design and operation of heap leach pads · the design and operation of heap leach pads: Ædesign...

42
Design and Operation of Heap Leach Pads By: John F. Lupo, Ph.D.

Upload: others

Post on 30-Oct-2019

31 views

Category:

Documents


1 download

TRANSCRIPT

Design and Operation of Heap Leach Pads

By:

John F. Lupo, Ph.D.

Purpose of Presentation

Summarize advancements made in the design and operation of heap leach pads:

Design and construction of leach pads and working with operations over the last 20 yearsWorking with difficult ore material types (saprolite, laterite, agglomerated ore, etc)Construction and operational problems in harsh environments (high rainfall, freezing temperatures, heat, etc).

Subset of Topics Covered

Leach Pad ConfigurationLiner System DesignOre Properties TestingOperational Considerations

Leach Pad ConfigurationGeneral Overview

Leach Pad Configuration

Pad Configuration Types:Dedicated, single use pad (“standard”leach pad)On/Off or Reusable PadValley FillHybrid

Considerations:⎤ Ore material properties (leaching characteristics, durability, etc.)⎤ Water balance⎤ Land availability and ground slope⎤ Project cost (capital and operating)

Single Use Pad

Single Use Pad

Suitable for variable ore types and leach cycle times. Typically large area for leach pad. Pad area based on ore production, leaching cycle time, ore “aging”, etc. Flat topography to maintain geotechnical stability.Large storm event pond. Low initial capital costs.Incremental pad expansion costs must be considered in project cost.

On/Off Pad

On/Off Pad

Suitable for ore with short leach cycles and consistent leaching characteristics.Areas with limited flat terrain.Requires a rinsed ore site/pad.Durable “high-stress” liner system.Practiced in wide range of climate conditions.Smaller storm pond.Costs: double handling of ore, rinsing system, rinsed ore storage.

Valley Fill Pad

Valley Fill Pad

Best suited for hard, durable ore with good drainage. Can accommodate extended leach times.Used in steep terrain (slopes up to 40%).Internal solution storage reduces external pond requirements.Robust liner system (high hydraulic head and ore loads).Retaining structure for confinement of heap.High upfront capital cost.

Hybrid Pads

Combination dedicated, single use pad with partial internal solution storageSingle use pad combined with on/off padValley fill pad with a portion used as an on/off padSide-hill leach padsDump leach (no liner)

Liner System Design

Liner Design Advancements

Experience with geosynthetics under high loads and harsh conditionsOperation of heap leach pads with significant ore loads (+130 m)Construction and operation of very large leach pads (+ 1.5 billion tonnes and covering 10 km2 across varying foundation materials)Solution collection pipe performance under high ore load

Liner Design Components

Foundation materialsUnderliner soilsGeomembrane linerOverliner materials (drainage and/or protection layers)Solution collection/air injection piping

Not normally

considered liner

design

Strong interaction between each component and the overall system.

Construction Quality Assurance program needed to achieve good liner performance

Typical Single Composite Liner

Overliner Layer:-Drainage/protection layers-Solution collection pipes-Air injection pipes

Geomembrane

Underliner

Foundation

Ore

Typical Double Composite Liner

Secondary Geomembrane

Underliner Foundation

PrimaryGeomembraneLeak Detection Layer

Ore

Overliner Layer:-Drainage/protection layers-Solution collection pipes-Air injection pipes

Foundation Design Considerations

Heap stabilitySolution drainage/recoveryPerformance of geomembranePerformance of solution pipes

Underliner Design Considerations

Seepage controlEnvironmental impactEconomic impact

Interaction with geomembrane linerPrefer compacted native soil with a minimum saturated hydraulic conductivity of 1 x 10-8 m/s (World Bank Standard)Admixtures maybe consideredGeosynthetic Clay Liner (GCL) –limited

Underliner

40% slope

Geomembrane Considerations

Geosynthetics preferred over other liner materials (asphalt, concrete, etc).Typical: HDPE, LLDPE, and PVC (smooth and textured)Overall seepage control (environmental & economic issues)Foundation settlementPuncture by ore load and traffickingHeap stability (slippage along interface)

Geomembrane Liner Testing

Load Testing: Compatibility of geomembrane liner with rest of liner system under anticipated ore loadsInterface Shear: Shear strength of interface for heap stability analysis

Geomembrane Liner Puncture

Geomembrane Interface Shear

Overliner

Geomembrane

Underliner

Normal Stress

Shear Stress

Overliner Design Considerations

Protect geomembrane (ore loads, mine equipment trafficking, etc)Medium for solution collection, air injection, etcProtect solution collection/ air injection piping (ore loads, mine equipment trafficking, etc)Prefer native free-draining sand and gravels – durable materials.Hydraulic properties of overliner govern solution collection pipe design.

Overliner Placement

Note: Overliner placed directly over geomembrane and pipes

Ore Properties Testing

Material Test Types

Geomechanical propertiesHeap stabilityOre compressionSettlementOre durability

Hydraulic propertiesPercolationFlow versus ore loadDraindown moisture content (water balance and inventory)

Metallurgical testing (not covered)

Typical Geomechanical Tests

Unconfined Compression

Triaxial Compression

Direct Shear

Circular Failure

Block Failure

Tests simulate varying stress conditions within heap

Ore

Typical Hydraulic Tests

Column Tests:RecoveryPercolation rates Leaching parameters (time, concentration, etc)Moisture contents (drain down, leaching)

Load-Percolation:Sustainable percolation (unsaturated flow) under loadCompression of ore (settlement and density)

Load-Permeability:Saturated hydraulic conductivity under loadOre degradationOverliner characteristics

Hydraulic Testing

Column Tests

Load-Percolatio

n

Load-Permeabilit

y

Tests simulate varying hydraulic conditions within heap

Ore

Operational Considerations

Operational Issues

Ore stacking and schedulingLeach schedulingChemistry controlWater balanceCold or hot climate operationWet or dry climate operationDifficult ore types:

Low permeabilitySlow leachingAcid consuming/generating

Select Operational Issues

Wet Climates Positive water balance requiring storage and treatment of excess process solution. Dilution of solution grade.Ore heap instability due to high saturation and erosion

Low Permeability OreHeap instability due to high saturationPoor or delayed recoveryHigh inventory (lock-up in pore spaces)

Wet Climates

Operational Issues

Solution management/heap stability problem:Increase solution and storm pond sizes

Capital cost and land constraintsPump excess solutions onto the heap (“sponge” effect)

Does not reduce excess solution volumeRain Skirts / Covers

Capital costOperationally intensive during rainy season

Excess solution treatment/discharge

Rain Skirts

Rain Skirts

Low Permeability Ore

Operational Issues

Heap stability & recovery problem:Ore agglomeration

Controlling agglomeration process to provide consistent product (moisture important)

Maintain low heap height to preserve ore permeability

Capital cost and land constraintsBlending with more durable ore

Logistics of blending and controlInterlift liner systems

Capital costOperationally intensive

Interlift Liner

THANK YOU FOR YOUR TIME