ID WBS Task Name Duration Start Finish
1 1 Development of Coal Terminal - EQ1A Berth Expansion at VPT
1643 days Fri 3/18/11 Wed 9/16/15
2 1.1 Concession Agreement 862 days Fri 3/18/11 Sat 7/27/13
16 1.2 Consultants & Contractors 1474 days Fri 3/18/11 Tue 3/31/15
31 1.3 Financial Closure 416 days Sat 2/4/12 Tue 3/26/13
37 1.4 EPC Preliminaries and Administrative Costs
1141 days Wed 8/1/12 Wed 9/16/15
38 1.4.1 EPC Management/Supervision Cost 1141 days Wed 8/1/12 Wed 9/16/15
39 1.4.2 Indirect Costs At Head Office 1141 days Wed 8/1/12 Wed 9/16/15
40 1.4.3 Progress Reports & Photographs 1141 days Wed 8/1/12 Wed 9/16/15
41 1.4.4 Transportation 1141 days Wed 8/1/12 Wed 9/16/15
42 1.4.5 LC Opening Charges for BMH Equipment
954 days Mon 2/4/13 Wed 9/16/15
43 1.5 Design & Engineering 1376 days Sat 7/9/11 Wed 4/15/15
44 1.5.1 Design & Engineering: Site Investigation
487 days Sat 7/9/11 Wed 11/7/12
71 1.5.2 Detailed Engineering: Civil 771 days Mon 10/1/12 Tue 11/11/14
72 1.5.2.1 DE Civil: Return End wall 72 days Mon 10/1/12 Wed 12/12/12
77 1.5.2.2 DE Civil: Berth 399 days Sat 12/1/12 Sat 1/4/14
82 1.5.2.3 DE Civil: Stacking Yard 405 days Sat 12/1/12 Fri 1/10/14
87 1.5.2.4 DE Civil: Transfer towers 697 days Sat 12/1/12 Wed 10/29/14
92 1.5.2.5 DE Civil: Building - Admin, Sub-Station
697 days Sat 12/1/12 Wed 10/29/14
97 1.5.2.6 DE Civil: Tippler station 696 days Sat 12/1/12 Tue 10/28/14
102 1.5.2.7 DE Civil: BOQ 710 days Sat 12/1/12 Tue 11/11/14
106 1.5.3 Detailed Engineering: Mechanical 928 days Wed 5/16/12 Sun 11/30/14
107 1.5.3.1 DE Mechanical: Ship loader 881 days Wed 5/16/12 Tue 10/14/14
112 1.5.3.2 DE Mechanical: Conveyor systems
730 days Mon 10/1/12 Wed 10/1/14
117 1.5.3.3 DE Mechanical: Wagon tippler 920 days Wed 5/16/12 Sat 11/22/14
122 1.5.3.4 DE Mechanical: Stacker Reclaimer
900 days Wed 5/16/12 Sun 11/2/14
127 1.5.3.5 DE Mechanical: Transfer towers
480 days Mon 7/1/13 Fri 10/24/14
132 1.5.3.6 DE Mechanical: Sprinkling system
500 days Tue 7/9/13 Fri 11/21/14
137 1.5.3.7 DE Mechanical: BOQ 734 days Mon 11/26/12 Sun 11/30/14
141 1.5.4 Detailed Engineering: Utilities 626 days Fri 3/8/13 Mon 11/24/14
142 1.5.4.1 DE Utilities: Fire fighting system
617 days Fri 3/8/13 Sat 11/15/14
146 1.5.4.2 DE Utilities: Electrical System(HT/LT/ELT)
600 days Fri 3/8/13 Wed 10/29/14
150 1.5.4.3 DE Utilities: Internal Roads 357 days Fri 3/8/13 Fri 2/28/14
154 1.5.4.4 DE Utilities: Drainage 297 days Fri 3/8/13 Mon 12/30/13
3/18 9/163/18 10/24
0 days
158 days
46 days
327 days
371 days
16 days
656 days
193 days
393 days
381 days
673 days
673 days
812 days
656 days
666 days
799 days
716 days
810 days
808 days
678 days
725 days
666 days
446 days
575 days
590 days
297 days
221 days
H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Baseline Milestone
Baseline Summary
Progress
DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT
Page 1
Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14
ID WBS Task Name Duration Start Finish
158 1.5.4.5 DE Utilities: Water System 617 days Fri 3/8/13 Sat 11/15/14
162 1.5.4.6 DE Utilities: Land scaping/Green belt
357 days Fri 3/8/13 Fri 2/28/14
166 1.5.4.7 DE Utilities: BOQ 596 days Sun 4/7/13 Mon 11/24/14
170 1.5.5 Detailed Engineering: Railways 590 days Sat 3/2/13 Mon 10/13/14
171 1.5.5.1 DE Railways: Alignment 363 days Sat 3/2/13 Fri 2/28/14
175 1.5.5.2 DE Railways: Turn out Scheme 363 days Sat 3/2/13 Fri 2/28/14
179 1.5.5.3 DE Railways: Layout 363 days Sat 3/2/13 Fri 2/28/14
183 1.5.5.4 DE Railways: Tracks 363 days Sat 3/2/13 Fri 2/28/14
187 1.5.5.5 DE Railways: S & T 363 days Sat 3/2/13 Fri 2/28/14
191 1.5.5.6 DE Railways: Approvals 580 days Sat 3/2/13 Fri 10/3/14
195 1.5.5.7 DE Railways: BOQ 580 days Tue 3/12/13 Mon 10/13/14
199 1.5.6 Approvals & Clearances 1261 days Tue 11/1/11 Wed 4/15/15
200 1.5.6.1 CFE (APPCB) 163 days Tue 11/1/11 Thu 4/12/12
205 1.5.6.2 Port Estate Plan Approval 124 days Thu 5/17/12 Tue 9/18/12
209 1.5.6.3 AP Transco 59 days Sun 2/15/15 Wed 4/15/15
213 1.5.6.4 GVMC - Water Supply 75 days Sun 8/17/14 Fri 10/31/14
217 1.5.6.5 Fire Safety 88 days Sun 8/17/14 Thu 11/13/14
221 1.5.6.6 Marine clearance 60 days Thu 12/13/12 Mon 2/11/13
226 1.6 Procurement: Material Handling Systems
1009 days Tue 8/14/12 Wed 5/20/15
227 1.6.1 Procure: Mechanical Systems 804 days Tue 8/14/12 Mon 10/27/14
234 1.6.2 Procure: Electrical Systems 561 days Tue 3/26/13 Wed 10/8/14
242 1.6.3 Procure: Fire Fighting 178 days Thu 7/31/14 Sun 1/25/15
249 1.6.4 Procure: Railways 234 days Sun 9/28/14 Wed 5/20/15
257 1.6.5 Procure: Berth fixtures 403.3 daysSun 12/1/13 Thu 1/8/15
265 1.7 Construction 1140 days Thu 8/2/12 Wed 9/16/15
266 1.7.1 EPC Preliminaries and Administrative Costs
1110 days Sat 9/1/12 Wed 9/16/15
267 1.7.1.1 Guest House Accommodaion 1110 days Sat 9/1/12 Wed 9/16/15
268 1.7.1.2 Vehicles, Transportation etc 1110 days Sat 9/1/12 Wed 9/16/15
269 1.7.1.3 Progress Reports & Photographs 1110 days Sat 9/1/12 Wed 9/16/15
270 1.7.1.4 Ward and Watch 1110 days Sat 9/1/12 Wed 9/16/15
271 1.7.1.5 Safey and Training 1110 days Sat 9/1/12 Wed 9/16/15
272 1.7.1.6 Tools, Equipment and Machinery 1110 days Sat 9/1/12 Wed 9/16/15
273 1.7.1.7 Site Office Maintenance 1110 days Sat 9/1/12 Wed 9/16/15
274 1.7.2 Establishment of Site Office, P&MYard, Lab, Sores, PC Yard, Utilities
406 days Thu 8/2/12 Thu 9/12/13
275 1.7.2.1 Establishment of Site Offices 406 days Thu 8/2/12 Thu 9/12/13
282 1.7.2.2 Establishment of P&M yard 41 days Wed 9/5/12 Tue 10/16/12
290 1.7.2.3 Establishment of Laboratory 26 days Sat 12/15/12 Thu 1/10/13
296 1.7.2.4 Establishment of Stores 84 days Thu 8/2/12 Thu 10/25/12
541 days
316 days
446 days
377 days
305 days
267 days
328 days
293 days
220 days
493 days
377 days
634 days
-47 days
0 days
698 days
468 days
486 days
0 days
406 days
280 days
310 days
436 days
406 days
612.3 days
327 days
327 days
0 days
0 days
-3 days
-37 days
29 days
H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Baseline Milestone
Baseline Summary
Progress
DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT
Page 2
Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14
ID WBS Task Name Duration Start Finish
300 1.7.2.5 Establishment of precast Yard 35 days Tue 12/18/12 Tue 1/22/13
305 1.7.2.6 Establishment of utilities 133 days Tue 10/16/12 Tue 2/26/13
313 1.7.2.7 Site Safey: Sign Board, Safey Board & Hording, etc
367 days Sat 9/8/12 Tue 9/10/13
315 1.7.3 Site Development Activities 337.04 days
Sat 9/1/12 Sun 8/4/13
316 1.7.3.1 Site Grading 45 days Sat 9/1/12 Tue 10/16/12
322 1.7.3.2 Area Fencing & Lighting 280.04 days
Sun 10/28/12 Sun 8/4/13
327 1.7.3.3 Traffic Diversions 32 days Thu 11/1/12 Mon 12/3/12
330 1.7.4 Selective Demolition 817 days Sun 11/25/12 Fri 2/20/15
331 1.7.4.1 Demo: Boat Basin Jetty 194 days Sun 11/25/12 Fri 6/7/13
338 1.7.4.2 Demo: Tug tie-up Jetty 173 days Sun 8/31/14 Fri 2/20/15
345 1.7.4.3 Demo: Old M F jetty 109 days Mon 9/1/14 Fri 12/19/14
352 1.7.4.4 Demo: NEW M F Jetty 109 days Sat 11/1/14 Wed 2/18/15
359 1.7.4.5 Demo: Lunch&Store room 73 days Mon 12/17/12 Thu 2/28/13
366 1.7.4.6 Demo: Scooter shed 64 days Mon 12/17/12 Tue 2/19/13
373 1.7.4.7 Demo: SMS (OH) office & buildings, sheds etc
64 days Sat 4/27/13 Sun 6/30/13
380 1.7.5 Civil Structures 1002 days Thu 11/1/12 Fri 7/31/15
381 1.7.5.1 Return end wall 348 days Thu 11/1/12 Tue 10/15/13
390 1.7.5.2 Berth with diaphragm wall 821 days Wed 5/1/13 Fri 7/31/15
398 1.7.5.3 Ground improvement at stock yard
812 days Wed 1/23/13 Wed 4/15/15
403 1.7.5.4 Stacker reclaimer foundation 692 days Thu 5/9/13 Wed 4/1/15
412 1.7.5.5 Wagon tippler house 556 days Fri 8/16/13 Mon 2/23/15
426 1.7.5.6 Transfer tower houses 138 days Wed 10/29/14 Mon 3/16/15
434 1.7.5.7 Dump ponds 467 days Thu 10/24/13 Tue 2/3/15
441 1.7.5.8 Sub station 166 days Mon 9/15/14 Sat 2/28/15
450 1.7.5.9 Conveyor foundations 92 days Mon 11/17/14 Tue 2/17/15
457 1.7.5.10 MCC building 202 days Mon 9/15/14 Sun 4/5/15
466 1.7.5.11 Administrative Building Construcion
202 days Mon 9/15/14 Sun 4/5/15
468 1.7.5.12 Maintenance Yard Construction 202 days Mon 9/15/14 Sun 4/5/15
470 1.7.6 Mechanical Structures 372 days Fri 8/15/14 Sat 8/22/15
471 1.7.6.1 Ship loader fabrication 273 days Fri 8/15/14 Fri 5/15/15
476 1.7.6.2 Ship loader erection 222 days Mon 1/12/15 Sat 8/22/15
480 1.7.6.3 Stacker reclaimer fabrication 180 days Wed 9/3/14 Mon 3/2/15
484 1.7.6.4 Stacker reclaimer erection 236 days Tue 12/2/14 Sun 7/26/15
489 1.7.6.5 Conveyer structural steel fabrication
141 days Wed 10/1/14 Thu 2/19/15
493 1.7.6.6 Conveyer structural steel erection
165 days Sun 2/1/15 Thu 7/16/15
-37 days
-37 days
0 days
-9.96 days
-10 days
-9.96 days
-10 days
496 days
16 days
496 days
522 days
583 days
-37 days
-37 days
-37 days
387 days
155 days
387 days
560 days
424 days
369 days
502 days
325 days
443 days
538 days
516 days
467 days
467 days
400 days
625 days
487 days
289 days
401 days
544 days
667 days
H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Baseline Milestone
Baseline Summary
Progress
DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT
Page 3
Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14
ID WBS Task Name Duration Start Finish
497 1.7.6.7 Transfer tower struct. Fabrication
141 days Fri 10/24/14 Sat 3/14/15
501 1.7.6.8 Transfer tower struct. Erection 159 days Thu 1/15/15 Tue 6/23/15
505 1.7.6.9 Wagon tippler fabrication 213 days Tue 9/23/14 Fri 4/24/15
509 1.7.6.10 Wagon tippler erection 207 days Mon 12/22/14 Fri 7/17/15
513 1.7.7 Railway Network 180 days Sun 1/11/15 Fri 7/10/15
514 1.7.7.1 Civil works - Area Grading & Ballast Laying
150 days Sun 1/11/15 Wed 6/10/15
515 1.7.7.2 Track laying 150 days Tue 2/10/15 Fri 7/10/15
516 1.7.8 Electrical Works 266 days Sun 12/14/14 Sun 9/6/15
517 1.7.8.1 Electrical Works: For Conveyors 65 days Sun 4/19/15 Tue 6/23/15
518 1.7.8.2 Electrical Works: For Stacker / Reclaimer
123 days Thu 2/5/15 Mon 6/8/15
519 1.7.8.3 Electrical Works: For Wagon Tippler Station
127 days Sat 12/27/14 Sun 5/3/15
520 1.7.8.4 Electrical Works: For Shiploader 110 days Wed 2/18/15 Mon 6/8/15
521 1.7.8.5 Electrical Works: Control and Communication
266 days Sun 12/14/14 Sun 9/6/15
522 1.7.9 Construction Utilities 310 days Wed 8/27/14 Fri 7/3/15
523 1.7.9.1 Fire fighting system 57 days Mon 12/15/14 Tue 2/10/15
526 1.7.9.2 Electrical System(HT/LT/ELT) 150 days Tue 2/3/15 Fri 7/3/15
527 1.7.9.2.1 Substation 116 days Tue 2/3/15 Sat 5/30/15
530 1.7.9.2.2 DG Sets 39 days Tue 2/24/15 Sat 4/4/15
533 1.7.9.2.3 MCC panels 122 days Tue 3/3/15 Fri 7/3/15
536 1.7.9.2.4 HT/LT Cabling 112 days Tue 2/3/15 Tue 5/26/15
539 1.7.9.2.5 Earthing 88 days Fri 2/13/15 Tue 5/12/15
542 1.7.9.2.6 Lighting 81 days Tue 2/3/15 Sat 4/25/15
545 1.7.9.2.7 Data / Controls Network 119 days Tue 3/3/15 Tue 6/30/15
548 1.7.9.3 Internal Roads 136 days Wed 8/27/14 Sat 1/10/15
554 1.7.9.4 Drainage 129 days Fri 8/29/14 Mon 1/5/15
559 1.7.9.5 Water System 133 days Fri 8/29/14 Fri 1/9/15
566 1.7.9.6 Land scaping/Green belt 133 days Tue 9/2/14 Tue 1/13/15
571 1.7.9.7 Dust Suppression System 51 days Mon 1/5/15 Wed 2/25/15
573 1.8 Testing & Commissionning 86 days Fri 6/12/15 Sun 9/6/15
574 1.8.1 Testing & Comm.: Ship Loaders 50 days Sat 7/18/15 Sun 9/6/15
575 1.8.2 Testing & Comm.: Stacker reclaimer 50 days Fri 7/3/15 Sat 8/22/15
576 1.8.3 Testing & Comm.: Conveyer & Transfer Towers
50 days Sat 7/18/15 Sun 9/6/15
577 1.8.4 Testing & Comm.: Wagon tippler 50 days Fri 6/12/15 Sat 8/1/15
578 1.9 Project Completion 10 days Sun 9/6/15 Wed 9/16/15
579 1.9.1 Snags and Punch list 5 days Sun 9/6/15 Fri 9/11/15
580 1.9.2 Project Completion 5 days Fri 9/11/15 Wed 9/16/15
581 1.9.3 Project Finish 0 days Wed 9/16/15 Wed 9/16/15
511 days
493 days
634 days
364 days
495 days
414 days
437 days
424 days
499 days
465 days
634 days
592 days
587 days
465 days
684 days
712 days
414 days
447 days
433 days
266 days
423 days
409 days
327 days
9/16
H2 '10 H1 '11 H2 '11 H1 '12 H2 '12 H1 '13 H2 '13 H1 '14 H2 '14 H1 '15 H2 '15 H1 '16 H2 '162010 2011 2012 2013 2014 2015 2016
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Critical
Critical Split
Baseline
Baseline Milestone
Baseline Summary
Progress
DEVELOPMENT OF EQ-1A BERTH AT VISAKHAPATNAM PORT
Page 4
Project: Development of EQ-1A Berth at Visakhapatnam PortDate: 03/03/14