design & estimation of intze tanks-major project report

Upload: sdutta2591

Post on 02-Jun-2018

234 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    1/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    2/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    3/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    4/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    5/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    6/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    7/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    8/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    9/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    10/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    11/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    12/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    13/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    14/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    15/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    16/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    17/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    18/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    19/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    20/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    21/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    22/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    23/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    24/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    25/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    26/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    27/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    28/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    29/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    30/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    31/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    32/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    33/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    34/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    35/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    36/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    37/75

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    38/75

    Design of Roof Dome:

    Considering a rise of 1.80 m, radius of the roof dome is given from

    1.80(2R-1.80) = (4.75)2

    R = 6.525m.

    Sin = (4.5)/6.525= 0.7241

    and = 43.36< 51.8

    Hence no tension

    Assuming t = 100mm.

    Hoop stress @ level of springing:

    f = [cos ]

    = [0.72 . ]

    f =0.0298 N/mm2

    Hoop stress @ Crown:

    =0

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    39/75

    f = .. [1 ]

    f =0.107 N/mm2

    Meridional thrust @ level of sprining:

    T =

    = ..

    =18778.34 N/m

    Compressive stress

    = .

    =0.125 N/mm2 provoide 8mm

    Ring beam @ top :

    Horizontal component of T= Tcos

    =13520.40 N/m

    Hoop stress in the ring beam

    =14339.82

    =60841.82

    Area of steel required

    = ..

    =311.73 mm2

    We have to provide 12 mm,4 bars of 452.38 mm

    Size of the ring beam:

    Let the area of the ring beam section = A mm2

    Equivalent concrete area = +(m-1)

    = +(13.33-1)452.38

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    40/75

    = +5577.8454

    Limiting tensile stress on the eqvivalent concrete area to 2 N/mm2

    Cylindrical wall:

    Pressure intensity at the bottom of cylindrical wall = 49810

    =39240 N/mm2

    Consider bottom strip of the wall as 1 mm.

    Hoop tension = 39240

    = 176580 N

    Ast

    =.

    = 853.04 mm2

    Provide 8 bars of 12 mm diametre of 142.85 mm distance.

    Thickness of the wall may be kept as 200 mm.

    Distribution steel = [200 1000]

    = 480 mm2

    Provide 8 mm diametre bars.

    = .

    Provide 10 mm diametre bars of spacing 100 mm between them.

    Check for compressive stress at the bottom of the cylindrical wall.

    Vertical component of T1 = V1 = T1sin = 24917 0.68

    = 17184.137 N/m.

    Weight of the wall = 0.2 4 25000

    = 20000 N/m.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    41/75

    Weight of ring beam = 0.2 0.2 25000

    = 1000 N/m.

    Total load V2 =38184.137 N/m.

    Compressive stress = .

    = 0.19 N/mm2

    Nominal vertical stress is equql to 0.24% of gross area.

    Vertical steel = . 200 100

    = 480 mm2

    Provide 10 bars of 8 mm diametre of spacing 100 mm.

    Ring beam at B :

    Let T2 be the thrust /m run exerted by the conical wall at the junction B.

    Resolving vertically at B

    T2sin = V2

    tan = ..

    = 1

    = 45 .

    T2 =

    = .

    = 54000.52 N/m.

    Resolving horizontally at B

    H2 =T2cos =54000.52 cos 45

    = 38184.137 N/m

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    42/75

    This horizontal load H2 will produce a hoop tension in ring beam B

    Hoop tension due to H2 =H2

    =38184.137 N

    =171828.6165N

    Let the rinmg beam be 500mm deep

    Water pressure on the ringh beam

    =9810 4

    =19620 N/m

    Hoop tension due to water = 19620

    =88290 N

    Total hoop tension = 88290 +171828.61

    = 260118.61 N

    Steel for hoop tension = ..

    = 1256.611mm2

    Provide 6 bars 18 mm

    Ast = 1526.81 mm2.

    Let A be the area of ring beam

    Equivalent concrete area = A+(m-1)Ast

    = A+(13.33-1) 1526.81

    = A+18825.61

    Limiting the tensile stress on the equivalent concrete area to 2 N/mm2

    .

    . = 2

    Ac =11233.688 mm2

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    43/75

    Provide 250 500 mm size

    Design of conical slab:

    Conical slab should be designed for

    a) Hoop tensionb) Bending as it spans on a sloping slab from the ring beam @ B at the ring

    girder @ c

    Design for hoop tension:

    + tan

    Where

    Ww= weight of water resting on the conical slab.Ws = weight of the conical slab.

    = inclination of the conical slab with the horizontal.

    Area of water section standing on the conical slab

    =. 1.5 = 7.125 m2.

    X =[ . ]

    . = 0.52 m.

    Weight of water resting on the conical slab Ww = 9810 7.125 2 [3.52]

    = 1545882.24 N

    Length of conical slab = 2.121 m.

    Take thickness of the slab as 200 mm.

    Weight of the conical slab Ws = 0.2 2.121 25000 2 [. ] = 249874.42 N.

    Hoop tension =. .

    =531838.349 N.

    Hoop steel on the entire section = ..

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    44/75

    = 2569.267 mm2.

    Provide 14 bars of 6 mm

    =14 64 = 2814.86 mm2.

    Design for bending moment:

    Load per metre width of the conical slab =

    = . . . = 76214.279 N.

    Maximum bending moment = = . .

    = 14290.177 Nm.

    Axial compression V2 = T2sin = .

    = 54000.52 N.

    Providing 16 mm diametre bar at clear covers of spacing 25 mm.

    Effective depth = 20025 8 = 167 mm.

    Distance between centre of section and centre of steel x = d = 167100

    = 67 mm

    Resultant bending moment = M+T2.x =14290.177 10 +54000 67

    = 17908212.15 Nmm.

    Ast =.. = 518.04 mm

    2

    Spacing of 16 mm diameter bars = 333.33 mm and provide 3 bars.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    45/75

    The bottom dome:

    Let R be the radius of the dome,then 32 = 1.2(2R1.2)

    = 4.35 m.

    Let 2 be the angle subtended by the dome.

    sin = = 43 36

    cos = 0.68

    Thickness of dome = 200 mm.

    Loads:

    Dead load = 25000 0.2 = 5000 N/mm2.

    Weight of water resting on the dome = [ h (3R )]

    =9810[155.50817.869] = 1350234.872

    Area of dome surface = 2 Rh = 2 4.315 1.2

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    46/75

    = 32.79 m2.

    Load intensity due to weight of water = .. = 41178.25 N/m2.

    Total load intensity = 5000+41178.25 = 46178.25 N/m2.

    Meridional thrust = = . ..

    = 116788.016 N/m.

    Meridional compressive stress = . = 0.583 N/mm2.

    Hoop stress = [cos ]

    = . .. [0.72

    . ]

    = 0.139 N/mm2.

    Hoop stress at the crown = 0 .

    Maximum hoop stres = [cos ] = 502188.46

    = 0.502 N/mm2.

    These stresses are low and hence provide nominal 0.3% steel.

    Provide 8 mm bars @100 mm spacing.Circular girder:

    The total load on the circular girder consists of the following;

    Total weight of water W1 = weight of water on conical slab + weight of water ondome.

    = 1545882.24+1350234.872 = 2896117.112.

    Weight of dome + cylindrical wall + ring beam at A W2 = 38184.137 2 4.5

    = 1079631.039 N.

    Weight of ring beam at B W3 = 0.25 0.5 25000 2 4.5

    = 88357.29 N.

    Weight of conical wall W4 = 249874.42 N.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    47/75

    Weight of lower dome W5 = 5000 32.79 = 163950 N.

    = 0.0075 4560396.668 3 = 102608.925 N.

    Torsion = 0.0015 W r = 20521.785 N. (from table 2)

    Angular distance for maximum torsion = 1244 .

    Let us provide 8 coloumns.

    Bending momment at the support = 0.0083W r = 0.0083 4591027.197 3

    = 114316.577 Nm.

    Bending moment at centre = 0.00416W r = 0.00416 4591027.197 3

    =57296.01 Nm.

    Torsion = 0.0006 4591027.197 3 = 8263.84 Nm.

    Angular distance for maximum torsion = 933 .

    Load at each support = = .

    = 573878.39 N.

    Shear force at the support = , V = 286939.199.

    Design at support section:

    Equating moment of resistance to the bending moment at support

    0.913bd2 = 114316.577 1000,

    0.913 400 d2 = 114316.577 1000,

    Then d2 = 278458.26, d =560 mm.

    Let the clear cover be 40 mm.

    Over all depth of beam = 600 mm.

    Actual effective depth = 600 mm.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    48/75

    Equivalent shear force = V+1.6 = 286939.199+1.6 .

    = 287160.093+( . . ).

    Vc = 319994.559.

    Equivalent nominal shear stress ve = =. = 1.42 N/mm2.

    Maximum shear stress ma x> v.

    ma x= 1.8 N/mm2.

    c< v.

    Provide longitudinal and transverse reinforcement according to B-6.4

    Longitudinal reinforcement:

    Me = M+Mt , Mt =( )

    . =. [ ]

    .

    = 12152705.88 Nmm.

    M = moment at crosssection.

    Mer = 1000 114316.577+12152705.88 = 126469282.9 Nmm.

    Ast= . = .

    = 1080.187 mm2.

    Transverse reinforcement:

    Asv= + . , b1 = 40080 = 320 mm , d1 = 60080 = 520 mm.

    Asv = [. + .. ]Sv

    Providing 4 legged 10 mm stirrups.

    Asv= 315 mm2 , 315 = 1.175, Sv = 267.95 mm.

    Take Sv as 250 mm.

    [ ]b Sv ,. . 400 Sv = 315 , Sv= 158.88 mm.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    49/75

    Provide 150 mm spacing.

    Steel for sagging moment = . .

    = 494.27 mm2.

    Provide 5 bars of 12 mm diameter.

    Ast = 565.48 mm2.

    Hoop stress:

    Tc = thrust exerted by the conical slab on the girder.

    Tcsin 2 r = Ww+Ws+weight of cylindrical wall and upper dome.

    Tcsin 2 r = 154588.24+249874.42+1079631.039

    Tcsin 2 r = 2875387.699.

    Tc =. = 215729.87 N.

    Horizontal component of Tc = 215729.87 cos45 , H1 = 152544.055 N.

    Horizontal component due to dome = 11678.016cos 43 36, H2 = 84574.59,

    H1H2 = Net,Net = 67969.46 N. Hoop stress = 67969.463 = 203908.38 N.

    Hoop compressive stress =. = 0.849 N/mm2.

    Coloumns:

    Coloumns should be designed for direct loads coming upon them and for thebending moments caused by wind load.

    Vertical load on one column at top = .

    = 573878.399 N.

    Let be the inclination of the column with the vertical.

    tan = , = 5 42 , sin = 0.0995, cos =

    = 0.995.

    Actual length of column = 10 + 1 = 10.05 m.

    Providing 300 mm 300 mm column.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    50/75

    Wt. Of column =10 0.3 0.3 25000

    = 22500 N

    Total vertical load = 573878.399+22500 N

    = 596378.399 N

    Corresponding axil load = ..

    = 59375.2754 N

    When tank is full = 599375.2754 N

    Wt. Of water in tank = .

    =3620124.639 N on each co lumnVertical load on each co lumn when tank is empty

    = 596378.399362014.239

    = 237361.036 N

    Corresponding axial load=.

    .

    = 238553.805 N

    Ignoring wind load effect if the steel requirement is Asc

    Then cAc + tAsc =599375.275 N

    5 Ac + 190 Asc =599375.275

    5[400 400 sc] +190 Asc =599375.275

    Asc =807.433 mm2.

    Min. Requirement of steel = 0.8% =. [300 300]

    =720 mm2

    Provide 6 bars of 20mm dia. =1884 mm2

    More steel has been subjected since column is subjected to B.M caused by windload.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    51/75

    Analysis due to wind pressure:

    Wind pr. =1200 mm2.

    Wind force on the top dome & cylindrical walls =(4+. ) 9.4 1200

    @Ht=13.95 =55272 N

    Wind force on the circular wa ll= . . 1.5 01200

    =14220 N

    Wind force on circular girder =0.66.4 1200

    =4608 N

    Wind force on column & braces =50.3 10 1200+3 0.3 1200

    =25560 N

    Total moment of wind pr. About the base

    =55272 13.95+14220 0.8+4608 10+25560 5

    =10982500Nm.

    Vetrical load on any column due to wind load = ^

    2 =2 42 +4(

    )2 =64m2

    Max. Wind load force in the most leeward side &the most windward side.

    = . =68656.275 N

    Max. Wind force in columns marked 5

    = . =48547.317 N

    Consider the windword column 1

    Vertical load due to dead +wind load

    =596378.399 +68656.275 N

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    52/75

    =665034.674 N.

    Corresponding axial load = ..

    =668376.556 N

    Horizontal comoponent of the axial forces caused by wind action

    =2 68456.275 0.0995+4 48547.317 0.0995

    =27285.39 N.

    Aactualhorizontal force @ base

    = 55272+14220+4608+2556027285.39 = 72374.61

    Horizontal shear column =.

    = 9046.826 N.

    Maximum bending moment for the column = 9046.826 . = 11308.532 N.

    Analysis of column section:

    Direct load = 668376.556 N.

    Bending moment = 11308.532 Nm.

    Provide 300 300 column.

    Provide 6 bars of 20 mm diameter at effective cover of 50 mm.

    Ast = 1884 mm2,

    Equivalent concrete area = Ac+(m-1)Ast = (300 300)+(12.33 1884)

    = 113229.72 N

    Polar moment of inertia of the equivalent concrete section,

    = +(mAst effective depth fromcentre),

    = +1884 12.33[150-50]2 = 1.582 109 mm4.

    Equivalent moment of inertia about full section =. = 791.14 106mm4.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    53/75

    Direct stress in concrete = = 5.9 mm2.

    Bending stress in concrete = .. = 2.14 N/mm2.

    Maximum stress = 5.9+2.14 = 8.04 N/mm2.

    Design of braces:

    Moment in brace BC = 2 moment for the column sec 45 ,

    = 2 11308.532 2 = 31985.358 Nm.

    Provide 300 300 mm bar section and a doubly reinforced beam with equal steel attop and bottom.

    Ast = Asc =.

    . = 702.357 mm2.

    Provide 4 bars of 18 mmdiameter at top and equal amount at bottom.

    Shear force for brace =

    ,

    Span of brace =2 sin22 30 = 2.678 m.

    Shesr force for brace = ..

    = 23887.49 N.

    Nominal shear stress v = =.

    = 0.30 N/mm2.

    Provide nomonal stirrups say 2 legged 10 mmdiameter stirrups at 200 mm clearcover.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    54/75

    Design of foundation:

    Total load on the column = 599375.27548 = 4795002.203 N.

    Approximate weight of foundation is 10% of column loads.

    = 479500.22 N.

    Then total load is equal to 5274502.22 N.

    Safe bearing capacity of 200 KN/m2 ,

    Area = =.

    = 26.37 m2

    .Let us provide outer dia of 9.5 m and inner dia of 6.5 m.

    = [9.526.52] = 37.69 m2.

    Net intensity = ..

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    55/75

    = 139.9 KN/m2.

    139.9 KN/m2< 200 KN/m2.

    Design of circular girder:

    Maximum bending moment occurs at support = 0.00416W r = 11508.005 Nm.

    Maximum bending moment occurs at support = 0.0083 4795002.203 4

    = 159194.073 Nm.

    Maximum torsion = 0.0006 W r = 11508.005 Nm.

    Maximum shear force at support = . (from table 2)

    = 299687.63 N.

    Design at support section;

    Moment of resistence = maximum bending moment at support.

    0.913bd2 = 159194.073 1000 , bd2 = 174363716.30 ,

    d = 590 mm ,clear cover = 60 mm , D = 650 mm.

    Equivalent shear stress Vv = V+1.6 = 299687.63+1.6 . ,

    = 336550.0176 N.Equivalent nominal shear v = = 1.14 N/mm2 , but c = 1.8N/mm2 ,

    Hence c< v .

    Longitudinal reinforcement:

    Mel = M+Mt , Mt =( )

    . =. [ ]

    .

    = 15569653.82 N ,Mel = 1000[159194.073+15569.653] = 174763.726 1000 N.

    Ast =..

    = 1430.964 mm2 ,

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    56/75

    Provide 9 bars of 16 mm diameter bars.

    Hence area os steel required is Ast = 1809.55 mm2 .

    Transverse reinforcement:

    Asv= + . , providing 4 legged 10 mm diamater of stirrups.

    Asv = 4 52= 314 mm2, b1 = 500-80 = 420 mm , d1 = 650-120 = 530 mm,

    314 = . + .. , 314 = Sr[0.224+0.983] , Sv = 260 mm.

    Let us provide 200 mm clear cover spacing.

    Steel for hogging mommentAst =.

    .

    = 653.31 mm2 ,

    Provide 4 bars of 16 mm diameter.

    Design of bottom slab:

    Provide a cantilever projection beyond the face of the beam = 0.6 m.

    Maximum bending moment for 1 m wide stirup = 139944.346 . Nm ,

    = 2518.98 Nm.

    Equating moment of resistence to bending moment ,

    0.913 bd2 = 25189.98 1000 , b = 1000 mm.

    Then d2 = 27590.339 , d = 166.1 mm.

    Let us provide 170 mm effective depth and 40 mm clear cover.

    D = 210 mm. Ast =.. = 715.82 mm

    2.

    Provide 4 bars of 18 mm diameter. Ast = 1017.87 mm2,and spacing of the bars is250 mm clear cover.

    Distribution steel:

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    57/75

    Provide 0.12 % steel and the steel required is =.

    = 252 mm2.

    Provide 6 bars of 8 mm diameter bars and spacing = = 160 mm clear cover.

    Check for sliding:

    Total load on the foundation when t ank is empty = 5274502.423-2896117.112

    = 2378385.311 N

    Horizantal force on the base = 72374.61 N.

    Let coefficient of friction = 0.5

    Fs=. .

    . = 16.43.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    58/75

    14. ESTIMATION

    14.1 Detailed estimation :

    Detailed estimate is an accurate estimate and consists of working out the quantitiesof each item of works, and working the cost. The dimensions, length, breadth andheight of each item are taken out correctly from drawing and quantities of each itemare calculated, and abstracting and billing are done.

    The detailed estimate is prepared in two stages:

    Details of measurement and calculation of quantities.

    The details of measurements of each item of work are taken out correctly from planand drawing and quantities under each item are calculated in a tabular form namedas details of measurement form.

    Abstract of estimated cost:

    The cost of each item of work is calculated in a tabular form the quantities alreadycomputed and total cost is worked out in abstract estimate form. The rates ofdifferent items of work are taken as per schedule of rates or current workable ratesfor finished item of work.

    Detailed estimation:

    S.No

    DECRIPTIONOF WORK

    NOS

    L m Bm

    A m2 HorD(m)

    QTYm3

    REMARKS

    1 Earthwork inexcavation

    1 73.89 1 73.89 = /4= 9.72 /4

    =73.89Earthwork infilling

    1 64.316

    2 a)R.C.C work infoundationb)steel infoundationi )Longitudanalii)Transverse

    1

    94

    7.068

    0.0082 0.0082

    0.2 1.4136

    0.0450.02 = 8

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    59/75

    3 R.C.C in columns

    Steel in columns

    8

    86

    0.3 0.3 0.09

    0.012

    10.04910.049

    7.2350.151

    4 RCC in

    [email protected] in [email protected] from G.L

    8

    88

    0.637

    50.6375

    0.3 0.09

    0.0092

    0.3 =0.459

    =0.01

    A= 0. 009

    =0.000254

    5 a) R.C.C inbracings @5mfrom G.L.b) Steel

    8

    88

    0.575

    0.575

    0.3 0.09

    0.0092

    0.3 0.414

    0.00936

    A= 0. 009=0.000254

    6 a)RCC in bracings7.5mb)steel

    8

    8

    8

    0.45

    0.45 0.0092

    0.324

    0.0072

    A= 0. 009=0.000254

    7 Top ring girdera)R.C.Cb)steel

    longitudinaltranseverse

    1

    5125

    D6

    6

    0.4 0.24

    0.0092

    0.6 4.52

    0.020.066

    8 Bottom domea)RCC in dome

    b) steel

    1

    L=6.6

    2

    =22.619

    0.067

    0.2 4.523

    0.443

    A=2 rh=2 3 1.2=22.619

    = 2 r=6.62

    9 a)RCC conicalslab

    b)steel

    steel for B.M.

    1

    14

    3

    23.56

    23.56

    23.56

    0.2

    0.0082

    2.121

    9.994

    0.066

    0.014

    [ 1 + 2]2

    = (9+6)/2

    10 a)RCC ring beam@ Bb)steel

    1

    628.27

    0.25 0.0082

    0.5 3.534

    0.03411 Cylindrical wall

    a)Main steel

    b)Distributionsteel

    1

    20

    4

    4.32

    28.27

    0.2

    0.0062 0.0042

    4 22.619

    0.0980.0056

    L=4+16d=4+16 0.012=4.32

    12 Ring beam @ Aa)concrete 1 9 0.2 0.04 0.2 1.13 L= D

    =9

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    60/75

    b)Steel 4 9 0.006 0.01213 Top dome R.C.C

    a) concrete

    b) Steel

    1

    100 9.93

    2 rh=50.89

    0.0042

    0.150

    7.63

    0.05

    A=2 rh=

    = 2 r

    12 Total RCC work 63.7956

    13 Total steel 1.01714 Plastering in CM

    (1:2) for Innersurface Of conicaldome (12mm)

    1 50.89 9.15 A=2 rh=50.89

    15 Plastering in CM(1:6) for outersurface Of conicaldome (12mm)

    1 55.135 9.92 A=2 rh=55.135

    16 Plastering in CM(1:2) for Innersurface Ofcylindrical wall(12mm)

    1 D 28.2 112.8 4 20.354

    17 Plastering in CM(1:6) for outersurface Ofcylindrical wall(12mm)

    1 D 29.5 118.82 4 28.349

    18 Plastering in CM(1:2) for Innersurface Of domedroof (12mm)

    1 22.619 4.07 A=2 rh=2 3 1.2=22.619

    19 Plastering in CM(1:6) for outersurface Of domedroof (12mm)

    1 26.38 4.74 A=2 rh=2 3 1.4

    20 Plastering in CM(1:6) for columns(12mm)

    8 0.3 0.3 0.09 17.28

    21 Plastering in CM(1:2) for ring beamat top (12mm)

    1 9 0.25.65

    1.01

    22 Plastering in CM(1:2) for ring beamat bottom (12mm)

    1 1.27

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    61/75

    23 Plastering in CM(1:6) for bracingsat 2.5m ht.(12mm)

    1 0.27

    24 Plastering in CM(1:6) for bracings

    at 5m ht.(12mm)

    1 0.24

    25 Plastering in CM(1:6) for bracingsat 7.5m ht.(12mm)

    1 0.19

    26 Plastering inCM(1:2) for innersurface of conicalslab(12mm)

    1 4.239 [ 1 + 2]2

    = (9+6)/2

    27 Plastering inCM(1:6) for outersurface of conical

    slab(12mm)

    1 4.46

    28 Total plastering 105.533

    29 Thick water proofcement paintingfor tank portion

    85.278

    30 white washing forcolumns

    8 0.312 0.312

    10.04 7.826

    31 Total whitewashing

    93.104

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    62/75

    ABSTRACT

    S.NO DESCRIPTIONOF WORK

    QTY ORNOS

    RATERS PS

    COSTRS PS

    1 Earth work inexcavation

    73.89

    2 Beldars 13 250 32503 Mazdoors 11 250 27504 Total 60005 Earth work in

    Filling In foundation

    64.316

    6 Beldar 7 250 17507 Bhisthi 2 285 5708 Mazdoors 5 250 12509 Total 357010 Total earth work in

    Filling11 Disposal of surplus

    earth in a lead 30m9.574

    12 Mazdoor 4 250 100013 Total 1000

    Total cost of earthwork

    10,570

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    63/75

    14.2 DATA SHEET:

    RCC M- 20 Nominal mix (Cement:fine aggregate: coarse aggregate) correspondingto Table 9 of IS 456 using 20mm size graded machine crushed hard granite metal(coarse aggregate) from approved quarry including cost and conveyance of allmaterials likecementFOUNDATION

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 0.601 1076 646.676Sand Cum 1.2 375 450

    Cement Cum 0.4 1620 6481st Class Mason Day 0.38 285 108.32nd Class Mason Day 1.03 285 293.55Mazdoor (Both Men and Women) Day 2.33 250 582.5Concrete Mixer 10/7 cf(0.2/0.8cum)capacity Hour 1 250 250Cost of Diesel for Miller Liter 0.52 45 23.4Cost of Petrol for Vibrator Liter 0.75 68 51Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 629.16Add MA 20% 629.16Add TOT 4% 176.166BASIC COST per 1 cum 4580.31

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    64/75

    COLUMNS

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 6.156 1076 6623.85

    Sand Cum 3.078 375 1154.25Cement Cum 2.052 1620 3324.241st Class Mason Day 1.99 285 567.152nd Class Mason Day 5.26 285 1499.1Mazdoor (Both Men and Women) Day 11.96 250 2990Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 1 250 250Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 2912.198Add MA 20% 2912.198Add TOT 4% 582.43BASIC COST per 1 cum 20967.816

    RCC RING BEAM AT TOP

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 0.96 1076 1032.96

    Sand Cum 0.48 375 180Cement Cum 0.32 1620 518.41st Class Mason Day 0.31 285 88.352nd Class Mason Day 0.83 285 236.55Mazdoor (Both Men and Women) Day 1.86 250 465Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 747.73Add MA 20% 747.73Add TOT 4% 149.54BASIC COST per 1 cum 5383.66

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    65/75

    RCC DOMED ROOF 150mm THICK

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 6.48 1076 6972.48

    Sand Cum 3.24 375 1215Cement Cum 2.16 1620 3499.21st Class Mason Day 2.1 285 598.52nd Class Mason Day 5.6 285 1596Mazdoor (Both Men and Women) Day 12.6 250 3150Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.267 250 66.75Labour centering Cum 10 971 9710Material hire charges for centering Cum 10 89 890Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 5558.33Add MA 20% 5558.33Add TOT 4% 1111.61BASIC COST per 1 cum 40018.6

    CONICAL SLAB 200mm THICK

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 8.49 1076 9135.24

    Sand Cum 4.25 375 1593.75Cement Cum 2.83 1620 4584.61st Class Mason Day 2.75 285 783.752nd Class Mason Day 7.34 285 2091.9Mazdoor (Both Men and Women) Day 16.52 250 4130Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 5 971 4855Material hire charges for centering Cum 5 89 445Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 5555.328Add MA 20% 5555.328Add TOT 4% 1111.06BASIC COST per 1 cum 39998.35

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    66/75

    RCC CYLINDRICAL WALL

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 19.23 1076 20691.48

    Sand Cum 9.62 375 3607.5Cement Cum 6.41 1620 10384.21st Class Mason Day 6.23 285 1775.552nd Class Mason Day 16.62 285 4736.7Mazdoor (Both Men and Women) Day 37.39 250 9347.5Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 10352.066Add MA 20% 10352.066Add TOT 4% 2070.432BASIC COST per 1 cum 74534.89

    RCC RING BEAM AT BOTTOM OFCYLINDRICAL WALLA. MATERIALS UNIT QTY RATERS AMOUNT

    RS20mm HBG graded metal Cum Cum 3 1076 3228

    Sand Cum 1.5 375 562.5Cement Cum 1 1620 16201st Class Mason Day 0.97 285 267.452nd Class Mason Day 2.59 285 738.15Mazdoor (Both Men and Women) Day 5.84 250 1460Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 1818.7Add MA 20% 1818.7Add TOT 4% 363.74BASIC COST per 1 cum 13094.64

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    67/75

    RCC CIRCULAR GIRDER

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 3.84 1076 4131.84

    Sand Cum 1.92 375 720Cement Cum 1.28 1620 2073.61st Class Mason Day 1.24 285 353.42nd Class Mason Day 3.32 285 946.2Mazdoor (Both Men and Women) Day 7.47 250 1867.5Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 2262.588Add MA 20% 2262.58Add TOT 4% 452.517BASIC COST per 1 cum 16290.61

    RCC BRACING AT 2.5m HT.

    A. MATERIALS UNIT QTY RATERS AMOUNTRS

    20mm HBG graded metal Cum Cum 0.39 1076 419.64

    Sand Cum 0.19 375 71.25Cement Cum 0.13 1620 210.61st Class Mason Day 0.125 285 35.6252nd Class Mason Day 0.33 285 94.05Mazdoor (Both Men and Women) Day 0.75 250 187.5Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 447.213Add MA 20% 447.213Add TOT 4% 89.44BASIC COST per 1 cum 3219.93

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    68/75

    RCC BRACING AT 5m HT.

    A. MATERIALS UNIT QTY RATERS AMOUNT

    RS20mm HBG graded metal Cum Cum 0.33 1076 355.08Sand Cum 0.17 375 63.75Cement Cum 0.11 1620 178.21st Class Mason Day 0.125 285 35.6252nd Class Mason Day 0.33 285 94.05Mazdoor (Both Men and Women) Day 0.75 250 187.5Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89

    Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 426.32Add MA 20% 426.32Add TOT 4% 85.264BASIC COST per 1 cum 3069.50

    RCC BRACING 7.5m HT.

    A. MATERIALS UNIT QTY RATE

    RS

    AMOUNT

    RS20mm HBG graded metal Cum Cum 0.27 1076 290.52Sand Cum 0.13 375 48.75Cement Cum 0.09 1620 145.81st Class Mason Day 0.08 285 22.82nd Class Mason Day 0.23 285 65.55Mazdoor (Both Men and Women) Day 0.535 250 133.75Concrete Mixer 10/7 cf (0.2/0.8cum)capacity Hour 0.26 250 65Labour centering Cum 1 971 971Material hire charges for centering Cum 1 89 89

    Water (including for curing) Ki 1.2 77.0 92.4Add 20% in Labour (1st Floor) 384.91Add MA 20% 384.91Add TOT 4% 76.98BASIC COST per 1 cum 2771.37

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    69/75

    Plastering withCM(1:6)&(1:2),12 mm thickCement Mortor1:61:2

    cumcum

    105.53365.4440.09

    552780

    3616531673

    Mason 1st class day 39 285 11115Bhisthi day 14 285 3990Mazdoor (unskilled) day 39 250 9750Add MA 20% 18539Add TOT 4% 3719Grand Total 114951

    Painting to new walls of tank portion with 2 coats of water proof cement paint o fapproved brand and shade over a base coat of approved cement primer grade Imaking making 3 coats in all to give an even shade a fter thourughly brushing thesurface to remove all dirt and remains of loose powdered materials, including cost

    and conveyance of all materials to work site and all operational, incidental, labourcharges etc. complete for finished item of work as per SS 912 for walls

    Epoxy primer for Hibond floor &protective coatings : Procoat SNP2 orZoriprime EFC 2

    Pack 26 548 14250

    1st class painter Day 4 355 1420Mazdoor Day 4 250 1000cost of water proof cement paint Cum 50 35 17501st class painter Day 2 355 710Mazdoor (unskilled) Day 2 250 500

    Add MA 20% 3926Add TOT 4% 786Total cost 24342

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    70/75

    Painting to new columns of tank portion with 2 coats of water proof cement paint ofapproved brand and shade over a base coat of approved cement primer grade I makingmaking 3 coats in all t o give an even shade after t hourughly brushing the surface toremove all dirt and remains of loose powdered materials, including cost andconveyance of all materials to work site and all operational, incidental, labour chargesetc. complete for finished item of work as per SS 912 for wa lls

    Cost of cement primer Pack 18 100 18001st class painter Day 1 355 3552nd class painter Day 1 250 250cost of water proof cement paint Cum 6 35 2101st class painter Day 1 355 355Mazdoor (unskilled) Day 1 250 250Add MA 20% 644Add TOT 4% 129Total cost 3993

    Total cost of project:

    Total cost of R.C.C = 2,23,930

    Total cost of steel = 5,18,924

    Total cost of plastering = 1,14,951

    Total cost of painting = 28,335

    Total cost of earthwork = 10,570

    8,96,710

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    71/75

    15. CONCLUSION

    Storage of water in the form of tanks for drinking and washing purposes, swimmingpools for exercise and enjoyment, and sewage sedimentation tanks are gainingincreasing importance in the present day life. For small capacities we go forrectangular water tanks while for bigger capacities we provide circular water tanks.Design of water tank is a very tedious method. With out power also we canconsume water by gravitational force.

    Intze tank is constructed to minimize the project cost why because lower dome inthis construction resists the horizontal thrust.

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    72/75

    16. REFERENCES

    Table 16.2. Coefficients for moment in cylindrical wall fixed at base (As Per IS3370)

    Moment = Coefficient (wH 3 ) Nm/m

    H2 Co efficient at points

    DT 0.1 H0.2 H 0.3 H0.4 H 0.5 H 0.6 H 0.7 H 0.8H

    0.4 + 0.0005 + 0.0014 + 0.0021 + 0.0007 - 0.0042 -0.0150 -0.0302-0.0529

    0.8 + 0.0011 + 0.0037 + 0.0063 + 0.0080 + 0.0070 + 0.0023 + 0.0068 -0.0024

    1.2 + 0.0012 + 0.0042 + 0.0077 + 0.0103 + 00112 + 0.0090 + 0.0022 -0.0108

    1.6+ 0.0011 + 0.0041 + 0.0075 + 0.0107 + 0.0121 + 0.0111 + 0.0058 -0.0051

    2.0+ 0.0010 + 0.0035 + 0.0068 + 0.0099 + 0.0120 + 0.0115 + 0.0075 -0.0021

    3.0 + 0.0006 + 0.0024 + 0.0047 + 0.0071 + 0.0090 + 0.0097 + 0.0077 +0.0012

    4.0 + 0.0003 + 0.0015 + 0.0028 + 0.0047 + 0.0066 + 0.0077 + 0.0069 +0.0023

    5.0 + 0.0002 + 0.0008 + 0.0016 + 0.0029 + 0.0046 + 0.0059 + 0.0059 +0.0028

    6.0 + 0.0001 + 0.0003 + 0.0008 + 0.0019 + 0.0032 + 0.0046 + 0.0051 +0.0029

    8.0 0.0000 + 0.0001 + 0.0002 + 0.0008 + 0.0016 + 0.0028 + 0.0038 +0.0029

    10.0 0.0000 + 0.0000 + 0 0001 + 0.0004 + 0.0007 + 0.0019 + 0.0029 +0.0028

    12.0 0.0000 + 0.0000 + 0.0001 + 0.0002 + 0.0003 + 0.0013 + 0.0023 +0.0026

    14.0 0.0000 0.0000 0.0000 0.0000 + 0.0001 + 0.0008 + 0.0019 +0.0023

    16.0 0.0000 0.0000 -0.0001 - 0.0002 -0.0001 + 0.0004 + 0.0013 +0.0019

    Table 1:

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    73/75

    Permissible stresses in concreteAll values in N/mm 2

    Grade permissible stresses in compression permissible stress in bondOf concrete for plain bars in tension

    Bending Direct (average)

    cbc cc bd

    M 10 3.0 2.5 _

    M 15 5.0 4.0 0.6

    M 20 7.0 5.0 0.8

    M 25 8.5 6.0 0.9

    M 30 10.0 8.0 1.0M 35 11.5 9.0 1.1

    M 40 13.0 10.0 1.2

    M 45 14.5 11.0 1.3

    M 50 16.0 12.0 1.4

    Table 1.1:Grade of M10 M15 M20 M25 M30 M35 M40 M45 M50Concrete

    Tensile 1.2 2.0 2.8 3.2 3.6 4.0 4.4 4.8 5.2Stress(N/mm 2 )

    Table 2:Moments for circular girders

    For 8 columns B.M@ B.M@ TorsionSupport centre

    0.0083Wr 0.00416Wr 0.0006Wr

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    74/75

    17. REFERENCE BOOKS

    I.S 456:2000 for RCC.

    I.S 800:1984 for STEEL.

    I.S 872 Part I and Part II.

    I.S 3373 (Part IV-1967).

    Reinforced concrete structures (M.Ramamrutham).

    Element of environmental engineering (BIRIDI).

    . Estimating, costing and evaluation (B.N.Datta).

    . Standard schedule of rates (SSR)

  • 8/10/2019 Design & Estimation of Intze Tanks-Major Project Report

    75/75