dhelk solutions - presentation 3 v9.pptx
TRANSCRIPT
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
1/30
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
2/30
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
3/30
Presentation Outline Introduction Process Description
Process Modeling
Mass and Energy Balance
Exergetic Analysis Economic Analysis
Sustainability Metrics
Sustainable Development
Questions and Suggestions
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
4/30
Introduction Enhanced Coal Bed Methane; CSG + CO2 Capture and storage
enhanced methane recovery.
Project Requirements: 250MW ECBM Power Generation Plant.
Zero net Greenhouse Gas emissions.
Focus on power production and CO2 capture techniques. Project Description:
CO2 injection into coal bed to stimulate release of natural gas.
CBM contains 70% CH4 as well as CO2, N2 and water.
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
5/30
Site Selection
Location: Surat Basin, QLD, Australia (Macalister Coal Seam)Low rank coal except as a shallower depth thus is easier to desorbmethane, resulting in higher recovery fractions
Map Produced from Queensland's IRTM System
The State of Queensland (Department of Natural Resources and Mines) 2009-2012. While every care is taken to ensure the accuracy of this product, the Department of Natural Resources and Mines makes no representations or warranties about its accuracy, reliability,completeness or suitability for any particular purpose and disclaims all responsibility and all liability (including without limitation, liability in negligence) for all expenses, losses, damages (including indirect or consequential damage) and costs which you might incur as aresult of the product being inaccurate or incomplete in any way and for any reason.
SITE Dalby
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
6/30
CO2 Capture Oxy-fuel, Pre-combustion.
Post-Combustion.
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
7/30
CO2 Capture Absorber and stripper.
Solvent Monoethanolamine (MEA).
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
8/30
Power Generation Natural Gas Combined Cycle
High temperature Brayton cycle followed by low temperature Rankine cycle.
Independent steam cycle.
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
9/30
Boundary Conditions Assumptions:
Complete combustion.
For every mole of CO2 adsorbed, 2.5 additional moles of CH4 isdesorbed.
Reservoir has unlimited storage capacity for CO2.
The design of the following processes has been contracted toFluor:
Subsurface design and ancillary surface equipment.
Brine Treatment.
Solid waste transport and treatment.
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
10/30
Process Overview
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
11/30
Model 1 Model Assumptions:
Composition of Coalbed methane = 70mol% CH4
Complete combustion of CH4. No NOx or SOx production. Combustion with 5% excess air.
Simple Design: Rstoic, Separators & Single Turbine Little Heat Integration. Optimisation of Methane & Steam Flow Rate using Design Specs. thermal = 25%.
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
12/30
Model 2 HP, IP and LP Steam Turbines
Unrealistically high flue gas temperature More heat recovered. Less lost to waste steam.
thermal = 29%
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
13/30
Model 3 More accurate model of steam heating within boiler. Flue gas at realistic temperature. Used to preheat air and methane.
Multistage compression with intercooling implemented: Reduced work requirements and capture of heat of compression. Capital Expenditure vs Reduced Operating Expenses.
Improved Carbon Capture Model: CO2 combined with cool, lean MEA solution. Heat requirements of MEA reboiler modeled. Heat sourced from compressor intercooling and flue gas excess heat
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
14/30
Model Comparison
Model 3 most efficient with lowest CO2 emissions.
58g CO2/kWh compared to 570g/kWh for conventional plant.
0%
5%
10%
15%
20%
25%
30%
35%
40%
0
200
400
600
800
1000
1200
1400
1 2 3
ThermalEfficie
ncy(%)
Flow
rate(m
ol/s)
Model
Methane in (mol/s) CO2 Emmisions (mol/s) Thermal Efficiency
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
15/30
Mass and Energy Balance
Stream no. 1 5 7 9 14 16 20 22 23 24 29 48
Description CBM Air Hot Air Flue Gases Water MEA Flue Gas Liquid CO2 Water Fresh Steam Waste Steam Work
From Feed Feed B4 B5 B7 B13 B8 B9 B17 B10 B15 Turbines
To B1 B3 B5 B6 Waste B10 Stack Coal Seam B10 B11 B16 Grid
Phase Mixed Vapor Vapor Vapor Liquid Liquid Vapor Vapor Liquid Vapor Vapor Work
Mole Flow (mol/s) -
CH4 910 - - - - - - - - - - -
H2O 352 - - 1820 1820 1255 - - 5785 5785 5785 -
CO2 5 - - 914 - - 91 823 - - - -
O2 - 1911 1911 91 - - 91 - - - - -
N2 33 7188 7188 7221 - - 7221 - - - - -
MEA - - - - - 1255 - - - - - -
Total Flow (mol/s) 1300 9099 9099 10047 1820 2510 7404 823 5785 5785 5785 -
Temperature (K) 298 298 1123 1773 373 313 393 429 312 873 449 -
Pressure (MPa) 0.1 0.1 3 3 0.1 0.1 0.1 15.3 16.7 16.7 0 -
Enthalpy (kJ/mol) -130.6 0 25.9 -26.4 -281.6 -269.6 -2.1 -391.6 -286.3 -223.9 -236.7 -Enthalpy (MW) -169.8 -0.1 235.5 -264.9 -512.5 -676.8 -15.4 -322.3 -1656.3 -1295.4 -1369.1 -250
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
16/30
Exergetic Analysis
Exergy Maximum useful work obtainable from a system at a given state.
Irreversibility Exergy destroyed during a process
Dead State 298.15K and 1 atm
Compressors and Gas Turbine major areas of irreversibility.
Future optimisation to further improve overall process efficiency
0.00
5.00
10.00
15.00
20.00
25.00
30.00
35.00
40.00
45.00
Irreversibility (MW)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Exergetic Efficiency (%)
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
17/30
Economic Analysis High variability in electricity and gas prices
Potential shortage of domestic natural gas in Queensland
0
10
20
30
40
50
60
70
80
1998 2003 2008 2013
Price($/MWh)
QLD Wholesale Electricity Prices
0
2
4
6
8
10
12
14
1/1/12 4/10/12 7/19/12 10/27/12 2/4/13
Price($/GJ)
QLD Gas Prices - 2012/13
An uncertain future for the Carbon Tax
Switch to Emissions Trading Scheme in 2016 $12.10 per tonne CO2e
May be gone as soon as September
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
18/30
Economic Analysis
Sources: National State Economic Forecasts to 2034 - (NIEIR, 2012)
Australian Energy Market Operator Historical Prices
Carbon Capture Approaches for NGCC Systems (NETL, 2010)
Carbon Tax Conditions: Floating price in FY16 forecast to drop to $12.10
Free permits issued for 95% of CO2 sequestered.
CurrentAnnual Growth Rate
To FY16 To FY43
Electricity ($/MWh) 56.60 5.50% 3.30%
Natural Gas ($/GJ) 4.95 4.10% 4.00%
Carbon Tax ($) 23 $24.15 , $25.40 $122.50
Capital Cost ($) 257,972,802 - -
Plant Life 30 years - -
Discount Rate (%) 10% - -
Gas Consumed (kmol/y) 28,695,002
Gas Consumed (GJ/y) 23,023,148
Power Produced (MWh/y) 2,190,000
CO2 emissions (t/y) 126,918
CO2 sequestered (t/y) 1,142,258
Cost Forecasts Yearly Plant Data
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
19/30
Discounted Payback Period
-$300M
-$250M
-$200M
-$150M
-$100M
-$50M
$M
$50M
$100M
$150M
$200M
0 5 10 15 20 25 30
NPV($million
s)
Year
Discounted Payback Period = 12.8 years
Undiscounted Payback Period = 7.5 years
Discounted Payback Period = 12.8 yrs
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
20/30
Internal Rate of Return
Internal rate of return = 15.4%
Borderline commercial viability
May require government incentives such as CCS Flagships program
-$400M
-$200M
$M
$200M
$400M
$600M
$800M
$1000M
$1200M
$1400M
$1600M
0% 5% 10% 15% 20% 25% 30% 35%
NPV($m
illions)
Discount Rate (%)
NPV = $162,399,076
IRR = 15.4%
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
21/30
Sustainable Development
AusPlume Modeling
Sustainability Metrics
Social/Political Drivers
Compliance with Sustainable Development
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
22/30
AusPlume
Model CO2 and N2 release rates to evaluate effects onsurrounding receptors
Site3km
3km
D(-8, -8)
C(8, -5)
A(10, 6) B
(15, 5)
N
S
EW
Kogan
Tara
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
23/30
Emission rates
AusPlume
Worst case scenario for emissions spread
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
24/30
AusPlume
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
25/30
a measure of sustainability performance of an operating unit- Quantifies the benefit of implementing sustainability
Emissions
Environmental Burden
Sustainability Metrics
))(( ,1
NiN
ni
ii PFWEB
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
26/30
Land Use- 3 km2 occupied by the site including a buffer zone for OHS
- Land rehabilitation for use by the Traditional Owners
- Infrastructure removal, treatment of contaminated areas andrevegetation.
Sustainability Metrics
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
27/30
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
28/30
Social and Political Drivers Inextricably linked! Social Political Drivers. Currently, Society is unimpressed by CSG.
Increase strength of local economy.
Cultural Heritage; Barunggam tribe
Political Drivers; using legislation, tax and incentives. Mining and Carbon Tax.
Incentives; for clean, efficient energy or renewable. Clean Energy Finance Corporation; $10 billion.
Clean Technology Innovation Program; $200 million.
How will a change in governmentaffect this?
Source; The Telegraph 2010 (ABC 2013)
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
29/30
Sustainable Development Compliance
ECBM is the most sustainable fossil fuel due to efficientuse of resources and zero net carbon emissions.
However, not sustainable since it uses a finite resource.
Lifecycle Assessment should be performed.
Some examples show that ECBM falls short onAcidification, Ozone Layer Depletion and Fossil FuelDepletion.
development that meets the
needs of the present without
compromising the ability of future
generations to meet their own
needs (Vesilind 2009)
-
7/27/2019 DHELK Solutions - Presentation 3 v9.pptx
30/30
Switched on to a brighter future