design purposed of rain water harvesting system at roof level

Upload: ayub-saidi

Post on 06-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Design Purposed of Rain Water Harvesting System at Roof Level

    1/4

    DESIGN PURPOSED OF RAIN WATER HARVESTING SYSTEM AT ROOF

    LEVEL

    CALCULATION OF BEAM

    CALCULATED BY: AYUB SAIDI

    DATA:

    Slab thickness: 200mm

    Finishes: 1.0 Kn/m2

    Live load (qk): 7.5 KN/ m2 (Base on table 8, BS 6399: pt1:

    1984)

    Exposure Condt. Mild

    Fcu: 30 N/mm2

    Fy: 460 N/ mm2

    Self weight of slab

    0.2m X 24 KN/m3 = 4.8 KN/ m2

    Load due to finishes

    10 KN/ m2

    Load due to imposed load

    7.5 KN/ m2

    Ultimate Design Load

    1.4 gk + 1.6 qk = (1.4(5.8) + 1.6(7.5)) = 20.12 KN/ m2

    For beam C.A/1-2 = Beam C.A/2-3

    Load from slab, 2 way slab action base on calculation ly/lx;

    Ly/lx = 5.2/4.6 =1.13 < 2.0 ( 2 way slab)

  • 8/3/2019 Design Purposed of Rain Water Harvesting System at Roof Level

    2/4

    At beam C.A / 1-2

    Each trapezium area;

    5.182+0.582X 2.3 X 20.12 KN/ m2 = 133. 32 KN

    2 X 133.32 KN = 266.64 KN

    At end of beam, point load equal to 133.32KN each

    At beam 2/C-D

    Each triangle acting on it equal to

    4.62 X 2.3 X 20.12 KN/ m2= 106.43 KN

    4 X 106.43 KN = 425.72KN/ 9.2 m = 46.27 KN/m

    Primary Beam size (600 X 225)

    Self weight of beam = (0.6 X 0.23 X 24) = 3.312 KN/m

    Design load = 1.4 X 3.312 KN/m = 4.64 KN/m

    Add to existing load; 46.27 + 4.64 = 50.91kn/m

    Hence for beam 2/C-D, all load acting on it is

    Design on beam 2/C-D

    Maximum bending moment

    WL82 +

    PL4 = 538.63 + 306.64 = 845.27 KN.M

    K = M/ fcubd2

    Assume main bar and cover = 25 mm, d = 600 - 25 - (25/2) =

    562.5 mm

    845.27 X 106 / 30 X 225 X 562.52 = 0.396 > 0.156 (doubly

    reinforcement)

  • 8/3/2019 Design Purposed of Rain Water Harvesting System at Roof Level

    3/4

    Z = d ( 0.5 + 0.25-k/0.9 ) = 562.5 ( 0.5 + 0.25-0.396/0.9 )

    = 528.75

    Area of compression reinforcement (As)

    As = (k-k) fcubd2 / 0.95 fy (d-d)

    Assume diameter of compression bar = 25 mm

    d = cover + diam eter of bar/2 = 37.5mm

    As = (0.396-0.156) 30X225X562.52 / 0.95X460X(562.5-37.5)

    = 2234.6 mm2, provide 5T25 (2450 mm2)

    Area of tension reinforcement (As)

    As = M/ 0.95fyz = 845.27 X 106 / 0.95X460X528.75

    = 3658.17 mm2, provide 8T25 (3930 mm2)

    Since the new load to resist is massive in number, we have to

    check if this new load can be resist by the existing beam

    structure in this area.

    Deflection check

    Actual, span/d = 9200/ 562.5 = 16.36

    Permissible;

    Fs = 2/3 X fy X (As req/ As Prov)

    = 2/3 X 460 X (3658.17 / 3930 ) = 285.45

    Modification factor;

    = 0.55 + [(477 Fs)/ 120 (0.9 + m/bd2 )], m/bd2 = 11.87

    0.55 + [0.125] = 0.675

    Thus, L/d basic(simply supported) = 20

    l/d allow = 0.675 X 20 = 13.5 < 16.36

    (The deflection is unacceptable)

    Further calculation cant be made because the deflection

    criteria is not acceptable. To counter this measure, we can

    suggest that we have to provide deeper concrete section for

    this beam. Further calculation was made for beam 1 / C-D and

    still the result is just the same. Since the existing structure

    cant be alter and resist the load, we decide not to design the

    rainwater harvesting system in this building.

  • 8/3/2019 Design Purposed of Rain Water Harvesting System at Roof Level

    4/4