design-build scope of services...design-build scope of services project no. 478968 gre-ir 675-3.10...

24
1 DESIGN-BUILD SCOPE OF SERVICES PROJECT No. 478968 GRE-IR 675-3.10 PID No. 85364 STATE OF OHIO DEPARTMENT OF TRANSPORTATION JERRY WRAY, DIRECTOR THIS SCOPE OF SERVICES MUST BE INCLUDED IN YOUR BID PACKAGE IN ORDER FOR YOUR BID TO BE CONSIDERED FOR AWARD OF THIS PROJECT. LETTING DATE TBD PRE-BID MEETING TBD SCOPE OF WORK. The Contractor’s Consultant shall provide for the engineering services, design, and preparation of detail construction plans for the construction of the proposed project. The Contractor shall provide for the furnishing of materials, construction and completion in every detail of all the work described in the Conceptual Documents and Scope of Services in order to fulfill the intent of the contract. Project Description: NOISE BARRIER PANEL REPLACEMENT

Upload: others

Post on 28-Jun-2020

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

1

DESIGN-BUILD

SCOPE OF SERVICES

PROJECT No. 478968

GRE-IR 675-3.10

PID No. 85364

STATE OF OHIO

DEPARTMENT OF TRANSPORTATION

JERRY WRAY, DIRECTOR

THIS SCOPE OF SERVICES MUST BE INCLUDED IN YOUR BID PACKAGE IN ORDER

FOR YOUR BID TO BE CONSIDERED FOR AWARD OF THIS PROJECT.

LETTING DATE

TBD

PRE-BID MEETING

TBD

SCOPE OF WORK.

The Contractor’s Consultant shall provide for the engineering services, design, and preparation of detail construction plans for the construction of the proposed project.

The Contractor shall provide for the furnishing of materials, construction and completion in every detail of all the work described in the Conceptual Documents and Scope of Services in order to fulfill the intent of the contract.

Project Description: NOISE BARRIER PANEL REPLACEMENT

Page 2: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

2

12/14/07 Rev 16

ODOT

DESIGN BUILD

SCOPE OF SERVICES

PID # _85364_____ State Project # 478968

County GRE Route IR 675 Section 3.10

Table of Contents

Section Page

1 Project Identification 3

1A Prima Facie Speed Limit 3 1B Railroad Coordination 3 1C Airway/Highway Clearance 3 2 Pre-bid Meeting 4 3 Addenda Process 4 4 Pre-qualification 4 5 Contractor’s Consultant 4 6 Scope of Work 57 Field Office 78 General Provisions for The Work 7 9 Environmental 11

10 Right of Way (ROW) 11 11 Utilities 11 12 Design and Construction Requirements : Maintenance Of Traffic (MOT) 12 13 Design and Construction Requirements : Location & Design 14 14 Design and Construction Requirements : Structures 15 15 Design and Construction Requirements : Traffic Control 15 16 Project Schedule Requirements 18 17 Plan Submittals and Review Requirements 18 18 Buildable Units 23 19 Index of Attachments 24

Page 3: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

3

1. PROJECT IDENTIFICATION

PID # 85364 State Project # 478968

County GRE Route IR 675 Section 3.10

Local Route Name _N/A_____

Highway Functional Classification & Federal Aid System Urban Interstate

Structure Identification: Bridge # GRE-675-0352L and GRE-675-0352R. Work on existing bridges should only involve replacing existing bridge mounted noise barrier panels (not the posts). Should modifications be required to any portion of the existing bridge to replace the existing bridge mounted noise barrier, the Design Build Team (DBT) will be required to submit the required modifications to ODOT for review and approval prior to performing the bridge mounted noise barrier replacement work.

Structure File Number: 2903296 for GRE-675-0352L and 2903318 for GRE-675-0352R

1.1 Design Designation: Traffic data provided by ODOT Office of Technical Services:

2010 2022 2030 Location ADT ADT ADT K D T24 TD GRE

I-675 s/o US 35 72300 80800 86500 0.10 0.56 0.06 0.04

1.2 Existing plans: Project does not involve new locations of noise barrier or relocations of any portion of existing noise barrier. Construction plans for the existing barrier have been posted in the following location for information only:

\\Ctrfs100\d08$\ExistingPlans\GRE-85364 (Update this location as needed)

These are NOT AS-BUILT PLANS. The Design-Build Team (DBT) is advised to verify the preceding referenced plans to determine if they accurately depict existing field conditions.

1A PRIMA FACIE SPEED LIMIT

NO REDUCTION IN THE POSTED SPEED LIMIT.

614 Work Zone Speed Limit Sign

NOT APPLICABLE.

Double Fines in Work Zones Sign

NOT APPLICABLE.

1B RAILROAD COORDINATION

NOT APPLICABLE.

1C AIRWAY/HIGHWAY CLEARANCE

Because there are existing airport facilities in close proximity to the project, an Airway/Highway Clearance analysis in accordance with ODOT L&D Manual Volume 3

Page 4: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

4

Section 1404 will be required. Review and approval of the analysis by ODOT will be required.

2 PRE-BID MEETING

**This section will be completed by the Offices of Estimating and of Contracts once the

necessary information has been processed.**

This meeting is to discuss and clarify all issues that the project may have.

Location : Date :

Time :

3 ADDENDA PROCESS

All questions prior to the letting date shall be directed in writing to: Name: PREBID

Phone number: 614-387-0739 Fax: 614-887-4444 E-mail: [email protected]

http://www.dot.state.oh.us/CONTRACT/prebid/prebid_questions.htm

4 PRE-QUALIFICATION

It is required that the bidder be an ODOT pre-qualified Contractor who has engaged the services of an ODOT pre-qualified Design Consultant Team to perform all the design and construction work required in these Conceptual Documents. If the Design Consultant and/or the Design Sub-Consultant(s) submitted do not meet all the required qualifications, the Office of Contracts may reject the contractor’s bid.

5 CONTRACTOR’S CONSULTANT

The Contractor must name the Design Consultant and all Design Sub-Consultant(s) in the space(s) provided below. The Contractor must list relevant prequalification categories for prime and sub-consultants to show that the prequalification requirements listed below are satisfied. All Consultant names and addresses must be the same as that on file with the Department. The following work types must be performed by members of the Design Consultant Team (combination of Consultant and Sub-Consultant(s)):

1) Non-Complex Roadway Design

2) Level 1 Bridge

3) Geotechnical Engineering and Geotechnical Laboratory

Design Consultant

Firm Name: __________________________________________________________________

Address: __________________________________________________________________

List work types the Consultant will perform: _______________________________________________

Design Sub-Consultant

Firm Name: ___________________________________________________________________

Address: ___________________________________________________________________

List work types the Sub-Consultant will perform: ____________________________________________

Page 5: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

5

Design Sub-Consultant

Firm Name: ___________________________________________________________________

Address: ___________________________________________________________________

List work types the Sub-Consultant will perform: ____________________________________________

Restrictions on Participation in Design-Build Contracts:

The Contractor’s Consultant and any of the sub-consultants who have provided services to the Department that have been directly utilized in this design-build proposal or Scope of Services document will NOT be eligible to participate in this design-build contract for this project, either as a prime consultant or as a sub-consultant.

6 SCOPE OF WORK

The intent of the project is to replace all existing noise barrier panels for all ODOT owned noise barriers along I-675 in the vicinity just north and south of the Vineland Trail overpass with fiberglass or concrete noise barrier panels. These panels may be reflective or absorptive and may only come from ODOT approved barrier suppliers.

The existing top of noise barrier elevations shall be maintained with the replacement panels along with the existing noise barrier locations. The existing top of barrier elevations shall be recorded at each post prior to the start of construction. The field measured top of panel elevation shall be recorded on the design drawings. Additional noise analysis or noise barrier location warrants will not be required for the project. Match the final top of noise barrier elevation to the existing elevation as a minimum. At locations where the existing noise barrier posts extend above the existing panels, the new wall panels shall extend to the top of the existing post. Shortening of the existing posts is prohibited. Place the new panels flush to the interstate side of the noise barrier posts. Replacement panels shall be snug fit or secured in posts to prevent panel movement under wind loading. The use of unsecured wedges is prohibited.

Field inspections by ODOT personnel have indicated that most of the existing noise barrier posts are in salvageable condition and do not need to be replaced. However, the DBT will have the option to use as much or as little of the existing posts and foundations necessary to meet the intent of the scope. There may be spot locations where post replacement will be required due to damage. The District has estimated that approximately 35 posts will need to be replaced. If a post is replaced, it shall be of the same design using the same materials, or better, as the existing post. If the DBT opts to modify the location, number or configuration of existing posts or foundations along the existing alignment, a report shall be submitted at Stage 1 summarizing these changes and shall also provide any supporting calculations. Coating requirements and replacement hardware for any replacement posts or damage to existing posts while in construction shall be in accordance with the highest and most current industry standard for structural stability and durability. All panel and post (if required) design, including the post foundations, shall be designed and constructed in accordance with the ODOT Bridge Design Manual (BDM) Section 800, dated January 2009, and the most current version of ODOT Standard Drawing NBS-1-09. It is the responsibility of the DBT to design the replacement panels in such a manner that the existing posts and foundations, if used, are structurally capable of handling all loads placed on them by the new panels, in accordance with, but not limited to, current ODOT design standards, including the ODOT BDM and NBS-1-09.

The noise barrier replacement shall be performed consistent with current ODOT Noise Policy and Aesthetic Guidelines. The Contractor will be required to match the noise barrier panel color and pattern on both the resident side and the interstate side as closely as possible. The proposed panel color and texture must be approved by the ODOT District 8 Environmental Coordinator (DEC) prior to full manufacturing. The DBT will provide a full-size mock up of the proposed final noise barrier system (typical post and

Page 6: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

6

panels for the standard barrier and the bridge barrier) for review and acceptance by the Department at least 45 days prior to production fabrication of the panels. Production fabrication shall not begin until written acceptance of the panel system has been provided to the DBT by the Department. Fiberglass panels may not be painted; color must be integral to the panels. Sealing of concrete panels, if selected, shall be per NBS-1-09, using Federal Color 10324 Dark Neutral.

The noise barrier replacement work shall be constructed in a way which maximizes the preservation of vegetation during construction and clearing and grubbing operations.

When the sequence of construction activities requires, or should the Contractor desire, the removal of the existing lighting, the Contractor shall be responsible for providing temporary lighting of this portion of the roadway. Prior to installing such lighting, the Contractor shall prepare and submit four sets of the temporary lighting plan to the Engineer for review and approval. This plan shall show locations of poles, lengths of bracket arms, styles of luminaires, mounting heights, wiring methods and other pertinent information. The temporary lighting shall provide an average initial intensity of 1.2 footcandles (13 lux) with an average to minimum uniformity not to exceed 3:1. Mounting height of temporary luminaires shall not be less than 30 feet (9 meters), and the minimum overhead conductor clearance shall be 20 feet (6 meters). Temporary overhead construction shall not be less than Grade "A" for strength requirements as defined by the National Electric Safety Code. Wood poles with overhead wiring may be used. However, temporary lighting shall meet Federal and State safety criteria. If breakaway poles are used to meet these criteria, then underground wiring shall be used. Reconditioned or used materials may be furnished for temporary lighting. All materials necessary to complete the temporary lighting shall be furnished and installed by the Contractor. When no longer needed, the temporary lighting installation shall be removed and properly disposed of by the Contractor. The existing light poles shall then be re-erected and returned to their proper working order. Any damage to the existing circuits, poles or hardware, as a result of this work shall be repaired by the contractor.

Highway signs may be removed if they are in conflict with construction operations and re-erected once the construction activities in the vicinity of the sign are completed. The DBT will be responsible for providing a Maintenance of Traffic plan for both I-675 and Vineland Trail.

Existing drainage patterns are to be maintained and any disruption caused as a result of the noise panel replacement (damaged conduits, headwalls, filled in ditches, etc.) shall be repaired by the contractor to the satisfaction of the Engineer.

The use of steel for noise barrier panels mounted on the bridges will not be allowed on the project. Only ODOT approved fiberglass or aluminum powder coated material for these bridge mounted noise barrier panels may be used. If using fiberglass material for the bridge mounted noise barrier replacement panels, in an effort to prevent dislodging of the panels in the event of a vehicle impact into the barrier on the bridge, each individual fiberglass panel shall be fastened to the post at each end. The DBT shall, within 30 days of the signed contract, remove and dispose of the existing panels from the bridge structures only. The DBT will have a total of 120 days, (inclusive of design, review and subsequent approval of drawings) from the date of the signed contract to have the new panels for the bridges only, complete, in place and functional.

The following locations of the existing noise barriers, to which the above described replacement work shall be performed, have been logged by ODOT District 8:

Greene County: SLM 3.10 – 3.50 Left SLM 3.26 – 3.68 Right These logged locations of the existing noise barriers are approximate. Actual locations will be determined

Page 7: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

7

on-site by the DBT.

The Contractor’s Consultant shall provide for the engineering services, design, and preparation of detail construction plans for the construction of the proposed project.

The Contractor shall provide for the furnishing of materials, construction and completion in every detail of all the work described in the Conceptual Documents and Scope of Services in order to fulfill the intent of the contract.

The removal and disposal of the existing panels, posts and foundations (where required), and associated hardware shall be incidental to the work to replace the panels.

Completion date: 18 months from date of award

7 FIELD OFFICE

Field office Type B , as required by Supplemental Specification 619, shall be available and completely functional no later than 1 week prior to the start of construction work.

8 GENERAL PROVISIONS FOR THE WORK

8.1 Governing Regulations: All services, including but not limited to survey, design and construction work, performed by the DBT and all subcontractors, shall be in compliance with all applicable ODOT Manuals and Guidelines.

The fact that the bid items for this Design-Build project are general rather than specific shall not relieve the Contractor of the requirement that all work performed and all materials furnished shall be in reasonable conformity with the specifications. The Contractor’s Consultant shall reference in the plans the appropriate Construction and Material Specifications Item Number for all work to be performed and all materials to be furnished.

The attention of the Bidder is directed to the provisions of Section 100 of the Construction and Material Specifications as modified in the design-build proposal. It will be the responsibility of the DBT to acquire and utilize the necessary ODOT manuals that apply to the design and construction work required to complete this project.

The current edition, including updates released on or before the prebid meeting date, of the following ODOT Manuals and Guidelines shall be met or exceeded in the performance of the design and construction work required to complete this project:

Bridge Design Manual - 2007 Location and Design Manuals Volume One - Roadway Design Volume Two - Drainage Design Volume Three - Plan Preparation Pavement Design & Rehabilitation Manual Specifications for Geotechnical Explorations Survey Manual Construction and Material Specifications Proposal Notes for Construction and Material Specifications Supplemental Specifications for Construction and Material Specifications Standard Construction Drawings

Page 8: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

8

Traffic Engineering Manual Ohio Manual of Uniform Traffic Control Devices Real Estate Administration Policies and Procedures Manual: Appraisal Acquisition Property Management Relocation ROW Plan Utilities Waterway Permit Manual Design Mapping Specifications CADD Engineering Standards Manual Geotechnical Bulletins Project Development Process Manual (Appendix B) Noise Barrier Specifications and Standard Drawings Standard Procedure for Analysis and Abatement of Highway Traffic Noise

8.2 Basis of Payment: All Items covered by Construction and Material Specifications, Supplemental Specifications, Proposal and Special Provision notes with unit price as a basis of payment will be paid for under the appropriate Lump Sum bid item, unless a unit line price item has been established in the Scope Of Services.

The DBT shall be required to furnish the Department with a complete breakdown of the lump sum bid items. The breakdown shall include materials to be used in the work, and shall be in sufficient detail to provide ODOT with a means to check partial payment requests.

8.3 Final Payment: The DBT shall prepare and submit the following prior to the request for final payment:

1. All original project files and notes utilized in the preparation of the survey, design and construction of the project.

2. Record-Drawing Plans as required below.

8.4 Record-Drawing Plans:

A. General: At the completion of the work, prior to final acceptance of the construction, the Consultant shall furnish the Department Record-Drawing construction plans. When the Record-Drawing plans are completed, the Consultant shall have the title sheet endorsed (signed and sealed) by a Professional Engineer.

All plan sheets shall be submitted in accordance with ODOT L&D Manual Volume 3 requirements, which includes the required text size and plan sheet materials. Plans shall also be submitted in electronic format as TIFF images in accordance with the ODOT CADD engineering website.

In addition to the information shown on the construction plans, the Record-Drawing plans shall show the following:

1. All deviations from the original approved construction plans which result in a change of location, material, type or size of work

2. Any utilities, pipes, wellheads, abandoned pavements, foundations or other major obstructions discovered and remaining in place which are not shown, or do not conform to

Page 9: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

9

locations or depths shown in the plans. Underground features shall be shown and labeled on the Record-Drawing plan in terms of station, offset and elevation.

3. The final option and specification number selected for those items which allow several material options under the specification (e.g., conduit).

4. Additional plan sheets may be needed if necessary to show work not included in the construction plans.

Notation shall also be made of locations and the extent of use of materials, other than soil, for embankment construction (rock, broken concrete, etc.).

The Plan index shall show the plan sheets which have changes appearing on them.

Two copies of the Record-Drawing plans shall be delivered to the Project Engineer for approval upon completion of the physical work but prior to the request for final payment. After the Department has approved the Record-Drawing plans, the original tracings and the associated electronic files shall be delivered to the District Production Administrator. Acceptance of these plans and delivery of the original tracings and the associated electronic files is required prior to the work being accepted and the final estimate approved.

The delivered original tracings shall be prepared in conformance with the Location and Design Manual Volume III (Section 1200 - Plan Preparation).

B. CADD Files shall supplied by DBT: X Yes NoIf marked yes, the Consultant shall comply with ODOT’s CADD Standards, and supply files in accordance with the CADD Engineering Standards Manual. All data shall be provided to the Department according to the provisions as detailed under the appropriate CADD links accessed from the Department’s Office of Production’s web site. This includes, but is not limited to, the level assignments, symbols, lines and line styles that are to be used, line weights, cells, placement of text and file naming conventions. The web site can be accessed at the following URL address: http://www.dot.state.oh.us/cadd/http://www.dot.state.oh.us/prod/

The following can be accessed from the above URL address:

1. ODOT CADD Standard files by selecting the “CADD Standards” link 2. ODOT’s Location and Design, Volume 3 by selecting the “L&D Volume 3" link 3. ODOT’s GEOPAK Standards by selecting the “GEOPAK” link

The Department will accept CADD files on CD ROM electronic media only.

1. The Consultant shall submit all CADD information produced in the process of plan development. All CADD information shall be submitted in the current version of MicroStation (*.dgn) format as indicated in the CADD Engineering Standards Manual. This requirement ensures that ODOT receives an end product that is directly usable on ODOT’s CADD systems without additional work. The responsibility to provide the Department with correct and complete CADD data rests with the consultant.

2. The Consultant shall submit all GEOPAK information produced in the process of plan development. The submission shall include all files generated by GEOPAK as the result of the plan processing and these files shall include but are not limited to the following:

a. Coordinate databases (*.gpk) b. Digital terrain models (*.tin) c. Original cross section (XS) cell design files

Page 10: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

10

d. Edited observation files (*.obs) e. ASCII text files containing all raw point data (PT #, X, Y, Z, Linking Code/Mapping

Code) f. ASCII text files containing all adjusted point data (PT #, X, Y, Z, Linking Code/Mapping

Code, Attribute data if any) g. ASCII text file(s) listing chain data for all existing and proposed horizontal alignments;

including the centerline of construction, the centerline of right of way and ramp baselines.

h. ASCII text file(s) listing vertical alignment data for all existing and proposed profiles. i. ASCII text files listing the Northing, easting, station, offset and elevation for all existing

and proposed monuments.

A separate file name should be used for each horizontal or vertical alignment. The CADD Engineering Standards Manual provides specific requirements for the content of the required ASCII reports and provides directions on how to create these reports using GEOPAK software.

3. The Consultant shall submit the following aerial photography and/or mapping information produced in the process of plan development. The submission shall contain the following files:

a. Three-dimensional (3D) MicroStation design file with an extension of “*.3D” containing all DTM data which were utilized to create the surface for the project (or section)

b. 3D MicroStation design file containing all topographic, planimetric, ground control points, grids and legend and shall have an extension of “*.TTN”

c. An “.ASC” file for mass points and break lines (ASCII format).

These requirements and procedures may be updated from time to time with notification in the (DRRC) Design Reference Resource Center website which is located at the following URL, http://www.dot.state.oh.us/DRRC/. Organizations exchanging ODOT CADD data are responsible for ensuring they are using the current version of these requirements, CADD reference manuals, ODOT cell files and ODOT seed files.

8.5 Post-Award Conference: Within 10 days after bid opening, the Contractor shall attend a mandatory post-award meeting. This confidential meeting shall be held with the Estimating Office of the Division Of Contract Administration to discuss the Lump Sum estimate with the Department.

8.6 Partnering Agreement: The DBT is invited to enter into a cooperative partnership agreement with the Department on this project. The objective of this agreement is the timely completion of the work and a quality product that will be a source of pride to both the Department and the DBT. This Partnering Agreement will not affect the terms and conditions of the contract. It is a document which is solely intended to establish an environment of cooperation between the parties. The cost of the partnering workshop(s) will be agreed to and shared equally between the Department and the Contractor. The Contractor will pay all costs directly and the Department will authorize its share to the Contractor by change order. The Contractor is not entitled to any mark ups on the invoiced cost.

8.7 Communication: All communication during design and construction shall be with the District Project Manager and the District Project Engineer.

District Project Manager: Teri C. Scanlon, P.E. Phone number: 513-933-6620 Fax: 513-933-8252

E-mail: [email protected]

Page 11: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

11

The District Project Engineer shall be named at the pre-design meeting.

At the pre-design meeting, the Contractor shall name a Project Manager who will act as a liaison between the DBT and the Department.

8.8 Permits: DBT will be required to obtain a permit from the State or local government having jurisdiction, to perform any non-construction work within the existing ROW and/or limited access.

8.9 Entry On Private Property: The DBT, acting as The Department’s agent, may enter upon any lands within the State for the purpose of inspecting, surveying, leveling, digging, drilling, or doing any work deemed necessary in the execution of any survey authorized by the Director of Transportation in accordance with Section 5517.01 of the Ohio Revised Code and Section 102.6 (inclusive of Sections 102.61 through 102.66) of ODOT’s Survey Manual. Prior to performing said survey, the DBT will send notification letters indicating the date and duration of entry to the affected property owners no less than forty-eight hours nor more than 30 days prior to the date of entry for said survey in accordance with 102.6 of ODOT’s Survey Manual. The DBT shall forward copies of all notification letters distributed to ODOT’s Project Manager. Any subsequent claims for compensation due to damages incurred while said survey was being performed will be negotiated between the DBT and the affected property owners with final approval from ODOT’s Project Manager. Crop and property damage minimization and reimbursement information, together with the crop damage reimbursement formula and Special Waiver of Damage form, will be provided to the DBT by ODOT’s Project Manager. Any subsequent entries onto private property for the purpose of obtaining additional survey or soil information prior to the submission of the bid will be made in accordance with the procedures outlined in this section. If there is no potential for actual damage to the property nor substantial interference with possession or use of the property, then no notification is required. However, it is always in the interest of good relations with the public to at least knock on someone’s door to let them know what is going on upon their property. If a property owner refuses the crew’s request to enter upon the property, then ODOT D8 will need to be notified in order to gain a right of entry for survey work or a court order will be needed.

9 ENVIRONMENTAL

The proposed project is considered to be a maintenance activity under the Programmatic Categorical

Exclusion Agreement between the Federal Highway Administration and the Ohio Department of Transportation dated March 6, 2003. As such, the project is classified as an EXEMPT ACTION under that agreement and will not require any environmental documentation.

10 RIGHT OF WAY (ROW)

All necessary construction work for the project will be performed within the existing right of way.

The DBT will stake and flag the existing right of way in the field prior to the start of construction and will maintain said stakes and flags throughout the duration of the project.

The DBT will identify and show all right of way encroachments on the construction plans at the Conceptual Review Submission. ODOT’s Project Manager will be responsible for clearing all encroachments on Federal-aid projects in accordance with standard encroachment removal.

11 UTILITIES

Utilities Special Provisions in addition to the Governing Regulations listed in section 8.1 of this document and section 153.64 of the Ohio Revised Code.

Page 12: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

12

11.1 Existing Utilities: It will be the responsibility of the DBT to locate all existing utilities within the project area and show them on the plans. Sources of existing utility location information within the project area should include, but not be limited to, the District Utility Coordinator, the registered Underground Utility Protection Services - Ohio Underground Protection Service (OUPS) and Oil and Gas Producers Underground Protection Service (OAGPUPS) and any other utility owners that are non-members of any utility protection services.

11.2 DBT Utility Coordination Responsibilities:Utilities/ITS equipment shall be field verified by the project designer. The location of the barrier(s) shall reflect any utility requirement.

As soon as it is feasible after the final plan is approved by the Department, the Contractor shall stake the existing ROW (and new ROW if additional is acquired) in the field and shall perform clearing and grubbing within that ROW as required by the specifications and the proposal documents, in order to allow utility relocation and reduce potential delays. ROW stakes shall be maintained and updated as needed throughout the project length.

The DBT shall be cognizant of the project's impact on utility facilities. In the event utility rearrangements are required, the project shall not be designed to preclude legal occupancy of the highway ROW by the rearranged utility facilities.

The DBT shall coordinate all existing utilities with construction activities on this project. The DBT shall insure that potential delays in coordination and relocation of the affected utilities are minimized. The DBT shall copy the Project Manager and the District Utility Coordinator on all correspondence or phone calls between the DBT and each utility. This shall include the submittal of plans to each utility.

A meeting at or near the preliminary review shall be held between the DBT the District Utility Coordinator and the utility owners to determine if any significant utility relocations can be eliminated or mitigated.

Any betterment to the utility's facility and ineligible, or unnecessary, work shall not be a part of the project's expense but the utility company’s fiscal requirement. Determination of eligibility can be coordinated through the District Utility Coordinator. Payment for betterments or ineligible costs shall be made by the appropriated utility through ODOT to the Contractor.

The cost of all utility coordination shall be bid as a Lump Sum Item.

11.3 Subsurface Utilities Engineering (SUE): Not Applicable.

12 DESIGN AND CONSTRUCTION REQUIREMENTS :

MAINTENANCE OF TRAFFIC (MOT)

Maintenance of Traffic (MOT) Special Provisions in addition to the Governing Regulations listed in section 8.1 of this document.

12.1 General: All temporary MOT devices shall comply with the National Cooperative Highway Research Program (NCHRP) 350 Hardware report.

12.2 MOT Restrictions:

Permitted Lane Closures: 1 LANE MAY BE CLOSED TO TRAFFIC FROM 7 PM TO MIDNIGHT AND MIDNIGHT TO 5 AM DAILY. NO WORK SHALL BE PERFORMED AND

Page 13: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

13

ALL EXISTING LANES SHALL BE OPEN TO TRAFFIC DURING THE FOLLOWING DESIGNATED HOLIDAYS OR EVENTS: CHRISTMAS FOURTH OF JULY NEW YEARS LABOR DAY MEMORIAL DAY THANKSGIVING EASTER

THE PERIOD OF TIME THAT THE LANES ARE TO BE OPEN DEPENDS ON THE DAY OF THE WEEK ON WHICH THE HOLIDAY OR EVENT FALLS. THE FOLLOWING SCHEDULE SHALL BE USED TO DETERMINE THIS PERIOD:

DAY OF THE WEEK TIME ALL LANES MUST BE OPEN TO TRAFFIC

SUNDAY 5 AM FRIDAY THROUGH 7 PM MONDAY MONDAY 5 AM FRIDAY THROUGH 7 PM TUESDAY TUESDAY 5 AM MONDAY THROUGH 7 PM WEDNESDAY WEDNESDAY 5 AM TUESDAY THROUGH 7 PM THURSDAY THURSDAY 5 AM WEDNESDAY THROUGH 7 PM MONDAY FRIDAY 5 AM THURSDAY THROUGH 7 PM MONDAY SATURDAY 5 AM FRIDAY THROUGH 7 PM MONDAY NO EXTENSIONS OF TIME SHALL BE GRANTED FOR DELAYS IN MATERIAL DELIVERIES, UNLESS SUCH DELAYS ARE INDUSTRY-WIDE, OR FOR LABOR STRIKES, UNLESS SUCH STRIKES ARE AREA-WIDE. SHOULD THE CONTRACTOR FAIL TO MEET ANY OF THESE REQUIREMENTS, THE CONTRACTOR SHALL BE ASSESSED A DISINCENTIVE IN THE AMOUNT OF $1,000.00 PER 15 MINUTES THE LANE REMAINS CLOSED TO TRAFFIC BEYOND THESE SPECIFIED TIMES.

Minimum lane width: EXISTING Maximum duration of detour: NOT APPLICABLE

Shoulder restrictions: THE CONTRACTOR SHALL NOT PARK VEHICLES ON OR WORK FROM SHOULDER FROM 5 AM TO 9 AM AND 3 PM TO 7 PM ON I-675.

12.3 Additional Description of Required Work and special provisions:

The contractor may close the right lane as per OMUTCD and ODOT Standard Construction Drawings during the times detailed above.

THE CONTRACTOR’S EQUIPMENT SHALL BE OPERATED IN THE DIRECTION OF TRAFFIC. THE CONTRACTOR’S EQUIPMENT SHALL BE EQUIPPED WITH AT LEAST ONE AMBER FLASHING LIGHT. EQUIPMENT MAY BE PARKED IN AREAS ALONG THE HIGHWAY WHEN OPERATIONS ARE SCHEDULED TO CONTINUE WITHIN THE NEXT WORKDAY IN COMPLIANCE WITH ODOT CONSTRUCTION AND MATERIAL SPECIFICATIONS SECTION 614.03, INCLUDING THE REQUIREMENT TO LOCATE EQUIPMENT, VEHICLES AND MATERIAL NOT LESS THAN 6 FEET BEHIND EXISTING GUARDRAIL OR NOT LESS THAN 30 FEET BEYOND THE TRAVELED WAY. OTHERWISE THE EQUIPMENT SHALL BE STORED AT A STORAGE AREA OUTSIDE THE L/A, THE LOCATION OF WHICH SHALL HAVE PRIOR APPROVAL OF THE

Page 14: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

14

ENGINEER. WHEN PARKING ALONG THE HIGHWAY THE EQUIPMENT SHALL BE PLACED AND DELINEATED AS PER 614.03. NO EQUIPMENT SHALL BE PARKED IN THE MEDIAN OF THE HIGHWAY. ADEQUATE BARRICADES AND LIGHTS SHALL BE PLACED ON THE PAVEMENT SIDE OF THE EQUIPMENT TO IDENTIFY THE LIMITS OF THE EQUIPMENT. ALL OTHER EQUIPMENT, INCLUDING PRIVATE VEHICLES, SHALL BE STORED AT THE APPROVED CONTRACTOR’S STORAGE AREA. NO EQUIPMENT SHALL BE PARKED ON PRIVATE PROPERTY UNLESS PRIOR APPROVAL OF THE OWNER AND THE PROJECT ENGINEER/SUPERVISOR HAS BEEN GRANTED.

12.4 Construction Notification to the Public:

TO ENSURE THAT THE PUBLIC IS NOTIFIED OF CONSTRUCTION ACTIVITIES, THE FOLLOWING PLAN NOTE WILL BE ADDED TO THE PROJECT PLANS: THE CONTRACTOR WILL ADVISE THE PROJECT ENGINEER A MINIMUM OF FOURTEEN (14) DAYS PRIOR TO THE FOLLOWING: THE START OF CONSTRUCTION ACTIVITIES, LANE CLOSURES, AND OR ROAD CLOSURES. THE PROJECT ENGINEER WILL FORWARD THIS INFORMATION TO THE DISTRICT PUBLIC INFORMATION OFFICER (PIO) BY FAX AT (513) 932-7651 OR EMAIL AT [email protected]. THE PIO WILL, IN TURN, NOTIFY THE PUBLIC, THE LOCAL EMERGENCY SERVICES, AFFECTED SCHOOLS AND BUSINESSES, AND ANY OTHER IMPACTED LOCAL PUBLIC AGENCY OF ANY OF THE ABOVE MENTIONED ITEMS, VIA MEDIA SOURCES.

13 DESIGN AND CONSTRUCTION REQUIREMENTS:

LOCATION & DESIGN

Location & Design Special Provisions in addition to the Governing Regulations listed in section 8.1 of this document:

13.1 Survey

All survey data shall come from the DBT. All survey data shall be submitted using ODOT’s standard field codes and GEOPAK’s standard mapping codes. Reduced point data, in comma delimited ASCII text format, will be provided for all surveyed points. This data will include: point number, x coordinate, y coordinate, elevation and point ID. Customized GEOPAK information is available on the ODOT web site.

Monumentation shall not be disturbed. If the Contractor does disturb the monumentation, then it shall be replaced, in-kind, by a Registered Surveyor, with a current registration, recognized by the Ohio State Board of Registration for Professional Engineers and Surveyors. Costs associated for this item shall be borne by the Contractor. Copies of all monumentation changes shall be forwarded to the District ROW.

All control points, provided by ODOT, shall be included in the ASCII file supplied by the Contractor to ODOT. They should retain the original point numbers and coordinate values as assigned by ODOT.

The DBT shall provide the following items prior to final acceptance of the Record-Drawing plans: a) Copies of all field notes (written or electronic) which shall include the following information- Date Crew members Weather conditions, including temperature, barometric pressure, etc. Instrument(s) used (Serial Number) Raw observation field data Other notes as needed

Page 15: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

15

b) Copies of all Deeds, Plats, Maps and other written evidence used to establish points related to the project including summaries of all parole evidence acquired as a part of the survey operation.

c) Listing of all found monumentation (Horizontal and Vertical).

d) Listing of all monumentation set as part of the project (Horizontal and Vertical) including reference ties for recovery.

e) All monumentation shall be located utilizing NAD 83 (Horizontal Data), NAVD 88 (Vertical Data).

f) Short report indicating adjustment factors and methods, signed and certified by a Registered Surveyor (State of Ohio).

13.2 Vertical and Horizontal Alignment: N/A

13.3 Pavement: N/A

13.4 Roadway: N/A

13.5 Drainage: Yes ; No X

13.6 Design Exceptions:

Previously approved Design Exceptions: N/A

The DBT shall advise of any future design features that do not meet the minimum design criteria. The DBT shall prepare all future design exceptions and submit to ODOT for approval.

13.7 Landscape: Yes ; No X

13.8 Fencing: Yes _____; No _X__

13.9 Additional Description of Required Work and Special Provisions:

14 DESIGN AND CONSTRUCTION REQUIREMENTS:

STRUCTURES

NOT APPLICABLE (Bridge Mounts)

15 DESIGN AND CONSTRUCTION REQUIREMENTS :

TRAFFIC CONTROL

15.1 Pavement Markings and Delineators Special Provisions in addition to the Governing Regulations listed in section 8.1 of this document:

A. Pavement Markings: Yes ; No X

B. Raised Pavement Markers: Yes ; No X

C. Delineators: Yes ; No X All flexible delineators shall conform to Item 620 and shall be placed in accordance with current design standards and policies. Confirmation, that no conflicts exist between the

Page 16: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

16

proposed locations of delineators and any underground utilities, shall be made prior to the installation of the delineators.

D. Barrier Reflectors: Yes ; No X All barrier reflectors shall confirm to Item 626 and shall be placed on bridge parapets and guardrails, in accordance with current design standards and policies. Barrier reflectors attached to guardrail shall be bolted.

E. Object Markers: Yes ; No X All object markers shall conform to Item 630, Sign, Flat Sheet Sign Type G

15.2 Signing Special Provisions in addition to the Governing Regulations listed in section 8.1 of this document:

A. Flat Sheet Signs: Yes ; No X a. Replace all existing flat sheet signs with new signs, except as indicated below. This

includes all signs on the mainline and interchange ramps. This also includes all STOP signs on intersecting roads. Size the signs in accordance with the OMUTCD, except as follows:

b. The following signs shall remain in place and not be replaced: c. The following signs shall be removed and not replaced: d. The following signs shall be installed where none currently exist: e. The following signs will be provided by ODOT for contract installation: f. At the following locations, the signs shall be mounted overhead: g. Removed flat sheet signs shall become the property of the Contractor.

B. Extrusheet Signs: Yes ; No X a. Replace all existing extrusheet signs with new signs, except at the locations indicated

below. This includes all signs on the mainline and interchange ramps. Size the signs in accordance with the OMUTCD (exceptions are noted below):

b. The entrance ramp approach signing on the following roads shall be included in this project:

c. TODS and logo signs are installed and maintained by Ohio Logos, Inc., under contract with and in locations approved by ODOT. Under the terms of the contract, Ohio Logos can be required to temporarily remove or relocate the signs during construction. They can also be required to permanently remove or relocate the signs. Contact Ohio Logos at 1-800-860-5646 to coordinate removals or relocations of TODS and logo signs.

d. At the following locations, the signs shall be mounted overhead: e. Removed extrusheet signs shall be returned to the ODOT Sign Shop, 1680 W. Broad

St., Columbus, Ohio.

C. Ground Mounted Post Supports: Yes ; No X a. Replace all existing ground mounted post supports with new supports. New sign

installations shall be on new supports. No reuse of existing ground mounted supports shall be allowed.

b. Removed ground mounted supports shall become the property of the Contractor.

D. Ground Mounted Beam Supports: Yes ; No X a. Replace all existing ground mounted beam supports, with new ones, except at the

locations indicated below: b. Supports subject to multidirectional impacts at intersections shall use the alternate

connection on sizes larger than S4 x 7.7.

Page 17: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

17

c. Removed ground mounted beam supports shall become the property of the contractor.

E. Overhead Supports: Yes ; No X a. Replace all existing overhead supports with new ones, except at the locations indicated

below: b. The steel portions of existing overhead sign supports at the following locations shall be

recoated using the process described below: c. The steel portions of new overhead supports at the following locations shall be coated

using the process described below: d. The following aesthetic treatments shall be used:

e. At all locations, a minimum vertical clearance of seventeen feet shall be maintained. f. At the following locations, the median end frame foundation shall be in accordance

with the details shown in Standard Construction Drawing TC-21.40. g. At the following locations, protection of the end frame or poles shall be achieved as

follows: h. All sign attachment assemblies shall be replaced.

i. Sign lighting shall be used at the following locations: Sign lighting shall be in accordance with the details shown in Standard Construction Drawing TC-31.21. Replace all luminaire support assemblies, ballasts, and luminaires, and rewire signs.

j. Removed overhead supports shall become the property of the Contractor.

15.3 Lighting Special Provisions in addition to the Governing Regulations listed in section 8.1 of this document:

15.4 Traffic Signals Special Provisions in addition to the Governing Regulations listed in section 8.1of this document:

A. Signal Supports: Yes ; No X a. Shall be galvanized steel. No wood poles.

b. For span wire installations, pole strength shall be designed for 3% sag and pole height shall be designed for 5% sag.

c. Strain poles shall be a minimum size of Design 5 and of the anchor base type. d. Location of the supports shall be as per the Traffic Control Design Information

Manual. e. Clearance from overhead electric wires shall be as per utility company requirements.

B. Vehicle Signal Heads: Yes ; No X a. Shall be made of . b. Lenses shall be 12 inch and made of . c. Shall be completely yellow except for the inside of visors which shall be black. d. Tri-stud wire entrance fitting e. Far side mounting of signal heads shall be used as much as practical.

f. For protected/permissive operation of a 5-section signal head (either left or right turn), the recommended location of the signal head is over an extension of the channelizing line, through the intersection, that separates the turn lane and the through lane.

C. Pullbox: Yes ; No X a. Shall be concrete, 713.08, 18 inch minimum opening size. b. Shall not be located in curb ramp areas. c. Shall not be located where subject to vehicular traffic.

Page 18: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

18

D. Conduit: Yes ; No X a. Maximum conduit run length between pullboxes and/or poles is 200 feet. b. Conduit under roadway pavement shall be 3 inch diameter minimum.

c. Conduit must be sized for the number and size of the conductors contained in the conduit. Cable fill should not exceed 40% of the inside cross sectional area of the conduit.

d. Conduit shall be 713.04.

E. Cable and Wire: Yes ; No X a. Unswitched power cable shall not be run inside of conduit, poles or pullboxes

containing other signal cables. b. Lighting cables operating at voltages higher than 120 volts shall not be run inside of

conduit, poles or pullboxes with signal cables. c. Utility company approval shall be obtained for the attachments of any interconnect

cables to utility poles, and for the location of power sources. d. All abandoned cables shall be removed from aerial spans, conduit and pullboxes.

Direct burial cables will be abandoned in place. e. Signal messenger wire size shall be 3/8 inch diameter.

f. All signal installations shall be designed and equipped for “approach monitoring”. If a two phase signal is used, a dual ring controller and cabinet wiring utilizing phases 2+6 and 4+8 will be furnished and installed.

16 PROJECT SCHEDULE REQUIREMENTS

The contractor shall begin working on the southern most noise barriers first. After work begins on a wall, the contractor will schedule work in a way that work is continuous until the wall is complete. Existing panels may only be removed at the time the replacement panel is ready to be placed. This project will utilize the critical path method progress schedule as per Proposal Note 105.

The DBT is advised of the presence of other construction contracts within the vicinity of this project. As per CMS 105.08, cooperation between contractors is required.

17 PLAN SUBMITTALS AND REVIEW REQUIREMENTS

17.1 Plan Components: All plans submitted by the DBT shall be in conformance with the following ODOT manuals:

1. Real Estate Policies and Procedures Manual Section 3100. The DBT shall also identify all topographic features within the existing and proposed

Right-of-way limits, including underground utilities. 2. Bridge Design Manual. 3. Location and Design Manual, Volume 3:

The following sections of the Location and Design Manual, Volume 3 are NOT required: 1302.13 Plan Signatures 1307.2 General summary sheet 1307.3 Subsummaries 1307.4 Pavement Quantity Calculations 1310.3 Earthwork and Seeding Quantities

Units of measure is NOT required

Page 19: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

19

Simplified plans (section 1301.2) are NOT allowed. 17.2 Quality Control: The DBT will be responsible for the professional quality, technical accuracy

and adherence to the Governing Regulations listed in section 8.1 of this document, for all plan submittals required under this contract.

The DBT shall immediately notify the Department of any apparent discrepancy between the various design and construction manuals and the Conceptual Documents.

Unless stated otherwise, review comments do not revise the scope or intent of the project and do not constitute a request for changes beyond the current contracted Scope of Services

In the event the Department determines that any required submission is incomplete, contains inaccuracies which preclude a meaningful review, or does not adhere to the Governing Regulations listed in section 8.1 of this document, the Department will advise the DBT of the short comings and direct the DBT to revise and resubmit the plan. No time extension will be granted as a result of such action. The Department will schedule a review meeting or issue review comments as appropriate.

In the event the DBT believes that any review comment, or orders issued by the Department, require a change to the scope of the agreed work, the DBT shall first contact the Department for clarification and shall, within 10 days of receipt of the comments or orders, provide written notice to the District Project Manager and Project Engineer concerning the reasons why the DBT believes the scope has been changed.

17.3 Preliminary Plan Review Submission: The Consultant shall submit the preliminary plan for a Limited Review by ODOT. This submission milestone must be shown on the Progress Schedule. The preliminary plan shall be for the whole project or each phase for multiple phase projects and shall include the following: (All sections refer to the Location & Design Manual, volume 3)

Title Sheet (1302) Schematic Plan (1303) Underground Utilities (1403.4) Preliminary utility Plan (1403.8) Conceptual Maintenance of Traffic (1403.6) Preliminary Drainage (1403.20) Storm Water Pollution Prevention Plan (1308)

Line, Grade, Typical section & Geometrics (1403.5) Slopes (1403.24)

Structures-Preliminary Design (1403.10) Supplemental Site Plan (1403.11)

This review submission shall include the noise barrier plan and profile. The contractor shall supply the Theoretical Noise line from the original plans on the new plans so the wall height can be verified.

The Department shall have 14 calendar days from receipt to review complete submissions. This review time must be shown on the required Progress Schedule.

Page 20: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

20

Following this review, the DBT shall correct any errors, incorporate modifications, perform required investigations and make related changes to the plans and supporting documents prior to submitting the plans for final review. Plan Review Distribution Table: The DBT shall supply half size (11" x 17") paper prints simultaneously to the parties indicated below. The DBT shall submit electronic PDF format of all plan submittals for electronic archive:

Number of half size Sets

ODOT District 8 Production 1

ODOT District 8 Construction 2

ODOT District 8, Planning and Environmental Department

1

ODOT Central Office, Division Of Highway Operations

2

ODOT Central Office, Construction Administration

1

Noel Alcala, ODOT Central Office, Office of Environmental Services

1

Sean Meddles, ODOT Central Office, Office of Structural Engineering

1

Each affected Utility Company 1

17.4 Major Design Decision: Separate submittals for concurrence with major design decisions made after the Preliminary Review are required. Major design decisions involve significant utility relocation, unforeseen acquisition of ROW, traffic operation or geometric decisions that involve two or more viable solutions, and any other decision that impacts the public, operation of the facility or future maintenance.

When the DBT becomes aware of additional decisions during the course of the design, they must advise the District Project Manager in writing.

17.5 Final Plan Review Submission: For each Buildable Unit the Consultant shall submit the following completed detailed design plans for a review by ODOT. All submissions must be shown on the required Progress Schedule.

Plans Affecting Utilities (1403.33) Roadway (1403.35) Drainage (1403.36) Structure (1403.37)

The Department shall have 14 calendar days from receipt to review complete submissions. This review time must be shown on the required Progress Schedule.

Following the review the Department will return to the DBT marked plans noted ‘ACCEPTED’, ‘ACCEPTED AS NOTED’ or ‘NOT ACCEPTED’ as described in section 105.02 of the

Page 21: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

21

Construction and Material Specifications. The DBT shall correct errors, incorporate changes, perform investigations and make related changes to the plans and supporting documents prior to submitting construction plans. Plan Review Distribution Table : The DBT shall supply half size (11" x 17") paper prints simultaneously to the parties indicated below. The DBT shall submit electronic PDF format of all plan submittals for electronic archive:

Number of half size Sets

ODOT District 8 Production 1

ODOT District 8 Construction 2

ODOT Central Office, Division Of Highway Operations

2

ODOT Central Office, Construction Administration

1

Noel Alcala, ODOT Central Office, Office of Environmental Services

1

Sean Meddles, ODOT Central Office, Office of Structural Engineering

1

ODOT District 8, Planning and Environmental Department

1

Each affected Utility Company 1

17.6 Construction Plans: After the review comments for the final plan review submission have been complied with, and following approval of the design documentation, the DBT shall prepare plan sets for use during construction. All review comments shall be resolved to the satisfaction of the Department before the DBT submits the construction plans. Each plan sheet shall have its last revised date noted on the sheet and clearly marked ‘Approved for Construction’. As per ODOT CADD Standards, the DBT shall also submit the final plans in electronic format as TIFF images.

Plans Distribution Table: The DBT shall supply half size (11" x 17") paper prints of the each plan submission simultaneously to the parties indicated below. The DBT shall submit electronic PDF format of all plan submittals for electronic archive:

# of Half Sets

ODOT District 8 Production 1

ODOT District 8 Construction 2

ODOT Central Office, Division Of Highway Operations 2

ODOT Central Office, Construction Administration 1

Page 22: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

22

Noel Alcala, ODOT Central Office, Office of Environmental Services

1

Sean Meddles, ODOT Central Office, Office of Structural Engineering

1

ODOT District 8, Planning and Environmental Department

1

Federal Highway Administration 1

Greene County Engineer 1

City of Beavercreek 1

Each affected utility company 1

17.7 Plan Distribution Addresses:

Ohio Department of Transportation, District 8 505 South State Route 741 Lebanon, OH 45036 Attn: Teri C. Scanlon, P.E., Production Project Manager

Ohio Department of Transportation, District 8 505 South State Route 741 Lebanon, OH 45036 Attn: Joe Bassil, P.E., District Construction Engineer

Ohio Department of Transportation, District 8 505 South State Route 741 Lebanon, Ohio 45036 Attn: Keith Smith, P.E., Environmental Project Manager

Ohio Department of Transportation Central Office Division of Highway Operations 1980 West Broad Street Columbus, Ohio 43223 Attn: Keith Swearingen, P.E., Deputy Director

Ohio Department of Transportation Central Office Construction Administration 1980 West Broad Street Columbus, Ohio 43223 Attn: Gary Middleton, P.E., Construction Administrator

Ohio Department of Transportation Central Office Office of Environmental Services 1980 West Broad Street Columbus, Ohio 43223 Attn: Noel Alcala, P.E., Noise and Air Quality Coordinator

Page 23: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

23

Federal Highway Administration 200 North High Street Room 328 Columbus, Ohio 43215-2408 Attn: Mark Vonder Embse, P.E.

Greene County Engineer’s Office 615 Dayton-Xenia Road Xenia, Ohio 45385 Attn: Robert Geyer, P.E., P.S.

City of Beavercreek 1368 Research Park Drive Beavercreek, OH 45432 Attn: Jeff Moorman, P.E., City Engineer

Utility Companies addresses as determined by the DBT. See Section 11.

18 BUILDABLE UNITS (BU)

Definition: Buildable Units are portions of the projects which can be designed, reviewed and built with only limited controls and assumptions coming from the design of other portions of the project. Often a Buildable Unit will be defined by a geographic area within the plan, but it may also be defined by types of work or construction stages which may require or permit similar, nearby work to be divided into separate Buildable Units. All Buildable Units shall summarize the materials required to construct that portion of the project. The summary shall include the Construction and Material Specifications Item Number, and a description of the materials to be used.

General: After the approval of the Preliminary Plan, DBT may break the project work into two or more separate BU which can be progressed through design and construction with minimal or known effect on each other and/or which can be dealt with sequentially such that sufficient data is available for design and review of each BU. In order that the design and construction of one BU may proceed without significant approved information from an associated BU, the DBT may develop and propose assumptions which will allow for the first BU to proceed through design and/or construction. These assumptions shall be submitted for review and comment but their accuracy and effort upon the final design are the sole responsibility of the DBT. Should error in these assumptions result in additional work, remedial work or other changes to assure an acceptable design or should they result in the need to remove work and substitute additional work, the DBT shall be responsible for all such costs including, removal of unacceptable materials from the site, modification, additional work, repairs, etc. as necessary to produce an acceptable result.

If the DBT elects to develop Buildable Units, the DBT shall prepare, for review by the Department, a table of Buildable Units for the project with each BU described in detail. If the table is approved, the DBT shall modify the Progress Schedule to show a separate group of activities for BU and these activities shall encompass all of the design and construction work in each BU. Work activities shall be further separated in the Progress Schedule to show a meaningful completion status (i.e. separate activities comprising the placement of a bridge deck on steel beams shall describe; shoring, form building, steel placement, placement of conduit & joints, pouring concrete, forming parapets, pouring or slip forming parapets, provision of membranes, provision of wearing surfaces, curing, repair, form removal, cleaning, etc.)

Page 24: DESIGN-BUILD SCOPE OF SERVICES...design-build scope of services project no. 478968 gre-ir 675-3.10 pid no. 85364 state of ohio department of transportation jerry wray,director this

24

The Final Review Submission and construction plans shall specifically be identified by the Buildable Unit code. If the design of a BU requires input information from an adjacent or related BU, the source for that information in previously approved plans shall be cited or the DBT shall provide an estimated value of the data. The input data shall also be carefully identified. In the same way any assumption, calculations or results from the stage and BU which are used as input to another BU shall be similarly identified, and where appropriate, compared back to that BU to verify previous assumptions. Should assumptions not match values calculated later, the DBT shall re-analyze all affected components and determine appropriate changes. Should those elements have already been constructed, the DBT shall recommend repairs, adjustments, modifications or replacement of the existing work as necessary to comply with the Scope of Work. All costs for re-design, re-submissions, modifications, removals, disposal of materials and new work needed to remedy the project and bring it to compliance shall be borne by the DBT and no time extensions shall be approved for this.

19 INDEX OF ATTACHMENTS

NONE