Design and Function of Packaging Lines Addressing the Risk of Cross Contamination L. A. Goff, Director of Quality Assurance Pharma Packaging and Labeling Conference Feb. 2017

Upload: lykhuong

Post on 23-Apr-2018

227 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Design and Function of Packaging Lines

Addressing the Risk of Cross Contamination

L. A. Goff, Director of Quality Assurance

Pharma Packaging and Labeling Conference Feb. 2017

Page 2: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Addressing Cross-Contamination in

Packaging

Agenda

1. Pre-existing cross contamination risks

2. Cross-contamination risks during

renovations

3. Final design to address cross-

contamination risks

2

Page 3: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Pre-existing Challenges: • Bulk/component

staging area • Common hallways • Product exposure • Fit & Finish • Lack of full

segregation btw/Pack Lines

Page 4: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

• Shared wash/clean rooms • Material flow (dirty/clean) • Wood pallets

Page 5: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Renovation Nation: Design Objectives & No Drug

Shortages

• Meet or exceed ISPE guidelines for Fit & Finish

• Deliver fully segregated packaging lines • Identify and Mitigate risks from cross

contamination • Deliver solution to address future

Serialization and Aggregation requirements • DO NOT ADVERSLY IMPACT ON-GOING

PACKAGING AND MANUFACTURING OPERATIONS

5

Page 6: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

6

The Challenge – renovate while continuing to pack, analogous to living in your house while completely renovating the kitchen

Page 7: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Mitigating Cross-contamination Risks during

Construction

• Containment Plans

o Hard containment walls vs. plastic

o Negative pressure to keep particulate matter inside construction area – directly exhausted to outside

o Magnehelic gauge to confirm airflow

o Monitored by QA daily for compliance to plan

o Air-monitoring for VP and NVP

• Gowning requirements for construction zones

Page 8: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

8

Major demolition

Page 9: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Containment plans designed to mitigate risks associated with construction activities.

Page 10: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

10

International Society of Pharmaceutical Engineers (ISPE) Area Designations

Page 11: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Design & Functionality of Packaging Lines

• Fully segregated packaging lines • Fill Rooms and Secondary Pack separated by PALs and

MALs • Use of “Bubble” Airlocks • Fill rooms w/dedicated HVAC systems single pass

w/appropriate ACH • Product exposure – only in Fill Room • Gowning changes when transitioning from Grey to White

zones • Gowning changes when transitioning to new Product Family • Smooth walls, ceilings and solid color floor for ease of

cleaning • Local extract at Case Packer to mitigate corrugate dust • Filler upgrades for the detection of foreign tablets • Elimination of wood pallets in GMP space • Submitted for ISP Facility of the Year Award

11

Page 12: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Blister suite prior to packaging line installation

Page 13: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Kanban

Page 14: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

• Improved capabilities to confirm tablet quality

• Fill room (Primary Pack) enhancements mitigates risk of cross-contamination

Page 15: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Finished goods leaving line in cases

Page 16: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Central Palletizer

Page 17: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

PA-5: new Formulation Suite

Page 18: Design and Function of Packaging Lines - Arena … · Design and Function of Packaging Lines ... • Meet or exceed ISPE guidelines for Fit & ... • Gowning requirements for construction

Questions???