
1st Site
G&P Geotechnics Sdn Bhd
1st Site
G&P Geotechnics Sdn Bhd
1st Site
G&P Geotechnics Sdn Bhd
1st Site
GRANITE FORMATIONCASE HISTORIES
G&P Geotechnics Sdn Bhd
Four sites in Kuala Lumpur and Selangor, Malaysia :
•Site A: 31-storey apartment•Site B: 45-storey apartment•Site C: 40 to 43-storey apartment•Site D: 15-storey apartment
Case Histories
G&P Geotechnics Sdn Bhd
Case Histories (Sites A to D)
• Pile size: 400mm to 600mm
• Pile working load: 1520kN to 3000kN
• All piles generally jacked to 2.0 times working load with holding time of 30-seconds (2 cycles)
G&P Geotechnics Sdn Bhd
• Silty SAND / sandy SILT overlying Granite Formation (weathered granite)
• Boulders encountered- Some piles installed after preboring
Case Histories (Sites A to D)
G&P Geotechnics Sdn Bhd
Site A
G&P Geotechnics Sdn Bhd
Site A
Granite Formation
G&P Geotechnics Sdn Bhd
Site C
Target Completion Mid 2011
G&P Geotechnics Sdn Bhd
Site D
G&P Geotechnics Sdn Bhd
Site B
G&P Geotechnics Sdn Bhd
Site B
G&P Geotechnics Sdn Bhd
Pile toe at hard weathered granite layer
Site B
G&P Geotechnics Sdn Bhd
Total of 22 static load tests carried out for the 4 sites
All piles selected for testing achieved minimum 2 times working load!!!
(No pile failed!)•No signs of plunging failure of pile•Settlement at working load: 3.04 – 9.88mm•Settlement at 2*WL: 6.96 – 22.22mm
Static Load Tests
G&P Geotechnics Sdn Bhd
Static Load Tests
• Pile as short as 6.5m tested with settlement at working load and 2*WL of 8.32mm and 19.73mm respectively
• Pile performance are satisfactory for piles where preboring have been carried out
• Termination criterion adopted adequate
G&P Geotechnics Sdn Bhd
Preboring through boulders
Boulders exposed after
preboring
G&P Geotechnics Sdn Bhd
Static Load TestsSite B
0 1 2 3 4 5 6 7 8 9 10111213141516171819202122PILE TOP SETTLEMENT (mm)
0200400600800
1000120014001600180020002200240026002800300032003400360038004000420044004600
APP
LIED
LO
AD
(kN
)
500mm Spun Pile, Pile length = 6.5m
G&P Geotechnics Sdn Bhd
Static Load TestsSite B
G&P Geotechnics Sdn Bhd
Static Load Tests
G&P Geotechnics Sdn Bhd
Termination criterion for jack-in piles in weathered granite:
“Jack the pile to 2.0 times of the design load for a minimum of two cycles. The corresponding pressure has to be held for minimum 30 seconds with settlement not exceeding 2mm”
Termination Criteria
G&P Geotechnics Sdn Bhd
Instrumented test piles Site C (3 Nos.)Site D (2 Nos.)
Piles instrumented using the Global Strain Extensometer method
Mobilised Resistance
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20DISPLACEMENT (mm)
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150M
OB
ILIS
ED S
KIN
FR
ICTI
ON
(kN
/m2 )
0.5m to 10.7m10.7m to 20.9m
600mm Spun Pile, Pile length = 21.4m(Nearest borehole, BH-20)
Site C
fsu = 5 x SPT-N (in kPa)
- conservative!!!
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
0 1 2 3 4 5 6 7 8 9 10DISPLACEMENT (mm)
0500
10001500200025003000350040004500500055006000650070007500800085009000
MO
BIL
ISED
EN
D-B
EARI
NG
RES
ISTA
NCE
(kN
/m2 )
600mm Spun Pile, Pile length = 21.4m(Nearest borehole, BH-20)
End-bearing not fully mobilised
Stiff end bearing response observed –
end-bearing mobilized with small toe displacement
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20DISPLACEMENT (mm)
0
25
50
75
100
125
150
175
200
225
250
275
300M
OB
ILIS
ED S
KIN
FR
ICTI
ON
(kN
/m2 )
0.5m to 5.75m5.75m to 14.75m14.75m to 20.75m20.75m to 23.0m
500mm Spun Pile, Pile length = 24.7m(Nearest borehole, BH-18)
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
fsu = 5 x SPT-N (in kPa)
- conservative!!!
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
0 1 2 3 4 5 6 7 8 9 10DISPLACEMENT (mm)
0500
100015002000250030003500400045005000550060006500700075008000
MO
BIL
ISED
EN
D-B
EAR
ING
RES
ISTA
NC
E (k
N/m
2 )
Stiff end bearing response observed –
end-bearing mobilized with small toe displacement
End-bearing not fully mobilised
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
0 2 4 6 8 10 12 14 16 18 20 22DISPLACEMENT (mm)
0
25
50
75
100
125
150
175
200
225
250
275
300M
OB
ILIS
ED S
KIN
FR
ICTI
ON
(kN
/m2 )
0.82m to 6.53m6.53m to 17.43m17.43m to 26.43m26.43m to 31.43m31.43m to 33.93m
600mm Spun Pile, Pile length = 34.8m(Nearest borehole, BH-5)
fsu = 5 x SPT-N (in kPa)
- conservative!!!
Site D
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
0 1 2 3 4 5 6 7 8 9 10DISPLACEMENT (mm)
020406080
100120140160180200220240260280300320340360380400
MO
BIL
ISED
EN
D-B
EAR
ING
RES
ISTA
NC
E (k
N/m
2 )
600mm Spun Pile, Pile length = 34.8m(Nearest borehole, BH-5)
End-bearing not fully mobilised
Stiff end bearing response observed –
end-bearing mobilized with small toe displacement
LIMESTONE FORMATIONCASE HISTORIES
G&P Geotechnics Sdn Bhd
Static Load Tests
0 5 10 15 20 25 30PILE TOP SETTLEMENT (mm)
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
6000
6500
7000
Legends:1st Cycle2nd Cycle3rd Cycle
Load-Settlement Curve for Pile Static Load Test
500mm Spun Pile, Pile length = 31.5m
500mm diameter spun pile
Pile working load = 2,300kN
1*WL
8mm
2*WL
16.5mm
3*WL
28.5mm
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
0 5 10 15 20 25 30DISPLACEMENT (mm)
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
150
160
170
180
190
200
MO
BILI
SED
SH
AFT
FRIC
TIO
N (k
N/m
2 )
Legends:1.0m to 9.0m9.0m to 19.5m19.5m to 27.5m27.5m to 31.0m
Mobilised Shaft Friction (Sunway)
500mm Spun Pile, Pile length = 31.5m(Nearest borehole, ABH-4)
fsu = 5 x SPT-N (in kPa)
- conservative!!!
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
0 1 2 3 4 5 6 7 8 9 10DISPLACEMENT (mm)
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
5500
6000
6500
7000
Mobilised End-Bearing Resistance (Sunway)
500mm Spun Pile, Pile length = 31.5m(Nearest borehole, ABH-4)
End-bearing not fully mobilised
Stiff end bearing response observed –
end-bearing mobilized with small toe displacement
ALLUVIAL DEPOSITSCASE HISTORIES
AP
PLI
ED
LO
AD
, kN
G&P Geotechnics Sdn Bhd
Static Load Tests
500mm diameter spun pile
Pile working load = 2,300kN
1*WL
11mm
2*WL
23mm
3*WL
44mm
Sudden structural failure of pile head!
MO
BIL
ISE
D S
HA
FT F
RIC
TIO
N (k
N/m
2 )
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
fsu = 5 x SPT-N (in kPa)
- conservative!!!
0 1 2 3 4 5 6 7 8 9 10DISPLACEMENT (mm)
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
1600
1700
1800
1900
2000
Mobilised End-Bearing Resistance (GEMA)
500mm Spun Pile, Pile length = 46.0m(Nearest borehole, BH-4)
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
End-bearing not fully mobilised
Stiff end bearing response observed –
end-bearing mobilized with small toe displacement
G&P Geotechnics Sdn Bhd
SUMMARY
G&P Geotechnics Sdn Bhd
• Termination criterion of jack to 2 times pile working load and holding time of 30-seconds (two to three cycles) with settlement not exceeding 2mm is satisfactory
• Ultimate pile capacity is a function of jack-in force during pile installation (consistent with other findings, e.g. Deeks et al., 2005)
SUMMARY
G&P Geotechnics Sdn Bhd
• Traditional correlations of skin friction based on driven piles (e.g. fs = 2.5*SPT-N) is too conservative for jack-in piles
• Conservative estimate based on instrumented test results:- Ultimate skin friction, fs ~ 5*SPT-N (expected to be even higher – to be verified with more test results)
SUMMARY
G&P Geotechnics Sdn Bhd
SUMMARY
•Jack-in piles demonstrates higher skin friction possibly due to:
- Less disturbance during installation -friction fatigue phenomenon (e.g. White & Lehane, 2004)
- Locked-in pressure (residual pressure) effect (e.g. Randolph, 2003)
G&P Geotechnics Sdn Bhd
SUMMARY
•Jack-in piles demonstrates stiffer end bearing response
- Consistent with Deeks, White & Bolton (2005):
Stiffness of jacked piles> 2 times stiffness of driven piles> 10 times stiffness of bored piles
METASEDIMENTARY FORMATION
CASE HISTORIES
G&P Geotechnics Sdn Bhd
NusajayaPROPOSED 4 BLOCKS OF 12 & 24 – STOREY RESIDENTIAL APARTMENTS (488 UNITS) AT PHASE C1B, EAST LEDANG, JOHOR
G&P Geotechnics Sdn Bhd
Static Load Tests
600mm diameter spun pile
Pile working load = 3,000kN
Prebored depth = 9.0mPile length = 9.5m
Mobilisation of end-bearing?
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
fsu 2 x SPT-N (in kPa) of original subsoil
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
End-bearing less stiff compared to behavior observed in granite formation, etc. Possibly due to
behavior of weathered sandstone/siltsone.
End-bearing mobilized still relatively high compared to
bored piles/driven piles!
G&P Geotechnics Sdn Bhd
Puteri HarbourPROPOSED MIXED DEVELOPMENT @ PUTERI HARBOUR ON LOT CS2, COMMERCIAL SOUTH, NUSAJAYA, JOHOR3 blocks up to 35-storey high
G&P Geotechnics Sdn Bhd
Puteri Harbour
Traders Hotel
CS2 – Jack-in Piles
CS1 – Driven Piles
G&P Geotechnics Sdn Bhd
CS-2Jack-in Piles
G&P Geotechnics Sdn Bhd
Static Load Tests
600mm diameter spun pile
Pile working load = 3,000kN
1*WL
5.5mm
2*WL
15mm
Maximum test load achieved 8,000kN (2.7*WL)
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
Prebored length = 13.0mInstalled pile length = 15.0m
Significant shaft resistance mobilised even after preboringfsu = 5 x SPT-N (in kPa)????
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
End-bearing less stiff compared to behavior observed in granite formation, etc. Possibly due to
behavior of weathered sandstone/siltsone.
End-bearing mobilized still relatively high compared to
bored piles/driven piles!
G&P Geotechnics Sdn Bhd
CS-1Driven Piles
G&P Geotechnics Sdn Bhd
Static Load Tests
400mm x 400mm RC square pile
Pile working load = 2,000kN
1*WL
8.5mm
2*WL
20mm
Maximum test load achieved 4,700kN (2.3*WL)
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
Prebored length = 12.0mInstalled pile length = 14.3m
Shaft resistance still influenced by original subsoil but magnitude less compared to jack-in pilesfsu = 2 x SPT-N (in kPa)????
G&P Geotechnics Sdn Bhd
Mobilised (Base) Resistance
End-bearing less stiff compared to behavior observed in granite formation, etc. Possibly due to
behavior of weathered sandstone/siltsone.
End-bearing mobilized still relatively high compared to
bored piles!
G&P Geotechnics Sdn Bhd
Static Load Tests
450mm x 450mm RC square pile
Pile working load = 2,500kN
1*WL
12mm
Maximum test load achieved 3,000kN (1.2*WL)
G&P Geotechnics Sdn Bhd
Mobilised (Shaft) Resistance
Prebored length = 12.0mInstalled pile length = 13.1m
Shaft resistance influenced by original subsoil but significant less compared to jack-in pilesfsu = 2 x SPT-N (in kPa)????
G&P Geotechnics Sdn Bhd
Mobilised (Base) ResistanceEnd-bearing less stiff compared to behavior observed in granite formation, etc. Possibly due to
behavior of weathered sandstone/siltsone.
End-bearing affected by softer layer beneath toe?
Re-testing carried out on another pile with deeper
preboring length of 15m (pile length 18m) but still failed at
1.3*WL
G&P Geotechnics Sdn Bhd
SUMMARY
G&P Geotechnics Sdn Bhd
• Noticeable differences in jack-in pile behavior between granite/sandy soil vs. metasedimentary formation (sandstone/siltsone) with preboring
• End-bearing response stiffer in granite/sandy soil without preboring
• End-bearing response for jack-in piles in metasedimentary formation still stiffer compared to bored piles and driven piles
SUMMARY
G&P Geotechnics Sdn Bhd
0 1 2 3 4 5 6 7 8 9 10DISPLACEMENT (mm)
0500
100015002000250030003500400045005000550060006500700075008000
MO
BIL
ISED
EN
D-B
EAR
ING
RES
ISTA
NC
E (k
N/m
2 )
Granite formation(without preboring)
Metasedimentary formation(with preboring)
G&P Geotechnics Sdn Bhd
• Due to heterogeneous characteristics of metasedimentary formation and effect of preboring, end-bearing resistance highly variable. Conservative assumptions of ultimate end-bearing resistance of 10,000kPa for pile design in metasedimentary formation with preboring– As opposed to granite formation where pile
capacity is a function of jack-in force during pile installation
SUMMARY
G&P Geotechnics Sdn Bhd
• Any difference between jack-in pile and driven pile?
• Results indicate shaft friction for jack-in pile higher than driven pile (approximately 2 times higher)
• Possibly affected by bigger prebored zone in driven square piles
SUMMARY
G&P Geotechnics Sdn Bhd
Jack-in Pile
Prebored length = 13.0mInstalled pile length = 15.0m
Significant shaft resistance mobilised even after preboringfsu = 5 x SPT-N (in kPa)????
G&P Geotechnics Sdn Bhd
Driven Pile
Prebored length = 12.0mInstalled pile length = 14.3m
Shaft resistance influenced by original subsoil but significant less compared to jack-in pilesfsu = 2 x SPT-N (in kPa)????
G&P Geotechnics Sdn Bhd
• Shaft friction after preboring very low or negligible?
– Shaft friction is a function of original subsoil even after preboring
– For jack-in pile, mobilized shaft friction still significant and fs ranges from 2*SPT-N to 5*SPT-N!
SUMMARY
G&P Geotechnics Sdn Bhd
CONCLUSION
G&P Geotechnics Sdn Bhd
• Jack-in pile can be an economical foundation system for high-rise buildings
• Behaviour of jack-in piles and driven piles different
– Pile length for driven piles would have to be longer to mobilize similar geotechnical capacity due to lower shaft friction and lower base stiffness
– Shaft friction mobilized in granite formation/sandy subsoil for jack-in pile can be conservatively assumed to be 5*SPT-N (likely to be higher subject to further test results)
CONCLUSION
G&P Geotechnics Sdn Bhd
• For granite formation/sandy subsoil:– Termination criterion of jack to 2 times pile
working load and holding time of 30-seconds (two to three cycles) with settlement not exceeding 2mm is satisfactory
– Ultimate pile capacity is a function of jack-in force during pile installation (consistent with other findings, e.g. Deeks et al., 2005)
CONCLUSION
G&P Geotechnics Sdn Bhd
• For metasedimentary formation:– Due to heterogeneous characteristics of
metasedimentary formation and effect of preboring, end-bearing resistance highly variable. Geotechnical capacity checks should be carried out with ultimate end-bearing resistance of 10,000kPa
• Significant shaft resistance is still mobilized after preboring for jack-in pile and it is still a function of original subsoil
CONCLUSION
G&P Geotechnics Sdn Bhd
• Jack-in Piles not suitable in soft ground?
• Jack-in Piles not suitable in limestone?
• Jack-in Piles not suitable for high-rise?
• Jack-in Piles less reliable compared to bored piles?
QUESTIONS TO PONDER
G&P Geotechnics Sdn Bhd
THANK YOU