dfw/nhesp and eoeea-it a collaborative effort
TRANSCRIPT
Vernal Pools and Rare Species
DFW/NHESP and EOEEA-ITA Collaborative Effort
EEA IT
Vernal Pool
NOT a Vernal Pool
Rare Species
Rare Species ???
EPA grant funded project for $250k.
Project Start 3/20/2011 Vendor on Board 9/9/2011 Project/Grant End 9/28/2012
Timeline and Budget
Web application to submit observations. Mobile application to submit observations. Application to process observation
submittals. Data migration to support other systems.
Featured Components◦ Mapping capability to draw representations ◦ Bulk observation submittals◦ File Upload, Storage, Retrieval◦ Data Warehouse
VPRS Deliverables
http://209.80.128.251/eea/eea.request/login/default.aspx?AppRef=VPRS
Application Demo
13 Months to Deliver Client had not done a formalized software
project before. New Technology to EEA-IT New environments to consolidated EEA-IT ITD Accessibility requirements for
applications.
Project Challenges…
Where are the maps? Supporting legacy systems When is the project over? Application maintenance handoff
Project Challenges Continued
Every project is different. Assess what is working or not working and adjust.
Cast a wide net and pick 3. Have a maintenance plan beyond bugs.
Management Tips and Tricks
guaranteed in life; answers aren’t.
Thank You!