detailed estimate for budget 2015.pdf
TRANSCRIPT
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
1/16
I. DIRECT COST
A. LABOR COST QTY UNIT Amount
Staking and Layouting 11.25 sqm 2.133 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common 3.75 cum 19.20 m-hr/cum 40.28 /m-hr 2,900
Hand Placed Rock Riprap 18.75 cum 7.680 m-hr/cum 43.06 /m-hr 6,200
Concrete Works 6.375 cum 10.04 m-hr/cum 42.2 /m-hr 2,700
Backfill - w/ compaction 0.938 cum 76.80 m-hr/cum 40.28 /m-hr 2,900
Sub-Total A 15,800.00
B. MATERIALS COST
QTY UNIT Amount
Boulders 18.75 cum 1200 /cum 22,500
Cement 101 Bags 245 /bag 24,714
Fine Aggregate 6.375 cum 1700 /cum 10,838
Coarse Aggregate 2.02 cum 1700 /cum 3,434
3" D x3m Long PVC pipe 4 pcs 300 /pc 1,200
Empty Rice Sack 10 pcs 11 /pc 110
Sub-Total B 62,795.88
C. MANUAL HAULING COST
Boulders 18.75 cum 770 /cum 14,438
Cement 101 Bags 75 /bag 7,566
Fine Aggregate 236.1 Cans 50 /can 11,806
Coarse Aggregate 74.81 Cans 50 /can 3,741
Sub-Total C 37,549
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
120,145.30
II. INDIRECT COST
9% (A+B+C) OT, Supervision, Transportation 10,453
15% (A+B+C) Contractors Profit/Mark up 17,422
10% (A+B+C) Overhead,Contingency, and Miscellaneous 11,615 2% (DC+OST+CP/MU+OCM) VAT 3,193
42,682.09
III. TOTA L (I+II) 162,827.39
INDIRECT COST TOTAL
PROJECT COST
PROPOSED FOREBAY 1 SLOPE PROTECTION GROUTED RIPRAP (L. CARBONEL AREA)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
Page 1 of 16
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
2/16
I. DIRECT COST
A. LABOR COST QTY UNIT Amount
Staking and Layouting 24.3 sqm 0.988 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common 8.1 cum 17.78 m-hr/cum 40.28 /m-hr 5,800
Hand Placed Rock Riprap 33.75 cum 8.533 m-hr/cum 43.06 /m-hr 12,400
Concrete Works 10.13 cum 12.64 m-hr/cum 42.2 /m-hr 5,400
Backfill - w/ compaction 2.025 cum 35.56 m-hr/cum 40.28 /m-hr 2,900
Sub-Total A 27,600.00
B. MATERIALS COST
QTY UNIT Amount
Boulders 33.75 cum 1200 /cum 40,500
Cement 169 Bags 245 /bag 41,344
Fine Aggregate 10.13 cum 1700 /cum 17,213
Sub-Total B 99,056.25
C. MANUAL HAULING COST
Boulders 33.75 cum 0 /cum -
Cement 169 Bags 100 /bag 16,875
Fine Aggregate 375 Cans 100 /can 37,500
Sub-Total C 54,375
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
185,031.25
II. INDIRECT COST
5% (A+B+C) OT, Supervision, Transportation 9,052
15% (A+B+C) Contractors Profit/Mark up 27,155
10% (A+B+C) Overhead,Contingency, and Miscellaneous 18,103
2% (DC+OST+CP/MU+OCM) VAT 4,787
59,096.19
III. TOTA L (I+II) 244,127.44
INDIRECT COST TOTAL
PROJECT COST
PROPOSED GROUTED RIPRAPALONG FOREBAY 1 SPILLWAY CANAL (MATEO,VIDANA,MABLAY)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
Page 2 of 16
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
3/16
Project Name: CONCRETING OF DAM1 FOOTPATH (A. CATALINO AREA)
Project Location: BINENG 1 ACCESS TRAIL - ATOS AREA
I. D IRECT COST
A. LABOR COST QTY UNIT TOTAL
Clearing/Layouting 12 sqm 1.3333 m-hr/sqm 53.13 /m-hr 850 Subgrade Preparation 12 sqm 2.0000 m-hr/sqm 50.00 /m-hr 1,200
Form works (Install/dismanli 6 sqm 4.00 m-hr/sqm 50 /m-hr 1,200
Concrete Works 1.935 cum 20.67 m-hr/cum 42.5 /m-hr 1,700
Sub-Total A 4,950.00
B. MATERIALS COST
QTY UNIT TOTAL
Cement 15 Bags 245 /bag 3,556
Fine Aggregates 1.606 cum 1700 /cum 2,730
Coarse Aggregates 2 cum 1700 /cum 3,290
1/2" Thick Plywood 2 Pcs 700 /Pcs 1,429
2*2 Rough Lumber 6 BF 40 /BF 222
CWN 2" 1 Kgs 60 /kg 33 Sub-Total B 11,260.07
C. MANUAL HAULING COST
Cement 15 Bags 35 / Bag 508
Fine Aggregates 59 cans 35 /Can (Size.3mx.3mx.3m) 2,082
Coarse Aggregates 72 cans 35 /Can (Size.3mx.3mx.3m) 2,508
1/2" Thick Plywood 2 pcs 10 / pcs 20
2*2 Rough Lumber 2 lgth 10 / lgt 17
Sub-Total C 5,135.27
D. FREIGHT AND HA NDLING 2 Trip 2000 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
25,345.34
II. INDIRECT COST
10% (A+B+C) OT, Supervision, Transportation 2,134.53
15% (A+B+C) Contractors Profit/Mark up 3,201.80
10% (A+B+C) Overhead,Contingency, and Miscellaneous 2,134.53
2% (DC+OST+CP/MU+OCM) VAT 656.32
8,127.19
III. TOTAL (I+II) 33,472.53
INDIRECT COST TOTAL
PROJECT COST
CONCRETING OF FOOTPATH (20 METERS)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
4/16
Project Name: CONCRETING OF FOOTPATH FROM KESBENG TO BINENG 1 " SHORT CUT"
Project Location: BINENG 1 ACCESS TRAIL - BITO AREA
I. D IRECT COST
A. LABOR COST QTY UNIT TOTAL
Clearing/Layouting 60 sqm 0.2667 m-hr/sqm 53.13 /m-hr 850 Subgrade Preparation 60 sqm 0.8000 m-hr/sqm 50.00 /m-hr 2,400
Form works (Install/dismanli 30 sqm 3.20 m-hr/sqm 50 /m-hr 4,800
Concrete Works 9.675 cum 8.27 m-hr/cum 42.5 /m-hr 3,400
Sub-Total A 11,450.00
B. MATERIALS COST
QTY UNIT TOTAL
Cement 73 Bags 245 /bag 17,778
Fine Aggregates 8.03 cum 1700 /cum 13,651
Coarse Aggregates 10 cum 1700 /cum 16,448
1/2" Thick Plywood 6 Pcs 700 /Pcs 4,346
2*2 Rough Lumber 28 BF 40 /BF 1,111
CWN 2" 3 Kgs 60 /kg 167 Sub-Total B 53,500.35
C. MANUAL HAULING COST
Cement 73 Bags 100 / Bag 7,256
Fine Aggregates 297 cans 65 /Can (Size.3mx.3mx.3m) 19,332
Coarse Aggregates 358 cans 65 /Can (Size.3mx.3mx.3m) 23,292
1/2" Thick Plywood 6 pcs 60 / pcs 373
2*2 Rough Lumber 8 lgth 50 / lgt 417
Sub-Total C 50,669.17
D. FREIGHT AND HA NDLING 2 Trip 2000 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
119,619.52
II. INDIRECT COST
7% (A+B+C) OT, Supervision, Transportation 8,093.37
15% (A+B+C) Contractors Profit/Mark up 17,342.93
10% (A+B+C) Overhead,Contingency, and Miscellaneous 11,561.95
2% (DC+OST+CP/MU+OCM) VAT 3,132.36
40,130.60
III. TOTAL (I+II) 159,750.12 PROJECT COST
CONCRETING OF FOOTPATH (100 METERS)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
DIRECT COST TOTAL (DC)
INDIRECT COST TOTAL
Unit Price
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
5/16
PROJECT NAME Bineng 2 Cottage Improvement
LOCATION Bineng 2 Power Plant
I. D IRECT COST
A. LAB OR COST QTY UNIT Amount
Layouting 3.1416 sqm 5.0929 m-hr/sqm 50 /m-hr 800
Dismantling Works 3.1416 sqm 7.6394 m-hr/sqm 50 /m-hr 1,200 Carpentry Works 3.1416 sqm 7.6394 m-hr/sqm 50 /m-hr 1,200
Tinsmithry Works 3.1416 sqm 7.6394 m-hr/kgs 50 /m-hr 1,200
Finishing Works 3.1416 sqm 7.6394 m-hr/sqm 52.08 /m-hr 1,250
Sub-Total A 5,650.00
B. MATERIALS COST
QTY UNIT Unit Price Amount
C3 Purlins 10' 10.00 Lght 230 / Lght 2300
10' Gutter - Spanish Type 3.00 pc 820 / pc 2460
10' Flashing - Spanish Type 3.00 pc 700 / pc 2100
2x2x12' Rough Lumber 51.75 BF 40 / BF 2070
1/2 Plywood 2 pc 680 / pc 1360
Paint 1 Gal 480 / Gal 480
1/8" x 3/4 Rivet - 500s 1 Box 550 / Box 550
GI Tie wire #16 1.5 kgs 53 / kgs 80
Tex screw 50 pcs 3 / pcs 150
Welding Rod 10 kgs 130 / kgs 1300
CW nail 2" 2 kgs 53 / kgs 106
CW nail 3" 2 kgs 53 / kgs 106
Brush 3" 2 pcs 50 / pcs 100
Nylon String 1 roll 45 / roll 45
Sub-Total B 13,206.50
C. MANUAL HAULING COST
QTY UNIT Unit Price Amount6mmx2"x2" Angle Bar 10.00 lght 150 /lght 1500
10' Gutter - Spanish Type 3.00 pc 20 /pc 60
10' Flashing - Spanish Type 3.00 pc 20 /pc 60
2x2x12' Rough Lumber 12.938 lght 40 /lght 518
1/2 Plywood 2 pc 50 /pc 100
Asstd Items 1000 L.S 1000
Sub-Total C 3,237.50
D. FREIGHT AND HANDLING 2 Trip 2000 4,000.00
Sub-Total D 4,000.00
E. EQUIPMENT COST
Electric Drill wi Accessories 1 150 /day 3 Days 450 Electric Welding Machine w Acce 1 250 /day 3 Days 750
Bar Cutter w Accessories 1 150 /day 3 Days 450
Angle Grinder w Accessories 1 150 /day 4 Days 600
Sub-Total E 2,250.00
28,344.00
II. INDIRECT COST
15% (A+B+C+E) OT, Supervision, Transportation 3,651.60
15% (A+B+C+E) Contractors Profit/Mark up 3,651.60
15% (A+B+C+E) Overhead,Contingency, and Miscellaneous 3,651.60
2% (DC+OST+CP/MU+OCM) VAT 785.98
INDIRECT COST TOTAL 11,740.78
DIRECT COST TOTAL (DC)
MAN-HOUR P/MAN-HOUR
DETAILED ESTIMATES
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
6/16
DETAILED ESTIMATES
I. DIRECT COST
A. LAB OR COST QTY UNIT Amount
Staking and Layouting 6.25 sqm 1.2800 m-hr/sqm 62.5 /m-hr 500
Form works 6.25 sqm 2.5600 m-hr/sqm 43.75 /m-hr 700
Reinforcing Steel Works 59.19 kgs 0.4055 m-hr/kg 52.08 /m-hr 1,250
Concreting Works 0.9375 cum 25.6000 m-hr/cum 50 /m-hr 1,200
Sub-Total A 3,650.00
B. MATERIALS COST QTY UNIT Amount
Cement 10 Bags 245 Bags 2,450
Sand 0.78 Cum 1700 Cum 1,328
Gravel 0.94 Cum 1700 Cum 1,594
16mm RSB 230mpa 59.19 kgs 35 kgs 2,072
2x2x10' Rough Lumber 13.896 BF 40 BF 556
1/4 Plywood 3 pc 350 pc 1,050
GI Tie wire #16 1 kgs 60 kgs 60
CW nail 2" 3 kgs 60 kgs 180
CW nail 3" 3 kgs 60 kgs 180
Nylon String 2 roll 20 roll 40
Sub-Total B 9,508.75
C. MANUAL HA ULING COST
Cement 10 Bags 100 /Bag 1,000
Sand 28.92 Cans 100 /Can 2,892
Gravel 34.72 Cans 100 /Can 3,472
12mm RSB 230mpa 11.11 Lght 50 /Lght 556 2x2x10' Rough Lumber 3.474 Lght 40 /Lght 139
Asstd Items 1 Lot 1000 L.S. 1,000
Sub-Total D 9,059.10
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000.00
E. EQUIPMENT COST
Concrete Vibrator 1 un 500 1.00 days 500
Concrete Mixer 1 un 1700 1.00 days 1,700
Bar Cutter w Accessories 1 un 150 1.00 days 150
Sub-Total E 2,350.00
28,567.85
II. INDIRECT COST
15% (A+B+C+E) OT, Supervision, Transportation 3,685.18
15% (A+B+C+E) Contractors Profit/Mark up 3,685.18
15% (A+B+C+E) Overhead,Contingency, and Miscellaneous 3,685.18
2% (DC+OST+CP/MU+OCM) VAT 792.47
INDIRECT COST TOTAL 11,848.00
III. TOTA L (I+II) PROJECT COST 40,415.84
DIRECT COST TOTAL (DC)
Unit Price
CONCRETE OF SLAB AT BINENG 2 TAILRACE
MAN-HOUR P/MAN-HOUR
Page 6 of 16
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
7/16
PROJECT NAME CONSTRUCTION OF T& B W/ SEPTIC TANK
LOCATION Bineng 2 Power Plant
I. D IRECT COST
A. LAB OR COST QTY UNIT Amount
Clearing and Layouting 8.4375 sqm 2.8444 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common soil 3 cum 8.0000 m-hr/cum 45.83 /m-hr 1,100
Subgrade Preparation 3 sqm 16.00 m-hr/cum 45.83 /m-hr 2,200
Manual Concrete breaking 1.505 cum 47.9 m-hr/cum 50 /m-hr 3,600
Boring works - Anchorage 4 pcsBH 10.0 m-hr/Bh 40.75 /m-hr 1,630
Form works 3 sqm 10.6667 m-hr/sqm 46.88 /m-hr 1,500
Carpentry Works 8.4375 sqm 3.7926 m-hr/sqm 46.88 /m-hr 1,500
Reinforcing Steel Works 78.133 kgs 0.4096 m-hr/kg 50.00 /m-hr 1,600
Concreting Works 3.475 cum 13.8129 m-hr/cum 43.75 /m-hr 2,100
Finishing Works 8.4375 sqm 3.7926 m-hr/sqm 50.00 /m-hr 1,600
Sub-Total A 17,930.00
B. MATERIALS COST
QTY UNIT Unit Price AmountCement 37 Bags 240 /Bag 8880
Sand 2.88 Cum 1700 /Cum 4903
Gravel 3.68 Cum 1700 /Cum 6248
MAN-HOUR P/MAN-HOUR
DETAILED ESTIMATES
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
8/16
4" CHB 395.00 pcs 16 /pc 6320
10mm RSB 230mpa 42.60 kgs 35 /kg 1491
12mm RSB 230mpa 35.53 kgs 35 /kg 1244
Fabricated Steel Window 1.5 sqm 3200 /sqm 4800
2x2x12' Rough Lumber 47.75 BF 38 /BF 1815
Fittings 6 pc 200 /pc 1200
PE Hose 15 lm 50 /lm 750
3" PVC Pipe 2.6667 Lgth 300 /Lgth 800
PVC Solvent Cement 4 can 75 /can 300
PVC Door 2 pc 2900 /pc 5800
Tile Glazed 12*8 100.02 pc 30 /pc 3001
Tile Unglazed 8*8 93.75 pc 25 /pc 2344
White Cement Filler Paste 6.125 kgs 120 /kgs 735
1/2 Plywood 6 pc 680 /pc 4080
Paint 2 Gal 480 /Gal 960
1/8" x 3/4 Rivet - 500s 1 Box 550 /Box 550
GI Tie wire #16 3 kgs 53 /kgs 159
Tex screw 42 pcs 3 /pcs 126
Langueta - 50s Bundle 1 Bundle 75 /Bundle 75
Welding Rod 20 kgs 130 /kgs 2600
CW nail 2" 3 kgs 53 /kgs 159
CW nail 3" 3 kgs 53 /kgs 159
Brush 3" 5 pcs 50 /pcs 250
Nylon String 2 roll 45 /roll 90
Sub-Total B 59,837.24
C. MANUAL HAULING COST
QTY UNIT Unit Price Amount
Cement 37 Bags 100 /Bag 3700
Sand 106.8 Cans 100 /Can 10682
Gravel 136.1 Cans 100 /Can 13611
4" CHB 395 pcs 20 /pc 7900
10mm RSB 230mpa 6 lght 50 /lght 30012mm RSB 230mpa 5 lght 50 /lght 250
Prefab Doors 2 pc 400 /pc 800
Fabricated Steel Window 2 pc 800 /pc 1200
PVC Pipes 2.6667 40 /lght 107
2x2x12' Rough Lumber 11.938 lght 40 /lght 478
1/2 Plywood 6 pc 50 /pc 300
Asstd Items 1500 L.S 1500
Sub-Total C 39,327.69
D. FREIGHT AND HANDLING 2 Trip 1700 3,400.00
Sub-Total D 3,400.00
E. EQUIPMENT COST Electric Drill wi Accessories 1 150 /day 5 Days 750
Electric Welding Machine w Acce 1 250 /day 3 Days 750
Bar Cutter w Accessories 1 150 /day 3 Days 450
Angle Grinder w Accessories 1 150 /day 3 Days 450
Sub-Total E 2,400.00
122,894.92
II. INDIRECT COST
9% (A+B+C+E) OT, Supervision, Transportation 10,754.54
15% (A+B+C+E) Contractors Profit/Mark up 17,924.24
20% (A+B+C+E) Overhead,Contingency, and Miscellaneous 23,898.98
2% (DC+OST+CP/MU+OCM) VAT 3,294.36
55,872.13
DIRECT COST TOTAL (DC)
INDIRECT COST TOTAL
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
9/16
Project Name: CONCRETING OF BINENG2 ACCESS TRAIL (RIMANDO AREA)
Project Location: BINENG 2 ACCESS TRAIL - RIMANDO AREA
I. D IRECT COST
A. LABOR COST QTY UNIT TOTAL
Clearing/Layouting 30 sqm 0.5333 m-hr/sqm 53.13 /m-hr 850 Subgrade Preparation 30 sqm 0.8000 m-hr/sqm 50.00 /m-hr 1,200
Form works (Install/dismanli 15 sqm 3.20 m-hr/sqm 50 /m-hr 2,400
Concrete Works 4.838 cum 8.27 m-hr/cum 42.5 /m-hr 1,700
Sub-Total A 6,150.00
B. MATERIALS COST
QTY UNIT TOTAL
Cement 36 Bags 245 /bag 8,889
Fine Aggregates 4.015 cum 1700 /cum 6,826
Coarse Aggregates 5 cum 1700 /cum 8,224
1/2" Thick Plywood 4 Pcs 700 /Pcs 2,523
2*2 Rough Lumber 14 BF 40 /BF 556
CWN 2" 1 Kgs 60 /kg 83 Sub-Total B 27,100.17
C. MANUAL HAULING COST
Cement 36 Bags 35 / Bag 1,270
Fine Aggregates 149 cans 35 /Can (Size.3mx.3mx.3m) 5,205
Coarse Aggregates 179 cans 35 /Can (Size.3mx.3mx.3m) 6,271
1/2" Thick Plywood 4 pcs 10 / pcs 36
2*2 Rough Lumber 4 lgth 10 / lgt 42
Sub-Total C 12,823.18
D. FREIGHT AND HA NDLING 2 Trip 2000 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
50,073.35
II. INDIRECT COST
10% (A+B+C) OT, Supervision, Transportation 4,607.34
15% (A+B+C) Contractors Profit/Mark up 6,911.00
15% (A+B+C) Overhead,Contingency, and Miscellaneous 6,911.00
2% (DC+OST+CP/MU+OCM) VAT 1,370.05
19,799.39
III. TOTAL (I+II) 69,872.75
INDIRECT COST TOTAL
PROJECT COST
CONCRETING OF FOOTPATH (50METERS)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
10/16
I. DIRECT COST
A. LABOR COST QTY UNIT Amount
Staking and Layouting 15 sqm 1.600 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common 5 cum 14.40 m-hr/cum 40.28 /m-hr 2,900
Hand Placed Rock Riprap 20 cum 7.200 m-hr/cum 43.06 /m-hr 6,200
Concrete Works 10.5 cum 12.19 m-hr/cum 42.2 /m-hr 5,400
Backfill - w/ compaction 1.25 cum 57.60 m-hr/cum 40.28 /m-hr 2,900
Sub-Total A 18,500.00
B. MATERIALS COST
QTY UNIT Amount
Boulders 20 cum 1000 /cum 20,000
Cement 143 Bags 245 /bag 34,974
Coarse Aggregate 5 cum 1700 /cum 7,650
Fine Aggregate 9.735 cum 1700 /cum 16,550
Sub-Total B 79,173.25
C. MANUAL HAULING COST
Boulders 20 cum 0 /cum -
Cement 143 Bags 120 /bag 17,130 Coarse Aggregate 167 Cans 100 /can 16,667
Fine Aggregate 360.6 Cans 100 /can 36,056
Sub-Total C 69,852
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
171,525.47
II. INDIRECT COST
4% (A+B+C) OT, Supervision, Transportation 6,701
15% (A+B+C) Contractors Profit/Mark up 25,129
14% (A+B+C) Overhead,Contingency, and Miscellaneous 23,454
2% (DC+OST+CP/MU+OCM) VAT 4,536
59,819.58
III. TOTA L (I+II) 231,345.06
INDIRECT COST TOTAL
PROJECT COST
PROPOSED GROUTED RIPRAPALONG FOREBAY 2 SPILLWAY CANAL (DAMASO AND WAKAT AREA)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
Page 10 of 16
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
11/16
Project Name: CONCRETING OF BINENG2B ACCESS TRAIL (CANUTO AREA)
Project Location: BINENG 2B ACCESS TRAIL - CANUTO AREA
I. D IRECT COST
A. LABOR COST QTY UNIT TOTAL
Clearing/Layouting 18 sqm 0.8889 m-hr/sqm 53.13 /m-hr 850 Subgrade Preparation 18 sqm 1.3333 m-hr/sqm 50.00 /m-hr 1,200
Form works (Install/dismanli 9 sqm 5.33 m-hr/sqm 50 /m-hr 2,400
Concrete Works 2.903 cum 13.78 m-hr/cum 42.5 /m-hr 1,700
Sub-Total A 6,150.00
B. MATERIALS COST
QTY UNIT TOTAL
Cement 22 Bags 245 /bag 5,333
Fine Aggregates 2.409 cum 1700 /cum 4,095
Coarse Aggregates 3 cum 1700 /cum 4,934
1/2" Thick Plywood 3 Pcs 700 /Pcs 1,794
2*2 Rough Lumber 8 BF 40 /BF 333
CWN 2" 1 Kgs 60 /kg 50 Sub-Total B 16,540.10
C. MANUAL HAULING COST
Cement 22 Bags 75 / Bag 1,633
Fine Aggregates 89 cans 75 /Can (Size.3mx.3mx.3m) 6,692
Coarse Aggregates 108 cans 75 /Can (Size.3mx.3mx.3m) 8,063
1/2" Thick Plywood 3 pcs 30 / pcs 77
2*2 Rough Lumber 3 lgth 30 / lgt 75
Sub-Total C 16,538.91
D. FREIGHT AND HA NDLING 2 Trip 2000 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
43,229.01
II. INDIRECT COST
10% (A+B+C) OT, Supervision, Transportation 3,922.90
15% (A+B+C) Contractors Profit/Mark up 5,884.35
15% (A+B+C) Overhead,Contingency, and Miscellaneous 5,884.35
2% (DC+OST+CP/MU+OCM) VAT 1,178.41
16,870.02
III. TOTAL (I+II) 60,099.03
INDIRECT COST TOTAL
PROJECT COST
CONCRETING OF FOOTPATH (30METERS)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
12/16
Project Name: CONCRETING OF FOOTPATH FROM NAWAL WAITING SHED TO G. MUYAO RESIDENCE
Project Location: BINENG 3 ACCESS TRAIL - MUYAO AREA
I. D IRECT COST
A. LABOR COST QTY UNIT TOTAL
Clearing/Layouting 57 sqm 0.2807 m-hr/sqm 53.13 /m-hr 850 Subgrade Preparation 57 sqm 0.8421 m-hr/sqm 50.00 /m-hr 2,400
Form works (Install/dismanli 29 sqm 3.37 m-hr/sqm 50 /m-hr 4,800
Concrete Works 9.191 cum 8.70 m-hr/cum 42.5 /m-hr 3,400
Sub-Total A 11,450.00
B. MATERIALS COST
QTY UNIT TOTAL
Cement 69 Bags 245 /bag 16,889
Fine Aggregates 7.629 cum 1700 /cum 12,969
Coarse Aggregates 9 cum 1700 /cum 15,625
1/2" Thick Plywood 6 Pcs 700 /Pcs 4,164
2*2 Rough Lumber 26 BF 40 /BF 1,056
CWN 2" 3 Kgs 60 /kg 158 Sub-Total B 50,860.33
C. MANUAL HAULING COST
Cement 69 Bags 12 / Bag 827
Fine Aggregates 283 cans 12 /Can (Size.3mx.3mx.3m) 3,391
Coarse Aggregates 340 cans 12 /Can (Size.3mx.3mx.3m) 4,085
1/2" Thick Plywood 6 pcs 7 / pcs 42
2*2 Rough Lumber 8 lgth 7 / lgt 55
Sub-Total C 8,399.81
D. FREIGHT AND HA NDLING 2 Trip 2000 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
74,710.15
II. INDIRECT COST
7% (A+B+C) OT, Supervision, Transportation 4,949.71
15% (A+B+C) Contractors Profit/Mark up 10,606.52
10% (A+B+C) Overhead,Contingency, and Miscellaneous 7,071.01
2% (DC+OST+CP/MU+OCM) VAT 1,946.75
24,573.99
III. TOTAL (I+II) 99,284.14
INDIRECT COST TOTAL
PROJECT COST
CONCRETING OF FOOTPATH (95 METERS)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
13/16
PROJECT NAME Bineng 3 Desander Guardhouse Floor Tiling(Frontage Area)
LOCATION Bineng 3 Desander
I. DIRECT COST
A. LABOR COST QTY UNIT TOTAL
Layouting\Levelling 13.5 sqm 3.5556 m-hr/sqm 41.67 /m-hr 2,000
Concreting Works 3.6 cum 13.3333 m-hr/cum 39.58 /m-hr 1,900 Laying/Setting of Tile 13.5 sqm 7.1111 m-hr/sqm 41.67 /m-hr 4,000
Finishing Works/Grouting 13.5 sqm 1.1852 m-hr/sqm 37.5 /m-hr 600
Sub-Total A 8,500.00
B. MATERIALS COST
QTY UNIT Unit Price TOTAL
12"x12" TILE 150 pcs 42 /pc 6300.00
Cement 41.076 Bags 245 /Bag 10063.62
Sand 3.3363 cum 1700 /cu 5671.71
White Cement Filler Paste 7.425 Kgs 130 /Kg 965.25
Cutting Disc 6 pcs 95 /pc 570.00
Sub-Total B 23,570.58
C. MANUAL HAUL ING COST
QTY UNIT Unit Price TOTAL
12"x12" TILE 150 pcs 20 /pc 3,000.00
Cement 41.076 Bags 50 /Bag 2,053.80
Sand 123.57 cans 50 /can 6,178.33
White Cement Filler Paste 7.425 Kgs 20 /Kg 148.50
Sub-Total C 11,380.63
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000 E. EQUIPMENT COST
Angle Grinder w Accessories 1 un 150 /day 2 Days 300
Sub-Total E 300.00
47,751.21
II. IND IRECT COST
10% (A+B+C+E) OT, Supervision, Transportation 4,375
15% (A+B+C+E) Contractors Profit/Mark up 6,562.68
10% (A+B+C+E) Overhead,Contingency, and Miscellaneous 4,375.12
2% (DC+OST+CP/MU+OCM) VAT 1,261.28
16,574.21
III. TOTAL (I+II) 64,325.42
DIRECT COST TOTAL (DC)
INDIRECT COST TOTAL
PROJECT COST
DETAILED ESTIMATES
MAN-HOUR P/MAN-HOUR
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
14/16
I. DIRECT COST
A. LABOR COST QTY UNIT Amount
Staking and Layouting 16.88 sqm 1.422 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common 5.625 cum 12.80 m-hr/cum 40.28 /m-hr 2,900
Hand Placed Rock Riprap 28.13 cum 7.680 m-hr/cum 43.06 /m-hr 9,300
Concrete Works 8.438 cum 15.17 m-hr/cum 42.2 /m-hr 5,400
Backfill - w/ compaction 1.406 cum 51.20 m-hr/cum 40.28 /m-hr 2,900
Sub-Total A 21,600.00
B. MATERIALS COST
QTY UNIT Amount
Boulders 28.13 cum 1200 /cum 33,750
Cement 141 Bags 245 /bag 34,453
Fine Aggregate 8.438 cum 1700 /cum 14,344
Sub-Total B 82,546.88
C. MANUAL HAULING COST
Boulders 28.13 cum 0 /cum -
Cement 141 Bags 60 /bag 8,438
Fine Aggregate 312.5 Cans 53 /can 16,563
Sub-Total C 25,000
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
133,146.88
II. INDIRECT COST
5% (A+B+C) OT, Supervision, Transportation 6,457
15% (A+B+C) Contractors Profit/Mark up 19,372
10% (A+B+C) Overhead,Contingency, and Miscellaneous 12,915
2% (DC+OST+CP/MU+OCM) VAT 3,438
42,181.88
III. TOTA L (I+II) 175,328.76
INDIRECT COST TOTAL
PROJECT COST
PROPOSED GROUTED RIPRAPALONG FOREBAY 3 SPILLWAY CANAL (MUYAO AREA)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
Page 14 of 16
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
15/16
I. DIRECT COST
A. LABOR COST QTY UNIT Amount
Staking and Layouting 27.9 sqm 0.860 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common 9.3 cum 15.48 m-hr/cum 40.28 /m-hr 5,800
Hand Placed Rock Riprap 38.75 cum 7.432 m-hr/cum 43.06 /m-hr 12,400
Concrete Works 11.63 cum 11.01 m-hr/cum 42.2 /m-hr 5,400
Backfill - w/ compaction 2.325 cum 30.97 m-hr/cum 40.28 /m-hr 2,900
Sub-Total A 27,600.00
B. MATERIALS COST
QTY UNIT Amount
Boulders 38.75 cum 1200 /cum 46,500
Cement 194 Bags 245 /bag 47,469
Fine Aggregate 11.63 cum 1700 /cum 19,763
Sub-Total B 113,731.25
C. MANUAL HAULING COST
Boulders 38.75 cum 0 /cum -
Cement 194 Bags 60 /bag 11,625
Fine Aggregate 430.6 Cans 53 /can 22,819
Sub-Total C 34,444
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
179,775.69
II. INDIRECT COST
5% (A+B+C) OT, Supervision, Transportation 8,789
15% (A+B+C) Contractors Profit/Mark up 26,366
10% (A+B+C) Overhead,Contingency, and Miscellaneous 17,578
2% (DC+OST+CP/MU+OCM) VAT 4,650
57,382.88
III. TOTA L (I+II) 237,158.57
INDIRECT COST TOTAL
PROJECT COST
PROPOSED GROUTED RIPRAPALONG FOREBAY 3 SPILLWAY CANAL (BILAG AREA)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
Page 15 of 16
-
8/18/2019 DETAILED ESTIMATE FOR BUDGET 2015.pdf
16/16
I. DIRECT COST
A. LABOR COST QTY UNIT Amount
Staking and Layouting 5.25 sqm 4.571 m-hr/sqm 45.83 /m-hr 1,100
Excavation - Common 1.75 cum 41.14 m-hr/cum 40.28 /m-hr 2,900
Hand Placed Rock Riprap 3.5 cum 20.571 m-hr/cum 43.06 /m-hr 3,100
Concrete Works 1.4 cum 45.71 m-hr/cum 42.2 /m-hr 2,700
Backfill - w/ compaction 0.438 cum 164.57 m-hr/cum 40.28 /m-hr 2,900
Sub-Total A 12,700.00
B. MATERIALS COST
QTY UNIT Amount
Boulders 3.5 cum 1200 /cum 4,200
Cement 21 Bags 245 /bag 5,102
Fine Aggregate 1.4 cum 1700 /cum 2,380
Coarse Aggregate 1.239 cum 1700 /cum 2,106
3" D x3m Long PVC pipe 2 pcs 300 /pc 600
Empty Rice Sack 7 pcs 11 /pc 77
Sub-Total B 14,465.43
C. MANUAL HAULING COST
Boulders 3.5 cum 200 /cum 700
Cement 21 Bags 300 /bag 6,248
Fine Aggregate 51.85 Cans 300 /can 15,556
Coarse Aggregate 45.89 Cans 300 /can 13,767
Sub-Total C 36,270
D. FREIGHT AND HANDLING 2 Trip 2000 /Trip 4,000
Sub-Total D 4,000
E. EQUIPMENT COST N/A
67,435.15
II. INDIRECT COST
9% (A+B+C) OT, Supervision, Transportation 5,709
15% (A+B+C) Contractors Profit/Mark up 9,515
10% (A+B+C) Overhead,Contingency, and Miscellaneous 6,344 2% (DC+OST+CP/MU+OCM) VAT 1,780
23,348.01
III. TOTA L (I+II) 90,783.16
INDIRECT COST TOTAL
PROJECT COST
PROPOSED RESTORATION OF DAMAGED SLOPE PROTECTION AT AMP S/S (GUILAO AREA)
DETAILED ESTIMATE
MAN-HOUR P/MAN-HOUR
Unit Price
DIRECT COST TOTAL (DC)
Page 16 of 16