Component Design Project data Design Progress Completion of Design/ Probable start of Construction Remarks Capacity enhancement of A104 from JKIA to Likoni Road junction Consultant: Gibb Africa Ltd in association with Associated Consultants Contract price: Kshs 91,750,763.45 and USD 217,442.00 Commencement Date: 1 st June 2012 Progress to date; 25% Certified Amount: Ksh 32,112,767.20 and USD 76,104.70 (25% Advance plus 10% inception) Completion date: 25 th June 2013 *additional time for detailed design for BRT may be necessary Probable start of construction: March 2014 - Inception report submitted July 2012. - Draft Preliminary Design submitted Feb 2013. -Estimated cost of construction Ksh.9.2Billion - Addendum for BRT detailed design under review. Capacity enhancement of A104 Likoni road to James Gichuru Road Junction Consultant: COWI in association with Otieno Odongo and Qutep Contract price: Kshs 82,284,240.00 and EURO 809,100.00 Commencement Date: 15th March 2012 Progress to date; 30% Certified Amount: Ksh. 45,256,322.00 and EURO 445,005.00 (25% Advance plus 10% inception and 20% preliminary) Completion date: 4th July 2013 *additional time for detailed design for BRT may be necessary Probable start of construction: March 2014 - Final Preliminary design report submitted October 2012 - Estimated cost of construction is USD 270 million - estimated cost of elevated roadway (viaduct) is USD 44 million per km. - Addendum for BRT detailed design under preparation Capacity enhancement of A104 James Gichuru Road junction to Rironi Junction Consultant: Eser Project And Engineering Co. Inc. in Association With Bosphorus Technical Consulting Corporation Contract price: KShs 113,033,265.00 Commencement Date: 22 nd May 2012 Progress to date; 30% Certified Amount: Ksh 39,561,642.75 (25% Advance plus 10% Inception and 20% preliminary) Completion date: 3rd September 2013 *additional time for detailed design for BRT may be necessary Probable start of construction: March 2014 -Inception report submitted in May 2012. - Draft Preliminary design report submitted December 2012 - Estimated cost of construction is Ksh 11.3 billion - Addendum for BRT detailed design under preparation Kisumu Northern Bypass Consultant: Sheladia Associates Inc in association with Abdul Mullick Associates Contract price: US$ 82,621.36 and KES 23,537,996.98 Commencement Date: April 2012 Phase 1 October 2012 Phase 2 Progress to date; 15% Certified Amount: KES 2,353,799.69 and US$ 8,262.14 Completion date: 6 th June 2013 Probable start of construction: November 2013 -ESIA and RAP reports submitted May 2012. - sectional draft preliminary reports submitted April 2013 SUSTAINABLE URBAN PUBLIC TRANSPORT Presentation to The 2 nd ACP/EC/UN Habitat Tripartite Conference 4 th September, Kigali, Rwanda By Eng. D. A. Odeck, Manager (Special Projects)

Upload: dangcong

Post on 06-Jul-2019

234 views

Category:

Documents


0 download

TRANSCRIPT

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

SUSTAINABLE URBAN PUBLIC TRANSPORT

Presentation to The 2nd ACP/EC/UN Habitat Tripartite Conference 4th September, Kigali, Rwanda

By Eng. D. A. Odeck, Manager (Special Projects)

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

Challenges arising from current public transport situation

Social Segregation/ Unequal access/ poor or unused NMT facilities/ Lack of safety and security

Air and noise pollution

Excessive energy consumption

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

Challenges arising from current public transport situation

Traffic congestion

unavailability and high cost of land along main corridors

mushrooming of slums

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

Efforts towards sustainable public transport solutions

Master Plan for Urban Transport in the Nairobi Metropolitan Area for 2006 -2025 Recommended Improvement of Transport system through

•better route assignment •corridor improvement •introduction of shuttle bus •mode interchange area improvement

Feasibility Study for Mass Rapid Transit System for the Nairobi Metropolitan Region of 2011

CRITERIA RECOMMENDATION CORRIDOR

PHPDT > 5,000 BRT Mombasa, Limuru & Langata Roads

PHPDT > 12,000 LRT Jogoo & Outer Ring Roads

PHPDT > 30,000 METRO Thika & Juja Roads

MIXED METRO/ BRT Ngong Road

MIXED LRT/ BRT Waiyaki Way

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

The Mass Rapid Transit Options

Range of construction cost (millions USD per km) Source: GTZ Guide

BRT – Bus typically operating on exclusive right-of-way at surface level with grade separation provided at intersections LRT – Rail car(s) typically operating on exclusive right-of-way at surface level with overhead electrical connectors METRO – Heavy rail transit system operating on grade separated tracks that are located principally underground.

- 50 100 150 200 250 300 350 400

BRT

LRT

METRO

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

The Athi River –Nairobi Railway Station- Kikuyu Corridor

•45km long running north-westerly along the Red line •Includes branch line to JKIA and loop in Nairobi CBD

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

Status of the Athi River –Nairobi Railway Station- Kikuyu Corridor project: Design activities ongoing

•45km long running north-westerly along the Red line •Includes branch line to JKIA and loop in Nairobi CBD

Source

: GTZ

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

BEST PRACTISE BRT INFRASTRUCTURE

Source: Transmilenio, Bogota

•Dedicated lanes on median •Passenger safe crossing structures •Overtaking lanes at station

Source: Transmilenio, Bogota

•Fare prepayment •Safe & clean stations

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

BEST PRACTISE BRT INFRASTRUCTURE

Source: Beijing

•Good brand and strong identity •Several doors for boarding •Universal access

Source: Guanghzou

•Passenger information •Multiple routes on same corridor

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

BEST PRACTISE BRT INFRASTRUCTURE

Source: Nantes

•Park & Ride schemes •Bike share stations

Source: Guanghzou

•Control centre •Intelligent transport Systems

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

CONTRIBUTION OF BRT TO SOLVING CURRENT URBAN TRANSPORTATION CHALLENGES

S/No. Problem How BRT will contribute to solution

1 Air and noise pollution BRTS to use fuels with low emissions (CNG).

Passenger information systems negate need for touting.

2 Excessive energy consumption Reduction in use of personal cars

3 Social segregation/ unequal

access/ Lack of safety and

security

Better BRT passenger/ NMT facilities integration

4 Traffic congestion Reduction in use of personal cars

Better parking regimes

5 unavailability and high cost of

land along main corridors

Acquisition for road expansion will be unnecessary in the short term.

In the long term, new unoccupied corridors may be identified

6 Mushrooming of slums Low income workers will afford regulated service and could stay in

cheaper but decent peri-urban housing

Component Design Project data Design Progress Completion of Design/ Probable

start of Construction

Remarks

Capacity enhancement of A104 from JKIA to

Likoni Road junction

Consultant: Gibb Africa

Ltd in association with Associated

Consultants

Contract price: Kshs 91,750,763.45 and

USD 217,442.00

Commencement Date: 1st June 2012

Progress to date; 25%

Certified Amount:

Ksh 32,112,767.20 and

USD 76,104.70

(25% Advance plus

10% inception)

Completion date: 25th June 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Inception report submitted July 2012.

- Draft Preliminary Design submitted Feb 2013.

-Estimated cost of construction Ksh.9.2Billion

- Addendum for BRT detailed design under review.

Capacity enhancement of A104 Likoni road to

James Gichuru Road Junction

Consultant: COWI in

association with Otieno Odongo and Qutep

Contract price: Kshs 82,284,240.00 and

EURO 809,100.00

Commencement Date: 15th March

2012

Progress to date; 30%

Certified Amount:

Ksh. 45,256,322.00 and EURO 445,005.00

(25% Advance plus 10% inception and 20%

preliminary)

Completion date: 4th July 2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

- Final Preliminary design report submitted October 2012

- Estimated cost of construction is USD 270 million

- estimated cost of elevated roadway (viaduct) is USD 44 million per km.

- Addendum for BRT detailed design under preparation

Capacity enhancement of A104 James Gichuru

Road junction to Rironi Junction

Consultant: Eser Project

And Engineering Co. Inc. in Association With

Bosphorus Technical Consulting Corporation

Contract price: KShs 113,033,265.00

Commencement Date: 22nd May

2012

Progress to date; 30%

Certified Amount:

Ksh 39,561,642.75

(25% Advance plus 10% Inception and 20%

preliminary)

Completion date: 3rd September

2013

*additional time for detailed design for BRT

may be necessary

Probable start of construction:

March 2014

-Inception report submitted in May 2012.

- Draft Preliminary design report submitted December 2012

- Estimated cost of construction is Ksh 11.3 billion

- Addendum for BRT detailed design under preparation

Kisumu Northern Bypass Consultant: Sheladia

Associates Inc in association with Abdul

Mullick Associates

Contract price:

US$ 82,621.36 and KES

23,537,996.98

Commencement Date: April 2012 –

Phase 1

October 2012 – Phase 2

Progress to date; 15%

Certified Amount:

KES 2,353,799.69 and

US$ 8,262.14

Completion date: 6th June 2013

Probable start of construction:

November 2013

-ESIA and RAP reports submitted May 2012.

- sectional draft preliminary reports submitted April 2013

THANK YOU FOR ATTENTION